Understanding Extension of Time Under Different Standard Design-Build Forms of Contract

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Scholarly Paper

Understanding Extension of Time under Different


Standard Design-Build Forms of Contract
Islam H. El-adaway, F.ASCE 1; Ricky A. Vance 2; and Ibrahim S. Abotaleb, A.M.ASCE 3

Abstract: Contractual provisions related to delay and extension of time are often written in difficult language or presented in a scattered
manner in construction contracts. This could lead to confusion and misunderstanding by the different parties as to rights and responsibilities.
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

Thus, it is not surprising that poor contract administration is always listed among the top reasons for conflicts, claims, and disputes in the
construction industry. The goal of this paper is to present contract administration guidelines for appropriate utilization of the provisions
related to extension of time under the most widely used standard design-build contracts. This is particularly valuable bearing in mind
the complexity of addressing construction delays in general, as well as the growing popularity of design-build delivery methods in particular.
To address this goal, the authors (1) analyzed the provisions related to extension of time under standard design-build contracts published by a
range of professional bodies and institutions; (2) highlighted the differences and commonalities among the studied contracts in a comparative
analysis form; and (3) developed a checklist of causes and questions to provide an easy-to-use systematic process to allow for a more robust
process for managing claims for extension of time. The presented checklist acts as a tool for assessing and enhancing contract administration
for extension of time under design-build contracts. The checklist also provides associated parties with guidelines for drafting contractual
clauses related to extension of time under new design-build contracts. This study is expected to promote effective and efficient contract
administration of requests for extension of time, thus minimizing conflicts, claims, and disputes as well as enabling associated parties
to mitigate the related time and cost negative impacts on their projects. DOI: 10.1061/(ASCE)LA.1943-4170.0000331. © 2019 American
Society of Civil Engineers.

Introduction compensation related to each type. However, contractual provisions


are often written in difficult language or presented in a scattered
Due to the complex nature of today’s construction projects, changes manner in construction contract. This could lead to confusion
and delays are becoming the norm rather than the exception (Kadry and misunderstanding by the different parties as to rights and
et al. 2016). Such delays often have negative impacts on all parties responsibilities, especially at the side of those focused on the tech-
involved. Accordingly, it is essential to define mechanisms for deal- nical side of the job.
ing with delays and how the responsible party shall compensate the Recent reports by Arcadis (2015, 2016, 2017) studying construc-
negatively impacted parties (Pickavance 2010). Being able to han- tion disputes in North America, Asia, the Middle East, and Europe
dle delays and settle the associated conflicts and claims amicably is have shown that poor contract administration is the most common
better than having them escalate to disputes cases. That is why cur- cause of disputes. These reports are also supported by the early find-
rent national and international standard contracts, which are used in ings of Colin et al. (1996), Diekmann et al. (1994), Sykes (1996),
most construction projects, provide provisions that define the dif- Cheung and Yiu (2006), and Blake Dawson Waldron (2006), who
ferent types of delays and direct the parties to the procedures and perceive poor contract administration by project parties as one of the
major causes of disputes. Accordingly, proper contract administra-
1
Hurst-McCarthy Professor of Construction Engineering and Manage- tion is a leading factor for minimizing construction disputes.
ment, Professor of Civil Engineering, and Founding Director of Missouri Some research efforts have been made to provide guidelines
Consortium for Construction Innovation, Dept. of Civil, Architectural, and/or enhance the understanding of different parties as related to
and Environmental Engineering/Dept. of Engineering Management and different construction contracts. For example, Fawzy and El-adaway
Systems Engineering, Missouri Univ. of Science and Technology, 228 (2013) provided guidelines for utilizing the delay analysis tech-
Butler-Carlton Engineering Hall, 1401 N. Pine St., Rolla, MO 65409 niques in projects funded by the World Bank. Such projects use
(corresponding author). ORCID: https://orcid.org/0000-0002-7306-6380.
the International Federation of Consulting Engineers (FIDIC)
Email: eladaway@mst.edu
2
Operation District Supervisor, Tennessee Dept. of Transportation, standard forms of contract. Also, Fawzy and El-adaway (2012)
2665 NW Broad St., Murfreesboro, TN 37129; formerly, M.Sc. Student, discussed time at large and presented helpful principles on how
Dept. of Civil and Environmental Engineering, Univ. of Tennessee, parties should administer their contracts in cases of delays and ex-
Knoxville, TN 37996. Email: adam.vance@tn.gov tension of time. Further, El-adaway et al. (2016) provided guide-
3
Postdoctoral Research Fellow, Dept. of Civil, Architectural, and lines for administrating change-order provisions under national and
Environmental Engineering, Missouri Univ. of Science and Technology, international forms of contracts. Another beneficial effort in this
211-Butler-Carlton Engineering Hall, 1401 N. Pine St., Rolla, MO 65409. stream was made by El-Hoteiby et al. (2017), who proposed par-
Email: abotaleb@mst.edu ticular conditions to cover potential risks of construction projects,
Note. This manuscript was submitted on August 28, 2018; approved on
April 2, 2019; published online on September 27, 2019. Discussion period
thus minimizing disputes resulting from such risks. In addition,
open until February 27, 2020; separate discussions must be submitted for Abdul-Malak and Khalife (2017) presented detailed analysis of
individual papers. This paper is part of the Journal of Legal Affairs and contract notices in order to minimize disputes resulting from mis-
Dispute Resolution in Engineering and Construction, © ASCE, ISSN handling them. Most recently, Abotaleb and El-adaway (2017) pro-
1943-4162. vided contract administration guidelines for handling payment

© ASCE 04519031-1 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031


obligations under national and international standard design-build In fact, the effect of the delay-causing event is calculated in a rea-
contracts. Nevertheless, it was found that no guidelines have been sonable and straightforward manner. However, when it comes to
provided for promoting enhanced understanding for administering concurrent delays, the contracts are silent on how to allocate the
and handling extension of time under design-build contracts. responsibility of the delay. In other words, the contracts only men-
The goal of this paper is to present contract administration tion what happens after the concurrent delays are analyzed and con-
guidelines for appropriate utilization of the provisions related to verted into excusable and nonexcusable delays through delay
extension of time under the most widely used standard design-build analysis. This leaves it to the discretion of the parties to choose
contracts. As such, this study fills an important gap in the body of the delay analysis technique that suits their project. Thus, following
knowledge. completion of the delay quantum analysis, determination of the root
causes for that delay follows to ascertain whether an extension of
time should be awarded.
Background Information Delay analysis utilizes both as-planned and as-built schedules.
On one hand, the as-planned schedule is a graphical representation
of the design-builder’s original intentions for the completion of the
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

Construction Delays and Extension of Time


project, and it shows the different critical paths as well as the
Extension of time disputes can arise due to several reasons includ- planned activities and their sequence. On the other hand, the as-
ing faulty drafting, understanding, or administration of the relevant built schedule shows the actual dates of the activities in the project
clauses in the contract. Liquidated damages may be applied by the as they occurred in real life—including start and finish times, work
owner in cases where the design-builder fails to complete a project completed, resources used, slowdowns, idle times, work disruption
within the stipulated period or by a specified date for reasons periods, suspension, acceleration, delivery of materials, and change
caused by themselves and/or reasons for which they are respon- orders—to provide evidence and/or assessment of liability for
sible. However, owners cannot claim liquidated damages if they any delay. From the as-built dates, the analyst can deduce how
are the ones causing the delay (Higgins v. City of Filllmore). the as-built sequencing varies from the planned logic. Ultimately,
On the other hand, extension of time should be granted to the the purpose of the delay analysis is to calculate the contribution of
design-builder in cases where project delays are beyond their con- each party to the total delay.
trol and/or not within their responsibility. For example, if the owner The Association for the Advancement of Cost Engineering
is responsible for material delivery and fails to supply such material (AACE) International lists nine different schedule delay analyses
on time, an extension of time is provided to the design-builder in its Forensic Schedule Analysis (AACE 2011). The most widely
(Gymo Constr. Co. v. Architectural Glass & Windows Inc.). The recognized ones are as follows:
different types of construction delays, their assessment methods, • As-planned versus as-built analysis: this is a retrospective meth-
and repercussions of each—if any—on the parties to the project od that compares the baseline, or as-planned, schedule with the
are specified in the contract. However, such delays are generally as-built schedule. This method is used when the baseline and as-
grouped in the following four broad categories (Menesi 2007; built schedules exist reliably, but the interim schedule updates
Fawzy and El-adaway 2012): are not reliable (because they either do not exist or are flawed).
• Nonexcusable delays, which are inclusive of the delays for • Impacted as-planned: this is where delays caused by the default-
which the design-builder either causes or is contractually re- ing party are identified and inserted into the as-planned sche-
sponsible for their risks, and thus the design-builder is not re- dule, and the result would be an impacted schedule with a
lieved of their consequences. new date for completion. As such, one party would insert
• Noncompensable excusable delays, which are caused by factors only the other’s responsible delays, and the resultant impact
that are not foreseeable, beyond the design-builder’s reasonable on the project duration shall represent the extension of time
control, or not attributable to the design-builder’s fault or negli- entitlement.
gence (i.e., adverse weather conditions). Thus, although the • Collapsed as-built (or but-for analysis): this is where the as-built
design-builder will not receive compensation for the cost of schedule is used, and then the activities representing the owner’s
delay, they will be entitled to additional time to complete the delays are removed to shorten the actual durations of delayed
work and are relieved from any contractually imposed liqui- activities. As such, the output will be a schedule that could
dated damages for the period of delay. have been achieved if it was not for the actions of the defaulting
• Compensable excusable delays, which include suspensions party.
and/or interruptions to all or part of the work caused by an • Windows/snapshot/time slice/contemporaneous period analysis:
act or failure to act by the owner resulting from noncompliance this is where the total duration of the project is divided into a
and/or breach of an obligation, stated or implied, in the contract. number of time periods (windows or snapshots). Then, the pro-
Thus, the design-builder is entitled to not only an extension of ject is updated at the end of each window using regular updates
time but also to an adjustment for any increase in costs caused of the as-planned schedule, and both the critical path as well as
by the delay. the extent of delay incurred to completion are determined at that
• Concurrent delays, which occur when both owner and design- date for each window. As such, the delays are then analyzed
builder are responsible for the delay. Depending upon the situa- within that window to determine the ones for which the design-
tion and the contractual terms and conditions, the concurrency builder is responsible and the ones for which the owner is re-
analysis can get more complicated at times as related to the ap- sponsible, and the process is repeated for all windows.
portionment to segregate the intertwined cause-and-effect rela- Each delay analysis technique has its own strengths and weak-
tionships and associated responsibility for the delay. A true nesses. However, all of them can be used to proportion and assess
concurrent delay is classified as excusable noncompensable the contribution of each entity to the total delay as well as estimate
delay that entitles the design-builder to a time extension as well the extension of time entitlement. Along the same lines, the Delay
as the remission of liquidated damages. and Dispute Protocol (SCL 2018) established by the Society of
Construction contracts usually clearly state how the parties Construction Law (SCL) also referenced the aforementioned delay
should proceed in the case of excusable and nonexcusable delays. analysis techniques as well as other techniques such as the time

© ASCE 04519031-2 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031


impact analysis and retrospective longest-path analysis. Moreover, Review and Analysis
the Protocol discussed the limitations of each technique and their
effect on the delay analysis. Thus, realizing that standard forms of Extension of Time under the AIA Design-Build
contracts generally do not recommend specific delay analysis tech- Contract
nique, the Protocol suggested that the parties to the contract should
try to agree on an appropriate method of delay analysis to better The AIA “publishes nearly 200 agreements and administrative
manage potential project delays. forms that are recognized throughout the design and construction
industry as the benchmark documents for managing transactions
and relationships involved in construction projects” (AIA 2014).
Design-Build Delivery Method The latest edition of AIA’s DB contract is AIA A141 (AIA
2014), which is the contract investigated in this paper.
Several project-delivery methods are currently used in construction
When delays are encountered under AIA A141, the owner and
projects; however, the most widespread ones for US government
design-builder need to take notice of Article 8. In particular, Article
contracts are design-bid-build (DBB) and design-build (DB)
8.2.1 states that if the design-builder is delayed due to no fault of
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

(Hale et al. 2009). DBB is the traditional delivery system where


their own, then the contract time shall be extended by work of a
an owner contracts separately with a designer and a design-builder.
change order for the reasonable amount of time that the owner sees
As such, the design-builder starts the construction works only when
fit. Also, Article 8.2.1 details the reasons for which the design-
the design documents are ready. On the other hand, in the DB de-
builder is due a time extension to include acts or neglect of the
livery system, the owner contracts with a single entity to perform
owner or of a consultant or separate design-builder employed by
both the design and construction under a single design-build con-
the owner. These reasons also include (1) any changes ordered
tract. This type of contract enables a single point of responsibility
by the owner to the original scope of work, labor disputes, fire,
for both design and construction (Moore 1998). The authors chose unusual delay in deliveries, unavoidable casualties or other causes
to focus this research on the DB method due to its growing use in beyond the design-builder’s control; and (2) delays authorized by
the industry as shown in the following statistics. the owner pending mediation and binding dispute resolution or by
A comparative study by the Construction Industry Institute (CII) other causes found justifiable by the owner.
and sponsored by the National Institute for Standards and Technol- If any of the aforementioned delays occur, the design-builder is
ogy (NIST) found that DB projects were about four times larger entitled to a time extension. However, this does not prohibit either
than DBB projects in terms of project cost (Thomas et al. 2002). entity from claiming other damages under other provisions of the
That study, as well as other recently published studies, suggested contract. Under Article 9.7, if the owner does not issue certificate
that DB projects generally outperform DBB projects in changes, for payment or pay the associated amount within the time indicated
rework, and practice use (Thomas et al. 2002; Riley et al. 2005; in the contract, the design-builder can stop the work after providing
Hale et al. 2009; Rosner et al. 2009). Due to its many advantages the owner with a 7-day written notice. This Article also gives way
in allocating clear responsibilities and incorporating project com- for justifiable time extension. In this case, the contract time shall be
plexities, the use of the DB method has increased noticeably in the extended appropriately and the contract sum shall be increased in
last decade, especially in large and complex projects (Shrestha accordance to the design-builder’s reasonable costs of shut down,
et al. 2012). In fact, the market shares for the DB method increased delay, start up, and interest.
from 29% in 2005 to 39% in 2013; in contrast, the market share for When events occur that could entitle the design-builder to time
the DBB method decreased from 67% in 2005 to 52% in 2013 extension under Article 8.1, the claim process shall follow Article
(Duggan and Patel 2013). For large projects, it was estimated that 14.1.6, where it is stated that written notice shall be provided, as
more than half of projects above $10 million are being completed with other claims pertained to the design-build document. When
through the DB method (Duggan and Patel 2013). For example, submitting claims per Article 14.1.6.1, the design-builder should
between 1990 and 2002 alone, approximately 140 Special Exper- include an estimate of the time and its effect on the progress of
imental Project No. 14 (SEP-14) projects, worth $5.5 billion, were the work. If the delay is continuous throughout the project, then
completed using the DB delivery method (FHWA 2006). only one claim is to be submitted. Article 14.1.6.2 goes on to men-
tion that if the delay is due to adverse weather conditions, then rel-
evant data should be submitted to show that the weather conditions
Methodology could not have been predicted and that they had an adverse effect
on the project time.
As follows, a multistep interdependent research methodology Time extension claims need to be submitted with substantiating
was devised to attain the research goals and objectives whereby documentation as soon as the delays occur. The design-builder need
the authors (1) reviewed and analyzed the provisions related not to wait until the end of the contract to submit a claim. To this
to extension of time under the most common national and end, under Article 14.1.3.1, claims by either party are to be initiated
international standard design-build contracts, including those pub- within 21 days of the occurrence of the event or within 21 days of
lished by the American Institute of Architects (AIA), Consensus- recognizing that the condition will give rise to a claim, whichever is
DOCS, Engineers Joint Contract Documents Committee (EJCDC), later. Such time limits are not time-barring. After the claim has been
Joint Contracts Tribunal (JCT), New Engineering Contract (NEC), filed and is processed under Articles 14.2.3 and 14.2.4, the design-
and FIDIC; (2) highlighted the differences and commonalities builder shall still proceed diligently with the work while the claim
among the aforementioned contracts in a comparative analysis is being assessed and evaluated. Article 14.2.5 states that although
form; and (3) developed a comprehensive checklist of causes the owner’s initial decision on any claim is final and binding, it is
and questions that acts as a tool for assessing and enhancing con- still subject to mediation and binding dispute resolution (i.e., arbi-
tract administration for extension of time under design-build con- tration) afterward if the parties fail to resolve their dispute through
tracts and provides associated parties with guidelines for drafting mediation. Article 14.2.6 details the process for initiating mediation
contractual clauses related to extension of time under new design- and/or arbitration, and the actual procedure for each is detailed
build contracts. under Articles 14.3 and 14.4, respectively.

© ASCE 04519031-3 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031


Extension of Time under the ConsensusDOCS (NSPE), the American Council of Engineering Companies, and
Design-Build Contract ASCE. EJCDC’s design-build contracts are handled under the
D-700 series.
The ConsensusDOCS contracts were established by 41 industry
There are several articles that deal with the issue of time exten-
organizations to represent the designers, owners, contractors,
design-builders, and sureties. ConsensusDOCS contracts purport sion due to delays within EJCDC D700 (EJCDC 2016). Article
to protect the best interests of the project rather than a singular 11.02 B states that the design-builder will be entitled to a time ex-
party, yielding better project results and fewer disputes (Harris tension for delays that are beyond their control and provides the
and Perlberg 2009). The following paragraphs will present how following list of excusable delays:
ConsensusDOCS 410—the agreement between the owner and • acts of neglect by the owner,
the design-build entity—handles the issues of delays and time • governmental agencies,
extension (ConsensusDocs 2017). • acts of neglect by utility companies,
Under ConsensusDOCS 410, the owner and the design-builder • delays due to other contractors working for the owner,
are to be aware of Article 6.3. In fact, Article 6.3.1 states that if the • fires,
• floods,
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

design-builder is delayed at any time during the commencement or


progress of the work due to causes beyond their control, they will be • epidemics,
entitled to an equitable extension in the contract time. The following • abnormal weather conditions,
causes are provided as legitimate bases for time extension requests: • acts of God, and
• acts of omission by the owner or others, • others.
• changes or decisions in the work ordered/changed by the owner, Article 11.02A states that extension of time claims should fol-
• unpredictable changes in transportation, low the procedure outlined under Article 9.03, where the original
• labor disputes not involving the design-builder, and ones that time for completion can only be modified using a change order.
impact the project but that are not related to the project, There are other articles in the EJCDC contract that entitle
• fire, the design-builder to a time extension. Under Article 4.02, the
• terrorism, design-builder is entitled to an extension of time if there are differ-
• epidemics, ing site conditions that were not included in the contract document
• adverse governmental actions, by the owner, or if the design-builder encounters conditions that
• unavoidable accidents, differ materially than what could have been anticipated for the site
• adverse weather, in question. At such instance, written notice has to be given to
• hazardous material, the owner. Subsequently, the owner will investigate the site, and
• concealed and unknown conditions, if the site differs to the extent of effecting the original time for
• delay by owner pending disputes resolutions, and completion, an equitable adjustment in time will be made. For
• suspension by the owner under Article 12.1, “Suspension for the design-builder to claim time extension, they have to follow
Convenience.” the times set out under Article 9.03.
All of the aforementioned delays are out of design-builder’s If hazardous material is encountered in the project and this was
control. It is obvious, however, that ConcensusDOCS 410 provides not accounted for under the contract and/or was not caused by the
more reasons for extension of time due compared with AIA A141. design-builder, then this would provide basis for a time extension
These differences and similarities will be detailed and discussed under Article 4.04C. In this case, if the owner and design-builder
subsequently in this paper. can agree on an acceptable time extension, a change order does not
Once an excusable delay occurs, a claim for a time extension can need to be issued. If an agreement cannot be reached, however, then
be filed. When filing a claim for time extension, both the owner and the design-builder should file a claim as per Article 9.03.
design-builder need to follow Article 9.6. Under this Article, the Under Article 9.02, the design-builder is entitled to a time ex-
design-builder should submit a claim within 21 days of the occur- tension if unauthorized changes in the work are required under
rence that has caused the delay or within 21 days after the design- Articles 6.16 and 12.04. On one hand, Article 6.16 allows for time
builder has noticed the condition giving rise to the claim, whichever extension if at any time the design-builder believes that the safety
is later. This ensures that the design-builder will be able to still sub- of the project, employees, or the surrounding is in jeopardy due to
mit a claim even if they do not immediately notice that the delay the specific scope and/or nature of the project. This requires the
was going to negatively impact the progress on the project. After the design-builder to change how the work is performed to ensure
claim has been submitted, the design-builder has 21 days to supply safety. Written notice has to be given to the owner of the variations
the supporting documentation. After the owner receives the claim that had to be made to the contract. This process will be handled
with its supporting documentation, they have 14 days to respond to under a change order. On the other hand, Article 12.04 allows the
the claim. A nonresponse to the claim means the claim was denied. design-builder to have a time extension if the owner requires that
If the claim is accepted, then it will be handled by a change order. If they uncover previously accepted construction work for further
a reasonable amount of time extension cannot be agreed upon, the testing, inspection, and evaluation. This type of time extension also
claim will be handled by a neutral party or a dispute review board falls under Article 9.03.
selected by both parties to the contract as per Article 13.3. If no Finally, under Article 14.01, the owner is allowed to suspend the
neutral is chosen, then the dispute shall be handled by mediation work at any time provided the design-builder is given a written
per Article 13.4. If no resolution is reached after Article 13.3 or notice indicating a fixed date as to when the work is to be resumed.
13.4, the claim will end up in arbitration. To this end, the design-builder is only allowed an extension of time
if a claim is filed in accordance to Article 9.03.
Article 9.03 addresses the issue of claims for extension of time
Extension of Time under the Engineers Joint Contract
and states that the design-builder has 15 days from the time of the
Document Committee Design-Build Contract
occurrence of the event causing the delay—or from the time when
The Engineers Joint Contract Document Committee (EJCDC) is a it was known that an agreement could not be reached—to submit
joint venture among the National Society of Professional Engineers a time extension claim. After the submission of a claim, the

© ASCE 04519031-4 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031


design-builder has 30 days to supply substantiating documentation • flood,
to support their claim. After receiving the supporting documents, • earthquake,
the owner will have 30 days to give a decision. If the design-builder • aircraft,
is not satisfied with the decision, they have 30 days to exercise their • riot and commotion, and
right to a dispute under Article 15. If the design-builder does not • escape of water from any water tank, apparatus, or pipe.
initiate the dispute within 30 days, then the decision is final. Article If any of these events occur, the design-builder is entitled to a
15 allows for the owner and design-builder to agree on how dis- time extension. However, this does not mean that these are the only
putes are handled. reasons that may warrant a time extension. If the design-builder
encounters other delays outside of its control, they needs to docu-
ment the delays and inform the owner.
Extension of Time under JCT Design-Build Contracts Extension of time is handled under Clauses 2-24 and 2-25.
The JCT was formed in 1931 by the Royal Institute of British Clause 2-24 requires that the design-builder gives notice to the
Architects (RIBA), and the first JCT standard form of building con- owner as soon as it has become apparently reasonable that the
progress of the work has been or will be delayed. Unlike the rest
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

tract was issued. The forms were not referred to as JCT until 1977.
JCT members revised the latest edition of their design-build con- of the contracts, which set a certain time frame for the design-
tract in 2016. As such, the JCT 2016 edition is the subject of this builder to submit the notice after the delaying event takes place,
paper (JCT 2016). this contract does not set this period numerically. Instead, it says
Under JCT 2016, the design-builder is entitled to time extension “as soon as possible.” This ambiguity could be risky because the
if the delays are defined as a relevant event per the contract docu- definition of “soon” may be conceived differently by the different
ments and if that event will indeed cause a delay to the completion parties. The notice shall include the causes of the delays and state
to any section or the entirety of the project. The concept of relevant which delay falls under relevant events. Once the design-builder
events is first mentioned under Clauses 2-23 to 2-26. These clauses has submitted a claim for a time extension, they shall submit
inform the design-builder of which events are considered relevant the effect the delay has on the project and an estimate of the time
events per their contract agreement and how they should report the needed to adjust to delay as soon as possible. Once the claim for a
associated delays. Clause 2-26 lists the relevant events that will delay has been submitted, the owner will investigate that the sub-
allow for time extension by the design-builder. The JCT contract mitted information is appropriate to being a relevant event and that
provides corresponding clauses that have additional information it will cause the project to extend beyond its original completion
to help clarify what is considered relevant events, and these are de- date. If both of these requirements are justified, then the owner
tailed in the following paragraphs. will give a time extension based on fair and reasonable estimates
Instructions from the owner are covered under Clauses 2-13, per Clause 2-25. Also, under Clause 2-25, the owner has to respond
3-10, 3-12, and 3-13-3. Clause 2-13 gives the design-builder enti- to the design-builder as soon as reasonably possible but no longer
tlement to a time extension if they notices any discrepancies in the than 12 weeks from the time the design-builder submitted the sup-
owner’s requirements, design-builders’ proposal, instruction issued porting documents. If the decision is not agreed upon by both par-
by the owner, or with the drawings and documents requested by the ties, then the claim will become a dispute that will be handled by
owner. Any of these discrepancies can affect either the design mediation, adjudication, or arbitration as per Clause 9.
and/or construction of the project and need to be clarified before
work continues. Clauses 3-12 and 3-13 allow the design-builder to
receive a time extension if the owner requires that the design- Extension of Time under the NEC Design-Build
Contract
builder uncovers the work for further tests and inspections. If the
tests and inspections prove to be of satisfaction to the owner, then The Institution of Civil Engineers, based in the United Kingdom,
the design-builder is entitled to time that will compensate for the created and published the New Engineering Contract (NEC 2013),
time required to uncover, test, and recover. which is a suite of standard form of construction contracts. Exten-
Clause 3-15 applies to any antiquities or fossils that are uncov- sion of time under the NEC was covered before by El-adaway et al.
ered or discovered during any operation of the construction project. (2016) for design-bid-build projects but because the same contract
This requires the design-builder to stop construction works and in- is still applicable to design-build, there will be significant unavoid-
form the owner of what is found. The owner then investigates the able similarities in the forthcoming discussions.
site and determines how they want to handle the preservation of the There are several events under the NEC under which the
artifacts. This may even require that the design-builder works with design-builder is entitled to compensation, extension of time, or
a third party under the direction of the owner. Accordingly, a time both. Clause 60.1 addresses the compensation events and includes
extension will be allowed. the following:
Under Clause 4-11, the design-builder is allowed a time exten- 1. The project manager releases an instruction to change the work
sion if they are to suspend the work in case the owner does not pay information, except in the following cases:
as per the contract. The design-builder has to submit their intention • a change to accept a defect, or
to suspend work 7 days in advance with proper justification. • a change provided by the design-builder in its design, made
The owner and design-builder must then reach an agreement on at its request, or to comply with other work information
an adequate time to allow for the project to be completed once provided by the owner.
the design-builder resumes work. Another relevant event that is fur- 2. The owner does not allow the design-builder access to the site
ther defined is the issue of specified perils. The following specified or part of it by later than the agreed access date shown in the
perils, also referred to as force majeure events, are listed under accepted program.
Section 6 of the JCT design-build contract: 3. The owner fails to provide something as agreed and in accor-
• fire, dance with the accepted program.
• lightning, 4. The project manager gives instructions to stop or change a
• explosion, key date.
• storm, 5. The owner or the other parties

© ASCE 04519031-5 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031


• do not work in accordance with the time in the accepted changed, or the design-builder is requested to submit quotations.
program, In NEC 3 (NEC 2013), under Clause 61.4, the project manager
• do not work in accordance with the conditions in the work has to send a reply within 1 week from receiving the design-build-
information, or er’s notification, or within a longer period if the design-builder
• carry out work not stated in the work information. agrees. The assessment of the extension of time is done in accor-
6. The project manager or supervisor fails to reply to commu- dance with Clause 63.3.
nication in accordance with the time period stated in the In case the project manager fails to reply within the aforemen-
contract. tioned time limit, the design-builder may notify them. If still no
7. The project manager gives instructions to deal with historical reply is sent within 2 weeks, it can be interpreted as an acceptance
artifacts or other objects of value or interest found on site. from the project manager of the event as a compensation event
8. The project manager or the supervisor makes changes to pre- and as a request to submit quotations. In this case, the design-
viously communicated decisions within the contracts. builder shall submit quotations of the desired compensation for
9. The project manager withholds acceptance, except an accep- the delaying event within 3 weeks of being instructed to do so.
tance for quotation for acceleration, or for not correcting a The project manager then replies within 2 weeks of that submis-
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

defect. sion with either an acceptance, instructions to submit a revised


10. The design-builder is instructed by the supervisor to search for proposal, or a notification that the proposed instruction will not
a defect and they do not find one, unless the instruction was be given, that a proposed change to a decision will not be made,
made because the design-builder had failed to give proper or that they will make their own assessment. In accordance with
notice of work and obstructed a test or inspection. Clause 62.6 again, failure of the project manager to reply to sub-
11. An unnecessary delay is caused by a test or inspection done by mitted quotations within 2 weeks of submission will lead to the
the supervisor. same aforementioned scenario. The design-builder may send a no-
12. The design-builder encounters physical conditions that would tification to this effect. If there is no reply within 2 weeks, this
have been judged by any experienced design-builder to have a may be considered as an acceptance of the quotation. However,
small chance of occurring and it would have been unreason- in accordance with Clause 64.1, if the design-builder fails to sub-
able to be allowed. mit a quotation within the previously mentioned 3-week period,
13. An abnormal weather measurement that is expected to occur the project manager is given the discretion to assess the compen-
on average less than once in 10 years is recorded. sation event. Eventually, if the design-builder’s quotation is ac-
14. An event that is stated as an owner’s risk occurs. cepted or treated as such or the project manager makes their
15. The project manager certifies the takeover of part of the works own assessment, the compensation event will be implemented
before completion date. in accordance with Clause 65.1.
16. The owner fails to provide materials, facilities, sample tests, or According to Clause 13.1, all notifications shall be in writing.
inspection stated in the work information. According to Clause 13.7, notices are to be communicated sepa-
17. The project manager sends a notification to correct or/and rately from other communications. Therefore, a notice of compen-
adjust a previously stated assumption about a compensation sation should not be included in a progress report, for example.
event. A separate communication is needed for compensation events. In
18. The owner is in breach of the contract, which is not one of the case the design-builder is dissatisfied with the project manager’s
compensation events in the contract. decision, this matter is to be handled by adjudication and/or tribu-
19. An event that nal, in accordance with Options 1 and 2 of NEC.
• makes the design-builder unable to complete the works,
• makes the design-builder unable to perform the works in ac-
cordance with the accepted program, Extension of Time under FIDIC Design-Build Contract
• cannot be prevented by neither party, or The FIDIC is well known for its standard forms of contracts
• would have been judged by an experienced contractor, at the directed for the construction industry worldwide. The most recent
contract date, to have a such a small chance of occurring that and up-to-date suite of contracts was published in 2017 (FIDIC
it would have been unreasonable to be allowed, and is not 2017b), and includes the second edition of the so-called design-
one of the compensation events. build Yellow Book. Extension of time under the FIDIC was
In accordance with Clause 16.1, the design-builder may notify covered before by El-adaway et al. (2016) but because there is some
the project manager, as an early warning, of any event that delays commonality between the Red and Yellow Books, some similarity
the completion date. This is to ensure that the design-builder does in the forthcoming discussion is unavoidable (FIDIC 2017a).
not benefit due to failure to give an early warning. The warning In the FIDIC Yellow Book’s Subclause 8.4, the following list of
may mitigate the effect of the compensation event. conditions where a design-builder could be entitled to an extension
NEC has a slightly different procedure from other contracts. The of time is given:
project manager and the design-builder are both obligated, under • a variation, except adjustment to time for completion agreed in
Clauses 61.1 and 61.3, to notify each other. Under Clause 61.1, accordance with Subclause 13.3 “Variation Procedures,” or
the project manager has to notify the design-builder of the compen- other substantial changes to the quantity of an item in the works,
sation event at the time of giving the instruction or making a change • exceptionally adverse climatic conditions,
to an earlier decision. Under Clause 61.3, the design-builder is • unforeseeable shortage of personnel or goods due to epidemics
given a time bar of 8 weeks to send a notification of a compensation or governmental actions, and
event to the project manager. Failure to do so with that time period • any delay, impediment, or prevention caused by or attributable
will leave them with no entitlement to extension of time unless the to the owner, the owner’s personnel, or the owner’s other
project manager was required to send a notification of the event to contractors.
the design-builder. The notice is a condition precedent. After re- Subparagraph (b) mentions “a cause of delay giving an entitle-
ceipt of the notification, the project manager shall reply with a no- ment to extension of time under a Sub-Clause of these conditions.”
tification of its decision, where the completion date is not to be This easily overlooked part is important for design-builders

© ASCE 04519031-6 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031


and gives more situations where an extension of time could be advance of any future events that may cause delay to the execution
warranted (Fawzy and El-adaway 2012). Bunni (2005) listed the of the works. In such an event, the engineer may request a proposal
following subclauses: for variation to be submitted by the contractor. This aims to min-
• 1.9: delayed drawings or instructions, imize or avoid the effect of such known or probable events. How-
• 2.1: delay in giving access to or possession of the site, ever, the subclause does not mention the consequences for failure to
• 4.7: error in specified referenced points, give such advance warning.
• 4.12: adverse unforeseeable physical conditions,
• 4.24: fossils,
• 7.4: delayed testing caused by the owner, Discussion
• 8.5: delays caused by authorities,
• 8.9: suspension initiated by the owner, This paper reviewed and analyzed the bases that entitle the design-
• 10.3: interference by owner in tests on completion, builder to a time extension and investigated the corresponding pro-
• 13.1: variations, cedure and rights under different standard design-build contracts.
• 13.7: adjustments for changes in legislation, To this effect, and as outlined in Table 1, each of the investigated
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

• 16.1: design-builder’s entitlement to suspend work, contracts has its own set of conditions to initiate a claim for exten-
• 17.4: owner’s risk, and sion of time. The matter of properly understanding the provisions
• 19.4: force majeure. of the contract with respect to extensions of time is of significant
The procedure for extension of time is similar to that of addi- importance, especially in relation to the provided time limits for
tional payment. It is covered in Subclause 20.1 and is shown in both the design-builder as well as the engineer/architect/project
Fig. 1. Procedures for continuing delay are covered in Subclause manager. Because this paper is not only dealing with US contracts,
20.1 and are shown in Fig. 2. Failure of the design-builder to send but also incorporates other international contracts, some of the dis-
notice of claim within 28 days will result in nonextension of the cussion might not be always pertinent or supported by US courts.
time for completion. A proper notice is a condition precedent to As such, parties should always resort to professional legal advice to
entitlement to extension of time. Also, the design-builder is respon- avoid any ambiguity or confusion.
sible for submitting interim claims at monthly intervals with the As far as the design-builder is concerned, Knowles (2005) stated
accumulated delays and/or the amount claimed. They are also re- that in case of a design-builder’s failure to follow notice and claim
quired to send a final claim within 28 days of the end of the delaying provisions, “this will not result in the loss of rights to an extension
event. In case of the design-builder’s failure to follow the proce- of time unless the conditions of the contract expressly state that the
dures and provide details of the claim for extension of time in re- service of a notice is a condition precedent to such rights.” Also,
lation to any claim, any extension of time and/or additional payment Chappell (2007) stated that giving of the notice is not a precondi-
tion to the award of an extension of time unless the contract ex-
shall take account of the extent, if any, to which the failure has pre-
pressly states so. Along the same token, if the design-builder does
vented or prejudiced proper investigation of the claim. After receipt
not provide a condition precedent delay notice, this failure may
of a claim, the engineer has 42 days to approve or disapprove claim
simply result in waiver or forfeiture of a claim (El-adaway et al.
and must provide detailed comments with the response.
2016). Accordingly, if the design-builder fails to serve a proper
If any of the parties is unsatisfied with the engineer’s decision,
delay notice, this would not result in the loss of rights to an
they should first attempt amicable settlement. According to the pro-
extension of time under design-build contracts developed by AIA,
cedure in Clause 20, they can refer the matter to the dispute adju-
ConsensusDocs, and JCT because the time limits mentioned
dication board, followed by arbitration. As far as time is concerned,
therein are not time-barring. However, design-build contracts of
Subclause 8.4 requires all project parties to advise each other in EJCDC, NEC, and FIDIC provide time limits that are conditions
precedent for recovering the claimed right. EJCDC states under
Article 10.05.F that “no claim for an adjustment in contract price
or contract times will be valid if not submitted in accordance with
this paragraph 10.05.” NEC also considers failure by the design-
builder to comply with the contractual time period (8 weeks) in
submitting a notification of the compensation event to the project
manager as time-barring. The latter will therefore leave the design-
builder with no entitlement for extension of time unless they had
Fig. 1. Extension of time under the FIDIC (2017b) Yellow Book.
already been notified by the project manager. Finally, Subclause
20.1 of the FIDIC Yellow Book states.
If the Contractor fails to give notice of a claim within such
a period of 28 days, Completion shall not be extended, the
Contractor shall not be entitled to additional payment, and
the Employer shall be discharged from all liability in connec-
tion with the Claim.
On the other hand, and as far as the engineer/architect/project
manager is concerned, the contracts under investigation deal differ-
ently with this matter. For example, according to 10.05.D of
EJCDC, if the engineer failed to take action on a claim with the
aforementioned timescale of 30 days, the claim will be deemed de-
nied. However, under the FIDIC Yellow Book, if the engineer fails
Fig. 2. Extension of time for events having continuing effects under
to determine extensions of time in accordance with the provisions
FIDIC (2017b) Yellow Book.
of the contract and if the design-builder is entitled to extension of

© ASCE 04519031-7 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031


Table 1. Process for extension of time claims under standard design-build contracts
Procedure AIA ConsensusDOCS EJCDC JCT NEC FIDIC
(A) Report delaya 21 days 21 days 15 days As soon 8 weeks 28 days
as possible
Does the design-builder lose the Not clear Not clear Not clear N/A Yes unless project manager Yes
right to claim for an extension was the one supposed to
of time caused by the delay after send the notification being
the reporting period (A) is over? the instructor of the change
causing the delay
(B) Supporting documentationb 21 days 21 days 30 days As soon 3 weeks 20 days
as possible
What happens if the design- Not clear Not clear Not clear N/A Project manager can assess Any extension of time and/
builder does not provide the based on their view or additional payment shall
supporting documents on time? take account of the extent, if
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

any, to which the failure has


prevented or prejudiced
proper investigation of the
claim
(C) Decisionc 10 days 14 days 30 days 12 weeks 1 week for notice and 42 days
2 weeks for supporting
documents
What happens if the owner/ Not clear Claim is denied Not clear Not clear Quotation deemed accepted Not clear
engineer/project manager fail to
provide a decision or a reply
within the decision period (E)?
(D) Disputed 30 days — 30 days — 4 weeks 20 days
(E) Determined bye Owner Negotiated Owner Employer Project manager Engineer
(F) Relating article/clausef 14.2 9.6 9.03 2-24/2-25 60 through 64 8.4 and 20
a
Maximum time between the event causing the delay and submitting a notice by the design-builder.
b
Maximum time between submitting the notice and the supporting documents showing the details of the requested extension of time.
c
Maximum time for the owner/engineer/project manager after receiving the supporting documentation to reply with approval/disapproval of the requested
extension of time.
d
Duration for which the design-builder can exercise the right to dispute the decision of the owner/engineer/project manager, calculated from the day the design-
builder receives the decision of the owner/engineer/project manager. A forward slash symbol means that the contract is silent regarding that matter. Under
EJCDC, if the design-builder does not rebuttal the decision within 30 days, the decision becomes final.
e
Final determination of the extension of time and the corresponding added compensation is provided by which party.
f
Clause in the contract that is associated with extension of time and its relevant procedure.

time and can prove that right, the owner loses its entitlement for the contract is free of ambiguities and to ensure that they have a
liquidated damages and the design-builder shall finish the work proper understanding of the contract provisions related to exten-
within a reasonable time (El-adaway et al. 2016). To this end, sion of time. In case of drafting a new contract, the checklist will
Bunni (2005) stated that failure by the architect to respond to aid such a drafting process. The new contract should contain pro-
the design-builder’s notice of claim for additional time within a visions that clearly answer those questions. The developed check-
specified period results in the loss of architect’s right to grant list is shown in Fig. 3. The provided questions in this checklist are
an extension of time; accordingly there is no date from which liqui- expected to act as a tool for assessing and enhancing contract
dated damages can be computed, thus no liquidated damages are administration for extension of time under design-build contracts.
recoverable (Bunni 2005). The same analysis is applied to AIA In addition, they provide associated parties with guideline for draft-
design-build contracts. ing contractual clauses related to extension of time under new
Also, as per Clause 63 of JCT, the owner would not have the design-build contracts.
right to deduct liquidated damages until all of the design-builder’s Based on initial feedback from various industry professionals
applications for extension of time have been decided (Fawzy and as well as considering documented cases for extension of time dis-
El-adaway 2012). As for NEC, if the project manager fails to notify putes under different design build contracts, the authors believe that
the design-builder of the decision within the duration stipulated in such checklist provides an easy to use systematic process to allow
Clause 61.4 and the design-builder provides notifications, it will be for more robust process for managing claims for extension of time.
considered as an acceptance of the compensation event or quotation
by the project manager after a 2-week period.
After thorough review of the studied forms of contract, the au- Conclusion
thors developed a comprehensive checklist that provides guidelines
to assist the design-builder in drafting and administering provisions Despite the comprehensiveness of the currently available standard
related to extension of time in design-build contracts. The checklist forms of design-build contracts, poor administration of contracts
lists 32 causes of delays and presents eight questions that, when remains one of the leading cause of conflicts, claims, and disputes
answered, facilitate better understanding of the prerequisites and in the construction industry. Studies have shown that proper con-
requirements for acquiring a time extension. The contract admin- tract administration is in fact one the most effective actions for
istrator should be able to answer all such questions to ensure that avoiding disputes. Because delays are becoming the norm rather

© ASCE 04519031-8 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031


Type of Delay If Excusable Compensable

Non-Excusable Non-Compensable

Compensation Includes Direct

Compensation Includes Direct

Compensation Includes Direct

Compensation Includes Direct

Compensation Includes Direct


Excusable Non-Compensable

Cost + Defined Overhead** +


Cost + Defined Overhead**

Cost + Overhead* + Profit*


Excusable Compensable

Cost + Overhead*

Defined Profit**
Cost Only
Causes of Delays

Other
Delay in the commencement of the work due to the Owner negligence (postponing site
1
possession)
2 Changes in the scope of the work (Change Order)
3 Labor disputes involving the Design-Builder
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

Labor Disputes not involving the Design-Builder (ones that impact the project but that
4
are not related to the project)
5 Unforeseen delay in deliveries of supplies
6 Unavoidable causalities beyond the Design-Builder’s control
Authorized delays from the owner due to disputes pursuant of the Design Build
7
Documents
8 Late approvals/testing by the Owner or the Engineer
9 Acts of omission by the Owner
10 Changes or decisions in the work ordered/changed by the Owner
11 Unpredictable changes in transportation
12 Adverse governmental actions
13 Safety accidents
14 Expected adverse weather conditions
15 Exceptionally adverse weather conditions
16 Hazardous material
17 Concealed and unknown conditions
18 Delay by owner pending disputes resolutions
19 Suspension by the owner
20 Acts of neglect by utility companies
21 Delays due to other contractors working for the Owner
22 Rightful suspension of the project by the contractor due to late payment by Owner
23 Low productivity due to shortage of funds caused by delayed payment by Owner
24 Impediment, prevention, or default by the Owner
25 Delay in permissions or approvals that the contractor has tried to avoid
26 Unexpected significant increase in material prices
27 Negligence by the Design-Builder
28 Fire
29 Floods
30 Terrorism
31 Epidemics
32 Acts of God
* Calculated by the Design-Builder at the time of the delay Excusable: gives the right to extension of time
** Percentage set in the contract Compensable: gives the right to additional compensation

1. In the table shown above, can you classify the 32 types of delays? (Delays are classified as Excusable Compensable, Excusable Non-Compensable, or Non-
Excusable Non-Compensable) Check the corresponding cells in the table.

2. For the compensable delays, what is the compensation exactly for each type of delay? Is it just the costs incurred by the design-builder or does it also
include overhead and profit? If overhead and profit are included, how are such amounts set? Use the table shown above to input the answer.

3. When should the design-builder inform the owner that the project will be delayed?

4. What is the procedure and timeline for contractor to request an extension of time?

5. After receiving the delay notice/claim from the design-builder, when should the owner reply with the decision?

6. Does the design-builder lose the right to claim for an extension of time after a certain period after the delaying event takes place?

7. Does the design-builder have the right to stop work or slow down work if the owner refuses to grant him an extension of time till the matter is
resolved?

8. What are dispute resolution procedure in case the design-builder is not satisfied with the owner’s decision relating to extension of time and/or
additional compensation?

Fig. 3. Checklist for administering extension of time under design-build contracts.

© ASCE 04519031-9 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031


than the exception in today’s complex construction world, delays Blake Dawson Waldron. 2006. Scope for improvement: A survey of pres-
cause a significant number of disputes. As such, the goal of this sure points in Australian construction and infrastructure projects.
paper was to present contract administration guidelines for appro- Rep. Prepared for the Australian Constructors Association. Sydney,
priate utilization and administration of the provisions related to ex- Australia: Blake Dawson Waldron.
tension of time under the most widely used standard design-build Bunni, N. G. 2005. The FIDIC forms of contract. West Sussex, UK:
Wiley-Blackwell.
contracts (i.e., AIA, ConsensusDOCS, EJCDC, JCT, NEC, and
Chappell, D. 2007. The JCT design and build contract 2005. 3rd ed.
FIDIC). To this effect, the authors reviewed and analyzed the pro-
London: Blackwell.
visions related to extension of time—as related to basis of enti- Cheung, S., and T. W. Yiu. 2006. “Are construction disputes inevitable?.”
tlement and claiming procedures—under the aforementioned six IEEE Trans. Eng. Manage. 53 (3): 456–470. https://doi.org/10.1109
contracts and provided an associated comparative analysis in a /TEM.2006.877445.
tabulated form. Ultimately, the authors developed a checklist that Colin, J., D. Langford, and P. Kennedy. 1996. “The relationship between
contains 32 causes of delays and eight questions to provide an easy construction procurement strategies and construction contract conflicts.”
to use systematic process to allow for more robust process for man- In Proc., CIB W92 Procurement Symp. London: E&FN Spon.
aging claims for extension of time. This checklist acts as a tool for ConsensusDocs. 2017. ConsensusDocs 410: Owner and design builder
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

assessing and enhancing contract administration for extension agreement. Arlington, VA: ConsensusDocs.
of time under design-build contracts. The checklist also provides Diekmann, J. E., M. J. Girard, and N. Abdul-Hadi. 1994. Dispute potential
associated parties with guidelines for drafting contractual clauses index: A study into the predictability of contract disputes. Boulder, CO:
related to extension of time under new design-build contracts. This Construction Industry Institute.
study is expected to promote efficient contract administration of Duggan, T., and D. Patel. 2013. Design-build project delivery market
share and market size report. Norwell, MA: Reed Construction
extension of time, thus minimizing conflicts, claims, and disputes
Data/RSMeans Market Intelligence.
as well as enabling associated parties to mitigate the related neg-
EJCDC (Engineers Joint Contract Documents Committee). 2016.
ative impacts on their projects. Standard general conditions of the contract between owner and
design/builder. EJCDC D700. Alexandria, VA: EJCDC.
El-adaway, I., S. Fawzy, M. Ahmed, and R. A. White. 2016. “Administering
Acknowledgments extension of time under national and international standard forms of con-
tracts: A contractor’s perspective.” J. Leg. Aff. Dispute Resolut. Eng. Constr.
The authors very much appreciate the constructive remarks and in- 8 (2): 0000182. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000182.
sights provided by the anonymous reviewers that helped hone and El-Hoteiby, A. I., O. A. Hosny, and A. F. Waly. 2017. “Particular conditions
strengthen the quality of this paper during the peer-review process. to cover potential risks of construction projects.” J. Leg. Aff. Dispute
Resolut. Eng. Constr. 9 (3): 05017002. https://doi.org/10.1061
/(ASCE)LA.1943-4170.0000223.
Fawzy, S. A., and I. H. El-adaway. 2012. “Contract administration
References guidelines for effectively and efficiently applying different delay
analysis techniques under World Bank–funded projects.” J. Leg. Aff.
Dispute Resolut. Eng. Constr. 5 (1): 35–44. https://doi.org/10.1061
List of Cases /(ASCE)LA.1943-4170.0000104.
Gymco Const. Co., Inc. v. Architectural Glass & Windows, Inc., 884 F.2d Fawzy, S. A., and I. H. El-adaway. 2013. “Time at large within the common
1362 (11th Cir. 1989). law legal system: Application to standard forms of contract.” J. Leg. Aff.
Higgins v. City of Fillmore, 639 P.2d 192 (Utah 1981). Dispute Resolut. Eng. Constr. 6 (1): 04513002. https://doi.org/10.1061
/(ASCE)LA.1943-4170.0000124.
FHWA (Federal Highway Administration). 2006. Design-build effective-
Works Cited ness study. Washington, DC: FHWA.
FIDIC (International Federation of Consulting Engineers). 2017a.
AACE (American Association of Clinical Endocrinologists). 2011. Foren- Construction contract. 2nd ed. Geneva: International Federation for
sic schedule analysis. AACE International Recommended Practice Consulting Engineers.
No. 29R-03. Morgantown, VA: AACE.
FIDIC (International Federation of Consulting Engineers). 2017b. Plant
Abdul-Malak, M. A., and S. Khalife. 2017. “Models for the administration
and design-build contract. 2nd ed. Geneva: FIDIC.
of structured construction contract notices.” J. Leg. Aff. Dispute Resolut.
Hale, D. R., P. P. Shrestha, G. E. Gibson, and G. C. Migliaccio. 2009.
Eng. Constr. 9 (3): 04517017. https://doi.org/10.1061/(ASCE)LA.1943
“Empirical comparison of design/build and design/bid/build project
-4170.0000228.
delivery methods.” J. Constr. Eng. Manage. 135 (7): 579–587. https://
Abotaleb, I., and I. El-adaway. 2017. “Administering employers’ payment
doi.org/10.1061/(ASCE)CO.1943-7862.0000017.
obligations under national and international design: Build standard forms
of contract.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 9 (2): 04517003. Harris, L. D., and B. M. Perlberg. 2009. “Advantages of the Consensus-
https://doi.org/10.1061/(ASCE)LA.1943-4170.0000213. DOCS construction contracts.” Constr. Law. 29 (1): 1–6.
AIA (American Institute of Architects). 2014. Owner design-builder con- JCT (Joint Contracts Tribunal). 2016. Design and build contract. London:
tract agreement. AIA A141. Washington, DC: AIA. JCT.
Arcadis. 2015. “Global construction disputes 2015: The higher stakes, the Kadry, M., H. Osman, and M. Georgy. 2016. “Causes of construction
bigger the risk.” Accessed January 22, 2018. https://www.arcadis.com delays in countries with high geopolitical risks.” J. Constr. Eng.
/en/global/our-perspectives/construction-disputes-rise-in-value-over-60 Manage. 143 (2): 04016095. https://doi.org/10.1061/(ASCE)CO.1943
-percent-to51million/. -7862.0001222.
Arcadis. 2016. “Global construction disputes 2016: Don’t get left behind.” Knowles, R. 2005. 150 contractual problems and their solutions. 2nd ed.
Accessed January 22, 2018. https://www.arcadis.com/media/3/E/7 London: Blackwell.
/%7B3E7BDCDC-0434-4237-924F-739240965A90%7DGlobal%20 Menesi, W. 2007. “Construction delay analysis under multiple baseline
Construction%20Disputes%20Report%202016.pdf. updates.” M.S. thesis, Dept. of Civil and Environmental Engineering,
Arcadis. 2017. “Global construction disputes 2017: Avoiding the same pit- Univ. of Waterloo.
falls.” Accessed January 22, 2018. https://www.arcadis.com/en/united Moore, S. D. 1998. “A comparison of project delivery systems on United
-states/our-perspectives/global-construction-disputes-report-avoiding-the States federal construction projects.” Rep. No. AFIT-98-048. Dayton,
-same-pitfalls/. OH: Air Force Institute of Technology, Wright-Patterson AFB.

© ASCE 04519031-10 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031


NEC (New Engineering Contract). 2013. Engineering and construction SCL (Society of Construction Law). 2018. “Delay and disruption protocol.”
contract. NEC 4. London: Institution of Civil Engineering. Accessed July 10, 2018. https://www.scl.org.uk/resources/delay
Pickavance, K. 2010. Delay and disruption in construction contracts. -disruption-protocol.
3rd ed. London: Sweet & Maxwell. Shrestha, P. P., J. T. O’Connor, and G. E. Gibson. 2012. “Performance
Riley, D. R., B. E. Diller, and D. Kerr. 2005. “Effects of delivery systems on comparison of large design-build and design-bid-build highway proj-
change order size and frequency in mechanical construction.” J. Constr. ects.” J. Constr. Eng. Manage. 138 (1): 1–13. https://doi.org/10.1061
Eng. Manage. 131 (9): 953–962. https://doi.org/10.1061/(ASCE)0733 /(ASCE)CO.1943-7862.0000390.
-9364(2005)131:9(953). Sykes, J. 1996. “Claims and disputes in construction.” Constr. Law J.
Rosner, J. W., A. E. Thal, and C. J. West. 2009. “Analysis of the design 12 (1): 3–13.
build delivery method in air force construction projects.” J. Constr. Eng. Thomas, S. R., C. L. Macken, T. H. Chung, and I. Kim. 2002. Measuring
Manage. 135 (8): 710–717. https://doi.org/10.1061/(ASCE)CO.1943 the impacts of the delivery system on project performance: Design-
-7862.0000029. build and design-bid-build. Gaithersburg, MD: NIST.
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.

© ASCE 04519031-11 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2020, 12(1): 04519031

You might also like