CHAPTER-7
INVENTORY MANAGEMENT
Introduction
0702. It is neither economical nor available space will permit holding inventory of
whole range of naval stores. Therefore, inventory should be planned. Steps in
planning inventory should be as follows:
a. Step-1. Prepare WH wise CAL taking data from ships’ warrants. Data
as recorded on ship’s warrants i.e. WNS {F (NS) 1}, WOSEF {F (NS) 2} and
SAL {F (NS) 3} are to be compiled on a prescribed format known as CAL. An
abridged example of the CAL format is given in Annex D to Chapter 5. CAL
indicates:
(c) Availability
Ship’s Warrant
0703. Planning ship board inventory begins with the determination of ship’s
requirements of naval stores. Individual requirements are then compiled in NSD to
determine BN requirements of naval stores known as Consolidated Allowance List
(CAL). Ship’s requirements are to be recorded on following three documents
generically known as warrants:
WNS {F(NS) 1}
0704. These are the stores which are neither an element of ship
system/equipment/fittings nor their spare parts but are required for their up keep,
ship’s husbandry and crew habitability, facilitating crew activity (e.g. cotton rugs,
scrubbing brush, sanitary brush, mop, glass cleaner, soap, detergent, metal polish,
varnishing material, paint, painting gears, ropes, grease, lubricant, navigational
instrument and gear, RIGGING, flags and buntings and so forth.) Ship’s shall
prepare three sets of WNS and forward to NHQ (DNS) for approval WNS. NHQ
(DNS) shall retain on copy and send one copy each to NSD and ship. Some helpful
sources in identifying requirements are:
a. Rigging Warrant
b. Paint Scheme
7-2
RESTRICTED
RESTRICTED
WOSEF {F(NS) 2}
0705. WOSEF {F(NS) 2} contains the record of ship board system (e.g. Fire Control
System, Propulsion System, Missile System etc and their units like engine, gearbox,
shaft, propeller in propulsion system; Equipment (e.g. Gyro, Sonar, Speed Log,
Communication Equipment etc) and Fittings (e.g. Anchor) which come along with the
ship through new construction or off-the-shelf buy.
SAL {F(NS) 3}
0706. SAL {F(NS) 3} contains list of spare parts, components, sub-assemblies and
their authorized ship board stock for operational maintenance and depot stock as
back up of ship board stock i.e. the stock of spares, components, sub-assemblies in
NSD. Functional relation between ship’s stock and depot stock is shown in the figure
below. In this functional (logistical) relation, it is the ship who determines items and
quantity required to be maintained on board and the quantity to be held in the depot
as its back up. Such determination shall be based on 3 years requirements (item and
quantity). Three year’s quantity is divided into ‘on board stock’ and ‘depot stock’. For
example; a ship has determined the 3 years requirements of a ‘seal’ to be 60 in
number. Now the ship decides to keep 30% (18 in number) ‘on board’ (this quantity
is also depot’s minimum inventory level) and 70% (42 in number) in the ‘depot’ (this
quantity is also depot’s maximum inventory level). Thus:
The ratio between ‘on board stock’ and ‘depot stock’ is variable at the discretion of
ship/establishment/organization because some ships may not have ideal storage
facilities on board.
7-3
RESTRICTED
RESTRICTED
Figure 7.1: Functional Relation between ship’s Stock and Depot Stock
Ship’ Stock
Demand
Supply
Depot Stock
0707. WNS {F(NS) 1}. Ship/Establishment shall prepare two sets of this document;
one set for NSD and one set for ship. WH wise customer catalogue is the most
useful source of information to prepare this document. This has made the
preparation of WNS so simple. A customer can view complete list of supplies in BN,
download the catalogue on the intranet or collect soft copy from NSD, select the
essential items and delete non-essential items and insert quantity requirements
(quarterly). WNS of similar class or type of ship can be useful guide in preparing
WNS.
a. New Ship Construction. Ship builder shall prepare two sets of this
document for BN. Procurement Directorate shall assign this responsibility to
ship builder through contractual agreement. BN Project Team Leader/Project
Officer, if so nominated, shall validate this document by endorsing his
signature. BN Project Management Team shall assist ship builder in preparing
this document but has the responsibility to ensure that the ship builder
prepares a complete document. Both the sets are to be sent to NSD Ctg for
review. CO NSD Ctg after necessary correction and shall endorse approval
retain one set on board and send another set to the ship’s CO. CO NSD Ctg
7-4
RESTRICTED
RESTRICTED
shall ensure that information from this document are fed into the data base as
required by NSD’s IMS.
a. New Ship Construction. Ship builder shall prepare two sets of this
document for BN. Procurement Directorate shall assign this responsibility to
ship builder through contractual agreement. BN Project Team Leader/Project
Officer, if so nominated, shall validate this document by endorsing his
signature. BN Project Management Team shall assist ship builder in preparing
this document but has the responsibility to ensure that the ship builder
prepares a complete document. Both the sets are to be sent to NSD Ctg for
review. CO NSD Ctg after necessary review and shall endorse approval retain
one set on board and send another set to the ship’s CO. CO NSD Ctg shall
ensure that information from this document are fed into the data base as
required by NSD’s IMS.
7-5
RESTRICTED
RESTRICTED
d. While preparing SAL, the out dated concept “Just in Case” must be
avoided. This concept only contributes to build up excess inventory and
multifaceted problems in inventory management.
7-6
RESTRICTED
RESTRICTED
Storage in the
Warehouse
Inspection Notification
Delivery to Depot
Inspection
7-7
RESTRICTED
RESTRICTED
(2) CMD has to ensure before delivery of goods whether the items
are already in the depot inventory list:
7-8
RESTRICTED
RESTRICTED
division.
7-9
RESTRICTED