Professional Documents
Culture Documents
M-4 21cvi53
M-4 21cvi53
2
Syllabus
Highway drainage: Significance and requirements, Surface drainage
system and Examples, Subsurface drainage system, design of filter
materials, Types of Cross Drainage Structures, their Choice and
Location.
Highway Economics: Highway user benefits, VOC using charts only –
Examples. Economic analysis – annual cost Method – Benefit Cost
Ratio Method – NPV –IRR methods – Examples.
3
What is Highway Drainage?
4
What is Highway Drainage?
5
Significance of Drainage
6
Significance of Drainage
8
Significance of Drainage
• Flow of surface water across the road and shoulders and along slopes
should not cause formation of cross ruts or erosion.
10
Requirements of Highway Drainage
• Highest level of ground water table should be kept well below the
level of subgrade, preferably by at least 1.2m.
11
Surface Drainage
• During rains,
Ø Part of the rain-water flows on surface
Ø Part of it percolate through the soil mass as gravitational water until it
reaches the ground water below the water table.
• Removal and diversion of surface water from the roadway and
adjoining land is termed as surface drainage.
• Diversion and removal of excess of soil water from the subgrade is
termed as Sub-Surface Drainage.
12
Methods of Surface Drainage
13
Components of Surface Drainage System
14
Cross Slope or Camber
• Water from the pavement surface and shoulders is first drained off
within the help of cross slope or camber.
• Rate of slope depends on:
ØType of the pavement surface
ØAmount of rainfall in a region
• Recommended range of camber
ØFor earth road: 1 in 25 or 4%
ØFor bituminous road: 1 in 60 or 1.7%
ØFor earth shoulders: 4 to 5%
15
Cross Slope or Camber
16
Road-Side Drain
• On sloping terrain (cross slope < 4%), provided on one side only.
17
Surface Drainage
18
Surface Drainage
• Depth of side drains is kept 1.0 to 1.5 m to prevent the entry of drain
water into the embankment.
19
Surface Drainage
20
Surface Drainage
2. Catch Basin and Inlets in Urban Areas
21
Surface Drainage
2. Catch Basin and Inlets in Urban Areas
• The catch basin (catch pit) is provided with grating to prevent the entry
of rubbish into the drainage system.
22
Surface Drainage
2. Catch Basin and Inlets in Urban Areas
Inlets
23
Shoulder Drainage
24
Shoulder Drainage
• For a quick drainage it is necessary to ensure that shoulder surface is
properly sloped and free from irregularities and depressions.
• On the outer side, the shoulder should be made to drain away from the
pavement, a low rate of super elevation are provided.
• On the other hand, where higher rate of super elevation, the outside
shoulder are kept level or rounded.
26
Median Drainage
27
Median Drainage
• Except for a median less than 5m wide, it is not desirable to drain the
median area towards the pavement surface.
28
Median Drainage
• If carriage way slopes towards the median, central drain maybe made
to carry the runoff and slope should not be steeper than 6:1.
• When the median has only earthen surface, it should not be crowned
because it can result in soil particles being carried to the pavement
surface making it slippery.
29
Sub-Surface Drainage
• Removal or Diversion of excess soil-water from sub-grade is termed as
sub-surface drainage.
30
Sub-Surface Drainage
31
Lowering Water Table
• In order to that the sub-grade and pavement are not subjected to
excessive moisture the water table should kept at least 1.0 to 1.2 m
below the sub-grade.
• But when the formation level is at or below the general ground level it
is necessary to lower the water table.
32
Lowering Water Table in Permeable Soils
33
Lowering Water Table
(a) If soil is relatively permeable, it may be possible to lower WT by
constructing longitudinal drainage trenches with drain pipe and filter
sand and top of trenches is covered with clay seal.
34
Lowering Water Table in Permeable Soils
35
Lowering Water Table in Permeable Soils
(b) If the soil is less relatively less permeable, the lowering of ground
WT may not be adequate.
36
Control of Seepage Flows
37
Control of Seepage Flows
38
Control of Seepage Flows
39
Control of Capillary Rise
40
Control of Capillary Rise
41
Design of Subsurface Drainage System
• The size and spacing of the sub-surface drainage system depend on
the quantity of water to be drained off, the type of soil and type of
drain.
• And also resist the flow of the fine foundation soil resulting in soil
piping.
42
Design of Subsurface Drainage System
• The Steps are as follows:
• Draw grain size distribution curve on log scale %passing vs. particles
size for the foundation soil.
• The size of filter material should be 5 times more than the size of
foundation soil.
43
Piping failure
44
Design of Subsurface Drainage System
To fulfill the condition to prevent piping.
• D15 of filter/D85 of foundation <5
• Hence plot a point represent the upper limit of D15 size of filter given
by 5*D85 of foundation.
• Find the size of the perforation in the drain-pipe or the gap in the open
jointed pipes and let this be =Dp
• Plot a point representing D85 size of filter given by the size 2Dp.
• The Shaded area thus obtained represents the region within which the
grain size distribution curve of satisfactory filter material should lie.
45
Design of Subsurface Drainage System
46
Road Construction in Water-Logged Areas
47
Road Construction in Water-Logged Areas
• In case of sub-grade subjected soil water to soaking cond., capillary
rise, and in extreme condition, Even flooding for prolonged periods is
termed as water-logged areas.
48
Cross Drainage Structure
• In an irrigation project, when the network of
main canals, branch canals, distributaries, etc.
are provided, then these canals may have to
cross the natural drainages like rivers,
streams, nallahs, etc at different points within
the command area of the project.
• At the crossing point, the water of the canal and the drainage get
intermixed. So, far the smooth running of the canal with its design
discharge the cross drainage works are required.
50
Necessity of Cross Drainage Structure
• The site condition of the crossing point may be such that without any
suitable structure, the water of the canal and drainage can not be
diverted to their natural directions. So, the cross-drainage works must
be provided to maintain their natural direction of flow.
51
Types of Cross Drainage Structure
• Type I (Irrigation canal passes over the drainage)
(a) Aqueduct
(b) Siphon aqueduct
• Type II (Drainage passes over the irrigation canal)
(a) Super passage
(b) Siphon super passage
• Type III (Drainage and canal intersection each other of the same level)
(a) Level Crossing
(b) Inlet and outlet
52
Type I (Irrigation canal passes over the drainage)
53
Aqueduct
54
Aqueduct
55
Aqueduct
• The aqueduct is just like a bridge where a canal is taken over the deck
supported by piers instead of a road or railway.
56
Aqueduct
• An inspection road is provided along the side of the trough.
• The bed and banks of the drainage below the trough is protected by boulder
pitching with cement grouting.
• The section of the trough is designed according to the full supply discharge
of the canal.
• The height and section of piers are designed according to the highest flood
level and velocity of flow of the drainage.
57
Aqueduct
• The piers may be of brick masonry, stone masonry or reinforced
cement concrete.
• Deep foundation (like well foundation) is not necessary for the piers.
58
Siphon Aqueduct
59
Siphon Aqueduct
• The siphon aqueduct, the bed of the drainage is depressed below the
bottom level of the canal trough by providing sloping apron on both
sides of the crossing.
• The section of the drainage below the canal trough is constructed with
cement concrete in the form of tunnel. This tunnel acts as a siphon.
60
Siphon Aqueduct
• Cut off walls are provided on both sides of the apron to prevent
scouring.
• The other components like canal trough, piers, inspection road, etc.
should be designed accordingly to the methods adopted in case of
aqueduct.
61
Type I (Irrigation canal passes over the drainage)
Advantages of Type1:
1. The canal running perennially is above ground and is open to
inspection.
2. Damage done by floods is rare.
Disadvantages of Type1:
1. During high floods, the foundation can be scoured or the water way
of the drain may be chocked with trees.
62
Type2-Drainage passes over the irrigation canal:
• In this type of cross drainage work, drainage is taken over the canal.
63
Super Passage
64
Super Passage
• The super passage is just opposite of the aqueduct. In this case, the
bed level of the drainage is above the fully supply level of the canal.
65
Super Passage
• The trough should be constructed of reinforced cement concrete.
• The bed and banks of the canal below the drainage trough should be
protected by boulder pitching or lining with concrete slabs.
66
Siphon Super Passage
67
Siphon Super Passage
• It is just opposite siphon aqueduct.
• In this case, the canal passes below the drainage trough. The section
of the trough is designed according to high flood discharge.
• The bed of the canal is depressed below the bottom level of the
drainage trough by providing sloping apron on both sides of the
crossing.
68
Siphon Super Passage
• The section of the canal below the trough is constructed with cement
concrete in the form of tunnel which acts as siphon.
69
Type2-Drainage passes over the irrigation canal:
Advantages of Type2:
1. C.D works are less liable to damage then the earthwork of canal.
Disadvantages of Type2:
1. Perennial canal is not open to inspection.
2. It is difficult to clear the silt deposited in the barrels of the C.D. work.
70
Type3-Drainage and Canal intersection at the same level
In this type of work, the canal water and drainage water are permitted
to intermingle.
71
Level Crossing
72
Level Crossing
• The level crossing is an arrangement provided to regulate the flow of
water through the drainage and the canal when they cross each other
approximately at the same bed level. The level crossing consists of the
following components:
• Crest Wall: It is provided across the drainage just at the upstream side
of the crossing point. The top level of the crest wall is kept at the full
supply level of the canal.
73
Level Crossing
• Drainage Regulator: It is provided across the drainage just at the
downstream side of the crossing point. The regulator consists of
adjustable shutters at different tiers.
74
Inlet and Outlet
• In the crossing of small drainage with small channel no hydraulic
structure is constructed. Simple openings are provided for the flow of
water in their respective directions. This arrangement is known as inlet
and outlet.
• At the points of inlet and outlet, the bed and banks of the drainage are
protected by stone pitching.
75
Inlet and Outlet
76
Type3 - Drainage and Canal intersection at the same level
Advantages of Type3:
1. Low initial cost
Disadvantages of Type3:
1. Regulation of such work is difficult & requires additional staff
2. The canal has to be designed to carry the increased flood discharge of
drain.
3. The faulty regulation of the gates may damage the canal.
4. There is additional expenditure of silt clearance.
77
Proper Site for Drainage Crossing
The site selected for the cross-drainage works should have the following main
characteristics,
3. Sufficient headway is available for the super structure of the aqueduct over
the H.F.L of the natural stream.
78
Selection of type of cross-drainage works
• Economical consideration
• Construction problems
79
Selection of type of cross-drainage works
• When the bed level of the canal is much above the H.F.L. of the
drainage so that , sufficient headway is available for floating rubbish
etc., and also of the structure element of the work and aqueduct is the
obvious choice.
• Similarly, if the bed level of the drain well above the F.S.L. of the
canal, super passage is provided.
80
Selection of type of cross-drainage works
• The necessary headway between the canal bed level and the drainage
H.F.L. can be increased by shifting the crossing to the d/s of the
drainage.
• Thus, in the case of syphon aqueduct, the H.F.L. of the drain is above
the bed of the canal.
81
Selection of type of cross-drainage works
• When the canal bed level is much lower, but the F.S.L. of the canal is
higher than the bed level of drainage, a canal syphon is preferred.
• When the drainage and the canal cross each other practically at the
same level, a level crossing may be preferred. This type of work is
avoided as far as possible.
82
Highway Economics
83
Purpose of Economic Evaluation
• Preparation of highway plans at the national regional and local
level.
84
Purpose of Economic Evaluation
• To evaluate alternative strategies stage construction or full
construction;
85
Basic Concepts of Economic Analysis
• National view-point.
86
Basic Concepts of Economic Analysis
• Marginal differences
87
Aspects of Project Appraisal
• Engineering Aspects
• Managerial Aspects
• Financial Aspects
• Economic Aspects
88
Engineering Aspects
• Deal primarily with the technical construction process
and the operating of the project after it is completed,
as well as with the estimates of capital and operating
costs.
89
Managerial Aspects
• Deal with the multitude of management and staffing problems
involved in constructing and operating the project.
90
Financial Aspects
•Deal with the cost and revenue of the enterprise
responsible for the project.
91
Economical Aspects
• Deal with the economic costs and benefits from the point of
view of the country as a whole.
92
Total Transportation Cost
93
Construction Cost
• Survey, Investigation and Design Cost
• Construction Costs
• Physical Contingencies
94
Maintenance Cost
• Ordinary repairs
• Periodic repairs
• Operation expenses
95
Road User Cost
96
Benefits from Highway Improvements
Road User Benefits
97
Benefits from Highway Improvements
Social benefits
• Improvement in administration, Law and order and
defense.
• Traffic projections.
102
Stages Involved in Economic Evaluation
• Economic analysis.
103
Vehicle Operating Cost (VOC)
Important Factors Contributing to the Cost of Vehicle Operation:
(i) Fuel
(iii) Lubricants
104
Vehicle Operating Cost
Important Factors Contributing to the Cost of Vehicle Operation:
(vi) Depreciation
• Cost depending on speed include cost of fuel, oil, tyre per vehicle-
Kilometer-time-cost of vehicles, travel time value of passenger etc.,
106
Vehicle Operating Cost
The VOC depends on;
• Cost dependent on road condition, geometrics (pavement surface,
magnitude and length of gradient, radius and number of curves).
• Accident Costs
107
Vehicle Operating Cost
108
Vehicle Operating Cost
109
Methods of Economic Evaluation
110
Net Present Value Method (NPV)
• In this method the stream of costs/ benefits associated with the
project over an extended period of time is calculated and is
discounted at a selected discount rate to give the present value.
113
Thank You
114