TRA-HYL-MST-CW-GEN-00031 00 MST Chilled Water Piping System Installation & Testing
TRA-HYL-MST-CW-GEN-00031 00 MST Chilled Water Piping System Installation & Testing
CONTRACT NO CN0063
CLIENT / PROJECT DEC MAIN
EMPLOYER MANAGER CONTRACTOR
METHOD STATEMENT
Ref.: TRA-HYL-MST-CW-GEN-00031
Prepared Reviewed Approval for Description & page Number of
Rev Date
By by Issuance by Revision
R00 26/07/2021 MURTADA ASIM ASIM FOR REVIEW & APPROVAL
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Table of Contents
1. PURPOSE........................................................................................................................... 5
2. PROJECT DETAILS:............................................................................................................. 5
3. SCOPE................................................................................................................................5
Under Ground – Pre-insulated Black Steel pipes.........................................................5
Above Ground – Insulated Black Steel pipes...............................................................5
4. Sequence of Work:............................................................................................................5
5. REFERENCES & STANDARDS:.............................................................................................6
6. DEFINITIONS & ABBREVIATIONS.......................................................................................6
7. RESOURCES:...................................................................................................................... 8
7.1 HUMAN RESOURCES:......................................................................................................... 8
RESPONSIBILITIES:................................................................................................................... 8
7.2 MATERIALS.................................................................................................................. 10
7.3 EQUIPMENTS & TOOLS.....................................................................................................10
8. SAFETY & HEALTH........................................................................................................... 12
9. PROCEDURE.................................................................................................................... 16
9.1 Safety...........................................................................................................................16
9.2 Handling and Storage.................................................................................................. 16
9.3 Work Sequence and Methodology..............................................................................16
9.4 Installation of Chilled Water piping:............................................................................17
9.5 Threaded Connection procedure:................................................................................18
9.6 Welding connection procedure:..................................................................................19
9.7 TESTING OF CHILLED WATER PIPES & FITTINGS..........................................................21
9.8 INSULATION OF CHILLED WATER PIPING.....................................................................21
10. ATTACHMENTS............................................................................................................23
Risk Assessment..............................................................................................................23
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
1. PURPOSE
2. PROJECT DETAILS:
3. SCOPE
Supply, installation & Testing of the chilled water piping and its accessories for all
applications in line with project requirements.
4. Sequence of Work:
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Contract
Project Specifications:
230000 Particular HVAC Specification.
o
235210 Piping and Accessories
o
230529 Hangers and Supports for HVAC Piping and Equipment.
o
230700 HVAC Pipe Insulation.
o
230823 Systems Commissioning.
o
Legislation and code of practice:
For other standards & codes refer to Project Specifications.
Approved supplier details
230010.1 Approved Manufacturer List
o
Approved IFC drawings.
Approved other method statement.
Material approval
Contract Scope, Drawings & Specification.
Project Quality Plan
Project HSE Plan
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
7. RESOURCES:
PROJECT TEAM:
DOCUMENT
AITA KHATI aita@hennesseyllc.com 0561224230
CONTROLLER
DOCUMENT
REDEN NAVA reden@hennesseyllc.com 0524483679
CONTROLLER
RESPONSIBILITIES:
Project Manager:
Responsible for overall project execution, quality and safety.
o
Adopt a leading role with respect to Contractor’s quality and
safety procedures.
The PM is responsible for the overall implementation of this
o
method of statement.
The Project Manager shall ensure that the key personnel are
o
well aware of the specifications and method of statement.
QA/QC Engineer:
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Project Engineer:
shall arrange all materials, equipment, safety related items and
o
manpower
direct the Site Engineers & Foremen to resort appropriate action
o
for the smooth execution of the works.
Safety Officer:
shall be responsible for safe working environment & conditions.
o
Coordinate with Site Engineer to identify potential hazards
o
before works
advise methods of safe working from new developments.
o
Surveyor:
shall be responsible for setting out for levels, layout, and lines &
o
establish top levels.
Ensuring setting out books are properly maintained and filed
o
when completed.
To coordinate with the SBJV & DEC surveyor in determining
o
coordinates, levels, and limits.
General Forman:
shall ensure that all works are carried out according to approved
o
IFC drawings. He shall direct the surveyor for the setting out lines
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Document Controller:
Distribution of Project information in timely and appropriate
o
manner. [IR’s, RFI’s, MST & RA as per instruction of project
Manager.
Preparing daily reports in coordination with the project manager.
o
Keeping a record of all material delivery notes, requests to
o
testing laboratory, material submittals, drawings, certificates and
other project documents.
7.2 MATERIALS
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
The capacity / size of the above tools and equipment shall be judged in
accordance with site conditions, requirements, and availability at the time of
execution
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
HENNESSEY LLC Site HSE Management Plan & Precautions shall be applied.
SBJV HSE guidelines and management plan shall be strictly adhered during the
substructure concreting works.
TRA EMPLOYER, ENGINEER & PROJECT HSE guidelines and management plan
shall be strictly adhered during the substructure concreting works.
HENNESSEY LLC will ensure that the approved Method Statement, Risk
Assessment and local authority requirements fully complied prior to commence
the works & while following permit to work system.
Safety of the personnel and properties is to be given prime importance and all
the works to be carried out without causing any accidents or property
damages.
Valid Copy of all test certificate will be available at site reference upon request.
HENNESSEY LLC Site HSE Management Plan & Precautions shall be applied.
SBJV HSE guidelines and management plan shall be strictly adhered during the
substructure concreting works.
TRA EMPLOYER, ENGINEER & PROJECT HSE guidelines and management plan
shall be strictly adhered during the substructure concreting works.
HENNESSEY LLC will ensure that the approved Method Statement, Risk
Assessment and local authority requirements fully complied prior to commence
the works & while following permit to work system.
Safety of the personnel and properties is to be given prime importance and all
the works to be carried out without causing any accidents or property
damages.
Valid Copy of all test certificate will be available at site reference upon request.
All personnel involved will use necessary PPE as required such as:
Safety helmet, Hard Hat.
o
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Safety Boots
o
Safety Goggles;
o
Neoprene work gloves
o
N95 Respirator;
o
Disposable coveralls;
o
ear plugs etc.
o
Adequate access and egress should be provided to the site for work.
All the equipment, tools and tackles being used for the work should be in good
working condition and maintained.
HSE officer to ensure that excavated area is barricaded. Adequate warning
tapes and warning signs are provided.
All access from adjacent working area to extension area shall be closed and
monitored.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Though the excavation is minor in nature a hazard analysis table is attached for
excavation activities. All major possible risks/ hazards are highlighted.
The workers will be made aware of safety requirements related to this activity
through daily tool box and safety talk.
All the personnel will be provided with daily toolbox talk and safety talk on the
procedures to execute the work safely. The tool box talks will be recorded. The
safety inspector will continually monitor any risk assessment factors of all
manual handling activities.
All required work permits will be acquired and kept available at respective work
site hanged clearly in plastic folders.
Signs or directional signboards, shall be placed in all strategic places as
required.
Safety notice board will be installed.
Access to carry out works below ground level will be accessed by use of ladders
and scaffold. Ladder and scaffold prior to use must be inspected by a
competent person for visible defects on a periodic basis.
Metal ladders must have rubber shoes fixed it base all the time.
In the event short term access is required, ladders, suitably and properly
attended will be used.
All Possible techniques should be implemented and used to minimize the levels
of noise transmission to the environment as far as possible
Trained operatives to be deployed under a competent supervision.
Summer mid-day breaking timing shall be strictly followed as per local authority
regulations.
Covid-19 Control measures added to the attached Risk Assessment.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Emergency Arrangements:
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
9. PROCEDURE
9.1 Safety
Qualified person must be trained and authurised for use electrical machines.
Ensure all concerned personnel shall use PPE (Personal Protective Equipment)
and all other items as required.
Ensure adequate lighting is provided in the working area at night time.
Ensure service area/work area openings are provided with barricade, tape, and
safety nets.
All the materials delivered to site are inspected properly and stored as per the
manufacturer recommendations.
MIR shall be issued, for the inspection of materials received to Consultant for
their approval.
Work shall be carried out by the site staff under the strict supervision and
guidance of the concerned Supervisors / Engineers.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Site Engineer shall check the work as per the check list attached, further checked
by the Consultant.
WIR shall be prepared by QA/QC Engineer and to be issued to Consultant for
checking the work.
Sub-contractor site Engineer & QA/QC Engineer shall co-ordinate with Contractor
and Consultant and arrange for their inspection.
QA/QC Engineer is responsible for getting the work inspected / approved by
Consultant.
The propossed chilled water pipes above grade is Seamless black steel SHIELD in
accourdance to ASTM A-53 Grade-B SCH-40 as per manufacturer
recommendation and approval.
Fix the sleeves as per approved shop drawings and specification, during the
construction of structural elements.
Ensure All chilled water pipes shall be painted with two coats of red oxide primer
prior to application of insulation.
Pipe sizes 65mm and larger shall have welding joint. Pipe sizes 50mm and smaller
shall have threaded ends as per manufacturer recommendation. Also refer to
point #. 7.4.1 for threded connection procedure and 7.4.2 for welding connection
procedure.
Welding of the pipes must be as per specifications and approved procedure.
Mark the location of piping as per specification and approved shop drawing.
Install approved supports, brackets for piping as per specification, approved shop
drawings and site requirements for each individual case (ie. Slab, Wall etc.).
Supports shall be installed as per pipe manufacturer’s recommendations.
Ready made hardwood shall be used for supporting the vertical chilled water
piping, which is placed on galvanized L angle or U channels and fastened with GI
threaded rods.
Roller supports shall be installed for the pipes 200mm and above and in the
expansion joints.
Flexible Pipe connectors shall be installed at all air handling units, pumps, and
chillers.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
All the open ends of the pipes shall be protected properly at the end of each
day’s work.
Drains shall be installed at low points in mains and branch lines (Vertical /
Horizontal) consisting of gate valve and short threaded nipple and cap so that the
system shall be drained completely.
Valves, Piping specialties and accessories shall be installed as per manufacturer
recommendation and approved shop drawings.
Unions shall be provided adjacent to each screwed type valve and shall be on the
outlet side of the valve.
All valves shall be installed suitably to permit easy access for future maintenance.
Eccentric reducers shall be installed in Horizontal chilled water system &
concentric reducers shall be installed in vertical chilled water system.
Automatic Air vents shall be installed at high points and where ever required in
order to trap air from the chilled water system.
Air separator to be installed with in the networks.
Condensate drain piping shall be connected to the equipment drain pan
connections as per approved shop drawings.
Condensate drain piping will be extended to the nearest floor drain and
connected to the drain system.
Plug all open ends of pipes at the end of each day’s work using end caps.
Raise Request for Inspection of Installation of Chilled Water Piping and fittings
including supports / brackets, valves, piping specialties and accessories as per the
approved shop drawing, by Consultant.
After approval of installation of pipes and fittings, flushing shall be done for
chilled water Pipes with clean water to remove dust and debris that might have
been present during construction work.
Plug all connections / branches / drains and fill with clean water for hydro
testing.
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
In order to ensure that all welding takes place in safe manner, the following will be
considered:
Welders
The welding Equipment
Working location
Working instructions.
Welder:
Equipment:
On site, arc welding is usually carried out with direct current (DC), supplied from
diesel driven generator or Power source. Welding leads and welding return cables
are frequently dragged over rough surface, their insulation should therefore be
suitable for resisting fear and wear.
The cables and couplings should be examined frequently for defects.
The part of the cable which connected to the electrode holder should be
as flexible as possible.
The welding return should be firmly connected to the metal by
constructed clamp.
Electrode holder should be fully insulated.
Electrode holder is essentially a pair of spring-loaded jaws.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Working requirements:
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Check all required approved chilled water pipe insulations materials are readily
available on site.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
Pipes shall be generally insulated with rigid sections of aluminium foil faced glass
fibre insulation with density of 64 Kg/m3 having a thermal conductivity factor of
0.029 w/m.k at 10 deg. C.
Internal chilled water pipes (inside buildings) shall be insulated by 40mm thick
rigid insulation for pipes upto 40mm dia and 50mm for pipe sizes 50mm dia and
above.
External chilled water pipes (on roofs and in chiller yard) shall be insulated by
50mm thick rigid insulation for pipe sizes up to 40 mm dia and 75 mm for for
50mm dia and above.
For both internal and external pipes the insulation shall be finished with a water
proof Aluglass Cloth backing (18u / FR Glue / 8x8 Mesh Aluglass Cloth), combined
with a high performance flame retardant solvent acrylic adhesive, protected by
an easy-release silicone release paper.
Where insulated pipework is run on roof, in plant room, chillers yard and tunnels
it shall be clad using an outer covering of plain aluminium sheet of 0.7mm or
thicker.
Where exposed, insulated pipework runs through occupied or public areas it
shall be clad using an outer covering of plain aluminium sheet of 0.7 mm or
thicker as per manufacturer recommendation in the material submittal.
Moke-up for pipe insulation shall be provided for consultant review and
approval.
Apply the approved insulation materials and accessories according to
specification and manufacturer instructions.
Ensure all insulation materials are in dry condition during the application.
Pipe surface shall be cleaned properly and painted as per specification.
Apply insulation with longitudinal seams at top and horizontal pipe runs.
Pipe insulation shall be applied with least number of joints.
Approved adhesive shall be applied in longitudinal seam and end faces of the
insulation and entire pipe surfaces as per Approved material.
For flanges, elbows, fittings and valves mitered section of pipe insulation of same
material shall be used.
Permissible access shall be maintained to the valves to operate without
disturbing the insulation.
Removable type insulation sections shall be prepared and provided to valves
including check valves and strainer basket and other valves.
Project Name: Doc. no.: TRA-HYL-MST-
CW-GEN-00031
PACKAGE G3 - BEACH BAR
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA) Rev.: 00
METHOD STATEMENT Date: 26/07/21
Chilled Water Piping and Accessories Installation & Pressure Testing Page of 24
In case of rising steam valves used in chilled water system, insulation shall be
extended and insulation joints and valve specialties seams shall be sealed
properly in order to prevent passage of air to pipe surface.
Aluminium tape shall be applied on the joints of insulation segments properly as
per manufacturer recommendation.
Cover the approved THERMOFOIL sheet properly on the entire circumference of
the Insulated duct and pull sheet tight and smooth.
Use Thermo foil recommended Tape to seal the joints in a way no air can
penetrate through the joints
Raise request for inspection of Insulation of Chilled Water Piping, by Consultant.
Identification for Chilled Water Supply and return line and valves and specialties
shall be done as per specification with approved identification materials.
Raise request for inspection of Identification of Chilled Water Piping and
Accessories, by Consultant.
10.ATTACHMENTS
Risk Assessment
Quality Checklist
Project Name: Doc. no.: TRA-HYL-MST-CW-GEN-00031
PACKAGE G3 - BEACH BAR Rev.: 00
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA-PG3)
METHOD STATEMENT Date: 26/07/21
RISK ASSESSMENT
Project Name: Doc. no.: TRA-HYL-MST-CW-GEN-00031
PACKAGE G3 - BEACH BAR Rev.: 00
THE ROYAL ATLANTIS RESORT & RESIDENCES (TRA-PG3)
METHOD STATEMENT Date: 26/07/21
Quality Checklist