Professional Documents
Culture Documents
Ohs MP
Ohs MP
DOCUMENT INFORMATION
Document Title Occupational, Health & Safety Management Plan
i
8.2. Visitor OHS Induction ______________________________________________ 15
8.3. Ongoing OHS Training and Awareness _____________________________ 15
8.4. Pre-job safety meeting and Tool box talks __________________________ 16
8.5. Specific training and competence ________________________________ 16
ii
19.1. Standards for OHS Management and Control ______________________ 33
19.2. Safe work practices _______________________________________________ 34
19.3. Stop Work ________________________________________________________ 34
19.4. Housekeeping ____________________________________________________ 35
19.5. Personal protective equipment (PPE) ______________________________ 36
19.6. Hand tools and equipment use and inspection _____________________ 38
19.7. Electrical safety ___________________________________________________40
19.8. Noise and Vibration _______________________________________________ 41
19.9. Working environment _____________________________________________ 42
19.10. Barricades, safety signs and labelling of equipment _____________ 43
19.11. Manual handling ______________________________________________ 44
19.12. Welding/ hot works ____________________________________________ 44
19.13. Stacking of Materials ___________________________________________46
19.14. Working at height and Fall Protection ___________________________ 47
19.15. Scaffolding ____________________________________________________ 49
19.16. Lifting operations and lifting equipment _________________________ 51
19.17. Hazardous Substances, Materials and Gases Management ______ 53
19.18. Permit to work _________________________________________________ 55
19.19. Lockout & Tag out (LOTO) and Commissioning __________________ 56
19.20. Confined space _______________________________________________ 59
19.21. Civil works, Formwork and support work _________________________ 60
19.22. Traffic Management Plan ______________________________________ 62
19.23. Medical and Health surveillance _______________________________ 63
iii
APPENDIX E: OHS OBSERVATION (OHSO) REPORT FORM ERROR! BOOKMARK
NOT DEFINED.
iv
v
1. INTRODUCTION
This Occupational Health and Safety Management Plan (OHSMP) forms part of the EPC
Contractor’s.This OHSMP will be resourced, implemented and maintained throughout the
project execution.
The OHSMP also provides the framework for personnel training and control measures for
monitoring the effectiveness of the OHSMP’s implementation.
The OHSMP, including all the appendices, is a live document that will be subject to periodic
review by the EPC Contractor’s HSE Manager and team to enable continued compliance
and suitability.
Full compliance with the Project’s OHS legal and contractual obligations
1
Occupational, Health & Safety Management Plan
3. PROJECT DETAILS
3.1. Location
Installation of Mast
2
Occupational, Health & Safety Management Plan
4. OHS POLICY
BarkoTel recognizes and is committed to its responsibility for the health, safety
and welfare of its employees, subcontractors, suppliers and the general
public. It will demonstrate through policy development that health and safety
receives priority attention on a continual basis. In order to deliver these
responsibilities Barkotel undertakes to
Maintain a safe and healthy place of work with safe access and egress;
Provide adequate welfare facilities;
Ensure that risk assessments are being carried out on an on-going basis
with employees participating in the risk assessment process.
Provide sufficient information, instruction, training and supervision to
enable employees to avoid hazards and to contribute positively to the
health and safety of themselves and others whilst at work;
Consult with employees on issues relating to OH&S;
Ensure access to competent health and safety advice;
Provide plant, equipment and systems of work which are safe and
without risks to health;
Ensure safe arrangements for the use, handling, storage and transport
of articles and substances;
Ensure compliance with all relevant safety legislation, regulations,
codes of practice and other requirements
Arrange for the effective planning, organization, control, monitoring
and review of preventative and protective measures.
3
Occupational, Health & Safety Management Plan
5. OHS MANAGEMENT
The OHS management system upon which this Plan has been based is the widely accepted
approach of the Plan- Do-Check-Act cycle for continual improvement. The PDCA
management cycle has been adopted and integrated into the framework of many
technical management systems. In addition, this OHSMP is structured enable compliance
with good industry standards and guidelines, the OHS requirements of the Developer, the
and OHSAS 18001.
To implement these OHS obligations the main sections of the OHSMP include and detail the
Project’s:
OHS Site Rules that are applicable to all personnel and activities;
OHS hazard identification and classification procedures that are the foundation for
the detailed OHS control measures for a range of typical construction related
activities;
4
Occupational, Health & Safety Management Plan
Number of Fatality Days after last Medical treatment case
Number of Lost days Lost time index rate
Number of Restricted days Reportable incidence index rate
First Aid cases Notices
Medical treatment cases Fines
Near miss incident Training plan vs. Actual
Property damages No of Inducted personnel
Unsafe act and Condition No of Induction training
Total number of Manpower Tool Box talks
worked Pre-job safety meeting
Manpower hours Inspection, tours and audits
Safe Manpower hrs HSE Committee meetings
Days after last accident/incident Mock Drills
0 fatalities
Reportable HSE incident rate (TRIR) of less than 0.5 per 200,00 manhours
Calculated as follows:
LTIR = No. of cases with lost workdays x 200.000/ (Manhours worked by employees, hours)
5
Occupational, Health & Safety Management Plan
5.2. OHS Site Rules
The following are the Project’s OHS rules and minimum requirements that all personnel are to
follow:
Employees shall not to work under the influence of drugs or alcohol which is a
disciplinary offence that leads to dismissal.
Use routine toolbox talks to review work, hazards and safe practices.
Work safely using common sense – think about how your actions may affect
others
Act upon safety notices and signs and follow site rules
Don’t walk by. Make unsafe situations safe if it’s safe for you to do so or barricade
and call a supervisor
Raise the alarm without delay. (Rather a false alarm than a slow alarm.)
6
Occupational, Health & Safety Management Plan
6. LEGAL & OTHER REQUIREMENTS
The EPC Contractor has identified applicable legal and other requirements and has
addressed them in this OHSMP. The legal and other requirements, include the following:
Law 4/1994, modified by law 9/2009 and amended by law 105/2015 and its
executive regulation, modified by the ministerial decrees; no. 1095/ 2011, no.
710/2012, and no. 964/201 and Annex 9 of Decree of the relevant executive
regulation modified by Decree 1095/2011;
OHSAS 18001.
7
Occupational, Health & Safety Management Plan
7. OHS ORGANIZATION & RESPONSIBILITIES
7.1. OHS Organizational management structure
The overall OHS organization and management structure for the projects is shown in the
organogram below
The EPC Contractor’s OHS resources shall include a dedicated on-site OHS Manager who will
have overall responsibility for all sites .
8
Occupational, Health & Safety Management Plan
7.3.1. Project Director
The overall implementation of OHS policy and OHMP to prevent injury, ill health
and enable compliance
Ensuring that adequate financial provisions are made available for the
implementation of the policy.
Undertaking regular site OHS tours and inspections and recording OHS
observations
Promoting the liaison on OHS matters between the EPC Contractor and all the
Project’s stakeholders
Arranging for regular meetings with the appropriate personnel to discuss OHS
management and performance and continual improvement plus chairing the
monthly OHS meeting.
Personally accountable for the timely closure of all actions relevant to OHSE
findings
All subcontractors pre-approval is based on OHSAS 18001 and passed the OHSE
review and approval process
Ensure that safety specifications are listed and available with the procurement
officer as a reference and incorporated in the procurement processes and
relevant procedures
Ensure that OHS Award and Disciplinary programs are budgeted, implemented,
monitored and reported
Planning all works in accordance with the OHSMP requirements and ensuring that
working methods are regularly examined to avoid and/or take account of
simultaneous operations and interfaces, establish if improvements or
modifications should be made.
9
Occupational, Health & Safety Management Plan
Ensuring the allocation of adequate OHS resources to cover working methods
and reasonable welfare facilities.
Ensure, so far as is reasonably practicable, that work, once started is carried out
as planned, and that accounts taken of changing or unforeseen conditions as
work proceeds and update the written assessments as necessary and is carried
out in accordance with the OHSMP
Ensuring that any design calculations for unusual scaffolds. working platforms and
lifts are independently checked.
Ensuring that Sub-Contractors undertake tool box talks and conduct internal
health and safety audits/inspections.
Ensuring that there is liaison on Health and Safety matters between the EPC
Contractor and others working on the site by regular Safety talks, distribution of
Safety Bulletins and where necessary Site Meetings with other Sub-Contractors.
Note any person exceeding or failing to discharge their OHS responsibilities and if
required take disciplinary action or provide an award
Undertaking regular site OHS tours and inspections and recording OHS
observations
Ensure that all procured material and equipment of any type to have safety
specifications and those specifications are logged and reviewed by the OHSE
Manager
Ensure that site Supervisors are competent and reflect OHS compliance at their
work areas, work activities and through workers
Consider OHS issues as part of works planning and execution so that they are
carrying out in accordance with the OHSMP requirements
Organizing sites so that work is carried out to the required standard with minimum
risk to employees, other subcontractors, the public, equipment or materials.
Where necessary, ensure written instructions that include OSH requirements are
issues so that they set out the method of work.
10
Occupational, Health & Safety Management Plan
Planning and maintaining a tidy site. "A safe site is a tidy site".
Ensure that sub-contractors are aware of their responsibilities for safe working and
that they are not required or permitted to take unnecessary risks. Stop any work if
you consider that there is an imminent risk of serious injury to any person.
Ensuring all plant and equipment is tested at the statutory intervals and will not be
brought onto site by anyone, including sub-contractors, without the appropriate
certified proof of regular testing.
Ensure that any accident on site which results in an injury to any person (not just
employees) and/or damage to plant or equipment is reported and investigated
Lead and promote OHS throughout the Project and works as an integral part of
business and operational efficiency.
Ensure all applicable legal and statutory related OHS are identified and action
plan is drawn for compliance
Discussion with Client Representative on OHS requirements and issues during the
execution phase and will provide, in a timely manner, all information/resources as
requested
Ensuring that OHS registers, records and reports are up-to-date and properly filled
in and ensure that they are kept in a safe place. Ensure that copies of regulations
are available and statutory notices are prominently displayed.
Ensure all personnel, EPC Contractor and sub-contractors are aware of their
responsibilities and that each administers the requirements of this OHSMP.
Provide liaison and external communication with the Project’s stakeholders and
provide periodic OHS management and performance reports.
11
Occupational, Health & Safety Management Plan
Represent the EPC Contractor on the EHSL Steering Committee or provide a
delegate
Arrange and lead OHS meetings and ensure minutes are distributed and action
followed up.
Managing the OHS team to ensure that support the delivery of the Project’s OHS
objectives and targets
Undertaking periodic site OHS tours and make reports and recommendations for
improving general site safety.
Provide advice on OHS matters and training requirements and arrange training
courses if requested. Ensure that adequate Safety Training is provided for all
personnel
Ensure all personnel and visitors received an approved site OHS induction before
being allowed on site and keep records of site inductions
Ensure that all firefighting equipment is maintained, fire exits kept clear and fire
drills organized on a regular basis
Keep up to date daily signing in/out register and visitors book. Only site inducted
personnel are allowed on site unsupervised.
Lead and promote OHS throughout the Project and works as an integral part of
business and operational efficiency.
Ensuring that OHS registers, records and reports are up-to-date and properly filled
in and ensure that they are kept in a safe place. Ensure that copies of regulations
are available and statutory notices are prominently displayed.
12
Occupational, Health & Safety Management Plan
Monitor and ensure all personnel, EPC Contractor and sub-contractors are aware
of their responsibilities and that each administers the requirements of this OHSMP.
Support the provision of tool box talks and deliver induction training
Undertaking daily and periodic site OHS tours and make reports and
recommendations for improving general site safety.
Warning new employees, particularly young people, of known hazards and OHS
procedures.
Do not start work that is unsafe and STOP and report work that is unsafe.
Correctly use all work and personal protective equipment in accordance with
instructions and training received and not to interfere with or misuse such
equipment.
7.3.7. Visitors
Receive a OHS induction before entering the site in order to understand and
support the Project’s OHS policy, OHSMP and standards
Stay with the Project person who is guiding you around site.
13
Occupational, Health & Safety Management Plan
8. OHS AWARENESS AND TRAINING
The EPC Contractor shall ensure that all personnel working on site have the required
competence to do so without putting the OHS guidelines and workers safety at significant risk.
Competence will be assessed before starting work by checking of education and
experience. The OHS Manager in consultation with Construction Manager or his designate is
responsible for providing and maintain the records for OHS training to the new & existing
personnel. The EPC Contractor will undertake a OHS training needs analysis to support the
development and implementation of the OHS training program. The FMC’s OHS Guideline’s
Appendix 3 will be use for the template of the training needs analysis. The OHS training
program will include the following.
Subcontractors will liaise with the EPC Contractor OHS Manager to arrange OHS induction so
that a request for induction is to be submitted 24 hours prior to date that induction is required.
The EPC Contractor will provide a dedicated OHS training facility and will keep it in good
order.
The OHS Induction training shall include, and not be limited to, the following topics
OHS Policy
Project Introduction
Alcohol and drugs being a dismissible offence and monitored by random testing
Working at height
Electricity.
PTW
Incident reporting
14
Occupational, Health & Safety Management Plan
Emergency Contact details
Records related to induction training shall be maintained and acceptance form shall be
signed by all personnel.
PPE
The EPC Contractor and its subcontractor shall provide continue OHS training for the workers
under its control, so they know how to carry out new tasks, meeting the necessary control
measures, and/or to improve their competence and awareness in OHS matters. A register of
OHS training will be kept.
Site specific formal or informal OHS training will be given on a weekly basis and will be carried
out by the subcontractors OHS and Supervision team. A OHS meeting will be held to share
the lessons learnt from any serious incident or accident that happened on site.
The ongoing OHS training program shall cover, as relevant, and not limited to:
Confined Spaces.
Use of PPE
Working at height.
15
Occupational, Health & Safety Management Plan
Hot work.
Fire-fighting.
The pre-job safety meeting/tool box talk at the start of each shift shall cover and discuss in
the workers own language the following:
Review & Communicate the Hazards and Risk associated with respective
activities
Discuss and agree the specific control methods and OHS precautions to be
followed
What to do in an emergency
Appendix B: List of Toolbox talks contains suggestions for toolbox talk and pre-start meeting
topics.
16
Occupational, Health & Safety Management Plan
Crane operator.
Rigger – banksman.
Scaffold Inspector
Electrical work
Scaffolding Supervisor
First Aider
Excavation inspector
These personnel should in possession of the necessary theoretical and practical knowledge
and experience and documented evidence of competency/authorisation
17
Occupational, Health & Safety Management Plan
9. MANAGEMENT OF SUBCONTRACTORS
The EPC Contractor expects and shall demand the same level of OHS management and
performance from its subcontractors as it does from its own employees. In particular:
All sub-contractors are required and expected to comply with the Project OHSMP,
local legislation and contractual obligations.
The EPC Contractor will monitor all its contractors' personnel and subcontractors
understanding and compliance with this OHSMP and all applicable laws and
contractual obligations.
The EPC Contractor shall carry out periodic OHS inspections and/or audits on the
subcontractor’s OHS management and performance, at least monthly, to ensure
that their OHS plan is being implemented and maintained.
Subcontractors and their personnel are to comply with all reasonable instructions
and directions given to them by the EPC Contractor.
Subcontractors are required appoint and assign dedicated and competent OHS
personnel such that the ratio of workers to dedicated competent OHS personnel
shall not exceed 1:40 (one to forty) for the Project as whole. A OHS representative
shall be deputed once the workforce count reaches 15.
Subcontractors are required to submit, to the EPC Contractor for review and
approval, their OHSMP that covers their works. The Subcontractors’ OHSMP shall
comply with the Project OHSMP as a minimum. In case of any discrepancy, the
EPC Contractor’s OHSMP requirements shall prevail at all times.
After the awarding of the contract, a Project HSE Kick-off meeting will be held
and shall be attended by key personnel of both parties including: (but not limited
with) Project Managers, Construction Managers and OHS Manager. The meeting
agenda will include, at least:
18
Occupational, Health & Safety Management Plan
- OHS Leadership
- Key Performance Indicators
- Contractual OHS requirements and the OHSMP
- OHS Induction, Training and Awareness
- Key OHS processes including Risk Assessment and Method Statement (RAMS)
reviews and Permit to Work
- Driving & Transportation
- Information Sharing, Meetings, Communications and Reporting
- HSE Observations and Incident Reporting
19
Occupational, Health & Safety Management Plan
10. OHS COMMUNICATIONS & MEETINGS
The EPC Contractor will make certain that the OHS communication system is setup to provide
Management, Supervisors and workers with up-to-date information OHS requirements and
issues. This communication system provides an opportunity for review of KPI, participation,
involvement, feedback, and HSE awareness for all personnel. The OHS communication
program will consist of the following elements.
All signposting, warnings, written communications/safety alerts, training and training materials,
instructions, etc., shall be written in English, Arabic and all other languages used by more
than 20% of the work force
Method statements
Risk assessments
20
Occupational, Health & Safety Management Plan
10.3. Bulletin Boards, OHS Notices and Signs
The EPC Contractor and the subcontractors shall set up around the Site a suitable and
sufficient number of bulletin boards exclusively dedicated to OHS matters. These notice
boards will be erected in key areas (offices, mess areas, etc.). As a minimum, OHS notice
boards will be set up at the front gates to the plots, the entrance halls of all main
administration offices and the entrance to the worker accommodation area.
The Project OHS Committee is responsible for developing and promoting OHS awareness and
safe work practices as well as makes recommendations to management that will improve
compliance performance as well as the health and safety of the workers on the project.
OHS safety signs will be available and installed as per risk assessments and good practices.
Signs will confirm to international standards and text will confirm to the project languages as
describe above. Appendix D: Examples of OHS Signs provides guidance on international
OHS signage.
The EPC Contractor will develop and implement a program of monitoring and reporting
activities based on a risk profile. Each contractor and subsequent sub-contractors shall
develop their own schedule of monitoring activities and shall submit this to the EPC
Contractor for review. Monitoring activities may be carried out jointly or separately; the
selection criteria and frequency of activity will be primarily based on risk. Monitoring reports
shall include a list of the identified risks and non-compliances and the measures taken to
control them and a tracking mechanism to ensure close out of items as part of the Project’s
non-conformance management process.
The OHS monitoring program shall consist of the activities included in the table below.
Format of
Description Warning Penalty
No penalty if violation was not one of the 10 life rules.
Written or verbal
1st Offence If violation was related to gross misconduct, negligence, ignoring
warning
PTW or one of the life rules then consider 1-day suspension
2nd
Written warning Temporary suspension 1- 3 days
Offence
3rd Offence Written warning Temporary suspension – 3-5 days
4th Offence Dismissal Dismissal from the project
A disciplinary Yellow, Amber Red card system will be implemented related to the use of
mandatory Personal Protective Equipment (helmet, goggles, gloves, safety shoes,) for repeat
offenders.
Description Penalty
1st Card – Yellow Warning
2nd Card – Amber ½ -1-day suspension
3rd Card - Red Dismissal from the project
Rewards will be nominated by the OHS Manager and decided upon at the monthly Project
OHS Committee meeting. Awards will be made monthly plus at the end of the project for
the best OHS person and contractor. In addition, the Project Director supported by the OHS
Manager and Construction Manager can decide to award sport rewards for exceptional
OHS behaviour or performance.
All serious and major OHS findings shall be formally communicated in writing to the relevant
subcontractor and shall include:
Date of finding
Signatures
A work plan that clearly specifies the timescale for the change and any control
measures to be implemented regarding:
Appendix I: List of Controlled OHS Documents and Records details the OHS documentation
that shall be managed by the EPC Contractor and subcontractors.
The person(s) directly involved in the incident or, if this is not possible, any witnesses of the
incident must report incidents to their supervisor or manager without delay.
Investigations shall be carried out by competent personnel from the EPC Contractor and its
subcontractors, and any investigation can be attended by the client representative. When
an incident has resulted in harm or property damage then an Incident report shall be
completed by the person(s) witnessing the event and the local OHS Engineer. A first
investigation of the incident shall be performed immediately after its occurrence. Appendix F:
Incident Investigation Form has a template for documenting the incident and the
investigation. Fatal and Lost Time Incidents will be formally investigated by a team former
and lead by the Construction and OHS Managers.
Incidents shall be notified to the EPC Contract and FMS guidelines which require and shall
include:
The provision of the final incident report and root cause analysis for LTIs within 14
working days of the incident to the client.
The ERP plan is to be periodically reviewed and updated, at least every three months, to
keep aligned with the construction phase and site arrangements.
The EPC Contractor and subcontractors must communicate the EPR to all personnel and
include an overview in the OHS induction.
The person who discovers an emergency situation or incident must raise the
alarm.
Local OHS Officer supported by Supervisors and OHS Manager rapidly assess the
situation and any possible casualties, and telephone the emergency services as
required.
In the event of an evacuation warning signal is given, all personnel will meet in
their designated meeting point.
If safe to do so, a trained emergency response and rescue team will be mobilize
to look for missing persons.
The EPC Contractor and subcontractors will support the local emergency
services and provide unrestricted access to the incident area.
Once the situation has been made safe and normalized, the OHS Manager and
Construction Manager will review the site.
If it is safe to do so, the EPC Contractor will issue a “safe to return to work” signal
and personnel may only then resume work
Elimination (physically remove the hazard, for example bringing works to be done
at height down to ground level for pre-assembly);
Isolation (contain the hazard by, for example using guards on rotating machinery)
The risk rating matrix is as below with the rating being the product of severity times likelihood
Likelihood
Severity 1 2 3 4 5 Legend:
T: tolerable risk
1 1T 2T 3T 4T 5 AA
AA: As low as reasonably
2 2T 4T 6 AA 8 AA 10 AA practicable and controlled
3 3T 6 AA 9 AA 12 I 15 I
By example the risk rating matrix can be used to assess the risk form is for Manual handling
that can lead to muscular skeletal strains and injury, damage to property.
The likelihood of occurrence is frequently which scores 4.
The probable severity of injury is a medical treatment case which scores 3.
So the risk rating of manual handling is 4x3=12 which is an Intolerable risk. The outcome is that
the current unmanaged practices need to be reduced by implementing the hierarchy of
control including safe work procedures
Appendix G: Project Level Risk Assessment contains the initial risk assessment for the most
common and foreseeable activities. This register is live document that will be reviewed and
updated throughout the life of the project. The control measures are the basis for details
contained in the next section on control measures and standards.
The register is available to all personnel and will be posted on the OHS notice board in the
entrance of the project management office.
The EPC Contractor and subcontractors must use the Method Statements work steps to
identify hazards capable of adversely affecting the health and safety of persons or damage
to property or to the environment and adequate mitigation measures to be implemented to
reduce these risks. These Risk Assessments must be reviewed regularly to determine the
efficiency of the assessment and if deficiencies are detected, the correct controls and
mitigations are to be applied and implemented. This must not be a paper exercise. All Risk
Assessments will be reviewed by the EPC Contractor before work commences.
Risk shall be evaluated considering the probability of accidents occurring and the severity of
injuries in the case of potential accidents.
Risk assessments shall be planned, carried out and used as a tool for preventing harmful
effects on people, the environment or material assets. The risk rating shall be completed as
detailed above.
Even if it is not possible to eliminate all risks connected with the scope of work, risk-reducing
measures shall whenever possible follow up the assessments.
For the risk assessment will be completed used the form in Appendix H: Risk Assessment Form.
It will be will be available at the point of task where employees are conducting the work.
Each worker must sign on the back of the RA which is in effect the job safety analysis. Where
a task can impact on other tasks adjacent to the area/process the other team leader should
also sign each other’s JSA in addition to Simultaneous Operations (SIMOPS) assessment.
Cover sheet including the signatures of the author, at least one reviser and one
approver. There should be space for revisions control with dates stated on them
as necessary.
A description of the vehicles, vessels, plant, machinery, tools and any other
equipment to be used during the activity
A section containing all the safety measures to be implemented to control all the
identified hazards/risks (this section must not include PPE)
UK Environmental Agency
- Choosing and using oil storage tanks, PPG2: prevent pollution, 15 April 2014
- Choosing and using oil separators, PPG3: prevent pollution, 1 April 2006
- Storing and handling drums and intermediate bulk containers, PPG26, 15 April
2014
These publications should be read in parallel with the overview information and guidelines
provided in the next sections.
A stop work situation will be managed using the following six steps:
The HSE Manager and Project Director are responsible for resolving any conflicts,
disagreements and differences in opinions in stop work orders and safe to return to work
orders. As part of the safety first philosophy there is no retribution for doing a stop work order
in good faith even if it is deemed unnecessary. Personnel must not feel apprehensive to act
on their obligation to initiate a stop work action and this will be included in the induction
training
19.4. Housekeeping
Housekeeping is the act of keeping the working environment cleared of all unnecessary
waste, thereby providing a first-line of defence against accidents and injuries. The EPC
Contractor and its subcontractors shall understand and accept that improper housekeeping
is the primary hazard in any construction site and ensure that a high degree of housekeeping
is always maintained. Housekeeping is the responsibility of all site personnel, and line
management commitment shall be demonstrated during site tours.
Subcontractors shall create a team of housekeeping personnel. This group shall ensure daily
cleaning at work sites and surrounding areas and maintain a log of works.
Housekeeping standards for a clean, tidy and orderly site will be based on the 5S
methodology and will, amongst other actions, be maintained by:
Keeping walkways and stairways always free of tripping hazards such as trailing
cables, building materials and waste. This is especially important for emergency
routes.
Making sure that all flammable waste materials (such as packaging and timber
offcuts) are cleared away regularly to reduce fire risks
Outdoor footpaths should be level and firm and should not be used for storing
materials.
All hoses, cables, extension cords and similar materials shall be located, arranged
and grouped so that they will not block any access way and will permit easy
cleaning and maintenance.
Tools, hoses, extension cords, chokers, welding leads, etc. are to be properly
rolled up and stored when not in use. All such equipment shall be routed out of
walkways and traffic.
Designating storage areas for all equipment, plant, materials, waste, flammable
substances (e.g. foam plastics, flammable liquids and gases such as propane)
and hazardous substances (e.g. pesticides and timber treatment chemicals).
Flammable materials shall be stored away from other materials and protected
from accidental ignition.
Do not store materials where they obstruct access routes or where they could
interfere with emergency escape, e.g. do not store flammable materials under
staircases or near to doors or fire exits
Eating and drinking will only take place in designated areas. Trash containers
shall be placed adjacent to all drinking water locations and areas used for
employees for lunch and/or break areas.
Subcontractors shall at all times maintain a minimum of 10% spare PPE's and safety
appliances for review during OHS.
The Contractor shall ensure that personnel inspect PPE prior to use. Such inspections shall
include identifying obvious signs of wear, tears, holes, cracks, or leaks, the proper function of
closures, the status of seams. Any PPE found to have excessive wear, tears, punctures, or any
defect of any nature shall be discarded and replaced with new PPE. All personnel are
Additional Personal Protective Equipment/Clothing may be required as per RAs. These could
include:
Permission is required from your supervisor before using wire slings to wrap around
pipe or beams to connect your lanyard.
Using the Tools inappropriately: Using pliers or wrenches as hammers, using screw
drivers as punch or chisels, using double-end spanners in place of ring spanners,
using pipe wrenches as spanners are examples of using tools incorrectly and so
can lead to harm. The appropriate tools of proper size and type should be used
to suit the job.
Using worn, blunt, dirty or broken tools: Tools should have handles intact. The
handles should be tightened with wedges whenever necessary. Sharp tools
improve efficiency and are safer than dull tools. Accumulated dirt or grease
should be wiped off to avoid slippage Split or broken handles should not be used.
Pipes or rods are prohibited.
Keeping Tools in Unsafe Places: Hand tools should not be allowed to lie on
workbenches, scaffolding to avoid falling objects. Hand tools should not be held
Never use electric equipment (such as drills, sanders, and saws) in wet or damp
conditions.
Electrical cords and welding leads will be routed overhead at a minimum height
of 2 meters. If this is not possible, routing over floors is permitted if kept out of
walkways, avoiding pinch points and tripping hazards are eliminated
Keep all equipment in proper working order and use the equipment according
to the manufacturer’s instructions.
Remove chuck keys from drills prior to use. Hold tools firmly and maintain good
balance.
Secure the work in a holding device, not in your hands. Wear eye protection
while operating these machines.
Do not suspend electrical cords by metal rods or nails. Suspend with non-
conducting supports only, such as plastic ties.
Disconnect power tools before making adjustments, changing discs, blades, etc
Ensure that all lock buttons or switches are off before plugging the machine tool
into the power source.
Never leave a portable pneumatic hammer with a chisel, star drill, rivet set, or
other tool in its nozzle.
Never operate grinding wheels at speeds more than the recommended speed.
Never adjust the work piece or work mounting devices when the machine is
operating
Do not exceed recommended depth of cut for the grinding wheel or machine.
Remove work piece from grinding wheel before turning machine off.
Only competent persons, electricians, are authorized to perform work on any electrical
systems. They must be competent to undertake the specific tasks and must be given specific
training before any work can be authorized.
Overhead wires can be struck by metal devices, such as poles or ladders, and by
vehicles with metal booms. Vehicles or grounded metal objects brought into
close proximity with overhead wires can result in arcing between the wires and
the object, without actual contact. Establishing “No Approach” zones around or
under high voltage power lines in conformance with the following table.
Marking all energized electrical devices and lines with warning signs.
Locking out (de-charging and leaving open with a controlled locking device)
and tagging-out (warning sign placed on the lock) devices during service or
maintenance.
Checking all electrical cords, cables, and hand power tools for frayed or
exposed cords and following manufacturer recommendations for maximum
permitted operating voltage of the portable hand tools.
Protecting power cords and extension cords against damage from traffic by
shielding or suspending above traffic areas.
All distribution boards shall be protected by both overload trios and RCD/RCCBs
– which maybe combined
The EPC Contractor and Subcontractors shall periodically monitor noise level periodically
across the sites. Areas with actionable noise levels are to be signed to alert personnel of the
control and PPE requirements. Before issuing hearing protective devices as the final control
mechanism, contractors shall use acoustic insulating materials, isolation of the noise source,
and other engineering controls to reduce and noise levels.
Hearing protective devices provided should be capable of reducing sound levels at the ear
to at least 85dB(A).
Periodic medical hearing checks should be performed on workers exposed to high noise
levels.
Exposure to hand-arm vibration from equipment such as hand and power tools, or whole-
body vibrations from surfaces on which the worker stands or sits, should be controlled through
choice of equipment, installation of vibration dampening pads or devices, and limiting the
duration of exposure. PPE should be used as the last hierarchy of control.
Heat stress is a name given to a collection of health hazards that can occur as a result of
strenuous work in hot, humid environments. The effects range from minor discomfort to life-
threading implications. Prolonged exposed exposure to freezing or cold temperatures can
result in serious health problems such as trench foot, frostbite, and hypothermia. In extreme
cases, including cold-water immersion, exposure can result in death. In the event of any
symptoms, Contractor shall ensure appropriate medical attention is provided as per the EPR
plan.
Barricade tape will be used to wrap around the physical barrier or in conjunction with the
physical barrier to provide additional warning of the hazards or danger that exist and/or to
increase the visibility of the barrier.
Barriers will be constructed of material of substantial strength such as scaffold tubing or 50mm
x 100mm lumber.
Barricades shall be visible at all times where a hazard or danger exists, and additional signs
may also be required.
All streets, roads, highways, and other public thoroughfares, construction roads which are
closed to traffic, shall be protected by effective barricades on which shall be placed
acceptable and highly visible warning signs. Barricades shall be located at the nearest
intersecting, highway, street or road on each side of the blocked section.
All floor openings, open trenches and other excavations shall be provided with suitable floor
opening covers, barriers, signs and lights to the extent that adequate protection is provided
to the employees and public. Obstructions such as material piles and equipment shall be
provided with similar warning signs and lights.
All road barricades and obstructions shall be illuminated by means of warning lights from
sunset to sunrise.
Materials stored upon or alongside construction roads and public streets and highways shall
be so placed, and the work at all times shall be so conducted as to cause the minimum
obstruction and inconvenience to the traffic.
All barricades, signs, lights and other protective devices shall be installed and maintained.
Signs, signals and barricades shall be removed when the hazard no longer exists.
All vessels that may contain substances that are hazardous because of chemical or
toxicological properties, or temperature or pressure, should be labelled as to the contents
and hazard, or appropriately colour coded.
Similarly, piping systems that contain hazardous substances should be labelled with the
direction of flow and contents of the pipe, or colour coded whenever the pipe passing
through a wall or floor is interrupted by a valve or junction device.
Safety signs will follow the colour codes specified in local rules and regulations and as per
Appendix D: Examples of OHS Signs. Areas deemed hazardous or harmful based on a RA
The most common injuries from manual handling are sprains or strains, often to the back.
Sprains and strains arise from incorrect application of bodily force; poor posture and
excessive repetition of movement can be important factors in their onset. Every contractor
must provide training and PPE to the workforce regarding back protection and prevention
measures. Whenever reasonable, processes and procedures must be modified/replaced to
eliminate or diminish the need of manual handling.
Injuries due to manual handling, take prolonged and repeated exposures to develop, and
typically require periods of weeks to months for recovery. This problem should be minimized
or eliminated to maintain a productive workplace. Controls may include:
Selecting and designing tools that reduce force requirements and holding times
and improve postures.
Incorporating rest and stretch breaks into work processes and conducting job
rotation.
Hot work is defined as “operations requiring the use of open flames or the local application
of heat or friction”. Examples include Welding, Flame cutting, Soldering, Brazing, Grinding or
the use of other equipment incorporating a flame, e.g. tar boilers, etc.
Co-ordination of the work activities with other persons or other work processes,
according to the procedure for interference management
Before starting welding, all connections to the machine, insulation on the holders
and cable shall be checked to make certain that they are in good order.
The work lead shall be attached firmly to the work and laying work connections
loosely on the work should be avoided.
Welders should never permit the metal part of an electrode, the electrode holder
to touch either his bare skin or any wet coverings on his body.
Electrodes shall be removed from holders when not in use to eliminate danger of
Electrical contact with the persons or conducting objects. Electrode holders
when not in use shall be stored to avoid electrical contact between them and
persons or conducting objects.
Each welder is responsible for containing sparks and slogs and removing
combustibles.
Hoses and welding leads should not be run through doorways or wall openings.
Do not leave the rod in the electrode holder when you lay it down.
An approved welding helmet shall be worn. Not less than nine (9) filter plate, with
a clear safety plate on both sides.
Proper barriers or screens must be erected to protect others from the arc (flash
burn)
A twenty 5kg or larger dry chemical fire extinguisher must be within 6 meters of
any welding, burning or flame work.
All hot work equipment must be inspected by a competent inspector and must
bear the current colour coded monthly inspection tag to be used.
Surfaces meant for stockpiling must be levelled and have the appropriate resistance.
The height of the pile must not exceed the one established by the manufacturer of the
relevant material, or the height 3 times the base
The same pile must not include materials featuring different shapes or vessels with different
contents.
The stockpiling of soil and aggregates must be carried out in accordance with the following
rules.
If the pile exceeds a height of 1,8 m, the whole stockpile area must be fenced or
marked out.
Piles must never be placed over roads or access ways; however, if that is
necessary, piles must be duly marked out.
Piles of soil or aggregates must never be placed by drainage devices that may
get blocked as a consequence of the dragging of those materials piled up or
that otherwise may get blocked simply because of the discharge of the device.
Spotters if used must undergo training (approved by the client) to do this safely
For the stacking of pipes, frames, prefabricated elements and scrap items the following
safety rules must be followed:
The stacking of pipes must be carried out in a way that ensures their stability by
using the appropriate shoes to such effect.
Transportation of pipes must be carried out using the appropriate tools in order to
prevent the sliding or fall of those elements being transported. Such tools must be
regularly inspected to as to guarantee the appropriate use conditions.
Scrap items must be stacked by the corresponding site, avoiding contact with
wet surfaces so as to prevent them from rusting and therefore preventing them
from losing their resistance qualities.
Works at height require a permit to work to be submitted to the EPC Contractor for approval.
When work at height is a specific part of a construction method, it must be included in the
method statement as a specific hazard/risk.
The hierarchy of preference for controls for working at height will be:
If fixed platforms are not a practical option then other systems which prevent falls,
such as a restraint system which prevents a person approaching a position where
they can fall can be considered.
Finally, if fixed platforms and restraint systems which prevent falls are not practical,
systems which minimize the consequences of a fall such as a harness, an air bag
system or a safety net must be used.
Everybody working at a height above 1.8metres, shall where fall protection, e.g.
safety harness with a double lanyard, with both tied off.
Before the commencement of the works at heights the company in charge of those works
must appoint the person responsible for the preparation of a Fall Protection Plan. The fall
protection plan shall include:
a risk assessment of all work carried out from an elevated position which shall
include the procedures and methods used to address all the risks identified per
location;
the processes for evaluation of the employees physical and psychological fitness
necessary to work at elevated positions and the records thereof;
the programme for the training of employees working from elevated positions
and records thereof; and
the procedure addressing the inspection, testing and maintenance of all fall
protection equipment.
Installation of guardrails with mid-rails and toe boards at the edge of any fall
hazard area.
Use of fall prevention devices, including safety harness and lanyard travel limiting
devices to prevent access to fall hazard area, or fall protection devices such as
full body harnesses used in conjunction with shock absorbing lanyards and self-
retracting inertial fall arrest devices attached to fixed anchor point or horizontal
life-lines. Fall arrest systems must be appropriate for the specific situation and
approved by a competent person. Its selection must be in accordance with a
documented risk assessment carried out by someone trained and competent to
make such a selection.
All contractors must deliver a list of all work at height equipment (harnesses, fall arrestors,
portable life lines, locking devices, ascending and descending devices, etc.) This list must
contain the following information:
Owner (PPE for works at height is personal, so the same equipment cannot be
used by two workers)
Date of manufacture
Date of last inspection or inspection history, when applicable (external) and date
of next inspection (manufacturer certificates and test approval certificates from
authorized third parties must be available for review)
All safety harnesses will be identified and number and inspected Monthly and
recorded in a register.
All personnel performing works at height must have a relevant certification from an
authorized third party (unless the contractor itself has a valid homologation as “specialist” or
Working on Ladders:
All ladders will be inspected before and after use and records of these are to be
placed in the site HSE File.
Ladders must use the 1 out 4 up formula when setting it up against a structure or
building.
Ladders must protrude at least 900mm above the structure that it is leaning
against.
A ladder register must be kept and these records are to be placed in the site HSE
File.
19.15. Scaffolding
Where work cannot be performed from the ground or other safe surface, the Subcontractor
shall provide a scaffold or other means of support that provides an equivalent level of safety.
Scaffold planning, erection and use is controlled as part of the Permit to Work
system and so all scaffolds required a permit to work to be issued before erection
may begin.
The appointed scaffold Competent Person will direct and supervise the erection
and dismantling of all scaffolding on the project.
The Identified personnel will sign and attach one of the following color-coded
scaffold tags to each scaffold:
Written inspection logs and a scaffold tagging system shall be implemented for
every scaffolding system.
- prior to use and sign the tag at the time of the inspection,
- a minimum of once per week,
Contractor shall provide the EPC Contractor with an engineering for the scaffold
including design criteria and drawings.
Scaffolds must be used only to support people and light equipment/tools unless
they are specifically designed, engineered and certified for another purpose.
Before using a scaffold, all personnel shall ensure that the scaffold has been
approved and tagged, and visually confirm that there is no obvious damage or
defects.
The Competent Person from subcontractor responsible for erecting the scaffold must inspect
the scaffold after erection and before use, which inspection shall include checking the
following:
Scaffold and their components, except for wire or fibre rope suspension, must be
capable of supporting 4 times the maximum intended load.
Wire or fibre rope used to suspend scaffolds must be capable of support at least
6 times the maximum intended load.
If a scaffold is more than 2 feet above or below a level, there must be a way to
get on or off such as a ladder, ramp, or personnel hoist.
Uprights must be vertical and braced to prevent swaying; platforms must be level.
Scaffold platforms and walkways must measure at least 18 inches (0.46 m) wide.
Keep scaffold platforms and access ways free of tripping or slipping hazards
Clear working platforms of ice, snow and oil before using them.
Do not allow open fires upon or near wooden scaffolds or metal scaffolds with
flammable components.
Fork-lift trucks
Lifts
Hoists
The following good practices shall be implemented to mitigate hazards associated with lifting:
All lifting equipment must be certified by a recognized third party before it arrives
to site.
Appropriately supervised.
Critical lifting operations require a method statement and a permit to work to be submitted
to the EPC Contractor for approval. Minor or non-critical lifting operations do not require a
method statement. Critical lifting operations are the following:
Dual lifts
Tandem lifts
All flammable materials and hazardous substances must be stored and handled
in accordance with the manufacturer recommendations.
All flammable and hazardous substances, fuels and thinners must be stored in
appropriate containers out of direct sunlight and away from sources of ignition
All flammable materials and hazardous substances will be returned back to their
secured storage areas when work is complete or at the end of the working day
All paints shall be stored within an appropriate paint store, which shall have
upper and lower ventilation which shall allow the build of fumes to dissipate into
the atmosphere.
All flammable materials and hazardous substances storage areas shall be clearly
signed with appropriate warning and advising signs
All naked flames, sources of ignition and smoking shall be forbidden within the
vicinity of all flammable materials and hazardous substances
All flammable fluids and hazardous liquids shall be stored within a protective
containment area away from drains, pits, sewers, excavations well fumes can
build up.
All LPG, pressurized gas cylinders and flammable gases storage areas shall be
secured and positioned at least 6m away from any site accommodation.
Quantities of stored LPG, pressurized gases and flammable gases shall be kept in
minimum requirements, where this is reasonably practicable
All gas cylinders shall be clearly labelled, or colour coded to show their contents
Full and empty gas cylinders shall be labelled and physically segregated
All empty gas cylinders shall be removed from site promptly to the appropriate
storage area to wait for immediate backload to the suppliers.
All gas cylinder end caps shall be put back onto the cylinders when they are not
in use
Grease, oil and oxidizing substances shall be kept away from gas cylinders
Gas cylinders shall not be stored inside containers or the welfare facilities, unless
designed for the specific purpose
All naked flames, sources of ignition and smoking shall be forbidden within the
vicinity of all LPG, pressurised gas and flammable materials.
In closed storage areas, ventilation must be constant and sufficient and therefore
such areas must include holes and openings which communicate directly with
outside areas; such holes and openings must be duly distributed in high and low
areas. The total surface of such openings must be equal to, at least, 1/18 if the
total area of the storage facility.
gas cylinders must be protected against any kind of mechanical damage such
as blows with one another or against hard surfaces.
gas cylinders with removable caps must not be lifted by the cap.
gas cylinders must not be dragged, slid or rotated while in horizontal position.
Valves of full or empty bottles must be closed by securing the appropriate safety
caps (Shrouds).
Metallic chains or cables, or even cables covered with rubber, must not be used
to lift or transport bottles, since they may slip.
Ensure that such activities can be carried out with due regards to safety, health
and welfare or workers.
Prevent any incompatible work from being carried out at the same time on
project.
Ensure that the necessary safety precautions are taken and enforced when such
work is being carried out
No proscribed work shall start unless a Permit to Work when necessary is completed and
signed off by all those required. Each Permit to Work shall be accompanied by a Risk
Assessment and Method Statement.
Some of these permits will be issued daily while others may be issued for longer periods as
follows:
A copy of RAMS and Permit to Work shall be available at the work location for all to review if
necessary during the course of work.
The Contractor shall be responsible, with the assistance of the Engineer required, for
requesting the issue of a relevant Permit to Work outlining the work he proposes to do and
giving the name of the competent person to which the Permit to Work should be issued. The
Contractor shall ensure that the plant and equipment covered by the Permit to Work meets
his requirements and that the period of cover is also adequate.
Hot Work
Excavation Permit
Radiography
Road Closure
Erection of scaffolds
Working at Height
Only competent and trained personnel may under take LOTO operations and Lock/Tag
Installation Authorized employees, contractors and subcontractors shall follow these steps
when performing lockout.
Personnel are prohibited from working on energized systems without written authorization
from the Construction Manager and consultation with HSE Manager and his signature for final
approval.
A standard “DANGER – DO NOT OPERATE” tag and individually keyed locks will be used on
the Project.
All tags will be dated, signed and a description of the work being performed shown on the
tag and securely attached to the equipment/lock.
Any device with a tag or lock attached shall not be operated regardless of circumstances.
It is the discipline supervisor’s responsibility to ensure that work is performed within the
protection of locks and tags.
The following tables detail the steps to be followed when undertaking LOTO operations
Step Action
3. Identify and disconnect the supply of power before placing locks /Tags on the
equipment.
5. Obtain verification from all employees who will work on the equipment that the proper
lockout has been performed.
6. Fill out a Lockout/Tag-out Form completely and display prominently at the job
Environmental (see Appendix E for example of the form).
Implementing LOTO
Electrical Control:
Step Action
Authorized employees, contractors and sub-contractors shall follow these steps to remove
locks and restore equipment to normal operation.
Step Action
2. Confirm that all tools have been removed from the machinery or equipment.
3. Confirm that all guards, pulleys, and safety devices have been reinstalled and are
secure.
4. Remove all locks and tags only after one final check to ensure all employees are safely
in the clear.
5. Notify all Affected employees that the lockout/tag devices have been removed
and that the equipment will be re-energized.
In the event that an Authorized employee is not available to remove their lockout/Tag-out
device, the Lockout/Tag-out coordinator may remove the lockout/Tag-out device for them.
A record log will be maintained for this activity. Use the following procedure for non-owner
lock removal.
Step Action
1. Verify that the Authorized employee who applied the locking device is not present at
the facility.
2. Make all reasonable efforts to contact the Authorized employee that the lockout or
Tag-out device is being removed.
4. Ensure the Authorized employee is informed, before resuming work at the facility, that
the lockout or Tag-out device has been removed.
All works in a confined space require a RAMS and a permit to work request to be submitted
to the EPC Contractor for review and issues.
- Process or feed lines into the space should be disconnected or drained, and
blanked and locked-out.
- Mechanical equipment in the space should be disconnected, de-energized,
locked-out, and braced, as appropriate.
- The atmosphere within the confined space should be tested to assure the
oxygen content is between 19.5 percent and 23 percent, and that the
presence of any flammable gas or vapour does not exceed 10 percent of its
respective Lower Explosive Limit (LEL).
- If the atmospheric conditions are not met, the confined space should be
ventilated until the target safe atmosphere is achieved, or entry is only to be
undertaken with appropriate and additional PPE.
wExcavation works require a method statement and a permit to work to be submitted to the
EPC Contractor for approval. Proper identification of hazards (underground services like
water, sewage, electricity, etc.) must be done for each process when there is a suspect
about the presence of these.
Each week, all contractors must provide an excavation plan including the location and
duration of each work. This will facilitate the analysis of conditions to set proper traffic
controls.
Piling and drilling holes must be covered until they are filled.
Excavation work shall be carried out carefully and follow recognized safe digging
and excavation shuttering/protection practices.
Once a locating device has been used to determine cable positions and routes,
excavation may take place, with trial holes dug using suitable hand tools as
necessary to confirm this.
Excavation shall be alongside the service rather than directly above it.
Insulated tools shall be used when hand digging near electric cables.
Previsions must be taken to pump water out of any excavation when necessary.
Illumination is mandatory when the excavation is so deep that light is not enough
at the bottom
Working pits of more than four meters deep with restricted dimensions and
narrow trenches of more than four meters deep and less than two meters wide
are deemed to be - and classified as - confined spaces to which specific safety
provisions shall apply (permanent supervision from outside the working pit,
continuous oxygen monitoring, monitoring harmful substances, safety harnesses
with lanyards for evacuation, etc.).
The forming and striking of concrete is an operation carried out manually by specialized
personnel. The formwork unit is in charge of the construction of the panels, the assembly of
the formwork and subsequent striking, if appropriate.
Formworks may fall into two categories: "traditional" (usually wooden) and "prefabricated"
(metallic or wooden). Formwork assembly is the joining of different single panels which are
modulated until the desired form is achieved, both regarding height and length, including
working platforms, accesses, etc. Units included in formworks are: assembly, transportation
and placement.
The control measures for form and support works shall include
All works must be carried out from the working platforms and, whenever
assembly conditions do not allow to work from the aforementioned elements,
fall-arrest safety harnesses must be used; therefore, anchorage points must be set
in place in advance.
If the formwork is not placed horizontally on the natural ground but inclined, the
mooring and unmooring by means of cramps must be carried out using ladders.
The access tubular ladder must meet the appropriate safety requirements and it
must be braced.
Formwork panels must not be unhooked until they are properly stabilized.
Stabilization of panels must be carried out in accordance with their size and
following the instructions of the manufacturer.
The use of struts and winches must be restricted to those cases in which, due to
space or other reasons, it may not be possible to use stabilizers.
The assembly of panels may require the use of personal protective equipment to
avoid the risk of falls from a height; therefore, the use of certified harness hooks
for those hitches available must be foreseen; such hitches are in many cases just
the holes drilled on the ribs of the formworks which are already secured.
The kind of formwork used must be defined based on the type of structure.
Likewise, the formwork must be solid enough to support, without substantial
deformations, the concrete load it contains.
The guiding principles to be adopted for traffic management safety in construction zone are
to
All construction workers should be provided with high visibility jackets with
reflective tapes.
Provide safe and clearly marked lanes for guiding road users.
Wherever operations undertaken are likely to interfere with public traffic, specific traffic
management plans shall be drawn up and implemented in consultation with the approval of
local police and statutory authorities
The primary traffic control devices used in work zones shall include signs, delineators,
barricades, cones, pylons, pavement markings and flashing lights.
Regulatory signs impose legal restriction on all traffic. It is essential, therefore, that they are
used only after consulting the local police and traffic authorities.
Warning signs in the traffic control zone shall be utilised to warn the drivers of specific hazards
that may be encountered. The contractor shall place detour signage at strategic locations
and install appropriate warning signs. In order to minimize disruption of access to residences
and business, the contractor shall maintain at least one entrance to a property where
multiple entrances exist.
At the start of work and entry to site as part of pre-start medical fitness test, and
General health
Musculoskeletal fitness
Signage.