Evaluation of tender detail to maintain efficient work sequence - Long
1 Precast Concrete lead item Focus on approval of planting schedule, assesment of necessary 2 Plantation Schedule documentation and procedurus, consider climate conditions - Long lead item
3 Visa Procedures Take early action not to face delays on progress
Rather than bits and pieces, arrange work sequence in a planned
4 Overall approach to site progress manner
Get a solid understanding of the procedure and consider when
5 QA/QC Procedures scheduling
Get a solid understanding of the procedure and consider when
6 HSE Procedures scheduling
7 Benchmarks A List of items that require benchmarks to be decided.