Ref: Fab-Work / Panvel/ 2023/023 Date: 17/09/2023

To,
The Chairman / Secretary,
Indiabulls Greens,
Opp.Honda Warehouse, Rasayani Road,
Panvel, Kon, Maharashtra 410206.

Sub: Revised Quotation of Shed fabrication work at above said address.

Dear Sir,
We are introducing ourselves as one of the civil and electrical contractors in Navi Mumbai and
Mumbai, and we are very glad to submit our proposal for shed fabrication work in your society's
buildings.

Sr. No Description UOM Quantity Rate Amount


1 Installation of Shed Fabrication
Work over the roof top of
Lump 1 1,15,000 1,15,000
buildings of the Society with
Sump
material of Corrugated
polycarbonate sheet 2mm,Frame
- Hot dip galvanized angle (50
mmx 50mm x 6mm),Complete
Fabrication (welding, angle
fastener, J bolt, Nut-bolt or self
screw etc as required ) and
Material loading, unloading and
shifting material upto the 37th
floor from the base of building
Total Amount in figure 1,15,000

Total Amount in Rupees One Lakh Fifteen Thousand Only.


Words
We request you to look after it and hope we will get the positive reply from your side.
Terms & Condition

1. 50 % Advance should be released against Work order.


2. Balance payment should be released after completion of work within seven days.
3. The above said amount is inclusive with GST.
4. GST amount should be paid after receiving full and final payment.
5. Welding, Chemical bolt, All Material structure Warranty of 5 Years after the installation.
There is no warranty on polycarbonate sheet.
6. If any disaster causes the fabricated shed structure to collapse, the warranty on the
structure and material should not be valid.
7. Work Should be completed within 15 days after clearing the advance cheque.
8. Providing of Electricity and Water should be scope of Society.

Thanks and Warm Regards,