Scheduled Work List For Annual Interruption Day 08.06.2024
Scheduled Work List For Annual Interruption Day 08.06.2024
Section: Electrical
Date: 08.06.2024
Time: 08:00 Hrs. to 17:00 Hrs.
Location: Ambathale Production Complex
Preliminary Activities
1. Earth Rods Installation for Intake and other transformers
2. Check, test and refill fuel tank of fuel for all standby generators prior to the work
start.
Proposed Temporary Power Arrangements:
• 110 kVA Generator Supply for DGM Office
• 40 kVA Intake Generator Supply for Intake
• 50 kVA SPH Generator Supply for SPH – 01 and Main TP
• 37 kVA Mobile Generator (Denyo - Premises) Supply for Dehiwala GR
• 30 kVA Generator (Kiraloskar - Workshop) Supply for Workshop
• 150 kVA New Plant Generator for New Plant
• 37 kVA Mobile Generator (Denyo - Workshop) Supply for Main Plant
Chlorine House
3. Supply of safety materials (dust masks and cotton glows etc.), cleaning Items and
tools etc.
Note:
• Each team should be ready with;
✓ Complete 2 Nos Tool boxes
✓ Electrical Tools, Multimeter
✓ Scotch Tape, Insulation Tape, Nut and bolts, ect.
✓ Air Blower
✓ Vacuum Cleaner
✓ Paint Brushes
✓ Cotton Waste
✓ 2 ltr. Turpentine
✓ Contact Cleaners
✓ Penetration oil (WD40)