Professional Documents
Culture Documents
Method Statement For Concrete Works Sub Structure
Method Statement For Concrete Works Sub Structure
Document No:
Method Statement for Rev : 0
Concrete Works - Substructure Date:
Page 1 of 10
Document No:
Method Statement for Rev : 0
Concrete Works - Substructure Date:
Page 2 of 10
Revision Record
1. This cover page is a record of all revisions of the document identified above by number and
tlaboratorye. All previous cover pages are hereby superseded and are to be destroyed.
2. The contractor has the full right to modify, amend or change Method Statement and supporting
documents as required or as deemed necessary. All such documents will be submitted to the
“CONSULTANT” for approval.
Document No:
Method Statement for Rev : 0
Concrete Works - Substructure Date:
Page 3 of 10
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
5.0 RESPONSIBILITIES
6.0 MATERIALS
9.0 PROCEDURE
10.0 ATTACHMENTS
1.0 PURPOSE
The purpose of this document is to lay down the systematic procedures for the various activities required for CONCRETE WORKS- SUBSTRUCTURE
(CAST IN-SITU) to ensure that all works are carried out in accordance with the approved construction drawings and contract specification.
SCOPE
2.0
This procedure cover all activities related to concreting substructure:
PROJECT NAME
Document No:
Method Statement for Rev : 0
Concrete Works - Substructure Date:
Page 4 of 10
Setting out
Shuttering
Concrete pouring
Concrete finishing
D-shuttering
Concrete curing
3.0 REFERENCES
Project Specifications Cast in Place Concrete
5.0 RESPONSIBILITIES
Project Manager is responsible for overall project execution, quality and safety. Adopt a leading role with respect to Contractor’s quality and safety
procedures. The PM is responsible for the overall implementation of this method of statement. The Project Manager shall ensure that the key personnel
are well aware of the specifications and method of statement.
CM / Project Engineer shall arrange all materials, equipment, safety related items and manpower and direct the Site Engineers & Foremen to resort
appropriate action for the smooth execution of the works.
Safety Engineer shall be responsible for safe working environment & conditions. Coordinate with Site Engineer to identify potential hazards before
works and advise methods of safe working from new developments.
Surveyor shall be responsible for setting out for levels, layout, and lines & establish top levels. Ensuring setting out books are properly maintained and
filed when completed. To coordinate with the CONSULTANT surveyor in determining coordinates, levels, and limits.
QA/QC Engineer shall be responsible for ensuring that execution of works are complying with approved method statement; specifications, approved
shop drawings and ensure ITR are submitted based on ITP requirements.
Site Engineer shall ensure that all works are carried out according to approved shop drawings. He shall direct the surveyor for the setting out lines &
levels in concurrence from the Construction Manager/Senior Civil Engineer.
MEP Coordinator / Engineer shall be responsible for proper execution of MEP works involved before, during and after the works.
6.0 MATERIALS
PROJECT NAME
Document No:
Method Statement for Rev : 0
Concrete Works - Substructure Date:
Page 5 of 10
Vibrators
Concrete Pumps
Chute
Crane
Transit Mixtures
Generator-For night concreting
Air compressor
Hand tools, hand saw, wire cutter, brush,
Line dory
Measuring tapes
Tamper
Shovel
Wooden Float
Power float
Calibrated survey equipment
Water pump and PVC flexible hose for curing
The capacity / size of the above tools and equipment shall be judged in accordance with site
conditions, requirements, and availability at the time of execution
9.0 PROCEDURE
General:
PROJECT NAME
Document No:
Method Statement for Rev : 0
Concrete Works - Substructure Date:
Page 6 of 10
All the related documents, approved shop drawings, method of statements, material approvals, subcontractor’s approvals and test certificates etc. must
be approved and available upon request.
Ensure that required water proofing provided for all structures below raft footing.
Submit mix design and trial mix test result for Client/Engineer approval.
Ensure that all the pipes & ducts for MEP works which have to be installed inside the fill shall be provided as per the drawings & specifications.
Ensure that Field Density Test and Plate Bearing Test found satisfactory and test results by LABORATORY are submitted for the CONSULTANT
review and approval.
Ensure that anti termite treatment has been applied on the compacted fill as specified.
Ensure that 1 layer of approved 1000 gauge Polythene sheet has been laid.
Arrange the cube moulds, slump cone, and thermometer etc for the quality checking.
Polythene sheets, hessian cloths sweet water etc shall be arranged for the proper curing.
Formworks.
Materials
All reinforcing materials shall be as per approved materials and test results by the
LABORATORY to be submitted for CONSULTANT approval.
Fabrication
Bar bending schedule shall be prepared in accordance to approved shop drawing and
comply with relevant BS 4466.
All reinforcement shall be cut to length and bend it to the shape shown in BBS. Slow
and steady pressure shall be ensured during bending process. After bending all bars
must be securely tied together in bundles and appropriately belted with member
reference identification.
Fixing of Reinforcement
PROJECT NAME
Document No:
Method Statement for Rev : 0
Concrete Works - Substructure Date:
Page 7 of 10
Plastic or concrete spacer blocks made from approved mix design. The mix
proportions shall match those of the surrounding concrete and the blocks shall be
comparable to the surrounding concrete in strength, durability and appearance.
Wherever reinforcements are placed in two or more layers, minimum 25mm spacer
shall be placed between layers. All bars in upper layers must be placed directly
above those in the bottom layers.
All embedment or inserts related to MEP shall be placed as per approved shop
drawings.
All reinforcement must be cleared to ensure that it is free from all oil, dust,
rust/corrosion and deleterious materials.
General
Concrete placement shall not start until all other trades have completed / installed
their embedment. Once all embedment are completed CONSULTANT approval
shall be obtained.
All surfaces shall be cleared thoroughly, remove any water. De-shuttering oil shall
be placed on the formwork.
Concrete Pouring
Cranes, concrete bucket, Pumps, chute, Shovel and manual methods will be used as
per the elevation’ quantity of concrete and to suit the site condition towards
conveying & spreading concrete.
PROJECT NAME
Document No:
Method Statement for Rev : 0
Concrete Works - Substructure Date:
Page 8 of 10
Concrete shall be delivered to site within 75 minutes after the introduction of the
water to the cement, and shall be placed and compacted within 45 minutes of arrival.
The concrete shall be compacted and in its finial position within 120 minutes of the
introduction of the cement to the aggregate. Elapsed time between batching and
placing of concrete using combination of GGBS and OPC of 180minutes can be
accepted.
Target slump will be 160mm to the mix with a tolerance +40mm as per approved
mix design.
Concrete shall be placed in layers not exceeding the specified thickness. Each layer
must be properly consolidated using air poker and diesel vibrator to ensure
Maximum compaction of concrete. The pokers head must be inserted 150mm into
the previous layer in order have proper kneading.
Delay between two successive layers must be minimize in order to avoid any cold
joint.
Concrete temperature shall not exceed 30C at the time of placing and during hot
weather the forms shall be shaded and sprayed with water. To prevent the premature
drying of concrete it shall be covered with polythene and reflective sheets
During hot weather pouring will be carried out in such a way that there will be no
formation of cold joint. If concreting activities are carried out during night time
adequate illumination shall be provided. Concrete shall be placed in shallow layers
enough to assure vibration well into the layers below and the elapsed time between
the layers be minimized to avoid cold joints.
Expansion joint b/w old and new concrete floor to floor will be filled with 20mm
filled board. Approved expansion joint sealant will be applied on the expansion joint
as per the manufacturer’s recommendations and it will be covered with a metal trim
as per approved shop drawings details.
Floor to wall joint will be filled with 20mm filler board and approved expansion
joint sealant will be applied as per the manufacturer’s recommendations and
approved shop drawing details.
Document No:
Method Statement for Rev : 0
Concrete Works - Substructure Date:
Page 9 of 10
Curing shall be started immediately after initial set of concrete and finishing as free
water has disappeared from the surface of concrete. Curing shall be continued for
minimum of 7 days.
FORM REMOVAL
Forms and shoring in the formwork used to support the weight of concrete in beams,
slabs and other structural members shall remain in place until concrete has reached a
minimum of 70% of the specified 28 day strength i.e. 45 N/mm 2. In absence of
concrete cube results periods specified in clause 2.3.3 of Spec. Section 03300 shall
apply to the removal of formwork.
Concrete shall be thoroughly wetted as soon as the forms are first loosened and shall
be kept wet during the removal operation and until the curing media is applied.
Great care shall be exercised during the removal of forms to avoid shocks or reversal
of stresses in the concrete.
10.0 ATTACHMENTS