06/11/202408:24:30 Spreadsheet ShoppeWork Flow Management 1 of 1

Time Period
Daily

Gantt Chart Dates Site : MALL CIJANTUNG


Beginning Date 6/3/2024 Project : FTTX - GPON
Today PIC : Yusuf Surawijaya
Exclude
Task Duration Calculation Include
Weeken Weeken
24
ds ds 20
Jun
Start End Task % Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Thu
Level WBS Task Resource Start Date End Date Duration Complete 3 4 5 6 7 10 11 12 13 14 17 18 19 20 21 ###
1 P 1 Description Task Owner 03/06/2024 26/06/2024 24 #REF!
A 1.1 Preparation #REF! 05/06/2024
B 1.1.1 Approval Request HSP 03/06/2024 05/06/2024 3
B 1.1.2 Material Request HSP 05/06/2024 14/06/2024 10
A 1.2 Implementation Process - CCTV #REF! #REF!
B 1.2.1 Pulling UTP CAT6 Cable HSP/dhost 17/06/2024 20/06/2024 4
B 1.2.2 CCTV Installation HSP/dhost 21/06/2024 21/06/2024 1
B 1.2.3 CCTV Configuration HSP/dhost 22/06/2024 25/06/2024 4
B 1.2.4 Testing and Commisioning HSP/dhost 26/06/2024 26/06/2024 1
A 1.3 Implementation Process - WIFI
B 1.3.1 Pulling UTP CAT6 Cable HSP/dhost 17/06/2024 20/06/2024 4
B 1.3.2 AP Installation HSP/dhost 21/06/2024 21/06/2024 1
B 1.3.3 AP and captive portal config HSP/dhost 22/06/2024 23/06/2024 2
B 1.3.4 Testing and Commisioning HSP/dhost 24/06/2024 24/06/2024 1
A 1.4 Migration Tenant 06/06/2024 26/06/2024
B 1.4.1 Tenant Activation 11-20 HSP/dhost 06/06/2024 12/06/2024 7
B 1.4.2 Tenant Activation 21-30 HSP/dhost 13/06/2024 19/06/2024
B 1.4.2 Tenant Activation 31-40 HSP/dhost 20/06/2024 26/06/2024 7
A 1.5 RFS 26/06/2024 26/06/2024 1