Professional Documents
Culture Documents
Understanding Extension of Time Under Different Standard Design-Build Forms of Contract
Understanding Extension of Time Under Different Standard Design-Build Forms of Contract
Understanding Extension of Time Under Different Standard Design-Build Forms of Contract
Abstract: Contractual provisions related to delay and extension of time are often written in difficult language or presented in a scattered
manner in construction contracts. This could lead to confusion and misunderstanding by the different parties as to rights and responsibilities.
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.
Thus, it is not surprising that poor contract administration is always listed among the top reasons for conflicts, claims, and disputes in the
construction industry. The goal of this paper is to present contract administration guidelines for appropriate utilization of the provisions
related to extension of time under the most widely used standard design-build contracts. This is particularly valuable bearing in mind
the complexity of addressing construction delays in general, as well as the growing popularity of design-build delivery methods in particular.
To address this goal, the authors (1) analyzed the provisions related to extension of time under standard design-build contracts published by a
range of professional bodies and institutions; (2) highlighted the differences and commonalities among the studied contracts in a comparative
analysis form; and (3) developed a checklist of causes and questions to provide an easy-to-use systematic process to allow for a more robust
process for managing claims for extension of time. The presented checklist acts as a tool for assessing and enhancing contract administration
for extension of time under design-build contracts. The checklist also provides associated parties with guidelines for drafting contractual
clauses related to extension of time under new design-build contracts. This study is expected to promote effective and efficient contract
administration of requests for extension of time, thus minimizing conflicts, claims, and disputes as well as enabling associated parties
to mitigate the related time and cost negative impacts on their projects. DOI: 10.1061/(ASCE)LA.1943-4170.0000331. © 2019 American
Society of Civil Engineers.
tract was issued. The forms were not referred to as JCT until 1977.
JCT members revised the latest edition of their design-build con- of the contracts, which set a certain time frame for the design-
tract in 2016. As such, the JCT 2016 edition is the subject of this builder to submit the notice after the delaying event takes place,
paper (JCT 2016). this contract does not set this period numerically. Instead, it says
Under JCT 2016, the design-builder is entitled to time extension “as soon as possible.” This ambiguity could be risky because the
if the delays are defined as a relevant event per the contract docu- definition of “soon” may be conceived differently by the different
ments and if that event will indeed cause a delay to the completion parties. The notice shall include the causes of the delays and state
to any section or the entirety of the project. The concept of relevant which delay falls under relevant events. Once the design-builder
events is first mentioned under Clauses 2-23 to 2-26. These clauses has submitted a claim for a time extension, they shall submit
inform the design-builder of which events are considered relevant the effect the delay has on the project and an estimate of the time
events per their contract agreement and how they should report the needed to adjust to delay as soon as possible. Once the claim for a
associated delays. Clause 2-26 lists the relevant events that will delay has been submitted, the owner will investigate that the sub-
allow for time extension by the design-builder. The JCT contract mitted information is appropriate to being a relevant event and that
provides corresponding clauses that have additional information it will cause the project to extend beyond its original completion
to help clarify what is considered relevant events, and these are de- date. If both of these requirements are justified, then the owner
tailed in the following paragraphs. will give a time extension based on fair and reasonable estimates
Instructions from the owner are covered under Clauses 2-13, per Clause 2-25. Also, under Clause 2-25, the owner has to respond
3-10, 3-12, and 3-13-3. Clause 2-13 gives the design-builder enti- to the design-builder as soon as reasonably possible but no longer
tlement to a time extension if they notices any discrepancies in the than 12 weeks from the time the design-builder submitted the sup-
owner’s requirements, design-builders’ proposal, instruction issued porting documents. If the decision is not agreed upon by both par-
by the owner, or with the drawings and documents requested by the ties, then the claim will become a dispute that will be handled by
owner. Any of these discrepancies can affect either the design mediation, adjudication, or arbitration as per Clause 9.
and/or construction of the project and need to be clarified before
work continues. Clauses 3-12 and 3-13 allow the design-builder to
receive a time extension if the owner requires that the design- Extension of Time under the NEC Design-Build
Contract
builder uncovers the work for further tests and inspections. If the
tests and inspections prove to be of satisfaction to the owner, then The Institution of Civil Engineers, based in the United Kingdom,
the design-builder is entitled to time that will compensate for the created and published the New Engineering Contract (NEC 2013),
time required to uncover, test, and recover. which is a suite of standard form of construction contracts. Exten-
Clause 3-15 applies to any antiquities or fossils that are uncov- sion of time under the NEC was covered before by El-adaway et al.
ered or discovered during any operation of the construction project. (2016) for design-bid-build projects but because the same contract
This requires the design-builder to stop construction works and in- is still applicable to design-build, there will be significant unavoid-
form the owner of what is found. The owner then investigates the able similarities in the forthcoming discussions.
site and determines how they want to handle the preservation of the There are several events under the NEC under which the
artifacts. This may even require that the design-builder works with design-builder is entitled to compensation, extension of time, or
a third party under the direction of the owner. Accordingly, a time both. Clause 60.1 addresses the compensation events and includes
extension will be allowed. the following:
Under Clause 4-11, the design-builder is allowed a time exten- 1. The project manager releases an instruction to change the work
sion if they are to suspend the work in case the owner does not pay information, except in the following cases:
as per the contract. The design-builder has to submit their intention • a change to accept a defect, or
to suspend work 7 days in advance with proper justification. • a change provided by the design-builder in its design, made
The owner and design-builder must then reach an agreement on at its request, or to comply with other work information
an adequate time to allow for the project to be completed once provided by the owner.
the design-builder resumes work. Another relevant event that is fur- 2. The owner does not allow the design-builder access to the site
ther defined is the issue of specified perils. The following specified or part of it by later than the agreed access date shown in the
perils, also referred to as force majeure events, are listed under accepted program.
Section 6 of the JCT design-build contract: 3. The owner fails to provide something as agreed and in accor-
• fire, dance with the accepted program.
• lightning, 4. The project manager gives instructions to stop or change a
• explosion, key date.
• storm, 5. The owner or the other parties
• 16.1: design-builder’s entitlement to suspend work, contracts has its own set of conditions to initiate a claim for exten-
• 17.4: owner’s risk, and sion of time. The matter of properly understanding the provisions
• 19.4: force majeure. of the contract with respect to extensions of time is of significant
The procedure for extension of time is similar to that of addi- importance, especially in relation to the provided time limits for
tional payment. It is covered in Subclause 20.1 and is shown in both the design-builder as well as the engineer/architect/project
Fig. 1. Procedures for continuing delay are covered in Subclause manager. Because this paper is not only dealing with US contracts,
20.1 and are shown in Fig. 2. Failure of the design-builder to send but also incorporates other international contracts, some of the dis-
notice of claim within 28 days will result in nonextension of the cussion might not be always pertinent or supported by US courts.
time for completion. A proper notice is a condition precedent to As such, parties should always resort to professional legal advice to
entitlement to extension of time. Also, the design-builder is respon- avoid any ambiguity or confusion.
sible for submitting interim claims at monthly intervals with the As far as the design-builder is concerned, Knowles (2005) stated
accumulated delays and/or the amount claimed. They are also re- that in case of a design-builder’s failure to follow notice and claim
quired to send a final claim within 28 days of the end of the delaying provisions, “this will not result in the loss of rights to an extension
event. In case of the design-builder’s failure to follow the proce- of time unless the conditions of the contract expressly state that the
dures and provide details of the claim for extension of time in re- service of a notice is a condition precedent to such rights.” Also,
lation to any claim, any extension of time and/or additional payment Chappell (2007) stated that giving of the notice is not a precondi-
tion to the award of an extension of time unless the contract ex-
shall take account of the extent, if any, to which the failure has pre-
pressly states so. Along the same token, if the design-builder does
vented or prejudiced proper investigation of the claim. After receipt
not provide a condition precedent delay notice, this failure may
of a claim, the engineer has 42 days to approve or disapprove claim
simply result in waiver or forfeiture of a claim (El-adaway et al.
and must provide detailed comments with the response.
2016). Accordingly, if the design-builder fails to serve a proper
If any of the parties is unsatisfied with the engineer’s decision,
delay notice, this would not result in the loss of rights to an
they should first attempt amicable settlement. According to the pro-
extension of time under design-build contracts developed by AIA,
cedure in Clause 20, they can refer the matter to the dispute adju-
ConsensusDocs, and JCT because the time limits mentioned
dication board, followed by arbitration. As far as time is concerned,
therein are not time-barring. However, design-build contracts of
Subclause 8.4 requires all project parties to advise each other in EJCDC, NEC, and FIDIC provide time limits that are conditions
precedent for recovering the claimed right. EJCDC states under
Article 10.05.F that “no claim for an adjustment in contract price
or contract times will be valid if not submitted in accordance with
this paragraph 10.05.” NEC also considers failure by the design-
builder to comply with the contractual time period (8 weeks) in
submitting a notification of the compensation event to the project
manager as time-barring. The latter will therefore leave the design-
builder with no entitlement for extension of time unless they had
Fig. 1. Extension of time under the FIDIC (2017b) Yellow Book.
already been notified by the project manager. Finally, Subclause
20.1 of the FIDIC Yellow Book states.
If the Contractor fails to give notice of a claim within such
a period of 28 days, Completion shall not be extended, the
Contractor shall not be entitled to additional payment, and
the Employer shall be discharged from all liability in connec-
tion with the Claim.
On the other hand, and as far as the engineer/architect/project
manager is concerned, the contracts under investigation deal differ-
ently with this matter. For example, according to 10.05.D of
EJCDC, if the engineer failed to take action on a claim with the
aforementioned timescale of 30 days, the claim will be deemed de-
nied. However, under the FIDIC Yellow Book, if the engineer fails
Fig. 2. Extension of time for events having continuing effects under
to determine extensions of time in accordance with the provisions
FIDIC (2017b) Yellow Book.
of the contract and if the design-builder is entitled to extension of
time and can prove that right, the owner loses its entitlement for the contract is free of ambiguities and to ensure that they have a
liquidated damages and the design-builder shall finish the work proper understanding of the contract provisions related to exten-
within a reasonable time (El-adaway et al. 2016). To this end, sion of time. In case of drafting a new contract, the checklist will
Bunni (2005) stated that failure by the architect to respond to aid such a drafting process. The new contract should contain pro-
the design-builder’s notice of claim for additional time within a visions that clearly answer those questions. The developed check-
specified period results in the loss of architect’s right to grant list is shown in Fig. 3. The provided questions in this checklist are
an extension of time; accordingly there is no date from which liqui- expected to act as a tool for assessing and enhancing contract
dated damages can be computed, thus no liquidated damages are administration for extension of time under design-build contracts.
recoverable (Bunni 2005). The same analysis is applied to AIA In addition, they provide associated parties with guideline for draft-
design-build contracts. ing contractual clauses related to extension of time under new
Also, as per Clause 63 of JCT, the owner would not have the design-build contracts.
right to deduct liquidated damages until all of the design-builder’s Based on initial feedback from various industry professionals
applications for extension of time have been decided (Fawzy and as well as considering documented cases for extension of time dis-
El-adaway 2012). As for NEC, if the project manager fails to notify putes under different design build contracts, the authors believe that
the design-builder of the decision within the duration stipulated in such checklist provides an easy to use systematic process to allow
Clause 61.4 and the design-builder provides notifications, it will be for more robust process for managing claims for extension of time.
considered as an acceptance of the compensation event or quotation
by the project manager after a 2-week period.
After thorough review of the studied forms of contract, the au- Conclusion
thors developed a comprehensive checklist that provides guidelines
to assist the design-builder in drafting and administering provisions Despite the comprehensiveness of the currently available standard
related to extension of time in design-build contracts. The checklist forms of design-build contracts, poor administration of contracts
lists 32 causes of delays and presents eight questions that, when remains one of the leading cause of conflicts, claims, and disputes
answered, facilitate better understanding of the prerequisites and in the construction industry. Studies have shown that proper con-
requirements for acquiring a time extension. The contract admin- tract administration is in fact one the most effective actions for
istrator should be able to answer all such questions to ensure that avoiding disputes. Because delays are becoming the norm rather
Non-Excusable Non-Compensable
Cost + Overhead*
Defined Profit**
Cost Only
Causes of Delays
Other
Delay in the commencement of the work due to the Owner negligence (postponing site
1
possession)
2 Changes in the scope of the work (Change Order)
3 Labor disputes involving the Design-Builder
Downloaded from ascelibrary.org by SUNY at Stony Brook on 10/01/19. Copyright ASCE. For personal use only; all rights reserved.
Labor Disputes not involving the Design-Builder (ones that impact the project but that
4
are not related to the project)
5 Unforeseen delay in deliveries of supplies
6 Unavoidable causalities beyond the Design-Builder’s control
Authorized delays from the owner due to disputes pursuant of the Design Build
7
Documents
8 Late approvals/testing by the Owner or the Engineer
9 Acts of omission by the Owner
10 Changes or decisions in the work ordered/changed by the Owner
11 Unpredictable changes in transportation
12 Adverse governmental actions
13 Safety accidents
14 Expected adverse weather conditions
15 Exceptionally adverse weather conditions
16 Hazardous material
17 Concealed and unknown conditions
18 Delay by owner pending disputes resolutions
19 Suspension by the owner
20 Acts of neglect by utility companies
21 Delays due to other contractors working for the Owner
22 Rightful suspension of the project by the contractor due to late payment by Owner
23 Low productivity due to shortage of funds caused by delayed payment by Owner
24 Impediment, prevention, or default by the Owner
25 Delay in permissions or approvals that the contractor has tried to avoid
26 Unexpected significant increase in material prices
27 Negligence by the Design-Builder
28 Fire
29 Floods
30 Terrorism
31 Epidemics
32 Acts of God
* Calculated by the Design-Builder at the time of the delay Excusable: gives the right to extension of time
** Percentage set in the contract Compensable: gives the right to additional compensation
1. In the table shown above, can you classify the 32 types of delays? (Delays are classified as Excusable Compensable, Excusable Non-Compensable, or Non-
Excusable Non-Compensable) Check the corresponding cells in the table.
2. For the compensable delays, what is the compensation exactly for each type of delay? Is it just the costs incurred by the design-builder or does it also
include overhead and profit? If overhead and profit are included, how are such amounts set? Use the table shown above to input the answer.
3. When should the design-builder inform the owner that the project will be delayed?
4. What is the procedure and timeline for contractor to request an extension of time?
5. After receiving the delay notice/claim from the design-builder, when should the owner reply with the decision?
6. Does the design-builder lose the right to claim for an extension of time after a certain period after the delaying event takes place?
7. Does the design-builder have the right to stop work or slow down work if the owner refuses to grant him an extension of time till the matter is
resolved?
8. What are dispute resolution procedure in case the design-builder is not satisfied with the owner’s decision relating to extension of time and/or
additional compensation?
assessing and enhancing contract administration for extension agreement. Arlington, VA: ConsensusDocs.
of time under design-build contracts. The checklist also provides Diekmann, J. E., M. J. Girard, and N. Abdul-Hadi. 1994. Dispute potential
associated parties with guidelines for drafting contractual clauses index: A study into the predictability of contract disputes. Boulder, CO:
related to extension of time under new design-build contracts. This Construction Industry Institute.
study is expected to promote efficient contract administration of Duggan, T., and D. Patel. 2013. Design-build project delivery market
share and market size report. Norwell, MA: Reed Construction
extension of time, thus minimizing conflicts, claims, and disputes
Data/RSMeans Market Intelligence.
as well as enabling associated parties to mitigate the related neg-
EJCDC (Engineers Joint Contract Documents Committee). 2016.
ative impacts on their projects. Standard general conditions of the contract between owner and
design/builder. EJCDC D700. Alexandria, VA: EJCDC.
El-adaway, I., S. Fawzy, M. Ahmed, and R. A. White. 2016. “Administering
Acknowledgments extension of time under national and international standard forms of con-
tracts: A contractor’s perspective.” J. Leg. Aff. Dispute Resolut. Eng. Constr.
The authors very much appreciate the constructive remarks and in- 8 (2): 0000182. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000182.
sights provided by the anonymous reviewers that helped hone and El-Hoteiby, A. I., O. A. Hosny, and A. F. Waly. 2017. “Particular conditions
strengthen the quality of this paper during the peer-review process. to cover potential risks of construction projects.” J. Leg. Aff. Dispute
Resolut. Eng. Constr. 9 (3): 05017002. https://doi.org/10.1061
/(ASCE)LA.1943-4170.0000223.
Fawzy, S. A., and I. H. El-adaway. 2012. “Contract administration
References guidelines for effectively and efficiently applying different delay
analysis techniques under World Bank–funded projects.” J. Leg. Aff.
Dispute Resolut. Eng. Constr. 5 (1): 35–44. https://doi.org/10.1061
List of Cases /(ASCE)LA.1943-4170.0000104.
Gymco Const. Co., Inc. v. Architectural Glass & Windows, Inc., 884 F.2d Fawzy, S. A., and I. H. El-adaway. 2013. “Time at large within the common
1362 (11th Cir. 1989). law legal system: Application to standard forms of contract.” J. Leg. Aff.
Higgins v. City of Fillmore, 639 P.2d 192 (Utah 1981). Dispute Resolut. Eng. Constr. 6 (1): 04513002. https://doi.org/10.1061
/(ASCE)LA.1943-4170.0000124.
FHWA (Federal Highway Administration). 2006. Design-build effective-
Works Cited ness study. Washington, DC: FHWA.
FIDIC (International Federation of Consulting Engineers). 2017a.
AACE (American Association of Clinical Endocrinologists). 2011. Foren- Construction contract. 2nd ed. Geneva: International Federation for
sic schedule analysis. AACE International Recommended Practice Consulting Engineers.
No. 29R-03. Morgantown, VA: AACE.
FIDIC (International Federation of Consulting Engineers). 2017b. Plant
Abdul-Malak, M. A., and S. Khalife. 2017. “Models for the administration
and design-build contract. 2nd ed. Geneva: FIDIC.
of structured construction contract notices.” J. Leg. Aff. Dispute Resolut.
Hale, D. R., P. P. Shrestha, G. E. Gibson, and G. C. Migliaccio. 2009.
Eng. Constr. 9 (3): 04517017. https://doi.org/10.1061/(ASCE)LA.1943
“Empirical comparison of design/build and design/bid/build project
-4170.0000228.
delivery methods.” J. Constr. Eng. Manage. 135 (7): 579–587. https://
Abotaleb, I., and I. El-adaway. 2017. “Administering employers’ payment
doi.org/10.1061/(ASCE)CO.1943-7862.0000017.
obligations under national and international design: Build standard forms
of contract.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 9 (2): 04517003. Harris, L. D., and B. M. Perlberg. 2009. “Advantages of the Consensus-
https://doi.org/10.1061/(ASCE)LA.1943-4170.0000213. DOCS construction contracts.” Constr. Law. 29 (1): 1–6.
AIA (American Institute of Architects). 2014. Owner design-builder con- JCT (Joint Contracts Tribunal). 2016. Design and build contract. London:
tract agreement. AIA A141. Washington, DC: AIA. JCT.
Arcadis. 2015. “Global construction disputes 2015: The higher stakes, the Kadry, M., H. Osman, and M. Georgy. 2016. “Causes of construction
bigger the risk.” Accessed January 22, 2018. https://www.arcadis.com delays in countries with high geopolitical risks.” J. Constr. Eng.
/en/global/our-perspectives/construction-disputes-rise-in-value-over-60 Manage. 143 (2): 04016095. https://doi.org/10.1061/(ASCE)CO.1943
-percent-to51million/. -7862.0001222.
Arcadis. 2016. “Global construction disputes 2016: Don’t get left behind.” Knowles, R. 2005. 150 contractual problems and their solutions. 2nd ed.
Accessed January 22, 2018. https://www.arcadis.com/media/3/E/7 London: Blackwell.
/%7B3E7BDCDC-0434-4237-924F-739240965A90%7DGlobal%20 Menesi, W. 2007. “Construction delay analysis under multiple baseline
Construction%20Disputes%20Report%202016.pdf. updates.” M.S. thesis, Dept. of Civil and Environmental Engineering,
Arcadis. 2017. “Global construction disputes 2017: Avoiding the same pit- Univ. of Waterloo.
falls.” Accessed January 22, 2018. https://www.arcadis.com/en/united Moore, S. D. 1998. “A comparison of project delivery systems on United
-states/our-perspectives/global-construction-disputes-report-avoiding-the States federal construction projects.” Rep. No. AFIT-98-048. Dayton,
-same-pitfalls/. OH: Air Force Institute of Technology, Wright-Patterson AFB.