Erection Sequence at Jetty - Watermarked
Erection Sequence at Jetty - Watermarked
Erection Sequence at Jetty - Watermarked
West Africa
SPCPL: Barge Loader 001
ERECTION MANUAL
ERECTION MANUAL
3 ERECTION SEQUENCE
3.1 General Notes
These main components will be delivered by ship. For installation works, temporary erection
supports has to be set on the pier.
For the execution of the erection works of the ship loader please refer to:
G e n e r a l Arrangement of Barge Loader
Transport sketch
Erection support sketch
Operation & Maintenance Manual (O&M Manual)
Based on the above mentioned drawings and manuals, all detailed drawings required for the
execution of the subject are listed in the respective drawing list.
The erection and commissioning of the ship loader should take place in the presence of
ThyssenKrupp advisors.
Prior start of erection all embedded parts are installed in accordance to GA drawings.
Furthermore all foundations have to be ready to bear the loads as mentioned in G A drawing.
Note: Before lifting of the parts, the weights have to be checked with the actual
packing list and to be controlled with the crane capacities!
Attention: The weld back current cable has to be positioned close to the
weld joint! All welds have to be performed and checked in
accordance to their drawings, welding procedures and
specifications, and have to be approved by the client! The
welding procedures will be prepared by the erection contractor
and approved by TKF.
Welding seams that have to be checked by ULTRASONIC are
designated on the drawings and the test schedules!
ERECTION MANUAL
Sub Structure
Slewing connection
First the Sub Structure part has to be lifted into its final
position, adjusted with shim plates and mounted
(t i g h t e n i n g torques) to the anchor bolts on the
foundation.
Weights:
Sub Structure approx. 3 7 0 0 0 kg
Slewing connection approx. kg
Weight:
Slew Deck approx.88,000 kg
ERECTION MANUAL
Weight:
Hydraulic cylinder approx. 2.800 kg
Transport Sketch
Arrangement boom/shuttle
Arrangement Ship Loader
Hinge point – boom conveyor
Erection support sketch
Preconditions:
The boom has to be assembled with all mechanical parts, necessary for installation of the
shuttle.
A temporary erection support has to be positioned on the pier to support the boom during
erection until the counterweights are installed and the hoisting system is ready for operation
(s e e hereto erection support sketch).
The direction of the hinge point axis of the boom ( Slew Deck ) must be rectangular to the pier
and the storm locking device to be installed and locked.
ERECTION MANUAL
Lifting sequence:
When the preconditions are satisfied the boom can be lifted (in horizontal position) and
placed between the hinge points of the Slew Deck.
When the pins have reached their final position, the boom can be lowered onto the erection
support and fixed with staying ropes.
After lowering the boom onto the erection support, the crane can be released.
ERECTION MANUAL
After installation, the shuttle has to be completely retracted and locked, to avoid an extending
of the shuttle during erection works.
The boom incl. shuttle can be completed now with all remaining mechanical items, as well as
the electrical installation.
Note: Special attention has to be paid to the correct tightening of the shrink disc of the
hinge pins. ( See hereto O&M Manual ).
Weights:
Boom ( steel structure only ) approx. 200,000 kg
Shuttle ( steel structure only ) approx. 54,000 kg
Attention: If the mechanical items of the shuttle are installed prior lifting and
slotting procedure, the forces of the erection support rises up to
approx. XXXXkN ( each girder ) see erection support sketch!
ERECTION MANUAL
The support for the hydraulic unit has to be installed ( it contains to the stairs and railing of the
Slew Deck ). Afterwards the hydraulic power pack has to be installed.
The hydraulic motor with gear box has to be installed, adjusted and tightened in accordance
with the respective manual.
The hoses and pipes for the hydraulic motor as well as for the hoisting cylinder have to be
installed.
After installation of the hydraulic systems they have to be flushed and air extracted before
setting in operation.
Note: The flushing of the hydraulic systems has to be executed by using a temporary
bypass filter system with an independent pump. The hydraulic system has to be
flushed in the presence of a ThyssenKrupp-advisor! ( See Hydraulic Manual )
After set in operation of the hydraulic system, the hoisting cylinder has to be connected to the
boom.
Weight:
Hydraulic power pack approx. 900 kg
ERECTION MANUAL
The cabling and electrical equipment will be installed parallel to the mechanical erection.
3.8 Counterweight
Boom counterweight
During the balancing procedure no erection tools, scaffolding material etc. should remain
around the boom.
The balancing procedure should be carried out with a minimum of wind influences.
Balancing procedure:
Two pressure gauges ( glycerine absorbed ) with a measuring accuracy of 1% or better have
to be connected to the control block measuring points, rod side and piston side, at the
hydraulic cylinder. Hydraulic cylinder has to be checked for a proper function.
Attention has to be paid to place the counterweight blocks shock less onto the boom back part.
The counterweights have to be inserted step by step.
For the theoretical counterweight please refer to counterweight drawing. It has assumed that
the final weight of the counterweights has been checked by weighing and the copies of the
weighing cards/protocol been submitted to TKF upon the weighing operation.
The measurement schedule of the forces in the boom hoisting cylinder during balancing
procedure shall be submitted immediately to ThyssenKrupp for checking.
The remaining counterweights have to be installed until correct pressure values of luffing
cylinder are achieved in accordance to the “Control of the forces in the hydraulic cylinder of the
boom”. (Document is attached to chapter 3)
A further adjusting of the counterweights may become necessary as a result of the final
verification by our Engineers.
Counterweight has to be erected under the instructions of the ThyssenKrupp (TAG) advisor.
ERECTION MANUAL
After balancing, the boom should be lifted or lowered to all relevant positions and pressure in
the hydraulic cylinder will be checked and transmitted to ThyssenKrupp.
Weight:
Counterweight each single part approx. 74,000 kg
The installation of the ladders, railings and platforms will be executed parallel to the
mechanical erection and electrical installation.
Weight:
Round platform ( 4 peaces ) each approx. 1.100 kg
3.10 Lubrication