CADANGAN TAMBAHAN DAN

UBAHSUAI BAGI SEBUAH PUSAT


JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS LOT
3140, BANDAR TAIPING DAERAH
LARUT DAN MATANG, PERAK
DARUL RIDZUAN.
Document No:
GLSS-JP-MS-CS16
Method Statement for Rev : 00
Handrail Date: 14/07/2019
Page 1 of 8

METHOD STATEMENT FOR

HANDRAIL

Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS LOT
3140, BANDAR TAIPING DAERAH
LARUT DAN MATANG, PERAK
DARUL RIDZUAN.
Document No:
GLSS-JP-MS-CS16
Method Statement for Rev : 00
Handrail Date: 14/07/2019
Page 2 of 8

Revision Record

1. This cover page is a record of all revisions of the document identified above by number and
title. All previous cover pages are hereby superseded and are to be destroyed.

2. The contractor has the full right to modify, amend or change Method Statement and
supporting documents as required or as deemed necessary. All such documents will be
submitted to the “CONSULTANT” for approval.

Prepared Reviewed Approval for Description & page Number of


Rev Date
By by Issuance by Revision
00 14/07/19 Afiq Faisal GLS Setia

Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS LOT
3140, BANDAR TAIPING DAERAH
LARUT DAN MATANG, PERAK
DARUL RIDZUAN.
Document No:
GLSS-JP-MS-CS16
Method Statement for Rev : 00
Handrail Date: 14/07/2019
Page 3 of 8

CONTENTS

1.0 SCOPE

2.0 PURPOSE

3.0 REFERENCES

4.0 DEFINITIONS AND ABBREVIATIONS

5.0 RESPONSIBILITIES

6.0 MATERIALS

7.0 EQUIPMENT & TOOLS

8.0 SAFETY & HEALTH

9.0 PROCEDURE

10.0 ATTACHMENTS

Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS LOT
3140, BANDAR TAIPING DAERAH
LARUT DAN MATANG, PERAK
DARUL RIDZUAN.
Document No:
GLSS-JP-MS-CS16
Method Statement for Rev : 00
Handrail Date: 14/07/2019
Page 4 of 8

1.0 SCOPE

This method statement covers the detailed procedure to be followed for Installation
of Handrail.
2.0 PURPOSE

The purpose of this document is to lay down the systematic procedure for
Installation of Handrails.
3.0 REFERENCES

 Project Specifications for Metal Fabrication

 Bill of Quantity

Material Submittal

Supplier Details

4.0 DEFINITIONS & ABBREVIATIONS
Consultant/Client:
Contractor:
PM: Project Manager
CM: Construction Manager
PE: Project Engineer
QA QC: Quality Assurance and quality Control
PPE: Personal Protective Equipment
HSE: Health, Safety and Environment

5.0 RESPONSIBILITIES

 Project Manager is responsible for overall project execution, quality and safety. Adopt a leading role with respect to Contractor’s quality
and safety procedures. The PM is responsible for the overall implementation of this method statement. The Project Manager shall ensure
that the key personnel are well aware of the specifications and method statement.

 CM / Project Engineer shall arrange all materials, equipment, safety related items & manpower & direct the Site Engineers & Foremen to
resort appropriate action for the smooth execution of the works.

 Safety Engineer shall be responsible for safe working environment & conditions. Coordinate with Site Engineer to identify potential
hazards before works and advise methods of safe working from new developments.

 Surveyor shall be responsible for setting out for levels, layout, and lines & establish top levels. Ensuring setting out books are properly
maintained and filed when completed. To coordinate with the CONSULTANT surveyor in determining coordinates, levels, and limits.

 QA/QC Engineer shall be responsible for ensuring that execution of works are complying with approved method statement;
specifications, approved shop drawings and ensure ITR are submitted based on ITP requirements.

 Site Engineer shall ensure that all works are carried out according to approved shop drawings. He shall direct the surveyor for the setting
out lines & levels in concurrence from the Construction Manager/Senior Civil Engineer.

 MEP Coordinator / Engineer shall be responsible for proper execution of MEP works involved before, during and after the works.

6.0 MATERIALS

 As per the approved material submittal

Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS LOT
3140, BANDAR TAIPING DAERAH
LARUT DAN MATANG, PERAK
DARUL RIDZUAN.
Document No:
GLSS-JP-MS-CS16
Method Statement for Rev : 00
Handrail Date: 14/07/2019
Page 5 of 8

7.0 EQUIPMENTS & TOOLS

Concrete Drill Machine



Rechargeable Tighter machine

Small cutting machine

Tool Box

Extension wire

Line Dory

Spirit level

Plastic Hammer

Metal Hammer

Screw Driver Flat

Screw Driver Star

Round and flat file

Chisel

Right Angle

Silicon gun

Rivet gun

Allen key

Plier

Vice grip

Measurement tape

Knife

Spanner

The capacity / size of the above tools and equipment shall be judged in accordance
with site conditions, requirements, and availability at the time of execution
Issue No.: 0
Revision No.: 0
CADANGAN TAMBAHAN DAN
UBAHSUAI BAGI SEBUAH PUSAT
JAGAAN AMBULATORI SWASTA
SETINGGI 4 TINGKAT DI ATAS LOT
3140, BANDAR TAIPING DAERAH
LARUT DAN MATANG, PERAK
DARUL RIDZUAN.
Document No:
GLSS-JP-MS-CS16
Method Statement for Rev : 00
Handrail Date: 14/07/2019
Page 6 of 8

8.0 SAFETY & HEALTH

 All the equipment, tools and tackles being used for the work should be in good working condition and maintained.

 All the personnel will be provided with toolbox talk on the procedures to execute the work safely.

 All employees shall attend Safety Induction and training Course to identify all Hazards associated with this work.

 The safety office of the site will be responsible for carrying risk assessment and record updated and can be inspected at site office.

 All workers / field staff shall be provided with PPE such as coverall, helmet, safety shoes, safety goggles, safety harness … etc.

9.0 PROCEDURE

9.1 General:
 Ensure that Material submittal and subcontractor / supplier are approved by the CONSULTANT.

 Ensure that shop drawings are complete and method of fixation, details of handrails units submitted is approved by the consultant

 Verify the sizes of the profiles in the shop drawings if they are the same as per the material submittals approved by the consultant.

 Ensure that before preparing the cutting list, site verification is done e.g. elevation of FFL, Structural concrete elevation to avoid waste of
materials.

 Installation should be done as per the manufacturer recommendations and as per approved mock up.

9.2 Installation:
 Handrail is installed prior to the floor finishing.

 Brackets are fixed to the vertical post by approved bolts and nuts.

 Placed the vertical member to the concrete in its position using the Anchor bolts/ and proper packing.

 Adjust the alignment and slope of the handrail as required.

 Embed the vertical frame permanently to the concrete and cast.

 Connect the loose parts/members to the next assembly section using approved fasteners/screws and sleeve, and repeat the procedure
up to the last portion of the handrail.

 Fit in the shoe cap to cover the posts and keep the final finishing.

 Ensure that there is a proper protective tape to avoid scratches and denting and discoloration by other trade.

 Cleaning and Handing over.


10.0 ATTACHMENTS

 ITP

 Checklist

 Risk Assessment