Professional Documents
Culture Documents
1.0 Laminar Air Flow Installation Qualification
1.0 Laminar Air Flow Installation Qualification
Document No:
XX PHARMACEUTICALS LIMITED
117 Adams Street, Brooklyn, NY 11201, USA
Location:
XX PHARMACEUTICALS LIMITED
117 Adams Street, Brooklyn, NY 11201, USA
Approval of Document:
Prepared By:
Name: Rex Barrett
Designation: Manager, Validation
Department: Engineering
Signature & Date:
Checked By:
Name: Caleb Hines
Designation: Manager, Engineering
Department: Engineering
Signature & Date:
Agreed By:
Name: Milton Alvarado
Designation: Manager, Engineering
Department: Engineering
Signature & Date:
Approved By:
Name: Joanna Warner
Designation: Manager, Quality Assurance
Department: Quality Assurance
Signature & Date:
CONTENTS
Page
1 DOCUMENT DESCRIPTION 4
2 PURPOSE 4
3 SCOPE 4
4 RESPONSIBILITIES 4
5 BACKGROUND
5. Project Description & Related issues 4
1
5. Purchasing Information 4
2
6 SYSTEM DESCRIPTION 5
7 VERIFICATION OF INSTALLATION 5
9 ATTACHMENTS 8
10 REPORT SUMMARY 9
11 CONCLUSION 10
12 VERIFICATION OF COMPLETION 11
13 REPORT APPROVAL 12
14 ABBREVIATION 13
.
1. DOCUMENT DESCRIPTION
Document No. :
Version No. :
Date :
Description :
2. PURPOSE
To verify and document that the Laminar Air Flow Unit of Sterile Area of Cephalosporin Block is designed, built
and installed according to XX Pharmaceuticals Limited’s demand and manufacturer specifications and that
documentation is compiled to verify the integrity of the installation.
3. SCOPE
This Installation Qualification (IQ) is to be performed against agreed acceptance criteria on the Laminar Air
Flow Unit installed above the turn table after Depyrogenation Tunnel in Room of Sterile Production floor of
Cephalosporin Block. The scope will include assessment of equipment design and installation, connection of
utilities, presence and function of instruments.
4. RESPONSIBILITIES
4.1 Preparation of protocol
Engineering Department.
4.2 Executing the protocol
Engineering department or other suitably qualified staff allocated from the site or contracted specialists as
appropriate.
4.3 Providing documentation on the equipment
Related departments i.e. Engineering Production, Validation or other appropriate departments and
manufacturer
4.4 Data documentation and preparation of the report
Raw data documentation is the responsibility of those conducting the validation. Preparation of the report and
incorporation of data will be the responsibility of the Engineering Department.
5. BACKGROUND
5.1 Project Description & Related issues
This Laminar Air Flow Unit has been installed in the year 20XX in the sterile production area of Cephalosporin
Block for dispensing of raw materials.
5.2 Purchasing Information
A Laminar Air Flow Unit is used to provide unidirectional air flow. Grade A is ensured under LAF using H14
HEPA filter. A blower is used to circulate the air. The air flow direction of this LAF is vertical. There is a
differential pressure gauge to see the differential pressure across the filters which indicate the blockage of
filters.
7. VERIFICATION OF INSTALLATION
7.1 Design Documentation
7.1.1 General Characteristics
3 Manufacturer GUSU
Observations:
Material of
2 SS304
construction
Power: 1.5 KW
Phase: Single
Observations:
Observation:
Frequency 50 Hz
Observation:
Deviation/
Description and Assessment of Impact on Validation Initial Date
Failure No.
9. ATTACHMENTS
Attached data are listed in the table below:
Attachmen
Description of Attachment Initial Date
t
No.
3 Instruments verification
4 Utility verification
Comments:
Performed by:
Verified by:
11. CONCLUSION
The Installation Qualification of Laminar Air Flow Unit of Cephalosporin Block Complies / Does Not Comply
with the acceptance criteria taken above and the results obtained have been filled up in the respective table of
each test.
The Laminar Air Flow Unit of Cephalosporin Block is / is not qualifying the Installation Qualification test as per
this Protocol. Hence, the system can be / cannot be used for Operational Qualification.
Performed by:
Verified by:
Comments:
14. ABBREVIATIONS