Build up rate for;


The following in 4 nos. roof trusses Type TF3 approximately 15000mm long including cutting, drilling, welding.
bolting, painting, hoisting and fixing in position etc. as shown on Drawing No. ABCD 2023/KAED/007 - Block C:-

125mm x 125mm x 4.5mm thick (16.9kg/m)

Steel truss 125mm x 125mm x 4.5mm thick (16.9kg/m) including bolts RM6.50 per kg
Steel worker RM110.00 per day
Unskilled RM75.00 per day
All in rate hire crane (include fuel and operator) RM1,000.00 per day

Assumption:
One set of roof truss weighing 302.5kg
A gang of labour consist of 3 skilled labours and 3 unskilled labours can fix one roof truss in 3 hours
Hoisting; one roof truss in 3 hour
Price of material includes delivery cost

Material

Steel roof truss; RM6.50 x 1000 kg RM 6,500.00


5% wastage RM 325.00
Material cost RM 6,825.00

Labour

Hoisting and fixing into position:


Steel worker; (RM 110/8) x 3 x 3 RM 123.75
Unskilled; (RM75/8) x 3 x 3 RM 84.38

Crane; (RM1000/8) x 3 RM 375.00

Labour and machine cost per hour per roof truss RM 583.13

Labour and machine cost per tonne;


RM583.13 / 0.3025 tonne RM 1,927.69
RM 8,752.69
Add 15% overhead and profit RM 1,312.90
RM 10,065.59