KABUPATEN TEGAL
Kegiatan :
Pekerjaan :
Lokasi :
TA : 2021
NO URAIAN SATUAN
1 Pekerja OH
2 Tukang gali OH
3 Mandor OH
4 Tukang cat/ plitur / batu OH
5 Kepala tukang cat/ plitur / batu OH
6 Tukang kayu OH
7 Kepala tukang kayu OH
8 Tukang Besi / ledeng OH
9 Kepala Tukang besi / ledeng OH
10 Tukang Besi Profil OH
11 Kepala Tukang besi Profil OH
12 Mekanik OH
13 Mekanik Pembantu OH
14 Operator terlatih/ masinis OH
15 Operator kurang terlatih OH
16 Pembantu operator/ pemb. masinis OH
17 Sopir truk OH
18 Sopir personil OH
19 Pembantu sopir OH
20 Buruh lapangan tak terlatih OH
21 Buruh lapangan semi terlatih OH
22 Buruh lapangan terlatih OH
23 Tukang masak aspal OH
24 Penjaga malam OH
B. UPAH TENAGA PEMASANGAN JARINGAN LISTRIK
1 Pasang CA1 Unit/Set
2 Pasang CA1' Unit/Set
3 Pasang CA2-1 Unit/Set
4 Pasang CA2 Unit/Set
5 Pasang CA2' Unit/Set
6 Pasang CA3 Unit/Set
7 Pasang CA3' Unit/Set
8 Pasang CA4 Unit/Set
9 Pasang CA4' Unit/Set
10 Pasang CA5 Unit/Set
11 Pasang CA5' Unit/Set
12 Pasang CA5-1 Unit/Set
13 Pasang CA5-1' Unit/Set
14 Pasang CA6 Unit/Set
15 Pasang CA6' Unit/Set
16 Pasang SE 1-2 ( 7 M) Unit/Set
17 Pasang E 1-2 ( 7 M ) Unit/Set
18 Pasang SE 1-2 ( 9 M) Unit/Set
19 Pasang E 1-2 ( 9 M ) Unit/Set
20 Pasang SE 1-2 ( 11 M) Unit/Set
21 Pasang E 1-2 ( 11 M ) Unit/Set
22 Pasang SE 1-2 ( 12 M) Unit/Set
23 Pasang E 1-2 ( 12 M ) Unit/Set
24 Pasang SE1-3 (11 M) Unit/Set
25 Pasang E1-3(11 M) Unit/Set
26 Pasang SE1-3 (12 M) Unit/Set
27 Pasang E1-3 (12 M) Unit/Set
28 Pasang SE2-2 Unit/Set
29 Pasang SE2-3 Unit/Set
30 Pasang E2-3 Unit/Set
31 Pasang F 1-2 Unit/Set
32 Pasang F 1-3 Unit/Set
33 Pasang J5-T (CJ2) Unit/Set
34 Pasang J7 - T (CJ3) Unit/Set
35 Pasang J6 - T (CJ4) Unit/Set
36 Pasang MJ6 - T (CJ4) Unit/Set
37 Pasang SG 105 25 KVA Unit/Set
38 Pasang SG 105 50 KVA Unit/Set
39 Pasang SG 106 25 KVA Unit/Set
40 Pasang SG 106 50 KVA Unit/Set
41 Pasang P.12 Unit/Set
42 Pasang P12.C Unit/Set
43 Pasang P12.C' Unit/Set
44 Pasang CM5 - 2 Unit/Set
45 Pasang CM2-11 Unit/Set
46 Pasang CM2 - 12 Unit/Set
47 Pasang CM2 - 12A Unit/Set
48 Pasang CM2-15 Unit/Set
49 Pasang CM3-4 Unit/Set
50 Pasang CM2-11 M Unit/Set
51 Pasang CM5-3 Unit/Set
52 Pasang CM5-4 Unit/Set
53 Pasang CM5-5 Unit/Set
54 Pasang CM5-6 Unit/Set
55 Pasang CM5-8 Unit/Set
56 Pasang CM5-9 Unit/Set
57 Pasang CM5-12 Unit/Set
58 Pasang CM5-13 Unit/Set
59 Pasang CM5-16 Unit/Set
60 Pasang CM5-20 Unit/Set
61 Pasang CJ5 Unit/Set
62 Pasang CJ6 Unit/Set
63 Pasang CJ6X / SJ6X Unit/Set
64 Pasang CJ7 Unit/Set
65 Pasang CJ8 Unit/Set
66 Pasang CJ10 Unit/Set
67 Pasang SJ5 Unit/Set
68 Pasang SJ6 Unit/Set
69 Pasang SJ7 Unit/Set
70 Pasang SJ8 Unit/Set
71 Pasang SJ10 Unit/Set
72 Pasang SA1 Unit/Set
73 Pasang SA1' Unit/Set
74 Pasang SA2 Unit/Set
75 Pasang SA2' Unit/Set
76 Pasang SA3 Unit/Set
77 Pasang SA3' Unit/Set
78 Pasang SA4 Unit/Set
79 Pasang SA4' Unit/Set
80 Pasang SA5 Unit/Set
81 Pasang SA5' Unit/Set
82 Pasang SA5-1 Unit/Set
83 Pasang SA5-1' Unit/Set
84 Pasang SA6 Unit/Set
85 Pasang SA6' Unit/Set
86 Pasang B1 Unit/Set
87 Pasang B1A Unit/Set
88 Pasang B2 Unit/Set
89 Pasang B3 Unit/Set
90 Pasang B4 Unit/Set
91 Pasang B5 Unit/Set
92 Pasang CC1 Unit/Set
93 Pasang CC1' Unit/Set
94 Pasang CC1-1 Unit/Set
95 Pasang CC1-A Unit/Set
96 Pasang CC.1-A' Unit/Set
97 Pasang CC.2 Unit/Set
98 Pasang CC.2' Unit/Set
99 Pasang CC2 - A Unit/Set
100 Pasang CC2-1 Unit/Set
101 Pasang CC2 - A' Unit/Set
102 Pasang CC.3 Unit/Set
103 Pasang CC.3' Unit/Set
104 Pasang CC 7 Unit/Set
105 Pasang CC 7' Unit/Set
106 Pasang CC 7 A Unit/Set
107 Pasang CC 7 A' Unit/Set
108 Pasang CC 8 Unit/Set
109 Pasang CC 8 - A Unit/Set
110 Pasang CC 8 A' Unit/Set
111 Pasang SC . 1 Unit/Set
112 Pasang SC. 1' Unit/Set
113 Pasang SC . 1 - A Unit/Set
114 Pasang SC 1 - A ' Unit/Set
115 Pasang SC 2 Unit/Set
116 Pasang SC 2 ' Unit/Set
117 Pasang SC2-A Unit/Set
118 Pasang SC2-A' Unit/Set
119 Pasang SC3 Unit/Set
120 Pasang SC3' Unit/Set
121 Pasang SC7 Unit/Set
122 Pasang SC7' Unit/Set
123 Pasang SC7-A Unit/Set
124 Pasang SC7-A' Unit/Set
125 Pasang SC8 Unit/Set
126 Pasang SC8-A Unit/Set
127 Pasang SC8-A' Unit/Set
128 Pasang SC9 Unit/Set
129 Pasang SC10 Unit/Set
130 Pasang SC 11 Unit/Set
131 Pasang SC12 Unit/Set
132 Pasang DC1 Unit/Set
133 Pasang DC2 Unit/Set
134 Pasang DC3 Unit/Set
135 Pasang DC4 Unit/Set
136 Pasang DC5 Unit/Set
137 Penanaman tiang batang
138 Pengangkutan tiang (dataran tinggi) batang
139 Pengangkutan tiang (dataran rendah) batang
140 Penomoran Tiang batang
141 Bongkar tiang batang
142 Bongkar LVTC 2 x 35 x N50 m
143 Bongkar pasang trafo buah
144 Biaya tarik jaringan
145 Jaringan JTM AAAC 70 mm2 m
146 Jaringan JTR only
- Kabel LVTC 2 x 70 + N50 m
- Kabel LVTC 2 x 35 + N50 m
2021
NAGA
HARGA ( Rp )
100,000.00
150,000.00
150,000.00
150,000.00
150,000.00
150,000.00
150,000.00
150,000.00
150,000.00
150,000.00
150,000.00
150,000.00
150,000.00
150,000.00
150,000.00
75,000.00
150,000.00
150,000.00
75,000.00
50,000.00
75,000.00
150,000.00
150,000.00
50,000.00
22,400.00
21,296.00
35,342.00
44,922.00
43,364.00
58,232.00
43,364.00
46,358.00
55,343.00
29,948.00
55,343.00
29,948.00
26,114.00
56,674.00
54,571.00
27,190.00
27,190.00
27,190.00
27,190.00
27,190.00
27,190.00
27,190.00
27,190.00
27,190.00
27,190.00
35,761.00
35,761.00
35,761.00
38,599.00
36,197.00
19,406.00
19,406.00
25,289.00
14,109.00
681,245.00
681,245.00
681,245.00
681,245.00
50,911.00
10,715.00
21,429.00
29,948.00
29,948.00
11,979.00
19,406.00
147,501.00
14,488.00
54,825.00
29,948.00
21,779.00
21,779.00
51,017.00
35,761.00
51,017.00
35,761.00
35,761.00
17,688.00
22,967.00
17,688.00
22,967.00
17,688.00
30,946.00
17,688.00
30,946.00
17,688.00
14,974.00
36,277.00
17,688.00
30,946.00
21,779.00
18,862.00
35,316.00
32,399.00
51,017.00
48,100.00
27,190.00
24,262.00
27,190.00
24,262.00
51,017.00
48,100.00
55,695.00
278,478.00
67,917.00
339,584.00
140,340.00
67,917.00
55,695.00
52,778.00
57,891.00
57,891.00
54,964.00
67,917.00
64,999.00
67,917.00
67,917.00
64,999.00
67,917.00
64,999.00
67,917.00
64,999.00
86,546.00
83,618.00
140,340.00
140,340.00
137,414.00
55,695.00
55,695.00
55,695.00
54,964.00
67,917.00
64,999.00
67,917.00
67,917.00
67,917.00
64,999.00
67,917.00
64,999.00
86,546.00
83,618.00
140,340.00
140,340.00
137,414.00
67,917.00
67,917.00
65,924.00
80,390.00
80,390.00
80,390.00
80,390.00
104,817.00
164,712.00
122,785.00
13,310.00
130,211.00
5,990.00
240,660.00
363,720.00
330,120.00
-
14,974.00
10,421.00
86,546.00
140,340.00
14,974.00
55,695.00
Kegiatan :
Pekerjaan :
Lokasi :
TA : 2017
HARGA
NO URAIAN SAT. SATUAN
SORT (Rp)
1 I. BAHAN DASAR
1 1 Abu Batu M3 ###
1 2 Abu Batu kg 220.00
1 3 Batu Bata 3 x 11 x 22 (20) Bh 1,000.00
1 Batu Bata 5 x 11 x 22 (20) Bh 1,150.00
1 4 Bata beton ringan (9x19x39) Bh 7,500.00
1 5 Batako Berlubang Hollow Blok HB-20 Bh 2,100.00
1 6 Batako Berlubang Hollow Blok HB-15 Bh 1,800.00
1 7 Batako Berlubang Hollow Blok HB-10 Bh 1,620.00
1 8 Batu belah M3 ###
1 9 Batu Blonos M3 ###
1 10 Batu pecah dg mesin (0,5-<1 cm) (Screening) M3 ###
1 11 Batu pecah dg mesin (1-2cm) M3 ###
1 12 Batu pecah dg mesin (2-3 cm) M3 ###
1 13 Batu pecah dg mesin (3-5 cm) M3 ###
1 14 Batu pecah dg tangan (5-7 cm) M3 ###
1 15 Batu pecah dg mesin (2/3 cm) per kg Kg 250.00 ###
1 16 Batu/Kerikil Pecah Tersaring M3 ###
1 17 Filler Kg 1,400.00
1 18 Kerikil Sungai M3 ###
1 19 Pasir M3 ###
1 20 Pasir (Harga pasir per kg) Kg 250.00
1 21 Pasir Urug M3 80,000.00
1 22 Pasir Beton M3 ###
1 23 PC Semen Abu - abu ( 50 Kg ) Kg 1,100.00
PC Semen Abu - abu ( 50 Kg ) zak 55,000.00
1 24 PC Semen Warna ( 40 Kg ) Kg 2,300.00
1 25 Mortar Perekat Hebel (40 kg) setara MU-380 zak ###
1 26 Sirtu M3 ###
1 27 Tanah Urug M3 70,000.00
1 28 Semen Grouting MU kg 3,150.00
1
1 II. PENUTUP ATAP
1 1 Asbes Gelombang (3,00x1,05)x4 mm (gelombang Lbr 97,000.00
1 2 Asbes Gelombang (2,70x1,05)x4 mm (gelombang Lbr 85,000.00
1 3 Asbes Gelombang (2,40x0,8)x4 mm (gelombang Lbr 60,250.00
1 4 Asbes Gelombang (2,10x0,8)x4 mm (gelombang Lbr 59,000.00
1 5 Asbes Gelombang (1,50x1,05)x4 mm (gelombang Lbr 41,650.00
1 6 Asbes Gelombang (2,50x0,92)x5 mm Lbr 92,200.00
1 7 Asbes Gelombang (2,25x0,92)x5 mm Lbr 83,100.00
1 8 Asbes Gelombang (2,00x0,92)x5 mm Lbr 71,900.00
1 9 Asbes Gelombang (1,80x0,92)x5 mm Lbr 58,600.00
1 10 Asbes Gelombang (2,40x1,08)x6 mm (gelombang Lbr 43,000.00
1 11 Asbes Gelombang (2,10x1,08)x6 mm (gelombang Lbr 41,100.00
1 12 Asbes Gelombang (1,80x1,08)x6 mm (gelombang Lbr 85,000.00
1 13 Asbes Gelombang (2,40x0,8)x3,5 mm (gelomban Lbr 50,000.00
1 14 Asbes Gelombang (2,10x0,8)x3,5 mm (gelomban Lbr 44,000.00
1 15 Asbes Gelombang (1,80x0,8)x3,5 mm (gelomban Lbr 37,000.00
1 16 Bubungan Asbes gelombang besar m' 65,000.00
1 17 Bubungan Asbes gelombang kecil m' 33,000.00
1 18 Bubungan Genteng keramik "KIA" Bh 10,700.00
1 19 Bubungan Genteng Morando Bh 8,800.00
1 20 Bubungan genteng pres jtw isi 4/m Bh 6,500.00
1 21 Bubungan genteng pres kebumen Bh 5,400.00
1 22 Bubungan genteng kodok Bh -
1 23 Bubungan genteng kodok glazur Bh -
1 24 Bubungan genteng plentong Bh -
1 25 Bubungan genteng plentong super / besar Bh -
1 26 Nok Genteng Beton Bh 7,500.00
1 27 Nok Genteng Metal polos bh 27,000.00
Nok Genteng Metal pasir bh 30,000.00
Nok Genteng galvalum bh 27,000.00
1 28 Genteng Keramik Glazur KIA isi 15/m2 warna m Bh 7,000.00
1 29 Genteng Keramik Glazur KIA isi 14/m2 warna tu Bh 6,850.00
1 30 Genteng Morando Glazur isi 20/m2 1550x20 Bh 4,550.00
1 31 Genteng Pres Jatiwangi isi 25/m2 750x25 Bh 2,400.00
1 32 Genteng Pres Kebumen Bh 2,650.00
1 33 Genteng Morando Natural isi 20/m2 oven 950x2 Bh 3,100.00
1 34 Genteng plentong Bh 2,150.00
1 35 Genteng plentong super Bh 2,500.00
1 36 Genteng kodok Bh 2,850.00
1 37 Genteng kodok glazur Bh 3,350.00
1 38 Genteng asbes Lbr 31,100.00
1 39 Genteng Beton bh 4,350.00
1 40 Genteng Beton Warna bh 6,550.00
1 41 Genteng Metal bh 44,500.00
1 42 Atap Sirap bh 1,400.00
1 42 Klem Wuwungan Bh 7,500.00
1 43 Glass Block Bh 20,500.00
1 44 Seng BJLS 30, Uk. 180 cm M' 50,100.00
1 45 Seng BJLS 20, Uk. 180 cm Lbr 41,350.00
1 46 Seng plat 3' x 6' ( 90 cm x 180 cm ) bjls 24 M' 34,000.00
1 47 Seng plat 3' x 6' ( 90 cm x 180 cm ) bjls 28 Lbr 43,750.00
1 48 Seng Plat BJLS 20 M2 22,850.00
1 49 Seng Plat BJLS 30 M3 33,650.00
1 50 Seng BJLS 20, uk 90 cm M' 25,000.00 #REF!
1 51 Galvalum Gelombang m2 58,200.00
1 52 Nok Galvalum bh 33,540.00
1 53 Aluminium foil m2 8,250.00
1 Genteng Bitumen Bergelombang Uk. 200 x 95 x Lbr ###
1 Genteng Bitumen Bergelombang Uk. 106 x 40 x 0 Lbr 50,500.00
1 Nok Bitumen (ex. Onduline) Bh 88,000.00
1
1 III. BAHAN KAYU
1 1 Bambu Btg 22,000.00
1 2 Kayu Bakar M3 ###
1 3 Kayu bengkir 6/14 cm M3 ###
1 4 Kayu bengkir 6/12 cm M3 ### 0.02
1 5 Kayu bengkir 5/10 cm M3 ### 41.67
1 6 Kayu Bengkir 5/7 cm M3 ### ###
1 7 Kayu Bengkir 8/12 cm M3 ###
1 8 Kayu Bengkir 4/6 cm M3 ###
1 9 Kayu Bengkir 3/4 cm M3 ###
1 10 Kayu Bengkir 2/ 3 cm M3 ###
1 11 Kayu Bengkir 3/20 cm M3 ###
1 12 Kayu Bengkir 10/20 cm M3 ###
1 13 Kayu Papan bengkirai 2x20x400 M3 ###
1 14 Kayu Papan jati M3 ###
1 15 Kayu Jati 8/20 cm (perum) M3 ###
1 16 Kayu Jati 3/20 cm (perum) M3 ###
1 17 Kayu Jati 6/14 cm (perum) M3 ###
1 18 Kayu Jati 5/7 cm (perum) M3 ###
1 19 Kayu Jati 2/3 cm (perum) M3 ###
1 20 Kayu Jati 8/20 cm (rakyat) M3 ###
1 21 Kayu Jati 3/20 cm (rakyat) M3 ###
1 22 Kayu Jati 6/14 cm (rakyat) M3 ###
1 23 Kayu Jati 5/7 cm (rakyat) M3 ###
1 24 Kayu Jati 2/3 cm (rakyat) M3 ###
1 25 Kayu Papan kempas M3 ###
1 26 Kayu Kempas 8/12 M3 ###
1 27 Kayu Kempas 6/12 M3 ###
1 28 Kayu Kempas 3/20 M3 ###
1 29 Kayu Kempas 5/7 M3 ###
1 30 Kayu Kempas 4/6 M3 ###
1 31 Kayu Kempas 3/5 M3 ###
1 32 Kayu Kempas 3/4 M3 ###
1 33 Kayu Kempas 2/3 M3 ###
1 34 Kayu Meranti 5/7 M3 ###
1 35 Kayu Meranti 4/6 M3 ###
1 36 Kayu Meranti 3/5 M3 ###
1 37 Kayu Meranti 2/3 M3 ###
1 38 Kayu Papan kruing M3 ###
1 39 Kayu Kruing 8/12 M3 ### 0.03
1 40 Kayu Kruing 6/12 M3 ### 31.85
1 41 Kayu Kruing 5/10 M3 ### ###
1 42 Kayu Kruing 3/20 M3 ###
1 43 Kayu Kruing 5/7 M3 ###
1 44 Kayu Kruing 4/6 M3 ###
1 45 Kayu Kruing 3/5 M3 ###
1 46 Kayu Kruing 3/4 M3 ###
1 47 Kayu Kruing 2/3 M3 ###
1 48 Kayu Papan Cetak Pinus M3 ###
1 49 Kayu Stoot ( bambu ) 5 mtr Btg 17,500.00
1 50 Kayu Lokal 5/7 M3 ###
1 51 Kayu Lokal 4/6 M3 ###
1 52 Kayu Lokal 2/3 M3 ###
1 53 Kayu Lokal Papan M3 ###
1 54 Dolken kayu lokal M3 ### 0.03
1 55 Dolken Kayu 8-10/400 cm Btg 22,000.00
1
1 IV. BAHAN PENUTUP DINDING / LANTAI
1 1 Batu Tempel Sukabumi hijau M2 ###
1 2 Batu Tempel Palimanan kuning M2 ###
1 3 Batu Tempel ( Tidak Beraturan ) kecil M2 ###
1 4 Batu Tempel ( Tidak Beraturan ) besar M2 ###
1 5 Batu Candi 20/20, 5/20 M2 ###
1 6 Batu Susun sirih Andesit (Jabar) 3x30x1,3 cm M2 ###
1 7 Batu Susun sirih Templek M2 ###
1 8 Batu Andesit (Candi Jawa Barat) 15x30cm Baka M2 ###
1 9 Batu Andesit (Candi Jawa Barat) 15x30cm Mesi M2 ###
1 10 Batu Candi 20/40 M2 ###
1 11 Batu Candi 15/30 M2 ###
1 12 Granit Uk. 40 x 40 cm M2 ###
1 13 Granit Uk. 40 x 40 cm 6bh / duz buah 28,250.00
1 14 Granit Uk. 30 x 30 cm M2 ###
1 15 Granit Uk. 30 x 30 cm buah 11,400.00
1 16 Granit uk. 60 x 60 cm (kw 1) M2 ###
1 17 Granit uk. 60 x 60 cm (kw 1) 3bh / duz buah 60,000.00
Granit uk. 60 x 60 cm (kw 2) M2 ###
Granit uk. 60 x 60 cm (kw 2) 3bh / duz buah 37,000.00
1 18 Plint Granit 10 x 30 cm buah 3,850.00
1 19 Plint Granit 10 x 40 cm buah 4,400.00
1 21 Plint Granit 10 x 60 cm buah 15,000.00
1 22 Keramik 20/25, putih M2 53,100.00
1 23 Keramik 20/25, warna M2 54,600.00
1 24 Keramik 20/25, warna (bisa untuk dinding) buah 2,750.00
1 25 Keramik 20/20, anti slip ( u/.lantai Km/wc) M2 54,600.00
1 26 Keramik 20/20, anti slip ( u/.lantai Km/wc) buah 2,200.00
1 27 Keramik 20/20, warna M2 53,750.00
1 28 Keramik 20/20, warna (bisa untuk dinding) buah 2,150.00
1 29 Keramik 10/20, warna M2 55,000.00
1 30 Keramik 10/20, warna buah 1,100.00
1 31 Keramik 30/30 (putih polos) M2 48,000.00
1 32 Keramik 30/30 (putih polos) buah 4,400.00
1 33 Keramik 30/30, warna M2 51,500.00
1 34 Keramik 40/40, (putih polos) M2 52,200.00
1 35 Keramik 40/40, (putih polos) buah 8,700.00
1 36 Keramik 40/40, warna M2 56,200.00
1 37 Keramik 40/40, Anti Slip M2 60,200.00
1 38 Keramik Uk. 5 x 20 cm Plint Bh 3,500.00
1 39 Keramik Uk. 10 x 20 cm Plint Bh 5,000.00
1 40 Keramik Uk. 10 x 30 cm Plint Bh 16,000.00
1 41 Keramik Uk. 10 x 40 cm Plint Bh 15,000.00
1 42 Keramik Anti Slip 30x30 M2 56,600.00
1 43 Keramik lis Uk. 7 x 20 Bh 4,150.00
1 44 Keramik lis Uk. 7 x 30 Bh 13,500.00
1 45 Keramik lis Uk. 13 x 40 Bh 10,000.00
1 46 Keramik kuku macan M' 8,500.00
1 47 Wallpaper m2 64,800.00
1 48 Parquet Kayu Jati Lokal KW 1 uk. 1.2 x 5 x 20 c m2 ###
1 49 Marmer 100 cm x 100 cm m2 ###
1
1 V. BAHAN CETAK
1 1 Buis Beton 1/2 dia 20 cm m' 38,000.00
1 2 Buis Beton 1/2 dia 30 cm m' 45,000.00
1 3 Buis Beton Ø 20 cm m' 50,000.00
1 4 Buis Beton Ø 30 cm m' 66,250.00
1 5 Buis Beton Ø 40 cm m' ###
1 6 Buis Beton Ø 50 cm m' ###
1 7 Buis Beton Ø 60 cm m' ###
1 8 Buis Beton Ø 80 cm m' ###
1 9 Paving Block tebal 6 cm abu - abu K175 (Sekela M2 95,000.00
1 10 Paving Block tebal 6 cm warna K175 (Sekelas M M2 ###
1 11 Paving Block tebal 8 cm abu - abu K175 (Sekela M2 ###
1 12 Paving Block tebal 8 cm warna K175 (Sekelas M M2 ###
1 13 Paving Block tebal 6 cm abu - abu lokal M2 75,000.00
1 14 Paving Block tebal 6 cm warna lokal M2 85,000.00
1 15 Grass Block 40 x 40 x 8 m2 ###
1 16 Rooster bata Bh 14,200.00
1 17 Kansteen beton 10.20.50 Bh 15,000.00
1 18 Kansteen beton 8.10.25.50 Bh 22,500.00
1 19 Kansteen beton 8.15.30.50 Bh 26,500.00
1 20 Kansteen beton 8.15.30.50 Bh 26,500.00
1 21 Kansteen beton taman Bh 25,500.00
U-Ditch (Kapasitas Gandar < 5 Ton)
22 U 300 x 300 x 1200 mm . 5 cm Bh ###
23 U 300 x 400 x 1200 mm . 5 cm Bh ###
24 U 300 x 500 x 1200 mm . 5 cm Bh ###
25 U 400 x 400 x 1200 mm . 6 cm Bh ###
26 U 400 x 500 x 1200 mm . 6 cm Bh ###
27 U 400 x 600 x 1200 mm . 6 cm Bh ###
28 U 500 x 500 x 1200 mm . 6 cm Bh ###
29 U 500 x 600 x 1200 mm . 6 cm Bh ###
30 U 500 x 700 x 1200 mm . 6 cm Bh ###
31 U 600 x 600 x 1200 mm . 8 cm Bh ###
Cover / Tutup U-Ditch
44 CU 300 x 1200 x 60 mm Bh ###
45 CU 400 x 1200 x 80 mm Bh ###
46 CU 500 x 1200 x 80 mm Bh ###
47 CU 500 x 1200 x 100 mm Bh ###
48 CU 600 x 1200 x 80 mm Bh ###
49 CU 600 x 1200 x 100 mm Bh ###
DAFTAR HARG
Wilayah Bawah ; Kec. Slawi, Dukuhwaru, Lebaksiu, Talan
Dukuhturi, Pagerbarang, Kedungbanteng, Krama
Kegiatan :
Pekerjaan :
Lokasi :
TA :
NO URAIAN
I. BAHAN DASAR
1 Abu Batu
2 Abu Batu
3 Batu Bata 3 x 11 x 22 (20)
Batu Bata 5 x 11 x 22 (20)
4 Bata beton ringan (9x19x39)
5 Batako Berlubang Hollow Blok HB-20
6 Batako Berlubang Hollow Blok HB-15
7 Batako Berlubang Hollow Blok HB-10
8 Batu belah
9 Batu Blonos
10 Batu pecah dg mesin (0,5-<1 cm) (Screenin
11 Batu pecah dg mesin (1-2cm)
12 Batu pecah dg mesin (2-3 cm)
13 Batu pecah dg mesin (3-5 cm)
14 Batu pecah dg tangan (5-7 cm)
15 Batu pecah dg mesin (2/3 cm) per kg
16 Batu/Kerikil Pecah Tersaring
17 Filler
18 Kerikil Sungai
19 Pasir
20 Pasir (Harga pasir per kg)
21 Pasir Urug
22 Pasir Beton
23 PC Semen Abu - abu ( 50 Kg )
PC Semen Abu - abu ( 50 Kg )
24 PC Semen Warna ( 40 Kg )
25 Mortar Perekat Hebel (40 kg) setara MU-380
26 Sirtu
27 Tanah Urug
28 Semen Grouting MU
II. PENUTUP ATAP
1 Asbes Gelombang (3,00x1,05)x4 mm (gelom
2 Asbes Gelombang (2,70x1,05)x4 mm (gelom
3 Asbes Gelombang (2,40x0,8)x4 mm (gelom
4 Asbes Gelombang (2,10x0,8)x4 mm (gelom
5 Asbes Gelombang (1,50x1,05)x4 mm (gelom
6 Asbes Gelombang (2,50x0,92)x5 mm
7 Asbes Gelombang (2,25x0,92)x5 mm
8 Asbes Gelombang (2,00x0,92)x5 mm
9 Asbes Gelombang (1,80x0,92)x5 mm
10 Asbes Gelombang (2,40x1,08)x6 mm (gelom
11 Asbes Gelombang (2,10x1,08)x6 mm (gelom
12 Asbes Gelombang (1,80x1,08)x6 mm (gelom
13 Asbes Gelombang (2,40x0,8)x3,5 mm (gelo
14 Asbes Gelombang (2,10x0,8)x3,5 mm (gelo
15 Asbes Gelombang (1,80x0,8)x3,5 mm (gelo
16 Bubungan Asbes gelombang besar
17 Bubungan Asbes gelombang kecil
18 Bubungan Genteng keramik "KIA"
19 Bubungan Genteng Morando
20 Bubungan genteng pres jtw isi 4/m
21 Bubungan genteng pres kebumen
22 Bubungan genteng kodok
23 Bubungan genteng kodok glazur
24 Bubungan genteng plentong
25 Bubungan genteng plentong super / besar
26 Nok Genteng Beton
27 Nok Genteng Metal polos
Nok Genteng Metal pasir
Nok Genteng galvalum
28 Genteng Keramik Glazur KIA isi 15/m2 warn
29 Genteng Keramik Glazur KIA isi 14/m2 warn
30 Genteng Morando Glazur isi 20/m2 1550x20
31 Genteng Pres Jatiwangi isi 25/m2 750x25
32 Genteng Pres Kebumen
33 Genteng Morando Natural isi 20/m2 oven 95
34 Genteng plentong
35 Genteng plentong super
36 Genteng kodok
37 Genteng kodok glazur
38 Genteng asbes
39 Genteng Beton
40 Genteng Beton Warna
41 Genteng Metal
42 Atap Sirap
42 Klem Wuwungan
43 Glass Block
44 Seng BJLS 30, Uk. 180 cm
45 Seng BJLS 20, Uk. 180 cm
46 Seng plat 3' x 6' ( 90 cm x 180 cm ) bjls 24
47 Seng plat 3' x 6' ( 90 cm x 180 cm ) bjls 28
48 Seng Plat BJLS 20
49 Seng Plat BJLS 30
50 Seng BJLS 20, uk 90 cm
51 Galvalum Gelombang
52 Nok Galvalum
53 Aluminium foil
Genteng Bitumen Bergelombang Uk. 200 x
Genteng Bitumen Bergelombang Uk. 106 x
Nok Bitumen (ex. Onduline)
V. BAHAN CETAK
1 Buis Beton 1/2 dia 20 cm
2 Buis Beton 1/2 dia 30 cm
3 Buis Beton Ø 20 cm
4 Buis Beton Ø 30 cm
5 Buis Beton Ø 40 cm
6 Buis Beton Ø 50 cm
7 Buis Beton Ø 60 cm
8 Buis Beton Ø 80 cm
9 Paving Block tebal 6 cm abu - abu K175 (Se
10 Paving Block tebal 6 cm warna K175 (Sekel
11 Paving Block tebal 8 cm abu - abu K175 (Se
12 Paving Block tebal 8 cm warna K175 (Sekel
13 Paving Block tebal 6 cm abu - abu lokal
14 Paving Block tebal 6 cm warna lokal
15 Grass Block 40 x 40 x 8
16 Rooster bata
17 Kansteen beton 10.20.50
18 Kansteen beton 8.10.25.50
19 Kansteen beton 8.15.30.50
20 Kansteen beton 8.15.30.50
21 Kansteen beton taman
U-Ditch (Kapasitas Gandar < 5 Ton)
22 U 300 x 300 x 1200 mm . 5 cm
23 U 300 x 400 x 1200 mm . 5 cm
24 U 300 x 500 x 1200 mm . 5 cm
25 U 400 x 400 x 1200 mm . 6 cm
26 U 400 x 500 x 1200 mm . 6 cm
27 U 400 x 600 x 1200 mm . 6 cm
28 U 500 x 500 x 1200 mm . 6 cm
29 U 500 x 600 x 1200 mm . 6 cm
30 U 500 x 700 x 1200 mm . 6 cm
31 U 600 x 600 x 1200 mm . 8 cm
Cover / Tutup U-Ditch
44 CU 300 x 1200 x 60 mm
45 CU 400 x 1200 x 80 mm
46 CU 500 x 1200 x 80 mm
47 CU 500 x 1200 x 100 mm
48 CU 600 x 1200 x 80 mm
49 CU 600 x 1200 x 100 mm
X. BAHAN KACA
1 Kaca patri
2 Kaca bening 5 mm
3 Kaca ryban 5 mm
4 Kaca Es
5 Kaca Bening 12 mm
6 Kaca Buram 12 mm
7 Kaca Cermin tebal 5mm
8 Kaca one way
9 Kaca tebal 3 mm
10 Profil Kaca
CATATAN :
- Harga belum termasuk keuntungan
pemborong dan PPN10% KEPALA DINAS PERUM
RAKYAT, KAWASAN PERMUKIMAN, TATA RUANG DAN PERTANAHAN
2023
M3 135.000,-
kg 220.00
3 x 11 x 22 (20) Bh 1,000.00
5 x 11 x 22 (20) Bh 1,150.00
n ringan (9x19x39) Bh 7,500.00
rlubang Hollow Blok HB-20 Bh 2,100.00
rlubang Hollow Blok HB-15 Bh 1,800.00
rlubang Hollow Blok HB-10 Bh 1,620.00
M3 265,000.00
M3 225,000.00
h dg mesin (0,5-<1 cm) (Screening) M3 305,500.00
h dg mesin (1-2cm) M3 305,500.00
h dg mesin (2-3 cm) M3 305,500.00
h dg mesin (3-5 cm) M3 305,500.00
h dg tangan (5-7 cm) M3 250,000.00
h dg mesin (2/3 cm) per kg Kg 250.00
il Pecah Tersaring M3 423,000.00
Kg 1,400.00
M3 170,000.00
M3 225,000.00
ga pasir per kg) Kg 250.00
M3 150,000.00
M3 305,500.00
n Abu - abu ( 50 Kg ) Kg 1,500.00
n Abu - abu ( 50 Kg ) zak 55,000.00
n Warna ( 40 Kg ) Kg 2,300.00
rekat Hebel (40 kg) setara MU-380 zak 122,500.00
M3 136,000.00
M3 70,000.00
kg 3,150.00
ombang (3,00x1,05)x4 mm (gelombang Lbr 97,000.00
ombang (2,70x1,05)x4 mm (gelombang Lbr 85,000.00
ombang (2,40x0,8)x4 mm (gelombang Lbr 60,250.00
ombang (2,10x0,8)x4 mm (gelombang Lbr 59,000.00
ombang (1,50x1,05)x4 mm (gelombang Lbr 41,650.00
ombang (2,50x0,92)x5 mm Lbr 92,200.00
ombang (2,25x0,92)x5 mm Lbr 83,100.00
ombang (2,00x0,92)x5 mm Lbr 71,900.00
ombang (1,80x0,92)x5 mm Lbr 58,600.00
ombang (2,40x1,08)x6 mm (gelombang Lbr 43,000.00
ombang (2,10x1,08)x6 mm (gelombang Lbr 41,100.00
ombang (1,80x1,08)x6 mm (gelombang Lbr 85,000.00
ombang (2,40x0,8)x3,5 mm (gelomban Lbr 50,000.00
ombang (2,10x0,8)x3,5 mm (gelomban Lbr 44,000.00
ombang (1,80x0,8)x3,5 mm (gelomban Lbr 37,000.00
Asbes gelombang besar m' 65,000.00
Asbes gelombang kecil m' 33,000.00
Genteng keramik "KIA" Bh 10,700.00
Genteng Morando Bh 8,800.00
genteng pres jtw isi 4/m Bh 6,500.00
genteng pres kebumen Bh 5,400.00
genteng kodok Bh -
genteng kodok glazur Bh -
genteng plentong Bh -
genteng plentong super / besar Bh -
Bh 7,500.00
eng Metal polos bh 27,000.00
eng Metal pasir bh 30,000.00
eng galvalum bh 27,000.00
Keramik Glazur KIA isi 15/m2 warna m Bh 7,000.00
Keramik Glazur KIA isi 14/m2 warna tu Bh 6,850.00
Morando Glazur isi 20/m2 1550x20 Bh 4,550.00
Pres Jatiwangi isi 25/m2 750x25 Bh 2,400.00
Pres Kebumen Bh 2,650.00
Morando Natural isi 20/m2 oven 950x2 Bh 3,100.00
Bh 2,150.00
lentong super Bh 2,500.00
Bh 2,850.00
Bh 3,350.00
Lbr 31,100.00
bh 4,350.00
Beton Warna bh 6,550.00
bh 44,500.00
bh 1,400.00
Bh 7,500.00
Bh 20,500.00
S 30, Uk. 180 cm M' 50,100.00
S 20, Uk. 180 cm Lbr 41,350.00
3' x 6' ( 90 cm x 180 cm ) bjls 24 M' 34,000.00
3' x 6' ( 90 cm x 180 cm ) bjls 28 Lbr 43,750.00
M2 22,850.00
M3 33,650.00
S 20, uk 90 cm M' 25,000.00
m2 58,200.00
bh 33,540.00
m2 8,250.00
Bitumen Bergelombang Uk. 200 x 95 x Lbr 164,500.00
Bitumen Bergelombang Uk. 106 x 40 x 0 Lbr 50,500.00
en (ex. Onduline) Bh 88,000.00
Btg 22,000.00
M3 225,000.00
M3 11,954,800.00
M3 13,300,000.00
M3 9,240,000.00
M3 10,000,000.00
M3 10,158,400.00
M3 8,000,000.00
M3 8,000,000.00
M3 8,000,000.00
M3 12,133,400.00
gkir 10/20 cm M3 12,050,000.00
an bengkirai 2x20x400 M3 12,133,400.00
M3 10,826,400.00
8/20 cm (perum) M3 10,775,200.00
3/20 cm (perum) M3 10,540,400.00
6/14 cm (perum) M3 10,540,400.00
5/7 cm (perum) M3 10,540,400.00
2/3 cm (perum) M3 10,540,400.00
8/20 cm (rakyat) M3 10,540,400.00
3/20 cm (rakyat) M3 6,592,550.00
6/14 cm (rakyat) M3 6,885,500.00
5/7 cm (rakyat) M3 6,032,000.00
2/3 cm (rakyat) M3 6,095,000.00
M3 5,750,000.00
M3 5,512,300.00
M3 5,258,400.00
M3 6,246,700.00
M3 4,354,300.00
M3 4,072,400.00
M3 5,100,000.00
M3 5,100,000.00
M3 3,538,900.00
M3 3,110,000.00
M3 2,940,000.00
M3 3,025,000.00
M3 2,940,000.00
M3 6,900,000.00
M3 6,600,000.00
M3 6,900,000.00
M3 5,700,000.00
M3 8,300,000.00
M3 4,730,000.00
M3 4,470,000.00
M3 5,575,000.00
M3 5,575,000.00
M3 4,470,000.00
an Cetak Pinus M3 2,800,000.00
t ( bambu ) 5 mtr Btg 17,500.00
M3 2,200,000.00
M3 2,200,000.00
M3 2,672,200.00
M3 2,400,000.00
M3 1,540,000.00
yu 8-10/400 cm Btg 22,000.00
1200 x 60 mm Bh 156,000.00
1200 x 80 mm Bh 235,000.00
1200 x 80 mm Bh 270,000.00
1200 x 100 mm Bh 325,000.00
1200 x 80 mm Bh 220,000.00
1200 x 100 mm Bh 400,000.00
LANGIT - LANGIT
t tebal 6 mm (1,00 x 1,00) Lbr 18,500.00
M2 49,000.00
1 m2 t = 4 mm GRC m2 20,000.00
flex) 1 x 1 m2, t = 5 mm m2 16,500.00
k. 1,2 x 2,4 tebal 9mm Lbr 60,000.00
k. 1,2 x 2,4 tebal 9mm (Lapis allumuniu Lbr 75,000.00
Lbr 146,080.00
m' 19,400.00
M' 7,900.00
M' 4,600.00
0,9 x 2,1 t = 3 mm Lbr 154,000.00
0,9 x 2,1 t = 4 mm Lbr 159,500.00
1,9 x 2,4 t = 3 mm Lbr 180,000.00
x 2.4 tbl = 3 mm Lbr 75,000.00
x 2.4 tbl = 4 mm Lbr 85,000.00
x 2.4 tbl = 6 mm Lbr 110,000.00
x 2.4 tbl = 9 mm Lbr 145,000.00
x 2.1 uk pintu tbl 4 mm Lbr 85,000.00
x 2.1 uk pintu tbl 3 mm Lbr 50,000.00
FINISHING
Lbr 4,400.00
eritage alami Ltr 45,000.00
Kg 35,000.00
Kg 20,000.00
Kg 23,000.00
Kg 60,000.00
Kg 60,000.00
Kg 25,000.00
ok (setara Catylac) Kg 40,000.00
Kg 50,000.00
Kg 55,000.00
Kg 31,000.00
Bh 8,900.00
Bh 6,000.00
Kg 16,000.00
Kg 40,000.00
Kg 14,200.00
Kg 13,000.00
kat Wallpaper Kg 23,000.00
Kg 5,000.00
Kg 5,000.00
Ltr 60,000.00
Kg 24,100.00
Kg 25,350.00
Ltr 19,100.00
Ltr 56,000.00
Kg 56,000.00
Ltr 60,000.00
Bh 27,000.00
Ltr 120,000.00
Kg 21,700.00
Bh 29,000.00
Ltr 58,400.00
Kg 21,700.00
Bh 29,000.00
Kg 23,500.00
Ltr 27,000.00
Ltr 55,000.00
M2 300,000.00
M 2
110,000.00
M2 125,000.00
M 2
85,000.00
M2 306,300.00
M2 298,000.00
min tebal 5mm M2 158,800.00
M2 490,100.00
M2 60,000.00
M' 3,000.00
INSTALASI LISTRIK
10 Watt Bh 12,100.00
15 Watt Bh 16,100.00
18 Watt Bh 18,700.00
20 Watt Bh 22,800.00
36 Watt Bh 24,100.00
40 Watt Bh 26,900.00
100 Watt Bh 6,600.00
160 Watt Bh 202,100.00
250 Watt Bh 188,600.00
250 Watt Bh 336,500.00
70 Watt Bh 417,700.00
150 Watt Bh 269,500.00
250 Watt Bh 363,800.00
400 Watt Bh 43,300.00
Bh 296,500.00
70 watt Bh 269,500.00
80 watt Bh 269,500.00
125 watt Bh 283,000.00
250 watt Bh 296,500.00
400 watt Bh 350,400.00
6-16 Ampere Bh 113,500.00
17-35 Ampere Bh 67,300.00
Lebih dari 63 Ampere Bh 80,800.00
outbow Bh 12,804,700.00
outbow Bh 20,150.00
In bow Bh 107,800.00
In bow Bh 1,900.00
In bow Bh 67,300.00
In bow Bh 47,100.00
outbow Bh 40,400.00
In bow Bh 20,150.00
Biasa / tanopa arde Bh 18,700.00
dengan arde Bh 4,000.00
Bh 16,100.00
Bh 13,400.00
Plafon Pak 13,400.00
Gantung Bh 8,600.00
NYM Uk. 2x2,5 mm Bh 4,550.00
NYM Uk. 2 x 4 mm m' 9,300.00
NYM Uk. 4 x 4 mm m' 20,100.00
NYY Uk. 3x2,5 mm m' 9,300.00
NYY Uk. 2x4 mm m' 14,700.00
NYY Uk. 3x4 mm m' 16,100.00
NYY Uk. 4x4 mm m' 21,500.00
NYY Uk. 4x6 mm m' 26,900.00
DX / Twisted m' 53,800.00
LVTC 2x70 +N.50 m' 14,700.00
LVTC 2x35 +N.50 m' 53,800.00
Bh 2,650.00
Bh 10,700.00
Bh 20,150.00
Bh 202,000.00
Bh 242,500.00
Bh 3,369,600.00
uminium Lipat P 8 meter Bh 5,391,400.00
Bh 175,150.00
Bh 2,021,800.00
njang 6 meter Æ 2 " tebal 3 mm Medi Bh 673,900.00
njang 6 meter Æ 2 " tebal 2 mm Med Bh 606,500.00
Bh 121,250.00
u Son 250 Watt Lengkap Bh 3,774,000.00
u Son 250 Watt Type SMR 511 Bh 1,010,900.00
Bh 606,500.00
u Caping LHE Bh 1,077,000.00
Bh 33,600.00
Bh 53,800.00
Bh 6,600.00
Bh 80,800.00
Bh 33,600.00
Bh 26,900.00
Bh 5,484,100.00
plastik besar m' 3,800.00
ambu komplit Set 127,900.00
Bh 33,600.00
Bh 1,213,000.00
Set 269,500.00
Bh 202,100.00
FGBY 4 x 4 mm2 4x4 mm2 Mtr 37,000.00
FGBY 4 x 50 mm2 CU 4x50 mm2 Mtr 271,600.00
FGBY 4 x 95 mm2 CU 4x95 mm2 Mtr 514,950.00
FGBY 4 x 150 mm2 CU 4x150 mm2 Mtr 798,500.00
Y 1X 150 mm2 1x150 mm2 Mtr 167,100.00
2XSEFGbY 20 KV, 3 X 15 3x150 mm2 Mtr 367,000.00
2XSY 20 KV, 1 X 240 mm21x240 mm2 Mtr 122,100.00
2XSEYBY 20 KV, 3 X 240 3x240 mm2 Mtr 421,700.00
2XSY 20 KV, 1 X 150 mm21x120 mm2 Mtr 100,700.00
2XSEYBY 20 KV, 3 X 300 3x300 mm2 Mtr 487,400.00
2XSY 20 KV, 1 X 70 mm2 1x95 mm2 Mtr 71,610.00
2XSEYBY 20 KV, 3 X 95 3x95 mm2 Mtr 259,390.00
2XS2Y 20 KV, 1 X 150 m 1x150 mm2 Mtr 100,700.00
2XS2Y 20 KV, 1 X 240 m 1x240 mm2 Mtr 122,000.00
2XS2Y 20 KV, 1 X 300 m 1x300 mm2 Mtr 135,500.00
A2XSY-T-3 X 240+50 mm23x240 mm2 Mtr 334,800.00
A Fleksibel 2,5 mm2 2,5 mm2 Mtr 2,400.00
A Fleksibel 4 mm2 4 mm2 Mtr 5,400.00
A Fleksibel 6 mm2 6 mm2 Mtr 7,950.00
A Fleksibel 10 mm2 10 mm2 Mtr 12,730.00
A Fleksibel 16 mm2 16 mm2 Mtr 13,050.00
C Ukuran 3 x 35 + N.25 Mtr 27,400.00
C Ukuran 3 x 70 + N.25 Mtr 39,100.00
SANITAIR
tainless steel Royal Bh 210,000.00
tainless steel Viega ( 1.00 x 0.90 ) m2 Bh 185,000.00
tainless steel 80 cm Bh 150,000.00
lass vol 30 ltr Bh 285,000.00
i fiber glass, vol 120 ltr sudut Bh 228,900.00
i fiber glass, vol 120 ltr kotak Bh 255,000.00
i fiber glass, vol 150 ltr Bh 300,000.00
i fiber glass, vol 1000 ltr Bh 875,000.00
on air fiber isi 500 Ltr Bh 1,000,000.00
on air fiber isi 1000 Ltr Bh 1,900,000.00
n / Saringan pembuang pada lantai K Bh 16,600.00
n / Saringan pembuang pada lantai KM Bh 30,000.00
duk / Monoblok "INA", Putih Bh 1,225,000.00
duk / Monoblok "INA", Warna Tua Bh 1,350,000.00
duk / Monoblok + pembilas otomatis "I Bh 1,700,000.00
Bh 290,000.00
gkok INA warna tua Bh 180,000.00
gkok INA warna muda Bh 160,000.00
Bh 18,600.00
Bh 18,900.00
bh 65,000.00
Bh 87,400.00
abun keramik Bh 29,800.00
Bh 350,000.00
Bh 300,000.00
Bh 87,400.00
abun keramik Bh 29,800.00
INA ) Standar Bh 350,000.00
Bh 300,000.00
NGIKAT KAYU
Kg 20,000.00
Bh 16,000.00
ng, Usuk, Plafond) Kg 20,000.00
bh 325.00
Kg 12,750.00
Kg 45,000.00
Bh 1,100.00
Kg 19,000.00
Bh 1,550.00
Bh 1,200.00
Kg 50,000.00
Kg 50,000.00
Kg 20,000.00
Kg 50,000.00
Ltr 26,500.00
Ltr 185.00
Kg 7,480.00
Kg 8,400.00
Set 45,000.00
Bh 25,000.00
strip uk. 30 x 30 Bh 1,180,000.00
strip uk. 20 x 20 Bh 850,000.00
M2 35,000.00
M2 27,000.00
Kg 40,000.00
M2 18,500.00
epoxy mortar Kg 26,900.00
M 2
15,200.00
Ltr 20,000.00
Ltr 17,000.00
Ltr 30,000.00
Ltr 9,650.00
Ltr 6,500.00
Ltr 5,950.00
Ltr 8,820.00
Ltr 7,717.50
Ltr 8,600.00
Tube 13,500.00
Kg 16,000.00
Kg 9,500.00
1 2 3 4 5
A. PEK. GALIAN DAN PONDASI
1 Pekerjaan Pembersihan Lahan Ls 100 m2
2 Pekerjaan Bouwplank Ls 49 m'
3 Galian Tanah Pondasi A.2.3.1.1 84.37 m3
4 Urug kembali tanah pondasi A.2.3.1.9 28.05 m3
5 Urug pasir bawah pondasi A.2.3.1.11 3.12 m3
6 Pasangan batu kosong (anstm) A.3.2.1.9 12.89 m3
7 Pasang pondasi batu kali 1 : 5 A.3.2.1.3 28.43 m3
B. PEKERJAAN PASANGAN
1 Pasangan 1/2 bata 1 : 5 A.4.4.1.10 144.23 m2
2 Pasangan 1/2 bata 1 : 3 A.4.4.1.8 8 m2
3 Plesteran 1 : 5 A.4.4.2.5 288.66 m2
4 Plesteran 1 : 3 A.4.4.2.3 16.25 m2
5 Pekerjaan Ubin 40 x 40 cm A.4.4.3.35 50 dus
6 Pek. Ubin KM 30 x 30 cm A.4.4.3.36 3 dus
7 Luas Gunung - gunung(1) 12.58 m2
8 Luas Gunung - gunung(2) 9 m2
C. PEKERJAAN BETON
1 Beton Sloof
Pek. Beton K125 A.4.1.1.2 2.9 kg
Pek. besi tulangan & sengkang A.4.1.1.17a 352 batang
Pekerjaan bekisting sloof A.4.1.1.21 19.28 kg
2 Beton Bertulang kolom Praktis
Pek. Beton K125 A.4.1.1.2 1.3 kg
Pek. besi tulangan & sengkang A.4.1.1.17a 78 batang
Pek. bekisting kolom praktis A.4.1.1.22a 35.52 kg
3 Beton Bertulang Ring Balok
Pek. Beton K125 A.4.1.1.2 2.9 kg
Pek. besi tulangan & sengkang A.4.1.1.17a 352 batang
Pek. bekisting ring balok A.4.1.1.23a 19.28 kg
4 Dak Beton Bertulang
Pek. Beton K125 1.8 m2
Pek. Tulangan V 15 batang
Pek. Tulangan H 14 batang
Pek. Bekisting dak beton 18 m2
D. PEKERJAAN KAYU
1 Pek. Kusen Pintu & jendela Kayu A.4.6.1.1 0.2634 m3
2 Pek. Daun Pintu Panel Kayu A.4.6.1.5 10.23 m2
3 Pek. Daun Jendela Kaca Kayu A.4.6.1.6 5 m2
E PEKERJAAN ATAP
1 Rangka Kuda2 Baja Ringan 64 m2
2 Penutup Atap Genting 64 m2
F PEKERJAAN RANGKA PLAFOND
1 Pek. Plafon 51 m2
2 Pas. Langit - Langit 18 lembar
3 Pas. List Gipsum 72.58 m2
G PEKERJAAN LISTRIK
1 Panjang Kabel Listrik 50 m'
2 Saklar Tunggal 6 buah
3 Fiting 8 buah
4 Lampu 8 buah
5 Stopkontak 5 buah
6 Saklar Ganda 1 buah
7 Kap Lampu 8 buah
8 Box MCB 1 buah
9 KWH meteran 1 buah
H PEKERJAAN PENGECATAN
1 Cat Dinding A.4.7.1.10 49 kg
2 Cat kusen kayu pintu & jendela A.4.7.1.4 0.2634 m3
3 Cat plitur daun pintu panel & jendela A.4.7.1.7 10.23 m3
I PEKERJAAN SANITASI
1 Pemasangan closet duduk A.5.1.1.1. 1 buah
2 Panjang Pipa A.5.1.1.2. 66 buah
3 Pemasangan wastafel A.5.1.1.5. 1 buah
4 Pemasangan Keran 2 buah
5 Pemasangan Septictank 1 buah
6 Pemasangan Sumur Resapan 1 buah
7 Pemasangan Meteran PDAM 1 buah
8 Pemasangan Bak Kontrol 2 buah
J Pas. ASESORIS
1 Cylinder 5 buah
2 Grendel 1 buah
3 Engsel 20 buah
4 Kait Angin 4 buah
5 Handle 12 buah
6 Window Lock 2 buah
7 Gorden 2 buah
8 Soap Dispenser 1 buah
9 Storage Box 2 buah
10 Rode Hook 1 buah
11 Tooth Brush Holder 1 buah
12 Toilet Paper Holder 1 buah
13 Floor Drain 1 buah
14 Bak Mandi 1 buah
15 Jet Washer 1 buah
16 Sikat Toilet 1 buah
17 Gayung 1 buah
JUMLAH 2,313.886
JUMLAH DIBULATKAN
TERBILANG
DAFTAR HARGA UPAH DAN BAHAN
TAHUN ANGGARAN 2023
PEKERJAAN TANAH
A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
Harga
No Uraian Satuan Koefisien Satuan
(Rp)
A TENAGA
Pekerja OH 0.750 90,000.00
Mandor OH 0.025 110,000.00
JUMLAH TENAGA KERJA
B BAHAN
D Jumlah (A+B+C)
E Overhead + Profit 15% 15% x D
F Harga Satuan Pekerjaan (D+E)
D Jumlah (A+B+C)
E Overhead + Profit 15% 15% x D
F Harga Satuan Pekerjaan (D+E)
67,500.00
2,750.00
70,250.00
70,250.00
10,537.50
80,787.50
22,500.00
2,750.00
25,250.00
25,250.00
3,787.50
29,037.50
Jumlah
Harga
(Rp)
27,000.00
1,100.00
28,100.00
180,000.00
180,000.00
208,100.00
31,215.00
239,315.00
### DAFTAR HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN 2023
Harga
No Kode Uraian Pekerjaan Satuan Satuan
(Rp.)
PEKERJAAN TANAH
1 A.2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 m m3 80,787.50
2 A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah m3 29,037.50
3 A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug m3 239,315.00
PEKERJAAN PONDASI
4 A.3.2.1.3 Pemasangan 1 m3 Pondasi Batu Belah campuran 1SP : 5PP m3 965,563.00
5 A.3.2.1.9 Pemasangan 1 m3 batu kosong (anstamping) m3 575,667.00
PEKERJAAN DINDING
6 A.4.4.1.8 Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1/2 Bata Camp. 1Pc : 3PP m2 129,945.98
7 A.4.4.1.10 Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1/2 Bata Camp. 1Pc : 5PP m2 123,634.20
PEKERJAAN PLESTERAN
8 A.4.4.2.3 Pemasangan 1m² plesteran 1 PC :3 PP tebal 15 mm m2 69,721.05
9 A.4.4.2.5 Pemasangan 1m² plesteran 1 PC :5 PP tebal 15 mm m2 66,237.70
PEKERJAAN PENUTUP LANTAI DAN DINDING
10 A.4.4.3.35 Pemasangan 1m² lantai keramik ukuran 40cm x 40cm m2 574,132.90
11 A.4.4.3.36 Pemasangan 1m² lantai keramik ukuran 30cm x 30cm (anti slip) m2 462,326.45
12 A.4.4.3.54.a Pemasangan 1m² dinding keramik 20 cm x 25 cm m2
PEKERJAAN BETON
13 A.4.1.1.2 Membuat 1 m3 Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 m3 6,707,649.57
14 A.4.1.1.17a Pembesian dengan besi polos atau besi ulir kg 13,363.29
15 A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof m2 125,459.25
16 A.4.1.1.22a Pemasangan 1 m2 bekisting untuk kolom m2 150,374.00
17 A.4.1.1.23a Pemasangan 1 m2 bekisting untuk balok m2 150,374.00
PEKERJAAN KAYU
18 A.4.6.1.1 Pembuatan dan Pemasangan 1 m ᶟ kusen pintu dan kusen jendela, kayu kelas I m3 17,116,781.13
19 A.4.6.1.5 Pembuatan dan pemasangan 1 m² daun pintu panel, kayu kelas I & II m2 1,001,627.00
20 A.4.6.1.6 Pembuatan dan pemasangan 1 m² pintu dan jendela kaca, kayu kelas I & II m2 699,531.20
PEKERJAAN ATAP
21 A.4.6.1.14c. Rangka kuda - kuda baja ringan m2 158,529.81
22 A.4.5.2.32 Penutup Atap Genteng Beton bh 123,719.88
PEKERJAAN PLAFON
23 Pekerjaan Plafon m2 200,000.00
24 Pemasangan langit - langit lembar 43,661.13
25 Pemasangan list plafon m' 45,821.18
PEKERJAAN PENGECATAN
21 A.4.7.1.4 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) m2 42,758.15
PEKERJAAN SANITASI
24 A.5.1.1.1. Pemasangan 1 buah closet duduk/monoblock buah 1,966,854.20
23 Pemasangan Septictank buah 11,653,536.39
25 A.5.1.1.5. Pemasangan 1 buah wastafel buah 1,483,621.90
UJI KOMPETENSI KEAHLIAN
PRODI DPIB SMK NEGERI 1 ADIWERNA
TAHUN PELAJARAN 2023-2024
HARGA
NO URAIAN PEKERJAAN ANAL VOL SAT
SATUAN (Rp) JUMLAH (Rp) JUMLAH SEMUA (Rp)
1 2 3 4 5 6 7 8
A. PEK. GALIAN DAN PONDASI 45,453,509.77
1 Pekerjaan Bouwplank Ls 49 m' Rp 45,000.00 Rp 2,205,000.00
2 Galian Tanah Pondasi A.2.3.1.1 84.37 m3 Rp 80,787.50 Rp 6,816,041.38
3 Urug kembali tanah pondasi A.2.3.1.9 28.05 m3 Rp 29,037.50 Rp 814,501.88
4 Urug pasir bawah pondasi A.2.3.1.11 3.12 m3 Rp 239,315.00 Rp 746,662.80
5 Pasangan batu kosong (anstm) A.3.2.1.9 12.89 m3 Rp 575,667.00 Rp 7,420,347.63
6 Pasang pondasi batu kali 1 : 5 A.3.2.1.3 28.43 m3 Rp 965,563.00 Rp 27,450,956.09
B. PEKERJAAN PASANGAN 69,234,337.61
1 Pasangan 1/2 bata 1 : 5 A.4.4.1.10 144.23 m2 Rp 123,634.20 17,831,760.67
2 Pasangan 1/2 bata 1 : 3 A.4.4.1.8 8 m2 Rp 129,945.98 1,055,811.05
3 Plesteran 1 : 5 A.4.4.2.5 288.66 m2 Rp 66,237.70 19,120,174.48
4 Plesteran 1 : 3 A.4.4.2.3 16.25 m2 Rp 69,721.05 1,132,967.06
5 Pekerjaan Ubin 40 x 40 cm A.4.4.3.35 50 dus Rp 574,132.90 28,706,645.00
6 Pek. Ubin dinding 30 x 30 cm (KM) A.4.4.3.36 3 dus Rp 462,326.45 1,386,979.35
C. PEKERJAAN BETON 68,733,752.34
1 Beton Sloof
Pek. Beton K125 2.9 kg Rp 6,707,649.57 19,452,183.76
Pek. besi tulangan 352 batang Rp 13,363.29 4,703,877.20
Pekerjaan bekisting sloof A.4.1.1.2 19.28 kg Rp 125,459.25 2,418,854.34
2 Beton Bertulang kolom Praktis A.4.1.1.17a
Pek. Beton K125 A.4.1.1.21 1.3 kg Rp 6,707,649.57 8,719,944.45
Pek. besi tulangan 78 batang Rp 13,363.29 1,042,336.43
Pek. bekisting kolom praktis A.4.1.1.2 35.52 kg Rp 150,374.00 5,341,284.48
3 Beton Bertulang Ring Balok A.4.1.1.17a
Pek. Beton K125 A.4.1.1.22a 2.9 kg Rp 6,707,649.57 19,452,183.76
Pek. besi tulangan 352 batang Rp 13,363.29 4,703,877.20
Pek. bekisting balok ring A.4.1.1.2 19.28 kg Rp 150,374.00 2,899,210.72
D. PEKERJAAN KAYU A.4.1.1.17a 17,926,878.82
1 Pek. Kusen Pintu & jendela ky jati A.4.1.1.23a 0.2634 m3 Rp 17,116,781.13 4,508,560.15
2 Pek. Daun Pintu Panel ky jati 10.23 m2 Rp 1,001,627.00 10,246,644.21
3 Pek. Daun Jendela Kaca ky jati 5 m2 Rp 699,531.20 3,171,674.46
E PEKERJAAN ATAP 18,015,137.08
1 Rangka Atap 64 m2 Rp 158,529.81 10,097,065.08
2 Penutup Atap 64 m2 Rp 123,719.88 7,918,072.00
F. PEKERJAAN RANGKA PLAFOND 14,311,601.22
1 Pek. Plafon A.4.6.1.1 51 m2 Rp 200,000.00 10,200,000.00
2 Pas. Langit - Langit A.4.6.1.5 18 lembar Rp 43,661.13 785,900.34
3 Pas. List Gipsum A.4.6.1.6 72.58 m2 Rp 45,821.18 3,325,700.88
G PEKERJAAN LISTRIK 615,000.00
1 Panjang Kabel Listrik 50 m' Rp 3,500.00 175,000.00
2 Saklar Tunggal 6 buah Rp 4,000.00 24,000.00
3 Fiting 8 buah Rp 4,000.00 32,000.00
4 Lampu 8 buah Rp 14,000.00 112,000.00
5 Stopkontak 5 buah Rp 4,000.00 20,000.00
6 Saklar Ganda 1 buah Rp 4,000.00 4,000.00
7 Kap Lampu 8 buah Rp 14,000.00 112,000.00
8 Box MCB 1 buah Rp 11,000.00 11,000.00
9 KWH meteran 1 buah Rp 125,000.00 125,000.00
I PEKERJAAN PENGECATAN 1,936,229.02
1 Cat Dinding 49 kg Rp 30,280.65 1,483,751.85
2 Cat kusen kayu pintu & jendela 0.2634 m3 Rp 57,180.30 15,061.29
3 Cat plitur daun pintu panel & jendela 10.23 m3 Rp 42,758.15 437,415.87
J PEKERJAAN SANITASI 24,661,012.49
1 Pemasangan closet duduk 1 buah Rp 1,966,854.20 1,966,854.20
2 Panjang Pipa 66 buah Rp 125,000.00 8,250,000.00
3 Pemasangan wastafel 1 buah Rp 1,483,621.90 1,483,621.90
4 Pemasangan Keran A.4.7.1.10 2 buah Rp 6,000.00 12,000.00
5 Pemasangan Septictank A.4.7.1.4 1 buah Rp 11,653,536.39 11,653,536.39
6 Pemasangan Meteran PDAM A.4.7.1.7 1 buah Rp 75,000.00 75,000.00
7 Pemasangan Bak Kontrol 2 buah Rp 610,000.00 1,220,000.00
K Pas. ASESORIS A.5.1.1.1. 1,551,600.00
1 Cylinder A.5.1.1.2. 5 buah Rp 50,960.00 254,800.00
2 Grendel A.5.1.1.5. 1 buah Rp 2,700.00 2,700.00
3 Engsel 20 buah Rp 8,450.00 169,000.00
4 Kait Angin 4 buah Rp 5,000.00 20,000.00
5 Handle 12 buah Rp 34,800.00 417,600.00
6 Window Lock 2 buah Rp 15,000.00 30,000.00
7 Gorden 2 buah Rp 180,000.00 360,000.00
8 Soap Dispenser 1 buah Rp 35,000.00 35,000.00
9 Storage Box 2 buah Rp 20,000.00 40,000.00
10 Rode Hook 1 buah Rp 39,000.00 39,000.00
11 Tooth Brush Holder 1 buah Rp 20,000.00 20,000.00
12 Toilet Paper Holder 1 buah Rp 8,000.00 8,000.00
13 Floor Drain 1 buah Rp 8,500.00 8,500.00
14 Bak Mandi 1 buah Rp 80,000.00 80,000.00
15 Jet Washer 1 buah Rp 56,000.00 56,000.00
16 Sikat Toilet 1 buah Rp 5,000.00 5,000.00
17 Gayung 1 buah Rp 6,000.00 6,000.00
JUMLAH 262,439,058.34
JUMLAH DIBULATKAN 262,439,000.00
REKAPITULASI RENCANA ANGGARAN BIAYA
BOBOT Prestasi Pekerjaan Bulan Lalu Prestasi Pekerjaan Bulan ini Prestasi Pekerjaan Komulatif
No Jenis Pekerjaan Analisa Volume Satuan Prestasi Rerata Prestasi Rerata Prestasi Rerata
(%)
1 2 3 4 5 6
A. PEK. GALIAN DAN PONDASI
1 Pekerjaan Bouwplank Ls 49.00 m' 0.840 0.840 0.840
2 Galian Tanah Pondasi A.2.3.1.1 84.37 m3 2.597 2.597 2.597
3 Urug kembali tanah pondasi A.2.3.1.9 28.05 m3 0.310 0.310 0.310
4 Urug pasir bawah pondasi A.2.3.1.11 3.12 m3 0.285 0.285 0.285
5 Pasangan batu kosong A.3.2.1.9 12.89 m3 2.827 2.827 2.827
6 Pasang pondasi batu kali 1 : 5 A.3.2.1.3 28.43 m3 10.460 10.460 10.460
B. PEKERJAAN PASANGAN
1 Pasangan 1/2 bata 1 : 5 A.4.4.1.10 144.23 m2 6.795
2 Pasangan 1/2 bata 1 : 3 A.4.4.1.8 8.13 m2 0.402 0.402 0.402
3 Plesteran 1 A.4.4.2.5 288.66 m2 7.286
4 Plesteran 1 : 3 A.4.4.2.3 16.25 m2 0.432
5 Pekerjaan Ubin 40 x 40 cm A.4.4.3.35 50.00 dus 10.938
6 Pek. Ubin KM 30 x 30 cm A.4.4.3.36 3.00 dus 0.528
C. PEKERJAAN BETON
1 Beton Sloof
- Pek. Beton K125 A.4.1.1.2 2.90 kg 7.412 7.412 7.412
- Pek. besi tulangan A.4.1.1.17a 352.00 batang 1.792 1.792 1.792
- Pekerjaan bekisting sloof A.4.1.1.21 19.28 kg 0.922 0.922 0.922
2 Beton Bertulang kolom Praktis
- Pek. Beton K125 A.4.1.1.2 1.30 kg 3.323 3.323 3.323
- Pek. besi tulangan A.4.1.1.17a 78.00 batang 0.397 0.397 0.397
- Pek. bekisting kolom praktis A.4.1.1.22a 35.52 kg 2.035 2.035 2.035
3 Beton Bertulang Ring Balok
- Pek. Beton K125 A.4.1.1.2 2.90 kg 7.412
- Pek. besi tulangan A.4.1.1.17a 352.00 batang 1.792
- Pek. bekisting balok ring A.4.1.1.23a 19.28 kg 1.105
D PEKERJAAN KAYU
1 Pek. Kusen Pintu & jendela ky jati A.4.6.1.1 0.26 m3 1.718
2 Pek. Daun Pintu Panel ky jati A.4.6.1.5 10.23 m2 3.904
3 Pek. Daun Jendela Kaca ky jati A.4.6.1.6 4.53 m2 1.209
E PEKERJAAN ATAP
1 Pas. Rangka Atap 63.69 m2 3.847
2 Pas. Penutup Atap 64.00 m2 3.017
F PEKERJAAN PLAFON
1 Pas. Plafon 51.00 m2 3.887
2 Pas. Langit - Langit 18.00 lembar 0.299
3 Pas. List Gipsum 72.58 m2 1.267
G PEKERJAAN LISTRIK
1 Panjang Kabel Listrik 50.00 m' 0.067
2 Saklar Tunggal 6.00 buah 0.009
3 Fiting 8.00 buah 0.012
4 Lampu 8.00 buah 0.043
5 Stopkontak 5.00 buah 0.008
6 Saklar Ganda 1.00 buah 0.002
7 Kap Lampu 8.00 buah 0.043
8 Box MCB 1.00 buah 0.004
9 KWH meteran 1.00 buah 0.048
H PEKERJAAN PENGECATAN
1 Cat Dinding A.4.7.1.10 49.00 kg 0.565
2 Cat kusen kayu pintu & jendela A.4.7.1.4 0.26 m3 0.006
3 Cat plitur daun pintu panel & jendela A.4.7.1.7 10.23 m3 0.167
I PEKERJAAN SANITASI
1 Pemasangan closet duduk A.5.1.1.1. 1.00 buah 0.749
2 Panjang Pipa A.5.1.1.2. 66.00 buah 3.144
3 Pemasangan wastafel A.5.1.1.5. 1.00 buah 0.565
4 Pemasangan Keran 2.00 buah 0.005
5 Pemasangan Septictank 1.00 buah 4.440
6 Pemasangan Meteran PDAM 1.00 buah 0.029
7 Pemasangan Bak Kontrol 2.00 buah 0.465
J PEMASANGAN ASESORIS
1 Cylinder 5.00 buah 0.097
2 Grendel 1.00 buah 0.001
3 Engsel 20.00 buah 0.064
4 Kait Angin 4.00 buah 0.008
5 Handle 12.00 buah 0.159
6 Window Lock 2.00 buah 0.011
7 Gorden 2.00 buah 0.137
8 Soap Dispenser 1.00 buah 0.013
9 Storage Box 2.00 buah 0.015
10 Rode Hook 1.00 buah 0.015
11 Tooth Brush Holder 1.00 buah 0.008
12 Toilet Paper Holder 1.00 buah 0.003
13 Floor Drain 1.00 buah 0.003
14 Bak Mandi 1.00 buah 0.030
15 Jet Washer 1.00 buah 0.021
16 Sikat Toilet 1.00 buah 0.002
17 Gayung 1.00 buah 0.002
JUMLAH 100 33.60 33.60
Jumlah Dana yang digunakan sampai dengan Bulan ini ( Bulan 1) Rp 88,179,524 Pencapaian 33.60%
LAPORAN BULANAN