Standard costing as a management Analysis: Introduction,Meaning and limitations of Standard
Standard Cost and Budgeted Cost, Tool, Historical costing, Estimated Costing and Costing, Cost. Variance Analysis: Direct Material Determination of Standard Standard Cost for Direct Material, DirectCosting, torial Quantity Variance, Matei ial Variance - Material Cost Variance, Material Rate Labour ionce - Labour Cost Variance, Mix Variance, and Material Yield Variance, DirectVariance, Labour Rate Variance, Labour labour Variance, Idle Time Variance and Labour Yield Variance. efficiency Variance, Labour Mix co 5: Given information about standard and actual determine Direct Material and Direct Labour Variances. performance, the student will be able to Question 1:
The standard quantity and standard price of raw material
as follows: required for one unit of product Aare given Quantity (kg.) S.P. (Rs.) Material X 2 3 Material Y 4 2 The actual production and relevant data are as follows: Material X- 1,100 kgs. @ Rs. 3,410 Material Y- 1,800 kgs. @ Rs. 3,960 Calculate Variances. Actual production was 500 units. Solution:
Analysis of Given Data
Materi Standar d Data Actual Data al Price Value Quantity Price Value Quantity (Kg.) (Rs.) (Rs.) (Kg.) (Rs.) (Rs.) 3.00 3,000 1,100 3.10 3,410 X 1000 (500 x 2) 2000 (500 x 4) 2.00 4,000 1,800 2.20 3,960
7,000 2,900 7,370
3000
Material saSP (Rs.) RSQSP (Rs.) AQSP (Rs.) AQAP (Rs.)
966.67 x3 = 2,900 1,100 x 3
X 1,800 x 2 Y 1933.33 x 2 = 3,867 6,767 6,900 7,370 Total 7,000
Material = Rs. 7,000
Where (1)SQSP = Standard Cost of Standard Material = Rs 6,767 (2}RSQSP = Revised Standard Cost of Material = Rs. 6,900 (3) AQSP = Standard Cost of Actual