Professional Documents
Culture Documents
ATP Protection 1712851712
ATP Protection 1712851712
ATP Protection 1712851712
1
of phases of a probe and which phases will be illustrated in the CT saturation and CCVT transients starts with the transformer
graphical output file. building feature. Power system tools is where the user can add
protective relay components.
2
• Ipri = the primary current rating of the CT (e.g. 3000A
for a 3000:5 CT).
• Zb = the total secondary burden including the relay,
leads, and CT resistance.
• Zstd = is the sum of the accuracy class burden and CT
internal resistance.
• A value of Vs greater than 20 indicates the CT is
expected to saturate.
Figure 4: PlotXY
3
The saturable transformer model is convenient for modeling available fault currents to simulate the performance of a CT over
CT performance because the saturation characteristic can be the first few cycles of a fault.
entered directly from the excitation curve. The program includes
a sub-routine to convert these RMS current and voltage pairs
into peak current-flux pairs for the simulation. There are some
limitations to this model; it does not include any hysteresis and
cannot account for any remanence in the CT core. Despite these
limitations the model provides good results for the type of
significant saturation scenarios that would be of interest in most
protection studies. [2].
4
For ATP an equivalent source was modeled to provide the
required 11.2 kA fault current with an X/R ratio of 37.2 to match
the information directly entered into the Excel based model
provided by the PSRC. The resulting CT saturation was
compared to an ideal (non-saturated) secondary current in both
models and showed good agreement.
Figure 12: RMS Voltage and Current input pairs (red), and
simulation outputs (blue)
C1
Lt
Vm PT
C2
FSC Burden
5
(3) The size of the main CCVT capacitors is easily obtainable
! " #$ ∗! # from the nameplate however, the exact impedances of the FSC
components and secondary transformers are not typically
The tuning inductor can be determined by subtracting the reported on manufacturer drawings and must be requested from
PT inductance from the total. the manufacturer.
%& &' − *+ (4) The step-down transformer can be modeled using the same
saturable transformer model used to simulate the CT. For this
Both the tuning inductor and the potential transformer will application the saturation characteristics of the core are
have a small amount of capacitance that would be modeled in represented in less detail using the excitation current and
parallel with each component. The amount of capacitance is voltage from the no-load loss test as a single point for the
small, not as readily available, and can often be neglected in magnetization characteristic.
protection studies involving near nominal frequencies.
For the tutorial, typical data [5] was obtained to represent
CCVT’s will include a ferroresonance suppression circuit the simplified CCVT model.
(FSC) designed to dampen oscillations that may occur between
the circuit capacitance and the non-linear inductance of the TABLE I. CCVT TYPICAL DATA
potential transformer’s iron core. The FSC can be in the form Parameter Value
of an LC circuit tuned to the power system frequency (active
C1 2920 pF
FSC) or as a resistive load connected permanently or through a
spark gap to the secondary of the PT (passive FSC). C2 82000 pF
Lt 58 kW
PT Turns Ratio 6584/115
PT L primary 2997 W
PT R primary 400 W
Cf Lf
PT L secondary 0.001 W
PT R secondary 0.001 W
Gap
0.01421 A,
PT magnetization
Rf 13.7867 Wb
R 5.5 W,0.01 H,
Lf Rf Cf (RLC)
8 uF,
LF (RL) 3.9 W, 0.394 H
Figure 14: Typical active (left) and passive (right) FSC designs
Rf 40 W
FSCs, in particular active FSC circuits, can have a Burden 1000 W
significant impact on the transient response of the CCVT and
should not be neglected in protection studies.
This simplified model would be suitable for most protection
To represent FSC circuits using ATPDraw, the linear RLC studies interested in transient responses that would be observed
components can be configured to represent each side of the by relays immediately following a system fault. For
filter, the inductance is split out as two inductors representing investigations that involve frequencies higher than 500Hz or
each side of the tap, with a capacitance to one side, and the that are concerned with ferroresonance, additional modeling
associated resistances. may be required to account for the effects of stray capacitances
and the presence of any drain coil. A more detailed nonlinear
core model for the step-down transformer that includes
remanence, should also be used. A more comprehensive
discussion of CCVT modeling is provided in [2].
6
Figure 16: Simplified CCVT model
7
• High-Side Voltage: 13.8 kV
• Low-Side Voltage: 416 V
• Rating: 3.6 MVA
• Winding Configuration: Delta-Wye-Impedance
Grounded
• Impedance: 8.33% at 3.6 MVA
Figure 18: Transformer Structure, Ratings, and Connections Figure 20: Hybrid Transformer Core Parameters
The input data for the transformer inductance, resistance, After entering the values from the transformer test report
capacitance, and core parameters can be based on either the into the component and using typical values where appropriate,
design parameters of the transformer, test report values, or the advanced core settings dialogue box can be opened. The
typical values. The authors used the “Test Report” option to advanced settings allow the user to adjust the type of
model the inductance, resistance, and transformer core. Figure nonlinearity used for modeling the excitation characteristic.
19 below shows the series inductance and reactance values. The The advanced core settings also include an option to “add final
impedance and load losses can be entered directly from the test segment” that extrapolates the excitation characteristic into the
report. Typical values were used for the transformer saturation region. The author’s found this extrapolation to be
capacitances since these are not typically provided in a test very useful in producing realistic inrush current magnitudes.
report. For frequencies below approximately 2kHz these
capacitance values have little impact on the results and can The “typical values” options for the transformer parameters
often be omitted from protection studies. For higher frequency should be used with careful engineering judgement. Similarly,
studies investigating lightning transients, transient recovery use of the “design parameters” option require very detailed
voltage, or other high frequency events, the capacitance of the information about the transformer dimensions and the materials
transformer cannot be neglected [7]. used for the core and windings.
8
B. Model Validation Example
The transformer model should be checked for
reasonableness to verify that it is behaving as expected. Short-
circuit tests can be performed to verify that the impedance of
the transformer has been modeled correctly. This can be done
by connecting a time-controlled switch to the secondary
winding of the transformer and initiating a three-phase fault as
shown in Figure 21 below. The results can then be compared to
hand calculations, or fault simulation results from steady state
analysis software.
Figure 23: Load Flow Test Circuit
The low-side voltages from the load flow test are shown in
Figure 24. The peak magnitude was found to be approximately
324 V, which equates to an RMS magnitude of 229.1 VL-G, or
95.4% of nominal. The high-side currents are shown in Figure
25. The peak current was found to be 204 A, which equates to
an RMS magnitude of 144.2 A, or 95.7% of the transformers
rated current. The voltage drop across the transformer is
Figure 21: Through-Fault Simulation Setup reasonable considering the transformer impedance and the
amount of load current.
For the example system, the source impedance is modeled
with a resistance of 0.04 Ohms and an inductive reactance of
0.381 Ohms. The transformer impedance is 1.194 + j4.241
Ohms. Based on these impedances, a three-phase fault on the
secondary of the transformer should result in high-side currents
of 1,665 A. Figure 22 shows the high-side currents obtained
from the ATP model during a low-side three-phase fault. The
peak current magnitude was found to be 2,352 A, which equates
to a current magnitude of 1,663 A, indicating that the
transformer’s impedance has been modeled correctly. Similar
tests can be performed for other fault types such as phase-phase
and single-line-to-ground faults.
9
below, a source is connected to the hybrid transformer through shows the inrush currents obtained in ATP for the test
two time-controlled switches. The upper switch is closed at the transformer described above. The inrush simulation was
start of the simulation and is configured to open at a zero performed with the transformer unloaded. The peak inrush
crossing of the source voltage. The lower switch is configured current magnitude was found to be 1,420 A, which is 9.43 times
to close a short time after the first switch opens. When the upper the nominal current rating of the transformer. This fits within
switch opens, the core flux in the transformer will be near a the typical range for a power transformer. The maximum
peak due to the core flux effectively being the integral of the theoretical inrush current for a transformer can be requested
terminal voltage. To produce a worst-case inrush current, the from the transformer manufacturer. For our case, the
lower switch is closed at a subsequent zero crossing in the manufacturer’s documentation listed the maximum inrush
opposite direction. This drives the core into saturation and current as 1,342 A. The maximum inrush current observed in
causes the transformer to draw a substantial inrush current. The the ATP model was within 5.5% of the manufacturer’s
switch timing is illustrated in Figure 27. published theoretical maximum inrush current. Given the
number of approximations made during modeling with the
hybrid transformer component, the ATP model yielded
satisfactory results.
10
This feature is beneficial when there are several lines running
parallel to one another which would affect the mutual coupling.
The Bergeron and Pi Models are most commonly used for
the LCC template inputs as shown in Figure 29. The Pi model
is best used for shorter lines (~ less than 50 miles) and
calculating line constants, whereas lines longer than 100 miles
exhibit the distributed effects of the electrical parameters very
significantly. Therefore, a distributed parameter representation
(Bergeron model) is recommended.
In the model tab, select Overhead Line for the system type,
and the # of phases. When skin effect is checked, the user is
prompted to enter the DC resistance on the next tab. When this
is not checked, use AC resistance. ATP has internal equations to
convert between AC and DC resistance. Since skin effect is
expected to occur, it's a good practice to check this box and use
the DC resistance. When skin effect is checked and using DC
resistance, only the outer radius of the conductor is necessary.
Since the current flows on the outside of the conductor, the inner
radius is not used in the calculations and can be set to zero. If a
conductor is bundled, select “Auto Bundling” and the user will
be prompted to add in the number, spacing, and angle of the
conductor in the data tab. ATP uses Carson's Line Impedance
method.
Under the data tab for the LCC is where the user will enter Figure 31: LCC model view
the information of the line shown in Figure 30.
B. OPGW
The outer radius (Rout) of the line has the largest effect on
During an earth fault (Single or Double Line to Ground
the line resistance. The phase spacing affects the inductance of
type), return current will flow through the OPGW. The return
the line. The line height "Vtower” and “Vmid” which is the sag,
current can be very high, only limited by the available short
affects the electromagnetic fields on the ground. Select “View”
circuit current, parallel fault paths, tower footing resistances,
for a graphical representation of the conductors as shown in
and other line characteristics. The high return current flow
Figure 31.
causes heating that can cause damage to the internal fiber strands
of the OPGW. OPGW heating limits tend to be lower than other
conductors because of the thermal sensitivity of the optical
fibers. OPGW manufacturers publish thermal limits as a kA2-
sec value that should not be exceeded.
11
Contingency conditions increase the portion of the total fault highest fault currents, however, breaking the transmission line
current flowing through the OPGW or increase the time the into spans of about two miles and placing faults at either end of
OPGW is exposed to fault current. A contingency most often the line as well as midline is recommended to determine the
considered is a broken overhead shield wire (OHSW) where worst case fault scenario. The resistances shown on each span is
more fault current would be forced onto the OPGW. Figure 32 the tower footing resistance to provide a fault current path to
shows a double circuit with an OPGW and a shield wire ground. The LCC template will also be updated to include the
modeled. A series of switching and current probes are placed phases for the OPGW/OHSW in order to make an electrical
along segments of the line to determine fault currents. connection in the ATP model. The program also allows the
OPGW/OHSW to be modeled as continuously grounded or
segmented. That can be used to check if segmenting the
OPGW/OHSW is economically attractive compared to a
continuously grounded shieldwire system.
The simulated fault current and breaker clearing times are
the parameters that will have the most impact on the OPGW
thermal rating.
The inductance of the transmission line may impose a DC
component on the short circuit current producing an
asymmetrical current. The DC offset decays relatively quickly
(within a few cycles) but can have a significant impact on
heating while present. The DC offset is a function of the system
X/R ratio for the fault condition considered and the timing of the
fault initiation.
An addition of an OPGW requires iterative fault current
analysis to ensure the OPGW will not be damaged during
normal operating conditions.
12
Figure 33: Saving COMTRADE results
13
Using prim, sec, and P/S settings may alter the way the 36. The system model includes an equivalent utility source, a
COMTRADE data is presented depending on the specific test 230kV/13.8kV step-down transformer, the main distribution
equipment or viewing software settings. bus, and a series of downstream transformers. The utility source
was configured to provide a short circuit current of
The default settings for the COMTRADE model assumes approximately 15 kA. The 230kV/13.8kV transformer was a
the first three analog channels are three-phase voltages and the delta-wye, 60 MVA transformer, with 16% impedance. The
second three channels are three-phase current inputs. ATP may
main transformer’s core and capacitance parameters were
not automatically recognize that an input is a current or voltage.
modeled using the “typical values” option in the Hybrid model.
To manually set this, use the Edit Definitions button and
navigate to the nodes tab. There the “Kind” of input node can The current transformers for the relay under test were modeled
be defined directly with 2 corresponding to a voltage node, and as 2000:5 C200 CTs and followed the same approach described
1 representing a current node. in section III. The medium voltage potential transformers were
approximated using a resistive voltage divider. Twelve 3.6
MVA distribution transformers were included in the model and
were configured as described in Section V.
Selecting the help button in this tab will bring up a full list
of “Kind” options for reference.
Following a simulation, the output file is written to the same Figure 36: Sample system
location as the model by default. ATP does not use the optional
.HDR file, only the .CFG and .DAT files will be written. The The objective of the tests was to check the response of a
results can be previewed within ATP by hitting the “View” residual ground overcurrent relay that would be installed on the
button at the bottom of the model attributes tab. This can be main breaker at this industrial installation. Of particular
useful to quickly verify the results were recorded as expected. concern was the ground overcurrent relay’s response during
energization of the twelve distribution transformers. To
simulate the worst-case inrush current, two switches were
VIII. APPLICATION EXAMPLE
modeled as described in Section V. The upper switch was used
A practical use of ATP simulation results is to test the to establish residual flux in the transformers, and the lower
transient response of a protective relay, similar to what is done switch was used to re-energize. The current transformers were
during hardware in the loop (HIL) testing. While closed-loop modeled in series with the lower switch such that they would
testing cannot be performed using ATP, open loop playback of capture the inrush current waveform. The PT secondary voltage
ATP simulation results can provide valuable insight into a and CT secondary current were captured in a COMTRADE
relays response to system transients. Several HIL tests were record for playback with a test-set. Figure 37 shows the CT
recently performed to evaluate the response of residual ground secondary currents captured during the simulation.
overcurrent elements employed in a zone-selective interlocking
scheme applied on the medium voltage system at a large
industrial facility. A series of tests were performed to observe
the response of these residual ground elements to transformer
inrush as documented in [8]. A similar power system was
modeled in ATP. A single line of the system is shown in Figure
14
Figure 37: ATP output
15
IX. ATP RELAY COMPONENTS ATPDraw. Setup of the previous stable version (6.3) looks very
ATP has several built-in protective relay components for similar.
functions such as overcurrent, time-overcurrent, quadrilateral
distance, mho distance, differential, over/undervoltage and The following ATP files were obtained prior to the
over/underfrequency. A detailed introduction to these installation process:
components is outside the scope of this paper. These • ATP Core Engine Version: tpbigi64.exe and
components can be useful for getting a general idea for how a tpgigi64.exe files (4/26/2020 from
relay might respond to a system disturbance. Care should be www.eeug.org)
taken when using these components as the algorithms employed • ATPDraw stable version: 7.3 with patch 1
by the generic models in ATP may not align with the (5/8/2021, source: www.atpdraw.net)
implementation for a given manufacturer’s relay. The models • PlotXY program files (August 2020, source:
can be modified and/or refined, but this can be a time- www.ceraolo-plotxy.ing.unipi.it)
consuming and difficult task if the user is not familiar with • ATPDraw 7.3 User’s Manual: Preliminary
ATP’s programming language. Open-loop testing using a Release No. 1.0 (May 2021, source:
COMTRADE export from ATP played back to an actual relay www.atpdraw.net)
is a more efficient and effective method for gauging relay
performance. A. Step 1 – Remove undesired versions of ATPDraw
X. CONCLUSION
ATP is a free tool that provides the capability to model Uninstall or delete undesired versions of ATPDraw. A
simple and complex electrical systems and run various transient computer that previously had ATPDraw will likely have a
simulations. It allows engineers to model power system configuration file (ATPDraw.ini) located at:
components in greater detail than typical steady-state analysis ‘C:\Users\username\AppData\Roaming\atpdraw\’. This file
software. Using ATP, protection engineers can quickly stores the default folder structures and program settings. If you
calculate transmission line parameters from physical data; as want different folder structures or program settings to be loaded
well as investigate the impacts of CT saturation, transformer on program startup you will need to manually remove the
inrush, and other complex phenomena on protection system residual configuration file. Once deleted, a new configuration
performance. file will automatically be created when a new version of
ATPDraw is launched. Note that the ‘AppData’ folder may be
Model validation is an important part of any transient hidden. Instructions to show hidden files can be found online.
simulation. It's possible to produce simulation results that
appear reasonable but may not match reality. Hand calculations, It is possible to have multiple versions of ATPDraw on your
test reports, and simplified cases in other software should all computer. However, they share the same .ini file.
serve to validate a transient model prior to applying the results Consequently, if the installed versions are very different,
of a simulation. having multiple versions may not work well. If an installation
is not working properly, one fix may be to completely remove
The output of a simulation can be exported in COMTRADE all ATP/ATPDraw instances and start over with a clean install.
format from ATP and “played back” to a microprocessor-based
relay using commonly available test sets in an open-loop B. Step 2 – Create folder structure
format. This can be advantageous for engineers who do not Create the folders where the ATP core engine, ATPDraw,
have access to hardware in the loop (HIL) simulators but have and PlotXY will be installed as shown in Table III. Historically
a need to verify a relays response to complex system conditions. ATP has had difficulty with spaces in path names (e.g.
While this type of testing does not provide all the features of a C:\Program Files\...). Recent versions of ATPDraw seem to
closed loop environment, it can be used to generate very similar have overcome this problem, but it is something to be aware of
results to HIL testing on a smaller and less expensive scale. if you run into path name problems. Note that ATPDraw model
files (.acp files) cannot have spaces in the filename or the
XI. APPENDIX – ATP INSTALLATION program will crash.
This appendix provides guidance on installing ATP. In TABLE III. ATP FOLDER STRUCTURE
order to obtain the installation files from www.atpdraw.net, the
Folder Function
user must first become licensed. The license application form
can be found at www.eeug.org. The steps below will guide the C:\ATP\ Root directory
reader through a manual setup of ATP and ATPDRAW. This This will be the folder
setup was tested in Windows 10. The specific steps here are where the ATP core
C:\ATP\atpintl64\
intended for new users. Experienced users may find various engine is stored.
ways to customize setup. Screenshots are from version 7.0 of
16
Folder Function D. Step 4 – Setup ATPDraw
This will be the folder Navigate to the C:\ATP\ATPDraw\ folder and run
where ATPDraw is Atpdraw.exe. When prompted, allow creation of folders that do
C:\ATP\ATPDraw\
stored. not exist (click “All”).
This will be the folder Click the ‘ATP’ menu option at the top of the ATPDraw
where the plot program, program window then select ‘Setup ATP connection’ (ATP
C:\ATP\PlotXY\
PlotXY, is stored. setup Wizard) from the drop-down menu. You should get the
window shown in Figure 40. Match the paths and selections
shown. If already checked, uncheck the radio box for ‘Set
C. Step 3 – Extract Files to Respective Folders externally (in bat-file or Windows)’. This causes the ‘Same as
Solver’ option to appear. The ATP core engine can be either
Obtain the ATP core engine zip file. The file used for this tpbigi64.exe or tpgigi64.exe. The difference between these two
tutorial was atpintl64.zip. Extract the zip file contents into the files is that the ‘gig’ version allows models with larger
folder C:\ATP\atpintl64\. This unpacks several files, including component counts. Normally the ‘big’ version is sufficient, but
another zip file called “armafit”. Perform an ‘extract here’ if you get errors from exceeding component limits in a large
function to unpack the armafit file into the same model you can try the ‘gig’ version. It is possible to compile
C:\ATP\atpintl64\ folder. versions with custom component limits, but that is beyond the
scope of this document. For most cases, one of these pre-
Obtain the ATPDraw zip file (the image file, not the setup compiled files will be adequate. The final step is to click “Save”
file). The version used for this tutorial is and then “Ok”.
ATPDraw73_Image.zip. ATPDraw is the graphical user
interface and must be linked to the core ATP engine (done in a
later step). Extract the zip file contents into the folder
C:\ATP\ATPDraw\. Since these are image files, no setup utility
is necessary; they are executable upon extraction.
ATPDraw.net has a setup file option for download. Use of that
option is not covered here, but much of the configuration will
be similar.
Obtain the PlotXY zip file. The latest version used for this
tutorial was PlotXY-2020-Aug-Win.zip. PlotXY is the plotting
program most used with ATPDraw though there are other
options. Extract the zip file contents and copy them into the
folder C:\ATP\PlotXY\. The contents of the zip file may extract
into a single subfolder. Copy/cut all the contents out of this
folder and paste them directly into the C:\ATP\PlotXY\ folder.
Figure 40: ATP setup wizard
17
the data in the tabs per the guidelines in Figure 41, Figure 42,
and Figure 43. The “General” tab is not shown and can be
left at default. In the “Preferences” tab, you may need to
delete the Armafit path. This file is needed for the “Noda”
transmission line model. Pi, Bergeron, and JMarti are the
primary models that are typically used so the Armafit entry
can be left blank. After finishing, click ‘Save’ at the bottom
of the ATPDraw Options window, then click ‘Apply’, and
finally click ‘ok’.
18
www.atpdraw.net. These are generally released as zipped XIII. BIOGRAPHIES
image files of the ATPDraw.exe file. Copy the zipped image Aaron Findley, P.E. is a protection engineer with POWER
file to the same location as the existing ATPDraw.exe file Engineers and is based out of Vancouver, Washington. While
and extract it to the same location. Click ‘Yes’ when a pop- at POWER, Aaron has worked on a wide variety of protective
up window asks for confirmation of file replacement. relaying projects ranging from distribution protection up to
EHV series compensated line protection and RTDS
modeling/testing. His background also includes substation
XII. REFERENCES
design and grounding system analysis. He earned his bachelor’s
degree, summa cum laude, in energy engineering from the
[1] M. J. T. a. B. H. Ariana Hargrave, "Beyond the Knee Oregon Institute of Technology in 2010 and is currently
Point: A Practical Guide to CT Saturation," in 44th registered as a Professional Engineer in California and a
Annual Western Protective Relay Conference, member of IEEE.
Spokane Washington, 2017.
[2] IEEE Power System Relaying Committee, Jared Mraz, P.E. earned his B.S. degree, summa cum
"Mathematical Models for Current, Voltage, and laude, in electrical engineering from the University of Idaho in
Coupling Capacitor Voltage Transformers," IEEE 2007. Upon graduation, he joined the SCADA and
Transactions on Power Delivery, pp. 62-67, January Analytical Services group at POWER Engineers in
2000. Clarkston, Washington. He has spent the past 14 years
performing a variety of electrical system studies, with an
[3] R. Folkers, "Determine Current Transformer
emphasis on protective relaying. His experience includes
Suitability Using EMTP Models," in Western
protective relaying for distribution, transmission,
Protective Relay Conference, Spokane Washington,
generation, and industrial applications, as well as testing of
1999.
protection and control schemes using Real Time Digital
[4] IEEE Power System Relaying Committee, "CT SAT Simulation. Jared is a registered professional engineer in
Calculator (PSRC)," 30 Dec 2001. [Online]. Washington, Texas and Louisiana and is a member of the
Available: http://www.pes- WPRC planning committee.
psrc.org/kb/published/reports/CT_SAT%2010-01-
03.zip. [Accessed 2002]. Morgan Brimstein is a protection and infrastructure design
[5] I. P. S. R. Committee, "EMTP Reference Models for studies engineer with POWER Engineers in Boise, Idaho. She
Transmission Line Relay Testing," 2005. graduated with her B.S. degree in Electrical Engineering from
[6] L. P. F. P. Hans Kristian Høidalen, ATPDraw Version Boise State University and has worked for POWER for the last
7.0 for Windows User's Manual, 2019. 5 years. During her time at POWER, she has performed various
protection and arc flash studies for several refineries and
[7] B. A. M. F. G. D. I. N. C. Hans K. K. Høidalen,
primarily focuses on line design studies such as insulation
"Implementation and verification of the Hybrid
coordination, line impedance calculations, OPGW thermal
Transformer model in ATPDraw," in International
analysis, EMF, Corona, and substation grounding studies.
Conference on Power Systems Transients (IPST’07),
Lyon, France, 2007.
[8] A. F. N. M. C. S. D. D. R. T. B. Jared Mraz, "Impacts
of Transformer Inrush Current on CT Performance
and Residual Ground Overcurrent Protection," in
Western Protective Relay Conference, Spokane WA,
202.
[9] "IEEE 738-2012 Standard for Calculating the
Current-Temperature of Bare Overhead Conductors,"
IEEE, 2013.
[10] USDA, "Bulletin 1724E-100, Design Manual For
High Voltage Transmission Lines," USDA, 2015.
[11] IEEE Power Engineering Society, "Tutorial on
Electromagnetic Transient Program Applications to
Power System Protection," in Power Engineering
Education Committee, 2000.
19