Professional Documents
Culture Documents
Earnedvaluemanagement Template
Earnedvaluemanagement Template
Cost Performance
Date Planned Value (PV) Earned Value (EV) Actual Cost (AC) Cost Variance (CV)
Index (CPI)
ue Management (EVM)
Do Not Modify Below Values
Planned Value (PV): $ - Schedule Performance Index (SPI): 0
Earned Value (EV): $ - Estimate At Completion (EAC): $ -
Cost Variance (CV): $ - Estimate To Completion (ETC): $ -
Cost Performance Index (CPI): 0 Variance At Completion (VAC): $ -
Schedule Variance (SV): $ - To-Complete Performance Index (TCPI): 0
Planned Percent Completed: 0%
Schedule
Schedule Variance Estimate At Estimate To Variance At
Performance Index
(SV) Completion (EAC) Completion (ETC) Completion (VAC)
(SPI)
To-Complete
Performance Index
(TCPI)
(empty)
Column B
Column C
Column D