Professional Documents
Culture Documents
Considerations For Filing Global Construction Claims Legal Perspective
Considerations For Filing Global Construction Claims Legal Perspective
Abstract: Delays and disruptions that frequently lead to cost overruns on, and late completion of, construction projects are often accom-
panied by claims for time extensions and/or additional compensations by construction contractors. To this effect, contractors’ claims can
become complex to an extent where it is difficult to relate losses incurred to individual events or causes and thereby establish grounds
for putting forward global claims. The foundation of this category of claims is that multiple claim-causing events, for which the owner
is responsible, have composite implications that render the determination of explicit individual cause-effect relations impossible or imprac-
ticable. As such, the aim of the work presented in this paper is to identify and synthesize the conditions that have contributed to making global
construction claims more admissible and potentially successful or that have hindered their success. The adopted research methodology
included (1) reviewing the literature regarding the main principles underlying global claims, (2) deducing the success and failure criteria
for such claims through a case law review of 26 industry-reported cases spanning the last five decades, (3) developing a construct synthesizing
the identified success and failure criteria and their interactions, and (4) pinpointing emergent trends that seem to be moderating the legal
admissibility and success requirements of these claims. The findings revealed six criteria that can be viewed as contributing to the success of
such claims, three of which mirror those found to be the basis for their failure. The emergent relaxation of requirements was found to be in
relation to three of the identified success criteria, pertaining to (1) the contractor not unreasonably delaying the claim, (2) impracticability
or impossibility to particularize, and (3) lack of the contractor’s responsibility for the added costs. DOI: 10.1061/(ASCE)LA.1943-
4170.0000393. © 2020 American Society of Civil Engineers.
Introduction increased project costs, are considered one of the most destructive
relationship killers in construction contracting (Yiu and Cheung
The construction industry has been tainted with dispute occurrence 2004; Cheung and Pang 2012). When such disputes are not suitably
between project participants, leading nowadays to various dispute resolved, they may intensify and eventually get litigated, a process
resolution strategies and mechanisms (Gebken and Gibson 2006; that can be tremendously expensive for the parties concerned
Rajendran et al. 2013; Orgut et al. 2018). Construction projects (Cheung et al. 2004).
are exposed to enormous uncertainties and the contract is inevitably The American Institute of Architects (AIA), as cited by Levin
incomplete in terms of including all the requirements needed to (1998), defined a claim as “a demand or assertion by one of the
tackle the various contingencies (Yiu and Cheung 2004). As such, contracting parties seeking, as a matter of right, adjustment or in-
shared efforts are looked for in such circumstances to resolve the terpretation of the contract terms, payment of money, extension of
complications that may arise during the course of work execution. time, or other relief with respect to the terms of a contract” (p. 35).
However, unsettled problems or conflicts, subsequently developing On the other hand, a dispute in construction projects arises when a
into disputes and causing disruptions to construction schedules and claim, submitted by a stakeholder (e.g., the contractor or subcontrac-
tor), has been opposed, prohibited, or disallowed by another stake-
1
Ph.D. Graduate, Dept. of Civil and Environmental Engineering, holder (e.g., the project owner) (Mehany et al. 2018). Since disputes
Maroun Semaan Faculty of Engineering and Architecture, American Univ. emerge after claims are discredited, it is reasonable that the causes of
of Beirut, Beirut 1107 2020, Lebanon. Email: fsd01@mail.aub.edu disputes are analogous to those of claims (Mehany et al. 2018). To
2
Formerly, Ph.D. Student, Dept. of Civil and Environmental Engineer- this end, the probability of claim and dispute occurrence ranges from
ing, Maroun Semaan Faculty of Engineering and Architecture, American 10% to 30% in the construction industry, and the average yearly
Univ. of Beirut, Beirut 1107 2020, Lebanon. ORCID: https://orcid.org amounts paid to settle these claims and disputes vary from $4 to
/0000-0003-1907-4547. Email: sgk19@mail.aub.edu
3 $12 billion or more (Gebken and Gibson 2006; McGeorge et al.
Professor of Construction Engineering and Management, Dept. of
Civil and Environmental Engineering, Maroun Semaan Faculty of Engi- 2007). Accordingly, disputes are nowadays considered endemic
neering and Architecture, American Univ. of Beirut, Beirut 1107 2020, in the construction industry due to the poor resolution of claims
Lebanon (corresponding author). ORCID: https://orcid.org/0000-0003 in the course of work execution, which justifies the exertion of ef-
-3382-2257. Email: mamalak@aub.edu.lb forts by both parties to the construction contract that can be geared
4
Associate Professor, Dept. of Civil and Environmental Engineering, toward diminishing the occurrence of claims (Ren et al. 2001).
Hole School of Construction Engineering, Univ. of Alberta, Edmonton, For a loss and/or expense claim to be successful, the contractor
AB, Canada T6G 2R3. ORCID: https://orcid.org/0000-0002-3986-9534. usually declares and proves three main issues: (1) one or more
Email: hamzeh@ualberta.ca events for which the defendant is accountable, (2) loss and expense
Note. This manuscript was submitted on September 16, 2019; approved
on October 30, 2019; published online on March 17, 2020. Discussion per-
experienced by the claimant, and (3) a causal relationship between
iod open until August 17, 2020; separate discussions must be submitted for the event(s) and their associated loss and expense [John Doyle
individual papers. This paper is part of the Journal of Legal Affairs and Construction Limited v. Laing Management (Scotland) Limited
Dispute Resolution in Engineering and Construction, © ASCE, ISSN (2004)]. Nevertheless, contractors’ claims are sometimes tremen-
1943-4162. dously complex, making it tough or intolerable to attribute every
events/matters relied upon and the alleged loss and damage or delay is claimed which is the difference between the total actual cost and
that relief is claimed for.” In the Australian context, and more par- the contract price : : : ” (paragraph 6.28). On the other hand,
ticularly in Holland Construction & Engineering Pty Ltd. v. “composite claim” and “rolled-up claim” are described as “claims
Kvaerner RJ Brown Pty Ltd., Byrne J. defined the global claim where there are a number of events and only some are presented as
as follows: “The claim as pleaded : : : is a global claim, that is, a group in a global claim.” It is further clarified that “in this type of
the claimant does not seek to attribute any specific loss to a specific claim, separate sums are claimed for particular events and a single
breach of contract, but is content to allege a composite loss as a result sum is claimed for the remaining group of events that are not so
of all the breaches alleged, or presumably as a result of such particularised.”
breaches as are ultimately proved.” Likewise, in the commentary
on Wharf Properties v. Eric Cumine Associates, the editors define
global claims as “ones where the connections between the matters Pivotal Changes Introduced by the 2017 SCL Delay
complained of and their consequences, whether in terms of time or and Disruption Protocol
money, are not fully spelled out.” All these definitions focus on one
important aspect in global claims: the nexus between the events and The SCL Delay and Disruption Protocol (SCL 2002) (hereafter
the alleged entitlements, where the core issue lies in proving this protocol) discourages parties from using global claims. It states,
impracticable connection. “In what should only be rare cases where the financial consequen-
Some terms are frequently used together—or interchangeably— ces of the various causes of compensation are impossible to distin-
with global claims, such as “composite claims,” “rolled-up claims,” guish, so that an accurate apportionment of the compensation
and “total cost claims.” Although these expressions may be claimed cannot be made between the several causative events, then
used interchangeably with “global claim,” some authors do distin- in this rare situation it is acceptable to quantify individually those
guish them from one another. For instance, Atkinson (2007) differ- items of the claim which can be dealt with in isolation and claim
entiates between “total cost,” “composite,” and “rolled-up” claims. compensation for the remainder as a composite whole” (p. 27). This
The term “total cost claim” is said to be “a claim where a single sum edition of the protocol (2002) takes a tremendously strict approach
regarding global claims, stricter possibly than the courts have ever As with many areas of the common law, the law related to global
taken. In this regard, it asserts that “the not uncommon practice of claims has advanced through a number of cases, each of which has
contractors making composite or global claims without substanti- required the court to find an impartial and reasonable equilibrium
ating cause and effect is discouraged by the Protocol and rarely between the practical difficulties regularly confronted by a wronged
accepted by the Courts.” It recommends, in fact, that if accurate claimant and the unquestionable right of a defendant to appropri-
and adequate records are kept, the contractor can establish the ately recognize the case made against him [John Holland Construc-
causal link between the employer’s risk event and the subsequent tion & Engineering Pty Ltd v. Kvaerner RJ Bown Pty Ltd (1996);
loss and/or expense incurred without the need to file for a global also, Wharf Properties v. Eric Cumine Associates (1991)]. Accord-
claim, and that the failure to keep such records does not defend the ingly, this section of the research work does not aim to offer a
contractor in submitting a global claim. historical scrutiny of the advancement of the law on global claims.
However, there is now a more lenient approach in courts toward Rather, it strives to provide a study of important cases encoun-
global claims. The introduced changes in the protocol mirror this tered mainly under the common law legal systems of the United
gradual cultural shift. Accordingly, the second edition of the pro- Kingdom, Australia and other Commonwealth countries, and the
tocol (2017) has tackled, among other issues, developments in case United States. A total of 26 cases were adopted for the analysis,
law related to global claims. It thus states, “Some of the key following a systematic search effort that yielded two primary sets
changes introduced by the 2nd edition are as follows: : : : .(e) There of 13 and 11 cases in which the global claim is found to have either
is recognition of an apparent trend for the construction legal indus- succeeded or failed, respectively. The remaining two cases re-
try and the courts to take a more lenient approach towards global present a main shift in legal analyses of global claims, which can
claims, albeit the risks of proceeding on this basis remain.” The be regarded as reflecting a more tolerant view of contractors pursu-
protocol also states that the contractor must be conscious that there ing such claims. A number of search engines were relied upon in
is a risk that a global claim will not succeed at trial if any substantial this regard, including Google Scholar, BAILII, FindLaw, Fenwick
contribution to the causality of the global damage can be proven to Elliot, and the like. The search resulted in filtering a total number of
have been made by an event for which the employer has no 26 related cases, arranged according to their year of decision, as
accountability and it is not practicable for the contract administra- shown in Fig. 2. Accordingly, the adopted cases were thoroughly
tor, adjudicator, judge or arbitrator to weigh the value of that non- examined, and key statements made in support of the courts’ rul-
recoverable portion on the existing evidence (SCL 2017). ings were properly scrutinized and filtered, thereby highlighting the
core reasoning behind the decisions given by the concerned courts.
Criteria for Success/Failure: Legal Perspective Criteria Pertaining to the Success of Global Claims
Having established that a more lenient approach has been taking This section presents research findings concerned with the identi-
place toward global claims by courts of law, this section exam- fication of essential criteria contributing to the success of global
ines, from a legal perspective, the criteria that can contribute to claims. Based on the in-depth review of the filtered 13 cases sum-
improving the chances of success with submitted global claims or marized in Table 1, the frequencies associated with the reported
lead to their failure. Global claims can be categorized, depending success criteria (SCs) were of main interest. To this end, a thorough
on the award (i.e., time or money) that the contractor asks for, review and inspection of all encountered criteria allowed their clas-
into two main types: “total cost or loss and expense” and “delay sification into general headings that offer a clearer representation of
and disruption.” In the loss and expense claim, it is alleged that what is reported to be critical to the success of global claims. Table 2
numerous variations that cannot be disentangled are deemed to lists the six generated headings along with their corresponding
have contributed to the project’s global cost overrun. The basic frequencies.
claim will then be the difference between the contractor’s actual The listed headings are presented in decreasing order of occur-
costs incurred and the contract price, thus looking for a “cash- rence frequency. The adopted heading “Impracticable or impossible
neutral” position. In the global delay claim, it is assumed that the to particularize (i.e., establish the causal nexus between each event
project total delay is attributable to several instructions, varia- and the attributed loss),” SC1, was found to have the highest cita-
tions, interferences, and disruptions that are claimed to be inter- tion frequency of 11, thus confirming the exceptional implication of
fering with the work and so entitle the contractor to an extension satisfying this criterion if with global claims are to be successful.
of time and/or extra payment. Once more, there is no connection SC1 is a vital condition or prerequisite for a contractor to demon-
between the individual alleged events and their contributions to strate that it is impossible or impractical to disentangle the part
the total delay. of the loss attributable to each head of claim in order to succeed
© ASCE
C1 J. Crosby & Sons Ltd. “The result in terms of delay and disorganization, of each of the matters referred to : : : was a continuing one. As each matter occurred its consequences were
v. Portland Urban & District added to the cumulative consequences of the matters which had preceded it. The delay and disorganization which ultimately resulted was cumulative and
Council (1967) attributable to the combined effect of all these matters. It is therefore impracticable, if not impossible, to assess the additional expense caused by delay and
disorganization due to any one of these matters in isolation from the other matters. : : : I can see no reason why [the arbitrator] should not recognize the
realities of the situation and make individual awards in respect of those parts of individual items of claim which can be dealt with in isolation and a
supplementary award in respect of the remainder of these claims as a composite whole.”
C2 London Borough of Merton “ : : : that a rolled-up award can only be made in a case where the loss or expense attributable to each head of claim cannot in reality be separated and secondly
v. Stanley Hugh Leach (1985) that a rolled-up award can only be made where apart from that practical impossibility the conditions which have to be satisfied before an award can be made
have been satisfied in relation to each head of claim. : : : If application is made : : : for reimbursement of direct loss and expense attributable to more than one
head of claim and at the time when the loss or expense comes to be ascertained, it is impractical to disentangle or disintegrate the part directly attributable to
each head of claim then, provided of course that the contractor has not unreasonably delayed in making the claim and so has himself created the
difficulty, the architect must ascertain the global loss attributable to the two causes : : : ”
C3 Mid Glamorgan County “ : : : Where however a claim is made for extra costs incurred through a delay as a result of various events whose consequences have a complex interaction that
Council v. J Devonald Williams renders specific relation between event and time/money consequence impossible or impracticable, it is permissible to maintain a composite claim.”
(1991)
C4 Servidone Construction “ : : : presented evidence under the total cost method. Servidone, 19 Cl.Ct. at 384. Under this method, the contractor must show: (1) the impracticability of
Corporation v. the United proving actual losses directly; (2) the reasonableness of its bid; (3) the reasonableness of its actual costs; and (4) lack of responsibility for the added costs.”
States (1991)
C5 Matthew Hall v. Nauru “Matthew Hall : : : is not obliged to give particulars of “nexus” when it is not part of its case to establish a nexus between each alleged disrupting event,
Phosphate Royalties (1992) particular disruptions and loss.”
C6 Imperial Chemical Industries “The objectives sought to be achieved by the Court in orders made relating to Scott Schedules are to ensure that when the action is entered for trial: each
plc v. Bovis Construction Ltd. individual item claimed is particularised : : : the amount asserted by both parties : : : the contentions of each parties [sic] : : : areas of agreement relating
(1992) to the description of the item and quantum : : : the aggregate of the claims and areas of admissions of each party are known.”
C7 GMTC Tools & Equipment Ltd “I have come to the clear conclusion that the plaintiff should be permitted to formulate their claims for damages as they wish, and not to be forced into a
v. Yuasa Warwick Machinery straitjacket of the judge’s or their opponent’s choosing. The fundamental concern of the court is that the dispute between the parties should be determined
05020003-5
Ltd (1994) expeditiously and economically and, above all, fairly, and while a plaintiff is entitled to present its claim as it thinks fit, on the other hand a defendant is entitled to
know the case which it has to meet with as much certainty and particularity as is reasonable, having regard to the circumstances and to the nature of the acts
themselves by which the damage is done.”
C8 British Airways Pension “The basic purpose of pleadings is to enable the opposing party to know what case is being made in sufficient detail to enable that party properly to prepare to
Trustees v. Sir Robert McAlpine answer it. : : : This is again not a case in which it could be said that the plaintiff’s claims were fundamentally flawed, in the sense that no further particulars
& Sons Ltd. (1994) could assist their cause, nor a case where (as in Wharf Properties v. Eric Cumine) there had been an express refusal to provide further particulars or a
contumelious disregard of court orders : : : the default of the plaintiffs, serious though it was, fell far short of calling for the draconian remedy of striking
them out.”
C9 Inserco Ltd v. Honeywell “Inserco pleaded case provided sufficient agenda for the trial and the issues for the trial and the issues are about quantification. : : : There is here as in Crosby an
“It will be apparent that I have rejected the pursuers’ argument that, if prolongation costs are caused both by an employer delay and by a concurrent
seems to be based on a rigidly logical application of the principles of causation as they apply in the general law of contract and delict. Under clause 26, however, as
contractor delay, the contractor will not be entitled to recover such costs if he would have incurred them as a result of the contractor delay. That approach
with a global claim. As such, there is no nexus shown or proved by
with clause 25, I am of opinion that such an approach is not appropriate; instead, the direct loss and expense sustained by the contractor should be
the claimant between the individual events and their respective con-
sequences, whether in terms of time or money requested. Awards
given on a global basis in Case C1 have been supported in the con-
text of “an extremely complex interaction [ : : : where] it may be
difficult or even impossible to make an accurate apportionment
way of putting forward a claim for loss and expense in circumstances where it is difficult to link each item to a particular breach.”
apportioned between the events for which the employer is responsible and the events for which the contractor is responsible.”
Case C2, the judge stated that, in a global claim, the “loss or ex-
pense attributable to each head of claim cannot in reality be sep-
arated.” In Case C10, the court deduced that the defendant’s
breaches instigated the additional cost or cost overrun and the
causal link was inferred rather than proved. Similarly, the court’s
Downloaded from ascelibrary.org by Western Sydney University Library on 03/21/20. Copyright ASCE. For personal use only; all rights reserved.
judgment in eight other cases ascertained that this was the case.
However, it should not be overlooked that, at trial, the claimant
must prove his case and that there is a significant difference be-
tween a global claim as a matter of pleading and such claim as
a matter of evidence, as cited in Case C8.
As a second criterion for a successful global claim, the claimant
(i.e., contractor) must secure the necessary evidence and particulars
in order to (1) prove the losses claimed (C6) and (2) enable the
defendant (i.e., employer) to recognize what case is being made
against him in adequate details (C8 and C9). The onus of demon-
Courts’ citation
strating the case remains with the plaintiff, and the evidential bur-
den of proof should not be basically transferred to the respondent.
To this end, the apparently absolute requirement of “impossibility”
might be integrated with a responsibility to use adequate and suf-
ficient particularity (SC2) by the claimant. Accordingly, the fragile
nature of a global claim is a strong incentive to keep adequate re-
cords as a standard practice; the more that can be demonstrated
by submitting sufficient records and documents, the more vigorous
the global claim, as in Cases C7 and C10. In Cases C6 and C8, the
courts balanced the needs of the plaintiff to submit further and
better particulars with the purpose of assisting the defendant in
understanding the case that to be answered. For instance, the plain-
tiff’s claim in Case C8 was recognized by the court as utterly
flawed in failing to particularize the claim basis; however, it was
permitted to proceed with additional and better particulars having
been requested.
Additionally, the claimant has to prove, based on a balance of
probabilities, that the actual costs would not have been incurred in
any other event or incident (SC3). This is done by demonstrating
(1) that the contractor’s accepted tender was adequately well-
Note: Bold denotes text in support of global claim success criteria.
in the case) provided evidence under the total cost method. Using
this method, the contractor must show (1) the impracticability of
proving actual losses directly (SC1); (2) the reasonableness of
Table 1. (Continued.)
its bid (SC5); (3) the reasonableness of its actual costs (SC3);
and (4) lack of responsibility for the added costs (SC6). The claim-
ant computes the damages as the difference between the actual
costs and the contract price submitted in his bid. However, the court
Case code
C13
27
1
2
1
5
2
2
4
1
2
2
2
1
2
to present evidence and submit adequate particularity with a
detachment of those events that may be the reason behind the in-
efficiencies in the plaintiff’s submitted claim, unreasonable tender
costs, or events that are the liability of neither of the disputing par-
ties. It follows that any cause of loss would not be the responsibility
Lack of contractor’s
between causes, the contractor must prove that all the events com-
—
—
—
—
—
—
—
—
—
—
—
—
p
1
plained about are the fault of the respondent (SC6). In other words,
Downloaded from ascelibrary.org by Western Sydney University Library on 03/21/20. Copyright ASCE. For personal use only; all rights reserved.
was not liable. Thus, the contractor had been able to prove having
no responsibility for the added costs before the global award
(SC5)
was made.
—
—
—
—
—
—
—
—
—
—
—
—
p
2011, p. 232). Such conduct of the claimant is, for instance, high-
—
—
—
—
—
—
—
—
p
p
4
lighted in Case C2, where the judge stated “ : : : provided that the
contractor has not unreasonably delayed the making of the claim
and so has himself created difficulty the architect must ascertain the
global loss directly attributable to the two causes : : : ”
Reasonableness of
contractor’s actual
—
—
p
p
p
impeding the success of global claims is the failure to plead the case
particularity (i.e., balance
vital impact in global claim cases. The main reason courts consider
(SC2)
—
—
—
—
—
—
—
p
p
p
p
this criterion sensitive to a global claim case is the need to “alert the
5
opposite party” with sufficient details to assess and know exactly its
position in the case being made against it (Case C15). In Case 16,
the judge asserted that global claims are difficult to handle, and
giving particulars, or justifying the inability to do so, is important
to reduce the extent of argument and help in managing the litiga-
tion. Additionally, in Case 17, the judge further explained the need
to particularize (i.e., establish
11
p
p
p
p
p
p
p
p
p
p
C10
C11
C12
C13
C1
C2
C3
C4
C5
C6
C7
C8
C9
© ASCE
C14 Lichter v. Mellon Stuart “Once it had thus been established that only part of the claim represented extra cost chargeable to Mellon, the one question remaining was whether a reasonable
Company (1962) allocation of part of the total sum was possible. The court undertook such an allocation, guided by evidence concerning the extra time required for the
performance of the stone contract as the result of the improper shelf angles. We cannot say that this was an arbitrary method of allocation. Indeed, the plaintiff is
not in position to complain that the allocation was imprecise since it bore the burden of proving how much of the extra cost resulted from Mellon’s improper
conduct. The plaintiff risked the loss of its entire claim, as occurred with reference to the masonry contract, if the court should not have been able to make a
reasonable allocation.”
C15 Wharf Properties v. Eric “The pleading is hopelessly embarrassing as it stands. : : : The failure even to attempt to specify any discernable nexus between the wrong alleged and the
Cumine Associates (1991) consequent delay provides, to use Mr Thomas’s [counsel for the defendants] phrase, “no agenda for the trial. : : : This has, however, no bearing upon the
obligation of a plaintiff to plead his case with such particularity as is sufficient to alert the opposite party to the case which is going to be made against him at
the trial. : : : This claim is advanced not only without any specification of the causal connection between the breaches and the sums claimed but without any
facts which will enable the defendant to ascertain which parts of these sums are being alleged to be attributable to the breaches alleged.”
C16 Nauru Phosphate Royalties “Global claims are difficult for the parties and the court to handle. To compel a plaintiff to give particulars of nexus or justify its inability to do so may reveal the
Trust v. Matthew Hall bogus claim. If particulars are produced they may clarify issues and reduce the area of argument even if the plaintiff can only provide alternative hypothesis. I can
Mechanical & Electrical see no reason why, for example, a judge controlling a building case list or arbitrator could not require the plaintiff to particularise the nexus or to justify its
Engineering Pty Ltd (1994) assertion that it is not possible to do so. Such directions would be justifiable upon the grounds that they would assist in the management of the litigation. The
issue raised here for decision is whether there is an abuse of process arising from the globally pleaded claim. I consider that, in all the circumstances, there is not.”
C17 John Holland Construction “In my opinion, the court should approach a total cost claim with a great deal of caution, even distrust. It would not, however, elevate this suspicion to the level
& Engineering Pty Ltd of concluding that such a claim should be treated as prima facie bad : : : Nevertheless, the point of logical weakness inherent in such claims, the causal nexus
v. Kvaerner RJ Bown Pty between the wrongful acts or omissions of the defendant and the loss of the plaintiff, must be addressed. : : : the court should be assiduous in pressing the
Ltd (1996) plaintiff to set out this nexus with sufficient particularity to enable the defendant to know exactly what is the case it is required to meet : : : . And it should not
be overlooked that an important means of achieving the result that, once it starts, the trial should be conducted without undue prejudice, embarrassment and delay,
is by ensuring that, when it begins, the issues between the parties including this nexus are defined with sufficient particularity to enable the trial judge to address
the issues, to rule on relevance and generally to contain the parties to those issues : : : . And if, in such a case, the plaintiff fails to demonstrate this causal nexus in
sufficient detail because it is unable or unwilling to do so, then this may provide the occasion for the court to relieve the defendant of the unreasonable burden
which the plaintiff would impose on it : : : ”
05020003-8
C18 Shimizu Corporation Ltd “I am satisfied that Shimizu did suffer some disruption to the Tower, in particular delay to the construction of [stair drum 2] : : : . but that it ceased, or should have
v. Attorney General (1996) ceased, to have effect by L6 : : : I am unable to quantify the effect of disruption to stair drums to L6 and I do not think that in the circumstances it is encumbent
[sic] upon me to estimate a figure for disruption : : : when the Tower disruption claim is presented as a global claim. Accordingly the disruption claim for the
Tower fails.”
C19 Amec Building Ltd. v. “Certainly, it seems to me that there is no substance in the complaint that the arbitrator had set his face against global claims and that, thereby, prejudiced Amec.
Cadmus Investment Co Ltd. What appears to have happened, is that, upon justifiable complaint of lack of particularity, the arbitrator insisted upon an allocation of the overall claim to
(1997) particular heads which was attempted by Amec and, when these matters were investigated by the accountants and in evidence and cross-examination, it clearly
became quite clear to the arbitrator that there were occasions of duplications, matters compensated elsewhere and a general lack of particularization. In those
circumstances, it seems to be what the arbitrator concluded that the plaintiff had not proved the costs incurred were due to the faults by Cadmus. : : : As is clear
“ : : : it will be the rare case indeed where no overrun cost beyond the contract price and no time overrun beyond the contract period is due to an act or omission
H&M specifically disavowed any attempt to demonstrate a causal link between any particular act of disruption, delay or prevention on the one hand and
“[The arbitrator] warned himself that if a global claim was to succeed whether or not it is the total claim, the contractor must eliminate from the causes of his loss
and expense all matters that are not the responsibility of the employer. It is clear that he concluded that this is precisely what S.J.W. had failed to do in the
find that there was any procedural mishap. If the arbitrator committed an error I do not consider it comes within the realm of those which would justify the removal
for which the contractor is responsible. : : : a global claim must fail if any part of the extra cost or time is the responsibility of the contractor. Thus, the
“ : : : It would not be fair to Petrobras, nor a practical way of the court proceeding, if Petromec were not required to give adequate particulars of their claim. : : :
claimant must show that the whole of the overrun is the consequence of the compensable events for which the proprietor is contractually responsible. : : :
contract due to the plaintiff’s failure to prove its actual costs
(Case C20), (3) inability to prove the reasonableness of the total
expended hours and attribution of the additionally incurred hours
only to the events of disruption relied on (Case C24), and (4) pro-
viding the court what it considered to be a small number of docu-
ments (Case C22). As for this last example, it was stated
in Case C22 that providing insufficient documents to the court
“would not be fair to [defendant], nor a practical way of the court
proceeding.”
The second criterion hindering the success of global claims is
the failure to (1) eliminate from the causes of the plaintiff’s loss and
expenses those matters that were not the responsibility of the
Downloaded from ascelibrary.org by Western Sydney University Library on 03/21/20. Copyright ASCE. For personal use only; all rights reserved.
defendant, or (2) prove that the costs incurred were the defendant’s
fault (Case C19). In such cases, the claim would be infeasible un-
less the plaintiff could reasonably make rational apportionment
such that a part of the total sum is allocated, and only for which
the defendant is responsible (Cases C14 and C21). Accordingly, the
plaintiff is thought to bear the burden of proving how much of the
extra cost indeed resulted from the defendant’s improper conduct
of an arbitrator for misconduct. The central factual contention relied on by the plaintiff fails.”
the court indicated that there was thus “no agenda for the trial.”
The nexus in global claim cases must be treated as a common-sense
requirement, as directed in Case C21: “That is particularly impor-
tant, in my view, where averments are made attributing, for exam-
ple, the same period of delay to more than one cause.”
Construction v. Laing
H&M Engineering &
Construction (2011)
Anor (2009)
C23
C24
p
C18 p —
p — 1
C19 p
a
—
p 2
C20 —
p pb 2
C21 —
p 2
C22 —
p — 1
C23 —
p p —
p 1
C24 3
Total 8 6 5 19
a
This denotes the wording adopted in C19.
b
This denotes the wording adopted in C21.
each event causing the delay and disruption, and that was why the if rough and not very accurate computations are produced: “In
claim had been submitted on a global basis. The reasoning adopted the third place, even if it cannot be said that events for which the
by Laing was that all extra costs allegedly incurred by John Doyle employer is responsible are the dominant cause of the loss, it
needed to have been due to the delay and disruption caused by the may be possible to apportion the loss between the causes for
defendant (i.e., Laing). Subsequently, if one of the events claimed which the employer is responsible and other causes. In such
by Doyle had proven not to have been caused by Laing, the case cases it is obviously necessary that the event or events for which
would have failed. The court confirmed that there is no problem the employer is responsible should be a material cause of the
with submitting a global claim if there exists a large number of loss. Provided that condition is met, however, we are of the opi-
interrelating events and the loss linked to each of these events can- nion that apportionment of loss between the different causes is
not be proven. As long as John Doyle could determine or prove possible in an appropriate case.”
those events, the accountability of Laing for each of them, their • The merits of a global claim and its chances of success are not
contribution to the global loss, and the method for computing likely to be specified at an “interlocutory stage.” The matter of
the loss incurred, the claim would be successful. whether causation can be demonstrated should usually be post-
The decision of the Inner House in Doyle v. Laing is a signifi- poned until the trial, when all the particularity and evidence is
cant reassessment of the judicial approach to global claims, and submitted, and therefore it would apparently not be determined
thus includes three main changes of emphasis in the law, each of at some “interlocutory stage” upon the submission of a request
which provides an inducement to the pursuit of these types of to strike out.
claims, as follows:
• Whereas previously it was confirmed that any cause of loss pro- Walter Lilly & Company Limited v. Giles Patrick Cyril
ven not to be the fault of the respondent would be deadly to the Mackay, DMW Developments Limited (2012)
global claim (SC6 or FC2), it seems now that this is only valid if Walter Lilly & Company Ltd won a £15.3 million tender in 2004 to
the cause of the damage is dominant or overriding. In other construct a luxurious development project in Bolton Place, South
words, the employer must show that the cause of the alleged Kensington. The contract between the employer (i.e., Mackay) and
delay and/or loss not its liability is significant in order for the contractor (Walter Lilly) was the JCT Form of Building
the global claim to fail. That said, even where the loss has been Contract (JCT 1998—without quantities) with a Contractor’s De-
caused both by events for which the employer is accountable signed Portion (CDP) supplement. Walter Lilly suffered significant
and by others for which the employer is not, the global claim delays and claimed for an extension of time and losses and ex-
can still be successful if those for which the employer is liable penses, leading to strained relations between the disputing parties.
are the main cause of loss: “If an event or events for which the The judge, Mr. Justice Akenhead, in charge of the Technology and
employer is responsible can be described as the dominant cause Construction Court (TCC) in London, describes the case as “a full-
of an item of loss, that will be sufficient to establish liability, blooded conflict between the parties in which there seems to have
notwithstanding the existence of other causes that are to some been little, no or belated room for comprise.” Mr. Justice Akenhead
degree at least concurrent : : : ” provided some interesting and valuable guidelines for preparing
• In cases where it is not feasible to recognize the dominant cause and pursuing global claims. He reviewed much case law, including
of the loss, and the causes of damages are actually concurrent, a Cases C1, C2, C10, and Doyle v. Laing, and deduced that there is
global claim may partly succeed. Accordingly, it may be pos- nothing wrong in principle with global claims, stating, “In princi-
sible for the court to apportion liability for the loss amid those ple, unless the contract dictates that a global cost claim is not per-
events for which the defendant is liable and other events. In this missible if certain hurdles are not overcome, such a claim may be
way, the contractor is awarded a part of the claimed award, even permissible on the facts and subject to proof.” To this effect, three
Prior to Lilly V. MacKay, it was a requirement for the contractor to loss would have always occurred irrespective of the events relied
prove that it is impossible or impractical to separate out the con- upon by the claimant contractor or that other events (which are not
sequences of each delaying event in order to for the global claim relied upon by the claimant as causing or contributing to the loss or
to be successful (SC1). In Lilly v. Mackay, the Judge stated that which are the ‘fault’ or ‘risk’ of the claimant contractor) occurred
Walter Lilly must prove its global claim as a “matter of fact” while may have caused or did cause all or part of the loss” [paragraph
pursuing it. In particular, a contractor must prove its claim based 486(d)].
“ : : : on a balance of probabilities that, first, events occurred which
entitle it to loss and expense, secondly, that those events caused
delay and/or disruption and thirdly that such delay or disruption
Interconnections between Success and Failure
caused it to incur loss and/or expense : : : .” Nevertheless, Mr.
Criteria
Justice Akenhead ruled that it is no longer a requirement for the
contractor to demonstrate that “ : : : it is impossible to plead and In order to further elaborate on the interconnections between the
prove cause and effect in the normal way or that such impossibility already deduced criteria contributing to the success and failure of
is not the fault of the party seeking to advance the global claim : : : ” a global claim, a framework has been conceptualized as illustrated
in order for the global claim to be successful. He recognized that in Fig. 3. Prior to Lilly v. MacKay, the contractor was required
the court might be “more skeptical about the global cost claim to show that it was impossible or impracticable to separate the loss
if the direct linkage approach is readily available but is not de- or expense attributable to each head of claim (SC1/FC3), which
ployed” but also stated that this does not imply that a global claim was considered the core condition to pursue a global claim. How-
should be vetoed. Additionally, He refused Mackay’s argument ever, as proved by Lilly v. MacKay, this is not acknowledged any-
that a global claim should not be permitted if the contractor had more as a “matter of principle” (Fawzy and El-Adaway 2015).
created the impossibility of disentanglement. Accordingly, he As such, the contractor must keep satisfactory contemporaneous
stated that the argument that “a global award should not be allowed records and proper documentation (payment certificates, minutes
where the contractor has himself created the impossibility of dis- of meetings, site instructions, timesheets, material invoices, etc.)
entanglement : : : is wrong.” in order to provide appropriate particulars that can be used for
Employer Not Liable for Losses and Damages (1) supporting the losses claimed (SC2/FC1, SC3) and (2) proving
Prior to Doyle v. Laing, it was generally affirmed that, if an em- the impracticability to attribute or link the actual costs to individual
ployer could prove that a part of the contractor’s damage had been events (SC1, SC2/FC1). Conditional to the success of the global
due to a matter that was not the employer’s liability, the contractor’s claim is the basic requirement that a global award should not be
global claim would be a dead approach and fail in its entirety (FC2 allowed if the contractor itself created the difficulty of disentangle-
or SC6). However, global claims, as in Lilly v. MacKay, are no lon- ment (SC4), justifying the link between SC4 and SC1 and
ger likely to be stroked out if they encompass elements related to SC2/FC1. To be noted though is that, in the view of Judge
events for which the employer is unaccountable. Any such events, Akenhead in Lilly v. MacKay, the unreasonable delay by the con-
involving any contractor’s culpable events, must be removed from tractor in making its global claim does not impede the success of
the global claim and thus be apportioned. Therefore, according to the claim at trial.
Mr. Justice Akenhead, that a global claim included events for which In the pursuit of a global claim, the plaintiff has the burden of
the employer is not liable does not cause the global claim to fail quantifying the loss suffered, which is usually equal to the total cost
completely. As an alternative, the global claim would be decreased that the claimant has incurred over and above the contract price. It is
by the loss resulting from that event: “The fact that one or a series calculated as the difference between the actual cost of the contrac-
of events or factors (unpleaded or which are the risk or fault of the tor and the price submitted in his tender. While there is nothing “in
claimant contractor) caused or contributed (or cannot be proved principle” wrong with pursuing a global claim, the contractor is
not to have caused or contributed) to the total or global loss does required to show that its tender was appropriately well-priced by
not necessarily mean that the claimant contractor can recover proving that the loss incurred would not have been incurred in
nothing.” any other event (SC5). That said, the claimant must submit evi-
dence suggesting that its contract price was reasonable and that
Contractor’s Damage Not Incurred in Any the claimed damage occurred only because of the employer’s
Other Event events relied upon by the contractor. Subsequently, the contractor
Lilly v. MacKay affirmed that the contractor, as required previously, must provide the necessary particulars in order to prove the reason-
has the burden of proving that it would not have incurred the loss in ableness of the figures representing the actual incurred costs (SC3).
any other event in the pursuit of a global claim (SC5). In particular, That is, the claimant, while not being required to demonstrate cau-
Mr. Justice Akenhead stated that the contractor has to show that the sation, must adduce the necessary evidence and particulars in order
loss “would not have been incurred in any event”—for example, to prove the adequacy of the information relied upon as the basis for
that the bid price submitted by the contractor was not underpriced. the total cost claim.
SC1 SC2
Impracticable or Sufficient or adequate
impossible to particularize particularity
Downloaded from ascelibrary.org by Western Sydney University Library on 03/21/20. Copyright ASCE. For personal use only; all rights reserved.
FC3 FC1
Failure “even to attempt” Failure to plead the case
to specify any discernable with sufficient or adequate
nexus particularity and facts
SC5 SC3
Reasonableness of the
Reasonableness of the
contractor's actual incurred
contractor's bid price
costs
Legend
Success criterion No longer a prerequisite for
(SC) the success of claim as per
Walter Lilly’s case CS6
SC6
Failure criterion
Lack of the contractor's
(FC)
responsibility for the added
No longer a prerequisite for
the success of claim as per costs
Related criteria John Doyle’s case FC2
Failure to prove the costs
incurred were due to faults
by defendant
Mirroring success/failure criteria
Fig. 3. Interconnections between failure and success criteria for global construction claims.
Wallace (2012) considered courts to be generally reluctant in nexus between individual breaches and incurred losses might
accepting claims based on the total cost method in construction dis- render the relationships between those individual events and their
putes. Nevertheless, the total cost method has been employed in respective consequences tremendously complex or even impracti-
those odd situations where no other technique to calculate losses cable to accurately apportion. However, the courts have methodi-
is practicable and where the tribunal adopts appropriate precau- cally enforced stringent conditions, prior to the filing of any such
tions. Accordingly, the link (SC3, SC5) is mainly concerned with claim, in relation to the pleadings and in particular regarding any
the pursuit of a total cost claim, where the contractor computes the contribution to the damage that may have been the result of the
losses as the difference between the actual costs incurred and the plaintiff’s events. This research paper provides an exhaustive inves-
contract price, hence aspiring to a cash-neutral state. To be noted tigation of the conditions that have helped in making global claims
here is that the contractor must include in its claim only the losses more admissible and potentially successful. A case law review,
that are the responsibility or fault of the employer (SC6/FC2), jus- involving a total of 26 cases, was performed as part of the inves-
tifying the link (SC3, SC6/FC2). However, Doyle v. Laing and Lilly tigation. This followed a methodical search effort that produced
v. MacKay show that even if the global claim contains an event that two main sets of 13 and 11 cases, in which the global claim either
is not the fault of the employer, this does not imply that the con- succeeded or failed, respectively, because of a number of inferred
tractor will not recover a part of the claimed damages; the award
factors (i.e., success and failure criteria). The remaining two
thus depends heavily on the significance of this event.
cases signify a critical shift in legal analyses which can be viewed
as providing a more lenient prospect for contractors filing global
Conclusions claims.
Six essential criteria, deduced from the case law review, are in-
It has been more than five decades since courts of law opened the dicated to contribute to the success of global claims. A number of
door to the pursuit of global claims, realizing that a composite observations or deductions can be drawn in this regard:
• One important success criterion calls on the claimant to separate H&M Engineering & Construction Pty Ltd v. Laing O’Rourke Australia
the consequence of events that are not the responsibility of the Construction Pty Ltd NSWSC 818 (2010).
employer and consequently do not entitle it to an extension of Holland Construction & Engineering Pty Ltd. v. Kvaerner RJ Brown Pty
Ltd., 82 Building Law Reports (BLR) 83 (1996).
time and/or losses. This obviously corresponds to the failure cri-
How Engineering Services Limited v Lindner Ceilings Floors Partitions
terion requiring the contractor to prove that the losses incurred PLC, 3 TCLR 273 (2001).
were due to faults by the defendant. However, Doyle v. Laing Imperial Chemical Industries Plc v. Bovis Construction Ltd., 32 Construc-
and Lilly v. MacKay demonstrate that, even if the global claim tion Law Reports (ConLR) 90 (1992).
includes an event that is not the liability of the owner, this does Inserco Ltd. v. Honeywell Control Systems EWCA Civ 222 (1998).
not result in the plaintiff not being awarded a part of the claimed J. Crosby & Sons Ltd. v. Portland Urban & District Council, 5 Building
losses, contingent on the significance of the event in question. Law Reports (BLR) 121 (1967).
• Apart from the aforementioned critical criteria, the plaintiff must Jackson Construction Co., Inc. v. U.S., No. 97-31C (Fed. Cl.) (2004).
satisfy two basic principles in order to succeed in its global John Doyle Construction Limited v. Laing Management (Scotland)
claim, namely: (1) not having unreasonably delayed making Limited, Building Law Reports (BLR) 295 (2004).
John Holland Construction and Engineering Pty Ltd. v. Kvaerner RJ Brown
the claim, and (2) proving the reasonableness of both its tender
Pty Ltd., 82 Building Law Reports (BLR) 83 (1996).
price and the actual incurred costs. Lichter v. Mellon Stuart Company 305 F.2d. 216 3d Cir (1962).
Finally, it is important to note that the industry-reported cases London Borough of Merton v. Stanley Hugh Leach, 32 Building Law
reviewed in this paper and the analyses of their peculiarities are not Reports (BLR) 31 (1985).
to be understood or interpreted as legal advice for contractors when London Underground Ltd. v. Citylink Telecommunications Ltd. B.L.R.391
filing global claims. Rather, the synthesis of success and failure (2007).
criteria aims to provide guidance to contractors as to the viability Mid Glamorgan County Council v. Devonald Williams and Partners,
of a global claim and, from a legal perspective, the criteria that need 8 Construction Law Journal (Constr LJ) 61 (1991).
to be met for it to succeed. Also to be noted is that the 26 cases Nauru Phosphate Royalties Trust v. Matthew Hall Mechanical & Electrical
examined for the purpose of analysis span about five decades. Engineering Pty Ltd 2 V.R. 386 (1994).
Petromec Inc v. Petroleo Brasileiro SA Petrobras 2 Costs LR 212 (2007).
Given the criteria identified in this work, further case analysis
SJW Facades Ltd v. Bowen Construction Ltd & Anor IEHC 49 (2009).
would only endorse these criteria or possibly reveal new ones. That Servidone Construction Corp. v. US, 931 F 2d 860 (Fed. Cir.) (1991).
is, any additionally determined criteria cannot realistically be ex- Shell Refining (Australia) Pty Limited v. A J Mayr Engineering Pty Limited
pected to negate those designated as success criteria that contractors NSWSC 94 (2006).
must strive to satisfy when embarking on a global claim. Shimizu Corporation v. Attorney General HKCFI 499 (1996).
In brief, a global claim may be observed as the exception to, or Walter Lilly & Company Limited v. Giles Patrick Cyril Mackay, DMW
at least the alteration of, more commonly accepted event-based, Developments Limited, England and Wales High Court (EWHC)
cause-effect claims. The work presented in this paper is not in- 1773 (TCC) (2012).
tended to support or encourage the pursuit of global claims by con- Wharf Properties v. Eric Cumine Associates, 52 Building Law Reports
(BLR) 8 (1991).
tractors. Rather, it serves the purpose of approaching such claims
from the perspective of criteria that, from a legal perspective, are
critical to them. Ultimately, when these legally based success Works Cited
criteria (three of which happen to mirror all three identified failure
criteria) are satisfied, it is believed that the prospect of a successful AACE (American Association of Cost Engineers). 2019. Cost engineering
terminology. AACE International Recommended Practice No. 10S-90.
global claim will greatly improve.
Morgantown, WV: AACE International.
Atkinson, D. 2007. Causation in construction law: Principles and methods
of analysis. London: Daniel Atkinson Limited.
Data Availability Statement Chappell, D., V. Powell-Smith, and J. H. Sims. 2008. Building contract
claims Hoboken, NJ: Wiley.
All data, models, and code generated or used during the study Cheung, S. O., and K. H. Y. Pang. 2012. “Anatomy of construction dis-
appear in the published article. putes.” J. Constr. Eng. Manage. 139 (1): 15–23. https://doi.org/10
.1061/(ASCE)CO.1943-7862.0000532.
Cheung, S.-O., H. C. Suen, S. T. Ng, and M.-Y. Leung. 2004. “Convergent
views of neutrals and users about alternative dispute resolution.”
Acknowledgments J. Manage. Eng. 20 (3): 88–96. https://doi.org/10.1061/(ASCE)0742
-597X(2004)20:3(88).
The authors would like to acknowledge the generous endowed doc- CMS (Cameron McKenna and Sigle) Law-Now. 2005. “Global claims—
toral research funding granted by the Maroun Semaan Faculty of The effect of John Doyle v Laing Management.” Accessed August 10,
Engineering and Architecture at the American University of Beirut 2019. http://www.cms-lawnow.com/ealerts/2005/03/global-claims-
in support of this research. the-effect-of-john-doyle-v-laing-management?cc_lang=de.