Cost Calculations
Cost Calculations
£ 250,645,463.64 £ 250,645,463.64
Indirect Cost
Type of cost % of cost Total cost
£ -
CUT & FILL
Cut Durations
Cut Quantities m3 Cost Rate (L.E/m3) Total Cost (L.E) Duration
11607.99 60 696479.4 6
2.22 60 133.2 1
999.37 60 59962.2 1
7702.87 60 462172.2 2
147976.95 60 8878617 11
147071.48 60 8824288.8 11
15808.01 60 948480.6 4
22227.11 60 1333626.6 4
18325.68 60 1099540.8 5
225272.81 60 13516368.6 15
135379.42 60 8122765.2 9
87.79 60 5267.4 1
16013.48 60 960808.8 5
31103.92 60 1866235.2 6
7837.28 60 470236.8 4
0 60 0 0
0 60 0 0
10891.61 60 653496.6 3
84180.86 60 5050851.6 9
119894.05 60 7193643 12
83451.19 60 5007071.4 9
23198.04 60 1391882.4 4
1,109,032.13 £ 66,541,927.80 122
Fill Durations
Fill Quantities m3 Cost Rate (L.E/m3) Total Cost (L.E) Duration
13171.38 80 1053710.4 4
35321.9 80 2825752 6
25639.83 80 2051186.4 5
3528.78 80 282302.4 2
39.47 80 3157.6 1
342.51 80 27400.8 1
343.1 80 27448 1
0.6 80 48 1
671.39 80 53711.2 1
0 80 0 0
7095.56 80 567644.8 4
17562.28 80 1404982.4 5
10466.72 80 837337.6 6
0 80 0 0
110898.25 80 8871860 10
211767.27 80 16941381.6 11
98617.97 80 7889437.6 10
16281.81 80 1302544.8 5
0 80 0 0
0 80 0 0
0 80 0 0
0 80 0 0
551,748.82 £ 44,139,905.60 73
Gr
Cost / Day Stations (1000 m)
263427.6
Station 1
470958.666666667
410237.28
Station 2
141151.2
3157.6
Station 3
27400.8
27448
Station 4
48
53711.2
Station 5
0
141911.2
Station 6
280996.48
139556.266666667
Station 7
0
887186
Station 8
0
0
Station 9
Station 9
260508.96
0
Station 10
0
0
Station 11
0
SUM Of One Layer
Stations (1000 m)
Station 1
Of Subgrade H59:H74 (15 cm)
Station 2
Station 3
Station 4
Station 5
Station 6
Station 7
Station 8
Station 9
Station 10
Station 11
SUM Of One Layer
G
Stations (1000 m)
Station 1
Station 2
Station 3
Station 4
Station 5
Station 6
Station 6
Station 7
Station 8
Station 9
Station 10
Station 11
SUM Of One Layer
Grading
Compac
Cost / Day Stations (1000 m) Phases (500 m)
24062.5 Phase 1
Station 1
24062.5 Phase 2
24062.5 Phase 1
Station 2
24062.5 Phase 2
28875 Phase 1
Station 3
25666.6666667 Phase 2
24062.5 Phase 1
Station 4
26000 Phase 2
26000 Phase 1
Station 5
11700 Phase 2
26000 Phase 1
Station 6
26000 Phase 2
26000 Phase 1
Station 7
26000 Phase 2
26000 Phase 1
Station 8
26000 Phase 2
26000 Phase 1
Station 9
26000 Phase 2
26000 Phase 1
Station 10
26000 Phase 2
26000 Phase 1
Station 11
27194 Phase 2 (348.64 m)
SUM Of One Layer
Compacting D
Cost / Day Stations (1000 m) Phases (500 m)
24062.5 Phase 1
Station 1
24062.5 Phase 2
24062.5 Phase 1
Station 2
24062.5 Phase 2
48125 Phase 1
Station 3
12916.6666667 Phase 2
19375 Phase 1
Station 4
25833.3333333 Phase 2
26014.8888889 Phase 1
Station 5
51314.6666667 Phase 2
12916.6666667 Phase 1
Station 6
25833.3333333 Phase 2
25833.3333333 Phase 1
Station 7
25958.5 Phase 2
26328.7777778 Phase 1
Station 8
26053.8333333 Phase 2
25833.3333333 Phase 1
Station 9
Station 9
25957 Phase 2
26334.3333333 Phase 1
Station 10
26085.1111111 Phase 2
25833.3333333 Phase 1
Station 11
27020.4166667 Phase 2 (348.64 m)
SUM Of One Layer
Compacting
Cost / Day Stations (1000 m) Phases (500 m)
32083.3333333 Phase 1
Station 1
32083.3333333 Phase 2
32083.3333333 Phase 1
Station 2
32083.3333333 Phase 2
24062.4444444 Phase 1
Station 3
19375 Phase 2
25833.3333333 Phase 1
Station 4
25833.3333333 Phase 2
26014.8148148 Phase 1
Station 5
51311.1111111 Phase 2
38750 Phase 1
Station 6
25833.3333333 Phase 2
25833.3333333 Phase 1
Station 7
25958.4444444 Phase 2
26328.8148148 Phase 1
Station 8
26053.7777778 Phase 2
25833.3333333 Phase 1
Station 9
25957.037037 Phase 2
26334.2962963 Phase 1
Station 10
26085.1111111 Phase 2
25833.3333333 Phase 1
Station 11
27020.4444444 Phase 2 (348.64 m)
SUM Of One Layer
Compacting
Cost / Day Stations (1000 m) Phases (500 m)
48125 Phase 1
Station 1
48125 Phase 2
48125 Phase 1
Station 2
48125 Phase 2
48124.8888889 Phase 1
Station 3
38750 Phase 2
38750 Phase 1
Station 4
38750 Phase 2
39022.2222222 Phase 1
Station 5
25655.5555556 Phase 2
38750 Phase 1
Station 6
Station 6
38750 Phase 2
38750 Phase 1
Station 7
38937.6666667 Phase 2
39493.2222222 Phase 1
Station 8
39080.6666667 Phase 2
38750 Phase 1
Station 9
38935.5555556 Phase 2
39501.4444444 Phase 1
Station 10
39127.6666667 Phase 2
38750 Phase 1
Station 11
27020.4444444 Phase 2 (348.64 m)
SUM Of One Layer
Compacting £ 58,540,263.29
ourse (8 cm)
Total Cost (L.E) Duration Cost / Day Stations (1000 m)
£ 1,564,640.00 2 782320
Station 1
£ 1,564,640.00 2 782320
£ 1,564,640.00 2 782320
Station 2
£ 1,463,040.00 2 731520
£ 1,361,440.00 2 680720
Station 3
£ 1,310,640.00 2 655320
£ 1,259,840.00 2 629920
Station 4
£ 1,259,840.00 2 629920
£ 1,268,689.36 2 634344.68
Station 5
£ 1,278,351.52 2 639175.76
£ 1,261,038.88 2 630519.44
Station 6
£ 1,158,240.00 2 579120
£ 1,056,640.00 2 528320
Station 7
£ 1,184,656.00 2 592328
£ 1,284,000.48 2 642000.24
Station 8
£ 1,270,599.44 2 635299.72
£ 1,259,840.00 2 629920
Station 9
Station 9
£ 1,265,864.88 2 632932.44
£ 1,284,274.80 2 642137.4
Station 10
£ 1,272,123.44 2 636061.72
£ 1,259,840.00 2 629920
Station 11
£ 878,484.40 2 439242.2
£ 26,766,723.20 44 SUM
Stations (1000 m)
Station 1
Station 2
Station 3
Station 4
Station 5
Station 6
Station 7
Station 8
Station 9
Station 10
Station 11
SUM
Markings, Signs & Reflectors
Reflectors
Phases (500 m) Quantities piece Cost Rate (L.E/piece) Total Cost (L.E)
Phase 1 615 10 6150
Phase 2 615 10 6150
Phase 1 615 10 6150
Phase 2 615 10 6150
Phase 1 615 10 6150
Phase 2 615 10 6150
Phase 1 615 10 6150
Phase 2 558 10 5580
Phase 1 558 10 5580
Phase 2 558 10 5580
Phase 1 558 10 5580
Phase 2 558 10 5580
Phase 1 558 10 5580
Phase 2 558 10 5580
Phase 1 558 10 5580
Phase 2 558 10 5580
Phase 1 558 10 5580
Phase 2 558 10 5580
Phase 1 558 10 5580
Phase 2 558 10 5580
Phase 1 558 10 5580
Phase 2 (348.64 m) 394 10 3940
SUM 12511 £ 118,960.00
Signs
Phases (500 m) Quantities piece Cost Rate (L.E/piece) Total Cost (L.E)
Phase 1 32 800 25600
Phase 2 0 800 0
Phase 1 3 800 2400
Phase 2 2 800 1600
Phase 1 7 800 5600
Phase 2 7 800 5600
Phase 1 5 800 4000
Phase 2 0 800 0
Phase 1 9 800 7200
Phase 2 26 800 20800
Phase 1 4 800 3200
Phase 2 4 800 3200
Phase 1 4 800 3200
Phase 2 16 800 12800
Phase 1 38 800 30400
Phase 2 16 800 12800
Phase 1 4 800 3200
Phase 2 13 800 10400
Phase 1 19 800 15200
Phase 2 2 800 1600
Phase 1 2 800 1600
Phase 2 (348.64 m) 0 800 0
SUM 213 £ 144,800.00
£ 777,524.81