TRA-HYL-QCP-CW-GEN-00031 00 Chilled Water Pipes
TRA-HYL-QCP-CW-GEN-00031 00 Chilled Water Pipes
:
RESORT & RESIDENCES (TRA) TRA-HYL-QCP-CW-
GEN-00998 00
QUALITY CHECKLIST FOR:
HVAC - Chilled Water Piping system Page 1 of 2Z
recommendation.
5. Check the insulation is properly & correctly aligned,
lapped & adequately bonded. Ensure no gaps & shall
cover the entire surface of the pipes.
6. Check the vapour sealing has been correctly applied.
Ensure that all penetrations to the insulation are
properly sealed.
7. Check the vapour seal around the support & anchor if
properly installed. Any extra Insulation to be cut
around obstructions.
8. Ensure that the insulation around the joints is not
opening. Check for any insulation becoming loose.
9. Check that high-density rubber blocks at point of pipe
support are insulated as per specification.
10. Check that service identification labels are provided
on exposed insulated chilled water pipe works and in
access doors.
11. Check that annular spaces between insulation and
sleeve have been sealed with approved material.
12. Ensure that all pipe work insulation is not sagging.
For Sub-Con. / HENNESSEY: Date: For MAIN CONTRACTOR Date For CONSULTANT Rep. Date:
QA/QC: