Formation of New Six lane road from Thatchur (Design Chainage : 21+700) to Punnapakkam (Design Road Chainage 35+000)

with paved shoulders and two lane Service road on


Project Name
both sides in Section-2 of Chennai Peripheral Ring Road project under package-1 on Engineering, Procurement and Construction (EPC) mode including maintenance for 7 years

Client Name Tamil Nadu Road Infrastructure Development Corporation (TNRIDC)


Authority Engineer Intercontinental Consultants and Technocrats Pvt. Ltd in association with Mukesh & Associates
EPC Contactor SPK And Co..,
DAILY RFI SUMMARY
Date of Submission 02-06-2024
Sr. Chainage Length in Inspection
RFI Description of Work Side Remarks
No. From To Meter. Date Time
1 SPK/ICT/EPC-01/STR/10461 MJB - Pile Boring (LP4-1) 29+172 03-06-2024 09.00AM

2 SPK/ICT/EPC-01/STR/10462 Drainage Raft Reinforcement Checking & Concrete 22+200 22+240 LHS 40 03-06-2024 09.00AM

3 SPK/ICT/EPC-01/STR/10463 MNB - Dirt Wall Reinforcement Checking and Concrete (SRA2 ) 29+322 RHS 03-06-2024 10.00AM

4 SPK/ICT/EPC-01/STR/10464 Drainage - EarthWork Excavation 22+150 22+200 LHS 50 03-06-2024 10.00AM

5 SPK/ICT/EPC-01/STR/10465 Drainage - M15 PCC Concrete 22+150 22+200 LHS 50 03-06-2024 10.30AM

6 SPK/ICT/EPC-01/STR/10466 Drainage - Wall Final Lift & Slab Reinforcement Checking & Concrete 22+400 22+430 RHS 30 03-06-2024 11.00AM

7 SPK/ICT/EPC-01/STR/10467 MJB - Pedestal Reinforcement checking & concrete (RP6) 29+172 RHS 03-06-2024 12.00PM

8 SPK/ICT/EPC-01/STR/10468 Drainage - Wall 1st Lift Reinforcement Checkcing & Concrete 27+020 27+050 LHS 30 03-06-2024 12.00PM

9 SPK/ICT/EPC-01/STR/10469 Drainage Raft Reinforcement Checking & Concrete 27+070 27+110 LHS 40 03-06-2024 01.00PM

10 SPK/ICT/EPC-01/STR/10470 Retaining Wall - Final Lift Reinforcement Checking & Concrete 28+760 28+800 LHS 40 03-06-2024 02.00PM

11 SPK/ICT/EPC-01/STR/10471 MJB - Pile Cage Lowering & Concrete (LP4-1) 29+172 03-06-2024 02.00PM

12 SPK/ICT/EPC-01/STR/10472 Drainage - Wall Final Lift & Slab Reinforcement Checking & Concrete 27+810 27+840 LHS 30 03-06-2024 03.00PM

13 SPK/ICT/EPC-01/HW/10473 FDD - Ground Improvement 7th Layer (Pond Ash) A1 Side 27+430 27+475 BHS 45 03-06-2024 11.00AM

14 SPK/ICT/EPC-01/HW/10474 RE Wall - Panel Erection - 1st Lift - A2 Side (LC53, R1 to LC73, R1) 24+600 24+640 LHS 40 03-06-2024 11.30AM

15 SPK/ICT/EPC-01/HW/10475 RE Wall - Panel Erection - 1st Lift - A2 Side (LC53, R1 to LC73, R1) 24+600 24+640 RHS 40 03-06-2024 11.45AM

16 SPK/ICT/EPC-01/HW/10476 FDD - Check for Embankment 1st Layer - MCW 28+080 28+200 BHS 120 03-06-2024 03.30PM

17 SPK/ICT/EPC-01/HW/10477 FDD - Check for Embankment 1st Layer - SR 28+080 28+200 LHS 120 03-06-2024 04.00PM

18 SPK/ICT/EPC-01/HW/10478 FDD - Check for Embankment 1st Layer - SR 28+080 28+200 RHS 120 03-06-2024 04.30PM

19 SPK/ICT/EPC-01/HW/10479 FDD - Ground Improvement 3rd Layer (Pond Ash) A2 Side 27+693 27+800 BHS 107 03-06-2024 05.00PM