Professional Documents
Culture Documents
Chapter 7. Project Administration & Documentation
Chapter 7. Project Administration & Documentation
L. O. Muku
21-Feb-24
7.1 Introduction
Key aspects of Project administration and documentation:
1. Line of authority and communication among owner, consultant and contractor.
2. Project meetings, client-consultant and site meetings.
3. Progress documentation and reports.
4. Site diary/log/Site journal.
5. Records and drawings.
6. Records of change orders, claims and delays, and plant.
7. Resource planning, coordination and control.
21-Feb-24
Site Agent & Assistants
The Contractor shall constantly keep upon the Works a suitably qualified and experienced
Person who shall be deemed to be the Site Agent of the Contractor for the purposes of the
Contract, together with such senior assistants and supervisory staff in each trade as may be
necessary as set out in the Contract Documents or as amended from time to time after prior
approval of the Architect.
o If any such directions are so given and confirmed in writing by the Architect /Engineer
then as from the date of issue of that confirmation it shall be deemed to be an
Architect’s/Engineer’s instruction.
21-Feb-24
Line of Authority on Construction Projects
Agency relationship
– Actual authority: express grant of actual authority
– Apparent authority: allows another party to operate with the appearance of
authority to act on behalf.
– Delegation of authority: to delegate authority to others
– Limited authority: limitations on the scope of the agent’s authority.
21-Feb-24
Types of Meetings with the Contractor
o Pre-bid conference.
o Pre-construction conference.
o Requests for substitutions of materials or products.
o Change orders and extra work.
o Corrections required.
o Scheduling changes.
o Mediation of construction difficulties.
o Protests and dispute.
o Difficulties caused by conflicts in drawings & specs.
o Project acceptance and transfer of responsibility.
o Post project review meeting.
Steering group/team
To consider project brief, design concepts, capital budget and schedules.
To approve changes to project brief.
To review project strategies and overall progress towards achieving client’s goals.
To approve appointments of consultants and contractors.
21-Feb-24
Project team
o To agree cost plan and report on actual expenditure against agreed plan.
o To review tender lists and tenders received and decide on awarding work.
o To report on progress on design and construction schedules.
o To review and make recommendations for proposed changes to design and costs,
including client changes.
o To approve relevant modifications to project programmes.
o To provide effective communication between teams responsible for the various phases of
the project.
o To monitor progress and report on developments, proposed changes and schedule
implications.
o To review progress against schedules for each stage/section of the project/works and
identify any problems
o To review procurement status
o To review status of information for construction and contractors’ /subcontractors’
requests for information.
21-Feb-24
Design team
o To review, report and implement all matters related to design and cost.
o To determine/review client decisions
o To prepare information/ report/ advice to project team on:
– Appointment of sub/specialist contractors
– Proposed design and/or cost changes
o To review receipt, co-ordination and processing of subcontractors’ design information.
o To ensure overall co-ordination of design and design information.
Information:
o Issued by design team
o Required from design team
o Required from contractor
21-Feb-24
Procedure for meetings
o Agenda – issued in advance stating action/submissions required.
o Minutes and circulation list (time limits involved).
o Written confirmation and acknowledgement of instruction given at meetings (time limit
involved).
o Reports/materials tabled at meetings to be sent in advance to the chair.
21-Feb-24
Contract Documents
o Drawings
o Specifications
o Bills of Quantities (Contract Bills)/Schedule of rates)
o Agreement
o Conditions of Contract.
Documentation
Certificates
o Interim certificate
o Certificate of practical completion
o Certificate of making good defects
o Final certificate
Others
o Certificate of Non-completion
o Architects / Engineers Instructions
o Variation Orders
21-Feb-24
Drawings
o Survey plan
o Site plan, layout and drawing
o General arrangement
– for services
– foundation
– floor plans
– roof plan
o Elevations
o Sections
o Ceiling plans
o Construction details
o Large scale details
21-Feb-24
Schedules
o Window schedule
o Door schedule
o Finishes schedule
o Manhole schedule
21-Feb-24
Construction Site Office Files
o Correspondence
o Working/construction/Job drawings
o Shop/fabrication drawing submittals
o Requisitions
o Reports
o Samples
o Operating tests
o Deviation request/change order.
Construction Records
o Progress of the work
o Telephone calls
o Testing of materials
o Diary
o Log of submittals
21-Feb-24
Daily Construction Reports
o Project name and job number
o Client’s name (name of project owner)
o Contractor’s name
o Name of Project Manager for the design organization
o Report number and date of report (use consecutive numbering).
o Day of the week
o Weather conditions (wind, humidity, temperature, sun, clouds, etc.)
o Average field force, both supervisory and non-supervisory
– Name of each contractor or subcontractor on the job that day
– No. of manual workers (skilled and general labour) at the site
– No. of non-manual workers (superintendents and foremen) at the site.
o Visitors at the site: include names, employers, and time in and out.
o List identity, size, and type of all major pieces of construction equipment at the site each
day. Indicate if idle, and reason, if applicable.
o Log all work commenced; status of all work in progress; and all new work started. Identify
location of the work as well as its description, and which contractor or subcontractor is
performing it.
o Sign the daily report with your full name, title, and date.
21-Feb-24
Format of Construction Diary /log/Site journal
o Use only a hardcover, stitched-binding field book.
o No erasures should be made. In case of error, simply cross out the incorrect information
and enter the correct data next to it.
o Every day should be reported, and every calendar date should be accounted for.
21-Feb-24
Content of Construction Diary/log/Site journal
o Record telephone calls made or received, and substantial outline of the nature of such
calls, including any statements or commitments made during the call.
o Record of any work or material in place that does not correspond with the drawings or
specifications, as well as the action taken.
o List any other problems or abnormal occurrences that arose during each day, including
notations of any particular lack of activity on the part of the contractor. Note corrective
actions taken.
o Record time and the nature of the contractor’s representative to whom field orders are
delivered, and the nature of the contents of the field order.
o Note unforeseen conditions observed by the inspector that may cause a slowdown by the
contractor.
o Where extra work is performed because of an unforeseen underground obstruction, make
a record of all personnel and equipment at the site and how they are occupied. (the
number and craft of each person idled, idle equipment etc. )
21-Feb-24
Content of Construction Diary /log/Site journal..
o Record the content of all substantive conversations held with the contractor at the site
and any trade-offs, deals, or commitments made by either party.
o Record all field errors made by any party at the site. Identify in detail and indicate
probable effect.
o Sign every diary entry and indicate your title immediately under the last line of entry
on each day’s report.
21-Feb-24
Objectives of Construction documents
o Communication of Information
o Evidence of conformity
o Knowledge sharing
21-Feb-24
Extent of documentation differ from one organization to another
due to…
o The size of organization and type of activities;
o The complexity of processes and their interactions, and
o The competence of personnel.
21-Feb-24
Documents
o Process map, process flow charts and/or process descriptions.
o Organization charts.
o Specifications.
o Work and/or test instructions.
o Documents containing internal communications.
o Production schedules.
o Approved suppler lists.
o Test and inspection plans.
o Quality plan.
21-Feb-24
Control of documents
o To approve documents for adequacy prior to issue.
o To review and update as necessary and reapprove documents.
o To ensure that
– changes and the current revision status of documents are identified.
– the relevant versions of applicable documents are
available at points of use.
– documents remain legible and readily identifiable
– documents of external origins are identified, and their distribution controlled.
21-Feb-24