PEKERJAAN SFO

LAJUR PANJANG LEBAR LUAS TEBAL STATUS


NO JALUR STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m P1 / P2
A 1+900 2+050 4.20 150.00 4.20 630.00 0.06
A 2+850 3+000 3.80 4.20 150.00 8.00 1,200.00 0.06
A 3+400 3+550 3.80 150.00 3.80 570.00 0.06 ex. Gerbang
A 3+400 3+550 4.20 150.00 4.20 630.00 0.06 ex. Gerbang
A 3+750 3+950 3.80 200.00 3.80 760.00 0.12 RB
A 4+100 4+200 3.80 100.00 3.80 380.00 0.12 RB
A 4+400 4+600 4.20 200.00 4.20 840.00 0.12
A 4+850 4+950 3.80 100.00 3.80 380.00 0.06
A 5+200 5+450 4.20 250.00 4.20 1,050.00 0.12
A 5+200 5+450 4.20 250.00 4.20 1,050.00 0.06
A 6+200 6+350 4.20 150.00 4.20 630.00 0.12
A 6+500 6+600 3.80 100.00 3.80 380.00 0.06
A 6+750 7+200 3.80 450.00 3.80 1,710.00 0.06 RB
A 8+000 8+200 4.20 200.00 4.20 840.00 0.21 RB
A 8+600 9+250 4.20 650.00 4.20 2,730.00 0.21 RB
A 9+450 9+545 3.80 95.00 3.80 361.00 0.06
A 9+500 9+700 4.20 200.00 4.20 840.00 0.06
A 9+510 9+650 4.20 140.00 4.20 588.00 0.21 RB
A 10+000 10+200 4.20 200.00 4.20 840.00 0.21 RB
A 12+450 13+000 4.20 550.00 4.20 2,310.00 0.21 RB
A 13+600 14+200 4.20 600.00 4.20 2,520.00 0.21 RB
A 15+800 15+900 4.20 100.00 4.20 420.00 0.06 SG
A 15+800 16+000 4.20 200.00 4.20 840.00 0.06 SG
A 16+100 16+400 4.20 300.00 4.20 1,260.00 0.06 SG
A 16+100 16+250 4.20 150.00 4.20 630.00 0.21 RB
A 16+360 16+700 4.20 340.00 4.20 1,428.00 0.21 RB
A 16+800 16+900 4.20 100.00 4.20 420.00 0.21 RB
A 16+935 17+400 4.20 465.00 4.20 1,953.00 0.21 RB
A 17+500 17+600 4.20 100.00 4.20 420.00 0.21 RB
A 17+700 17+850 4.20 150.00 4.20 630.00 0.21 RB
A 17+900 18+050 4.20 150.00 4.20 630.00 0.21 RB
PEKERJAAN SFO
LAJUR PANJANG LEBAR LUAS TEBAL STATUS
NO JALUR STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m P1 / P2
A 20+430 20+600 4.20 170.00 4.20 714.00 0.21
A 21+080 21+300 4.20 220.00 4.20 924.00 0.21
A 21+400 21+900 4.20 500.00 4.20 2,100.00 0.21 RB
A 22+872 22+937 4.20 65.00 4.20 273.00 0.21
A 23+400 23+896 4.20 496.00 4.20 2,083.20 0.21 RB
A 24+055 24+300 4.20 245.00 4.20 1,029.00 0.21
A 24+400 24+500 4.20 100.00 4.20 420.00 0.21
A 24+565 25+000 4.20 435.00 4.20 1,827.00 0.21
A 25+248 25+398 4.20 150.00 4.20 630.00 0.21
A 25+400 25+500 4.20 100.00 4.20 420.00 0.21 RB
A 26+200 26+500 3.80 300.00 3.80 1,140.00 0.06 RETAK
A 26+200 26+500 4.20 300.00 4.20 1,260.00 0.12 RETAK
A 26+200 26+500 4.20 300.00 4.20 1,260.00 0.06 RETAK

SUB TOTAL JALUR A 10,471.00 43,950.20


PEKERJAAN SFO
LAJUR PANJANG LEBAR LUAS TEBAL STATUS
NO JALUR STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m P1 / P2
B 26+600 26+500 3.80 100.00 3.80 380.00 0.06
B 26+600 26+500 4.20 100.00 4.20 420.00 0.21
B 26+600 26+500 4.20 100.00 4.20 420.00 0.06
B 26+500 26+250 4.20 250.00 4.20 1,050.00 0.21
B 26+500 26+250 4.20 250.00 4.20 1,050.00 0.06
B 26+200 26+100 4.20 100.00 4.20 420.00 0.06
B 26+200 26+000 4.20 200.00 4.20 840.00 0.21
B 25+800 25+600 4.20 200.00 4.20 840.00 0.21
B 25+400 25+200 4.20 200.00 4.20 840.00 0.21
B 24+700 24+450 4.20 250.00 4.20 1,050.00 0.06
B 24+300 24+000 4.20 300.00 4.20 1,260.00 0.21
B 24+300 24+000 4.20 300.00 4.20 1,260.00 0.06
B 24+000 23+800 4.20 200.00 4.20 840.00 0.06
B 24+000 23+800 4.20 200.00 4.20 840.00 0.06
B 23+500 23+100 4.20 400.00 4.20 1,680.00 0.21
B 22+900 22+700 4.20 200.00 4.20 840.00 0.21
B 22+600 22+400 4.20 200.00 4.20 840.00 0.21
B 22+000 21+800 4.20 200.00 4.20 840.00 0.06
B 22+000 21+200 4.20 800.00 4.20 3,360.00 0.21
B 21+500 21+400 3.80 3.80 100.00 7.60 760.00 0.06
B 21+500 21+400 4.20 100.00 4.20 420.00 0.06
B 21+400 21+300 4.20 100.00 4.20 420.00 0.06
B 21+200 21+000 3.80 200.00 3.80 760.00 0.06
B 20+600 20+450 4.20 150.00 4.20 630.00 0.06
B 20+600 20+450 4.20 150.00 4.20 630.00 0.06
B 19+800 19+550 3.80 250.00 3.80 950.00 0.06
B 19+800 19+550 4.20 250.00 4.20 1,050.00 0.21
B 19+400 19+000 4.20 400.00 4.20 1,680.00 0.21 RB
B 17+800 17+400 3.80 400.00 3.80 1,520.00 0.06 RUTTING
B 17+800 17+400 4.20 400.00 4.20 1,680.00 0.12 RUTTING
B 17+300 17+150 4.20 150.00 4.20 630.00 0.21
PEKERJAAN SFO
LAJUR PANJANG LEBAR LUAS TEBAL STATUS
NO JALUR STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m P1 / P2
B 17+150 17+000 4.20 150.00 4.20 630.00 0.12 RUTTING
B 17+150 17+000 4.20 150.00 4.20 630.00 0.06 SEGREGASI
B 17+150 17+000 4.20 150.00 4.20 630.00 0.06 SEGREGASI
B 17+000 16+800 4.20 200.00 4.20 840.00 0.21
B 16+800 16+600 4.20 200.00 4.20 840.00 0.21
B 16+400 16+200 4.20 200.00 4.20 840.00 0.21 RB
B 16+400 16+200 4.20 200.00 4.20 840.00 0.06 SEGREGASI
B 16+200 16+000 4.20 200.00 4.20 840.00 0.12 RUTTING
B 15+900 15+700 4.20 200.00 4.20 840.00 0.21 RB
B 15+400 15+100 4.20 300.00 4.20 1,260.00 0.12 RUTTING
B 15+000 14+600 4.20 400.00 4.20 1,680.00 0.21 RB
B 14+600 14+400 4.20 200.00 4.20 840.00 0.21 RB
B 14+000 13+800 4.20 200.00 4.20 840.00 0.21 RB
B 13+000 12+800 4.20 200.00 4.20 840.00 0.21 RB
B 12+800 12+500 4.20 300.00 4.20 1,260.00 0.21
B 12+800 12+500 4.20 300.00 4.20 1,260.00 0.06
B 12+500 12+300 4.20 200.00 4.20 840.00 0.06
B 12+500 12+300 4.20 200.00 4.20 840.00 0.06
B 12+100 12+000 4.20 100.00 4.20 420.00 0.12 RUTTING
B 11+700 11+400 4.20 300.00 4.20 1,260.00 0.12 RUTTING
B 11+750 11+200 4.20 550.00 4.20 2,310.00 0.06
B 11+400 10+900 4.20 500.00 4.20 2,100.00 0.21 RB
B 10+900 10+800 4.20 100.00 4.20 420.00 0.21
B 10+100 9+800 4.20 300.00 4.20 1,260.00 0.06
B 9+800 9+600 3.80 200.00 3.80 760.00 0.06
B 9+800 9+600 4.20 200.00 4.20 840.00 0.21
B 9+800 9+700 4.20 100.00 4.20 420.00 0.21
B 9+800 9+700 4.20 100.00 4.20 420.00 0.06
B 7+900 7+700 3.80 200.00 3.80 760.00 0.06
B 7+600 7+400 3.80 200.00 3.80 760.00 0.06
B 7+600 7+400 4.20 200.00 4.20 840.00 0.21
PEKERJAAN SFO
LAJUR PANJANG LEBAR LUAS TEBAL STATUS
NO JALUR STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m P1 / P2
B 6+000 6+800 4.20 800.00 4.20 3,360.00 0.21
B 6+000 6+800 4.20 800.00 4.20 3,360.00 0.06
B 5+300 5+200 4.20 100.00 4.20 420.00 0.21
B 5+000 4+750 4.20 250.00 4.20 1,050.00 0.21
B 5+000 4+750 4.20 250.00 4.20 1,050.00 0.06
B 4+700 4+600 4.20 100.00 4.20 420.00 0.21
B 4+700 4+600 4.20 100.00 4.20 420.00 0.06
B 2+900 2+800 3.80 100.00 3.80 380.00 0.06
B 2+550 2+450 4.20 100.00 4.20 420.00 0.06 SG
B 2+550 2+450 4.20 100.00 4.20 420.00 0.06 SG
SUB TOTAL JALUR B 16,900.00 70,660.00
TOTAL 27,371.00 114,610.20
PEKERJAAN REKON

LAJUR PANJANG LEBAR LUAS TEBAL SLAB STATUS


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 m bh P1 / P2

A 8+850 8+860 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00


A 9+890 9+965 - 3.80 - - - - 75.00 3.80 285.00 0.30 15.00
A 10+000 10+005 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 10+375 10+390 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
A 10+410 10+420 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
A 11+045 11+065 - 3.80 - - - - 20.00 3.80 76.00 0.30 4.00
A 11+595 11+600 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 12+300 12+305 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 12+375 12+380 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 12+445 12+450 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 12+470 12+475 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 12+980 12+985 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 13+250 13+270 - 3.80 - - - - 20.00 3.80 76.00 0.30 4.00
A 13+990 14+005 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
A 14+100 14+105 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 14+210 14+245 - 3.80 - - - - 35.00 3.80 133.00 0.30 7.00
A 14+540 14+560 - 3.80 - - - - 20.00 3.80 76.00 0.30 4.00
A 14+715 14+725 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
A 14+890 14+905 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
A 15+300 15+305 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 17+150 17+165 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
A 17+200 17+205 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 17+300 17+305 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 17+650 17+655 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 18+350 18+355 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 18+500 18+510 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
A 18+985 18+995 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
A 19+060 19+090 - 3.80 - - - - 30.00 3.80 114.00 0.30 6.00
A 19+230 19+240 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
A 19+300 19+310 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
PEKERJAAN REKON

LAJUR PANJANG LEBAR LUAS TEBAL SLAB STATUS


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 m bh P1 / P2

A 20+585 20+595 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00


A 21+205 21+220 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
A 21+350 21+375 - 3.80 - - - - 25.00 3.80 95.00 0.30 5.00
A 21+500 21+510 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
A 21+770 21+800 - 3.80 - - - - 30.00 3.80 114.00 0.30 6.00
A 23+300 23+315 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
A 23+325 23+330 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 23+400 23+415 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
A 24+085 24+100 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
A 24+710 24+720 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
A 24+900 24+910 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
A 25+100 25+105 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 25+300 25+305 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
A 25+330 25+340 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
A 25+800 25+820 - 3.80 - - - - 20.00 3.80 76.00 0.30 4.00
A 26+200 26+210 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
A Off Ramp Bitung - 3.80 - - - - 150.00 3.80 570.00 0.30 30.00
SUB TOTAL JALUR A 755.00 2,869.00 151.00
PEKERJAAN REKON

LAJUR PANJANG LEBAR LUAS TEBAL SLAB STATUS


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 m bh P1 / P2

B 26+390 26+340 - 3.80 - - - - 50.00 3.80 190.00 0.30 10.00


B 26+300 26+280 - 3.80 - - - - 20.00 3.80 76.00 0.30 4.00
B 25+900 25+895 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 25+130 25+125 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 25+065 25+045 - 3.80 - - - - 20.00 3.80 76.00 0.30 4.00
B 24+850 24+840 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 24+800 24+795 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 24+755 24+745 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 24+250 24+240 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 23+835 23+815 - 3.80 - - - - 20.00 3.80 76.00 0.30 4.00
B 23+675 23+665 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 23+500 23+490 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 23+350 23+345 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 23+200 23+195 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 23+050 23+040 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 21+700 21+690 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 21+615 21+605 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 21+500 21+495 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 21+475 21+465 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 21+450 21+440 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 21+000 20+990 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 20+675 20+670 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 20+625 20+620 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 19+980 19+965 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
B 19+895 19+890 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 19+930 19+920 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 19+915 19+910 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 19+150 19+135 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
B 18+900 18+885 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
B 17+900 17+890 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
PEKERJAAN REKON

LAJUR PANJANG LEBAR LUAS TEBAL SLAB STATUS


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 m bh P1 / P2

B 16+510 16+500 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00


B 15+710 15+700 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 15+675 15+665 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 15+375 15+370 - 3.80 - - - - 5.00 3.80 19.00 0.30 1.00
B 15+145 15+135 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 14+500 14+480 - 3.80 - - - - 20.00 3.80 76.00 0.30 4.00
B 14+460 14+440 - 3.80 - - - - 20.00 3.80 76.00 0.30 4.00
B 13+500 13+485 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
B 13+380 13+370 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 13+350 13+330 - 3.80 - - - - 20.00 3.80 76.00 0.30 4.00
B 12+850 12+835 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
B 12+795 12+785 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 12+450 12+425 - 3.80 - - - - 25.00 3.80 95.00 0.30 5.00
B 12+300 12+290 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 12+100 12+090 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 11+385 11+375 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 11+250 11+235 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
B 11+075 11+065 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 11+000 10+985 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
B 9+250 9+240 - 3.80 - - - - 10.00 3.80 38.00 0.30 2.00
B 9+060 9+045 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
B 8+835 8+810 - 3.80 - - - - 25.00 3.80 95.00 0.30 5.00
B 8+750 8+735 - 3.80 - - - - 15.00 3.80 57.00 0.30 3.00
B 8+450 8+420 - 3.80 - - - - 30.00 3.80 114.00 0.30 6.00

SUB TOTAL JALUR B 680.00 2,584.00 136.00


TOTAL 1,435.00 5,453.00 287.00
PEKERJAAN REKONSTRUKSI FLEXIBLE

RENCANA REALISASI
LAJUR PANJANG LEBAR LUAS TEBAL LAJUR PANJANG LEBAR LUAS TEBAL
NO JALUR STA STA NO JALUR STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m BL L1 L2 L3 L4 BD m m m2 m
A 7+750 7+900 4.30 150.00 4.30 645.00 0.21 - - 0.21 Retak Buaya
A 8+020 8+150 4.30 130.00 4.30 559.00 0.21 - - 0.21 Retak Buaya + Rutting + Banyak Patching
A 8+500 9+250 4.30 690.00 4.30 2,967.00 0.21 - - 0.21 Retak Buaya
A 9+950 10+100 4.30 120.00 4.30 516.00 0.21 - - 0.21
A 11+100 11+300 4.30 180.00 4.30 774.00 0.21 - - 0.21
A 12+385 12+800 4.30 275.00 4.30 1,182.50 0.21 - - 0.21
A 13+300 13+400 4.30 100.00 4.30 430.00 0.21 - - 0.21
A 13+750 14+250 4.30 500.00 4.30 2,150.00 0.21 - - 0.21
A 14+600 14+700 4.30 100.00 4.30 430.00 0.21 - - 0.21
A 14+800 14+932 4.30 132.00 4.30 567.60 0.21 - - 0.21
A 15+750 16+000 4.30 100.00 4.30 430.00 0.21 - - 0.21
A 16+550 16+650 4.30 - 4.30 - 0.21 - - 0.21
A 16+800 17+000 4.30 150.00 4.30 645.00 0.21 - - 0.21
A 17+100 17+400 4.30 200.00 4.30 860.00 0.21 - - 0.21
A 17+550 17+800 4.30 215.00 4.30 924.50 0.21 - - 0.21
A 17+925 18+100 4.30 - 4.30 - 0.21 - - 0.21
A 18+760 18+950 4.30 155.00 4.30 666.50 0.21 - - 0.21
A 19+120 19+200 4.30 80.00 4.30 344.00 0.21 - - 0.21
A 20+890 20+920 4.30 30.00 4.30 129.00 0.21 - - 0.21
A 20+915 21+085 4.30 170.00 4.30 731.00 0.21 - - 0.21
A 21+760 21+860 4.30 100.00 4.30 430.00 0.21 - - 0.21
A 22+872 22+919 4.30 47.00 4.30 202.10 0.21 - - 0.21
A 23+775 23+900 4.30 125.00 4.30 537.50 0.21 - - 0.21
A 24+055 24+305 4.30 195.00 4.30 838.50 0.21 - - 0.21
A 24+400 24+506 4.30 106.00 4.30 455.80 0.21 - - 0.21
A 24+565 24+890 4.30 225.00 4.30 967.50 0.21 - - 0.21
A 25+248 25+473 4.30 155.00 4.30 666.50 0.21 - - 0.21

SUB TOTAL JALUR A 4,430.00 19,049.00 SUB TOTAL JALUR A - -


PEKERJAAN REKONSTRUKSI FLEXIBLE

RENCANA REALISASI
LAJUR PANJANG LEBAR LUAS TEBAL LAJUR PANJANG LEBAR LUAS TEBAL
NO JALUR STA STA NO JALUR STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m BL L1 L2 L3 L4 BD m m m2 m
B 26+465 26+220 4.20 95.00 4.20 399.00 0.21 - - 0.21 RB
B 25+800 25+640 4.20 160.00 4.20 672.00 0.21 - - 0.21 RB
B 25+450 25+350 4.20 50.00 4.20 210.00 0.21 - - 0.21 RB
B 25+075 24+810 4.20 185.00 4.20 777.00 0.21 - - 0.21 RB
B 24+785 24+550 4.20 140.00 4.20 588.00 0.21 - - 0.21 RB
B 24+298 24+188 4.20 40.00 4.20 168.00 0.21 - - 0.21 RB
B 23+435 22+965 4.20 170.00 4.20 714.00 0.21 - - 0.21 RB
B 21+810 21+475 4.20 115.00 4.20 483.00 0.21 - - 0.21 RB
B 19+800 19+700 4.20 100.00 4.20 420.00 0.21 - - 0.21 RB
B 19+250 19+000 4.20 250.00 4.20 1,050.00 0.21 - - 0.21 RB
B 18+800 18+600 4.20 50.00 4.20 210.00 0.21 - - 0.21 RB
B 17+855 17+525 4.20 290.00 4.20 1,218.00 0.21 - - 0.21 RB
B 17+495 17+395 4.20 75.00 4.20 315.00 0.21 - - 0.21 RB
B 17+200 16+755 4.20 370.00 4.20 1,554.00 0.21 - - 0.21 RB
B 15+200 14+900 4.20 190.00 4.20 798.00 0.21 - - 0.21 RB
B 15+900 15+700 4.20 200.00 4.20 840.00 0.21 - - 0.21 RB
B 9+480 9+340 4.20 140.00 4.20 588.00 0.21 - - 0.21 RB

SUB TOTAL JALUR B 2,620.00 11,004.00 SUB TOTAL JALUR B - -


TOTAL 7,050.00 30,053.00 TOTAL - -
PEKERJAAN REKONTRUKSI RIGID
RENCANA REALISASI

LAJUR PANJANG LEBAR LUAS TEBAL SLAB LAJUR PANJANG LEBAR LUAS TEBAL SLAB
NO JALUR STA STA NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 m bh BL L1 L2 L3 L4 BD m m m2 m bh

A 8+950 9+250 - 4.30 - - - 300.00 4.30 1,290.00 0.30 60.00 A - - - 0.30 -


A 9+950 10+100 - 4.30 - - - 150.00 4.30 645.00 0.30 30.00 A - - - 0.30 -
A 11+200 11+300 - 4.30 - - - 100.00 4.30 430.00 0.30 20.00 A - - - 0.30 -
A 12+450 12+490 - 4.30 - - - 40.00 4.30 172.00 0.30 8.00 A - - - 0.30 -
A 12+700 12+850 - 4.30 - - - 150.00 4.30 645.00 0.30 30.00 A - - - 0.30 -
A 14+530 14+580 - 4.30 - - - 50.00 4.30 215.00 0.30 10.00 A - - - 0.30 -
A 14+710 14+720 - 4.30 - - - 10.00 4.30 43.00 0.30 2.00 A - - - 0.30 -
A 15+750 15+900 - 4.30 - - - 150.00 4.30 645.00 0.30 30.00 A - - - 0.30 -
A 16+150 16+200 - 4.30 - - - 50.00 4.30 215.00 0.30 10.00 A - - - 0.30 -
A 16+550 16+650 - 4.30 - - - 100.00 4.30 430.00 0.30 20.00 A - - - 0.30 -
A 16+950 17+100 - 4.30 - - - 150.00 4.30 645.00 0.30 30.00 A - - - 0.30 -
A 17+150 17+250 - 4.30 - - - 100.00 4.30 430.00 0.30 20.00 A - - - 0.30 -
A 17+635 17+670 - 4.30 - - - 35.00 4.30 150.50 0.30 7.00 A - - - 0.30 -
A 18+470 18+550 - 4.30 - - - 80.00 4.30 344.00 0.30 16.00 A - - - 0.30 -
A 18+850 18+865 - 4.30 - - - 15.00 4.30 64.50 0.30 3.00 A - - - 0.30 -
A 18+930 18+950 - 4.30 - - - 20.00 4.30 86.00 0.30 4.00 A - - - 0.30 -
A 21+760 21+960 - 4.30 - - - 200.00 4.30 860.00 0.30 40.00 A - - - 0.30 -
A 23+750 23+780 - 4.30 - - - 30.00 4.30 129.00 0.30 6.00 A - - - 0.30 -
A 24+105 24+125 - 4.30 - - - 20.00 4.30 86.00 0.30 4.00 A - - - 0.30 -
A 24+135 24+170 - 4.30 - - - 35.00 4.30 150.50 0.30 7.00 A - - - 0.30 -
A 24+600 24+700 - 4.30 - - - 100.00 4.30 430.00 0.30 20.00 A - - - 0.30 -
A 24+850 24+920 - 4.30 - - - 70.00 4.30 301.00 0.30 14.00 A - - - 0.30 -
A 25+350 25+420 - 4.30 - - - 70.00 4.30 301.00 0.30 14.00 A - - - 0.30 -
SUB TOTAL JALUR A 2,025.00 8,707.50 405.00 SUB TOTAL JALUR A - - -
PEKERJAAN REKONTRUKSI RIGID
RENCANA REALISASI

LAJUR PANJANG LEBAR LUAS TEBAL SLAB LAJUR PANJANG LEBAR LUAS TEBAL SLAB
NO JALUR STA STA NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 m bh BL L1 L2 L3 L4 BD m m m2 m bh

B 26+370 26+440 - 4.30 - - - 70.00 4.30 301.00 0.30 14.00 B - - - 0.30 -


B 26+410 26+380 - 4.30 - - - 30.00 4.30 129.00 0.30 6.00 B - - - 0.30 -
B 26+370 26+280 - 4.30 - - - 90.00 4.30 387.00 0.30 18.00 B - - - 0.30 -
B 25+400 25+350 - 4.30 - - - 50.00 4.30 215.00 0.30 10.00 B - - - 0.30 -
B 25+020 25+000 - 4.30 - - - 20.00 4.30 86.00 0.30 4.00 B - - - 0.30 -
B 24+860 24+800 - 4.30 - - - 60.00 4.30 258.00 0.30 12.00 B - - - 0.30 -
B 24+695 24+600 - 4.30 - - - 95.00 4.30 408.50 0.30 19.00 B - - - 0.30 -
B 24+230 24+160 - 4.30 - - - 70.00 4.30 301.00 0.30 14.00 B - - - 0.30 -
B 23+450 23+300 - 4.30 - - - 150.00 4.30 645.00 0.30 30.00 B - - - 0.30 -
B 23+150 23+000 - 4.30 - - - 150.00 4.30 645.00 0.30 30.00 B - - - 0.30 -
B 21+770 21+750 - 4.30 - - - 20.00 4.30 86.00 0.30 4.00 B - - - 0.30 -
B 21+650 21+450 - 4.30 - - - 200.00 4.30 860.00 0.30 40.00 B - - - 0.30 -
B 18+800 18+650 - 4.30 - - - 150.00 4.30 645.00 0.30 30.00 B - - - 0.30 -
B 17+750 17+710 - 4.30 - - - 40.00 4.30 172.00 0.30 8.00 B - - - 0.30 -
B 17+450 17+425 - 4.30 - - - 25.00 4.30 107.50 0.30 5.00 B - - - 0.30 -
B 17+050 17+025 - 4.30 - - - 25.00 4.30 107.50 0.30 5.00 B - - - 0.30 -
B 16+950 16+900 - 4.30 - - - 50.00 4.30 215.00 0.30 10.00 B - - - 0.30 -
B 15+850 15+830 - 4.30 - - - 20.00 4.30 86.00 0.30 4.00 B - - - 0.30 -
B 15+190 15+140 - 4.30 - - - 50.00 4.30 215.00 0.30 10.00 B - - - 0.30 -
B 15+100 15+060 - 4.30 - - - 40.00 4.30 172.00 0.30 8.00 B - - - 0.30 -
B 15+000 14+980 - 4.30 - - - 20.00 4.30 86.00 0.30 4.00 B - - - 0.30 -
B 14+700 14+690 - 4.30 - - - 10.00 4.30 43.00 0.30 2.00 B - - - 0.30 -
B 12+875 12+865 - 4.30 - - - 10.00 4.30 43.00 0.30 2.00 B - - - 0.30 -
B 11+250 11+215 - 4.30 - - - 35.00 4.30 150.50 0.30 7.00 B - - - 0.30 -
B 10+960 10+935 - 4.30 - - - 25.00 4.30 107.50 0.30 5.00 B - - - 0.30 -

SUB TOTAL JALUR B 1,505.00 6,471.50 301.00 SUB TOTAL JALUR B - - -


TOTAL 3,530.00 15,179.00 706.00 TOTAL - - -
REALISASI
LAJUR PANJANG LEBAR LUAS TEBAL
NO JALUR TANGGAL STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m
A 20-Aug 3+465 3+535 5.31 70.00 5.31 371.70 0.08
A 25-Nov 3+760 3+955 4.07 195.00 4.07 793.65 0.06
A 3-Dec 5+205 5+350 3.90 145.00 3.90 565.50 0.06
12-Dec 6+375 6+555 3.86 180.00 3.86 694.80 0.06
A 6-Apr 6+750 6+780 3.82 30.00 3.82 114.73 0.05 BPJT
A 19-Nov 8+375 8+425 4.01 50.00 4.01 200.50 0.12
A 27-Nov 8+635 8+685 4.03 50.00 4.03 201.50 0.12
A 24-Nov 9+350 9+400 3.81 50.00 3.81 190.50 0.12
A 23-Nov 9+615 9+810 3.71 195.00 3.71 723.45 0.07
A 17-Nov 9+730 9+820 4.01 90.00 4.01 360.90 0.12
A 7-Apr 11+300 11+330 3.89 30.00 3.89 116.83 0.06 BPJT
A 1-Dec 11+600 11+675 3.98 75.00 3.98 298.50 0.13
A 18-Nov 12+105 12+235 4.02 130.00 4.02 522.60 0.12
A 9-Jun 15+105 15+209 3.75 104.00 3.75 390.00 0.07
A 19-Jun 15+350 15+435 4.05 85.00 4.05 344.25 0.12
A 20-Jun 15+435 15+485 3.98 50.00 3.98 199.00 0.11
A 21-Jun 15+485 15+570 3.89 85.00 3.89 330.65 0.11
A 7-Jun 15+750 15+850 3.40 100.00 3.40 340.00 0.11
A 8-Jun 15+850 15+940 3.33 90.00 3.33 299.70 0.11
A 29-May 15+700 15+785 3.65 85.00 3.65 310.25 0.11
A 30-May 15+785 15+870 3.69 85.00 3.69 313.65 0.11
A 31-May 15+870 15+955 3.70 85.00 3.70 314.50 0.11
A 5-Jun 15+955 16+035 3.67 80.00 3.67 293.60 0.11
A 11-Nov 17+370 17+430 4.19 60.00 4.19 251.40 0.13
A 6-Apr 18+350 18+380 4.06 30.00 4.06 121.71 0.06 BPJT
14-Dec 22+945 23+045 4.03 100.00 4.03 403.00 0.13
11-Dec 23+045 23+145 4.03 100.00 4.03 403.00 0.13
A 28-Nov 23+145 23+195 4.04 50.00 4.04 202.00 0.13
13-Dec 23+195 23+295 3.87 100.00 3.87 387.00 0.13
A 12-Oct Off Ramp Bitung 3.61 90.00 3.61 324.90 0.15

A 13-Oct Off Ramp Bitung 3.54 72.00 3.54 254.88 0.15

A 21-Mar Off Ramp Kunciran 1 4.30 30.00 4.30 129.00 0.07 BPJT

A 20-Oct On Ramp Tengerang 3.18 60.00 3.18 190.80 0.07

A 20-Oct Off Ramp Bitung (Sisi Kanan) 3.58 166.00 3.58 594.28 0.08

A 21-Oct Off Ramp Bitung (Sisi Kiri) 3.86 70.00 3.86 270.20 0.15

A 9-Nov On Ramp Kb Jeruk 3.84 112.00 3.84 430.08 0.06


REALISASI
LAJUR PANJANG LEBAR LUAS TEBAL
NO JALUR TANGGAL STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m

3,179.00 12,253.01
REALISASI
LAJUR PANJANG LEBAR LUAS TEBAL
NO JALUR TANGGAL STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m
B 21-Mar On Ramp Bitung 2 4.20 15.00 4.20 63.00 0.07 BPJT
B 18-Oct On Ramp Bitung 3.89 90.00 3.89 350.10 0.14

B 12-Sep 25+285 25+177 3.94 108.00 3.94 425.52 0.06


B 5-Apr 25+250 25+220 4.25 30.00 4.25 127.42 0.06 BPJT
24+700 24+685
B 10-Sep 3.78 190.00 3.78 718.20 0.06 IRI
24+675 24+500
B 13-Dec 24+295 24+095 3.77 130.00 3.77 490.10 0.05

B 15-Dec 23+800 23+700 3.82 100.00 3.82 382.00 0.06

B 25-May 20+600 20+525 3.60 75.00 3.60 270.00 0.11 Segrasi


B 26-May 20+525 20+450 3.63 75.00 3.63 272.25 0.11 Segrasi
B 12-Dec 19+150 19+000 4.02 150.00 4.02 603.00 0.12
B 26-Mar 18+500 18+465 4.31 35.00 4.31 150.85 0.12 BPJT
B 22-Nov 17+865 17+772 3.99 93.00 3.99 371.07 0.13
B 5-Apr 17+500 17+470 4.04 30.00 4.04 121.27 0.06 BPJT
B 6-Nov 16+340 16+220 4.01 120.00 4.01 481.20 0.13
B 7-Nov 16+220 16+075 4.04 145.00 4.04 585.80 0.12
B 8-Nov 16+565 16+463 4.04 102.00 4.04 412.08 0.13
B 2-Dec 15+900 15+800 3.80 100.00 3.80 380.00 0.12
B 10-Jun 15+405 15+309 4.07 96.00 4.07 390.72 0.11
B 12-Jun 15+309 15+209 3.35 100.00 3.35 335.00 0.12
B 14-Jun 14+900 14+800 3.92 100.00 3.92 392.00 0.13
B 13-Jun 14+800 14+700 4.04 100.00 4.04 404.00 0.12
B 15-Jun 14+700 14+630 4.07 70.00 4.07 284.90 0.13
B 21-Nov 13+550 13+445 4.03 105.00 4.03 423.15 0.12
B 30-Nov 12+830 12+770 4.03 60.00 4.03 241.80 0.13
B 5-Dec 12+600 12+450 3.69 150.00 3.69 553.50 0.06
B 6-Dec 12+450 12+350 3.60 100.00 3.60 360.00 0.06
B 23-Jun 12+058 11+992 3.52 66.00 3.52 232.32 0.13
B 25-Mar 11+985 11+945 4.09 40.00 4.09 163.60 0.06 BPJT
B 24-Jun 11+550 11+470 4.01 80.00 4.01 320.80 0.12
B 25-Jun 11+470 11+390 4.08 80.00 4.08 326.40 0.12
B 21-Jul 11+390 11+310 4.12 80.00 4.12 329.60 0.12
B 22-Jul 11+310 11+230 3.77 80.00 3.77 301.60 0.12
B 24-Jul 11+230 11+150 3.89 80.00 3.89 311.20 0.12
B 25-Jul 11+150 11+070 3.72 80.00 3.72 297.60 0.12
B 26-Jul 11+070 11+000 3.55 70.00 3.55 248.50 0.12
REALISASI
LAJUR PANJANG LEBAR LUAS TEBAL
NO JALUR TANGGAL STA STA JENIS KERUSAKAN KETERANGAN
BL L1 L2 L3 L4 BD m m m2 m
B 10-Aug 11+000 10+848 3.68 152.00 3.68 559.36 0.13
B 26-Nov 10+848 10+788 4.01 60.00 4.01 240.60 0.12
B 7-Apr 10+450 10+420 4.01 30.00 4.01 120.30 0.06 BPJT
B 20-Nov 9+790 9+730 4.04 60.00 4.04 242.40 0.12
B 25-Mar 9+730 9+700 4.03 30.00 4.03 120.75 0.07 BPJT
B 15-Oct 9+240 9+150 3.84 95.00 3.84 364.80 0.06
B 19-Oct 8+985 8+830 3.77 159.00 3.77 599.43 0.06
B 22-Oct 8+795 8+700 4.23 95.00 4.23 401.85 0.06
B 4-Dec 8+615 8+460 4.01 155.00 4.01 621.55 0.06
B 23-Oct Tapper Masuk TI 3.94 122.00 3.94 480.68 0.07

SUB TOTAL JALUR B 4,083.00 15,872.28


TOTAL 7,262.00 28,125.29
REALISASI REKONSTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS TEBAL SLAB


NO JALUR TANGGAL STA STA KETERANGAN

BL L1 L2 L3 m m m2 m bh

A 16-Sep 8+840 8+850 3.75 10.40 3.75 39.00 0.30 2.00


A 21-Oct 14+210 14+245 3.50 35.80 3.50 125.30 0.30 7.00
A 21-Oct 14+265 14+275 3.45 10.80 3.45 37.26 0.30 2.00
A 02-Sep-23 17+055 17+075 3.48 20.70 3.48 72.04 0.30 4.00
A 25-Aug 17+210 17+220 3.72 10.80 3.72 40.18 0.30 2.00
A 2-Dec 17+730 17+770 4.04 40.10 4.04 162.00 0.30 8.00
A 18-Jul 18+470 18+480 3.52 11.20 3.52 39.42 0.30 2.00
A 18-Jul 18+495 18+505 3.51 10.00 3.51 35.10 0.30 2.00
A 25-Nov 18+845 18+895 3.85 50.20 3.85 193.27 0.30 10.00
A 28-Jul 18+985 18+995 3.54 10.20 3.54 36.11 0.30 2.00
A 28-Jul 19+060 19+075 3.50 15.20 3.50 53.20 0.30 3.00
A 14-Jul 19+320 19+330 3.80 10.90 3.80 41.42 0.30 2.00
A 1-Aug 19+390 19+400 3.85 12.50 3.85 48.13 0.30 2.00
A 20-Jun 20+585 20+595 3.52 11.50 3.52 40.48 0.30 2.00
A 22-Jun 21+205 21+220 3.75 15.10 3.75 56.63 0.30 3.00
A 25-Oct 21+190 21+220 3.76 30.00 3.76 112.80 0.30 6.00
A 23-Oct 21+220 21+280 3.46 60.40 3.46 208.98 0.30 12.00
A 20-Oct 21+280 21+340 3.47 60.00 3.47 208.20 0.30 12.00
A 16-Oct 21+340 21+390 3.61 51.00 3.61 184.11 0.30 10.00
A 24-Jun 21+345 21+370 3.78 26.50 3.78 100.17 0.30 5.00
A 7-Nov 21+390 21+445 3.92 55.00 3.92 215.60 0.30 11.00
A 10-Jul 21+500 21+510 3.85 10.50 3.85 40.43 0.30 2.00
A 5-Nov 21+510 21+570 3.61 61.00 3.61 220.27 0.30 12.00
A 25-Jul 21+745 21+775 3.41 30.90 3.41 105.37 0.30 6.00
A 2-Nov 21+775 21+790 4.23 13.95 4.23 59.01 0.30 3.00
A 29-Oct 21+760 21+840 3.65 80.00 3.65 292.00 0.30 16.00
A 12-Jun 23+265 23+290 3.80 25.85 3.80 98.23 0.30 5.00
REALISASI REKONSTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS TEBAL SLAB


NO JALUR TANGGAL STA STA KETERANGAN

BL L1 L2 L3 m m m2 m bh

A 12-Jun 23+310 23+320 3.71 10.90 3.71 40.44 0.30 2.00


A 14-Jun 23+335 23+345 3.45 10.80 3.45 37.26 0.30 2.00
A 15-Dec 23+765 23+815 3.58 50.00 3.58 179.00 0.30 10.00
A 20-Sep 24+025 24+075 3.67 50.00 3.67 183.50 0.30 10.00
A 9-Jun 24+075 24+090 3.80 15.80 3.80 60.04 0.30 3.00
A 22-Sep 24+075 24+125 3.28 50.25 3.28 164.82 0.30 10.00
A 27-Sep 24+125 24+165 3.84 40.00 3.84 153.60 0.30 8.00
A 4-Oct 24+195 24+220 3.81 25.30 3.81 96.39 0.30 5.00
A 18-Sep 24+220 24+255 3.74 35.10 3.74 131.27 0.30 7.00
A 27-Oct 24+255 24+305 3.75 50.25 3.75 188.44 0.30 10.00
A 29-Sep 24+600 24+650 3.73 50.00 3.73 186.50 0.30 10.00
A 2-Oct 24+650 24+705 3.69 55.00 3.69 202.95 0.30 11.00
A 11-Nov 24+705 24+755 3.74 50.10 3.74 187.37 0.30 10.00
A 5-Jun 24+710 24+720 3.49 11.10 3.49 38.74 0.30 2.00
A 7-Dec 24+755 24+805 3.71 50.00 3.71 185.50 0.30 10.00
A 12-Dec 24+805 24+850 3.80 43.80 3.80 166.44 0.30 9.00
A 15-Sep 24+895 24+935 3.67 41.40 3.67 151.94 0.30 8.00
A 7-Jun 24+920 24+930 3.54 10.60 3.54 37.52 0.30 2.00
A 6-Oct 25+265 25+315 3.70 50.50 3.70 186.85 0.30 10.00
A 7-Jul 25+280 25+290 3.42 11.00 3.42 37.62 0.30 2.00
A 7-Jul 25+310 25+320 3.37 10.30 3.37 34.71 0.30 2.00
A 10-Oct 25+315 25+370 3.90 55.00 3.90 214.50 0.30 11.00
A 9-Nov 25+420 25+470 3.74 50.20 3.74 187.75 0.30 10.00
A 5-Jul 25+770 25+790 3.41 22.45 3.41 76.55 0.30 4.00
A 12-Jul 26+200 26+210 3.34 10.95 3.34 36.57 0.30 2.00
A 17-Jun Underpass Bitung 4.01 91.00 4.01 364.91 0.30 18.00
A 16-Dec Off Ramp Karang Tengah Barat 4.33 44.60 4.33 193.12 1.30 9.00
REALISASI REKONSTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS TEBAL SLAB


NO JALUR TANGGAL STA STA KETERANGAN

BL L1 L2 L3 m m m2 m bh

SUB TOTAL JALUR A 1,776.90 6,589.01 350.00


B 31-Oct 26+405 26+335 3.43 69.00 3.43 236.67 0.30 14.00
B 20-Aug 26+400 26+370 3.80 30.00 3.80 114.00 0.30 6.00
B 3-Nov 26+335 26+290 3.82 45.00 3.82 171.90 0.30 9.00
B 26-Aug 26+370 26+340 3.72 33.40 3.72 124.25 0.30 6.00
B 13-Aug 26+330 26+285 3.67 45.30 3.67 166.25 0.30 9.00
B 6-Nov 26+150 26+120 3.80 29.85 3.80 113.46 0.30 6.00
B 31-Jul 25+925 25+915 3.55 8.60 3.55 30.53 0.30 2.00
B 31-Jul 25+905 25+895 3.50 11.15 3.50 39.03 0.30 2.00
B 24-Jul 25+830 25+820 3.65 10.90 3.65 39.79 0.30 2.00
B 5-Oct 25+450 25+400 4.00 51.80 4.00 207.20 0.30 10.00
B 11-Oct 25+400 25+350 3.85 50.00 3.85 192.50 0.30 10.00
B 11-Sep 25+220 25+210 3.50 10.80 3.50 37.80 0.30 2.00
B 6-Jul 25+135 25+125 3.64 10.30 3.64 37.49 0.30 2.00
B 4-Jul 25+065 25+055 3.52 10.85 3.52 38.19 0.30 2.00
B 26-Sep 24+915 24+865 3.80 50.20 3.80 190.76 0.30 10.00
B 3-Oct 24+865 24+825 3.90 40.00 3.90 156.00 0.30 8.00
B 30-Sep 24+905 24+880 3.51 25.20 3.51 88.45 0.30 5.00
B 20-Jul 24+800 24+790 3.62 10.90 3.62 39.46 0.30 2.00
B 13-Jul 24+755 24+725 3.58 30.60 3.58 109.55 0.30 6.00
B 14-Sep 24+725 24+690 3.49 35.00 3.49 122.15 0.30 7.00
B 17-Jul 24+710 24+700 3.64 10.60 3.64 38.58 0.30 2.00
B 19-Sep 24+690 24+655 3.50 35.00 3.50 122.50 0.30 7.00
B 9-Sep 24+695 24+685 3.77 9.70 3.77 36.57 0.30 2.00
B 17-Jul 24+685 24+675 3.63 10.90 3.63 39.57 0.30 2.00
B 9-Sep 24+625 24+615 3.70 11.30 3.70 41.81 0.30 2.00
REALISASI REKONSTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS TEBAL SLAB


NO JALUR TANGGAL STA STA KETERANGAN

BL L1 L2 L3 m m m2 m bh

B 21-Sep 24+260 24+210 3.71 50.60 3.71 187.73 0.30 10.00


B 8-Jul 24+250 24+210 3.70 40.85 3.70 151.15 0.30 8.00
B 10-Nov 23+920 23+870 3.71 50.00 3.71 185.50 0.30 10.00
B 22-Nov 23+870 23+820 3.69 50.80 3.69 187.45 0.30 10.00
B 19-Jun 23+835 23+805 3.76 31.30 3.76 117.69 0.30 6.00
B 10-Jun 23+675 23+660 3.60 15.63 3.60 56.27 0.30 3.00
B 13-Jun 23+530 23+520 3.81 10.90 3.81 41.53 0.30 2.00
B 18-Oct 23+435 23+385 3.80 50.40 3.80 191.52 0.30 10.00
B 20-Oct 23+385 23+335 3.90 50.00 3.90 195.00 0.30 10.00
B 6-Jun 23+340 23+330 3.71 11.00 3.71 40.81 0.30 2.00
B 24-Oct 23+335 23+285 4.10 50.75 4.10 208.08 0.30 10.00
B 26-Oct 23+285 23+235 4.13 50.20 4.13 207.33 0.30 10.00
B 28-Nov 23+235 23+180 3.98 55.00 3.98 218.90 0.30 11.00
B 8-Jun 23+180 23+175 3.63 5.90 3.63 21.42 0.30 1.00
B 8-Jun 23+165 23+155 3.60 10.90 3.60 39.24 0.30 2.00
B 25-Jun 23+080 23+070 3.66 11.30 3.66 41.36 0.30 2.00
B 24-Nov 22+980 22+940 3.95 40.00 3.95 158.00 0.30 8.00
B 8-Nov 22+540 22+490 4.00 50.00 4.00 200.00 0.30 10.00
B 23-Jun 21+725 21+695 3.73 30.80 3.73 114.88 0.30 6.00
B 1-Dec 21+690 21+650 3.83 39.80 3.83 152.43 0.30 7.00
B 6-Dec 21+650 21+595 3.76 55.50 3.76 208.68 0.30 11.00
B 11-Dec 21+595 21+575 3.83 20.00 3.83 76.60 0.30 4.00
B 13-Dec 21+575 21+535 3.82 40.00 3.82 152.80 0.30 8.00
B 14-Dec 21+535 21+480 3.72 53.40 3.72 198.65 0.30 11.00
B 21-Jun 21+635 21+605 3.65 30.90 3.65 112.79 0.30 6.00
B 15-Jun 21+555 21+545 3.52 10.70 3.52 37.66 0.30 2.00
B 15-Jun 21+535 21+520 3.60 15.50 3.60 55.80 0.30 3.00
REALISASI REKONSTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS TEBAL SLAB


NO JALUR TANGGAL STA STA KETERANGAN

BL L1 L2 L3 m m m2 m bh

B 15-Jul 21+495 21+485 3.73 10.65 3.73 39.72 0.30 2.00


B 15-Jul 21+470 21+440 3.72 30.50 3.72 113.46 0.30 6.00
B 2-Aug 21+445 21+410 2.62 33.80 2.62 88.56 0.30 6.00
B 3-Dec 21+445 21+392 3.74 63.50 3.74 237.49 0.30 12.00
B 22-Jul 21+420 21+410 3.90 10.50 3.90 40.95 0.30 2.00
B 22-Jul 21+345 21+335 3.60 11.10 3.60 39.96 0.30 2.00
B 19-Oct 21+280 21+220 3.47 60.00 3.47 208.20 0.30 12.00
B 5-Aug 20+680 20+670 3.73 11.00 3.73 41.03 0.30 2.00
B 26-Jul 19+985 19+970 3.64 15.90 3.64 57.88 0.30 3.00
B 29-Jul 19+940 19+930 3.87 10.20 3.87 39.47 0.30 2.00
B 29-Jul 19+910 19+890 3.77 20.80 3.77 78.42 0.30 4.00
B 15-Aug 19+195 19+185 3.53 11.00 3.53 38.83 0.30 2.00
B 15-Aug 19+160 19+145 3.58 15.80 3.58 56.56 0.30 3.00
B 9-Dec 17+025 17+000 3.64 25.00 3.64 91.00 0.30 5.00
B 28-Oct 17+000 16+920 3.52 80.00 3.52 281.60 0.30 16.00
B 4-Nov 16+920 16+850 3.54 70.00 3.54 247.80 0.30 14.00
B 7-Oct 10+180 10+165 2.95 16.50 2.95 48.68 0.30 3.00
B 14-Oct 9+240 9+215 3.80 25.90 3.80 98.42 0.30 5.00
B 14-Oct 9+180 9+175 3.45 8.00 3.45 27.60 0.30 1.00
B 14-Oct 9+160 9+150 3.50 9.20 3.50 32.20 0.30 2.00
B 23-Sep 9+065 9+050 3.52 15.30 3.52 53.86 0.30 3.00
B 23-Sep 8+995 8+985 3.48 10.80 3.48 37.58 0.30 2.00
B 16-Sep 8+830 8+795 3.51 36.10 3.51 126.71 0.30 7.00
B 21-Oct 8+760 8+745 3.85 15.10 3.85 58.14 0.30 3.00
B 12-Aug 8+455 8+440 3.68 15.90 3.68 58.51 0.30 3.00
B 19-Aug 8+420 8+410 3.56 10.90 3.56 38.80 0.30 2.00
B 3-Aug GT Kebon Jeruk 2 2.65 19.90 2.65 52.73 0.30 4.00
REALISASI REKONSTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS TEBAL SLAB


NO JALUR TANGGAL STA STA KETERANGAN

BL L1 L2 L3 m m m2 m bh

B 4-Aug GT Karawaci 4 5.78 9.70 5.78 56.07 0.30 2.00


B 7-Oct Off Ramp Tangerang 2.65 52.20 2.65 138.33 0.30 10.00
B 23-Nov On Ramp Kunciran 2 3.40 45.10 3.40 153.34 0.30 9.00
B 26-Nov On Ramp Kunciran 2 3.67 45.10 3.67 165.52 0.30 9.00
B 29-Nov On Ramp Kunciran 2 4.50 45.10 4.50 202.95 0.30 9.00
B 8-Dec On Ramp Kunciran 2 3.61 20.05 3.61 72.38 0.30 4.00
B 14-Dec On Ramp Kunciran 2 3.25 20.05 3.25 65.16 0.30 4.00

SUB TOTAL JALUR B 2,519.13 9,281.61 493.00


TOTAL 4,296.03 15,870.62 843.00
LOKASI RETAK BUAYA
LAJUR PANJANG LEBAR LUAS TEBAL
NO JALUR STA STA
BL L1 L2 L3 L4 BD m m m2 m
1 A 6+780 7+150 3.80 370.00 3.80 1,406.00 0.06
2 A 8+510 8+635 4.00 125.00 4.00 500.00 0.06
3 A 8+875 9+240 4.00 365.00 4.00 1,460.00 0.06
4 A 11+160 11+280 4.00 120.00 4.00 480.00 0.06
5 A 11+925 12+000 4.00 75.00 4.00 300.00 0.06
6 A 13+760 14+130 4.00 370.00 4.00 1,480.00 0.06
7 A 14+800 14+900 4.00 100.00 4.00 400.00 0.06
8 A 15+730 15+830 4.00 100.00 4.00 400.00 0.06
9 A 17+050 17+310 4.00 260.00 4.00 1,040.00 0.06
10 A 17+560 17+655 4.00 95.00 4.00 380.00 0.06

1,980.00 7,846.00
1 B 21+305 21+205 4.00 100.00 4.00 400.00 0.06
2 B 19+750 19+600 3.80 150.00 3.80 570.00 0.06
3 B 18+800 18+650 4.00 150.00 2.00 300.00 0.06
LOKASI RETAK BUAYA
LAJUR PANJANG LEBAR LUAS TEBAL
NO JALUR STA STA
BL L1 L2 L3 L4 BD m m m2 m
4 B 15+210 14+900 4.00 310.00 4.00 1,240.00 0.06

SUB TOTAL JALUR B 710.00 2,510.00


TOTAL 2,690.00 10,356.00
PEKERJAAN REKONTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS TEBAL SLAB


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 m bh

A Off Ramp KTB 2.50 10.00 2.50 25.00 0.30 2.00


A Off Ramp KTB 3.80 30.00 3.80 114.00 0.30 6.00
A 14+045 14+055 3.80 10.00 3.80 38.00 0.30 2.00
A 14+210 14+245 3.80 35.00 3.80 133.00 0.30 7.00
A 14+265 14+275 3.80 10.00 3.80 38.00 0.30 2.00
A 14+540 14+560 3.80 20.00 3.80 76.00 0.30 4.00
A 14+715 14+725 3.80 10.00 3.80 38.00 0.30 2.00
A 14+890 14+905 3.80 15.00 3.80 57.00 0.30 3.00
A 17+645 17+655 3.80 10.00 3.80 38.00 0.30 2.00
A 17+665 17+675 3.80 10.00 3.80 38.00 0.30 2.00
A 18+760 18+895 4.00 135.00 4.00 540.00 0.30 27.00
A 21+340 21+390 4.00 50.00 4.00 200.00 0.30 10.00
A 21+760 21+835 4.00 75.00 4.00 300.00 0.30 15.00
A 24+255 24+305 4.00 50.00 4.00 200.00 0.30 10.00
A 24+400 24+506 4.00 106.00 4.00 424.00 0.30 21.00
A 25+315 25+370 4.00 55.00 4.00 220.00 0.30 11.00
A 25+370 25+473 4.00 103.00 4.00 412.00 0.30 21.00
Off Ramp Bitung 4.01 100.00 4.01 401.00 0.30 20.00
On Ramp Catleya 3.80 40.00 3.80 152.00 0.30 8.00

SUB TOTAL JALUR A 874.00 3,444.00 175.00


B 26+465 26+290 4.00 175.00 4.00 700.00 0.30 35.00
B 25+400 25+350 4.00 50.00 4.00 200.00 0.30 10.00
B 23+435 23+235 4.00 200.00 4.00 800.00 0.30 40.00
B 24+095 24+085 3.80 10.00 3.80 38.00 0.30 2.00
B 21+695 21+430 4.00 265.00 4.00 1,060.00 0.30 53.00
PEKERJAAN REKONTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS TEBAL SLAB


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 m bh

B 21+300 21+175 4.00 125.00 4.00 500.00 0.30 25.00


B 19+800 19+665 4.00 135.00 4.00 540.00 0.30 27.00
B 17+905 17+895 3.80 10.00 3.80 38.00 0.30 2.00
B 17+875 17+865 3.80 10.00 3.80 38.00 0.30 2.00
B 16+525 16+495 3.80 30.00 3.80 114.00 0.30 6.00
B 15+710 15+700 3.80 10.00 3.80 38.00 0.30 2.00
B 15+695 15+685 3.80 10.00 3.80 38.00 0.30 2.00
B 15+665 15+655 3.80 10.00 3.80 38.00 0.30 2.00
B 15+635 15+610 3.80 25.00 3.80 95.00 0.30 5.00
B 15+145 15+115 3.80 30.00 3.80 114.00 0.30 6.00
B 9+260 9+240 3.80 20.00 3.80 76.00 0.30 4.00
B 9+200 9+190 3.80 10.00 3.80 38.00 0.30 2.00
B 9+170 9+160 3.80 10.00 3.80 38.00 0.30 2.00
B 8+760 8+745 3.80 15.00 3.80 57.00 0.30 3.00
B On Ramp Bitung 2 5.00 50.60 5.00 253.00 0.30 10.00
B On Ramp Bitung 2 5.00 50.60 5.00 253.00 0.30 10.00
B On Ramp Bitung 2 4.00 50.60 4.00 202.40 0.30 10.00
B Off Ramp dari arah merak 7.00 40.00 7.00 280.00 0.30 8.00
B Sebelum GT Bitung 1 10.00 25.00 10.00 250.00 0.30 5.00
B Setelah GT Bitung 1 8.00 20.00 8.00 160.00 0.30 4.00
B GT Tangerang Lama 3.80 35.00 3.80 133.00 0.30 7.00
B Off Ramp Kembangan 3.80 110.00 3.80 418.00 0.30 22.00
-
SUB TOTAL JALUR B 1,531.80 6,509.40 306.00
TOTAL 2,405.80 9,953.40 481.00
PEKERJAAN REKONTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS TEBAL SLAB KETERANGAN


NO JALUR STA STA

BL L1 m m m2 m bh

1 A 9+840 9+870 - 3.80 30.00 3.80 114.00 0.30 6.00


2 A 9+910 9+985 - 3.80 75.00 3.80 285.00 0.30 15.00
3 A 10+000 10+010 - 3.80 10.00 3.80 38.00 0.30 2.00
4 A 10+270 10+290 - 3.80 20.00 3.80 76.00 0.30 4.00
5 A 10+325 10+360 - 3.80 35.00 3.80 133.00 0.30 7.00
6 A 10+370 10+390 - 3.80 20.00 3.80 76.00 0.30 4.00
7 A 10+405 10+415 - 3.80 10.00 3.80 38.00 0.30 2.00
8 A Off Ramp KTB 2.50 10.00 2.50 25.00 0.30 2.00
9 A Off Ramp KTB 3.80 30.00 3.80 114.00 0.30 6.00
10 A 11+045 11+065 - 3.80 20.00 3.80 76.00 0.30 4.00
11 A 11+575 11+585 - 3.80 10.00 3.80 38.00 0.30 2.00
12 A 11+595 11+605 - 3.80 10.00 3.80 38.00 0.30 2.00
13 A 12+430 12+440 - 3.80 10.00 3.80 38.00 0.30 2.00
14 A 12+460 12+470 - 3.80 10.00 3.80 38.00 0.30 2.00
15 A 13+220 13+225 - 3.80 5.00 3.80 19.00 0.30 1.00
16 A 13+235 13+270 - 3.80 35.00 3.80 133.00 0.30 7.00
17 A 13+965 14+035 - 3.80 70.00 3.80 266.00 0.30 14.00
18 A 14+045 14+055 - 3.80 10.00 3.80 38.00 0.30 2.00
19 A 14+210 14+245 - 3.80 35.00 3.80 133.00 0.30 7.00
20 A 14+265 14+275 - 3.80 10.00 3.80 38.00 0.30 2.00
21 A 14+540 14+560 - 3.80 20.00 3.80 76.00 0.30 4.00
22 A 14+715 14+725 - 3.80 10.00 3.80 38.00 0.30 2.00
23 A 14+890 14+905 - 3.80 15.00 3.80 57.00 0.30 3.00
24 A 17+645 17+655 - 3.80 10.00 3.80 38.00 0.30 2.00
25 A 17+665 17+670 - 3.80 5.00 3.80 19.00 0.30 1.00
SUB TOTAL JALUR A 525.00 1,982.00 105.00
1 B 17+905 17+900 - 3.80 5.00 3.80 19.00 0.30 1.00
2 B 17+875 17+870 - 3.80 5.00 3.80 19.00 0.30 1.00
3 B 16+525 16+495 - 3.80 30.00 3.80 114.00 0.30 6.00
4 B 15+710 15+705 - 3.80 5.00 3.80 19.00 0.30 1.00
5 B 15+695 15+690 - 3.80 5.00 3.80 19.00 0.30 1.00
6 B 15+665 15+655 - 3.80 10.00 3.80 38.00 0.30 2.00
7 B 15+635 15+610 - 3.80 25.00 3.80 95.00 0.30 5.00
8 B 15+145 15+115 - 3.80 30.00 3.80 114.00 0.30 6.00
9 B 14+525 14+510 - 3.80 15.00 3.80 57.00 0.30 3.00
10 B 14+455 14+430 - 3.80 25.00 3.80 95.00 0.30 5.00
11 B 14+420 14+410 - 3.80 10.00 3.80 38.00 0.30 2.00
12 B 13+550 13+525 - 3.80 25.00 3.80 95.00 0.30 5.00
13 B 13+400 13+390 - 3.80 10.00 3.80 38.00 0.30 2.00
14 B 13+330 13+315 - 3.80 15.00 3.80 57.00 0.30 3.00
15 B 12+875 12+860 - 3.80 15.00 3.80 57.00 0.30 3.00
16 B 12+825 12+815 - 3.80 10.00 3.80 38.00 0.30 2.00
17 B 12+800 12+790 - 3.80 10.00 3.80 38.00 0.30 2.00
18 B 12+505 12+495 - 3.80 10.00 3.80 38.00 0.30 2.00
19 B 12+455 12+425 - 3.80 30.00 3.80 114.00 0.30 6.00
20 B 12+280 12+270 - 3.80 10.00 3.80 38.00 0.30 2.00
21 B 12+240 12+230 - 3.80 10.00 3.80 38.00 0.30 2.00
22 B 12+135 12+125 - 3.80 10.00 3.80 38.00 0.30 2.00
23 B 11+385 11+375 - 3.80 10.00 3.80 38.00 0.30 2.00
24 B 11+305 11+280 - 3.80 25.00 3.80 95.00 0.30 5.00
25 B 11+080 11+055 - 3.80 25.00 3.80 95.00 0.30 5.00
26 B 11+010 11+000 - 3.80 10.00 3.80 38.00 0.30 2.00
PEKERJAAN REKONTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS TEBAL SLAB KETERANGAN


NO JALUR STA STA

BL L1 m m m2 m bh

27 B 10+000 9+920 - 3.80 80.00 3.80 304.00 0.30 16.00


28 B 9+260 9+240 - 3.80 20.00 3.80 76.00 0.30 4.00
29 B 9+065 9+050 - 3.80 15.00 3.80 57.00 0.30 3.00
30 B 8+760 8+745 - 3.80 15.00 3.80 57.00 0.30 3.00
31 B Off Ramp dari arah merak - 7.00 40.00 7.00 280.00 0.30 8.00
32 B Sebelum GT Bitung 1 - 10.00 25.00 10.00 250.00 0.30 5.00
33 B Setelah GT Bitung 1 - 8.00 20.00 8.00 160.00 0.30 4.00
34 B GT Tangerang Lama - 3.80 35.00 3.80 133.00 0.30 7.00

SUB TOTAL JALUR B 640.00 2,799.00 128.00 -


TOTAL 1,165.00 4,781.00 233.00 -
PEKERJAAN REKONTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS SLAB


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 bh

A 8+840 8+850 - 3.80 - - - - 10.00 3.80 38.00 2.00


A 9+840 9+870 - 3.80 - - - - 30.00 3.80 114.00 6.00
A 9+910 9+985 - 3.80 - - - - 75.00 3.80 285.00 15.00
A 10+000 10+010 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 10+270 10+290 - 3.80 - - - - 20.00 3.80 76.00 4.00
A 10+325 10+360 - 3.80 - - - - 35.00 3.80 133.00 7.00
A 10+370 10+390 - 3.80 - - - - 20.00 3.80 76.00 4.00
A 10+405 10+415 - 3.80 - - - - 10.00 3.80 38.00 2.00
A Off Ramp KTB 2.50 - - - - 10.00 2.50 25.00 2.00
A Off Ramp KTB 3.80 - - - - 30.00 3.80 114.00 6.00
A 11+045 11+065 - 3.80 - - - - 20.00 3.80 76.00 4.00
A 11+575 11+585 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 11+595 11+605 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 12+430 12+440 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 12+460 12+470 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 13+220 13+225 - 3.80 - - - - 5.00 3.80 19.00 1.00
A 13+235 13+270 - 3.80 - - - - 35.00 3.80 133.00 7.00
A 13+965 14+035 - 3.80 - - - - 70.00 3.80 266.00 14.00
A 14+045 14+055 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 14+210 14+245 - 3.80 - - - - 35.00 3.80 133.00 7.00
A 14+265 14+275 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 14+540 14+560 - 3.80 - - - - 20.00 3.80 76.00 4.00
A 14+715 14+725 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 14+890 14+905 - 3.80 - - - - 15.00 3.80 57.00 3.00
PEKERJAAN REKONTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS SLAB


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 bh

A 17+055 17+075 - 3.80 - - - - 20.00 3.80 76.00 4.00


A 17+210 17+220 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 17+645 17+655 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 17+665 17+670 - 3.80 - - - - 5.00 3.80 19.00 1.00
A 18+470 18+480 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 18+495 18+505 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 18+985 18+995 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 19+060 19+075 - 3.80 - - - - 15.00 3.80 57.00 3.00
A 19+180 19+320 - 3.80 - - - - 140.00 3.80 532.00 28.00
A 19+320 19+330 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 19+390 19+400 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 20+585 20+595 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 21+205 21+220 - 3.80 - - - - 15.00 3.80 57.00 3.00
A 21+455 21+480 - 3.80 - - - - 25.00 3.80 95.00 5.00
A 21+500 21+510 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 21+755 21+785 - 3.80 - - - - 30.00 3.80 114.00 6.00
A 23+265 23+290 - 3.80 - - - - 25.00 3.80 95.00 5.00
A 23+335 23+345 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 23+600 23+700 - 3.80 - - - - 100.00 3.80 380.00 20.00
A 24+075 24+090 - 3.80 - - - - 15.00 3.80 57.00 3.00
A 24+710 24+720 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 24+920 24+930 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 25+280 25+290 - 3.80 - - - - 10.00 3.80 38.00 2.00
A 25+310 25+320 - 3.80 - - - - 10.00 3.80 38.00 2.00
PEKERJAAN REKONTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS SLAB


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 bh

A 25+770 25+790 - 3.80 - - - - 20.00 3.80 76.00 4.00


A 26+200 26+210 - 3.80 - - - - 10.00 3.80 38.00 2.00
A Off Ramp Bitung - 3.80 - - - - 190.00 3.80 722.00 38.00
A On Ramp Catleya - 3.80 - - - - 40.00 3.80 152.00 8.00
SUB TOTAL JALUR A 1,310.00 4,965.00 262.00
B 26+400 26+340 - 3.80 - - - - 60.00 3.80 228.00 12.00
B 26+265 26+220 - 3.80 - - - - 45.00 3.80 171.00 9.00
B 25+950 25+935 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 25+830 25+820 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 25+135 25+125 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 25+065 25+055 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 24+800 24+790 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 24+755 24+725 - 3.80 - - - - 30.00 3.80 114.00 6.00
B 24+710 24+700 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 24+680 24+670 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 24+260 24+220 - 3.80 - - - - 40.00 3.80 152.00 8.00
B 23+835 23+805 - 3.80 - - - - 30.00 3.80 114.00 6.00
B 23+675 23+660 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 23+530 23+520 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 23+340 23+330 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 23+165 23+155 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 23+080 23+070 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 21+725 21+695 - 3.80 - - - - 30.00 3.80 114.00 6.00
B 21+615 21+585 - 3.80 - - - - 30.00 3.80 114.00 6.00
PEKERJAAN REKONTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS SLAB


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 bh

B 21+555 21+545 - 3.80 - - - - 10.00 3.80 38.00 2.00


B 21+530 21+515 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 21+495 21+485 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 21+470 21+440 - 3.80 - - - - 30.00 3.80 114.00 6.00
B 20+515 20+505 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 19+985 19+970 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 19+940 19+930 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 19+910 19+890 - 3.80 - - - - 20.00 3.80 76.00 4.00
B 19+400 19+250 - 3.80 - - - - 150.00 3.80 570.00 30.00
B 19+195 19+185 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 19+170 19+155 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 17+905 17+900 - 3.80 - - - - 5.00 3.80 19.00 1.00
B 17+875 17+870 - 3.80 - - - - 5.00 3.80 19.00 1.00
B 16+525 16+495 - 3.80 - - - - 30.00 3.80 114.00 6.00
B 15+710 15+705 - 3.80 - - - - 5.00 3.80 19.00 1.00
B 15+695 15+690 - 3.80 - - - - 5.00 3.80 19.00 1.00
B 15+665 15+655 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 15+635 15+610 - 3.80 - - - - 25.00 3.80 95.00 5.00
B 15+145 15+115 - 3.80 - - - - 30.00 3.80 114.00 6.00
B 14+900 14+835 - 3.80 - - - - 65.00 3.80 247.00 13.00
B 14+700 14+690 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 14+525 14+510 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 14+455 14+430 - 3.80 - - - - 25.00 3.80 95.00 5.00
B 14+420 14+410 - 3.80 - - - - 10.00 3.80 38.00 2.00
PEKERJAAN REKONTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS SLAB


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 bh

B 13+550 13+525 - 3.80 - - - - 25.00 3.80 95.00 5.00


B 13+400 13+390 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 13+330 13+315 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 12+875 12+860 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 12+825 12+815 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 12+800 12+790 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 12+505 12+495 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 12+455 12+425 - 3.80 - - - - 30.00 3.80 114.00 6.00
B 12+280 12+270 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 12+240 12+230 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 12+135 12+125 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 11+385 11+375 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 11+305 11+280 - 3.80 - - - - 25.00 3.80 95.00 5.00
B 11+080 11+055 - 3.80 - - - - 25.00 3.80 95.00 5.00
B 11+010 11+000 - 3.80 - - - - 10.00 3.80 38.00 2.00
B 10+000 9+920 - 3.80 - - - - 80.00 3.80 304.00 16.00
B 9+260 9+240 - 3.80 - - - - 20.00 3.80 76.00 4.00
B 9+065 9+050 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 8+830 8+795 - 3.80 - - - - 35.00 3.80 133.00 7.00
B 8+760 8+745 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 8+455 8+440 - 3.80 - - - - 15.00 3.80 57.00 3.00
B 8+420 8+410 - 3.80 - - - - 10.00 3.80 38.00 2.00
B GT Kb. Jeruk - 3.80 - - - - 15.00 3.80 57.00 3.00
B Off Ramp dari arah merak - 7.00 - - - - 40.00 7.00 280.00 8.00
PEKERJAAN REKONTRUKSI RIGID

LAJUR PANJANG LEBAR LUAS SLAB


NO JALUR STA STA KETERANGAN

BL L1 L2 L3 L4 BD m m m2 bh

B Sebelum GT Bitung 1 - 10.00 - - - - 25.00 10.00 250.00 5.00


B Setelah GT Bitung 1 - 8.00 - - - - 20.00 8.00 160.00 4.00
B GT Karawaci 4 - 3.80 - - - - 10.00 3.80 38.00 2.00
B GT Tangerang Lama - 3.80 - - - - 35.00 3.80 133.00 7.00

SUB TOTAL JALUR B 1,490.00 6,029.00 298.00


TOTAL 2,800.00 10,994.00 560.00