Project Title: Marina Village

ITP DETAILS - Inspection and Test Plan for Survey Works Revision: C1 CN: SSC-ITP-SUR-0001
Inspection Responsibility
Item No Activity Description Reference Acceptance Criteria Remarks
Contract
3rd Party RSG
or

1.0 Document Review


Project Specification - Division 1(General Requirements), Approved Calibration Approved Documents
1.1 Method Statement, Survey Instrument Calibration Certificate R R RH
Certificate SSC-CHK-DRMR-0001
Approved Documents
1.2 Approved Drawings Project Specification - Division 1(General Requirements) R R RH
SSC-CHK-DRMR-0001
2.0 Material Receiving
SSC-CHK-DRMR-0001,
2.1 Trimble R750 and R780 Approved Method Statement, Approved Calibration Certificate H W W
Calibration Certificate
2.2 Other Tools (Steel Measuring Tape, Prisms, etc) Approved Method Statement SSC-CHK-DRMR-0001 S S S
3.0 Execution
Project Specification - Division 1(General Requirements), Section 01 73 00(Execution) Survey Report,
3.1 Survey setting out and Level H H H
under 3.3, Approved Drawing SSC-CHK-EXE-0001
Project Specification - Division 1(General Requirements), Section 01 73 00(Execution) Survey Report,
3.1a Benchmarks and Coordinates H H H
under 3.3, Approved Drawing SSC-CHK-EXE-0001
Project Specification - Division 1(General Requirements), Section 01 73 00(Execution) Survey Report,
3.1b Survey Reports H H H
under 3.3, Approved Drawing SSC-CHK-EXE-0001
4.0 Testing/Commissioning/Final Inspection
Project Specification - Division 1(General Requirements), Section 01 73 00(Execution) Survey Report,
4.1 Final Survey/As-built H H H
under 3.3 SSC-CHK-TAC-0001
Prepared By: Reviewed By: Approved By:

Name: Name: Name:

Designation: Designation : Designation:

Signature: Signature: Signature:

Date: Date: Date:

Legend:
1. H (Hold Point) - QA/QC team shall be notified for the schedule of inspection or test in advance. It should also be carried with the QA/QC team client representative.
2. S (Surveillance) - QA/QC team to monitor work in progress without notice from the construction organization or random check selection.
3. W (Witness) - QA/QC team shall be notified for the schedule of inspection or test in advance if the QA/QC team client representative can't come on time for inspection, the activity can proceed.
4. R (Review) - Required qualification/certification/reports shall be submitted for the QA/QC team review and approval.
5. RH - Review and Approval