Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

REPORT

MOORING INCIDENTS OVER


THE PAST YEARS, THEIR
ROOT CAUSES AND HOW
THEY CAN BE AVOIDED

Brought to you by:


REPORT MOORING INCIDENTS

INTRODUCTION

FPSO Mooring line(s) failure is a common threat FPSO operators faced today especially in deeper
water and harsh weather environment. Studies1 shown that there can be 1:50 (2%) chance of single
line failure per asset per annum with as many as 5 events taking place per year, and 1 event per year
for multiple lines failure.

The typical design life of mooring system is up to 25 years and the longer the design life of the
floaters, the higher chance of failure during its life cycle. Consider a 25 years design life of a FPSO,
there can be 50% chance of failure during the lifetime of a mooring line. According to historical
data published by the HSE (Morandini and Legerstee, 2009, with reference to DNV Industry AS,
2003)2, mooring failures in UK happened once in every seven operating years for FPSOs, about
once for every 17 years for FSOs.

The consequences of mooring line failure are undesirable. It is not just the danger of lines breaking,
but damage caused to the risers and other subsea equipment can make reinstatement extremely
costly too. The reputation of the operator will be at stake, there can be disruptions to production
and most important of all, lead to possible loss of lives and environmental issues.
REPORT MOORING INCIDENTS

GRYPHON ALPHA FPSO PETROJARL BNAFF & VARG FPSOS

Maersk’s operated Gryphon Alpha FPSO was one of the Nearby the Gryphon field at the Canadian Natural
longest serving permanently moored FPSO in Europe. It Resources’ Banff field in the North Sea, it was also
is located off the coast of Aberdeen in the UK North Sea reported that Teekay-operated, 20,000 dwt FPSO
and has a design life to remain on station since 1993 for Petrojarl Banff lost two of ten permanent mooring lines
up to 20 years. securing it at its position on January 2011.

On February 2011, Gryphon FPSO saw four of the ten Another Teekay FPSO, Petrojarl Varg, operated by former
mooring lines parted due to a heavy storm. The turret Talisman energy, now owned by Repsol suffered a single
moored floating facility drifted 180 metres off station line mooring line failure towards the end of 2012. The
and ripped all of the eleven gas lift risers out of the ten points turret moored FPSO located in Norway North
bottom of the ship and causing significant damage to the Sea was delivered in 1998. The same mooring line 4 also
subsea equipment. According to a paper (Statoil, 2013, failed in 2006.
page 29, and Brown, 2013), the first line failure on the
Gryphon Alpha was probably caused by fatigue failure of According to a report from Norwegian Continental Shelf2,
a flash butt weld in a chain below its design capacity. the root cause of the failure is due to high-cycle, low-
stress fatigue initiated on the external surface of the link.
Gryphon Alpha FPSO underwent an extensive The upper chain segment was led via a seven- pocket
refurbishment at the Damen shipyard in Rotterdam. fairlead wheel at the lower side of the turret through
The repair and upgrade work includes, replacements of a chain pipe up to the chain stopper on a turret deck
mooring system with capacity 20% stronger than the level with the main deck. General surface corrosion was
original mooring system, new marine control system obvious, with extensive localized corrosion, significant
installed, Turret was refurbished, power management wear and cracks on the external surface around the
and process control systems upgraded, thrusters and fracture surfaces. General and severe localized corrosion
motors overhauled, class renewal certification and some would have acted as stress intensifiers and initiation
550 tonnes of steel were replaced to extend vessel’s spots for fatigue cracks owing to roughening and pitting
structural life. of the external surface (DNV, 3 Apr 2013). Teekay Petrojarl
concluded that the direct cause was the broken chain
The anchor reconnection was completed on 8 September link being exposed for out of plane bending (OPB). This is
2012 with FPSO moored on ten stronger anchor lines. bending in fairlead or rotation of chain (twist) over time in
Commissioning and hook up was finalized on May 2013 a fixed position of the fairlead.
more than two years after the mooring incident. The
overall cost of reinstatement was estimated to be US$1.8
billion.
REPORT MOORING INCIDENTS

NORNE FPSO FPSO GIRASSOL BUOY

In another incident, Statoil’s Norne FPSO located in an Total E&P FPSO Girassol, which was installed in offshore
area with very harsh weather conditions had mooring area of Angola in Sep 2001 had a CALM (catenary anchor
line failure in November 2012 with the chain having leg mooring)-type offloading buoy anchored by means of
installed on the same location since 2007. According to 3 groups of 3 anchor legs, located approximately one mile
Statoil, there are two failures to the turret moored facility. away from the bow of the FPSO in depth of 1350m.
The first failure was caused by fatigue from the bending
of chain during abnormal load conditions close to the 235 days after the buoy installation, the buoy had anchor
weld. This can be either caused by incorrect location of legs B4, B5 and B6 broke almost simultaneously, followed
the chain in the fairlead or by the failure of the fairlead one month later by the rupture of the anchor leg B1. The
to rotate i.e. OPB effect. The second failure took place anchor legs were composed of co-linear segments of
in the same chain link immediately afterwards as a 81 mm studded chains and 130 mm diameter polyester
consequence of overload caused by the fatigue failure. ropes. The ruptures in B4, B6 and B1 occurred exactly at
the same location, i.e. at the 5th link of the Upper Chain
Other findings show that the crew on board had been Segment connected to the Buoy inside SBM standard-
unable to change the length of the lines monthly to type “curved chain hawses”, while Leg B5 broke in the
redistribute stress, and the chain member had upper rope segment.
unintentionally spent too long in each position. The chain
was 114mm of the NV K4 stud less type, with a breaking This incident led to the study of OPB (out-of-plane
load of 12,420kN. The winch of the mooring lines had not bending)-induced failure of mooring chain which was
worked as it should since May 2012 too. identified as one of the root cause of chain failures due to
fatigue.
There is no deviation in the material quality was found in
testing.
REPORT MOORING INCIDENTS

OTHERS THE CAUSES

Other major mooring incidents reported are as From the above-mentioned incidents, we infer that the
follows: root causes of mooring failures can be most commonly
 2011 Volve – 2 of 9 lines parted, no damage to riser. caused by OPB effect, high-cycle low stress fatigue,
 2010 Jubarte – 3 lines parted between 2008 localized corrosion, equipment design etc.
and 2010.
 2009 Nan Hai Fa Xian – 4 of 8 lines Other factors contributing to the mooring failures
parted; vessel drifted a distance, riser broken. include chain interaction with the seabed (soil properties,
 2009 Hai Yang Shi You – Entire yoke mooring column stiffening, damping etc.) and inadequate procedures,
collapsed; vessel adrift, riser broken. negligence and skills-deficiency relating to procurement,
 2006 Liuhua (N.H.S.L.) – 7 of 10 lines parted; vessel manufacturing, quality control, approval, storage, logistic
drifted a distance, riser broken. handling, installation, operation and maintenance etc.

For example, material properties, welding, bending,


heating, traceability for quality assurance, inspection
and testing methods, certification authority’s approval
process, perseveration after manufacturing, storage,
handling and loading during transport, operator skill
levels, inappropriate deployment leading to anchors mis-
aligned, wires kinking or twisted etc, incorrect tension
in lines, lack of proper maintenance, re-tensioning of
lines, re-using of mooring components, lack of proper
monitoring systems etc.

References:
1. BP’s Guy Drori 24 March 2015 - Underlying Causes of Mooring Lines Failures across the Industry
2. Report - Anchor line failures Norwegian continental shelf 2010-2014
REPORT MOORING INCIDENTS

HOW TO AVOID

Due to the rising number of mooring incidents over the years there is an increasing need to address the
root causes of the failures and how these incidents can be avoided.

Awareness of corrosion, wear, fatigue and relevant loading conditions during design will improve the
design and extend the service life of the structural components in the mooring system. Extensive
study had also been performed with variable design parameters to identify the stress ranges due to
OPB moments of the chains and fairleads using FEAs (finite element analyses). The results range from
redesigning of chain connection, improved designs in fairleads pocket styles to reduce the OPB effect.
There are also further tests still undergoing to determine more accurately the OPB stress relationship.

Aside from appropriate rules and regulation from the relevant authorities, the entire process starting
from design, manufacturing and eventually lead to installation and operation of new systems need
to be fit for purpose and fulfilling all quality and reliability requirements. This can be achieved by
honest and realistic expectations well communicated by all parties (operators, contractors, yard and
manufacturers). Operators should also continue to share their knowledge and experiences with the rest
of the industry.

The emphasis should also be on maintaining long term integrity rather than cutting upfront costs.
There must be competent supervision during installation and regular inspection and maintenance
programs devised over the lifetime of the mooring operation. In addition, monitoring systems should
be used as pre-emptive measures.
¡ 19- 22
September 2016
¡ Marina Bay Sands,
Singapore

THE ROAD AHEAD: FINDING OPPORTUNITY IN THE DOWNTURN


In this challenging market climate, leading FPSO decision-makers continue to choose
the FPSO World Congress as their main platform for industry dialogue. Hear leading
insights from our global speaker faculty, including:

Curtis Lohr Bernard van Leggelo Simon Harman Stuart Wheaton


Stones Project Director Managing Director, FPSO FPSO Category Manager UK Director and Business Unit
SHELL Business Unit WOODSIDE ENERGY Manager
SBM OFFSHORE PREMIER OIL

Richard Ella Puneet Sharma Chris Brett Eirik Barclay


Project Office Director Vice President President Chief Executive Officer
SBM OFFSHORE MODEC TEEKAY OFFSHORE YINSON PRODUCTION

FOR MORE INFORMATION, PLEASE LOG ON TO www.fpsoworldcongress.com

You might also like