Professional Documents
Culture Documents
Case Study On Home Office Overhead Claims
Case Study On Home Office Overhead Claims
Abstract: Time and cost overruns impact the parties to a contract, and often the starting point of disputes and disagreements are associated
with likely damages caused by delays. The most contentious aspect related to projects getting delayed is the quantum of claims. Home office
overheads (HOOHs) also form one of the claim heads where quantum is disputed. This paper focuses on analysis of unabsorbed HOOH
claims through a case study and as awarded in court judgments in India. It evaluates the various ways of calculating such claims and their basis
Downloaded from ascelibrary.org by Iowa State University on 03/22/19. Copyright ASCE. For personal use only; all rights reserved.
using scenario analysis on the case study, highlighting the difference in their quantum. The study also details discussion on the recent case
laws in India for usage, the overhead claims, and the basis for awarding them, including the records capturing factual information relied on by
the court for allowing the compensation. The findings identify challenges in using HOOH formulas with scope variations and taking on new
projects by the contractors. It also highlights that despite reliance on the Eichleay formula by many courts, there are other formulas that
indicate better understanding of scope variation and increase in contractor’s revenue through other projects during the delay period. The
insight will be helpful to contractors and owners to assess HOOH claims better in the view of scope variations and addition of new projects.
DOI: 10.1061/(ASCE)LA.1943-4170.0000288. © 2019 American Society of Civil Engineers.
Introduction factors from the literature and grouped them under eight broad
heads: contractor’s design requirement, local economic condition
Overhead claims are broadly grouped under field or site overhead in terms of construction work in market, financial and insurance
claims and home office overhead (HOOH) claims. The field over- costs, complexity of the project, procurement management, layout
head claims are less disputed for compensable delays because the of the site (whether regular or irregular and coverage), third-party
owners can verify the claim records from the daily records submit- influence (safety standards, neighborhood interest), and project
ted to them showing an account of the staff deployed on site. Based duration. The study also gathered the industry perspective in
on the daily rate incurred, the compensation claimed is justifiable. It Hong Kong that project duration primarily affects the project costs
is the HOOH claims that are contentious because the incurrence and other factors such as contractor’s design requirement, procure-
cannot be proven scientifically (SCL 2017). ment arrangement, financial and insurance costs, stakeholders’ in-
The HOOH cost is an incidental cost that is incurred by contrac- terest, and site layout. Based on the industry practice, the contractor
tors for running their business, irrespective of the expenditure on allocates the factors contributing to overheads that are common to
any particular contract. They are not directly incurred on any con- all projects as an estimated percentage to the projects. Accordingly,
struction project and are therefore apportioned across projects dur- the contractor estimates a higher HOOH for a particular project for
ing their bidding stage. They are usually accounted for as a markup the factors that are required exclusively for that project.
on the direct cost of the construction work (CIOB 2009). Industry- The HOOH claim comes from the costs incurred. It can be a
wide, this markup is a management decision and is decided upon fixed percentage specified within the contract if stated within the
considering the annual turnover of the contractor as predicted for contract. The standard forms of contract used by the government
the duration of the project (Baldwin and Bordoli 2014). When a agencies in India do not allow for any additional payments for the
construction project is completed on time and as per the scope HOOH cost incurred on account of delay (CPWD 2014).1 While the
of works defined under the contract, there is no need for increase legitimacy of the home office overhead claims cannot be denied in
in the home office overhead cost. This is different from the case the event of delays attributable to the owner, it is the quantum that is
when the work volume is delayed beyond a planned early construc- often under critical review at the dispute stage if the explicit content
tion schedule. In case of any variations in the job scope, say with of the contract does not allow for it. There is no computation known
increase in work, the time required to do the work may increase, for mathematically proving the damages related to overhead and
and that will likely increase the project overheads as well. Aside profit and therefore the trial courts in the United States have ac-
from the project costs, there are other factors that also contribute cepted and applied various formulas for its estimation (Manshul
significantly to the overhead costs. Chan (2012) analyzed these Constr. Corp., v. Dormitory Authority). However, the claimant
is required to show that the unabsorbed HOOH expenses increased
1
Professor of Construction Management, Dept. of Civil Engineering, in the period of delay. The absence of a mathematical proof is likely
Indian Institute of Technology Delhi, New Delhi 110016, India. Email: the reason the standard forms of contract do not allow for additional
kciyer@gmail.com payments for the overhead claims. Taam and Singh (2003) pro-
2
Ph.D. Candidate, Dept. of Civil Engineering, Indian Institute of Tech- vided clarity on their relative use of the formulas by using an
nology Delhi, New Delhi 110016, India (corresponding author). Email: example and providing extensive legal research defining the appli-
yogita.mananbindal@gmail.com cability in a given case. The example shows variations in the out-
Note. This manuscript was submitted on January 15, 2018; approved on
come of the HOOH estimates and they have been attributed to the
October 3, 2018; published online on March 18, 2019. Discussion period
open until August 18, 2019; separate discussions must be submitted for varied background and assumptions for the formulas used (Taam
individual papers. This paper is part of the Journal of Legal Affairs and Singh 2003; Zack 2002). The variation in outcomes from
and Dispute Resolution in Engineering and Construction, © ASCE, the estimation methods casts doubt on the contractor’s choice of
ISSN 1943-4162. a given estimation method. The owners expect the contractors to
13 Emden method 6,505,154 Construction Time based and includes loss of profit
random. A closer observation of the assumptions and factors of the scope does not contribute to further delay. This method agrees well
formula will narrow down the list to a select few and this is dealt if the contractor does not change the distribution of its direct costs
with in subsequent sections. Mainly, the difference arises from and its markup for overhead and profit for all the projects. In case
the fact that the calculations considered either cost- or time-related the contractor bids on a different markup for a project that later gets
information for computing the values. A 1.6% closeness was ob- delayed, the assessment of which markup should be applicable will
served for Hudson and Emden because both calculate the overhead be a point of contention.
loss along with the loss of profit for the delay period. Of the two, The third isolated range of value is for the burden fluctuation
Hudson gives a higher value because it factors in a normal home method. It attributes the unabsorbed overhead as the fluctuated
office rate versus the percentage computed from the ratio of actual rate of the remaining revenue of the contractor, after deducting
overhead costs to the actual revenue for the delay period. the actual billing, which contained the normal overhead rate. The
The difference in the HOOH values of the comparative absorp- Canadian method and the direct method (Taam and Singh 2003)
tion rate, total direct cost allocation, and modified Eichleay method have different approaches but the same formulas, and therefore
are within a range of 10% for the given case. The Eichleay method have the same values as seen in Fig. 1. Ernstorm and Carteret are
gives nearly half of the value obtained from the modified Eichleay used in the manufacturing industry and both are therefore not
method. While the modified Eichleay method gives an adjustment relevant for a construction project considered for the study. The
over the Eichleay formula by providing information on the actual Allegheny formula is used in case of supply contracts within the
costs incurred that will be preferred over the planned overhead rate, construction industry and therefore is not relevant for discussion
the comparative absorption rate also takes the actual overhead per- in relation to the case of a construction contract related to a high-
centage for its calculation of overhead allocable for the delayed way construction project detailed in the study.
project. The total direct cost allocation takes direct costs ratio The preceding methods are only attempting to use approximate
for the work done on this contract versus all other contracts by methods to estimate the unabsorbed overhead. The existing proc-
the firms (excludes the current project) and uses this ratio to com- esses do not differentiate between an overhead-intensive task and a
pute the overheads for the delay period. It has an advantage of re- labor- and material-intensive task. The project data were utilized to
moving the home office overheads earned through scope change by take into consideration two key scenarios relating to the scope
deducting the extension of time (EOT) from the owner-caused de- variation: those with variations impacting the project delay caused
lay for the time factor in its denominator, provided the increased by the owner, and those without impacting the owner-caused delay
on the project. In each of the two scenarios, scope variation was formulas are performing the intended purpose of showing zero un-
studied further to observe the value of unabsorbed HOOH, with absorbed overhead when all the increased scope of work compen-
four subscenarios: The first one considered scope decrease (10%); sates the lost HOOH in its markup and the owner-caused delay is
the second considered no change in scope; next, we considered a consumed entirely. The same values when seen for increased scope
scope change by 12.4% (because 12.4% is the given case study) of work with maintained owner-caused delay days result in the
and 25% (25% scope increase); and finally, to substantially leave highest value for unabsorbed HOOH for the last subscenario.
no unabsorbed HOOH. The last subscenario, which leaves no un- The result pegs an important point while applying Eichleay and
absorbed HOOH, refers to the situation in which the unabsorbed modified Eichleay for scope increase or decrease: the owner-caused
HOOH because of owner-caused delay is absorbed entirely by delay days must be reduced or increased, respectively, to account
the HOOH markup with the increase in scope. This subscenario is for the HOOH absorption as a result of scope variation.
said to have enough scope increase to leave no unabsorbed HOOH.
For the change in scope, the values of contractor revenue, total di-
rect cost, total labor cost (actual period), changed contract value, Legal Case Research Study
billing (original, delay, and actual period), labor cost (actual and
Increasingly, the disputes between parties to construction contracts
delayed period in the contract), total overhead and profit (actual
are being resolved at the arbitration level in India, and the case laws
period), and home office overhead in percentage during the actual
related to the overhead claims provide a reasoned direction for the
and delay period were also changed relatively in the same propor-
applicability of the formulas. Application of formulas for calculat-
tion. Other factors remained constant. The scenario consisting of no
ing a reasonable estimate of loss of profit and recovery of fixed
change order or variation was also considered to compare it with
overhead costs as incurred has been prevalent in many jurisdictions
scenarios having change orders and variations.
including the United States, United Kingdom, and Australia, and yet
For the scenario in which the owner-caused delay does not
the award of compensation so calculated is subject to assessment on
change as a result of the scope variation, it was observed that only
a case-by-case basis. The overhead formulas were searched for in
burden fluctuation method, Allegheny method, comparative ab- the litigated cases database on Manupatra, and 15 cases were found
sorption rate method, and Carteret method formulas factor compen- citing the use of Emden, Eichleay, and Hudson. The cases chosen
satory effect of the scope increase on the unabsorbed overheads were arbitrated previously, and there were arbitration petitions in
during the delayed period, while the rest show either no change courts. Of the 15 cases studied for overhead claims, compensation
in the changed scenarios or an increase in HOOH allocation as was allowed for in seven cases solely based on records furnished
the scope increased on the project. Table 3 gives the details. These by the plaintiff to the arbitration tribunal and later the court. In
results were different from the scope variations considered when the remaining eight cases, the arbitrator’s award was set aside for
they impacted the owner-caused delay. For scope variations offset- allowing HOOH and loss of profit claims without any records fur-
ting the impact on HOOH by reducing the owner-caused delay, the nished by the claimant. The judgments rely on project records and
HOOH values obtained by the formulas show an expected trend. how the records figure within the calculation of the formula used.
Table 4 gives the decrease in HOOH values as the scope increases.
In the given case, there was an increase in scope, which was com-
municated by the owner. It was also observed that those formulas Requirement of Project Records
that factor in the overhead charged, based on amount of work, do The Supreme Court of India recognized the use of Emden,
not consider the time factor, and those considering the time factor Eichleay, and Hudson formulas for the first time in the case of
do not consider the increased work volume during the delay period. McDermott International Inc., vs. Burn Standard Co. Ltd. and
Assessing the last scenario when the scope change is enough to Ors. The records relied on were the books of account (to establish
compensate the increased HOOH for the delayed period, only loss of profit as per the actual profit details) and other ancillary
Eichleay method, modified Eichleay method, specific base alloca- documents maintained by the plaintiff. In the given case, the
tion method, Canadian method, direct method, total direct cost al- Eichleay formula was also described to calculate only the unab-
location method, Hudson method, and Emden method show zero sorbed overhead when the contractor fails to show the books of
values for the HOOH; the rest do not. The result indicates that these account for the loss of profit. The courts sought the project records
as furnished by the contractor and the project owner to establish and their applicability among the industry professionals who submit
the facts of the case. In the case of Associate Builders, v. Delhi the claim and those who reject the claim and even the arbitrators.
Development Authority, the court relied on the Man-Day Account- Despite the existence of formulas, the contractors also use per-
ing System register as proof of delay caused by the owner to allow centage estimates as quoted in the case of Essar Procurement
for the damages related to prolongation. The most recent cases of Services Ltd., v. Paramount Constructions. The court noted from
records furnished by claimants are Chairman/Secretary, v. Naran- the arbitration award that the Central Water and Power Commission
pura Mazdoor Kamdar Sahkari Mandli Ltd., in which the claimant of the Ministry of Irrigation and Power considered 10% overhead
proved damages by providing project related correspondences, and and 10% profit after the survey made by the committee on several
National Highways Authority of India, v. Ssangyong Engineering, such works. It concluded that 10% overhead would be adequate to
which relied on contemporaneous records such as muster rolls cover expenditure on supervisory establishment, home office
and payment received from staff as verified incurrence of expenses expenses, and travel expenses, among other costs.7 The cost of al-
toward overheads. locating overheads based on such fixed percentages does not hold
ground in the case of petty contractors, where the expense is in-
curred on site alone, as noted in the case of Associate Builders,
Estimation Based on Values from Project Records
v. Delhi Development Authority. Even though the case allowed
Reviewing the judgment of McDermott v. Burns Standard, the for Emden, it cautions the use of the formula without assessing
court noted that since the assessment is of damages, the estimates the overhead records maintained by the contractor and submitting
of compensation would be more realistic if its factors took values of proof of the expenses incurred on overhead staff.
actual costs of overheads instead of the overhead percentages con-
sidered at the bid stage. Despite explaining Hudson, Emden, and
Eichleay, the judgment relied on Emden to calculate cumulative Discussion
loss of profit and overheads incurred after reviewing the book
of accounts. The mere extension of case law by arbitrators, as es- The preceding formulas have been obtained from various perspec-
tablished by McDermott v. Burns Standard without delving into the tives of the contractor and are mainly either time based or cost
facts of the case to infer damages from records, was considered an based (work volume). The two broad themes is that these formulas
impugned award and therefore was set aside by the courts. As noted depend on whether the calculation considers the delay period or
in cases of M/S.J.N. Construction, v. M/S. Shah Jagshi Jethabhai, not. If the formula is borrowed from the manufacturing industry,
and M/S. Shah Jagshi Jethabhai, v. J.N. Construction, the courts it clearly does not consider the time delay factor and therefore it
went to the extent of highlighting the need for arbitrators to follow is not justifiable to be used, i.e., Ernstorm, Carteret, and Allegheny.
the basic principles of the Code of Civil Procedure (CPC)3 and the The Eichleay formula is flawed in its evaluation since any factor
Indian Evidence Act, 1872, observing that the facts of the cases borrowed for calculation in the delay period should not include the
were not consummating to the final award. Such deficiencies on delay period for evaluation since it is not the normal period. In such
the part of an arbitrator have been referred to within the ambit circumstances, the modified Eichleay will be more realistic. The
of patent illegality,4 i.e., in conflict with public policy of India challenge with the contractor is to also identify the normal period
in the case of Essar Procurement Services Ltd., v. Paramount Con- on other projects to truly assess the overhead allocation factors
structions.5 This is also consistent with the judgments regarding the (ratios).
loss of profit claim, requiring proof of damage, which the claimant The Emden formula also considers the loss of profit so it needs
could not furnish and as a result the claim stood unverified and was to be considered separately along with the Hudson formula. The
rejected. Similarly, in the case of Chief Secretary v. Kothari and use of Hudson is not encouraged since the calculation is computed
Associates,6 the court ordered the award based on the Hudson for- from the bid stage value that has a component of HOOH in it. The
mula after reviewing the book of accounts of the respondent as evi- bid percentage of profit is multiplied to contract value, which al-
dence. The court relied on the standard formula given in Hudson’s ready contains the overhead and profit. This leads to double count-
Building Contract (Duncan-Wallace 1995) and Sections 55 and 73 ing and therefore it not used to suggest any claim value. Even
of the Indian Contract Act, 1872, for the recovery of overheads and though Hudson provides a value circumventing the values from
loss of profit. There is a lack of clarity on the use of these formulas other formulas, the reasoning is flawed at multiple levels. The delay
to negatively affect the risk contingencies available to the contrac- with sufficient proof on having incurred damages due to correction
tor (Crowley and Hancher 1995) and tend to raise hidden costs, being applied for considering scope changes if any. Alternatively,
reducing transparency. Unless the owners are actively mitigating the factors used as input values should be verified with the contrac-
the risks associated with underbidding, contractors are more likely tor’s accounting records. The arbitration awards as referred to in the
to underbid and win project bids (Honek et al. 2012). litigated cases have also deduced and highlighted the incompetency
The Hudson formula uses the profit and overhead margins of arbitrators in the usages of the various HOOH formulas.
as quoted in the contract agreement, but those rates are not The study also suggests that appropriate intentions of the parties
representative of actual damages, which is opposite of the flaws must be included in express terms in the contract, such as the re-
in Eichleay. There can be two perspectives to look at this. The first cords they consider relevant for verifying the incurrence when com-
one is that the parties have an agreement on the rates and figures pensation claims are being sought (rather than leaving it to the
initially, or use the same overhead and profit margins as estimated arbitrator or adjudicator to explore and guess at the time of dispute
by the contractor at the time of signing the contract by way of using resolution). If such terms are not already included in the standard
the estimation formula. This approach is focused on calculating the form of the contract, this should be included at the precontract
damages as per the agreed terms of the contract. The second per- negotiation stage. The study indicates limited analysis on which
spective is of damages as per actual incurred expenses. From this formula is more appropriate for what scenario or the scale of con-
perspective, the actual revenue is assumed to be earned without tractor since such a variation in values is difficult to justify reason-
delay on other projects, and also that the estimates are not increased ably. While these methods are all approximate estimations of the
by increase in overheads. For the second perspective, one assumes actual losses incurred, a system incorporating the time and cost
that the variables related to the HOOH costs incurred do not factors as highlighted in the paper for overhead expense is neces-
change. While it may be true of small contractors having less over- sary for a more objective assessment. A definitive way of looking
head expenses, for large contractors having considerable overhead through this claim is to work along the contractor’s actual events on
expenses with various regional offices and home offices, these var- all projects to infer what constitutes a cost to the contractor and how
iables may be more dynamic and therefore more likely to be left much of it has been offset. The expense incurred must be strength-
unabsorbed because of delayed projects. ened with verifiable accounting and project records as reaffirmed
Excluding the value obtained from Eichleay and those lower, from the legal research.
since they are referring to industries other construction, and Emden
and Hudson since they include profit element too, as shown in
Fig. 1, the rest of the formulas range from INR 2,675,691 to References
INR 1,984,623. That is the roughly how varied the values are when
switching from one formula to another for this case. List of Cases
Ahluwalia Contract (India) Limited, v. The Union of India, FAO (OS)
(COMM) 143/2017.
Conclusion Associate Builders, v. Delhi Development Authority, 2014(4)ARBLR
307(SC).
The study concludes that the HOOH values obtained using formu- Chairman/Secretary, v. Naranpura Mazdoor Kamdar Sahkari Mandli Ltd.,
las are reasonable only when calculated using input values reflec- 2015GLH.
tive of actual events. For scope increase without affecting the Chief Secretary, v. Kothari and Associates, 2003GLH(3)613.
number of owner-caused delay days, only a few formulas re- Edifice Developers and Project Engineers Ltd., v. M/s. Essar Projects
sponded with a decline in HOOH allocation to the project; for (India) Ltd., 2013(2)ABR244.
others the HOOH values increased. Burden fluctuation, Allegheny, Essar Procurement Services, Ltd., v. Paramount Constructions, 2016 (11)
comparative absorption rate, and Carteret formulas factored the Bom.
compensatory effect of the scope increase on the unabsorbed over- Kailash Nath and Associates, v. DDA 2015 (4) SCC 136.
Maharashtra State Electricity Distribution Company Limited, v. Vijai
heads during the delayed period. These formulas did not depend on
Electricals Limited, 2015(3)ARBLR336(Bom).
the total number of delay days by the owner. Eichleay, modified
Manshul Constr. Corp., v. Dormitory Authority, 436 N.Y.S.2d 724(App.
Eichleay, specific base allocation, and direct cost allocation, on the Div. 1981).
other hand, show a more reasonable variation when the owner- McDermott International Inc., v. Burn Standard Co. Ltd. and Ors., 2006(2)
caused delay days are changed, reflecting the reduced delays ARBLR498(SC).
days caused by scope changes. The direct cost allocation method, M/S. Shah Jagshi Jethabhai, v. J.N. Construction 2012 (3) Bom. C.R. 546.
modified Eichleay method, Eichleay, and specific base allocation National Highways Authority of India, v. Oriental Pathways (Nagpur) Pvt.
formulas show a change in line with scope increase only when the Ltd., 2016(3)ARBLR448(Delhi).
Endnotes
1 Works Cited
General conditions of the contract clauses of the Central Public Works
Downloaded from ascelibrary.org by Iowa State University on 03/22/19. Copyright ASCE. For personal use only; all rights reserved.
Department specify the changes to be paid for variations in terms of Baldwin, A., and D. Bordoli. 2014. A handbook for construction planning
labor price escalation, material price escalation, and fuel price escala- and scheduling, 136. Chichester, UK: Wiley.
tion, without providing any payment under unabsorbed home office Chan, C. T. W. 2012. “The principal factors affecting construction project
overhead, or field office overhead, which are incurred during compen- overhead expenses: An exploratory factor analysis approach.” Constr.
sable delays. Manage. Econ. 30 (10): 903–914. https://doi.org/10.1080/01446193
2
The formula is also known as the Manshul method. .2012.717706.
3
The Code of Civil Procedure, 1908 (Act No. 5 of 1908), through Sections CIOB (Chartered Institute of Building). 2009. Code of estimating practice.
30 (a) and (b) empowers the court to order discovery and determination 7th ed. Chichester, UK: Wiley.
of issues as necessary in all matters, except those bound by limitations CPWD (Central Public Works Department). 2014. “General conditions of
and conditions as prescribed. contract.” Accessed November 22, 2017. http://cpwd.gov.in/Publication
4
The doctrine of patent illegality was devised by the Supreme Court of /GCC14.pdf.
India in the case of ONGC, v. Saw Pipes. Crowley, L. G., and D. E. Hancher. 1995. “Evaluation of competitive bids.”
5
The cases chosen were arbitrated previously and they are arbitration J. Constr. Eng. Manage. 121 (2): 238–245. https://doi.org/10.1061
petitions in court under various sections of the Arbitration and Concili- /(ASCE)0733-9364(1995)121:2(238).
ation Act 1996. The court in these cases looks at patent illegality in Duncan-Wallace, I. N. 1995. Hudson’s building and engineering contracts,
terms given in the Arbitration Act. Recent amendment of the Arbitration 578. 11th ed. London: Sweet & Maxwell.
Act on the lines of the United National Commission on International Hewitt, R. 1991. Winning contract disputes. 2nd ed. Sacramento, CA:
Trade Law (UNCITRAL) suggests the courts not interference with Arthur Young.
the fact finding of the arbitrator’s award. Honek, K., E. Azar, and C. C. Menassa. 2012. “Recession effects in
6
The case of Chief Secretary, v. Kothari and Associates was an arbitration United States public sector construction contracting: Focus on the
petition filed by the owner and therefore the respondent was the original American Recovery and Reinvestment Act of 2009.” J. Manage.
plaintiff at the arbitration stage. The court established breach of con- Eng. 28 (4): 354–361. https://doi.org/10.1061/(ASCE)ME.1943-5479
tract by the owner since they delayed the site handover for work. .0000075.
The feasible days to work was reduced considerably, causing 78 days Ibbs, W., B. Benjamin, and F. Burckhardt. 2015. “Process model for iden-
of delay. Sections 55 and 73 of the Indian Contract Act, 1872, deliberate tifying and computing allowable home office overhead cost claims.”
on liability of performance during a fixed time (contract regards time as J. Leg. Aff. Dispute Resolut. Eng. Constr. 7 (3): 04514007. https://doi
being of the essence), and the consequential damages suffered in case of .org/10.1061/(ASCE)LA.1943-4170.0000164.
breach. The book of account maintained by Kothari and Associates in Kauffman, M. K., and C. A. Holman. 1995. “The Eichleay formula:
the regular course of business was furnished as evidence for proof of A resilient means for recovering unabsorbed overhead.” Accessed
damages incurred. Proof of damage is an essential element to the award November 22, 2017. http://heinonline.org/HOL/LandingPage?handle
was also reinforced in litigation repeatedly. The Kailash Nath and =hein.journals/pubclj24&div=19&id=&page=.
Associates, v. DDA judgment of the Supreme Court recently also reaf- SCL (Society of Construction Law). 2017. Delay and disruption protocol.
firmed that the claim for damages is not meant to be a windfall gain and 2nd ed. Wantage, UK: Society of Construction Law.
only to the extent of compensating the plaintiff for the damages Taam, T. M. C., and A. Singh. 2003. “Unabsorbed overhead and the
incurred. Eichleay formula.” J. Prof. Issues Eng. Educ. Pract. 129 (4): 234–245.
7
This was reported by the ministry in its Rate and Cost Committee report. https://doi.org/10.1061/(ASCE)1052-3928(2003)129:4(234).
Despite such a report stating 10%, the arbitrator in this case considered Zack, G. J. 2002. “Calculation and recovery of home/head office overhead.”
5% of the contract value as a reasonable award considering the facts of Accessed November 22, 2017. http://www.icoste.org/ZACK.pdf.