Assessing The New United Kingdom Protocol For Dealing With Delay and Disruption

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Assessing the New United Kingdom Protocol for Dealing

with Delay and Disruption


Steve Scott1; Richard Anthony Harris2; and David Greenwood3

Abstract: The recent publication of the U.K. Society of Construction Law’s protocol for dealing with delay claims has finally provided
a good opportunity to make progress with a continuing difficulty that besets most substantial construction projects. The protocol makes
recommendations on the issues that arise when delay claims must be managed. A report of recent research is conducted to test how U.K.
professionals understand some of these issues and how they deal with them in practice. The conclusions show some areas of good
agreement, notably in the way that early completion should be handled and the way that prolongation costs should be assessed. There are,
however, areas that give rise to some concern. The methodology ‘‘time impact analysis’’ appears not to be well used in practice, and it also
seems that contractors will have difficulty with the position taken on float ownership and concurrent delays.
DOI: 10.1061/共ASCE兲1052-3928共2004兲130:1共50兲
CE Database subject headings: Claims; Delay time; Time factors; Dispute resolution; United Kingdom.

Background causation and overall effect. Such claims have the potential to
become disputes either about the validity of the claim or about the
Numerous studies have shown that construction projects have a
extent of the money/time actually claimed 共Duncan-Wallace
tendency to suffer from delay 共National Economic Development
1995兲. Although much has been written about the issues affecting
Council 共NEDC兲 for Building 1983; NEDC for Construction
such claims, it is clear that problems remain due to the inad-
1988; Bresnen et al. 1990; Scott 1993a,b; Harris 2000兲. Such de-
equacy of existing contractual mechanisms in dealing with the
lays carry potential losses for all parties: for the employer 共client,
complexity of the situations encountered 共Yogeswaran et al.
owner兲 through loss of use, and for the contractor and subcontrac-
1998; Harris 2000兲.
tors through their prolonged presence on-site. As a result, con-
tracts generally contain mechanisms to allocate the liability for Mechanisms for Assessing Delay Claims
delays and compensate for their impact, including clauses that
deal with liquidated damages, extensions of time, and the reim- Perhaps the most difficult aspect that must be dealt with when
bursement of prolongation costs. Although the approach to deal- assessing claims for extensions of time is the mechanism used to
ing with these matters will be governed to some extent by any show the impacts of various delays on project completion. At the
legal precedent set in the country concerned, the issues that must heart of most of these mechanisms is the categorization of delays
be addressed are universal and complex, and the extent of the as culpable, excusable, and compensable 共Kraiem and Diekmann
problem is recognized to be great. This is confirmed in a recent 1987兲. One complication is that not all excusable or compensable
study by Thompson et al. 共2000兲 who compared recent innova- delays will attract an extension of time; this should only be the
tions to manage disputes in both the U.S. and the U.K. They case if they have a critical effect on the overall program 共sched-
found both construction industries to have similar working envi- ule兲. In the case of a delay to a noncritical activity, no extension
ronments and to be plagued with adversarial attitudes, a rising should normally be available, that is, of course, unless other
numbers of claims, and high litigation costs. changed circumstances cause the noncritical activity to become
The efficient and effective resolution of a delay claim will rely subsequently critical.
upon the ability to quantify a given delay and to evaluate its These criteria may seem relatively straightforward, but they
are not. For example, the relationship between planned and actual
1
Senior Lecturer, School of Civil Engineering and Geosciences, Univ. progress is a fluid, not a static affair. It could be argued that
of Newcastle upon Tyne, Claremont Road, Newcastle upon Tyne, NE1 assessing the impact of a particular event on an ‘‘as planned’’
7RU, United Kingdom. program is unrealistic, because the durations and relationships of
2 subsequent activities may have altered. A 10 week delay on a
Researcher, School of Civil Engineering and Geosciences, Univ. of
Newcastle upon Tyne, Claremont Road, Newcastle upon Tyne, NE1 7RU, planned critical path might not mean a 10 week delay to the
United Kingdom. project. Indeed, there would normally exist a contractual 共and
3
Associate Dean, School of the Built Environment, Northumbria common law兲 duty to mitigate the situation by endeavoring to
Univ., Ellison Place, Newcastle upon Tyne, NE1 8ST, United Kingdom. recoup some of the lost time 共see Yogeswaran et al. 1998兲. Much
Note. Discussion open until June 1, 2004. Separate discussions must has been written on this and other topics within the area, with
be submitted for individual papers. To extend the closing date by one
many authors offering their own solutions to the complications
month, a written request must be filed with the ASCE Managing Editor.
The manuscript for this paper was submitted for review and possible that emerge. Knoke and Jentzen 共1994兲, Bordoli and Baldwin
publication on January 22, 2003; approved on August 21, 2003. This 共1998兲, and Kartam 共1999兲 are recent examples, and Wickwire
paper is part of the Journal of Professional Issues in Engineering Edu- et al. 共1989兲 indicate the legal position in the U.S.
cation and Practice, Vol. 130, No. 1, January 1, 2004. ©ASCE, ISSN In essence, the main options for assessing the impact of delays
1052-3928/2004/1-50–59/$18.00. are

50 / JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JANUARY 2004
1. A global solution that ascertains the delay to the project as a one of which could have an impact on the completion date. How-
whole, then identifies all delays that are claimable under the ever, the situation becomes problematic when the causation of
contract and calculates the extension of time due on that each of the delays is different and would lead to different con-
basis, leaving the remaining delay as the responsibility of the tractual liabilities 共Rubin et al. 1983兲, an example being where an
contractor. This approach will not use critical path networks, activity is delayed at the same time by events attributable to the
and may relate the delays to the contractor’s time/cost ‘‘S contractor, the employer, and/or to neutral causes 共Scott
curves’’ 共Rubin et al. 1983兲. 1993 a, b兲. A further problem is that delays can be interrelated,
2. A solution that relies on critical path networks to show how even when not concurrent or overlapping 共Majid and McCaffer
specific delays affected the contractor’s ability to complete 1998兲, which is a particular problem because the causes of the
the work, with actual activity durations and the real impact interrelated delays are in different contractual categories, for ex-
of delays thus identified. Having established the facts of the ample, where an excusable delay is linked to a later, nonexcusable
case in this way, some means of showing how individual one.
delays affected project completion must be adopted. This The proper assessment and resolution of delay claims have
might be to remove the employer-responsible delays and ad- attracted a considerable amount of attention. In practice, however,
just the network to show how the contractor could have per- parties in the U.K. have little or no guidance; standard contracts
formed in the absence of such delays. are notoriously silent on such matters, and there is little useful
3. Time impact analysis—there appear to be variations on this case law. This first view is confirmed by Yogeswaran et al.
method, which either considers delays as they occur 共SCL 共1998兲, who state that ‘‘... most contractual regimes ... do not
2002兲 or by relating to a program update immediately before provide details of the principles governing the assessment of
the delay considered 共Bubshait and Cunningham 1998兲. claims for extensions of time and this is left to the professionals
Whichever approach is adopted, the specific impact of indi- involved in each project.’’ In the absence of any prior agreement,
vidual delays on an updated network is recognized, and the the options are either to compromise or to take the matter to
impact on contract completion dates is noted. During the adjudication, arbitration, or litigation. The unnecessary cost in
process, any patently unrealistic logic or durations should be terms of claims and litigation expense as well as soured relation-
corrected, by agreement where possible. An important differ- ships is testimony to the failure of the current contractual mecha-
ence between time impact analysis and Option 共2兲 is that nisms to deal with the complexities of real situations.1 The issues
impacts are recognized at the time they occur, rather than to be dealt with are clearly very complex, requiring an under-
attempting to understand these complex interactions at some standing of contract law, contract forms, contract administration,
time in the future. project planning techniques, and an appreciation of how construc-
Which of these methods are being used or which should be used tion activity typically takes place. It is not surprising then that
are important questions. Bordoli and Baldwin 共1998兲 conducted a there is much debate, not only about the proper way to deal with
study in which 96 respondents from across the industry were these questions, but also about whether one single approach can
questioned on their knowledge of the methods available. The be expected to hold good in all circumstances. In the U.K., the
most favored approach was one that used as-built bar charts, al- final version of a new guide to assist with these matters was
though 65% of the respondents also identified the use of networks published in October 2002 and the next section of the paper high-
and recognized the options of adding delays to a planned network lights the main points.
or subtracting delays from an as-built one. Bubshait and
Cunningham 共1998兲 used case studies to compare three network
approaches to delay analysis and concluded that there was no U.K. Society of Construction Law Protocol
single method that was preferable in all situations. The choice of
method should be governed by the time and resources available To address the issues described previously, the Society of Con-
and on the accessibility of project control documentation. struction Law 共SCL兲, whose aim is to promote for the public
benefit, education, study, and research in the fields of construction
law and related subjects, has produced a ‘‘Protocol for determin-
Particular Problem Areas
ing extensions of time and compensation for delay and disrup-
It is clear that the ability to analyze delays is greatly enhanced by tion’’ 共SCL 2002兲. The Protocol offers guidance on
the use of critical path analysis, however, within any overall ap- 1. Core issues relating to delay and compensation;
proach to delay analysis, there are two particularly difficult issues. 2. Preparing and maintaining programs and records;
These are the problems of the ownership of float and concurrent 3. Dealing with extensions of time during the course of the
delays. project; and
The word ‘‘float’’ is often used rather indiscriminately and 4. Dealing with disputed extension of time issues after comple-
confusingly by construction practitioners and their advisors, par- tion of the project.
ticularly those who do not understand critical path analysis tech- The Protocol also contains a comprehensive glossary of terms,
niques 共Yogeswaran et al. 1998兲. Who should be the ‘‘owner of model clauses for the keeping of records and for dealing with
float’’ is a vexed question that has been considered by many writ- programs, and a set of graphics illustrating points contained in the
ers, among whom are Householder and Rutland 共1990兲, Thomas Protocol.
共1993兲, Zack 共1993兲, and Yogeswaran et al. 共1998兲. The recom- The first draft of the Protocol was launched on December 4,
mendation made by most commentators is that whatever policy is 2001, and by the end of the initial consultation period, February
adopted, it should be clearly stated in the contract. 28, 2002, 80 detailed submissions had been received. These were
The question of how to deal with concurrent delays is essential said to be mostly supportive but also made suggestions for im-
for a workable mechanism for assessing delay claims, yet there is provement. A subsequent consultation workshop was held on May
no universally accepted definition of what constitutes concurrent 22, 2002, following which the drafting committee met to review
delay. Broadly speaking, this situation occurs when an activity is the observations made at that time. The final edition of the Pro-
affected by two or more contemporary or overlapping delays, any tocol was launched in London on October 16, 2002.

JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JANUARY 2004 / 51
An important question concerning such a document is its pro- additional resources will be provided or that work will be
posed legal or contractual status. In this case, the writers have done outside normal working hours, unless further payments
made it very clear that it is intended just as a guide. In an earlier are agreed upon.
version, it was suggested that those who draft contracts might 3. When assessing the contractor’s entitlement to compensation
want to incorporate parts of the Protocol, but this position has for prolongation, the site overheads included in the tender
now changed. The new position is that it ‘‘... represents a scheme should not be used. It is the contractor’s justified actual costs
for dealing with delay and disruption issues that is balanced and that are to be paid.
viable.’’ The drafters of the Protocol,2 who were a subcommittee
of the SCL, hope that in the future most contracts will use the Ownership of Float
guidance contained in the Protocol because they will recognize it The Protocol’s judgment on the ownership of float is that, ideally,
as the best way to deal with the issues. the position should be defined in the contract documents, but
The full version of the Protocol is 82 pages long and so the where no specific statements are made, the ‘‘fallback’’ position
description given in this paper must inevitably be a synopsis. should be that float is there to be used by whoever needs it first.
Nevertheless, an attempt will be made to describe the main points Whether U.K. contracts will actually pronounce on float owner-
and highlight any unusual suggestions or recommendations. ship is brought into question because the Protocol observes that
‘‘... the expression ‘float’ rarely if ever appears in standard form
conditions of contract’’ 共SCL 2002兲. Thus, unless the drafter of
General Recommendations
the specific contract document makes an addition to deal with
The Protocol endorses a number of points as good general prac- float, it is the fallback position that may be taken. The Protocol
tice and also includes a few reminders to practitioners regarding reflects upon how contractors may react to a rule that allows
issues that are not always fully understood. There is nothing new employers access to program float and speculates on the possibil-
here, but in attempting to produce a fully inclusive document, ity that the contractor may incorporate some additional time in
such statements need to be made. The following come into the activity durations. This is seen as ‘‘... perfectly acceptable and
first category: prudent planning practice’’ 共SCL 2002兲.
In reviewing the impact of float on a contractor’s compensa-
1. The importance of getting programs accepted and updated tion, the question of early completion is also considered. The
and of keeping good records is stressed 共see also a later Protocol’s view is that a contractor should be able to recover
section on this issue兲. compensation for prolongation when delayed by the employer,
2. The need to deal with extensions of time as soon as possible even when the project completes within time and thus no exten-
after the delaying event is recognized, leading to the require- sion of time is sought or granted. This should hold provided the
ment for interim assessments. The ‘‘wait and see’’ approach, employer knew of the contractor’s intention to complete early
in which the contract administrator 共CA兲 delays making a when the contract was signed and provided there is nothing in the
judgment on an extension of time until it is certain the con- contract that precludes it.
tractor needs one, is strongly discouraged.
3. For varied work 共change orders兲, the possibility of agreeing
on costs and time impacts before the work is done is empha- Concurrent Delay
sized, although it is recognized that this may not always be The Protocol recognizes that the advice it gives on concurrent
feasible, and, in such cases, the advice is to come to an delays is a compromise that is believed to be the most appropriate
understanding as soon as possible after the event. solution for what it considers to be a contentious issue, exacer-
4. Global claims, that is, ones that do not elaborate in detail on bated by the absence of agreement in the U.K. as to exactly what
individual causes and effects are discouraged, because they concurrency means. This is somewhat different to the U.S.,
are said to be rarely accepted by the courts. where, even in 1983, Rubin et al. 共1983兲 offered the definition ‘‘...
5. Unless the contract makes special allowances, the Protocol the term concurrent delays is used to describe two or more delays
recommends that costs for acceleration should be preagreed that occur at the same time, either of which had it occurred alone,
between the parties. This statement recognizes that U.K. would have affected the ultimate completion date.’’ Two scenarios
contracts may not provide for acceleration, but where the are addressed in the Protocol. These are 共1兲 when an employer-
contractor and the employer agree that accelerative measures risk event and a contractor-risk event occur at the same time, and
should be taken, it is wise to agree on the basis for payment their effects are felt at the same time; and 共2兲 when employer risk
in advance. Clearly, this acknowledges the difficulty of cost- events and contractor risk events occur sequentially, but have
ing the effects of efficiency losses that may result from ac- concurrent effects. The Protocol defines a contractor or employer
celeration, after the fact. risk event as an event or cause of delay, which under the contract
6. Disruption is seen as quite separate from delay, and ‘‘the is at the risk and responsibility of the contractor or employer. In
measured mile’’ approach 共i.e., comparing the same work in both situations, the remedy is that any contractor delay should not
disrupted and undisrupted conditions兲 is suggested as the reduce the amount of extension of time due to the contractor as a
best way to handle it, although the difficulties of finding result of the employer delay. Regarding compensation for prolon-
similar work on the same project are recognized. gation resulting from concurrent delays, the view is that this
The reminders are as follows: should be payable only to the extent that the contractor can sepa-
1. An extension of time only relieves the contractor from liabil- rate additional costs caused by the employer delay from those
ity for liquidated damages and does not necessarily include caused by the contractor delay. In practice, this is likely to be
any entitlement to compensation for prolongation. governed by the amount by which the employer delay exceeds the
2. It is accepted that the contractor will usually be required to contractor delay. A number of the graphics appended to the Pro-
mitigate the effects of any delay, but the Protocol prompts us tocol illustrate how concurrent delays should be managed 共SCL
to remember that this should not be seen as expecting that 2002兲.

52 / JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JANUARY 2004
Compensation for Prolongation 1. The interested parties should try to agree to an appropriate
method of analysis before any retrospective assessment is
Having accepted that employer delays have affected the contrac- done.
tor’s performance and the contractor is given either an extension 2. Agreement should be reached as to who is to carry out the
of time or the need to make payments is recognized, even though analysis, with consideration given to appointing an ‘‘inde-
the contract completion date has not been exceeded, there still pendent expert programming consultant.’’
remains the problem of how to assess the proper level of payment
for prolongation, i.e., site costs incurred by the contractor for an
extended time on site. What the Protocol makes very clear is that Programs and Records
the levels of compensation should relate to the period when the Without sensible policies for accepting and updating contract pro-
employer delay occurred and not to the extended period at the end grams and for keeping good, accessible records, the resolution of
of the contract. It is recognized that the contractor’s weekly ex- delay claims becomes much more onerous. This is recognized in
penditure at the end of the contract is likely to be a good deal less the Protocol not only as a core issue but also in the model clauses
than that incurred when the contract is fully underway, thus, the contained in the appendices. On dealing with the program, it is
level of compensation payments would be greater taking the Pro- recognized that most contract forms in the U.K. are quite vague
tocol’s position, when compared to the ‘‘end of contract’’ alterna- about a number of matters. The following are the main points
tive. To aid this often difficult assessment, it is recommended that from the guidance section and from the model specification
prolongation payments be preagreed and would, of necessity, re- clauses:
flect the different amounts expended by the contractor at different 1. The contractor’s initial program for a large complex project
stages of the work. should be submitted within 2 weeks of awarding of the con-
tract and should show at least the works to be completed in
Dealing with Extensions of Time during the Course the first 3 months. A program covering the whole of the
of the Project works must be submitted within the next 2 weeks. This
should be updated with actual progress at least once a month.
Wherever circumstances permit, the Protocol recommends that 2. The program is to be produced using commercially available
‘‘time impact analysis’’ is the methodology to be used for assess- critical path planning software adopting the activity-on-node
ing extensions of time. The contractor should be required to pro- method and presented as a linked bar chart.
duce a subnetwork showing the actual or anticipated effects of the 3. Information required from the CA that is identified in the
employer delay that is the subject of the claim and show how this program is to be referenced by links to actual activities and
links into the latest update of the full program. Concurrent delays not simply by specifying a ‘‘needed by’’ date.
should, of course, be identified at this stage and their impact 4. Key resources required by each activity are to be defined,
recognized. The expectation is that relevant documents and and the program is to be cross-referenced to a method state-
records to demonstrate the contractor’s entitlement will accom- ment, i.e., the written description of how the contractor in-
pany each claim and that common sense and experience will be tends to carry out the works.
brought to bear in both preparation and assessment. It is clear 5. In recognition, no doubt, of the real problems that can arise
that, as some say, common sense is not very common, but the when a contractor fails to provide a program or to update it
Protocol uses these words to explain the need for sensible and on a regular basis, the Protocol suggests making payments
considered judgement on these difficult matters. Having submit- when both of these activities are successfully completed. It
ted the claim, the CA will make an assessment and must inform also considers the withholding of payments for failure to
the contractor with sufficient information to allow the contractor perform.
to understand the reasons for the judgment made. If the contractor For the records that need to be kept, the advice is that the parties
does not accept the decision, the CA should be informed imme- should reach a clear agreement at the outset so that a detailed
diately, and if no agreement can be reached, the resolution proce- understanding of what work was carried out and when it was
dures available in the contract should be invoked. For U.K. con- carried out can be reliably provided. The model clause gives de-
tracts, these are likely to include conciliation, adjudication, and/or tails of the various record sets that will be required and includes a
arbitration. Leaving such matters to be resolved at the end of the weekly and a monthly report that relates project work to the ac-
contract should not be seen as an acceptable option. tivities referenced on the agreed program.

Dealing with Disputed Extension of Time Issues Research


after Completion of Project
Previous sections of this paper have reviewed some of the con-
Although clearly preferring the time impact analysis technique for tinuing difficulties that are encountered when attempts are made
assessing delay claims, the Protocol recognizes that the factual to analyze and account for the delays and disruptions that affect
material available will not always permit such an analysis. Ac- construction projects; they have also introduced the U.K. Society
knowledgement is given to other methods that may be cheaper of Construction Law’s protocol for dealing with such situations.
and carried out with less information; these are ‘‘as-planned ver- The following is a report of recent research conducted to test how
sus as-built,’’ ‘‘impacted as-planned,’’ and ‘‘collapsed as-built.’’ U.K. professionals understand some of these issues and how they
Whichever method is used, the adjudicator, judge, or arbitrator is deal with them in practice. Interviews were conducted with 20
exhorted to consider a contractor’s entitlement by recreating the employees of contracting organizations, 20 professionals em-
circumstances that pertained at the time the claim was made. That ployed by project employers as contract administrators, and 6
is, not to take account of information about the contractor’s actual claims consultants, 46 interviewees in total. The interviews were
performance on the rest of the contract work following the event designed to address issues that arise when dealing with delay
that generated the claim. Other advice given is as follows: claims. This particular mix of personnel was chosen to get the

JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JANUARY 2004 / 53
views of the two main protagonists in on-site claims negotiations
共the contractors and the contract administrators兲 but also to get a
third party view 共that of the claims consultants兲. All but one of the
interviewees had more than 15 years experience in construction,
principally in the civil engineering sector, and 40 out of the 46
had been dealing with claims for more than 10 years. Thus, they
were well placed to comment on the issues addressed in the sur-
vey. These issues, and the interviewees’ reactions to them, will
now be discussed.

Findings of Research

General Methodology for Assessing Delay Claims


Here, the respondents were asked to state how they would analyze
the impact of delays on a contract, given the following choices:
1. Global method—compares the planned progress with actual
progress and identifies employer delay events, but makes no
effort to demonstrate cause and effect.
2. Network analysis—inserts delays into the program network
共producing an as-built plan兲 and analyzes their effect.
3. Critical path only—considers only the critical path through
the network and the delays that impact that path.
4. Fragnet analysis—effectively ‘‘time impact analysis,’’ where
the impact of delays on a part of the network is assessed and
then inserted back into the main updated network.
None of the respondents suggested any methods other than
those shown, but they were generally unwilling to select just one
approach from the above list, because it would depend on the
contract, the other party, or at what stage the claim was made.
They were asked to make two choices, but to state which of the
two selected was the most likely to be used. First choices were Fig. 1. General methodology for assessing delay claims: Percentage
weighted ‘‘2,’’ with second choices weighted ‘‘1.’’ Results for the weighted responses
three categories of respondent and for all together are shown in
Fig. 1.
The global approach 共Option 1兲 and the use of fragnets 共Op-
tion 4兲 were undoubtedly the least popular methods of assessing 1. The contractor should have exclusive control of the float.
or presenting delay claims, although the claims consultants do 2. The employer should have exclusive control of the float.
appear to make some use of fragnets. Those who present and 3. Where the contractor does not require it, the employer
carry out initial assessments of delay claims, contractors and CAs, should have use of the float.
appear to prefer to use the full network to do this. How those 4. Float should be available to either party on a first-come first-
networks are analyzed, however, may vary, with contractors pre- served basis.
ferring to analyze the complete network, while CAs appear most 5. The specification should define who has control of the float.
concerned with delays on the critical path alone. This evidence The results are shown in Fig. 2, where it can be seen that the
suggests that if time impact analysis, the Protocol’s preferred majority of respondents chose Statement 1, that the contractor
method, is to become the norm, there may need to be considerable should have exclusive control of the float. Eighty percent of all
efforts made to make it more widely recognized. respondents said that the contractor should have control of the
To gain a greater insight into the way in which the network float, with 95% of contractors supporting this view, although 65%
will actually be analyzed, two essential major issues were ad- of CAs also agreed with them. The one contractor who thought
dressed: the ownership of float in networks and concurrent delays. differently felt that the contractor and employer should jointly
own the float. The views of the remaining 17% were varied.
Three CAs and one arbitrator said that the specification should
Ownership of Float
define who has control of the float. Three other CAs said it should
Attitudes toward who owns the float in a network are central to be available on a first-come first-served basis, and one CA be-
the way in which networks are likely to be analyzed, and, for this lieved that when the contractor does not need the float the em-
reason, the issue was approached in two ways. First, respondents ployer can have the benefit of it. These results indicate some
were asked to select the particular statement that most closely agreement between the two major parties on-site that the contrac-
represented their views on float ownership from a number of de- tor should have control of the float in their own program, al-
fined statements. Secondly, respondents were asked to consider though the view is clearly much more strongly held by contrac-
and make judgments on two scenarios that encapsulate the float tors than by CAs.
ownership question. The project that was used in the scenarios throughout the en-
The statements shown to the respondents in the first question tire questionnaire and that will be used in the second part of this
were as follows: section is shown in the top panel of Fig. 3. It has eight activities,

54 / JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JANUARY 2004
Fig. 4. Results of ownership of float Scenario 1: Contractor’s delay
first
Fig. 2. Ownership of float: Initial question results

two paths through the network, and was chosen to be as simple as pens first and one due to the employer coming second, affected
possible while still allowing it to be an effective test of time- the project during construction, and, as a result, the project was
related issues in contracts. late by 1 week. For this outcome, the respondents were asked
To attempt to understand how the respondents actually deal whether an extension of time should be awarded and, if so, for
with float in contracts, two separate scenarios were produced, how long; whether overheads should be paid to the contractor,
both of which can be explained by considering Fig. 3. Each sce- and if so, for how long; whether there should be deduction of
nario contains two versions of the project barchart: one that liquidated damages and, if so, for how long? The results are
shows how the contractor planned to carry out the work and one shown in Fig. 4, which uses a key to define the responses. A
that shows what actually happened on the project. In Fig. 3, it is response of T0, C0, D1, for example, signifies that the respondent
clear that two separate delays, one due to the contractor that hap- thought that no extension of time was due, no recovery of over-

Fig. 3. Ownership of float Scenario 1: Contractor’s delay first

JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JANUARY 2004 / 55
these delays would no doubt be that the employer had instructed
more lampposts and that the contractor had ordered the paving
late. The responses for this scenario are shown in Fig. 5, where it
can be seen that the interviewees’ views are not nearly so uni-
form. The contractors were quite single-minded, and most of
them gave the same response as for the first scenario, but the
CAs’ responses have changed considerably. Where 90% of them
gave the T1, C1, D0 response in the first scenario, only 45% gave
that response here, with 40% believing that there should be no
extension, no overheads, and either 1 or 0 weeks liquidated dam-
ages deducted 共T0, C0, D0 or T0, C0, D1兲.
Clearly, for a respondent who believes that the contractor
should have control of the float, the responses to both scenarios
should be the same, i.e., T1, C1, D0. The great majority of con-
tractors did believe that they should have control over the float
and also gave consistent responses to both scenarios. The CAs,
however, were not so faithful to their previously expressed views,
changing from 65% agreeing to the contractors’ rights to the float
in the first question to only 45% believing that the order in which
delays occur should not affect the outcome.
From the two different approaches to this issue, it can be seen
Fig. 5. Results of ownership of float Scenario 2: Employer’s delay that there is actually a real difference between the two main par-
first ties on this issue, which as has been previously said, is fundamen-
tal to agreement about how delay claims should be assessed. The
fallback position proposed by the Protocol may thus be difficult
heads should be made, but that liquidated damages should be for the U.K. construction industry, particularly for contractors to
deducted for 1 week. The results for this scenario show very accept. Perhaps a stronger exhortation to ensure that float owner-
strong agreement between all parties that the contractor should be ship is defined in the contract would be beneficial.
awarded a 1 week extension of time, with recovery of overheads
for 1 week, and no deduction of liquidated damages 共T1, C1, D0兲.
The second scenario placed in front of the interviewees was
Dealing with Concurrent Delays
exactly the same as the first, except that the order of the two On concurrent delays, several scenarios were tested with different
delays was reversed, with the employer-responsible delay affect- types of concurrent delay and with delays overlapping for only
ing ‘‘erect lamp-posts and signs’’ and the contractor-responsible part of their duration. In this paper, however, it is the relatively
delay affecting ‘‘footpath paving and guardrail.’’ The cause of simple problem shown in Fig. 6 that will be discussed. This ques-

Fig. 6. Concurrent delay: Employer and contractor delay begin and end at the same time

56 / JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JANUARY 2004
agreed with the approach suggested by the Protocol, where re-
sponsibility between the contractor and employer is shared, and
an extension of time without costs is awarded. The results show
that the major barrier to acceptance of this method in the U.K.
would be the views of the contractors, who clearly have difficulty
accepting that they may not be entitled to prolongation costs for
an employer caused delay in these circumstances. Clearly, these
opinions do not have the weight of legal precedent, but in the
absence of legal precedent, they may be the best guide available
as to what would be accepted by the industry.

Problem of Early Completion Schedules


Most construction contracts will specify a ‘‘time for completion,’’
in which the work must be complete, otherwise the employer may
be able to recover liquidated damages from the contractor. The
problem addressed here, and shown in Fig. 8, arises when the
contractor provides a program showing the work will be com-
pleted earlier than the completion date, the work is then delayed
Fig. 7. Concurrent delay results by the employer 共type E delay in the figure兲, and the contractor
makes a claim for the cost of overheads for the prolonged period
on-site.
tion assesses respondents’ views of a very basic concurrent delay For this scenario, the respondents were asked to say: should
problem, where contractor and employer delays start and end at there be an extension of time 共T兲, and if so for how long; should
the same time and both impact the completion date by equal there be overheads paid 共C兲 and if so for how long; should there
amounts. As in previous tests, interviewees were asked to indicate be liquidated damages deducted 共D兲 and if so for how long? The
what extension of time, prolongation costs, and liquidated dam- results are shown in Fig. 9, in which T1, C1, D0 represents the
ages they thought fair in such a situation. The results are shown in view that an extension of time of 1 week with costs for 1 week
Fig. 7 and indicate that the majority of respondents, 87%, thought and no deduction of liquidated damages should be awarded. Not
that the contractor was entitled to an extension of time of 3 weeks surprisingly, 90% of the contractors believed that costs should be
for the employer caused delay, although opinion differed on how paid for 1 week. This view was affirmed by 60% of the CAs, 20%
many weeks prolongation costs should be paid. of whom also wanted to give an extension of time, despite the fact
The majority of contractors 共60%兲 felt that they would be en- that none was needed, because the work was completed by the
titled to 3 weeks prolongation costs; whereas, only 20% of CAs completion date. There were, however, 40% of the CAs and 33%
and no claims consultants thought this fair. This highlights a pos- of the claims consultants who felt that no overhead costs should
sible area of confrontation, although 35% of CAs and 10% of be paid. Clearly, the majority view was that overhead costs should
contractors said that they would be prepared to negotiate the issue be paid, but there was a sizeable majority who disagreed about
of prolongation costs. Twenty-six percent of all respondents what must surely be a fairly common occurrence on construction

Fig. 8. Scenario showing early completion schedule

JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JANUARY 2004 / 57
Fig. 9. Results of early completion schedule scenario

contracts. Although the agreement here between contractors and


CAs is not so well defined, the evidence still shows a majority of Fig. 11. Prolongation costs: Results
CAs agreeing with the decision to award 1 week costs. The posi-
tion taken by the Protocol here would appear to have reasonable
support. end兲 that should be paid or whether it should be the level of
overheads being incurred by the contractor at the time of the
Issue of Prolongation Costs delaying event. Respondents were asked to choose from
1. Prolongation costs at the actual time of the delay should be
When an employer-caused delay gives the contractor the right to payable;
recover site overhead costs for a prolonged period on-site, there 2. Prolongation costs at the end of the contract should be pay-
has always been some controversy about the level of site over- able;
head costs that should be reimbursed. In the U.K. and in the 3. Prolongation costs at the end of the contract should be pay-
Protocol, prolongation costs or prolongation payments are the able, and the contractor should prove any other additional
terms used for these site overhead costs incurred by the contractor costs over and above these; and
for a prolonged period on-site. Fig. 10 helps to describe this situ- 4. Other 共please specify兲.
ation by showing how the contractor’s overhead costs may The results are shown in Fig. 11, where it can be seen that
change as the project proceeds. It clearly suggests that the level of almost all the contractors 共95%兲, all the claims consultants, and
weekly overheads toward the end of the contract, when the work 50% of the CAs chose 1, with most of the rest of the CAs 共35%兲
is coming to an end, is likely to be lower than during the period choosing 3—the other 15% chose 2. Among the CAs there was an
when work is in full flow. Thus the argument concerns whether it even split between those who would pay overheads at the
is the level of overheads during the extended period on-site 共at the ‘‘higher’’ rate and those who would either pay at the ‘‘lower rate’’

Fig. 10. Contractor’s overhead costs

58 / JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JANUARY 2004
or expect additional justification to convince them to pay at any- Endnotes
thing more than the lower rate. If it is accepted that claims con-
sultants have a greater appreciation of the ways in which claims 1
A recent example of costly litigation over these issues is the case
are eventually settled, their unanimous choice of paying at the of Balfour Beatty Building v. Chestermount Properties 共1993兲 62
higher rate might be seen to be meaningful. Another way of look- BLR 1.
ing at this result for the contractor would be that the contractor 2
The drafters of the Protocol were: Jeremy Winter 共Chair兲, Rich-
should ensure that overhead costs are recorded and, if possible,
ard Bayfield, Paul Brough, Anthony Caletka, Jonathan Douglas,
agreed with the CA in the expectation that proof will be required
Peter Johnson, Stuart Jordan, Stuart Nash, Keith Pickavance, Jim
to justify any claim for overheads at a level higher than those
Pragnell, and David Richards. A copy of the Protocol, including
applying at the end of the contract. This is another issue where the
proposed solution recommended by the Protocol appears to have the graphics may be obtained from the SCL web-site: http://
reasonably good hopes of being acceptable to the U.K. construc- www.scl.org.uk
tion industry.

References
Conclusions
The absence of detailed legal precedent in the U.K. to show how Bordoli, D., and Baldwin, A. 共1998兲. ‘‘A methodology for assessing con-
delay claims should be handled has previously made the develop- struction project delays.’’ Constr. Manage. Econom., 16, 327–337.
Bresnen, M. J., Haslam, C. O., Beardsworth, A. D., Bryman, A. E., and
ment of pervasive and consistent good practice in these areas an
Hell, E. T. 共1990兲. ‘‘Performance on site and the building client.’’
unlikely prospect. The publication of the SCL Protocol has
Occasional Paper No. 42, Chartered Institute of Building, Ascot, U.K.
brought these possibilities closer. When taken together with stan-
Bubshait, A. A., and Cunningham, M. J. 共1998兲. ‘‘Comparison of delay
dard forms of contract that fail to recognize the complexity of analysis methodologies.’’ J. Constr. Eng. Manage., 124共4兲, 315–322.
these areas, we begin to understand what a positive step the pub- Duncan-Wallace, I. N. 共1995兲. Hudson’s building and engineering con-
lication of the SCL Protocol is for the national construction in- tracts, 11th Ed., Sweet & Maxwell, London.
dustry. Harris, R. A. 共2000兲. ‘‘An assessment of construction contract claims in
The authors of this paper certainly welcome its publication and the UK.’’ PhD thesis, University of Newcastle upon Tyne, Newcastle
congratulate the SCL for its perspicacity and determination in upon Tyne.
confronting such a daunting task. The next step, of course, is to Householder, J. L., and Rutland, H. E. 共1990兲. ‘‘Who owns float?’’ J.
encourage widespread use of the Protocol, and it is hoped that the Constr. Eng. Manage., 116共1兲, 130–133.
results of research published in this paper will help to understand Kartam, S. 共1999兲. ‘‘Generic methodology for analyzing delay claims.’’ J.
where some of the difficulties may lie. Constr. Eng. Manage., 125共6兲, 409– 419.
The positions taken by the Protocol on early completion Knoke, J. R., and Jentzen, G. H. 共1994兲. ‘‘Facilitate delay claim analysis
schedules and on prolongation costs appear to be generally ac- with as-built schedule database.’’ Proc., 1st Congress on Computing
ceptable to the construction industry. On early completion sched- in Civil Engineering, ASCE, New York.
ules, the research shows a majority of those interviewed, includ- Kraiem, Z. M., and Diekmann, J. E. 共1987兲. ‘‘Concurrent delays in con-
ing both contractors and CAs, accepting that overhead costs struction projects.’’ J. Constr. Eng. Manage., 13共4兲, 591– 602.
Majid, M. Z. A., and McCaffer, R. 共1998兲. ‘‘Factors of nonexcusable
should be paid, despite there being no need for an extension of
delays that influence contractors’ performance.’’ J. Manage. Eng.,
time. On prolongation costs, most thought that overheads current
14共3兲, 42– 49.
at the time of delay should be paid, although this view was only National Economic Development Council 共NEDC兲 for Building. 共1983兲.
accepted by half of the CAs. There were, however, aspects of the ‘‘Faster building for industry.’’ National Economic Development Of-
SCL guidance that may cause concern. The preferred method of fice, HMSO, London.
assessing extension of time claims, ‘‘time impact analysis,’’ was National Economic Development Council 共NEDC兲 for Construction.
shown by the research not to be well used in practice and may 共1988兲. ‘‘Faster building for commerce.’’ National Economic Devel-
require considerable efforts to have it more widely recognized. opment Office, HMSO, London.
There also seem to be difficulties with the contractor’s acceptance Rubin, R. A., et al. 共1983兲. Construction claims analysis, presentation,
of the position taken on float ownership and on concurrent delays. defense, Van Nostrand Reinhold, New York.
The research showed that the contractors’ strong view was that Scott, S. 共1993a兲. ‘‘Dealing with delay claims: A survey.’’ Int. J. Proj.
they should have exclusive control of the float, in direct contrast Manage., 11共3兲, 143–153.
to the Protocol and to the views of the other parties interviewed. Scott, S. 共1993b兲. ‘‘The nature and effects of construction delays.’’ Con-
On concurrent delays, contractors still expected to be paid over- str. Manage. Econom., 11, 358 –369.
head costs when a contractor-caused delay was concurrent with Society of Construction Law 共SCL兲. 共2002兲. ‘‘Protocol for determining
an employer-caused delay. extensions of time and compensation for delay and disruption.’’
Clearly, the employer can insist that the parts of the Protocol 具http://www.eotprotocol.com典.
Thomas, R. W. 共1993兲. Construction contract claims, Macmillan, New
addressing float and concurrent delay be written into the contract,
York.
but it should be recognized that there are also ways that contrac-
Thompson, R. M., Vorster, M. C., and Groton, J. P. 共2000兲. ‘‘Innovations
tors can respond that would serve to nullify the effects of the new
to manage disputes: DRB and NEC.’’ J. Manage. Eng., 16共5兲, 51–59.
requirements. Care needs to be taken to ensure that any defensive Wickwire, J. M., et al. 共1989兲. ‘‘Use of critical path method techniques in
action does not effectively turn the process into more of a game contract claims: Issues and developments, 1974 to 1988.’’ Public Con-
than a serious attempt to find a fair solution. The fact that there tract Law J., 18, 338 –391.
are some areas of consensus among those involved in contract Yogeswaran, K., et al. 共1998兲. ‘‘Claims for extensions of time in civil
delays as to how those delays should be analyzed bodes well for engineering projects.’’ Constr. Manage. Econom., 16, 283–293.
the acceptance of the Protocol, but this will not be achieved with- Zack, J. G., Jr. 共1993兲. ‘‘Claimsmanship: Current perspective.’’ J. Constr.
out overcoming some of the difficulties described. Eng. Manage., 119共3兲, 480– 497.

JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JANUARY 2004 / 59

You might also like