Document Number

Kamoa Copper SA
NRN-CON-CIV-CL-014
Revision Number / Date
Quality Management System
00 / 16 July 2022

Page Number
TILING INSTALLATION - CHECKLIST
Page 1 of 1

Client: Project:
Main Contractor: Project No.:
Sub-Contractor: Drawing No:
Scope: Specification: SANS 10252 – 1 sect. 5; SANS 10254

THIS CHECKLIST SHALL BE DISPLAYED AT THE JOBSITE UNTIL P3 PUNCH IS COMPLETE

NERIN
CONTRACTOR QC
CONSTRUCTION
# ITEMS TO BE CHECKED INSPECTOR
SUPERVISOR
YES NO YES NO
1 Tiles correct according to specification
2 Tiles inspected upon receiving OSD reported.
3 Tile Grout according to specification and quantity adequate.
4 Centre lines set out and checked.
5 Area & surface clean & dust free.
6 Levels correct & Falls (External)
7 Joint strips inserted.
8 Chipped & cracked tiles replaced.
9 No hollow areas between tiles and grout.
10 Excess grout removed and cleaned.
11 Finishing good.
12 Wall Plaster QC forms completed.
13 Splashbacks & Tiles as per specifications.
14 Ensure Tiling inspection intervention points in QCP are signed off.

GENERAL COMMENTS:

APPROVAL

Contractor QC Inspector Contractor Supervisor NERIN Supervisor

Name:

Sign:

Date: