Checklist No:

Project: Marina Village SSC-CHK-EXE-0002

Document Title: Inspection Checklist for Execution of Work (Earthworks) Date:


S/N Acceptance Criteria References Pass Fail N/A Remarks
3.0 Execution of Work
3.1 Survey setting-out and Level As per Approved drawing, Section 01 73 00 clause 3.3
3.1a Engage a land surveyor to lay out the Work using accepted surveying practices. Section 01 73 00 clause 3.3
Establish benchmarks and control points to set lines and levels at each story of construction
3.1b Section 01 73 00 clause 3.3
and elsewhere as needed to locate each element of Project.
Establish dimensions within tolerances indicated. Do not scale Design Drawings to obtain
3.1c Section 01 73 00 clause 3.3
required dimensions
Site Improvements: Locate and lay out Site improvements, including pavements, grading, fill
3.1d Section 01 73 00 clause 3.3
and topsoil placement, utility slopes, and rim and invert elevations
Building Lines and Levels: Locate and lay out control lines and levels for structures, building
foundations, column grids, and floor levels, including those required for mechanical and
3.1e Section 01 73 00 clause 3.3
electrical work. Transfer survey markings and elevations for use with control lines and levels.
Level foundations and piers from two or more locations.
Record Log: Maintain a log of layout control work. Record deviations from required lines and
levels. Include beginning and ending dates and times of surveys, weather conditions, name and
3.1f Section 01 73 00 clause 3.3
duty of each survey party member, and types of instruments and tapes used. Make the log
available for reference by the Engineer.
Final Survey: The Contractor shall prepare a final survey of the Site showing all significant
features on the Site. Include on the survey a certification, signed by the surveyor, that principal
measures, boundaries, lines, and levels of the Project are accurately positioned as shown on
3.1g Section 01 73 00 clause 3.3
the survey. Include all boundary lines, survey markers, streets, Site improvements and utilities,
existing improvements and significant vegetation, adjoining properties, acreage, grade
contours, and the distance and bearing from a Site corner to a legal point, off the Site.
3.2 Existing Utilities Section 31 10 00
Verify that utilities have been disconnected and capped before proceeding with site
3.2a Section 31 10 00 clause 3.3
clearing.
Locate, identify, disconnect, and seal or cap utilities indicated to be removed or
3.2b Section 31 10 00 clause 3.3
abandoned in place.
3.2c Notify Engineer not less than two days in advance of proposed utility interruptions. Section 31 10 00 clause 3.3
3.2d Do not proceed with utility interruptions without Engineer's written permission. Section 31 10 00 clause 3.3
3.3 Clearing and Grubbing Section 31 10 00
Remove obstructions, trees, shrubs, and other vegetation to permit installation of new
3.3a construction. Do not remove trees, shrubs, and other vegetation indicated to remain Section 31 10 00 clause 3.3
or to be relocated.
Grind down stumps and remove roots, obstructions, and debris to a depth of 18 inches
3.3b Section 31 10 00 clause 3.3
(450 mm) below exposed subgrade.
Chip removed tree branches and stockpile in areas approved by Engineer or dispose of
3.3c Section 31 10 00 clause 3.3
off-site.
Place fill material in horizontal layers not exceeding a loose depth of 8 inches (200 mm)
3.3d Section 31 10 00 clause 3.3
and compact each layer to a density equal to adjacent original ground.
3.4 Excavation Section 31 20 00
3.4a Unclassified Excavation: Section 31 20 00 clause 3.4
If excavated materials intended for fill and backfill include unsatisfactory soil materials and
3.4a1 Section 31 20 00 clause 3.4
rock, replace with satisfactory soil materials.
Remove rock to lines and grades indicated to permit installation of permanent construction
3.4a2 Section 31 20 00 clause 3.4
without exceeding the following dimensions:
3.4a2.1 24 inches (600 mm) outside of concrete forms other than at footings. Section 31 20 00 clause 3.4
3.4a2.2 12 inches (300 mm) outside of concrete forms at footings. Section 31 20 00 clause 3.4
3.4a2.3 6 inches (150 mm) outside of minimum required dimensions of concrete cast against grade. Section 31 20 00 clause 3.4
Checklist No:
Project: Marina Village SSC-CHK-EXE-0002

Document Title: Inspection Checklist for Execution of Work (Earthworks) Date:


S/N Acceptance Criteria References Pass Fail N/A Remarks
Outside dimensions of concrete walls indicated to be cast against rock without orms or exterior
3.4a2.4 Section 31 20 00 clause 3.4
waterproofing treatments.
3.4a2.5 6 inches (150 mm) beneath bottom of concrete slabs-on-grade. Section 31 20 00 clause 3.4
6 inches (150 mm) beneath pipe in trenches, and the greater of 24 inches (600 mm) wider than
3.4a2.6 Section 31 20 00 clause 3.4
pipe or 42 inches (1065 mm) wide.
3.4b Classified Excavation: Section 31 20 00 clause 3.4
Earth excavation includes excavating pavements and obstructions visible on surface;
3.4b1 underground structures, utilities, and other items indicated to be removed; together with soil, Section 31 20 00 clause 3.4
boulders, and other materials not classified as rock or unauthorized excavation.
Rock excavation includes removal and disposal sf rock. Remove rock to lines and subgrade
3.4b2 elevations indicated to permit installation of permanent construction without exceeding the Section 31 20 00 clause 3.4
following dimensions:
3.4b2.1 24 inches (600 mm) outside of concrete forms other than at footings. Section 31 20 00 clause 3.4
3.4b2.2 12 inches (300 mm) outside of concrete forms at footings. Section 31 20 00 clause 3.4
3.4b2.3 6 inches (150 mm) outside of minimum required dimensions of concrete cast against grade. Section 31 20 00 clause 3.4
Outside dimensions of concrete walls indicated to be cast against rock without orms or exterior
3.4b2.4 Section 31 20 00 clause 3.4
waterproofing treatments.
3.4b2.5 6 inches (150 mm) beneath bottom of concrete slabs-on-grade. Section 31 20 00 clause 3.4
6 inches (150 mm) beneath pipe in trenches, and the greater of 24 inches (600 mm) wider than
3.4b2.6 Section 31 20 00 clause 3.4
pipe or 42 inches (1065 mm) wide.
3.5 Backfill and Compaction Section 31 23 00
Ensure that excavations and areas to be filled are free from loose soil, rubbish; untreated
3.5a Section 31 23 00 clause 4.4
sabkha and standing water.
The Contractor must take all necessary precautions to ensure stability of adjacent structures.
Place and compact fill against structures, membranes or buried services in a sequence and
3.5b manner that will ensure stability and avoid damage. Filling around pipes and cables shall Section 31 23 00 clause 4.4
commence with carefully placed fine material to cover the pipe or cable completely before the
normal infilling is placed.
3.5c Plant employed for transporting, laying and compacting must be suited to the type of material. Section 31 23 00 clause 4.4
Differing materials shall be laid separately so that only one type of material occurs in each
3.5d Section 31 23 00 clause 4.4
layer.
Where, during the progress of work, the difference in level between adjacent areas of filling
exceeds 600mm, cut into the edge of the higher filling to form benches having a minimum
3.5e Section 31 23 00 clause 4.4
width of 600mm and a height equivalent to the depth of a layer of compacted filling. Spread
and compact new fill so as to ensure maximum continuity with the previous filling.
The surface of filling to receive concrete shall be accurately levelled or graded to falls and
3.5f Section 31 23 00 clause 4.4
finished smooth to provide a time base for the concrete work following.
All filling to make up level for floors shall be compacted to 95% Mod. AASHTO density. Sand
3.5g replacement tests shall be carried out on each layer of fill, as required by the Engineer but in Section 31 23 00 clause 4.4
any case not less than 1 tests every layer for each 900m of fill.
3.6 Field Density Test Section 31 23 00
3.6a For Subgrade: Section 31 23 00 clause 1.6
One test to determine the plasticity index according to ASTM D4318 for every 500 m²
3.6a.1 Section 31 23 00 clause 1.6
completed layer.
3.6b For Backfill and Fill: Section 31 23 00 clause 1.6
One test for classification of soil according to ASTM D2487 for every 1000 sq.m for every
3.6b.1 Section 31 23 00 clause 1.6
completed layer.
Checklist No:
Project: Marina Village SSC-CHK-EXE-0002

Document Title: Inspection Checklist for Execution of Work (Earthworks) Date:


S/N Acceptance Criteria References Pass Fail N/A Remarks
One test of field density according to ASTM D1556 or D2167 as appropriate for every 500 m for
3.6b.2 Section 31 23 00 clause 1.6
every completed layer but not less than one test per day for each type of material placed.
3.6c For Subbase and Base Coarse: Section 31 23 00 clause 1.6
One test of gradation of material for each 500 m completed Subbase/base course in accordance
3.6c.1 Section 31 23 00 clause 1.6
with ASTM C136 or AASHTO T27.
One test of field density according to ASTM D1556 or D2167 as appropriate for each 500 m for
3.6c.2 Section 31 23 00 clause 1.6
every completed layer but not less than one test per day.
One test to determine the plasticity index according to ASTM D4318 for every 500 m²
3.6c.3 Section 31 23 00 clause 1.6
completed layer.
3.7 Protection Section 31 20 00
Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep
3.7a Section 31 20 00 clause 3.23
free of trash and debris.
Repair and re-establish grades to specified tolerances where completed or partially completed
3.7b surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent Section 31 20 00 clause 3.23
construction operations or weather conditions.
Scarify or remove and replace soil material to depth as directed by Engineer; reshape and
3.7c Section 31 20 00 clause 3.23
recompact.
Where settling occurs before Project correction period elapses, remove finished surfacing,
3.7d Section 31 20 00 clause 3.23
backfill with additional soil material, compact, and reconstruct surfacing.
Restore appearance, quality, and condition of finished surfacing to match adjacent work, and
3.7e Section 31 20 00 clause 3.23
eliminate evidence of restoration to greatest extent possible.

Prepared By: Reviewed By: AMAALA RSG Representative

Name: Name: Name:

Signature: Signature: Signature:

Date: Date: Date: