Professional Documents
Culture Documents
Only Dome - 27000 Ok
Only Dome - 27000 Ok
Dimensions :
Provide circular tank having total depth as 3.9 m and wall thickness at bottom
as 200 mm and at top as 150 mm as shown below.
0.15 0.15
8.00
3.5
Out-let Level
Dead storage = 0.1 m Scour Level
For the design of tank slab only one quarter portion shall be designed by
by considering it as a square pannel with two adjacent edges discontinuous.
Data:-
1) Capacity of Structure:-
2) Depth of tank:- 3.50 Mts.i/c free board.
3) Size of tank (LengthxBreadth) Length = 4.14 Mts. Breadth = 4.14 Mts.
4) Provde Free Board 0.15 Mts.
5) Design contant for M-20 Gr.Concrete.
i) sst = 150 N/mm^2 scbc = 7N/mm^2 K = 0.378 j = 0.874
R = 1.160
ii) sst = 190 N/mm^2 scbc = 7N/mm^2 K = 0.329 j = 0.890
R = 1.025
Say 976.00 mm 2
Say 272.00 mm 2
Say 160.40 mm 2
Distribution steel:-
= 0.30 -0.10 (Wall Thick. -100)/(450 -100)
= 0.12 %
Therefore area of steel = = 310.71 mm 2
Say 311.00 mm 2
Area of steel on each face = = 155.50 mm 2
4.90
D C
As the frame is symmetrical about both axis, moment distribution is done for one quarter of
the tank only.
Consider joint A
s AB = 4EI/ l , s AD = 4EI/ b
Therfore sAB/sAD= b/ l Therfore distribution factors = b/(l+b) :
= 0.40 :
JOINT:- A
Member AB AD
Dis.Factor 0.40 0.60
F.E.M. (-) 4.26 pa (+) 2.00 pa
Balancing (+) 1.06 pa (+) 1.20 pa
Final moment(Mf) ( - ) 3.20 pa (+) 3.20 pa
Mts.
0.874
0.890
N/mm 3
N/mm 3
l/(l+b)
0.60
N-m
N-m
N-m
N-m
N-m
N-m
N
N
N
N
N-m
0.890
0.890
0.890
0.890
ABSTRACT OF COST
NAME OF WORK:-PROV.LWSS TO PC HABITATION OF KOHLA
KALOOR & CHOA CHAKRALA IN TEHSIL NADAUN
DISTT. HAMIRPUR (HP)
(SUB HEAD:- W/E C/O CIVIL WORKS)
S.No. DESRIPTION OF ITEM REFERENCE AMOUNT
1) Main Storage tank of 238500 Annexure - I 484285.00
Lts.cap.at Node No.28
2) Collection Tank of 12600 Annexure - II 86079.00
at Node No.231
3) Storage tank of 36500 Lts. Annexure - III 230579.00
cap.at Node No.240
4) Main Storage tank of 141700 Annexure - IV 379296.00
Lts.cap.at Node No.1
5) Storage tank of 13200 Lts. Annexure - V 87320.00
cap.at Node No.105
6) Collection Tank of 79100 Annexure - VI 291038.00
at Node No.200
7) Storage tank of 7500 Lts. Annexure -VII 73287.00
cap.at Node No.202
8) Main Storage tank of 79100 Annexure - VIII 291038.00
Lts.cap.at Node No.147
9) Storage tank of 14200 Lts. Annexure - IX 90496.00
cap.at Node No.211
10) Storage tank of 17200 Lts. Annexure - X 101231.00
cap.at Node No.171
11) Storage tank of 12200 Lts. Annexure - XI 85071.00
cap.at Node No.145
12) C/O Pump House of size Annexure - XII 467872.00
4.50 x 3.00 Mtr. (2 No's)
13) C/O Pump House of size Annexure - XIII 451775.00
10.00 x 5.00 Mtr. (1No's)
TOTAL 3119367.00
Say Rs. 3119370.00
RCC TANK (With Dome Slab)
NAME OF WORK:-PROV.LWSS TO PC HABITATION OF KOHLA KALOOR
& CHOA CHAKRALA IN TEHSIL NADAUN DISTT. HAMIRPUR (HP)
(SUB HEAD:- C/O RCC STORAGE TANK OF 238500 Lts.)
S.No. Description of item
1) Tank below the ground 1.95 Mts.
2) Dimension of tank Dia. Length Breadth Ht./Depth
Outer 10.80 Mts.
Inner 10.10 Mts.
3) p 3.1416 Mts.
4) p/4 0.7854 Mts.
5) Scour pipe 6.00 Mts.
6) Size of trenches Aver. 0.65 0.98 Mts.
7) Thick.of Lean concrete 1:3:6 0.10 Mts.
8) Thick. of base floor 0.20 Mts.
9) Thick. of Wall Depth F.Board 0.15 Mts.
10) Internal depth i/c F.B. 3.00 0.15 3.15 Mts.
11) Long radius of dome (R ) 6.00 Mts.
12) Rise of dome (h) 1.50 Mts.
13) Width of ring beam 0.15 Mts.
14) Depth of ring beam 0.20 Mts.
15) Thick.of dome 0.10 Mts.
16) Inclined length of steel ladders 4.22 Mts.
17) Scour pipe 150 mm Rs. 683.10
18) Inlet,outlet pipe & overflow pipe.
125 mm Rs. 580.30
19) Size of man hole cover (Medium 500 mm
duty)
20) Cost of S/Valve' Chamber Rs. 5105.60
20) Cost of Sluice Valve 150 mm 11676.60
21) Cost of Sluice Valve 125 mm 10010.50
DETAIL OF MEASUREMENT
NAME OF WORK:-PROV.LWSS TO PC HABITATION OF KOHLA KALOOR
& CHOA CHAKRALA IN TEHSIL NADAUN DISTT. HAMIRPUR (HP)
(SUB HEAD:- C/O RCC STORAGE TANK OF 238500 Lts.)
S. Decription of item Nos. Dimension Qty.
No. L B H/D
1) Excavation in foundation & trenches
etc. in earth work in all kinds of soil
within all leads & lifts as per entire
satisfaction of Engineer in charge.
Tank p/4 10.80 10.80 1.95 178.64
Scour pipe 1.00 6.00 0.65 0.98 3.80
Total 182.44
2) P/L cement concrete1:3:6 (1Cement
:3Sand:6 graded stone aggregate 40
mm nominal size) & curing complete
Tank p/4 10.80 10.80 0.10 9.16
Total 9.16
3) P/L cement concrete1:1.5:3 (1Cement
:1.5 Sand:3graded stone aggregate 20
mm nominal size) & curing complete
excluding the cost of form work and
reinforcement for RCC work :-
(i) Base floor p/4 10.80 10.80 0.20 18.32
Total 18.32
(ii) Vertical wall p 10.25 0.15 3.15 15.22
Total 15.22
4) Prov.form work with steel shuttering
so as to give an fair finish complete
in all respect.
(i) Vertical wall Inside p 10.10 3.15 99.95
Outside p 10.40 3.15 102.92
Total 202.87
5) Prov.form work of ordinary timber so
as to give the rough finish complete
in all respect.
(i) Arches beyond 6.00 mts. Span. 2xp 6.00 1.50 56.55
Total (i) 56.55
Deduction of Man hole cover 2 x p/4 0.500 0.500 0.39
Total (ii) 0.39
Net Qty. (i -ii) 56.16
6) Prov.smooth finishing in cement
mortor 1:3 (1cement : 3 sand)
Inside p 10.10 3.15 99.95
Outside p 10.40 3.15 102.92
Total 202.87
7) Prov./ Laying c.concrete 1:2:4 (1Ce-
ment : 2 Sand : 4 Graded stone agg-
regate 20 mm nominal size) & curing
complete excluding the cost of form
DETAIL OF MEASUREMENT
NAME OF WORK:- PROV.LWSS TO PC HABITATION OF KOHLA KALOOR & CHOA
CHAKRALA IN TEHSIL NADAUN DISTT. HAMIRPUR (HP)
(SUB HEAD:- C/O RCC STORAGE TANK OF 12200 LTS. WITH FLAT SLAB)
S.No. Decription of item Nos. Dimension Qty.
Length Breadth Ht/Depth
1) Excavation in foundation & trenches
etc. in earth work in all kinds of soil
within all leads & lifts as per entire
satisfaction of Engineer in charge.
Tank p/4 3.60 3.60 0.70 7.13
Scour pipe 1.00 6.00 0.65 0.35 1.37
Total 8.49
2) P/L cement concrete1:3:6 (1Cement
:3Sand:6 graded stone aggregate 40
mm nominal size) & curing complete
Tank p/4 3.60 3.60 0.10 1.02
Total 1.02
3) P/L cement concrete1:1.5:3 (1Cement
:1.5 Sand:3graded stone aggregate 20
mm nominal size) & curing complete
excluding the cost of form work and
reinforcement for RCC work :-
(i) Base floor p/4 3.60 3.60 0.20 2.04
Total 2.04
(ii) Vertical wall p 3.15 0.15 1.90 2.82
Total 2.82
4) Prov.form work with steel shuttering
so as to give an fair finish complete
in all respect.
(i) Vertical wall Inside p 3.00 1.90 17.91
Outside p 3.30 1.90 19.70
(ii) Flat surfaces such as soffits of Total 37.60
suspended floors, roofs,landing and
the like.
Tank p/4 3.00 3.00 7.07
Total (i) 7.07
Deduction of Man hole cover 2 x p/4 0.500 0.500 0.39
Total (ii) 0.39
Net Qty. (i -ii) 6.68
5) Prov.smooth finishing in cement
mortor 1:3 (1cement : 3 sand)
Inside p 3.00 1.90 17.91
Outside p 3.30 1.90 19.70
Total 37.60
6) Prov./ Laying c.concrete 1:2:4 (1Ce-
ment : 2 Sand : 4 Graded stone agg-
regate 20 mm nominal size) & curing
complete excluding the cost of form
work & reinforcement for RCC work
(i) Flat slab p/4 3.60 3.60 0.10 1.02
Total (i) 1.02
Deduction of Man hole cover 2 xp/4 0.500 0.500 0.10 0.04
Total (ii) 0.04
Net Qty. (i -ii) 0.98
ABSTRACT OF COST
NAME OF WORK:- PROV.LWSS TO PC HABITATION OF KOHLA KALOOR & CHOA
CHAKRALA IN TEHSIL NADAUN DISTT. HAMIRPUR (HP)
(SUB HEAD:- C/O RCC STORAGE TANK OF 12200 LTS. WITH FLAT SLAB)
S.No. Desription of item Qty. Rate Unit Amount
1) Excavation in foundations,trenches etc., in 8.49 125.30 Cum 1064.00
earth work, lift upto 1.50 mts. Stacking the
excavated soil not more than 3 mts. Clear
from the edge of the excavation & then retur-
ning the stacked soil in 15 cms. Layers,when
required into plinths sides of foundation etc.,
consolidating each deposited layers by ramm-
ing & watering & then disposing of all surplus
excavated earth as dierected within all leads
& lifts as per entire satisfaction of Engineer in
charge.
2) Providing & laying cement concrete 1:3:6 (1 1.02 2373.00 Cum 2415.00
cement : 3 sand : 6 graded stone aggregate
40 mm nominal size) excluding the cost of
centring & shuttering in Foundation & plinth.
3) Providing & laying cement concrete1:1.5:3 (1
cement :1.5 sand : 3 graded stone aggregate
20 mm nominal size) & curing complete
excluding the cost of form work & reinforcem-
ent for reinforced concrete work in :-
(i) Foundation,footing,bases of columns and 2.04 2923.30 Cum 5951.00
the like & mass concrete.
(ii) Wall (any thickness but not less than 0.10 2.82 2975.90 Cum 8393.00
mts.Thickness)attached pillasters,buttresses
plinth,& string courses etc.from top of found.
level upto floor two level
4) Prov.form work with steel plates 3.15 mm thi-
ck welded with angle iron in frame 30x30x5
mm,so as to give a fair finish i/c centring
shuttering,strutting & propping etc. with woo-
den battens & ballies,ht. of propping & centri-
ng below supporting floor to ceiling not excee-
ding 4.00 mts. & removal of the same for in
situ-reinforced concrete & plain concrete
work :-
(i) Vertical surfaces such as wall (any thick.) 37.60 128.80 Sqm. 4844.00
partitions & the like i/c attached pillasters,
buttresses,plinth & string courses & the like.
(ii) Flat surfaces such as soffits of suspended 6.68 218.80 Sqm. 1461.00
floor,roofs, landing & the like.
5) Prov. In RCC work smooth finishing of the 37.60 41.70 Sqm. 1568.00
exposed surface with cement mortor 1:3 (1
cement : 3 sand )
6) Providing & laying cement concrete1:2:4 (1
cement :2 sand : 4 graded stone aggregate
20 mm nominal size) & curing complete
excluding the cost of form work & reinforcem-
ent for RC work in :-
(i) Suspended floor,roofs,landing & shelves 0.98 2750.10 Cum 2691.00
& their support balconies,beams,girders,bre-
ssumers & cantilever upto floor level.
7) Providing Tor steel reinforcement for RCC 477.77 37.20 Kg 17773.00
work i/c bending,binding & placing complete
upto floor two level.
8) Steel work welded in built up sections,trusses
& framed work,i/c cutting,hoisting & fixing
in position & applying a priming coat of red
paint :- In grating, framed ,guards,bars, 15.68 54.90 Kg 861.00
ladders, railing, brackets & similar works.
9) Providing & laying in trenches GMS/MS Tubes
(L/M class) tube fitting (Earth work in trenches
to be measured & paid for separatly)
i) 50 mm 6.00 134.90 Rmt. 809.00
ii) 50 mm 15.00 134.90 Rmt. 2024.00
10) Providing & fixing CI Sluice valve (with hand
wheel) as per IS : 780-1984 class-I upto 300
mm dia.(i/c brass spindle & as per 2906-1984
class-II for dia.> 300 mm) complete with bolts
nuts,rubber insertion etc.,(the tail piece if req-
uired shall be measured & paid for separatly)
i) 50 mm 1.00 4568.00 Each 4568.00
ii) 50 mm 3.00 4568.00 Each 13704.00
11) Constructing chamber for sluice valve, with CI
surface box 100 mm top dia.,160 mm bottom
dia. & 180 mm deep(inside) with chained lid
RCC top 1:2:4 mix (1 cement :2 sand :4 grad-
ed stone aggregate 20 mm nominal size) 100
mm thick foundation concrete 1:5:10 mix (1
cement : 5 sand : 10 graded stone aggregate
40 mm nominal size) & inside plastering with
cement mortor 1 :3 (1 cement : 3 sand) finish-
ed with a floating coat of neat cement i/c
curing complete.
600 x 600 x 750 mm inside syze
With 150 mm thick walls of RCC 1:2 :4 (1 ce- 2.00 5105.60 Each 10211.00
ment :2 sand :4 graded stone aggregate 20
mm nominal size) complete with form work
& reinforcement with 6 mm bars at not excee-
ding 150 mm centres both ways.
12) Prov. & fixing CI Man hole cover with frame 2.00 3367.00 Each 6734.00
having frames size of 500 mm internal dia.
(Medium duty). The weight of cover & frame
should not be less than 116 kg
Total 85071.00
ABSTRACT OF COST
NAME OF WORK:-
(SUB HEAD:-C/O SEDIMENTATION TANK OF 0 Lts.)
S.No. Desription of item Qty. Rate Unit Amount
1) Excavation in foundations,trenches etc., in 25.07 90.00 Cum 2257.00
earth work, lift upto 1.50 mts. Stacking the
excavated soil not more than 3 mts. Clear
from the edge of the excavation & then retur-
ning the stacked soil in 15 cms. Layers,when
required into plinths sides of foundation etc.,
consolidating each deposited layers by ramm-
ing & watering & then disposing of all surplus
excavated earth as dierected within all leads
& lifts as per entire satisfaction of Engineer in
charge.
2) Providing & laying cement concrete 1:3:6 (1 1.89 1650.00 Cum 3126.00
cement : 3 sand : 6 graded stone aggregate
40 mm nominal size) excluding the cost of
centring & shuttering in Foundation & plinth.
3) Providing & laying cement concrete1:1.5:3 (1
cement :1.5 sand : 3 graded stone aggregate
20 mm nominal size) & curing complete
excluding the cost of form work & reinforcem-
ent for reinforced concrete work in :-
(i) Foundation,footing,bases of columns and 3.79 2450.00 Cum 9282.00
the like & mass concrete.
(ii) Wall (any thickness but not less than 0.10 12.81 2600.00 Cum 33313.00
mts.Thickness)attached pillasters,buttresses
plinth,& string courses etc.from top of found.
level upto floor two level
4) Prov.form work with steel plates 3.15 mm thi-
ck welded with angle iron in frame 30x30x5
mm,so as to give a fair finish i/c centring
shuttering,strutting & propping etc. with woo-
den battens & ballies,ht. of propping & centri-
ng below supporting floor to ceiling not excee-
ding 4.00 mts. & removal of the same for in
situ-reinforced concrete & plain concrete
work :-
(i) Vertical surfaces such as wall (any thick.) 162.89 125.00 Sqm. 20361.00
partitions & the like i/c attached pillasters,
buttresses,plinth & string courses & the like.
(ii) Flat surfaces such as soffits of suspended 2.56 215.00 Sqm. 550.00
floor,roofs, landing & the like.
5) Prov. In RCC work smooth finishing of the 165.45 45.00 Sqm. 7445.00
exposed surface with cement mortor 1:3 (1
cement : 3 sand )
6) Providing Tor steel reinforcement for RCC 1418.35 4.00 Kg 5673.00
work i/c bending,binding & placing complete
upto floor two level.
7) Steel work welded in built up sections,trusses
& framed work,i/c cutting,hoisting & fixing
in position & applying a priming coat of red
paint :- In grating, framed ,guards,bars, 26.67 3500.00 Qtl. 93340.00
ladders, railing, brackets & similar works.
DETAIL OF MEASUREMENT
NAME OF WORK:-
(SUB HEAD:-C/O FILTER BED OF 44.55 mm 2 ) Lts.)
S.No. Decription of item Nos. Dimension Qty.
S.No. Decription of item Nos. Qty.
Length Breadth Ht/Depth
1) Excavation in foundation & trenches
etc. in earth work in all kinds of soil
within all leads & lifts as per entire
satisfaction of Engineer in charge.
Tank 1.00 9.50 6.40 1.20 72.96
Chamber 3.00 1.30 1.20 1.20 5.62
Scour pipe 3.00 6.00 0.65 0.60 7.02
Total 85.60
2) P/L cement concrete1:3:6 (1Cement
:3Sand:6 graded stone aggregate 40
mm nominal size) & curing complete
Tank 1.00 9.50 6.40 0.10 6.08
Chamber 3.00 1.30 1.20 1.20 5.62
Total 11.70
3) P/L cement concrete1:1.5:3 (1Cement
:1.5 Sand:3graded stone aggregate 20
mm nominal size) & curing complete
excluding the cost of form work and
reinforcement for RCC work :-
(i) Base floor Tank 1.00 9.50 6.40 0.20 12.16
Chamber 3.00 1.30 1.20 0.20 0.94
Total 13.10
(ii)Vertical surface Long walls 2.00 9.50 0.25 2.85 13.54
Short walls 2.00 5.50 0.25 2.85 7.84
Centre walls 2.00 5.50 0.25 2.85 7.84
Chamber
Front walls 3.00 1.20 0.15 3.15 1.70
Side short walls 6.00 1.15 0.15 3.15 3.26
Baffle wall 3.00 0.90 0.15 2.15 0.87
Total 35.04
4) Prov.form work with steel shuttering
so as to give an fair finish complete
in all respect.
(a) Vertical Surface
(i)Wall Inner side
Side of long wall 6.00 5.50 2.85 94.05
Sides of short wall 6.00 2.70 2.85 46.17
Side baffle walls 4.00 5.50 2.85 62.70
Chamber
Side front walls 3.00 0.90 3.15 8.50
Side short walls 6.00 1.00 3.15 18.90
Baffle wall 3.00 0.90 2.15 5.81
Outer side
Side of long wall 2.00 9.50 2.85 54.15
Sides of short wall 2.00 6.40 2.85 36.48
Chamber
Side front walls 3.00 1.20 3.15 11.34
Side short walls 6.00 1.15 3.15 21.74
(b) Suspended floors,roofs,landing and Total 359.84
soffits of beams etc.
Slab over chamber 3.00 1.00 0.90 2.70
Deduction of MH cover (M.Duty) 3.00 P/4X( 0.50)2 0.59
Net Qty. 2.11
5) Prov.smooth finishing in cement
mortor 1:3 (1cement : 3 sand)
Qty.same as per item No.4(a) 359.84
Qty.same as per item No.4(b) 2.11
Total 361.95
6) P/L cement concrete1:2:4 (1Cement
:2 Sand :4 graded stone aggregate 20
mm nominal size) & curing complete
excluding the cost of form work and
reinforcement for RCC work :-
Suspended floor,roofs,landing,balconi-
es,beams etc.
Slab over chamber 3.00 1.20 1.30 0.10 0.47
Deduction of MH cover (M.Duty) 3.00 P/4X( 0.50)2 0.10 0.06
Net Qty. 0.41
7) Prov.T.Steel for RCC work complete
in all respect.
Qty.as per item No.3(i) 13.10 Cum @ 70.00 Kg/Cum 916.72
Qty.as per item No.3(ii) 35.04 Cum @ 90.00 Kg/Cum 3154.01
Qty.as per item No.6 0.41 Cum @ 90.00 Kg/Cum 36.82
8) Steel work welded in built up sections, Total 4107.54
trusses and framed work i/c cutting,
hoisting,fixing in position compete
In grating,framed guards & ladders
etc.
L 40 x 40 x 5 mm for main V.Member 2.00 3.18 6.35 Rmt
6.35 Rmt. @ 3.00 Kg/Rmt 19.05
L 25 x 25 x4 mm for Horiz.Member 7.00 0.50 3.50 Rmt
3.50 Rmt. @ 1.40 Kg/Rmt 4.90
Total 23.95
9) Prov. & laying GMS/MS pipe for scour,
inlet,outlet & overflow pipe etc.:-
Scour pipe 100 mm 1.00 6.00 6.00
Inlet,outlet pipe & overflow pipe. Total 6.00
80 mm 3.00 5.00 15.00
Total 15.00
10) Prov. & fixing C.I. Sluice valve (Class
PN 1.00) of Leader/Kartar make as
per IS : 780-1984 & IS:2906-1984
complete in all respect.
Scour Pipe 100 mm 1.00 1.00
Inlet,outlet pipe & overflow pipe. Total 1.00
80 mm 3.00 3.00
Total 3.00
11) Constructing chamber 600x600x750
mm size for sluice valve,with CI sur-
face box 100 mm top dia.,160 mm
bottom dia.,& 180 mm deep with
chained lid & RCC top slab in 150
mm thick. RCC walls in c.conc.1:2:4
6.00 6.00
Total 6.00
12) Prov. & fixing CI Man hole cover with
frame having frames size of 500 mm
internal dia. (Medium duty) The weight
of cover & frame should not be less
than 116 kg 6.00 6.00
13) P/L cement concrete1:1.5:3 (1Cement Total 6.00
:1.5 Sand:3graded stone aggregate 20
mm nominal size) & curing complete
excluding the cost of form work :-
(a) Foundation & plinth. 120 2.40 0.075 0.10 2.16
Total 2.16
14) Precast concrete block masonry in
partitions walls 10 cm. thick with solid
blocks of approved size i/c quion block
closer etc. made of cement concrete
1:3:6( 1cement : 3 sand : 6 graded stone
aggregate 40 mm nominal & down gau-
ged) in CM 1:3 (1 cement : 3 Sand)
Slab over lateral drains 3.00 5.50 2.70 44.55
Total 44.55
15) Prov. & placing in horizontal layers of
filtering media duly graded, screened,
washed& cleaned as specified by the
Engineer-in-Charge:-
a) Top layer : Fine sand ( Eff.size 0.20 6.00 5.50 2.70 0.75 66.83
mm to 0.40 mm & uniformity coefficient
2.00 to 3.00)
b) Second layer :Coarse sand 3mm to 6.00 5.50 2.70 0.30 26.73
6 mm
c) Third layer : Bazri 20 mm to 25 mm 6.00 5.50 2.70 0.10 8.91
d) Fourth layer : Bazri 6 mm to 20 mm 6.00 5.50 2.70 0.10 8.91
e) Bottom layer:Broken stone 50 mm 6.00 5.50 2.70 0.15 13.37
to 75 mm
ABSTRACT OF COST
NAME OF WORK:-
(SUB HEAD:-C/O FILTER BED OF mm 2 ) Lts.)
S.No. Desription of item Qty. Rate Unit Amount
1) Excavation in foundations,trenches etc., in 85.60 90.00 Cum 7704.00
earth work, lift upto 1.50 mts. Stacking the
excavated soil not more than 3 mts. Clear
from the edge of the excavation & then retur-
ning the stacked soil in 15 cms. Layers,when
required into plinths sides of foundation etc.,
consolidating each deposited layers by ramm-
ing & watering & then disposing of all surplus
excavated earth as dierected within all leads
& lifts as per entire satisfaction of Engineer in
charge.
2) Providing & laying cement concrete 1:3:6 (1 11.70 1650.00 Cum 19298.00
cement : 3 sand : 6 graded stone aggregate
40 mm nominal size) excluding the cost of
centring & shuttering in Foundation & plinth.
3) Providing & laying cement concrete1:1.5:3 (1
cement :1.5 sand : 3 graded stone aggregate
20 mm nominal size) & curing complete
excluding the cost of form work & reinforcem-
ent for reinforced concrete work in :-
(i) Foundation,footing,bases of columns and 0.94 2450.00 Cum 2293.00
the like & mass concrete.
(ii) Wall (any thickness but not less than 0.10 35.04 2600.00 Cum 91116.00
mts.Thickness)attached pillasters,buttresses
plinth,& string courses etc.from top of found.
level upto floor two level
4) Prov.form work with steel plates 3.15 mm thi-
ck welded with angle iron in frame 30x30x5
mm,so as to give a fair finish i/c centring
shuttering,strutting & propping etc. with woo-
den battens & ballies,ht. of propping & centri-
ng below supporting floor to ceiling not excee-
ding 4.00 mts. & removal of the same for in
situ-reinforced concrete & plain concrete work
(i) Vertical surfaces such as wall (any thick.) 359.84 125.00 Sqm. 44979.00
partitions & the like i/c attached pillasters,
buttresses,plinth & string courses & the like.
(ii) Flat surfaces such as soffits of suspended 2.11 215.00 Sqm. 454.00
floor,roofs, landing & the like.
5) Prov. In RCC work smooth finishing of the 361.95 45.00 Sqm. 16288.00
exposed surface with cement mortor 1:3 (1
cement : 3 sand )
6) P/L cement concrete1:2:4 (1Cement
:2 Sand :4 graded stone aggregate 20
mm nominal size) & curing complete
excluding the cost of form work and
reinforcement for RCC work :-
Suspended floor,roofs,landing,balconi-
es,beams etc.
7) Providing Tor steel reinforcement for RCC 4107.54 4.00 Kg 16430.00
work i/c bending,binding & placing complete
upto floor two level.
12) Prov. & fixing CI Man hole cover with frame 6.00 3200.00 Each 19200.00
having frames size of 500 mm internal dia.
(Medium duty). The weight of cover & frame
should not be less than 116 kg
a) Top layer : Fine sand ( Eff.size 0.20 66.83 220.00 Cum 14702.00
mm to 0.40 mm & uniformity coefficient
2.00 to 3.00)
DETAIL OF MEASUREMENT
NAME OF WORK:-PROV.LWSS TO PC HABITATION OF KOHLA KALOOR
& CHOA CHAKRALA IN TEHSIL NADAUN DISTT. HAMIRPUR (HP)
(SUB HEAD:- C/O RCC RAW WATER TANK 79100 Lts.)
S. Decription of item Nos. Dimension Qty.
No. L B H/D
1) Excavation in foundation & trenches
etc. in earth work in all kinds of soil
within all leads & lifts as per entire
satisfaction of Engineer in charge.
Tank p/4 6.49 6.49 1.95 64.51
Scour pipe 1.00 6.00 0.65 0.98 3.80
Total 68.31
2) P/L cement concrete1:3:6 (1Cement
:3Sand:6 graded stone aggregate 40
mm nominal size) & curing complete
Tank p/4 6.49 6.49 0.10 3.31
Total 3.31
3) P/L cement concrete1:1.5:3 (1Cement
:1.5 Sand:3graded stone aggregate 20
mm nominal size) & curing complete
excluding the cost of form work and
reinforcement for RCC work :-
(i) Base floor p/4 6.49 6.49 0.20 6.62
Total 6.62
(ii) Vertical wall p 5.94 0.15 3.15 8.82
Total 8.82
4) Prov.form work with steel shuttering
so as to give an fair finish complete
in all respect.
(i) Vertical wall Inside p 5.79 3.15 57.30
Outside p 6.09 3.15 60.27
Total 117.56
5) Prov.smooth finishing in cement
mortor 1:3 (1cement : 3 sand)
Inside p 5.79 3.15 57.30
Outside p 6.09 3.15 60.27
Total 117.56
6) Prov.T.Steel for RCC work complete
in all respect.
Qty.as per item No.3(i) 6.62 Cum @ 70.00 Kg/Cum 463.14
Qty.as per item No.3(ii) 8.82 Cum @ 90.00 Kg/Cum 793.56
Total 1256.70
7) Steel work welded in built up sections,
trusses and framed work i/c cutting,
hoisting,fixing in position compete
In grating,framed guards & ladders etc.
L 40 x 40 x 5 mm for main V.Member 2.00 4.22 8.44 Rmt
8.44 Rmt. @ 3.00 Kg/Rmt 25.32
L 25 x 25 x4 mm for Horiz.Member 10.00 0.50 5.00 Rmt
5.00 Rmt. @ 1.40 Kg/Rmt 7.00
Total 32.32
8) Prov. & laying GMS/MS pipe for scour,
inlet,outlet & overflow pipe etc.:-
Scour pipe 100 mm 1.00 6.00 6.00
Inlet,outlet pipe & overflow pipe. Total 6.00
80 mm 3.00 5.00 15.00
Total 15.00
9) Prov. & fixing C.I. Sluice valve (Class
PN 1.00) of Leader/Kartar make as
per IS : 780-1984 & IS:2906-1984
complete in all respect.
Scour pipe 100 mm 1.00 1.00
Inlet,outlet pipe & overflow pipe. Total 1.00
80 mm 3.00 3.00
Total 3.00
10) Constructing chamber 600x600x750
mm size for sluice valve,with CI sur-
face box 100 mm top dia.,160 mm
bottom dia.,& 180 mm deep with
chained lid & RCC top slab in 150
mm thick. RCC walls in c.conc.1:2:4
2.00 2.00
ABSTRACT OF COST
NAME OF WORK:-PROV.LWSS TO PC HABITATION OF KOHLA KALOOR
& CHOA CHAKRALA IN TEHSIL NADAUN DISTT. HAMIRPUR (HP)
(SUB HEAD:- C/O RCC RAW WATER TANK 79100 Lts.)
S.No. Desription of item Qty. Rate Unit Amount
1) Excavation in foundations,trenches etc., in 68.31 125.30 Cum 8559.00
earth work, lift upto 1.50 mts. Stacking the
excavated soil not more than 3 mts. Clear
from the edge of the excavation & then retur-
ning the stacked soil in 15 cms. Layers,when
required into plinths sides of foundation etc.,
consolidating each deposited layers by ramm-
ing & watering & then disposing of all surplus
excavated earth as dierected within all leads
& lifts as per entire satisfaction of Engineer in
charge.
2) Providing & laying cement concrete 1:3:6 (1 3.31 2373.00 Cum 7850.00
cement : 3 sand : 6 graded stone aggregate
40 mm nominal size) excluding the cost of
centring & shuttering in Foundation & plinth.
3) Providing & laying cement concrete1:1.5:3 (1
cement :1.5 sand : 3 graded stone aggregate
20 mm nominal size) & curing complete
excluding the cost of form work & reinforcem-
ent for reinforced concrete work in :-
(i) Foundation,footing,bases of columns and 6.62 2923.30 Cum 19341.00
the like & mass concrete.
(ii) Wall (any thickness but not less than 0.10 8.82 2975.90 Cum 26240.00
mts.Thickness)attached pillasters,buttresses
plinth,& string courses etc.from top of found.
level upto floor two level
4) Prov.form work with steel plates 3.15 mm thi-
ck welded with angle iron in frame 30x30x5
mm,so as to give a fair finish i/c centring
shuttering,strutting & propping etc. with woo-
den battens & ballies,ht. of propping & centri-
ng below supporting floor to ceiling not excee-
ding 4.00 mts. & removal of the same for in
situ-reinforced concrete & plain concrete
work :-
Vertical surfaces such as wall (any thick.) 117.56 128.80 Sqm. 15142.00
partitions & the like i/c attached pillasters,
buttresses,plinth & string courses & the like.
5) Prov. In RCC work smooth finishing of the
exposed surface with cement mortor 1:3 (1
cement : 3 sand ) 117.56 41.70 Sqm. 4902.00
6) Providing Tor steel reinforcement for RCC 1256.70 37.20 Kg 46749.00
work i/c bending,binding & placing complete
upto floor two level.
7) Steel work welded in built up sections,trusses 32.32 54.90 Kg 1774.00
& framed work,i/c cutting,hoisting & fixing
in position & applying a priming coat of red
paint :- In grating, framed ,guards,bars,
ladders, railing, brackets & similar works.
8) Providing & laying in trenches GMS/MS Tubes
(L/M class) tube fitting (Earth work in trenches
to be measured & paid for separatly)
i) 100 mm 6.00 683.10 Rmt. 4099.00
ii) 80 mm 15.00 580.30 Rmt. 8705.00
9) Providing & fixing CI Sluice valve (with hand
wheel) as per IS : 780-1984 class-I upto 300
mm dia.(i/c brass spindle & as per 2906-1984
class-II for dia.> 300 mm) complete with bolts
nuts,rubber insertion etc.,(the tail piece if req-
uired shall be measured & paid for separatly)
i) 100 mm 1.00 11676.60 Each 11677.00
ii) 80 mm 3.00 10010.50 Each 30032.00
10) Constructing chamber for sluice valve, with CI
surface box 100 mm top dia.,160 mm bottom
dia. & 180 mm deep(inside) with chained lid
RCC top 1:2:4 mix (1 cement :2 sand :4 grad-
ed stone aggregate 20 mm nominal size) 100
mm thick foundation concrete 1:5:10 mix (1
cement : 5 sand : 10 graded stone aggregate
40 mm nominal size) & inside plastering with
cement mortor 1 :3 (1 cement : 3 sand) finish-
ed with a floating coat of neat cement i/c
curing complete.
600 x 600 x 750 mm inside syze
With 150 mm thick walls of RCC 1:2 :4 (1 ce- 2.00 5105.60 Each 10211.00
ment :2 sand :4 graded stone aggregate 20
mm nominal size) complete with form work
& reinforcement with 6 mm bars at not excee-
ding 150 mm centres both ways.
TOTAL 195281.00
UNIT
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Rmt
Rmt
Rmt
Rmt.
No.
No.
No's.
No's.
No's.
No's.
No's.
No's.
Amount
22860.00
21739.00
53560.00
45279.00
26130.00
98633.00
8460.00
2657.00
16256.00
115479.00
1774.00
4099.00
8705.00
11677.00
30032.00
10211.00
6734.00
484285.00
H FLAT SLAB)
H FLAT SLAB)
UNIT
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Cum
Cum
Cum
Cum
Cum
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Rmt
Rmt
Rmt
Rmt.
No.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
H FLAT SLAB)
Amount
1064.00
2415.00
5951.00
8393.00
4844.00
1461.00
1568.00
2691.00
17773.00
861.00
809.00
2024.00
4568.00
13704.00
10211.00
6734.00
85071.00
Lts.)
UNIT
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Kg
Kg
Kg
Kg
Kg
Kg
Rmt
Rmt
Rmt
Rmt.
No.
No.
Nos.
Nos.
Nos.
Nos.
Amount
2257.00
3126.00
9282.00
33313.00
20361.00
550.00
7445.00
5673.00
93340.00
3900.00
6750.00
8500.00
16500.00
6000.00
6400.00
223397.00
UNIT
UNIT
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Cum
Cum
Cum
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Rmt
Rmt
Rmt
Rmt.
No.
No.
Nos.
Nos.
Nos.
Nos.
No.
No.
Cum
Cum
Sqm
Sqm
Cum
Cum
Cum
Cum
Cum
Amount
7704.00
19298.00
2293.00
91116.00
44979.00
454.00
16288.00
16430.00
83831.00
3900.00
6750.00
8500.00
16500.00
18000.00
19200.00
6696.00
9801.00
14702.00
5881.00
1960.00
1960.00
2940.00
399183.00
UNIT
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Sqm.
Kg
Kg
Kg
Kg
Kg
Kg
Rmt
Rmt
Rmt
Rmt.
No.
No.
Nos.
Nos.
No.
Amount
8559.00
7850.00
19341.00
26240.00
15142.00
4902.00
46749.00
1774.00
4099.00
8705.00
11677.00
30032.00
10211.00
195281.00
NAME OF WORK:- AUG.LWSS TO BHOTA TOWN IN TEHSIL & DISTT. HAMIRPUR (HP)
(SUB HEAD:- STRUCTURAL DESIGN OF FILTER BED 51.00 M 2
Data:-
1) Capacity of Structure:-
2) Depth of tank:- 2.70 Mts.i/c free board.
3) Size of tank (Length x Breadth) Length = 10.20 Mts. Breadth = 5.00 Mts.
4) Provde Free Board 0.2 Mts.
5) Design contant for M-20 Gr.Concrete.
i) sst = 150 7N/mm 2 scbc = 7N/mm 2 K = 0.378 j = 0.874
R = 1.160
ii) sst = 190 7N/mm 2 scbc = 7N/mm 2 K = 0.329 j = 0.890
R = 1.025
NOTE:- The outside soil is assumed to be 1.50 Mts. below the top of wall
(i.e.Hsoil= 1.50 )
Let the wt. of soil = 17.00 KN/m 3 or 17000.00 N/mm 3
Wt.of water = 10.00 KN/m or 3
10000.00 N/mm 3
Angle of Repose f = 30 Degrees
Then Ka = (1-sinf)/(1+siof) = 1/3
Since L/B>2,hence the walls will be designed as cantilever & short wall upto 1Mts.
(h>H/4) be designed as cantilevers & top portion as slab supported by long walls.
(A) DESIGN OF LONG WALLS:-
a) Tank full with water i.e. no earth pressure:-
Bending Moment = w x H 3/6
Considering the provision of splasys at junctions of walls & base slab,the
cantilever effect of the long walls is considered to be effective from the top of splays.
Then effective height (Heff) = (H -.15)= 2.50 Mts.
B.M. (Max.) M = (w x (Heff) 3)/6 26041.67 N-m
Say 26042 N-m
Effective depth = ((M/R x b)) 0.5 150.00 mm
Total depth using tor steel of 16 mm dia. 183 mm
Hence adopt overall depth = 200 mm
Then effective depth (d) by using T/Steel bars of 16 167 mm
Ast required = M x 10 3/(j xd x sst) 1189.47 mm 2
Say 1189.00 mm 2
Spacing of Tor steel used 16 mm dia = 150.00 mm
Say 130 mm
Provide Tor steel of dia. 16 mm dia. bars @ 130 mm
c/c vertically on inner face of long walls.
Curtailment of reinforcement:-
Area of steel required at depth of "h"
Ast h/Ast= h 3/H 3 =
h=((Ast h/Ast) x H)) 1/3
H = 2.70 Mts.
"h" be the depth from top where 1/2 the steel can be curtialed.
"h" = (1/2) 1/3 xH 2.14 Mts.
Ht. from base = 0.56 Mts. However as per code requirements, the
bars are to continue further for a distance of 12 times of bars 16
mm dia = 192 mm or d(= 167 mm) whichever is more,
beyond this point. Hence curtail half the bars at 0.75 mts. or
1.00 mts.from base.
Similarly depth where only 1/4th reinforcement is required is
Mts. from base.
"h" = H (1/4)^0.3334 = 1.7 Mts.
Height from base = 1.00 Mts.However as per requiremen,the bars are to
continue further for a distance of 12 Times of dia. = 192 mm or d =
167 mm), whichever is more,beyond this point.Hence curtail 3/4th of bars at a
distance of 1.192 mts. Say 1.50 mts.from base.