Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 11

CADANGAN TAMBAHAN DAN UBAHSUAI

BAGI SEBUAH PUSAT JAGAAN


AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 1of 13

METHOD STATEMENT FOR

PLASTERING WORKS
CADANGAN TAMBAHAN DAN UBAHSUAI
BAGI SEBUAH PUSAT JAGAAN
AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 2of 13

Revision Record

1. This cover page is a record of all revisions of the document identified above by number and title. All
previous cover pages are hereby superseded and are to be destroyed.

2. The contractor has the full right to modify, amend or change Method Statement and supporting
documents as required or as deemed necessary. All such documents will be submitted to the
“CONSULTANT” for approval.

Prepared Reviewed Approval for Description & page Number of


Rev Date
By by Issuance by Revision
00 14/07/2019 AFIQ FAISAL GLS SETIA

CONTENTS:

1.0 SCOPE
CADANGAN TAMBAHAN DAN UBAHSUAI
BAGI SEBUAH PUSAT JAGAAN
AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 3of 13

2.0 PURPOSE

3.0 REFERENCES

4.0 DEFINITIONS & ABBREVIATIONS

5.0 RESPONSIBILITIES

6.0 MATERIALS

7.0 EQUIPMENTS & TOOLS

8.0 SAFETY & HEALTH

9.0 PROCEDURE

10.0 ATTACHMENTS

1.0 SCOPE

This Method Statement describes the steps that will be followed for the plastering work of
building within the construction area.
This procedure shall be read in conjunction with contract specification where applicable.
All works shall be as per approved shop drawing.
2.0 PURPOSE
CADANGAN TAMBAHAN DAN UBAHSUAI
BAGI SEBUAH PUSAT JAGAAN
AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 4of 13

The purpose of this procedure is to define how plastering shall be carried out under
controlled condition.
3.0 REFERENCES
 Project specifications

 Contract drawings

 Approved shop drawings

Approved Material Submittals



Project Quality Plan

4.0 DEFINITIONS & ABBREVIATIONS
PM: Project Manager

CM: Construction Manager

PE: Project Engineer

QCE: Quality Control Engineer

QA QC: Quality Assurance and quality Control

SE: Site Engineer

PPE: Personal Protective Equipment

HSE: Health, Safety and Environment

ITL: Independent Third Party Lab

ITP: Inspecting and Test Plan

5.0 RESPONSIBILITIES
 Project Manager is responsible for overall project execution, quality and safety. Adopt a leading role with respect to Contractor’s quality and safety
procedures. The PM is responsible for the overall implementation of this method statement. The Project Manager shall ensure that the key personnel
are well aware of the specifications and method statement.

 CM / Project Engineer shall arrange all materials, equipment, safety related items & manpower & direct the Site Engineers & Foremen to resort
appropriate action for the smooth execution of the works.

 Safety Engineer shall be responsible for safe working environment & conditions. Coordinate with Site Engineer to identify potential hazards before
works and advise methods of safe working from new developments.

 Surveyor shall be responsible for setting out for levels, layout, and lines & establish top levels. Ensuring setting out books are properly maintained and
filed when completed. To coordinate with the CONSULTANT surveyor in determining coordinates, levels, and limits.

 QA/QC Engineer shall be responsible for ensuring that execution of works are complying with approved method statement; specifications, approved
shop drawings and ensure ITR are submitted based on ITP requirements.

 Site Engineer shall ensure that all works are carried out according to approved shop drawings. He shall direct the surveyor for the setting out lines &
levels in concurrence from the Construction Manager/Senior Civil Engineer.

 Coordinator / Engineer shall be responsible for proper execution of MEP works involved before, during and after the works.

 ITL shall do the required test to ensure the quality of works.

6.0 MATERIALS
CADANGAN TAMBAHAN DAN UBAHSUAI
BAGI SEBUAH PUSAT JAGAAN
AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 5of 13

Approved plastering materials and accessories.


7.0 EQUIPMENTS & TOOLS

Below is the equipment involved in Plaster works:


Surveying Equipment

Line dory

Plumb bob

Spirit level

Trowel

Mixture Plaster Machine

Wheel Barrow

Bucket

Wood float

Straight edge

Steel Brush

Aluminum Section (2~3 m length)

Mobile scaffolds

The capacity / size of the above equipment shall be judged in accordance with site
conditions, requirements, and availability at the time of execution.

8.0 SAFETY & HEALTH


 All employees shall be provided with complete personal Protection equipment PPE.

 All employees shall attend Safety Induction and training Course to identify all Hazards associated with this work.

 All workers shall be provided with proper tools and equipment to execute the work safely.

 MSDS (material safety data sheet) shall be displayed at work location as appropriate.

9.0 PROCEDURE

9.1 GENERAL

 Ensure that material, samples and method Statement have been submitted and
approved by the CONSULTANT.
CADANGAN TAMBAHAN DAN UBAHSUAI
BAGI SEBUAH PUSAT JAGAAN
AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 6of 13

 Ensure that plastering accessories are approved and available.

 Ensure proper working platform and lighting arrangement provided.

 Surfaces to receive plastering shall be dry brushed to remove all loose particles,
dust, laitance, efflorescence, etc. and any projecting fins on concrete surfaces shall
be hacked off.

 Where surfaces are out of line, they shall be brought to level by hacking or dubbing
out prior to commencement of finishing.

 All required openings for mechanical & electrical services, conduits pipes, plugs
shall be installed and tested prior to plastering.

 Curing arrangements shall be provided for three days.

9.2 WORKMANSHIP

System 1: Using MP3 Rush Coat & MP13 Cement Render/Plaster by M & P

9.2.1 Surface Preparation and Installation of Plaster Accessories

All surfaces to be plastered or rendered shall be sprayed with water, which shall be

allowed to dry out before rush coat is applied.

Masonry work applied with scratch coat prior to plastering.


Concrete surfaces where plaster to be applied shall be made rough.


All undercoats shall be scratched to form an adequate key for the next coat.

Level Guides shall be provided up to required thickness.


All junctions between different materials and also over the embedded conduits shall

be reinforced with expanded metal which shall be plugged nailed or stapled as
required at required interval.
CADANGAN TAMBAHAN DAN UBAHSUAI
BAGI SEBUAH PUSAT JAGAAN
AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 7of 13

All horizontal and vertical and vertical external and internal angles of plastered

walls shall be protected with galvanized metal corner beads and shall be securely
plugged, nailed or stapled as required at proper intervals.

Plastering accessories such as plaster stops shall be used where plastering terminates

and is not covered by other finish at wall, ceiling, door, window frame junctions and
to all wall openings and corners.

Plastering shall proceed only when the masonry block works are completed.

9.2.2 Mixing of Rush Coat and Application (MP3)

 Surface must be sound, clean dry and free from any materials which may impair
the adhesion of Rush coat.

 Pre-wet & saturate the surface with potable water before applying rush coat.

 Thoroughly mix MP3 ( rush coat) with potable water at the rate of approx. 10L
of water /50 Kg. bag using a plaster machine is adjusted to obtain the consistent
mix of wet mortar.

 Mixing and application shall be done by mechanical mixer as approved by the


material manufacturer.

 Mix each batch separately. Clean out mixer between the batches.

 Mix no more material than used within one hour.

 The wet mixed mortar is sprayed on the wall using the spray gun of the machine.

 Apply the Rush coat using spray gun on the prepared surface in One or two coats
to obtain 2~5mm thick rough texture.

 Cure the applied Rush Coat with potable water for minimum of 3 days.

9.2.3 Mixing of Final Coat and Application (MP13)

 Wet rush coat evenly just before application of finish coat.


CADANGAN TAMBAHAN DAN UBAHSUAI
BAGI SEBUAH PUSAT JAGAAN
AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 8of 13

 In application using spray machine water flow is adjusted to obtain the


consistent mix of wet mortar. The wet mixed mortar is sprayed on the walls
using the spray gun of the machine.

 In case of manual mixing thoroughly mix MP13 with potable water at the rate of
approx. 7 L of water/50 kg bag using an electrical paddle mixer attachment. The
wet mixed mortar is then applied on the walls using trowel. Any caked and set
mortar should not be applied.

 Apply the MP13 directly over the concrete masonry block walls in single coat at
internal areas (10-20mm) and in double coat at external areas (15-20mm).

 On the prepared internal/external concrete surfaces (cast-in-situ or precast)


MP13 is applied in single coat (10-20mm).

 The plaster shall be applied to the required thickness and adequate drying time
shall be allowed for each undercoat prior to the application of the following coat.

 Finish the render plaster to medium fine finish using plastic/wooden trowel.
Over toweling and smoothing of the render/plaster surface to be avoided in the
final finishing.

 Final coat should be made in a true plane using an Aluminum straight edge.

All wall faces finish shall be made plane and true to line in all directions and that all

angles are straight, true and plumb.

Extra care shall be taken for plastering to be made neatly good up to wood frames,

skirting and around pipes or fittings.

Cure the applied MP13 with potable water for minimum of three days.

During the application existing work will be protected against spillage, staining and

other damages.

On walls plaster work shall be terminated at 100 mm above false ceiling elevation.

Ceiling surface shall be plastered with 10-12 mm thick.


Plaster shall only be stopped at corner beads or plaster stops at an induced groove.

CADANGAN TAMBAHAN DAN UBAHSUAI
BAGI SEBUAH PUSAT JAGAAN
AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 9of 13

Where plaster abuts any metal item which is set in the plaster and is flush with the

finished plaster surface, provide raked ‘vee’ joint at junction or as directed by the
CONSULTANT.

Point up and finish surfaces around fixtures, outlet boxes, piping, fittings, tile and

other work flush with adjacent plaster.

Each coat of all plasterwork is to be maintained in a moist condition for at least



three days after the plaster.

Finished work will be protected during progress of plastering work.


Defective work shall be removed and replaced with new.


If plaster thickness more than 2 cm, than we have to do double coat application, first

coat is applied as spatter coat of 8~10mm. Cure the first coat for min. 2 days before
over coating.

9.2.4 Plaster Accessories

Ensure that metal lath is straight, secured to substrate joint and surface perimeter

accessories are in place.

300mm wide strip metal lath centered over junctions of dissimilar backing materials

and casing beads @ terminations of plaster finish shall be installed.

Corner beads shall be in One length up to 3000mm and no length shall be less than

1800mm and has to set in order to form true arises and neat miters, secure at ends
and not more that 300mm apart with galvanized staples, galvanized wire ties or
concrete nails, staggered install at all vertical & horizontal plaster exterior corners
and to provide
corner beads extension slips where is required.

 Horizontal beads shall be level, vertical beads, plumb, straight and true,
assuming proper plaster thickness.
CADANGAN TAMBAHAN DAN UBAHSUAI
BAGI SEBUAH PUSAT JAGAAN
AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 10of 13

 Plaster Stop shall be used where called for or as required to stop plaster surface
against a dissimilar to form a neat and definite joint.

 Corner mesh shall be provided on all internal corners prior to plaster.

 At all control joint locations install back to back square nosed casing beads.

 Mock-up shall be provided showing the executions’ systematic of the works in


order to obtain the final approval accordingly.

9.2.5 Cutting, Patching & Repairing

 Cut out & repair all damaged plaster and all fine cracks, pits, checks waves,
blisters and other defects which in the opinion of the CONSULTANT will impair
the appearance and the life and usefulness of the finish surfaces.

 All repairs shall be used approved material.

9.2.6 Housekeeping / Cleaning

 Site will be kept clean and tidy during the works and all the debris / waste
material will be cleaned and carted away to approved dumping area.

9.2.7 Plaster in Wet Area

 Please refer to item 9.2.2 and 9.2.3 of this method statement.

9.2.8 Plastering in Case Total Thickness is More Than 20mm

 The areas where plaster thickness is expected to exceed 20mm, a multiple coat
of plaster must be applied in receding thickness. A base coat of 15-20mm
thickness should be applied and cure it for two days. After the base course
becomes hard and dry, then apply the second coat / final coat of plaster with a
thickness of 10-15mm.

 Wherever thickness is 40mm, it can be applied in two coats (20mm first coat, 20
mm second coat.)

 If the expected thickness to exceed 40mm, fiber mesh reinforcement should be


given after the second coat in wet condition. When the plaster is wet, fix the
mesh. After two days of curing, final coat can be applied to achieve a maximum
thickness of 60mm.

9.2.9 Testing of Plaster Materials


CADANGAN TAMBAHAN DAN UBAHSUAI
BAGI SEBUAH PUSAT JAGAAN
AMBULATORI SWASTA SETINGGI 4
TINGKAT DI ATAS LOT 3140, BANDAR
TAIPING DAERAH LARUT DAN MATANG,
PERAK DARUL RIDZUAN.

Document No:
GLSS-JP-MS-CS33
Method Statement for
Rev : 00
Plastering Works Date: 14/07/2019
Page 11of 13

 Compressive strength and flexural strength for 7 and 28 days of plaster as per
the relevant codes of practice.

9.2.10 Pull off Test for Plaster

 To be done by ITL as per CONSULTANT’s discretion and comments.

9.2.11 Plastering in the Daycare Area

 Plastering in the daycare room and other related areas will be done as per the
approved shop drawing details as shown in the drawing MGC-5999-SD-CPA-
121.

 Work will proceed as per approved Mock-Up.

System 2: Using SDB 210 Spatter Dash-SB & PLS 221 Plastermix-S

Please refer to the attached Technical Data Sheets for PLS 221 & SDB 210 and Method
Statement for the same by the by the Supplier / Manufacturer for details.
10.0 ATTACHMENTS
 System Recommendations and TDS for MP-3 Rush Coat, MP-13 Cement Render / Plaster

 TDS for Plastermix-S PLS 221

 TDS for Spatter Dash-SB SDB 210

 Method statement for Plastermix-S PLS 221

 Method statement for Spatter Dash-SB SDB 210

 Risk Assessment

 ITP

 Checklist

You might also like