MANHOURS PER QUANTITY

ITEM NO. WORK DESCRIPTION M.H./ UNIT


LOW AVE HIGH
pre-design+project M.H
`1 8 20 32
desgin development M.H
`2 24 60 96
construcation documentation M.H
`3 24 60 96
contract administration+construction M.H
`4 8 20 32
concept+schematic desgin M.H
`5 40 100 160
planning+development M.H
`6 8 20 32
contractor selection M.H
`7 32 80 128
defects+ post-construction M.H
`8 8 20 32

152 380 608

sa
year

2016

2017

2019

2020

2021

2022
‫‪salery report supply‬‬
‫‪year‬‬ ‫‪dep‬‬ ‫‪salary LE‬‬

‫‪2016‬‬ ‫رئيس الرسومات‬ ‫‪13000 LE‬‬

‫‪2017‬‬ ‫مدير المشروعات‬ ‫‪11000 LE‬‬

‫‪2019‬‬ ‫الرسومات التنفيذية‬ ‫‪10000 LE‬‬

‫‪2020‬‬ ‫التصميم الخارجي‬ ‫‪10000 LE‬‬

‫‪2021‬‬ ‫المخطاطات المعمارية‬ ‫‪6000 LE‬‬

‫‪2022‬‬ ‫التصميم الداخلي‬ ‫‪5000 LE‬‬


Factors no. factors α cost

F1 Contractor bidding strategy 0


F2 0
F3 0
F4 0
F5 Risk sharing between the parties 0.15 0
F6 Level of competition (number of competitors) 0
F7 <3 0
F8 <10 0.005 950
F9 open 0
F10 Labor cost 190000
F11 Labor availability 0 0
profit 0.45 85500
F12 Equipment (cost/availability/performance) 0.01 1900
F13 Level of workmanship (productivity and performance) 0.073 13870
F14 low 0
F15 ave 0.073 13870
F16 high 0
F17 Market conditions/ economic climate 0.0005 95
F18 stable 0 0
F19 unstable 0.005 0
F20 The project complexity 0.5 95000
F21 A (residency) 0.1 19000
F22 B (institutional and commerial) 0.07 13300
F23 C (industrial) 0.5 0
F24 D (specific industrial) 0.256 48640
F25 E (interstate construction- landscape) 0.273 51870
F26 F (heavy construction) 0.72 0
F27 A clear scope definition 0.7 133000
F28 Financial capabilities of the client 0 0
F29 LOW 0.1 0
F30 AVE 0.015 2850
F31 HIGH 0.007 1330
F32 Impact of project schedules 0.021 3990
F33 HIGH 0.15 28500
F34 LOW 0.1. 0
F35 Site constraints (access, storage, services 0
F36 Roads 0
F37 land scape 0.5 95000
F38 Buildings 0.02 3800
F39 Electromechanical 0.05 9500
F40 Water and sanitation 0.05 9500
F42 Other works 0
F43 The degree of the company classificatio 0 0
F44 The first category 0
F45 The second category 0
F46 The third category 0
F47 The fourth category 0
F48 Working experience team arch 0
F49 3 years 0
F50 3-5 years
F51 5-10 year 0.015 2850
F52 10-15 years 0
F53 Working experience team MEP 0
F54 3 years 0
F55 3-5 years 0
F56 5-10 year 0.015 2850
F57 10-15 years 0
F58 Working experience team Cvill 0
F59 3 years 0
F60 3-5 years 0
F61 5-10 year 0.015 2850
F62 10-15 years 0
F63 Working experience team safty 0
F64 3 years 0
F65 3-5 years 0
F66 5-10 year 0
F67 10-15 years 0
F68 Working experience team port and harbour 0
F69 3 years 0
F70 3-5 years 0
F71 5-10 year 0
F72 10-15 years 0
TOTAL 830015
direct cost should be