Professional Documents
Culture Documents
Costing - Inter - Aq
Costing - Inter - Aq
Costing - Inter - Aq
KS ACADEMY
CA – INTER
COSTING
1. A meeting of the heads of departments of the Arnav Ltd. has been called to review the
operating performance of the company in the last financial year. The head of the
production department appraised that during the last year the company could operate
at 70% capacity level but in the coming financial year 95% capacity level can be achieved
if an additional amount of `100 Crore on capex and working capital is incurred.
The head of the finance department has presented that during the last financial year the
company had a P/V ratio of 40%, margin of safety and the break-even were `50 crore
and `200 crore respectively.
To the reply to the proposal of increasing the production capacity level to 95%, the head
of the finance department has informed that this could be achieved if the selling price
and variable cost are reduced by 8% and 5% of sales respectively. Fixed cost will also
increase by `20 crore due to increased depreciation on additional assets. The additional
capital will be arranged at a cost of 15% p.a. from a bank.
In the coming financial year, it has been aimed to achieve an additional profit
of `10 crore over and above the last year’s profit after adjusting the interest
cost on the additional capital.
i.What will be the revised sales for the coming financial year?
A. 322.22 Crore
B. 311.11 Crore
C.300.00 Crore
D. 324.24 Crore
ii.What will be the revised break-even point for the coming financial year?
A.222.22 Crore
B. 252.22 Crore
C. 244.44 Crore
D. 255.56 Crore
1
K S ACADEMY SAP 10-03-2024
iii. What will be the revised margin of safety for the coming financial year?
A. 100 Crore
B. 58.89 Crore
C.55.56 Crore
D. 66.66 Crore
iv. The profit of the last year and for the coming year are:
A.50 Crore & 295 Crore respectively
B. 20 Crore & 65 Crore respectively
C. 20 Crore & 30 Crore respectively
D. 45 Crore & 66.66 Crore respectively
v.The total cost of the last year and for the coming year are:
A. 230 Crore & 292.22
B. 230 Crore & 275 Crore
C. 220 Crore & 282.22 Crore
D. 220 Crore & 292.22 Crore
2. K Ltd. is a manufacturer of a single product A. 8,000 units of the product A has been
produced in the month of March 2024. At the beginning of the year a total 1,20,000 units
of the product-A has been planned for production. The cost department has provided
the following estimates of overheads
Fixed Rs.12,00,000 Variable Rs.6,00,000
Semi-Variable Rs.19,200
Semi-variable charges are considered to include 60 per cent expenses of fixed nature and
40 per cent of variable character 3 The records of the production department shows that
the company could have operated for 20 days but there was a festival holiday during the
month.
The actual cost date for the month of march 2024 are as followings
Fixed Rs.1,19,000 Variable Rs.48,000
Semi-Variable Rs.19,200
The cost department of the company is now preparing a cost variance report for
managerial information and action. You being an accounts officer of the company are
asked to calculate the following information for preparation of the variance
Report (10 Marks)
i.What is the amount of variable overhead cost variance for the month of
March 2024:
A.10,200 (A)
B.10,400 (A)
C.10,800 (A)
D.10,880 (A)
ii. What is the amount of fixed overhead volume variance for the month of
March 2024:
A.9,000 (F)
B.9,000 (A)
2
K S ACADEMY SAP 10-03-2024
C.21,800 (A)
D. 11,000 (A)
iii. What is the amount of fixed overhead expenditure variance for the month
of March 2024
A.21,520 (A)
B. 21.500 (A)
C.21.400 (A)
D. 21.480 (A)
iv. What is the amount of fixed overhead calendar variance for the month of
March 2024:
A.5,400 (A)
B.5,450 (A)
C.5,480 (A)
D.5.420 (A)
v. What is the amount of fixed overhead cost variance for the month of
March 2024
A.43,320 (A)
B.43,300 (A)
C.43,200 (A)
D.43,380 (A)
3. If the amount of wages under Halsey plan is ` 420, total time allowed is 8 hours and the
guaranteed time rate is ` 60 per hour. What is the total time saved by the worker?
(a) 2 hours
(b) 3 hours
(c) 6 hours
(d) 3.5 hours (2 Marks)
4. From the following information, calculate the Total cost of Product A and B
using the ABC analysis:
Product A Product B
Units 5,000 5,000
Number of purchase orders placed 100 220
Number of deliveries received 70 200
Ordering Cost Rs.4,00,000
Delivery Cost Rs.1,35,000
A. A = Rs.47,500; B = Rs.1,27,500
B. A = Rs.2,67,500; B = Rs.2,67,500
C. A = Rs.1,60,00; B = Rs.3,75,000
D. A = Rs.1,47,500; B = Rs.1,47,500 (2 Marks)
3
K S ACADEMY SAP 10-03-2024
6. A product passes through Process-I. Input raw material issued were 8,000 units. Normal
loss anticipated was 10% of input with realisable value of ` 5 per unit. 7,600 units of
output were produced and transferred to next process. If the total cost incurred under
Process-I was ` 40,000, then amount of abnormal gain/(loss) is:
(a) 2,000
(b) (5,000)
(c) (2,500)
(d) 3,000 (2 Marks)
7. Find out the most appropriate unit cost from the following information of ZMD
Transport Services Ltd. dealing in goods carriage;
Total cost 5,25,000
Kms, Travelled 8,75,000
Tonnes carries 4,000
No of drivers 25
No of trucks 20
Tonnes Km carried 6,55,000
(a) 0.6
(b) 0.8
(c) 21,000
(d) 131.25 (2 Marks)
4
K S ACADEMY SAP 10-03-2024
5
K S ACADEMY SAP 10-03-2024
10. (c) In a factory, The basic wage rate is Rs.300 per hour and overtime rates are as follows:
Before and after normal working hours 180% of basic wage rate
During the previous year, the following hours were worked 230% of basic wage rate
Normal time 1,00,000 hours
Overtime before and after working hours 20,000 hours
Overtime on Sundays and holidays 5,000 hours
Total 1,25,000 hours
6
K S ACADEMY SAP 10-03-2024
11. (a) From the following information for the month of January, 20X9, PREPARE Process-
III cost accounts.
Opening WIP in process-III 1,600 Units at Rs.24,000
Transfer from process – II 55,400 Units at Rs.6,23,250
Transferred to warehouse 52,200 Units
Closing WIP of process -III 4,200 Units
Units Scrapped 600 Units
Direct Material added in process -III Rs.2,12,400
Direct Wages Rs.96,420
Productions overheads Rs.56,400
Degree of completions:
Opening Stock Closing stock Scrap
Material 80% 70% 100%
Labour 60% 50% 70%
Overheads 60% 50% 70%
7
K S ACADEMY SAP 10-03-2024
The normal loss in the process was 5% of the production and scrap was sold @ Rs.5 per
unit. (students may treat material transferred from process – II as material – A and fresh
material used in process – III as material B) {10 Marks}
Ans;
8
K S ACADEMY SAP 10-03-2024
12. (b) Discuss with example the level of activity method of segregating semi-variable costs
into fixed and variable cost ? {4 Marks}
Ans;
9
K S ACADEMY SAP 10-03-2024
13. (a) Arnav Ltd manufactures a product Q , the standard cost of which is a follow:
Standard Cost per unit (Rs)
Direct Material 600
Direct Labour;
Skilled @ Rs.80 per hours 120
Unskilled @ Rs.60 per hour 90
Variable overheads 75
Fixed overheads 30
915
During the month just ended 4,000 units of Q were product . The actual labour cost was
as follows;
Rate per hour (Rs) Cost (Rs)
Skilled 87.50 5,77,500
Unskilled 55.00 2,97,000
10% of the Labour time was lost due to idle time , The standard idle time was 7.5% of
labour time. Arnav Ltd has budgeted to produce 4,200 units of Q. Arnav Ltd . absorbs its
overheads on direct labour hour (effective hours) basis. Actual fixed and variable
overheads incurred were Rs.1,55,000 and Rs.2,85,000 respectively.
CALCULATE:
(i) Labour rate variance
(ii) Labour efficiency variance
(iii) Labour mix variance
(iv) Labour yield time variance
(v) Labour idle time variance
(vi) Variable overheads expenditure variance and
(vii) Variable overhead efficiency variance {10 Marks}
Ans:
10
K S ACADEMY SAP 10-03-2024
14. (b) A manufacturing company disclosed a net loss of Rs.3,47,000 as per their cost
accounts for the year ended March 31,20x8. The financial accounts however disclosed a
net loss of Rs. 5,10,000 for the same period. The following information was revealed
because of scrutiny of the figures of both the sets of accounts.
(Rs.)
(i)Factory Overheads under-absorbed 40,000
(ii)Administration Overheads over-absorbed 60,000
(iii)Depreciation charged in Financial Accounts 3,25,000
(iv)Depreciation charged in Cost Accounts 2,75,000
(v)Interest on investments not included in Cost Accounts 96,000
(vi)Income-tax provided 54,000
(vii)Interest on loan funds in Financial Accounts 2,45,000
(viii) Transfer fees (credit in financial books) 24,000
(ix)Stores adjustment (credit in financial books) 14,000
(x)Dividend received 32,000
PREPARE a memorandum Reconciliation Account. {4 Marks)
11
K S ACADEMY SAP 10-03-2024
Ans;
15. (a) A jobbing factory has undertaken to supply 300 pieces of a component per month for
the ensuing six months. Every month a batch order is opened against which materials
and labour hours are booked at actual. Overheads are levied at a rate per labour hour.
The selling price contracted for is 8 per piece. From the following data CALCULATE the
cost and profit per piece of each batch order and overall position of the order for 1,800
pieces.
Month Batch output Material cost Rs Direct Wages Rs Direct labour hours
January 310 1150 120 240
February 300 1140 140 280
March 320 1180 150 280
April 280 1130 140 270
May 300 1200 150 300
June 320 1220 160 320
12
K S ACADEMY SAP 10-03-2024
16. (b) KJ Motors Ltd. Is a manufacturers of auto components. Following are the details of
expenses for the year 202-21;
Rs
(i) Opening stock of material 15,00,000
(ii) Closing stock of material 20,00,000
(iii) Purchase of material 1,80,50,000
(iv) Direct Labour 90,50,000
(v) Factory overheads 30,80,000
(vi) Administrative overheads 20,50,400
During the FY 2021-22, the company has received an order from a car manufacturer
where it estimates that the cost of material and labour will be * 80,00,000 and 40,50,000
respectively. The company charges factory overhead as a percentage of direct labour
and administrative overheads as a percentage of factory cost based on previous year's
cost. Cost of delivery of the components at customer's premises is estimated at 9,50,000.
You are required to:
(i) CALCULATE the overhead recovery rates based on actual costs for 2020-21.
(ii) PREPARE a Job cost sheet for the order received and the price to be quoted if the
desired profit is 25% on sales {4 Marks}
Ans;
13
K S ACADEMY SAP 10-03-2024
17. (c) A factory produces two products, 'Ghee' and 'Cream' from a single process. The joint
processing costs during a particular month are:
Direct Material Rs.60,000
Direct Labour Rs.19,200
Variable Overheads Rs.24,000
Fixed Overheads Rs.64,000
14
K S ACADEMY SAP 10-03-2024
Sales: Ghee - 200 litre @ Rs.600 per litre; Cream -240 litre @R200 per litre. REQUIRED:
I. Apportion joints costs on the basis of:
(i) Physical Quantity of each product.
(ii) Contribution Margin method, and
II. Determine Profit or Loss under both the methods. {2 Marks}
Ans;
15
K S ACADEMY SAP 10-03-2024
19. (b) Explain standing charges and running charges in the case of transport organizations
List three examples of both. {6 Marks}
Ans;
16
K S ACADEMY SAP 10-03-2024
20. (a) A Ltd. produces a single product X. During the month of December 2021, the
company has produced 14,560 tonnes of X. The details for the month of December 2021
are as follows:
(i) Materials consumed 15,00,000
(ii) Power consumed 13,000 Kwh @7 per Kwh
(iii) Diesels consumed 1,000 litres @93 per litre
(iv) Wages & salary paid - 64,00,000
(v) Gratuity & leave encashment paid- 44,20,000
(vi) Hiring charges paid for HEMM-13,00,000
(vii) Hiring charges paid for cars used for official purpose - 80,000
(viii) Reimbursement of diesel cost for the cars - 20,000
(ix) The hiring of cars attracts GST under RCM @5% without credit.
(x) Maintenance cost paid for weighing bridge (used for weighing of final goods at the
time of despatch)-7,000
(xi) AMC cost of CCTV installed at weighing bridge (used for weighing of final goods at
the time of despatch) and factory premises is 6,000 and 18,000 per month respectively.
16,000
(xii) TA/ DA and hotel bill paid for sales manager-
(xiii) The company has 180 employees works for 26 days in a month.
Required:
(a) PREPARE a Cost sheet for the month of December 2021.
(b) COMPUTE Earnings per manshift (EMS) and Output per manshift (OMS) for the
month of December 2021 {5 Marks}
Ans;
17
K S ACADEMY SAP 10-03-2024
21. (a) Arnav Ltd. is producing a single product, has the profit-volume ratio of 40%. The
company wishes to increase the selling price by 10% which will increase the variable
cost by 5%. The fixed overheads will increase from its present level of Rs.20,00,000 to
Rs.30,00,000.
Required:
(i) Compute the company's original break-even point sales and the break-even point
sales after the increase.
(ii) Estimate the sales value for the firm to make a profit of Rs. 4,50,000
after the increase. {5 Marks}
Ans;
18
K S ACADEMY SAP 10-03-2024
19
K S ACADEMY SAP 10-03-2024
(or)
20