Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 26

PACKAGE G3 - BEACH BAR

THE ROYAL ATLANTIS RESORT & RESIDENCES


at THE PALM JUMIRAH, DUBAI, UAE

Doc Ref: TRA-HYL-MST-CW-GEN-00031 00


REVISION STATUS
Re Date Status/ Prepared Prepared Reviewed Approved Approved
v Modific by by by by by
ation
Name: Name: Name: Name: Name:
MURTADA ASIM S.P. HAN Valery Paquier
FOR OMER NAWAZ
26/07/2 REVIEW & Designation Designation Designation: Designation:
00 1 APPROVA : Designatio : PROJECT PROJECT
L PLANNING n: DEPUTY DIRECTOR
ENGINEER PROJECT DIRECTOR
MANAGER

Signature & Date

CONTRACT NO CN0063
CLIENT / PROJECT DEC MAIN
EMPLOYER MANAGER CONTRACTOR

METHOD STATEMENT

Chilled Water Piping and Accessories Installation &


Pressure Testing
Revision Record

Ref.: TRA-HYL-MST-CW-GEN-00031
Prepared Reviewed Approval for Description & page Number of
Rev Date
By by Issuance by Revision
R00 26/07/2021 MURTADA ASIM ASIM FOR REVIEW & APPROVAL
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

Table of Contents
1. PURPOSE........................................................................................................................... 5
2. PROJECT DETAILS:............................................................................................................. 5
3. SCOPE................................................................................................................................5
 Under Ground – Pre-insulated Black Steel pipes.........................................................5
 Above Ground – Insulated Black Steel pipes...............................................................5
4. Sequence of Work:............................................................................................................5
5. REFERENCES & STANDARDS:.............................................................................................6
6. DEFINITIONS & ABBREVIATIONS.......................................................................................6
7. RESOURCES:...................................................................................................................... 8
7.1 HUMAN RESOURCES:......................................................................................................... 8
RESPONSIBILITIES:................................................................................................................... 8
7.2 MATERIALS.................................................................................................................. 10
7.3 EQUIPMENTS & TOOLS.....................................................................................................10
8. SAFETY & HEALTH........................................................................................................... 12
9. PROCEDURE.................................................................................................................... 16
9.1 Safety...........................................................................................................................16
9.2 Handling and Storage.................................................................................................. 16
9.3 Work Sequence and Methodology..............................................................................16
9.4 Installation of Chilled Water piping:............................................................................17
9.5 Threaded Connection procedure:................................................................................18
9.6 Welding connection procedure:..................................................................................19
9.7 TESTING OF CHILLED WATER PIPES & FITTINGS..........................................................21
9.8 INSULATION OF CHILLED WATER PIPING.....................................................................21
10. ATTACHMENTS............................................................................................................23
 Risk Assessment..............................................................................................................23
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

 Inspection & Test Plan.....................................................................................................23


 Quality Checklist..............................................................................................................23
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

1. PURPOSE

This method statement to illustrate procedure, processes, safety measures and



all requirements for Installation and Pressure Testing of chilled water piping
and its accessories where applicable for below project
The MEP contractor must follow the Approved method statement for the

subject activities.
This method statement to be read in conjunction to Manufacture

recommendations, guidance and instructions.

2. PROJECT DETAILS:

Project Name: PACKAGE G3 - BEACH BAR - THE ROYAL ATLANTIS



RESORT & RESIDENCES
Client Atlantis The Palm 2 LLC

Employer Atlantis The Palm 2 LLC

Project Manager Turner International Middle East (TIME)

Engineer Dynamic Engineering Consultants (DEC)

Main Contractor SsangYong – Besix JV

Contractor HENNESSEY LLC

3. SCOPE

Supply, installation & Testing of the chilled water piping and its accessories for all
applications in line with project requirements.

 Under Ground – Pre-insulated Black Steel pipes.

 Above Ground – Insulated Black Steel pipes.

4. Sequence of Work:

As per project baseline programme.


Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

5. REFERENCES & STANDARDS:

Contract

Project Specifications:

230000 Particular HVAC Specification.
o
235210 Piping and Accessories
o
230529 Hangers and Supports for HVAC Piping and Equipment.
o
230700 HVAC Pipe Insulation.
o
230823 Systems Commissioning.
o
Legislation and code of practice:

For other standards & codes refer to Project Specifications.
Approved supplier details

230010.1 Approved Manufacturer List
o
Approved IFC drawings.

Approved other method statement.

Material approval

Contract Scope, Drawings & Specification.

Project Quality Plan

Project HSE Plan

6. DEFINITIONS & ABBREVIATIONS

TRA The Royal Atlantis



Client Atlantis The Palm 2 LLC

Employer Atlantis The Palm 2 LLC

Project Manager Turner International Middle East (TIME)

Engineer Dynamic Engineering Consultants (DEC)

Cost Consultant EC Harris

Main Contractor SsangYong – Besix JV

Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

Contractor HENNESSEY LLC



TIME Turner International Middle East

DEC Dynamic Engineering Consultants

HLLC HENNESSEY LLC

SBJV SsangYong – Besix Joint Venture

PM: CONTRACTOR’s Project Manager

PE: CONTRACTOR’s Project Engineer

QCE: CONTRACTOR’s Quality Control Engineer

SE: CONTRACTOR’s Site Engineer

QA / QC: Quality Assurance and quality Control

PPE: Personal Protective Equipment

HSE: Health, Safety and Environment

PQP Project Quality Plan

PSP Project Safety Plan

HSE Health, Safety and Environment

MS Method Statement

ITP Inspection Test Plan

QA/QC Quality Assurance / Quality Control Engineer.

SK Store Keeper.

WIR Inspection and Test Request

MDIR Material Delivery Inspection Record.\

Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

7. RESOURCES:

7.1 HUMAN RESOURCES:

PROJECT TEAM:

NAME DESIGNATION EMAIL M.PHONE

ASIM NAWAZ PROJECT MANAGER asim@hennesseyllc.com 0557725727


PROJECT
MURTADA
CONTROL / QA-QC murtada@hennesseyllc.com 0555799685
OMER
ENGINEER
SEETHARAMA
SR. QUANTITY
N seetharaman@hennesseyllc.com 0529099205
SURVEYOR
THANGAVELU
SYED QAISAR HSE ENGINEER qaiser@hennesseyllc.com 0588379210

DOCUMENT
AITA KHATI aita@hennesseyllc.com 0561224230
CONTROLLER
DOCUMENT
REDEN NAVA reden@hennesseyllc.com 0524483679
CONTROLLER

RESPONSIBILITIES:

Project Manager:

Responsible for overall project execution, quality and safety.
o
Adopt a leading role with respect to Contractor’s quality and
safety procedures.
The PM is responsible for the overall implementation of this
o
method of statement.
The Project Manager shall ensure that the key personnel are
o
well aware of the specifications and method of statement.

QA/QC Engineer:

Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

shall be responsible for ensuring that execution of works is


o
complying with approved method statement; specifications,
approved IFC drawings.
ensure ITR are submitted based on ITP requirements.
o

Project Engineer:

shall arrange all materials, equipment, safety related items and
o
manpower
direct the Site Engineers & Foremen to resort appropriate action
o
for the smooth execution of the works.

Safety Officer:

shall be responsible for safe working environment & conditions.
o
Coordinate with Site Engineer to identify potential hazards
o
before works
advise methods of safe working from new developments.
o

Surveyor:

shall be responsible for setting out for levels, layout, and lines &
o
establish top levels.
Ensuring setting out books are properly maintained and filed
o
when completed.
To coordinate with the SBJV & DEC surveyor in determining
o
coordinates, levels, and limits.

General Forman:

shall ensure that all works are carried out according to approved
o
IFC drawings. He shall direct the surveyor for the setting out lines
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

& levels in concurrence from the Construction Manager/Senior


Civil Engineer.

Document Controller:

Distribution of Project information in timely and appropriate
o
manner. [IR’s, RFI’s, MST & RA as per instruction of project
Manager.
Preparing daily reports in coordination with the project manager.
o
Keeping a record of all material delivery notes, requests to
o
testing laboratory, material submittals, drawings, certificates and
other project documents.

MEP Coordinator / Engineer:



shall be responsible for proper execution of MEP works involved
o
before, during and after the works.

Store Keeper (SK)


Responsible for overall Store operations in making sure to store


o
the material delivery to the site and keep it in suitable area that
will keep the material in safe from rusty and damage.

7.2 MATERIALS

As per the approved material submittal.

7.3 EQUIPMENTS & TOOLS

Following tools shall be arranged before starting the job:


Welding Machine

Cutting Equipment’s (oxygen, acetylene cylinders and cutting torch etc.)

Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

Threading Cutting Machine



Scaffolding

Pipe Wrench

Drilling Machine

Welding machine

Lifting arrangement

Tool Box

Measuring Tape

Spirit level

Manual pressure Pump.

Calibrated pressure gauge.

Steel Hammer

Hole Saw Cutter

Scissors

Razor

Marking Pen/Chalk Line

Ladders / Scaffolding.

The capacity / size of the above tools and equipment shall be judged in
accordance with site conditions, requirements, and availability at the time of
execution
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

8. SAFETY & HEALTH

HENNESSEY LLC Site HSE Management Plan & Precautions shall be applied.

SBJV HSE guidelines and management plan shall be strictly adhered during the

substructure concreting works.
TRA EMPLOYER, ENGINEER & PROJECT HSE guidelines and management plan

shall be strictly adhered during the substructure concreting works.
HENNESSEY LLC will ensure that the approved Method Statement, Risk

Assessment and local authority requirements fully complied prior to commence
the works & while following permit to work system.
Safety of the personnel and properties is to be given prime importance and all

the works to be carried out without causing any accidents or property
damages.
Valid Copy of all test certificate will be available at site reference upon request.

HENNESSEY LLC Site HSE Management Plan & Precautions shall be applied.

SBJV HSE guidelines and management plan shall be strictly adhered during the

substructure concreting works.
TRA EMPLOYER, ENGINEER & PROJECT HSE guidelines and management plan

shall be strictly adhered during the substructure concreting works.
HENNESSEY LLC will ensure that the approved Method Statement, Risk

Assessment and local authority requirements fully complied prior to commence
the works & while following permit to work system.
Safety of the personnel and properties is to be given prime importance and all

the works to be carried out without causing any accidents or property
damages.
Valid Copy of all test certificate will be available at site reference upon request.

All personnel involved will use necessary PPE as required such as:

Safety helmet, Hard Hat.
o
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

Safety Boots
o
Safety Goggles;
o
Neoprene work gloves
o
N95 Respirator;
o
Disposable coveralls;
o
ear plugs etc.
o

Adequate access and egress should be provided to the site for work.

All the equipment, tools and tackles being used for the work should be in good

working condition and maintained.
HSE officer to ensure that excavated area is barricaded. Adequate warning

tapes and warning signs are provided.
All access from adjacent working area to extension area shall be closed and

monitored.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

Though the excavation is minor in nature a hazard analysis table is attached for

excavation activities. All major possible risks/ hazards are highlighted.
The workers will be made aware of safety requirements related to this activity

through daily tool box and safety talk.
All the personnel will be provided with daily toolbox talk and safety talk on the

procedures to execute the work safely. The tool box talks will be recorded. The
safety inspector will continually monitor any risk assessment factors of all
manual handling activities.
All required work permits will be acquired and kept available at respective work

site hanged clearly in plastic folders.
Signs or directional signboards, shall be placed in all strategic places as

required.
Safety notice board will be installed.

Access to carry out works below ground level will be accessed by use of ladders

and scaffold. Ladder and scaffold prior to use must be inspected by a
competent person for visible defects on a periodic basis.
Metal ladders must have rubber shoes fixed it base all the time.

In the event short term access is required, ladders, suitably and properly

attended will be used.
All Possible techniques should be implemented and used to minimize the levels

of noise transmission to the environment as far as possible
Trained operatives to be deployed under a competent supervision.

Summer mid-day breaking timing shall be strictly followed as per local authority

regulations.
Covid-19 Control measures added to the attached Risk Assessment.

Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

Necessary risk assessment of the activities is reflected in the enclosed risk


assessment

Emergency Arrangements:

Internal trainings will arrange at the site for understanding in case of



emergency how the site team and workers will react.
In case of fire/ emergency evacuate the work area to the designated

assembly
points.

In the event of an accident or incident immediately notify the Project

Manager
and HSE Manager. The accident file, which is situated in the Site Office,

must be completed, by the SBJV HSE Manager/Trained First Aider or Trained
Construction Managers.
Rescue arrangement at place.

The Contractor’s Trained First Aiders available full time one site.

All Emergency Contact No. and emergency procedure Signage provided at

visible area.

Reference Telephone Numbers:


Police Ambulance Fire
999 998 997
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

9. PROCEDURE

9.1 Safety

 Qualified person must be trained and authurised for use electrical machines.
 Ensure all concerned personnel shall use PPE (Personal Protective Equipment)
and all other items as required.
 Ensure adequate lighting is provided in the working area at night time.
 Ensure service area/work area openings are provided with barricade, tape, and
safety nets.

9.2 Handling and Storage

 On receipt of the material at site, necessary precautions shall be taken for


unloading, shifting, and storage as follows:
 All material shall be inspected, handled and stored properly upon receipt at site.
 It shall be stored in a place free of water, dust and adequately covered to avoid
any kind of damages.
 All insulation materials shall be inspected for the thickness and densities.
 While unloading, shifting and storage, it should be ensured that there are no
transit damages.
 Any discrepancies, damage, and etc. found to the materials will be notified and
reported to QA/QC Engineer and Project Engineer for further action.
 Materials found not suitable for site use should be removed from site
immediately.

9.3 Work Sequence and Methodology

 All the materials delivered to site are inspected properly and stored as per the
manufacturer recommendations.
 MIR shall be issued, for the inspection of materials received to Consultant for
their approval.
 Work shall be carried out by the site staff under the strict supervision and
guidance of the concerned Supervisors / Engineers.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

 Site Engineer shall check the work as per the check list attached, further checked
by the Consultant.
 WIR shall be prepared by QA/QC Engineer and to be issued to Consultant for
checking the work.
 Sub-contractor site Engineer & QA/QC Engineer shall co-ordinate with Contractor
and Consultant and arrange for their inspection.
 QA/QC Engineer is responsible for getting the work inspected / approved by
Consultant.

9.4 Installation of Chilled Water piping:

 The propossed chilled water pipes above grade is Seamless black steel SHIELD in
accourdance to ASTM A-53 Grade-B SCH-40 as per manufacturer
recommendation and approval.
 Fix the sleeves as per approved shop drawings and specification, during the
construction of structural elements.
 Ensure All chilled water pipes shall be painted with two coats of red oxide primer
prior to application of insulation.
 Pipe sizes 65mm and larger shall have welding joint. Pipe sizes 50mm and smaller
shall have threaded ends as per manufacturer recommendation. Also refer to
point #. 7.4.1 for threded connection procedure and 7.4.2 for welding connection
procedure.
 Welding of the pipes must be as per specifications and approved procedure.
 Mark the location of piping as per specification and approved shop drawing.
 Install approved supports, brackets for piping as per specification, approved shop
drawings and site requirements for each individual case (ie. Slab, Wall etc.).
 Supports shall be installed as per pipe manufacturer’s recommendations.
 Ready made hardwood shall be used for supporting the vertical chilled water
piping, which is placed on galvanized L angle or U channels and fastened with GI
threaded rods.
 Roller supports shall be installed for the pipes 200mm and above and in the
expansion joints.
 Flexible Pipe connectors shall be installed at all air handling units, pumps, and
chillers.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

 All the open ends of the pipes shall be protected properly at the end of each
day’s work.
 Drains shall be installed at low points in mains and branch lines (Vertical /
Horizontal) consisting of gate valve and short threaded nipple and cap so that the
system shall be drained completely.
 Valves, Piping specialties and accessories shall be installed as per manufacturer
recommendation and approved shop drawings.
 Unions shall be provided adjacent to each screwed type valve and shall be on the
outlet side of the valve.
 All valves shall be installed suitably to permit easy access for future maintenance.
 Eccentric reducers shall be installed in Horizontal chilled water system &
concentric reducers shall be installed in vertical chilled water system.
 Automatic Air vents shall be installed at high points and where ever required in
order to trap air from the chilled water system.
 Air separator to be installed with in the networks.
 Condensate drain piping shall be connected to the equipment drain pan
connections as per approved shop drawings.
 Condensate drain piping will be extended to the nearest floor drain and
connected to the drain system.
 Plug all open ends of pipes at the end of each day’s work using end caps.
 Raise Request for Inspection of Installation of Chilled Water Piping and fittings
including supports / brackets, valves, piping specialties and accessories as per the
approved shop drawing, by Consultant.
 After approval of installation of pipes and fittings, flushing shall be done for
chilled water Pipes with clean water to remove dust and debris that might have
been present during construction work.
 Plug all connections / branches / drains and fill with clean water for hydro
testing.

9.5 Threaded Connection procedure:

 Use the appropriate sealing material.


 The internal parallel threads of the fitting have to be joined to the taper external
threads.
 The surfaces of the treads have to be cleaned before being threaded.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

 The sealing material has to be applied homogenously and thoroughly on the


external thread, using only sealing material suitable for the application.
 A film of lubricant should be applied on the surface to be threaded in order to
prevent the sealing material from getting stuck and thus avoid irregularities in
the sealing effect.
 Check if all axes of the different threaded joint components are aligned according
to the tolerance.

9.6 Welding connection procedure:

In order to ensure that all welding takes place in safe manner, the following will be
considered:
 Welders
 The welding Equipment
 Working location
 Working instructions.

Welder:

 The welders to be trained and certified


 The welder must be healthy
 The welder must be trained for safe work i.e. toolbox talk etc.

Equipment:

On site, arc welding is usually carried out with direct current (DC), supplied from
diesel driven generator or Power source. Welding leads and welding return cables
are frequently dragged over rough surface, their insulation should therefore be
suitable for resisting fear and wear.
 The cables and couplings should be examined frequently for defects.
 The part of the cable which connected to the electrode holder should be
as flexible as possible.
 The welding return should be firmly connected to the metal by
constructed clamp.
 Electrode holder should be fully insulated.
 Electrode holder is essentially a pair of spring-loaded jaws.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

 The electrode holder must be made from good quality material.

Working requirements:

 Arrange good ventilation in case of welding enclosed resets.


 Insulated materials will be used in case of wet floor.
 Working instructions.
 Fire extinguisher required with welding all the time.
 Screens to be used when necessary, available all the time.
 Avoid welding near flammable materials.
 Checking area before leaving is strongly required.
 Monitoring of the area for gasses will be done.

Testing of welded pipework installation:

 Testing of welded pipework installation shall be by either destructive of


nondestructive test method.
 Destructive Testing & examination shall be exactly as detailed under Test
for Welder Qualification.
 Non-Destructive Testing shall consist of radiographic inspection. This test
shall be carried out by a specialist consultant approved by the Consultant.
The specialist consultant shall provide a report on the Radiographic Test
which has been made which includes interpretative results.
 The radiographs which do not comply with the requirement, shall be
unacceptable & the weld in question shall be re-examined.
 If a weld fails the testing requirements, then two additional welds made
by the same operative shall be tested, at no cost to the contract. If both
additional welds are successful then, in the case of destructive testing,
the cost of making good shall be at no cost to the contract.
 If either of the two additional welds fails the test requirements, then
further tests on other or all of the welds made by that operative shall be
carried out, at the Consultant discretion.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

9.7 TESTING OF CHILLED WATER PIPES & FITTINGS

 Care shall be taken to all the equipments, apparatus, devices to a pressure


exceeding its prescribed test pressure as obtained from its name plate data or
product catalogues.
 Care shall be taken to Equipments, apparatus and devices that might be
damaged by the test pressure shall be removed or blanked off.
 Ensure All Valves are in open condition before starting pressure test, NO
pressure shall be applied against closed valves.
 Ensure Temporary blank flanges are anchored firmly in a way to accommodate all
developed end trust.
 The Piping system shall be tested closed by plugging all openings in the system in
a proper way and filled slowly with water.
 Ensure all system is free from air lock, if so all the vent all entrapped air from the
system.
 Ensure water is reached to the entire system by releasing plugs temporarily.
 Pressure shall be applied to the system by means of hand pump drawing from a
water container. The pump discharge shall be connected to the system through
a globe valve, check valve and calibrated pressure gauge of suitable range to
have the test pressure range in the middle of the range.
 Subject the Cold Water piping to hydro test, Test pressure shall be at least 1.5
times the working pressure. for 24 hours.
 Ensure Test pressure is same at highest point of the system.
 Repair the leaks and defects if any until satisfactory results are obtained.
 Raise Request for Inspection of hydro testing to witness the same, by Consultant.
 After approval of inspection of hydro testing, release the water gradually and
protect the piping installation, and end cap the pipe.

9.8 INSULATION OF CHILLED WATER PIPING

 Check all required approved chilled water pipe insulations materials are readily
available on site.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

 Pipes shall be generally insulated with rigid sections of aluminium foil faced glass
fibre insulation with density of 64 Kg/m3 having a thermal conductivity factor of
0.029 w/m.k at 10 deg. C.
 Internal chilled water pipes (inside buildings) shall be insulated by 40mm thick
rigid insulation for pipes upto 40mm dia and 50mm for pipe sizes 50mm dia and
above.
 External chilled water pipes (on roofs and in chiller yard) shall be insulated by
50mm thick rigid insulation for pipe sizes up to 40 mm dia and 75 mm for for
50mm dia and above.
 For both internal and external pipes the insulation shall be finished with a water
proof Aluglass Cloth backing (18u / FR Glue / 8x8 Mesh Aluglass Cloth), combined
with a high performance flame retardant solvent acrylic adhesive, protected by
an easy-release silicone release paper.
 Where insulated pipework is run on roof, in plant room, chillers yard and tunnels
it shall be clad using an outer covering of plain aluminium sheet of 0.7mm or
thicker.
 Where exposed, insulated pipework runs through occupied or public areas it
shall be clad using an outer covering of plain aluminium sheet of 0.7 mm or
thicker as per manufacturer recommendation in the material submittal.
 Moke-up for pipe insulation shall be provided for consultant review and
approval.
 Apply the approved insulation materials and accessories according to
specification and manufacturer instructions.
 Ensure all insulation materials are in dry condition during the application.
 Pipe surface shall be cleaned properly and painted as per specification.
 Apply insulation with longitudinal seams at top and horizontal pipe runs.
 Pipe insulation shall be applied with least number of joints.
 Approved adhesive shall be applied in longitudinal seam and end faces of the
insulation and entire pipe surfaces as per Approved material.
 For flanges, elbows, fittings and valves mitered section of pipe insulation of same
material shall be used.
 Permissible access shall be maintained to the valves to operate without
disturbing the insulation.
 Removable type insulation sections shall be prepared and provided to valves
including check valves and strainer basket and other valves.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24

 In case of rising steam valves used in chilled water system, insulation shall be
extended and insulation joints and valve specialties seams shall be sealed
properly in order to prevent passage of air to pipe surface.
 Aluminium tape shall be applied on the joints of insulation segments properly as
per manufacturer recommendation.
 Cover the approved THERMOFOIL sheet properly on the entire circumference of
the Insulated duct and pull sheet tight and smooth.
 Use Thermo foil recommended Tape to seal the joints in a way no air can
penetrate through the joints
 Raise request for inspection of Insulation of Chilled Water Piping, by Consultant.
 Identification for Chilled Water Supply and return line and valves and specialties
shall be done as per specification with approved identification materials.
 Raise request for inspection of Identification of Chilled Water Piping and
Accessories, by Consultant.

10.ATTACHMENTS

 Risk Assessment

 Inspection & Test Plan

 Quality Checklist
Project Name: Doc. no.: TRA-HYL-MST-CW-GEN-00031
PACKAGE G3 - BEACH BAR Rev.: 00
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA-PG3)
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing

RISK ASSESSMENT
Project Name: Doc. no.: TRA-HYL-MST-CW-GEN-00031
PACKAGE G3 - BEACH BAR Rev.: 00
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA-PG3)
METHOD STATEMENT Date: 26/07/21

Chilled Water Piping and Accessories Installation & Pressure Testing

INSPECTION & TESTING


PLAN
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT
Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing

Quality Checklist

You might also like