EPCI AKATARA GAS PROCESSING FACILITY & SALES

GAS PIPELINE PROJECT

PRECOMMISSIONING KP 0+000 SD 17+000


WATER FILLING CALCUATION

A DATA
1 OD Pipe OD = 8 inch = 203.2 mm = 0.203 m
2 thickness t = 0.34 inch = 8.636 mm = 0.009 m
3 ID Pipe ID=OD-2t = 7.32 inch = 185.928 mm = 0.186 m
4 Length of Section
KP awal 0+000 AGPF ( Parit lapis)
17+000 (Simpang semau)
Panjang berdasarkan Pipebook dari KP 0+000 sd KP 17+000 = 17,000.00 m
5 Feeder/Filling Pump
Capacity Q = 2500 = 150 m3/Hour
Efficiency eff = 75 %
B CALCULATION
1 Volume of Water in Pipeline at 0 psig
V = 0.25 x PI() x ID^2 x L `` = 461.6 m3

2 Duration of Filling Water


V 461.560 m3 = 4.10 Hours
t= =
Q x eff 150 x 75% m3/Hours

3 Velocity of Pig (Pig Travel speed)


v= L/t = 17000 m 4,146.34 m/hr = 1.152 m/s
4.1 hr
C SUMMARY
Berikut adalah durasi Waterfilling berdasarkan kapasitas Pompa
Filling Pump Capacity Pig Travel
No Duration of Filling Water
(L/mnt) (m/s)
1 1,000 10.26 Hours = 0 Days 10 Hours 16 Minutes 0.46
2 1,500 6.84 Hours = 0 Days 6 Hours 50 Minutes 0.96
3 2,000 5.13 Hours = 0 Days 5 Hours 8 Minutes 0.921
4 2,500 4.10 Hours = 0 Day 4 Hours 6 Minutes 1.152