Professional Documents
Culture Documents
Substations and Electrical Installations
Substations and Electrical Installations
Members
Corresponding Members
M. BECK DE A. CANHOTO PT
G. BECKER US T. SAIDA JP
Copyright © 2023
“All rights to this Technical Brochure are retained by CIGRE. It is strictly prohibited to reproduce or provide this publication in any
form or by any means to any third party. No part of this publication may be reproduced or utilized without permission from CIGRE”.
Disclaimer notice
“CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any responsibility, as to the
accuracy or exhaustiveness of the information. All implied warranties and conditions are excluded to the maximum extent permitted
by law”.
WG XX.XXpany network provided access is restricted to their own employees. No part of this publication may be
reproduced or utilized without permission from CIGRE”.
Disclaimer notice
“CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any
responsibility, as to the accuracy or exhaustiveness of the information. All implied warranties and
conditions are excluded to the maximum extent permitted by law”.
ISBN : 978-2-85873-625-6
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Executive Summary
This technical brochure summarises the work carried out between 2018 and 2023 by members of
international Working Group B3.50 of CIGRE Study Committee B3 representing users, original
equipment manufacturer (OEM), academia, and (independent) third party testing institutes
(consultants).
It is the consensus among the members of this Working Group that performing on-site high voltage
(HV) testing after installation, repair or extension of any gas-insulated switchgear (GIS) constitutes a
technically important and valuable step within the applied quality control procedures of both user and
OEM to ensure a higher reliability of the GIS for its operational life. It requires specialist knowledge
and is often considered as one of the last invasive activities on every GIS compartment.
On-site HV testing of GIS is an area where users and other stakeholders may have limited experience.
Typically, only utilities with a large fleet of GIS installations have the necessary exposure to on-site HV
testing to maintain the required know-how and experience in this specialised area. Therefore, a
structured outline of on-site HV testing of GIS is presented in this brochure.
It emphasises the importance of considering the relevant aspects of on-site HV testing early in the GIS
design process of the OEM and user, which is of benefit for the performance of the GIS over its
lifetime.
Some of these aspects, e.g. space requirements and testing power of HV test sets, kind of HV
injection, the injection point into the GIS and more, exhibit various levels of importance concerning
commissioning, repair, or extension of a GIS. Potential failure damage to GIS installations and service
personnel in the future can be significantly reduced where on-site HV testing is performed instead of
alternative test methods by means of service voltages from the power grid.
After the introduction of the different (inter)national standard requirements applied worldwide with
focus on test voltage levels, test durations, specifications for repetition procedures after disruptive
discharges (e.g. either in the conditioning phase or during the specified test voltage application) and
key drivers for performing on-site HV testing, further aspects for different interpretations of testing
procedures are introduced and discussed.
It is obvious that successful dielectric site testing of GIS needs more than the application of the
required or recommended test voltage values from (inter)national standards without occurrence of
disruptive and/or partial discharges. Proper planning, communication and problem-solving skills are
needed to coordinate between stakeholders to ensure that in the event of disruptive and/or partial
discharges occurring during testing, they are located and repaired, so that the overall quality of the
GIS installation is guaranteed.
On-site HV testing requirements of GIS users worldwide often exceed HV testing requirements stated
in (inter)national standards. However, an established assessment of the tangible benefits appears to
be a challenge, especially when transferring from specific circumstances towards typical application
scenarios. The limited return of experience indicates possible positive effects from enhanced HV
testing requirements concerning the reliability of critical and important GIS.
These requirements are also often linked with more stringent test procedures for partial discharge
(PD) measurements in terms of PD test voltage level and PD test durations. On the other hand,
approaches based on strict quality control measures exist with focus on moderate AC and PD test
parameters compared to common worldwide standard requirements, but with positive effects towards
GIS reliability.
This may be a potential area to be captured or treated in future reliability surveys to consider if
enhanced testing beyond current (inter)national standard requirements has led to improved reliability
or not.
A subsequent review of HV testing equipment and on-site HV testing methods for GIS summarises
some of the main aspects of the different testing technologies and their applications. The collection of
state-of-the-art information and an extensive summary presents a vast overview of different
procedures for ‘electrical conditioning’ or ‘conditioning phases’ in conjunction with the power-frequency
withstand voltage test itself.
The Working Group has focused on HV GIS testing activities and touches only briefly on other voltage
classes. However, some insights into worldwide current practices and their return of experience for on-
3
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
site HV testing of other GIS voltage classes than HV are presented. These range from different
specifications for test voltage values and test procedures, as well as for differences for the final
assessment of a test result. The display of some specific applied procedures for 'conditioning phases'
as well as for 'testing phases' are elaborated on in this brochure.
An analysis of evolutions of user specifications has been developed. These evolutions focus on
relevant aspects which have been adopted after return of experience made with on-site HV testing of
GIS. On the one hand external factors such as national regulations for system reliability and
performance targets where utilities risk loss of revenue or penalties in event of outages caused by GIS
failure or malfunction may influence the user. On the other hand, internal factors such as user
experience (or even lack thereof), network strength and redundancy, familiarity of staff with GIS
designs and technologies, or age and profile of existing installed GIS base can influence the decision
of the user in adopting specific requirements.
One common driver found within specifications of a few experienced users is the desire to adopt
common testing methodologies, independent of the OEM or third party responsible for on-site HV
testing. With respect to common testing methodologies, user requirements to achieve higher levels of
quality assurance during dielectric on-site testing activities can influence the physical design and
specification for the initial installation.
However, it was found by the Working Group that users appear not to be keen on implementing
dedicated or permanent test connection points to their specified GIS substations or critical
installations. This can be related to challenges which may arise from specific user specifications (e.g.
limitation for repositioning of test voltage generator or site specific constraints).
The different scenarios for which on-site HV testing activities should be implemented (e.g. after
installation, extension, retrofit or repair) have a wide range of impacts resulting from infrastructure,
lifting options, necessary air clearances, type of HV testing equipment and/or scheduling issues. Here,
especially the kind of HV injection point on the GIS can trigger significant different efforts in resources
and time. It is emphasised by the Working Group from the return of experience of on-site HV testing in
remote or urban substation locations that established coordination and communications lines between
the user / OEM / third party in a very short period is important, so that ‘everything’ is clarified.
An important topic is the agreement between user / OEM / third party regarding the specific HV test
procedures and the required acceptance criteria. This is emphasized with respect to test methods, test
voltage levels, test durations and repetition procedures after frequent disruptive discharges occur at
the GIS section under test. A suitable colour coding can support for good overview of various test
sections.
Moreover, timely clarifications before mobilisation to site concerning the level of test documentation,
technical requirements for the HV testing equipment, and in case of on-site HV tests on GIS
extensions the provision of historical operational information on the substation including specifications
for the test procedure of the interface between existing GIS and its extension can be very helpful.
Lastly, after mobilisation to site one important task was identified to verify location and space
requirement for the HV testing equipment at the site. Experience has shown that deviations can occur
between the planning and execution phase in this regard. Sometimes ad-hoc solutions need to be
worked out. The verification of the intended switching configuration and final check of safe working
area is essential, and each contributor to the test should know their role and responsibility.
A certain flexibility can be of benefit for those scenarios when time constraints apply, and
communication lines must be considered appropriately. This can especially arise from updates and
changes to the test procedure for investigation in case of the event of disruptive discharges or
detected partial discharge activities.
Over past years it was observed more frequently that delays from previous project stages are
expected by the project management (OEM and user) to be reduced during the on-site HV testing
period. This is contrary to the return of experience of the Working Group, when a smooth energisation
of a GIS can often be traced back to sufficient time being allowed for the on-site HV testing activities.
The Working Group B3.50 acknowledges and expresses thanks to all involved companies of the
Working Group members that have allowed their representatives time, travel, and encouragement to
contribute to the realisation of this technical brochure.
4
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Contents
Executive Summary ............................................................................................................ 3
1. Introduction.............................................................................................................. 12
1.1 Scope and chapter structure .................................................................................................................. 12
1.2 Drivers for on-site HV testing of GIS – reliability assurance (commissioning, repair, extension,
condition assessment) ........................................................................................................................................ 13
1.3 Review of (inter)national standards requirement (IEC, IEEE, GOST, GBT/DGT, JEC) ....................... 15
1.3.1 Comparison of requirements from relevant (inter)national standards ................................................ 16
1.3.2 Comparison of recommended repetition procedures after disruptive discharge during HV testing .... 21
2. Review of HV testing equipment and on-site testing methods for GIS ................ 23
2.1 Overview................................................................................................................................................... 23
2.1.1 Introduction ........................................................................................................................................ 23
2.1.2 GIS defects and their detection .......................................................................................................... 23
2.1.3 Electrical aging of solids caused by dielectric HV testing stress ........................................................ 25
2.2 AC HV testing ........................................................................................................................................... 26
2.2.1 General .............................................................................................................................................. 26
2.2.2 Examples of HV test set-ups for HV and UHV GIS ............................................................................ 26
2.2.3 HV conditioning phase and test durations.......................................................................................... 28
2.3 PD measurement on HV GIS ................................................................................................................... 34
2.4 PD measurement on MV and UHV GIS................................................................................................... 37
2.4.1 On-site PD measurement on MV GIS ................................................................................................ 37
2.4.2 On-site PD measurement on UHV GIS .............................................................................................. 39
2.5 LI (OLI) ...................................................................................................................................................... 39
2.5.1 Origin and background about the application of on-site LI (OLI) testing of GIS ................................. 39
2.5.2 LI (OLI) testing equipment ................................................................................................................. 40
2.5.3 LI (OLI) testing procedures ................................................................................................................ 41
2.5.4 LI (OLI) detection sensitivity for different defects ............................................................................... 48
2.6 SI (OSI)...................................................................................................................................................... 48
5
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
6
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
7
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
8
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
9
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure C.3 Example circuit diagram for power supply of a power-frequency test set ......................... 150
Figure C.4 Example of inductance for power compensation dependent on test capacity .................. 151
Figure D.1 Explanation of symbols of case study 1 ............................................................................ 152
Figure D.2 Substation in normal service condition .............................................................................. 153
Figure D.3 Failure on disconnector E04-Q2 ........................................................................................ 153
Figure D.4 Preparation of shut down plan 1 ........................................................................................ 153
Figure D.5 Preparation of shut down plan 2 ........................................................................................ 153
Figure D.6 Preparation of shut down plan 3 ........................................................................................ 154
Figure D.7 Preparation of shut down plan 4 ........................................................................................ 154
Figure D.8 Preparation of shut down plan 5 ........................................................................................ 154
Figure D.9 Preparation of shut down plan 6 ........................................................................................ 155
Figure D.10 Preparation of shut down plan 7 ...................................................................................... 155
Figure D.11 Preparation of shut down plan 8 ...................................................................................... 155
Figure D.12 Preparation of shut down plan 9 ...................................................................................... 156
Figure D.13 Preparation of shut down plan 10 .................................................................................... 156
Figure D.14 Preparation of shut down plan 11 .................................................................................... 156
Figure D.15 Preparation of shut down plan 12 .................................................................................... 156
Figure D.16 Preparation of shut down plan 13 .................................................................................... 157
Figure D.17 Explanation of symbols and colours of case study 2....................................................... 157
Figure D.18 Single line diagram - existing and future bays ................................................................. 157
Figure D.19 Gas pressure and switching positions during extension works at bay D07-BB1 ............ 158
Figure D.20 De-installation of end-modules BB1 ................................................................................ 158
Figure D.21 Installation of new modules BB1 ..................................................................................... 159
Figure D.22 Installation of adapter module BB1.................................................................................. 159
Figure D.23 Installation of new bays connected to BB1 ...................................................................... 159
Figure D.24 After installation of new bays connected to BB1 prepare gas works for installation works
at BB2 .................................................................................................................................................. 160
Figure D.25 Overview after installation of new bays connected to BB1 (phase L1) ........................... 160
Figure D.26 Overview after installation of new bays connected to BB1 (phases L2, L3) ................... 160
Figure D.27 Gas pressure and switching positions during extension works at bay D07-BB2 (phase L1)
............................................................................................................................................................. 161
Figure D.28 Gas pressure and switching positions during extension works at bay D07-BB2 (phases
L2, L3).................................................................................................................................................. 161
Figure D.29 De-installation of end-module BB2 (phase L1)................................................................ 161
Figure D.30 De-installation of end-modules BB2 (phases L2, L3) ...................................................... 162
Figure D.31 Installation of new modules BB2 ..................................................................................... 162
Figure D.32 Installation of adapter modules BB2 ................................................................................ 162
Figure D.33 Installation of new BB modules connected to BB2 .......................................................... 163
Figure D.34 HV test via BB1 - section 1 .............................................................................................. 163
Figure D.35 HV test via BB2 - section 2 .............................................................................................. 163
Figure D.36 HV test via BB1 - section 3 .............................................................................................. 163
Figure D.37 HV test via BB1 - section 4 .............................................................................................. 164
Figure D.38 Installation BB link at BB1 ............................................................................................... 164
Figure D.39 Installation BB link at BB2 ............................................................................................... 164
Figure D.40 Single line diagram (energized) ....................................................................................... 165
Figure E.1 Photos showing HV test set-up for investigation of 'PD calibration' procedures ............... 166
Figure E.2 Electric circuit diagram for investigation of 'PD calibration' procedures ............................ 167
Figure F.1 Staged energisation sequence of GIS ............................................................................... 168
Tables
Table 1.1 Applied test methods - user case examples ......................................................................... 15
Table 1.2 Recommended HV GIS site test voltages ............................................................................. 17
Table 1.3 Overview of recommended site test voltages for MV GIS according to standards ............... 18
Table 1.4 Overview of maximum specified site PD levels ..................................................................... 19
Table 2.1 Relative effectiveness of on-site tests on GIS defects [B1] .................................................. 24
Table 2.2 Example installations of frequency-tuned resonant systems for AC HV tests ...................... 26
Table 2.3 Overview of conditioning and testing procedures for HV GIS [B39] ..................................... 29
Table 2.4 Swiss practice for on-site HV test procedures introduced by third party (reference X1 = [B1])
............................................................................................................................................................... 30
Table 2.5 PD defect type vs. size and charge [B1] ............................................................................... 35
10
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Table 2.6 HV testing practices - number of responses within individual voltage classes (in %) ([B2]
table 6-5)................................................................................................................................................ 40
Table 2.7 Overview of some example calculations with different test capacitances [B57] ................... 42
Table 2.8 Simulation of equivalent circuit for calculation of the front time ............................................ 46
Table 3.2 Drivers for user specifications ............................................................................................... 55
Table 3.3 User requirements and technical standards .......................................................................... 56
Table 3.4 Site HV test voltage generator types for user considerations ............................................... 58
Table 3.5 Examples of user constraints in case of extension or replacement of GIS ........................... 64
Table 3.6 Specific user specifications for site dielectric tests ............................................................... 70
Table 3.7 Examples of special requirements of users for on-site HV test procedures ......................... 71
Table 3.8 User requirements for on-site PD measurement ................................................................... 73
Table 3.9 Testing practices after GIS extension ([B2] table 6-32) ........................................................ 76
Table 3.10 GIS extension - user case examples .................................................................................. 77
Table 4.1 Overview of test section details [B77] ................................................................................. 106
Table 4.2 Return of experience for HV test methods of GIS extensions [B72] ................................... 109
Table 4.3 Return of experience for HV test methods after GIS repair or refurbishment [B22] ........... 110
Table 4.4 User requirements for testing of GIS with attached cables [B66] ....................................... 111
Table 5.1 Example overview of test loads for 'Power VT' [B64] .......................................................... 124
Table A.1 Definition of general terms used in this technical brochure ................................................ 142
Table A.2 Abbreviations used in this technical brochure .................................................................... 142
Table C.1 Example data for calculation for series resonant HV test sets with variable frequency ..... 149
Table E.1 Result overview of investigation of 'PD calibration' procedures ......................................... 167
11
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
1. Introduction
1.1 Scope and chapter structure
On-site high voltage (HV) testing of gas-insulated switchgear is critically important to demonstrate the
dielectric withstand capability of gas-insulated switchgear (GIS) after installation on site. It is also
important to the quality assurance of the switchgear at installation, during commissioning procedures
and after repair too. Each GIS transport unit undergoes routine tests in the factory before being
shipped to site. However, on-site HV and PD tests both within and outside the scope of inter(national)
standards can be important measures to ensure that the GIS remains reliable and available
throughout its service life cycle.
On-site HV testing is applied at the various rated voltage test levels. Different test voltage wave
shapes are applied to detect irregularities in the insulation system and to verify dielectric integrity. The
relative effectiveness of these test methods is assessed for different defects in [B1].
Thorough insulation testing on-site after commissioning, repair or extension, specifically HV AC testing
and PD measurements, provide switchgear condition assessment and important data and results.
Frequently, on-site HV testing of GIS using SF6 or non-SF6 gas mixtures is performed in conjunction
with PD measurements. These data and test results can be used as the baseline to perform insulation
monitoring of the switchgear.
Insulation monitoring on site utilizing PD measurements provides information, which may help to avoid
unforeseen dielectric breakdowns in the switchgear such as those caused by insulator tracking,
insulator defects, contaminants on insulator surfaces including moisture, mobile particles, and loose
mechanical connections.
In most cases, on-site HV testing involves multiple parties that each perform a particular role. The user
and the manufacturer of the GIS are the two obvious parties that are frequently involved in the on-site
HV testing. Either of these parties could provide personnel and other resources (e.g. test equipment)
to perform the HV tests.
In some instances, an independent testing institute, external advisor with specific know-how or an
external service provider, not affiliated with the user or the manufacturer of the GIS, is tasked with
(assistance in the) performing of the HV tests, and support in defining test procedures, space
requirements in the substation for HV tests, acceptance criteria as well as expert’s opinions on
irregularities.
These participants are generally referred to as 'third party' in this and subsequent chapters of this
document. Such third party could take over some or all of the responsibilities of the user or the
manufacturer.
With respect to on-site HV testing in general, information regarding procedures given in (inter)national
standards is also subject to agreement between the manufacturer and the user, especially when
deviating from those standards or when simplified procedures are applied due to technical and/or
practical reasons. The choice of the final test procedure is mainly based on a combination of
requirements in international standards, return of experience and up-to-date quality assurance
concepts to balance the best possible compromise when looking at costs, strategic relevance and
redundancy of the substation, feasibility and defect detection sensitivity.
Chapter 1 introduces the importance of on-site HV testing of GIS. The drivers for HV testing of GIS to
ensure reliability after commissioning, repair, and extension are identified, as well as the importance of
condition assessment. (Inter)national standards and recommended practices for on-site testing of GIS
are reviewed. A description of test repetition after test failure is discussed.
Chapter 2 presents typical diagrams and test procedures describing the test method segments such
as conditioning phase, maximum withstand test voltage, and PD measurement. Moreover, a brief
description of the test equipment, procedures, limitations and preparations for on-site HV testing is
presented including descriptions of AC power-frequency tests, lightning impulse tests, oscillating
switching and lightning impulse tests and partial discharge measurements for medium voltage, high
voltage and ultra-high voltage switchgear.
Chapter 3 focuses on user specification requirements for on-site HV testing including the return of
experience related to the previous CIGRE reliability surveys. The drivers for modifications of
engineering and testing requirements in user specifications for GIS are presented. The importance of
requirements from user specifications with respect to test set-up, space requirements, test
12
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
procedures, documentation and overall site testing is discussed. Case studies that represent sample
on-site HV test arrangements and methods are introduced.
Chapter 4 describes preparatory work before on-site dielectric testing can be performed. The logistics
of the test set-up, test procedures and agreement of test methods with users are discussed. The
chapter also introduces site preparation methods for performance of HV tests such as space
requirements, switching configuration, safety methods etc. The minimum requirements for approval of
test documentation, technical requirements for HV test equipment and qualification of testing
personnel are discussed.
Chapter 5 summarises activities regarding on-site HV tests for GIS after mobilisation to site. The
arrangement of the test set-up including space requirements is presented. The preparation and
installations of the HV test equipment is discussed, as well as conducting and assessing of the tests
themselves. Procedures on how to handle in case irregularities occur are described. Finally, some
specific HV testing situations are described in more detail. This includes the description of all aspects
of HV testing of GIS after repairs or major maintenance of GIS and all aspects of HV testing of GIS for
new extensions to existing GIS. The details of testing and verifying the dielectric integrity of the
extension and connection to the existing GIS will be presented for both; same-to-same OEM
extensions; and OEM extensions by different OEM.
(a)
(b)
Figure 1.1 ‘Bathtub curve’ examples [B3], [B4]
For the evaluation of HV testing, the failures in the beginning of the time scale during time window (A)
in Figure 1.1 part (a) have been excluded, since routine tests as part of the production process will
expose failures commonly named ‘teething faults’.
13
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Part B of the curve in Figure 1.1 part (a) describes the predominant behaviour of GIS during its in-
service life. This time window is therefore the relevant time frame to perform long-term testing and
investigations. This time window will expose ‘random failures’ assuming required
inspections/maintenance are performed on the GIS.
Part C of the curve in Figure 1.1 part (a) describes the end of service life during time frame (C) where
the occurrence of failures is expected to be rising. These are aging failures or loss of functionality.
This has not been typically observed for GIS insulators in service, despite the longer life of the GIS
equipment as compared to AIS equipment.
It is therefore important to maintain a dedicated HV testing program throughout the service life of the
GIS, time frames (B) and (C). This is especially important to analyse trends associated with insulation
degradation. Voltage endurance graphs (life-time curves) describe the relation of the electrical field
strength to time factored with the failure probability as parameter [B3].
Next to the schematic presentation of a ‘bathtub curve’ in Figure 1.1 part (b) some return of
experience from ‘GIS user forum’ (representing approx. 25 German-speaking grid operators) can
express different occurrences of that ‘bathtub curve’, especially towards part C. According to [B4] it
can be relatively easy to draw wrong conclusions regarding failure rates if parameters like
‘manufacturer’, ‘GIS generation’, ‘voltage classes’ aren’t employed carefully.
Undoubtedly, cleanliness and quality assurance procedures for GIS installations have gradually
improved over the past decades. Even the design of GIS is slowly evolving to minimize the risk of
faults during installation or service. For example, horizontal partitions on the lower side of
compartments are more and more relocated to a vertical location, reducing the risk of particles on
these barrier insulators. Sometimes GIS designs are adapted to minimize the amount of intrusive work
that is needed for installation or repairs.
This is however offset by the ongoing efforts to reduce the physical, economical, and ecological
footprint of GIS installations, leading to more critical dielectric designs. Therefore, the permissible error
margins and allowable contamination inside the GIS appears to be continuously decreasing.
So, on one hand one might argue that production quality and successful completion of the FAT would
make (dielectric) testing on-site unnecessary. Indeed, some grid operators, e. g. the Japanese, insist
on rigorous cleanliness and quality control procedures rather than extensive on-site testing,
performing only a short duration ‘soak test’ (application of service voltage for a longer test period than
one minute) after installation. Such quality control procedures include on-site evaluation of
transportation shock recordings, visual inspection of GIS for particles above a defined size, verification
of CB drive characteristics and SF6 gas quality. These quality control procedures may not be feasible
in other applications [B5].
Some international standards give the consideration to limit on-site dielectric testing in situations
where small pre-assembled and pre-tested GIS assemblies are connected on site without major
intrusive work [B7].
It is common for circuit breakers which are opened at site during initial installation to add bushings that
these are not subjected to on-site AC high voltage tests. Also, when removable links are reinstalled at
cable terminations or on VTs or surge arresters, these compartments are often not subjected to typical
on-site AC high voltage tests.
It is not common practice to forego on-site AC high voltage tests for larger pre-assembled and pre-
tested GIS bays, individual modules with switching devices such as disconnectors and grounding
switches, or even VTs with disconnect device modules.
There is a much larger potential cost and projects schedule time trade-off, if an important GIS fails
during initial energisation or reenergisation after extension or repair. The cost of on-site AC high
voltage tests is economical insurance against the damage costs and project schedule time loss
caused by a failure of a GIS at initial energisation or during extension or repair. The total damage
costs, consisting of repair cost combined with the potential loss of revenue and penalties for the GIS
user, could be a significant part of the acquisition cost of the GIS and even exceed it in the worst-case
situation.
Also, relaxing (reducing) the test voltage may allow undetected PD, which can cause failure days to
years later. Internal particles may continue to move and potentially reach more critical dielectric areas
of the GIS until they cause a problem or broken internal components will discharge until they cause a
flashover. This may cause the GIS to fail prematurely.
14
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
On the other hand, as soon as the GIS assemblies leave the factory, many factors play a role that are
outside the control of the manufacturer or the user:
• Transportation damages. The installation of shock recorders can identify possible
transportation damages, but it may often not be feasible to install a shock recorder on every
transportation unit,
• Handling and installation of GIS parts on site. This is often performed by third party workers
with supervision from one representative of the manufacturer,
• Site conditions. These are very often disadvantageous if compared to factory assembly
conditions,
• Site gas handling. Erection units are transported from factory to site at reduced gas pressure
or with a different gas than the insulation gas, requiring some gas handling works.
If extension or repair works need to be performed on site - which in many cases involves intrusive
work over a prolonged period being performed on the GIS installation (see e.g. [B8]). The age of
different parts of the GIS installation may differ greatly in such a scenario. In some cases, parts of
different GIS manufacturers are involved.
If a failure occurs after installation, extension, or repair once the GIS is placed into service, significant
damages will likely occur inside the GIS installation. If critical components are damaged, or a full or
partial disassembly is required to replace damaged parts, the MTTR (mean time to restoration) could
be greater than one month.
However, a return of experience from a German distribution system operator with around 330
substations in the HV and MV range has shown only a very small number of major failures (including
power arcs) over the last decades. It was also observed that the reasons were mainly mechanical or
human irregularities, rather than dielectric weaknesses of the equipment [B9].
Therefore, in such cases, performing a dielectric HV test after the on-site installation works is highly
recommended.
However, the application of the different test methods can vary. An overview is given in Table 1.1 to
display some of the different approaches contributed to the Working Group.
See Chapter 3 for further details of user practices collected by the Working Group.
Table 1.1 Applied test methods - user case examples
No (or seldom) reduction of the test voltage levels for on-site testing compared to factory tests, not [B9]
even after retrofit or repairs
‘Soak test’ with reduced grid topology and modified protection settings after small intrusive [B10]
reparations (e.g. repair of gas leaks); in case of a flashover, the affected location needs to be
localized, repaired, and retested
On-site tests at 100 %-value of the factory tests; for rated voltages of 550 kV and above, at least at [B11]
90 %-value of the factory test is prescribed
On-site tests at 80 %-value of the factory tests; 65 %-value of the factory tests for 120 s if [B13]
extensions of existing GIS are tested
With rigorous quality controls during production, transportation, and assembly, a ‘soak test’ is [B5]
deemed sufficient
15
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
16
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
• If it is possible to perform a PD test and if agreed between user and OEM, then the guidelines
given in cl.11.102.2.6 should be applied wherever possible.
Below table gives a summary of the recommended HV GIS test voltages for the standards reviewed in
this chapter.
Table 1.2 Recommended HV GIS site test voltages
Method Value IEC 62271-203 IEEE C37.122 GOST R 54828 GB/T JEC
As summarised in Table 7.1 of [B14] the differences can be explained by the testing philosophies
applied in IEC and the IEEE standards. The voltage waveforms such as power-frequency, lightning
impulse and switching impulse are specified depending on the defect types and on the rated voltage of
GIS in IEC and IEEE.
1.3.1.2 Standard requirements for MV GIS
According to IEC [B15] for parts which have undergone a routine test and been erected on site or gas
compartments which have been filled on site - the following have to be considered:
• test voltage level of 80 % of routine test voltage level,
• no PD measurement foreseen.
In case the on-site HV test replace the routine test, the on-site AC test voltage level shall be 100 % of
the routine AC test voltage level, corresponding to 125 % of the values in Table 1.3 below.
17
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
A PD measurement is mentioned only in connection with the routine test in the factory and treated
there as the subject of an agreement between OEM and user - i.e. considered optional. The following
values are given there as limits for PD levels during factory testing (testing each phase individually)
after pre-stressing with the routine test voltage:
• for solid insulation ≤ 20 pC at 1.1xUr/√3 phase-to-ground,
• for non-rigidly grounded systems ≤ 100 pC at 1.1xUr phase-to-ground.
Further recommendations and return of experiences are given in Chapter 2.4.1.
According to IEEE [B16], [B17] on-site power-frequency withstand voltage tests shall not be performed
at more than 75 % of the ACWV-level, which results in the values in Table 1.3 below. For voltage
levels of 15 kV and below, as a reference value also the permissible on-site DC test voltage for
connected power cables is given. This value is identical to the peak value of the corresponding on-site
ACWV-level.
IEEE does not recommend or prescribe to use DC test voltages for on-site testing of the GIS itself.
The maximum permissible partial discharge level at 1.2xUr and/or 1.2xUr/√3 is 100 pC.
According to DL/T [B18] the test requirements of IEC 62271-1 are modified specifically for the Chinese
market.
Table 1.3 below lists the recommended on-site voltages from the standard, which are 80 % of the
recommended factory test voltages Ud, unless no dielectric tests have been performed at the factory,
in which case the on-site test voltage shall be 100 % of Ud, corresponding to 125 % of the values from
Table 1.3.
Table 1.3 Overview of recommended site test voltages for MV GIS according to standards
3.6 8 9.6 v
4.76 14 - v
7.2 16 18.4 v
8.25 27 - v
12 22.4 25.6 v
15 27 - v
17.5 30.4 36 v
24 40 48 v
27 45 - v
36 56 64 v
38 60 - v
18
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
48 78 - v
52 76 88 v
52 90 - v
Table notes:
1. A tick (v) indicates which of the reviewed standards recommends the specified test voltages
2. Rated voltage of GIS under test
3. Recommended test voltages between phases and between phase and earth
4. Recommended test voltages across safety isolating distances; values between brackets are applicable for solidly earthed
systems
General note: In case no factory dielectric tests have been performed, IEC and DL/T recommended site test voltages are 125 % of the
given values (=100 % of Ud)
The MV GIS standards considered in this section recognize that PD testing is a useful addition to the
high voltage tests, but that it is difficult to determine a reliable relationship between measured PD
quantities and the failure probability of a MV GIS. Therefore, PD tests are not mandatory, but subject
to agreement between user, manufacturer and third party if applicable.
The various return of experiences for PD pre-stress voltages, PD test voltages and PD measurement
duration are summarised in below table:
Table 1.4 Overview of maximum specified site PD levels
generic 100 per bay 1) Ud 1.2xUr/√3 >1 min. [B16] cl. C.6
19
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
20
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
21
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
determining a more precise location of the failure. It is however possible that the discharge energy
during on-site testing will not produce enough decomposition products for detection.
The other standards which are considered in this chapter give either no recommendations for
repetitions of on-site testing in the case of a flashover, or in the case of GB/T give the exact same
recommendations as IEC 62271-203 Annex C.6.2 described above.
1.3.2.2 Repetition procedures after disruptive discharges during HV testing
according to return of experience
The following text provides some introductory collection of practical information concerning the applied
repetition procedures after disruptive discharges during on-site HV testing activities, with a focus on
HV GIS and the application of an AC voltage waveform as test voltage. Generally, these events can
occur in the conditioning phase, or during the HV withstand voltage test itself. Typically, the finally
applied test procedures are agreed by both OEM, user and third party (if applicable) in advance.
WG members return of experience
For the situation of an on-site HV test after repair, it was found helpful to increase the reliability of the
repaired HV GIS module by locating any flashover and inspect the affected GIS module to define the
next working activity (e.g. continue HV testing, further repair). Thereafter, a repetition of the same HV
testing procedure commences [B10].
Sometimes, also no specific information regarding re-testing of equipment after a disruptive discharge
during the on-site HV testing have been addressed [B22].
In relatively rare situations with on-site HV testing on UHV GIS, often no flashovers at all are allowed.
In case of any disruptive discharge an examination for finding the root cause is a prerequisite for a
repetition of the test procedure. Typically, further HV test voltage applications or even conditioning
phases are necessary to help determine the discharge location [B11].
Moreover, when a disruptive discharge already occurs during the conditioning phase, focusing on the
readings of simultaneous PD measurement and lower voltage rate of rise during a second conditioning
phase may be helpful to detect the nature and origin of a further disruptive discharge, which may
occur during the second conditioning phase [B23], [B24].
If a disruptive discharge occurs during the HV withstand voltage test, the HV withstand test needs to
be repeated, unless unambiguous assessment for a flashover along the surface of a solid can be
made. Additionally in such case, it can be helpful to repeat also the preceding conditioning phase. In
case of uncertainty regarding the flashover location, first a repetition of the HV withstand voltage test
without prior GIS opening is proposed. For the scenario of a second disruptive discharge taking place,
and locating measures indicate the same zone as the previous discharge, the affected GIS module
needs to be opened for inspection and repair [B23], [B24].
Occasionally, optional testing activities after the original HV withstand voltage test are also considered
helpful. These often depend on numerous factors and are not always applicable. With regard to further
testing at rated frequency and rated voltage can reveal correctness of re-installations of disconnected
(temporarily for on-site HV testing) VTs, surge arresters (SA) and/or cables [B23], [B24].
Additionally, in situations applying LI withstand voltage tests on site after a disruptive discharge, or
already after significant deviations are noticeable between the different lightning impulses, an
additional sequence of lightning impulses (e.g. 10 impulses) of the same polarity can be applied to
verify dielectric integrity of the GIS section under test. Any further flashover as before triggers the
affected GIS module to be opened for inspection and repair. Afterwards, a repetition of the complete
test procedure including AC withstand voltage test and LI withstand test commences. Further
significant deviations in LI waveshape during the additional sequence may also indicate a problem in
the GIS and opening the GIS module for inspection and repairs must be considered [B23], [B24].
Finally, the return of experience also advises to focus on locating flashovers to those GIS sections
with assemblies of interfaces between GIS and HV testing equipment [B23], [B24].
Specifically, for MV GIS an elaborated return of experience is given in Chapter 2.4.1.
22
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
23
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Important information for the selection of a suitable test procedure can be gained from Table 2.1
below.
Table 2.1 Relative effectiveness of on-site tests on GIS defects [B1]
In Table 2.1 AC voltage tests are further distinguished between 'High AC' and 'Low AC'. 'Low AC' is
defined as 'low-voltage AC dielectric tests' with service voltage. 'High AC' is defined as 'high voltage
AC dielectric tests' with an applied voltage of 80 % of the power-frequency withstand voltage level. For
detailed definition see [B1]. The voltage level for PD measurement is defined as 80 % of 'High AC',
which is close to the IEC values for three-phase encapsulated HV GIS. Aspects relating 'effectiveness
of test methods' were already addressed a few years earlier in [B26] which constitute a preliminary
version of the work of CIGRE JWG 33/23.12. However, other references like [B27], [B28] have
elaborated also on the effectiveness of different on-site HV test methods with generally similar
conclusions as shown in Table 2.1.
Therefore, general major findings can be summarised as follow:
• AC HV tests show (only) reliable results in detecting free-moving particles,
• LI (OLI) tests are a very effective procedure to exclude (or show) the existence of particles on
spacers and protrusions on live parts,
• PD measurements are suitable options to indicate floating electrodes/parts, defects in
insulating spacers as well as free-moving particles,
• The combination of a high AC voltage test with PD measurement offers the most
comprehensive method in a single test set-up.
Although the two defect types 'protrusion' and 'particle on spacer' can pass the AC one-minute test
voltage undetected because of ‘corona stabilization’ [B29], they can both fail in the lightning impulse
test. The effect of corona stabilization at power-frequency voltage is illustrated below in Figure 2.1.
Additional details on this effect can be found in [B30]. Positive ions drift by electrical field forces
towards the cathode of the electrode configuration which result in a positive space charge located in
area b). So the critical gas volume in the direct vicinity of the protrusion tip in area a) gets limited to
develop further gaseous conditions for gas discharges.
Figure 2.1 Influence of space charge on electrical field distribution of defect type 'protrusion' [B29]
24
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Due to relatively slow electric field variation of the power-frequency voltage, space charge can build up
in front of a protrusion, and thus reduce the maximal electric field. The protrusion attains a quasi shield
built of space charge and the breakdown voltage of such an arrangement increases. However, if a
much faster electric field variation is applied – for example a lightning impulse or a very fast transient
caused by switching operations – the space charge does not have enough time to develop, and the
breakdown voltage of the same arrangement is significantly lower compared to AC voltage stresses.
The voltage-time curves for a clean GIS installation and an installation with protrusion in Figure 2.2
below shows this effect in detail.
25
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
different standards of the corresponding generations may be considered, and some examples are
presented in Chapter 3 and Chapter 4.
2.2 AC HV testing
2.2.1 General
Nowadays, on-site HV testing with AC is by far the most often applied test method on GIS, if dielectric
testing of the main insulation system is intended. This test method is basically applicable to MV, HV
and UHV GIS, also shown in [B2]. Initially, test transformers providing power-frequency HV were used,
but size and weight as well as technical limitations concerning feeding power capacities made the use
of these equipment more difficult with higher efforts, especially for GIS with voltage ratings above
170 kV. To overcome these disadvantages, nowadays compact and comparatively lightweight ‘test
voltage generators’ consisting of several separate apparatus serving as variable resonant reactor for
constant frequency or as constant resonant reactor with variable frequencies up to 300 Hz are used
[B33]. One current method using a frequency-tuned series resonance circuit for HV testing was initially
proposed and presented back in 1979, allowing to test HV apparatus with very large capacitances with
up to the highest test voltages [B34]. Since then, optimizations have been made mostly in the
automation and the power electronics of the used frequency converters.
Generally, frequency-tuned resonant test systems have a better weight-to-power ratio compared to
inductance-tuned systems [B27], but both systems are commonly used with regional popularities
worldwide.
In the case of limited space conditions, e.g. underground HV substations, metal-enclosed test voltage
generators are favourable to allow small clearances. Other aspects like dimensions, weights,
movability and handling, and optimisation for outage / safety isolation zones are also important. In
some cases, it is of interest to limit the time involved for completing an on-site HV test. Also, regarding
accompanying PD measurements (especially for conventional PD measurements) noise interference
is significantly lower applying metal-enclosed test voltage generators which are directly connected at
an applicable flange of the GIS under test.
On-site AC HV tests during GIS commissioning are sometimes also conducted by the application of
the service voltage for a longer test period than 1 minute. Often, this procedure is named ‘soak test’,
and references to the varying test durations can be found in Table 3.5.
2.2.2 Examples of HV test set-ups for HV and UHV GIS
Example installations of frequency-tuned resonant systems for AC HV tests are shown below in Table
2.2.
Table 2.2 Example installations of frequency-tuned resonant systems for AC HV tests
Photographs Reference
[B35]
26
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Photographs Reference
[B36]
[B24]
HV test equipment owned by user for on-site HV testing of GIS after installation
[B24]
HV test equipment owned by user for on-site HV testing of GIS after repair
The following Figure 2.3 shows an example of a test voltage generator for on-site HV testing of
underground substations up to 550 kV GIS [B37]. The physical dimensions are 4.9 meters long, 1.9
meters wide and 3.5 meters high with a total weight of about 7.8 tons. The figure also shows modules
(grey colour) to facilitate the connection of the HV test set to the HV GIS under test. The provided
reactive testing power can also allow for a certain capacitance under test, such that a complete HV
substation can be tested 'in one run' (e.g. 7 bays of 500 kV GIS, 15 bays of 220 kV GIS). However,
27
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
this approach can have some disadvantages (e.g. fault localisation, occurrence probability of
secondary flashovers, etc.), but can be considered as beneficial in case of 'running HV testing' without
any issues [B37].
28
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 2.5 Typical procedure for AC voltage conditioning and testing [B33]
A long-term experience of one OEM with HV testing of HV GIS results in the following voltage time
diagram in Figure 2.6.
Figure 2.6 Voltage time diagram for HV GIS with Ur = 245 kV [B39]
The graph shows a combination of two conditioning phases of 10 minutes duration each, followed
uninterrupted by the HV test at Uds and PD measurement. For other rated voltage levels of HV GIS,
typically the voltage time combinations according to Table 2.3 are applied [B39].
Table 2.3 Overview of conditioning and testing procedures for HV GIS [B39]
29
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Also, a well-established procedure with PD measurement at higher test voltage levels applied in
Switzerland with longer measurement duration is shown below.
Table 2.4 Swiss practice for on-site HV test procedures introduced by third party (reference X1 = [B1])
The voltage level of the PD measurement (indicated in red) is close to the value recommended in the
[B1], and is derived from the values of testing three-phase encapsulated GIS as described in [B7]. The
return of experience has shown a good defect elimination capability when following the
recommendation of [B1] by performing the PD measurement at roughly 80 % of the withstand voltage
test level on site to reach the PD inception voltage of certain critical defects. With a PD measurement
duration of at least 30 minutes also PD defects with inception delay or defects with intermittent
behaviour are detected well.
In return of experience from the Netherlands, for on-site commissioning tests of 245 kV GIS or higher,
the sequence is shown in Figure 2.7. For on-site HV testing a test duration of 1 minute at a test
voltage level of Uds is generally synonymous with the pre-stress voltage for the PD test. Therefore,
this graph is like the graphs used during the routine test, but deviations may exist.
Figure 2.7 Actual test procedure of OEM B for an extension of a 245 kV GIS of OEM A in The Netherlands
in 2013
The sequence shows a gradual increase up to the conditioning phase, during which the test voltage is
0.8xUds. The duration and voltage level of the conditioning phase is determined by the manufacturer
based on the design of the switchgear. After the conditioning phase, the voltage can be gradually
increased to the full test voltage Uds.
30
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
As soon as Uds is reached, this voltage is maintained for 1 minute, and if no flashover occurs, it is
gradually decreased to the PD test voltage. The test voltage Uds also serves as the pre-stress voltage
for the PD measurement. Therefore, it is critical that when reducing the test voltage, it does not drop
below the PD test voltage level, as this might extinguish PD activity and would invalidate the test.
The following diagram refers to applications in China and shows a combination of conditioning and
testing phase. In this case the test voltage values are based on a rated voltage of 550 kV [B38], [B37].
Figure 2.8 Procedure for HV withstand test of 550 kV GIS voltage in China [B38], [B37]
In case of on-site HV testing of UHV GIS special consideration is paid to the conditioning phase due
the fact that these types of GIS usually are a very important node in the transmission network.
Nevertheless, PD measurements - in this case by means of ultrasound detectors (detection frequency
range from 20 kHz to 100 kHz) - are not applied during the conditioning phase and in the HV testing
phase due to safety (test operator and diagnostic equipment) reasons.
The PD measurement phase is performed directly after voltage decrease from the HV test voltage
level. Figure 2.9 shows an example of an acoustic PD measurement conducted with the realization of
frequent measuring points. Here the sensor is attached to the GIS enclosure and typically the
amplitude of acoustic emission signal should be less than 5 dB with no obvious phase correlation to
50 Hz and 100 Hz [B38]. This represents a very special type of ‘PD analysis’ based on user
experience and is for technical information only rather than for a precise PD determination.
Figure 2.9 AC withstand voltage and PD test procedure for 1100 kV GIS in China [B38]
Examples of specific HV conditioning phases including withstand test
This first example case study of an OEM from Switzerland describes how to differentiate between
'conditioning' and 'testing', especially in case of load cycle limitations of the used test transformer
[B40].
Usually during 50 Hz / 60 Hz tests the voltage transformers of a GIS are disconnected or dismantled.
The following Figure 2.10 displays an example for a scenario where the VTs are not part of the test
set-up during the conditioning phase as well as the HV test sequence. This specific procedure is
especially applicable in case of using a test transformer providing power-frequency HV. It becomes
obvious when calculating possible load cycles of the test transformer that a feasible test sequence
could speed up the total testing time and allow to meet the duty cycle parameter of the test voltage
generator.
31
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
An example (assumption) GIS substation consisting of 12 testing sections, comprising 10 bays and 2
busbars in a double busbar arrangement (three-phase encapsulated design), consisting of 9 bays
cable feeders and 1 bay coupling bay with no bus sectionaliser is taken to illustrate the impact of the
chosen procedure on the total test duration with approximate values given.
• Option 1 - directly after the conditioning phase the HV test including PD measurement will be
performed (so every GIS test section will be subjected according to the possible procedure):
o total duration for a complete cycle for one phase of one GIS test section = 14.5
minutes
(0.5 minutes (voltage rise) + 5 minutes conditioning phase 1 + 0.5 minutes (voltage
rise) + 5 minutes conditioning phase 2 + 0.5 minutes (voltage rise) + 1 minute (HV
test) + 0.5 minutes (voltage decrease) + 1 minute (PD measurement) + 0.5 minutes
(voltage decrease))
o total duration for a complete cycle for three phases of 12 GIS test section = (14.5 x 12
x 3) minutes = 522 minutes (equals to 8.7 hours)
o caution: time for data recording, changing switching conditions and calibration for PD
measurement is not included in this example calculation
o comment: it might be challenging to locate a possible disruptive discharge, although
diagnostic equipment for locating purposes especially on metal-enclosed GIS exists
(e.g. ultrasound, light)
• Option 2 - conduct the conditioning phase of 12 bays first and subsequently followed by the
HV test including PD measurements for:
o total duration for the conditioning phase of the first part of the substation for three
phases (1 busbar + 5 bays) = (11.5 x 3) minutes = 34.5 minutes
(0.5 minutes (voltage rise) + 5 minutes conditioning phase 1 + 0.5 minutes (voltage
rise) + 5 minutes conditioning phase 2 + 0.5 minutes (voltage decrease))
o total duration for the conditioning phase of the second part of the substation for three
phases (1 busbar + 5 bays) = (11.5 x 3) minutes = 34.5 minutes
(0.5 minutes (voltage rise) + 5 minutes conditioning phase 1 + 0.5 minutes (voltage
rise) + 5 minutes conditioning phase 2 + 0.5 minutes (voltage decrease))
o total duration for HV test including PD measurement for 12 test section and three
phases = (3.5 x 12 x 3) minutes = 126 minutes
(0.5 minutes (voltage rise) + 1 minute (HV test) + 0.5 minutes (voltage decrease) + 1
minute (PD measurement) + 0.5 minutes (voltage decrease))
o total duration for 'conditioning' and 'testing' = (34.5 + 34.5 + 126) minutes = 195
minutes (equals to 3.25 hours)
o caution: time for data recording, changing switching conditions and calibration for PD
measurement is not included in this example calculation
32
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
OEM examples contain a lot of variations for the conditioning phase. The 'minimum conditioning time'
can range from 0 minutes to 15 minutes in these examples, and also a 'minimum time for PD
detection' can range from '≥ 1 minute' to 30 minutes. In the end this led to one user specifying the
requirement of a '5 step sequence' for the on-site test procedure to bring about consistency, or
standardisation of the test sequence across the GIS fleet of the same rated voltage but with GIS from
different OEM's being installed. Figure 2.11 shows a scenario for a 245 kV GIS with defined time
durations for the conditioning phase and PD measurement.
As shown in the users diagram the PD measurement is initially carried out at 1.2xUr according to
table 6 in [B7] (see also Table 3.7), but with an extended test duration of 5 minutes specified, followed
by a longer test duration of 20 minutes at 1.1xUr with potential extension up to 60 minutes. The total
test duration including preconditioning and PD measurement is therefore a minimum of 36 minutes
and may extend to 76 minutes in the event of any phase-correlated PD activity being observed during
the initial PD measurement periods.
While 'PD free' is the ultimate goal to be obtained, this may not always be easily achieved, depending
on the configuration of the installation and GIS design, however the acceptance criteria of 10 pC per
IEC may be too high a threshold for certain GIS installations of particular design or criticality to the
user. At the end of the initial 20 minute duration at 1.1xUr the decision to extend the PD monitoring
period for a further 40 minutes must be made in the case that detectable phase-resolved PD has been
observed for any consistent period throughout the 5 minute 1.2xUr or 20 minute 1.1xUr periods.
Should a pattern of incidences, such as flashovers or PD events be observed this gives clear
indication to both the OEM and the user that additional quality measures may be required and trigger
intervention such as investigation or cleaning of untested compartments. The principle of the extended
PD measurement duration according to the user specification is also to establish a suitable long
duration baseline, or initial fingerprint of the installation where continuous online PD monitoring
systems may be deployed.
Short snapshots of the GIS behaviour may be considered insufficient to baseline against continuous
monitoring systems that may be active during the initial period after placing into service. This initial
period after placing into service is considered the most critical point at which defects could become
apparent and PD measurement during the on-site testing phase was considered an enhancement by
the user in these cases.
It is acknowledged that this special case test procedure would most likely be applied to GIS of new or
unfamiliar design to the user for which they may not have suitable in-service experience at the time of
contract placement. GIS with suitable in-service experience as considered by the user may then
deviate more in line with the OEM's own test procedure on agreement with the user. Due to the
potential extended test durations the choice of test voltage generator to be used must be considered
by the user and parties responsible for designing the building or enclosure around the GIS and those
carrying out the on-site testing [B41].
The lower 1.1xUr specification value is also found in other user specifications from China to facilitate
the connection and testing of voltage transformers and surge arresters that may otherwise be
excluded from the conventional HV on-site testing [B38].
Figure 2.11 Example 2: Conditioning phase and HV test sequence for 245 kV GIS [B41]
In conclusion, no clear recommendation for any procedure can be given, since all the examples are
based on very individual circumstances and experiences. As mentioned above, the conditioning
procedure is not part of any required standard test and is no test by itself. Since the procedure is
33
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
mainly based on experiences made by the corresponding OEM, it is the OEM's responsibility to
conduct the conditioning phase appropriately. The only recommendation for users, who need full
information about conditioning procedures, is to get in discussion with suppliers as well as testing
personnel early enough in advance of any planned HV / PD tests.
34
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
The report of the CIGRE JWG 33/23.12 deals with the insulation co-ordination of GIS and the return of
experience concerning on site tests and diagnostic techniques [B1] and states the critical dimensions
and accompanying PD levels as given in Table 2.5.
Table 2.5 PD defect type vs. size and charge [B1]
Considering PD levels of protrusions and particle on insulation material with critical length, the low PD
level of 0.5 pC…2 pC can be a challenge on site. Often a 5 pC acceptance level is applied, and noise
levels of less than 0.5 pC for proper defect identification are difficult to achieve for the conventional PD
measurement. For these PD defect types it can be possible to achieve higher signal-to-noise ratios
when applying a highly sensitive UHF PD measurement method.
Partial discharges in cavities of electrical insulation (shrinkage cavities within the solid insulation
occurred during the casting process, delamination of electrodes, cracks due to incorrect mechanical
stress, etc.) can exhibit a statistical PD inception delay of more than 15 minutes [B44]. Concerning the
dimensions of these kind of defects, a spherical cavity having a diameter of 0.7 mm is already
considered large. Currently, research is being conducted on the detection of cavities without PD
inception delay by means of pulsed X-ray radiation [B46]. Cavities having diameter down to 0.3 mm
can be detected under certain circumstances. Some OEM have implemented the detection of cavities
in insulating materials by means of pulsed X-ray radiation at the incoming goods inspection of
insulators.
Nevertheless, due to the statistical PD inception delay of certain cavity sizes, it can be helpful in some
cases to extend the PD measurement duration to longer periods than 1 minute. Therefore, general
test set-ups and schedules can be favourable when enabling testing scenarios with testing durations
of generally up to 5 minutes or even longer. When using multiple UHF sensors, sequential connection
of single UHF sensors to spectrum analysers or portable UHF PD measuring equipment with fixed
(limited) numbers of measuring channels need to take place, the duration of the PD test may also be
extended. Load cycle requirements of the used test voltage generator may also have a limiting effect
for the test duration as well. For investigation and localization of a PD defect, test voltage generators
with sufficient thermal capacity are advantageous.
However, when no PD signals above noise level are detected at all, and a return of experience is also
given on the timely evolvement of progressive PD defect signals for the corresponding GIS design
under test, PD measurement durations clearly longer than 1 minute are not applied in certain current
user practices in some regions [B47].
Considering the effect of statistical PD inception delay (e.g. voids (cavities) or temporary PD extinction
(e.g. particle / contamination on insulation)) of certain PD defects, also longer PD measuring times in
the range of 30 minutes or more can be helpful for the PD detection and may have positive effects on
the removal of these PD defects.
Generally, in case of PD detection at the specified PD test level, the applied AC test set-up should
have corresponding thermal capabilities for comprehensive PD characterization and localization (e.g.
time-of-flight measurement) so that efficient testing is possible.
Because PD measurement is a non-destructive test method and applied in conjunction with the AC
voltage test (resulting in a single test sequence), this test combination is widely applied on site.
However, radio interference signals, large testing sections on site and the technique used for HV
injection (e.g. gas-insulated or air-insulated) can result in unfavourable noise signals for conventional
PD measurement. Often, interface modules of the HV GIS (e.g. bushing, cable) are sensitive to these
interference signals. Also, the location of the substation itself may have an influencing effect on the
35
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
noise level (e.g. in industrial / urban areas the occurrence of higher PD ground levels can result from
adjacent machines, engines, airports, cell antenna sites, etc.).
Since the introduction of the UHF PD measurement method in the late 1980s [B49], it has become
widely accepted and applicable for sensitive on-site PD measurement on HV GIS due to the high
detection sensitivity and good signal-to-noise ratio (SNR) which can be achieved.
Figure 2.13 below illustrates the signal processing of narrow-band UHF PD measurement.
Figure 2.13 Broad-band scanning narrow-band UHF PD measurement – illustration of signal processing
[B43]
At the place of origin, PD signals in SF6 show bandwidth past 10 GHz [B42]. Radio frequency PD
sensors in flanges of the enclosure act as antenna to pick up PD signals typically in the frequency
range of 0.1 - 2 GHz. To achieve a good SNR, broadband amplifiers are used with up to 50 dB
amplification. A spectrum analyser allows to observe PD signals in the broadband spectrum
presentation, and in case of PD signal activity to provide a down-converted PD signal for accumulation
of a phase-resolved PD pattern (e.g. 'finger-print') with a conventional PD measurement device. Often,
a multiplexer is applied to connect all PD sensors involved in the test section to the measuring device.
A great advantage of this method is the possibility to provide sensitive measurements even with high
level of disturbances due to the possibility to select a noise free frequency band containing PD activity.
More detailed description (see [B43]).
Figure 2.14 below illustrates the signal processing of the broad-band UHF-PD measurement.
Figure 2.14 Fixed broad-band UHF PD measurement – illustration of signal processing [B43]
This method is widely applied for online PD monitoring systems due to the low costs of the simple
front end and the low system complexity. The system consists typically of broad-band receivers
operating in fixed frequency bands. It is possible to make automatic simultaneous measurements on
tens or hundreds of UHF PD sensors. The signal is directly down-converted (e.g. using an envelope /
power detector) to base-band, from where a phase-resolved PD Pattern is generated [B43].
Since in practice the exact location of a PD source and therefore the signal transmission path to the
measuring sensor is unknown, no direct relationship between the received radio frequency (RF) signal
amplitude and the charge value of the PD source is existing. Even a calibration to the ‘apparent
charge’, as defined in IEC 60270, is not possible [B50].
However, this drawback can be considered over-compensated by the fact that RF interferences in the
UHF range can be often lower and so significantly easier to handle than in the measurement
bandwidth of the conventional PD measurement method, particularly on site. Another significant
advantage of measuring signals in the UHF range is the possibility to precisely determine the location
of the PD source to within a few centimetres by means of time-of-flight measurements [B51].
36
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Sometimes, the impact of extended testing sections and therefore different capacitances of the section
under test on the amplitude of conventional PD measurement signals are considered detrimental to
the calibration procedure. In APPENDIX E further information on this detail is given.
Example PD signals for ‘particle on insulation’ on a horizontal insulator of a VT are shown in Figure
2.15. For comparison, the PD signal has been measured simultaneously with both the UHF
narrowband and IEC 60270 methods [B43].
Figure 2.15 Comparison of PD signal between measured by UHF narrow-band and IEC method (2 mm
particle on insulation of a VT measured at 230 kV, conforms to 100 % ACWV) [B43]
Figure 2.15 show that for this specific PD defect the SNR of the UHF measurement can be
significantly higher than the SNR reached with the conventional PD measurement. The conventional
PD amplitude of approximately 0.5 pC is hardly recognizable above the noise level, whereas the UHF
method delivered a clear and interpretable PRPD pattern.
Often, in the practical application of the factory test also PD defects below the agreed PD acceptance
level are investigated and removed. Some OEM have also started to integrate UHF measurement
results into the PD test result evaluation of the conventional PD measurement with the goal to further
reduce the probability for occurrence of critical PD defects.
Beyond the applied factory PD testing procedure, the return of experience sometimes shows that
during on-site PD testing unacceptable PD signals can occur in GIS modules already at a test voltage
level significantly lower than the rated voltage. A corresponding case study revealed that a
disconnector / earthing switch was affected. Despite a thorough inspection and cleaning of the
affected gas compartment, during re-testing the PD signal appeared again. Therefore, the
disconnector / earthing switch gas compartment was removed from the installation to undergo an
inspection in the OEM laboratory. Through extensive troubleshooting, a process of eliminating
possible fault locations and consultation with the OEM, it was found out that a bolted connection of the
contact on the partition was the PD source. After cleaning and re-torquing of the bolted contact, the
disconnector / earthing switch gas compartment was re-installed, and during a further PD re-test no
PD activity was registered. This case study demonstrates the importance of in-depth inspection of a
compartment in case of too high PD signals - compared to the agreement between user / OEM / third
party made in advance of the test - during on-site testing [B52].
37
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
38
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
PD measurements, and deterioration of solids (e.g. 'electrical treeing') can be neglected for
acceptance PD levels < 20 pC for common test durations [B19], [B53].
2.4.2 On-site PD measurement on UHV GIS
The intention of the Working Group was to provide a kind of complete overview of on-site HV testing
on GIS, ranging from MV to UHV. Unfortunately, the return of experience in case of PD measurements
on UHV GIS is limited [B12]. So, the following practical example (Ur = 1100 kV) elaborates the
common practice for on-site HV testing in conjunction with PD measurement on UHV GIS in China
[B11], [B38].
Generally, user specifications for PD measurements in conjunction with on-site HV testing of UHV GIS
describe the applicability / requirement of non-conventional PD measurement techniques by
electromagnetic and acoustic methods. In this voltage range this kind of dielectric test constitutes a
major challenge with regard to external interference signals. In case of acoustic PD measurements on
1100 kV GIS in China the attachment of ultrasonic sensors to the GIS enclosure starts after
(successful) completion of the AC test and the subsequent voltage decrease to the PD test voltage
value (see also Chapter 2.2.2). The following figure displays some information on PD signals detected
and recorded during an on-site HV test. The upper part of the figure refers to electro-magnetic PD
measurements, and the lower part of the figure is related to acoustic PD measurements.
2.5 LI (OLI)
2.5.1 Origin and background about the application of on-site LI (OLI) testing of GIS
Today on-site HV testing with lightning impulse (LI), or oscillating lightning impulse (OLI) is applied for
many operating voltage levels a lot less than on-site HV testing with AC. That has been already earlier
evaluated [B2] and has been recalled in Table 2.6.
Furthermore, it has been stated, that the case of LI (OLI) application seems to be related to the
importance of the substation in the network, especially when the operating voltage level is higher.
39
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Table 2.6 HV testing practices - number of responses within individual voltage classes (in %)
([B2] table 6-5)
While this review of the application of on-site LI (OLI) HV testing is to date still describing the current
practice or state of the art resp., also older references are still presenting valid reasons for the
application of LI voltage as well as differentiations for not applying them [B26].
Technically, it is a well-established fact that LI test voltages are sensitive to possible defects of GIS,
which are 'protrusion on HV conductor' and 'particle on solid insulation'. Both types of defects may
also be detectable by PD measurements, but obviously the PD detection sensitivity can be different to
that of LI test voltage application. This was shown also in Table 3 in [B1]. Regarding the LI voltage
waveshape the requirements compared to that of type testing procedures are modified in terms of
front times, as especially for HV and UHV GIS travel time effects of electro-magnetic waves can cause
multiple reflections within extended GIS structures resulting in different voltage values along the tested
GIS section. This phenomenon can be moderated by allowing longer front times compared to type
testing protocols.
Nevertheless, investigations regarding effectiveness of longer front times of LI voltages to detect
specific kind of defects within a GIS are still ongoing. Also, an increase of the test voltage level of the
LI voltage waveshape is proposed to kind of compensate some effects [B54]. Concluding the work in
this reference it must be emphasized, that often investigations have been performed in laboratory test
set-ups, so that circumstances during situations of on-site LI testing may be different.
Also, the work of [B55] concludes with some results concerning the effectiveness of different test
methods in a laboratory test set-up.
But to date there is no evidence that increasing test voltage levels towards the test voltage levels of
type testing procedures increases the risk, that in case of disruptive discharges very fast transient
overvoltage (VFTO) can generate actual test voltage values exceeding the type test voltage levels at
some locations of the (extended) GIS under test, and the insulation system will be dielectrically
overstressed subsequently (resulting in additional disruptive discharges at other locations) [B56].
2.5.2 LI (OLI) testing equipment
Different types and designs of LI testing equipment exist. Some examples are summarised in the
following figures. Typically, their advantages for the use on site relate to flexibility, assembly options in
case of modular impulse voltage generators, short testing times in case of vehicular impulse voltage
generator, and compact size as well as low stray inductances in case of SF 6-insulated impulse voltage
generators.
The following figures display some impressions of the different test set-ups for LI and OLI on-site HV
testing equipment. This overview is subjected to further impressions of these type of testing
equipment.
40
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 2.17 Modular impulse voltage generator for on-site HV testing [B57]
Figure 2.18 Modular impulse voltage generator for on-site HV testing with OLI [B58]
Figure 2.19 Vehicular impulse voltage generator for on-site HV testing [B57]
Figure 2.20 SF6-insulated impulse voltage generator for on-site HV testing [B57]
41
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
42
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 2.22 Application case 1 in China - main single line diagram [B59]
The tested GIS was divided into two parts in terms of the voltage distribution simulation. The red part
constitutes the GIS under test.
43
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
(Part 1)
(Part 2)
Figure 2.23 Application case 1 in China - test segment / test section [B59]
For part 1, it passed the positive polarity impulse voltage test, but a disruptive discharge occurs in
negative polarity impulse voltage test. The test impulse voltage waveforms are shown in the following
Figure 2.24.
(Positive polarity)
44
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 2.25 Application case 1 in China - conductor displacement inside GIS [B59]
This GIS has passed the AC withstand voltage test. If no impulse voltage test would have been
conducted, the GIS would have been put into operation with this defect, and it could lead to a failure
sometime in the future.
The second case study (application case 2) is describing an on-site impulse voltage test of a 1000 kV
GIS [B59].
Figure 2.26 Application case 2 in China - main single line diagram of 1000 kV GIS [B59]
The substation is essentially one-and-a-half circuit breaker arrangement, but with a slightly different
design as two bays are of an incomplete design with only two CBs per bay. Subsequently, the
calculation of the relevant capacitance under test has been performed for the complete as well as for
the incomplete bay design.
45
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
A simulation of the equivalent circuit diagram gives some results for the voltage waveform including
the front time. The circuit data is summarised in Table 2.8.
Table 2.8 Simulation of equivalent circuit for calculation of the front time
Figure 2.28 Voltage waveform calculation of 1000 kV GIS (concentrated test capacitance) [B59]
For the case of a complete bay, it results in a front time of 13.8 µs, and an efficiency of the test voltage
generator of 125 %.
Following the voltage waveform calculation for the impulse voltage generator a calculation of the
voltage distribution along the GIS bay is made.
46
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 2.29 Voltage distribution along GIS based on wave impedance model [B59]
The result of this calculation shows that the voltage value at the disconnectors DS41 and DS46 are
quite similar.
Before the on-site HV test commences the final calculation in advance shows the overvoltage
occurrence in case of a disruptive discharge in the GIS section under test.
(Left to right: equivalent circuit diagram; maximum overvoltage at flashover point 1 is 2424 kV;
maximum overvoltage at flashover point 2 is 2440 kV; maximum overvoltage at flashover point 3 is
2515 kV)
Figure 2.30 Overvoltage calculation in case of disruptive discharge at 0.8x2400 kV [B59]
The results of the overvoltage calculation exhibit the maximum overvoltage at the ‘far away terminals’
(open disconnectors DS41 and DS46) in relation to the location of the disruptive discharge.
While finally conducting the on-site HV test with OLI voltage on the test section as indicated in the
circuit diagram, two measurements of example voltage applications are also shown.
47
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
2.6 SI (OSI)
Testing HV and UHV GIS on-site with switching impulse (SI) or oscillating switching impulse (OSI)
voltage waveforms is obviously less dominant in its cases of application. In Table 6-5 of [B2] which is
also used in the text for LI (OLI) above, it is not discriminated between LI and SI. Both impulse
waveforms have been evaluated jointly.
48
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Nevertheless, in [B7] the on-site HV test voltage waveform referring to OSI is no longer considered,
which was the case in the previous edition of that IEC standard from 2011.
The SI (OSI) voltage test is particularly effective for checking pollution (e.g. contamination), and
abnormal electric field structure (e.g. protrusion). It is typically suitable for on-site HV withstand tests of
GIS with higher rated voltage levels.
The rise time of the switching impulse (including oscillating switching impulse) should be generally
ranging from some tens to some thousands of microseconds, depending on the applied standard
(IEC62271-203 (2011) is from 150 μs till 10 ms; IEC 60060-3 (2006) is from 20 μs till 400 μs).
OSI voltages can be generated by conventional Marx generators, and it also can be generated by
discharging a capacitor to the low-voltage side of a power transformer, potential transformer, or test
transformer. The latter option is seldom used. Generally, the generating equipment for OLI voltages
can be used by changing the inductance to a suitable value and design for OSI voltage applications.
An OSI testing sequence can look like the display in the following Figure 2.32.
Figure 2.33 Modular impulse voltage generator for on-site HV testing with OSI
49
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
50
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
installation can play a vital role in the service performance of the equipment. Site testing is one of the
final steps in this path and should in theory be a verification and quality test of the preceding
installation and assembly steps only. Despite quality assurance processes and appropriate verification
steps being implemented in the manufacturing and site installation stages by OEMs, there remains
concern from some users that enhanced site testing procedures are seen as a means of reaching
further back along the quality chain preceding the site assembly stage to also uncover potential errors
from the factory assembly stage [B11], [B41]. This is evidenced in user specifications from China and
some European utilities specifying requirements for mechanical operations and extended time
durations for the conditioning voltage or PD measurement phases of the HV test due to perceived risk
of defects lying undetected by standard quality and on-site testing procedures.
51
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 3.2 Relative distribution of major failure modes in correlation with failure primary causes ([B61]
figure 5-88)
46 % or approximately half of the dielectric failures assessed were attributed to causes introduced
before putting into service. While the reliability report states, 'dielectric breakdowns can be avoided, in
a certain extent, in early GIS life by extensive routine and on-site dielectric testing' [B61], it is not
confirmed what testing or procedure had been implemented in each of the failure cases. Information
provided in the brochure notes that failures were dominated by components such as circuit breakers,
disconnectors and earth switches - however failures of other components such as busbars, busducts
and bushings were found which would typically not be factory routine tested as a complete assembly
and may only have been subjected to on-site testing at reduced levels [B61].
Where difficulties in implementing on-site HV tests are presented, users should therefore consider the
risk posed by failure (depending on the importance of the installation, location, and redundancy in the
network) when considering alternative test methods over the minimum recommended HV tests,
especially if sections of the GIS are assembled on site having not been subjected to factory dielectric
tests as a complete assembly.
User’s own experience shows that failures in service of new GIS attracts significant attention from
project stakeholders and pose reputational concern in the case of project delays. In the case of critical
customers being affected in loss of production or generation ability being curtailed, substantial
consequential costs or penalties may be imposed. In most new build and turnkey projects with HV or
EHV GIS for large consumers or generators there is invariably a continual focus on project timelines
and completion dates driven by commercial reasons. Failures that occur within a short period of the
initial energisation of customers can attract undue widespread attention and often requires significant
stakeholder management. Lessons learned or project reviews can often focus on such events as
being significant and result in requests to the engineering personnel to put in place steps to mitigate
such events from occurring in future.
As 23 % of GIS failures reported are attributed to dielectric breakdown mode cause, there is seen
adequate justification on the part of the user to have special or additional requirements for the on-site
dielectric testing of GIS to show additional measures have been taken over and above standards. The
63 % of major failures attributed to failing to perform requested operation may be primary mechanical
or secondary electromechanical failures of switching devices and has been found reflected in user
requirements for additional functional testing as part of routine factory or on site testing [B11], [B41].
The reliability figures provide sufficient case evidence for the users in this regard and confirmed in
surveys as detailed in [B2] where almost 80 % of the total respondents (2004-2007 survey) indicated
that they have changed their commissioning tests practice and quality control procedures in
comparison to procedures and practices used in the past.
In the collation of user experience in the formulation of this brochure it is evident that there is a variety
of practices used by OEMs, third parties and users themselves. International standards referred to in
the following sections of this chapter generally form the basis of user specifications. However, the
implementation of the test procedure to be used can depend on a multitude of factors that must be
discussed and agreed with the influencing parties. Several user cases show significant enhancements
onto the test procedures as recommended in IEC, IEEE, GOST and other national standards. Based
on feedback of user experience, it is more certain, than likely, that economics and market driven
factors such as GIS penetration and service experience in some regions undoubtedly play a large role
in influencing the user requirements.
52
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
While several users have concentrated on the final site testing requirements, some users have
reported good service experience and low history of failures from defects since implementing a
collaborative approach with manufacturers in regard to quality control [B5], [B6].
User experience from Japan has shown that HV site testing may be eliminated as a requirement if
strict quality controls are implemented in a collaborative approach between the user and
manufacturer. This approach offers advantages to both the manufacturer and the user in removing the
time and cost of performing HV testing on site. The number of major failures as reported since
implementation of this practice in 1998 in Japan has remained at a consistent low rate as shown
below and serves as a reminder of the importance and benefit of quality control at all stages from
initial factory production up to site installation and assembly works.
Figure 3.3 Change in failure rate attributed to on-site assembly in Japan following collaborative quality
approach [B5]
Shown in Figure 3.3 the failure rates observed in GIS installed in Japan decreased to a comparatively
low rate from 1998 onwards due to the collaborative quality approach taken between users and
OEMs. The most significant departure in Japanese standards has been the removal of the HV on-site
test in favour of strenuous quality control measures in all preceding stages to decrease site installation
time and cost. The use of soak testing only as the verification of the site assembly works appear to
have not presented any adverse effect for users or any increase in failure rates in service. This is an
interesting case example of quality and reliability improvement of GIS driven by focusing on reducing
on-site work.
It should also be considered that older/larger GIS designs are less susceptible to defects due to
smaller internal area with high electric field stress compared to new and more compact designs,
optimised in space requirement and reduction of SF6 quantities.
However, it is acknowledged that the same market alignments and structures may not be as readily
implementable in other regions of the world where open market competition is predominant, and users
and manufacturers tend to only engage after a procurement process has been completed. It does
nevertheless provide example of an interesting alternative strategy for both users and OEMs that
could be considered where feasible or warranted in the future. In some cases, the only feasible
method to verify the integrity of new GIS or sections of on-site may be soak testing only as outlined in
IEC 62271-203 Annex C - Application of service voltage. This scenario often arises in the cases of
extensions, repair or retrofit across all GIS users in the world.
53
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
standards change slowly (over decades) and knowledge increases continuously, users may have a
significant wealth of experience to refer to in their requirements for additional tests or enhanced test
levels, in addition to recommendations of organizations like CIGRE or other scientific results that may
be current at the time. User’s own requirements can have evolved from their experience and practices
in place for significant periods of time. Changes to these practices - unless identified as deficient, can
be slow for large utilities to adopt and move toward when the user has existing GIS in service that may
have been subject to those practices from the start of their lifecycle [B62].
As an example of user specification enhancements, [B7] is a widely used reference standard which
recommends PD measurement during the AC withstand voltage test for 245 kV GIS rated voltage and
higher. As referenced in case studies a significant number of utilities in Europe specify PD
measurements at the on-site acceptance test of GIS at 170, 145, 123 kV, and even down to 24 kV
rated voltage. For these users, the possibility to eliminate any possible defects with an additional
measurement and potentially increase the reliability outweighs any additional costs and efforts.
Regardless of the standards and user specifications, PD measurement is commonly carried out as
standard on GIS below 245 kV by some OEMs where the test arrangement and provisions are readily
available (such as UHF sensors integrated within the GIS or via conventional method). The
requirement to perform PD measurement at this early stage is found in some user specifications in
order to capture a baseline fingerprint of the GIS to serve as a reference baseline for future periodic
monitoring or installation of online monitoring systems. Previous Working Groups of users and OEMs
foresee the requirement for withstand testing with PD becoming mandatory for on-site testing in the
near future to facilitate condition assessment of both the insulation and mechanical integrity [B28].
In other regions following IEEE standards, e.g. [B21] - only the AC withstand test is specified and PD
measurement referenced as an optional requirement only. Several examples of different voltage
levels, durations and PD measurements utilised have been documented by the Working Group
members consisting of both users and manufacturers to illustrate the variations in application of the
most referenced international standards [B62].
HV testing that may be performed later in the GIS lifecycle for condition assessment purposes will
generally follow similar procedures and methods as recommended in standards and as applied to the
initial installation. Several case studies reviewed by the Working Group focused on the practical
aspects and sensitivity considerations necessary for PD measurement generally used as the method
of condition assessment evaluation [B63].
As these as other condition assessment techniques may be employed similar to the initial on-site HV
test, the same standard and considerations can also be deemed applicable for condition assessment
purposes.
54
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Examples of motivations for users as outlined in the high-level table above can be further detailed with
reference to international standards or source of reference (where applicable) to illustrate
requirements that are not covered or covered in principle only in current standards. It must be pointed
out that in many cases the user specification may serve as a scope of work and services required from
a contractual viewpoint between the user and the OEM, and therefore national or international
standards may not feasibly encompass all user specific requirements that may be stipulated in a
project and country specific specification. Some user requirements may be non-technical and so not
within the scope of international technical standards to provide guidance on. In the table below a
sample outline of requirements that may be specified by users are listed and the associated technical
standard(s) indicated where applicable. As indicated in the table, standards that do not currently
cover, or may only cover in part some user requirements, and therefore these may be open to be
agreed between the user and OEM on a project specific basis based on their own practices,
experience or local regulations if necessary to do so [B47].
55
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Test voltage generator technology to be used (e.g. air, oil or gas-insulated) and Not covered by technical standards
responsibility for supply
Size and minimum / maximum power rating required of the test voltage
generator
• Wave form
Roles and responsibilities of the user and OEM for the testing with respect to: Not covered by technical standards
• Assessment of PD measurements
Gas quality values (gas when inside GIS compartments) Defined (by the OEM)
Conditioning voltage level and application time / duration Defined (by the OEM see Chapter 3.5.4)
Assessment of the results and determination of HV test failure and repetition Covered in principle in technical standards, e.g. [B7]
procedure Annex C.6
PD prescribed measuring method (conventional, UHF, acoustic) Covered in principle in technical standards
Assessment of the results and determination of PD test limits Covered by technical standards
Optional HV tests for maintenance after major dismantling - test value and Covered in principle in technical standards [B7] cl.
duration [B23] 11.101.2.1
56
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
• HV cables
Site HV test report and documentation to be supplied Not covered by technical standards
Assessment criteria for HV testing, while covered in principle in standards as indicated above, may be
enhanced by users with acceptability limitations specified on the number of repeat flashovers that may
be encountered during testing before investigation must take place. As reported in ([B2] table 6-7),
when asked for their practices after encountering a flashover during the HV test about 10 % of users
indicated that they allowed that a cleaning flashover may occur before the GIS compartment must be
opened and inspected. It is expected that the opening and inspection in these cases shall only take
place after a repetition test has been performed to confirm a non-restoring flashover has occurred and
localise the failure. The responses collected in ([B2] table 6-7) have been received by approx. 30 %
from European users, and by approx. 60 % from Asian users.
When flashovers are encountered during the HV test it is standard practice to reapply the voltage at a
lower level, and increase in steps until further flashover occurs, or the applicable withstand voltage
level is maintained without breakdown. In events of suspected cleaning flashovers close to the
withstand voltage test level and subsequent voltage reapplication, some OEMs may maintain the peak
withstand voltage in excess of the one-minute duration in a slight deviation to IEC. Any user
specification requirements in this regard should be agreed with the OEM and experienced test
engineers as to what criteria for performance during testing may be applied to the particular GIS
installation and practices employed by the OEM in such events.
In the event of a disruptive discharge occurring, some user specifications may include some additional
requirements for the completion of the test procedure or the repetition of the applied voltage test that
overcome requirements of the relevant international standard. Such requirement may include the
production of a report in which the disruptive discharge event has to be documented (impulse peak
voltage value and wave form / power-frequency value, potential location of the disruptive discharge,
etc.). Furthermore, some requirements for the completion of the test may be prescribed such as the
repetition of the complete sequence of the conditioning voltage levels if a power-frequency withstand
test, or an additional number of impulses in one or both polarity from the original sequence in the case
of impulse testing being used.
3.4.2 Regulatory requirement drivers
Operators of transmission and distribution systems may be set specific targets for availability and
reliability by national regulatory authorities. Performance targets and financial penalties in cases
where the reliability of the GIS may impact customers is understood to be a significant driver for some
of the requirements in user specifications. The foremost advantages of GIS which greatly act as
incentives for users in adopting the equipment, such as lower footprint and maintenance, can also be
of concern in the event of repairs or extension being required which can have higher impact on
availability and restoration times. Maintenance, repair, and extension works on GIS may require a high
level of planning and longer outages over other technologies.
In certain countries or regions system operators are set performance targets in their license with
penalties or loss risks sufficient to drive users to seek similar or higher reliability in equipment
performance. In some countries a 100 % reliability of supply target is required implying zero days
outage allowed by incidents caused by failure or damage to the operation of HV equipment. Maximum
57
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
times for the restoration of supply in event of interruptions, while long common up to MV level are now
also seen for large HV connected demand and generation customers. The design and configuration of
the utility networks and GIS substations can accommodate redundancy where efficient and economic
to do so, but supply interruptions in the event of dielectric failures in key areas of the GIS such as
busbars and bay connection or cable compartments can still result in loss of supply to customers that
may not be repaired in the performance target timeframe.
In regions or countries with regulated utilities the cost of intervention in the event of reliability issues is
attributed to operational expenditure (OPEX) by the utility for which targets may have been pre-set.
Should the utility exceed their allocated budget for the period due to greater than estimated fault
responses and repairs, this may be seen as inefficient spending and the utility forced to bear the costs
directly and not permitted to recover through licenced cost recovery mechanisms. GIS which can be
compacted into small footprints still requires a large capital investment cost to install for the user and
redundancy may not be feasible in certain locations on the network, particularly in urban and city
areas where land space is limited and costs to purchase and build relatively high. This places the
need on the user to seek a higher level of reliability to mitigate the risk of future penalties and cost,
particularly in the event of cumulative hours lost limits being set or specific agreements with large
customers.
In order to demonstrate suitable diligence on their part to stakeholder, users may seek to set
additional criteria for the level of quality that may be acceptable for their GIS. In the case of new GIS,
case examples from Japan set criteria for the assessment of particle contamination allowable inside
compartments to determine at what stage additional intervention and cleaning may be required and
strict limits on the gas quality and moisture limits, irrespective of the manufacturer’s own acceptance
limits of their GIS design. While such quality measures can be seen as technical requirements, the
drivers for the user to specify such acceptance criteria to strict limits demonstrates the need of an
improvement for reliability purposes which serve regulatory drivers also [B5].
58
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
59
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
platforms, remote
installations
Lightning / Air-insulated • Effective for HV and EHV • Very large footprint and
switching impulse impulse test rated voltages safety clearances needed
voltage generator to live and earthed
1) • Simple and quick
equipment
connection where AIS
bushing interface is • Height of impulse
present on the GIS generator difficult to
accommodate within
indoor switch rooms
• Where located outside
weather and
environmental factors
must be allowed for
Table notes:
1. SF6-insulated type impulse generators are in use in some regions, however for the purpose of the user the connection from the
generator / voltage divider and the equipment under test is achieved via a conventional conductor in air and overall footprint
similar to an air-insulated impulse generator [B57]
Where the user has specific requirements for the test procedure, e.g. voltage level and time durations
these must be discussed and agreed with the OEM or third party to determine if the test voltage
generator proposed can meet the requirements. In order to ensure any specific or special site test
requirements can be achieved it is essential the user is aware of, and considers, the necessary
physical implications of the test method to be used. While new build installations can often be built as
turnkey type projects with little input from the user, the product is an installation that shall be operated
by the user who is generally responsible for its lifecycle - which may include repair, maintenance,
extension, and eventual retirement. Provisions for the situating and positioning of test equipment in
and out of the site over the lifecycle phases of the GIS are necessary to be considered at early project
planning stage by the user. Even if the user is not responsible for any aspect of a turnkey project to be
delivered it is essential, they detail any required maintenance practices and requirements in the case
of future extensions, repairs or retrofit of components. This is necessary in order to ensure sufficient
provision is made in the footprint of the overall site and access to connection points onto the GIS for
HV test voltage generators and other essential equipment such as gas handling equipment,
compressors and storage containers.
In the case of indoor GIS with no AIS components, gas-insulated test voltage generators may be
used. Sufficient dimensioning of the area surrounding the GIS to position the test equipment and
install the connections onto the GIS is required. The choice of the connection point for the test voltage
generator should ensure as large a coverage of the GIS to be tested is possible, while minimising the
required number of generator connection and disconnections. Where the capacitive load of the GIS
exceeds the capability of the test voltage generator to reach the test voltage, the GIS must be tested
in sections or parts and may require the test voltage generator to be dismantled and moved to a
different connection point onto the GIS.
In Figure 3.4 an example is shown for a compact resonance test voltage generator during its assembly
work (petrol equipment) directly coupled to 245 kV GIS for AC withstand testing including PD
measurement. The compactness of the test voltage generator provides significant savings in transport,
footprint, and assembly time requirements over the AIS examples. Accommodating the positioning of
the test voltage generator within indoor buildings must be coordinated by the user with the OEM to
ensure sufficient space is allowed for or can be facilitated e.g. with the temporary removal of access
platforms or inspection catwalks where necessary.
60
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 3.4 Example for temporary removal of access platforms or inspection catwalks
Example diagram and photograph shown below in Figure 3.5 illustrate the equivalent footprint for an
air-insulated resonant system to test similarly rated 245 kV GIS. The footprint required to
accommodate the clearances is considerable and, in many cases, not easily accommodated within
switch rooms at HV and EHV rated voltages as shown in examples in Chapter 4.
61
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 3.5 Example for air-insulated test voltage generator (e.g. typical footprint and clearances and
indoor installation)
Most GIS above MV (> 52 kV) require access and lifting provision for components such as circuit
breaker interrupters and voltage transformers. Weights of these components are stated as the
minimum requirement for any lifting equipment to be provided or fixed within the switch room, such as
overhead gantry cranes or hoists. Provision of the lifting equipment to these minimum requirements
may not be sufficient for use with larger or heavier components that the user may need during the
lifecycle of the installation, such as large gas treatment equipment or complete assembled bays in the
case of future extension that may require to be lifted within the indoor GIS room. Careful consideration
of the future use and requirements for the installation should be specified by the user if they require
the installation to be fully suited to any of their own specific practices. See Chapter 4 for further detail
of provisions required to facilitate HV testing.
Where the GIS is tested in several different sections requiring repositioning of the test voltage
generator, the provision and design of structural supports if required to elevate the generator to each
of the connection points of the GIS should be considered along with the footprint of the supports and
load bearing points. In several jurisdictions the location and design of such temporary supports are
classified as construction works and require certification from suitably qualified civil and mechanical
engineers requiring verification of the floor bearing capability. Users may allow for the repositioning of
gas-insulated test voltage generators for the advantages as set out in the table above - although this
may create voids or untested small sections of the GIS where the test voltage generator was
connected to, and then removed which may introduce a potentially untested compartment and source
of PD. See Chapter 5 for considerations for PD testing. This can also be a motivation for the user to
limit the number of test voltage generator repositioning's and reconnections required to perform the
dielectric test and may have impact for the OEM in the availability of a test voltage generator that has
62
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
sufficient power to meet the user requirements. Alternatively, users may consider facilitating HV tests
by provision of a dedicated test connection point or a spare bay that is easily accessible.
For special cases where criticality of the installation is a significant factor, the user may consider the
possibility for integration of a dedicated test point onto the GIS that may be permanently fixed onto a
specific point, or relocatable to other flanges that may be used for e.g. connection of voltage
transformers, surge arresters, busduct or busbars. This would provide a common point for which to
connect and perform testing in the future in the event of repair, extension, or condition assessment. As
shown in Figure 4.21, this may be a specialised adapter with HV cable extended to a testing bushing,
or an adapter with a directly mountable bushing to connect the test voltage generator to. Disconnector
or earthing switch facilities similar to those as used on the GIS could be integrated into a test module
as required to be affixed to a dedicated point on a non-critical bay or busbar. Gas barrier
arrangements can be selected to minimise impact on the bays to maintain in service condition. An
illustration of a dedicated test module that could be incorporated onto a bay or busbar is illustrated
below in Figure 3.6 for example purposes. This may be a module constructed with two or three gas
compartments (depending on GIS design) and permanently installed on a section of the GIS that can
be made easily accessible in the design of the switch room or connection point brought to a more
suitable location that may be within, or external to the building or housing.
63
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
technology, on-site impulse voltage tests are not as commonly used as the PD test for on-site
dielectric tests [B47].
The trend for use of the AC withstand voltage test only is partly driven by costs, time, and convenience
in utilising just one test voltage generator at site and appears to be the most common default method
of HV testing at site unless otherwise specified by the user. The adoption of compact resonance
generators that can be used up to HV levels offer significant benefit to the user in their compactness
and lower space requirement over air-insulated connected units which are typically required if impulse
testing is utilised. In the case studies, it has emerged that several users have defined specific
requirements for use of impulse tests on site and have driven the innovative development of more
easily transportable impulse test voltage generators. Examples of these are shown in Chapter 2 and
Chapter 4.
Where constraints for HV testing on site are identified, especially in case of extension, repair or retrofit
in existing substations, user specifications may require specific measures to be devised and
implemented by the OEM. These are typically operational or physical but can have implications for the
OEM in the design of the switchgear, performing of the on-site HV test and additional equipment that
may be needed.
Table 3.4 Examples of user constraints in case of extension or replacement of GIS
Operational • Sections of the station must be maintained • Point of connection to the GIS may
in service by the user with implications for be restricted
isolation and grounding
• Test procedure may require
• Time constraint for shutdowns of adjacent modification for:
live bays
o test voltage level
• HV cables or components such as surge
o PD acceptance criteria for
arresters may not be disconnectable
withstand test
• Additional isolation or gas
compartments required
Physical • Footprint of the substation or building may • Test voltage generator size / type
not accommodate test voltage generator may be restricted
• Safety clearances may be restricted by • Additional components required,
adjacent equipment in service e.g.
o Test adapter to connect
via bushing
o Additional compartments
or busduct for test
connection
o Cable adapter for HV
injection via cable socket
or flange
As the types of constraints outlined above can have material impact on the scheduling and test
procedure to be used, the planning of the testing should be treated in the initial stages of the project
conception. This places a requirement for a basic level of knowledge and experience upon the user to
determine the factors that may be of influence on the site testing phase which take place many
months or years after the initial planning stage especially in case of extension or repair in existing
substations. In the cases of HV or EHV GIS testing the physical constraints may require specialised
test set-ups and adapters to facilitate the connection onto the GIS via an air-insulated test set and
overhead connection as shown in other chapters of this brochure. The test sets that can be
accommodated and their positioning in relation to the GIS under test should be detailed where
required by the user at project specification stage to ensure OEMs are aware of constraints and can
design sufficient connection arrangements where required.
64
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
1 2
3 4
(Images 1 - 3: 52 kV rated GIS on-site testing
Image 4: 24 kV GIS)
Figure 3.7 MV GIS HV test set-up via cable test adapter
As shown in Figure 3.7 above both the test voltage generator and control module for power-frequency
testing of MV GIS can be accommodated on a single skid or positioned independently. With the
greater compactness of MV GIS and development of entire substations preassembled in packages or
modules of small size, there similarly can exist constraints for future HV testing at site of MV GIS to
that of HV GIS and long cable test adapters may be required if the test voltage generator cannot be
accommodated within the limited space available within containerised switchgear modules.
65
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Shown in Figure 3.8 below is a 52 kV / 24 kV GIS substation fully assembled in modules and then
transported to the substation site. Despite the relatively small footprint of test voltage generators for
MV, due to the limited space within the modules performing the HV test in future may require the test
voltage generator to be located external to the switch room. The physical installation of the test
voltage generator requiring crane offloading and set-down area must then be accommodated by the
user in the overall footprint of the substation limiting the compactness or minimum footprint the overall
site can occupy.
Figure 3.8 Example modular 52 kV and 24 kV GIS substation and positioning of test voltage generator
For the experienced user the requirements for employing a particular technology or voltage generator
may have evolved over time. This may be influenced by a number of factors:
• Familiarity or experience with a particular technology,
• Access or ownership of own test voltage generators,
• Reproduction and comparison with previous HV testing,
• Repeatability of test procedure and PD measurement,
• Type of GIS and HV injection point available,
• Space restrictions within the building or substation and adjacent in-service equipment,
• Configuration of the GIS and location of voltage transformers, surge arresters, bushings.
Where OEMs perform the on-site HV test they may have access to a limited number of test voltage
generators which may not all be the same type or technology. These can be in constant demand for
use between installations ongoing worldwide and shipped from site to site and with the intermittent
need for recalibration. Specifying a particular type of test voltage generator by the user is feasible and
may be stipulated for reasons such as space restrictions or safety. Limiting the generator type that can
be utilised may however subject the project to additional cost (dependant on the technology type) or
schedule constraint risk. This consideration is necessary to be highlighted to project scheduling
66
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
personnel as the completion of commissioning works by the user may therefore be affected or
commissioning works of external or secondary equipment may required to be rescheduled.
Where users have access to their own test equipment it may be required to use their own test voltage
generator to conduct the dielectric on-site tests. The user may intend the same generator to be used
during future maintenance activities to ensure repeatability and direct replication of the test procedure
and comparison of test results. Specific requirements may also be set out for the supply of the
necessary adaptation flanges and connecting parts to connect the test voltage generator to the GIS.
The motivation for this is to validate the compatibility of the supplied adaptation flanges to connect the
user test voltage generator and to prove and validate the feasibility of the dielectric test with the test
set-up that may be later reperformed by the user. In these specific cases the roles and responsibilities
of the OEM and the user must be carefully considered before creation of the test procedure.
Clarification and agreement of the roles and responsibilities between the user and the OEM for
carrying out of the on-site dielectric test and as outlined in Table 3.2 'Roles and Responsibilities of the
user and the OEM' would be more important to have clarified at an early stage where the users own
test equipment may be used. The OEM may require confirmation of the characteristics of the test
voltage generator and disconnection or protective facilities to suitably protect the GIS under test [B47].
3.5.3 User requirements for testing of HV cables
In several case examples user requirements for on-site HV testing are not confined to the integrity of
the GIS by itself. Users may wish to test other HV components connected to the GIS such as cables,
transformers, and reactors where disconnection for testing after installation during maintenance or
extension may be difficult or infeasible due to constraints and the need to keep adjacent sections in
service. The growing public reluctance to accept the large visual impact of overhead lines and outdoor
interfaces means more and more networks are fully cabled from station to station enclosing the cable
interface within the GIS. The requirement to perform testing on HV cables while remaining connected
to the GIS is being seen in user specifications. Testing of HV cables requires application of voltage
over varying frequency ranges down to DC levels. Additional disconnection or isolation facilities may
be required as a result to allow HV testing of the cable connected to sections of the GIS. Components
such as surge arrestors must be disconnected from the test circuit if present. GIS voltage transformers
can remain in the test circuit if the frequency of the test voltage is high enough to avoid saturation of
the VT.
These external factors which may not be confined to the GIS itself, but to the requirements of the
users overall substation or HV network can be found reflected in user specifications as found in case
study examples collected in this brochure [B8], [B65], [B66], [B67]. Such examples may become more
commonly encountered as users begin to extend or even replace existing GIS located in urban areas
where space is at a premium.
Special user requirements for on-site HV testing of HV cables when terminated to the GIS cable
compartment may require careful planning in the GIS layout design and configuration to ensure points
of isolation and disconnection from other components of the GIS is available. Dismantlement of
components of the GIS, or removal of internal links between the cable, voltage transformers and the
rest of the GIS may not be feasible in all cases depending on the configuration of the bay, location of
gas barriers and internal support barriers. Adequate accommodation and accessibility for cable test
voltage generators and the test interface should be considered along with the feasibility of
disconnection of the cable from the GIS compartment.
As covered in [B68] related to this subject, the additional space requirements for retraction of large
diameter cables is infeasible in many cases - depending on orientation of the HV cable and GIS
enclosure, and may require the user to specify the use of the GIS cable enclosure to be equipped with
suitable facilities to allow testing of the cable via a cable or bushing interface mounted on the
compartment. Shown below in Figure 3.9 at initial design stage is a draft concept to facilitate HV
testing of cables via the GIS interface by an air-insulated bushing adapter mounted onto the GIS cable
enclosure. The clearance distance to the walls of the switch room or adjacent equipment must be
coordinated by the user with respect to the test requirements for the HV cables rather than the GIS in
this case.
67
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 3.9 Arrangement for HV testing of cables via GIS enclosure versus disconnection and withdrawal
of cable via GIS adapter
In the example of the air-insulated bushing above, the clearances between bushing and earth ('R' in
top diagram) must be specified by the user in line with the insulation clearances required for the HV
test of the cable as these fall outside the boundary of interface with the GIS (see [B69]). These are
detailed in [B70].
The appropriate clearance distance required where such a test arrangement is required shall be
specified by the user in accordance with the rated voltage or insulation requirement of the power
cables with reference to their HV cable specification requirements. The suitability of the GIS enclosure
and any components that remain connected to the cable test voltage generator should be confirmed
with the OEM of the GIS, and suitable methods to disconnect inductive type voltage transformers if
necessary should be agreed [B8], [B65].
The alternative arrangement of disconnecting the cables from the enclosure and retracting via bends
within the basement may be impractical in some installations depending on the dimensional
requirements of below ground cable basements and minimum bending radius of the HV cables [B68].
68
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
to 145 kV depending on the OEMs experience. Other GIS designs may be subjected to an AC
conditioning phase voltage in several steps and time durations as noted in Chapter 2 where there is
greater potential for particles to reside in areas of high dielectric stress inside compartments.
3.5.5 Test voltage value - extension of different GIS generations
In the case of extensions requiring modifications to the existing GIS installation, high voltage testing is
generally required of the equipment affected by the modification works. However, especially for older
equipment, the insulation design limits may be different to that of the newer GIS equipment
considering the evolution of international standards over time and potential changes in insulation
design of newer equipment. For the dielectric test at the interface of the extension that will affect
existing equipment, this may therefore be subject to an older test value defined by the technical
specifications of the existing GIS and differ from recommended current standards. While preference
may be to confirm via original documentation from the OEM of the existing GIS, this may be difficult to
discover for legacy unsupported equipment or where the OEM is no longer in existence. The voltage
test level and duration should be discussed and agreed between the OEM and user for each specific
case dependent on the information available. See Chapter 4.4.2 for further details in this regard.
For GIS units transported without dismantling, or for ones where the dismantling is limited to some
simple connections, international standards allow power-frequency voltage tests at reduced test
voltage levels subject to agreement between user and OEM. For these particular cases user
specifications may prescribe the reduced voltage test value in accordance with (inter)national
standards or may reject the principle of reduced voltage tests as not being representative of the
required design withstand capability. Where users have defined specific requirements for the voltage
test value, or are considering change to the applied value in the case of existing GIS, they must also
consider the applicable safety clearances and distances required in the event of air-insulated test
voltage generators being used for the on-site test and ensure adequate space is provided [B71], [B72].
69
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Test value Lower than rated insulation level (typically ≤ 800 kV: Test value at 90 % of rated
80 %) voltage insulation level of the GIS
[B37], [B38]
Power- Test value Lower then rated insulation level and 72.5 kV to 363 kV: Test value at 100
frequency factory routine test value (typically 80 %) % of rated voltage insulation level of
withstand the GIS 2) [B11]
70
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Note that while [B7] Annex C defines an on-site test at reduced voltage for GIS transported from the
factory fully or mostly assembled this method does not appear to be commonly used in most regions
as a standard on-site test (1.1xUr/√3 for earthed systems or 1.9xUr/√3 for isolated or resonant earthed
systems), with the exception of Japan as explained in Chapter 3.4 or where specially defined by users
in the case of components not connected to the GIS during the power frequency or lightning impulse
withstand test.
Special requirements of user specifications were also found by the Working Group related to
requirements for the performing of the on-site test procedure. A summary of these is listed in Table 3.6
below for example. As shown, these may be quality checks or stipulation of values/limits for items
which are not defined in standards and left to the OEM and user to agree. The driver or motivation for
these requirements of the user can be easily referenced to Table 3.1. User specifications can require
some additional HV tests to be carried out with the voltage generator after the on-site dielectric test.
Examples of this are tests to be performed for a specific duration at the rated voltage and frequency
on voltage transformers and surge arresters reinstalled after the power-frequency test. The tables
above relating to user requirements for the on-site test and table below relating to additional or special
tests are a summation of specific requirements from a number of user specifications reviewed by the
Working Group, note that these are not applicable to one or all users, but examples of specific project
requirements and examples may only be applicable for specific types of projects or GIS installations.
Table 3.6 Examples of special requirements of users for on-site HV test procedures
GIS assembly Minimum vacuuming time of > 30 minutes upon reaching 133 Pa (absolute)
compartments and/or pressure
defined > 8 hours in total
71
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Gas quality Limits for moisture in the gas < 130 ppmv
compartments
Sample testing of gas to be carried out 24 hours
after filling
< 150 μL/L (150 ppmv) - CB compartments
< 250 μL/L (250 ppmv) - other compartments
[B11]
Reduced voltage tests Conditioning of GIS voltage 5 minutes at 1xUr (phase to ground)
transformers and surge
30 minutes at 1.1xUr (phase to ground)
arresters
5 minutes at 1.2xUr (phase to ground) with PD
Measurement
[B37]
Test frequency for voltage transformers to be
above 115 Hz (Ur ≥ 16 kV; overvoltage factor ≥ 1.9
/ 8h) (2)
[B19]
72
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Test assessment & Criteria for assessing tests as Assessment of flashovers to determine if self-
procedure successful or unsuccessful restoring / cleaning flashover or not
Table notes:
1. Conditioning tests as stated in Chapter 2 and section 3.5.4 shall be defined by the OEM specific to the design of the GIS. User
specifications in this regard may not be applicable and included here for information only of user requirements reviewed by the
Working Group
2. Swiss practice testing of MV GIS [B19]
3. HV cable tests in accordance with [B70], can also be defined as 2.5xUr/√3
4. Minimum number of mechanical conditioning operations to be performed on-site by the OEM prior to the HV test are exclusive
of operations carried out during factory routine tests
General note: (References to above extracted from: [B5], [B9], [B10], [B11], [B37], [B38], [B41], [B57], [B67]
1.1xUr
73
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
3-5 minutes
5 minutes
10 minutes
30 minutes
Measurement Conventional (IEC 60270) Sensitivity requirement specified for OEM to prescribe
method method
Non-conventional
(VHF/UHF/Acoustic) Acoustic localisation required of defects
The return of experience from users and details or background to the specific requirements as listed in
the table above were explored by the Working Group and examples covered in Chapter 2. Further
notes on the table are listed below:
• Voltage level for PD measurement is also shown to vary in user specifications with practices
in some countries to use a higher level in order to get a measurable signal of potential defects.
A higher voltage level than as recommended in the applicable standards is also adopted by
some users to standardise on the higher isolated neutral level in the event of reconfiguration
of their network or changes to the system neutral treatment [B43], [B74].
74
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
• Time duration - a minimal duration for the PD measurement in which the level of discharge is
monitored to confirm the absence of increasing trend over the duration time is prescribed by
some users. IEC recommendation of greater than 1 minute may be seen by some users to be
too short a time based predominantly on perception. Although some users may have
experienced time-based progressive defects on some switchgear technologies and specified
long measurement durations up to 60 minutes as a result, they clarified that if during
measurement there is no increasing trend observed during an initial period (20 minutes) the
duration may be shortened. If any phase correlated PD found, further investigation time is
applied, and the test duration extended. Care must be taken when attempting to compare /
evaluate PD levels found with widely varying PD test durations [B41], [B47].
• Measurement method - user specifications may define which method should be used, so that
common interpretation of the PD measurement results can be achieved. These are covered in
detail in Chapter 2 but considerations for user specifications are covered in principle below:
o From a user perspective the application of conventional and non-conventional
methods for PD measurement may be considered. The conventional method is used
for contractual purposes. The UHF method is an accepted stand alone method and
widely used. The acoustic method should be used last for the further localisation of
the PD source to a narrow section of the GIS test circuit, or to a single GIS
component.
o Some user specification requirements may have implication for the on-site calibration
of the PD measurement circuit being used. These may relate to requirements for
calibration of conventional PD measurement or on-site sensitivity check for UHF PD
measurement, minimum number of sensors to provide sufficient coverage of the
complete GIS installation, or type and number of amplifier levels used. Users should
note that while comparisons between substations containing identical types of GIS
may be feasibly performed to some level, the different substation environments,
configuration, or variations in positioning of sensors and measurement equipment
may require different amplification settings of sensors and so make direct and detailed
comparisons more complex.
• PD limit - some users and OEMs specified a maximal permissible level of PD lower than the
10-pC level prescribed in relevant (inter)national standards. Even if the value of 10 pC is
recommended in IEC 62271-203, the lower 5 pC limit may be applied for site testing to
improve the level of verification of the integrity of GIS insulation. Users may otherwise specify
the lower value to be applied to critical compartments such as circuit breakers and the higher
threshold allowable for non-interrupting compartments if accurate localisation can be
performed. The specification of 'no phase-correlated PD to be detectable' was associated with
testing of HV GIS and where the UHF method was applied. The requirement to perform 'UHF
measurement within one week' arose from a specific user specification which omitted the
requirement for a HV test in the case of repair and extension in favour of sensitive PD
measurement during an extended service voltage application period. In the event of PD
measuring level exceeding the prescribed value, some user specifications may include some
additional requirements for the investigation procedure in order to localise the source and
evaluate its potential effect.
3.6.3 Specification for GIS extension
In the cases of extensions of existing GIS installations connected to the network, HV tests are often
not covered by customers specifications or left to the OEM of the extension to consider and propose
appropriate tests. Guidance or recommended practices are outlined in a number of standards. [B7]
and [B75] recommend stand-alone testing of the extension bays the same as new GIS, before
connection to the existing GIS. The point of interface of the old and new GIS's when connected, if
supplied by the same or by different OEMs may not be as explicitly defined in standards although
referenced in e.g. IEC and IEEE.
In certain cases of limited extensions such as the addition of a small section of new GIS to an existing
GIS installation, some users may be doubtful about the benefit of on-site voltage tests considering the
cost, time and effort required by the implementation of the test set-up. If the test voltage generator
injection point is via the existing switchgear to test the new bay(s) or the interface, the connection and
disconnection of the test voltage generator to the GIS may risk introducing a potential future failure
possibility considering that the test voltage generator connection point would disturb the primary HV
conductor system and will not be tested after its dismantling and removal. However, for other users
75
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
despite the effort and the anticipated cost to implement the HV test on site, it is considered lower than
the effort and the cost to repair a major failure in a GIS. In many cases if the substation is critical to the
user network and heavily loaded with outages difficult to obtain, ‘soak tests’ may be the only feasible
option to the user irrespective of the specification [B47].
The return of experience and procedures applied to HV GIS extension scenarios is illustrated below
and further detailed in Chapter 4.
Figure 3.11 HV testing of GIS extensions after coupling to existing GIS [B72]
In the OEMs experience shown in Figure 3.11 new GIS extension bays were subjected to a HV test on
site as stand-alone or physically isolated before connection to the existing GIS. Standard practice as
shown in most cases above was not to perform any additional HV test on the newly joined section or
interface of the new and old sections.
While the return of experience from one OEM appears to indicate that testing of the interface is an
infrequent occurrence, the overall results from [B2] reported a significantly high number of users
having experience of performing on-site HV testing of GIS extension across the interface.
Approximately 82 % of the cases in the survey indicated that HV tests were performed on the interface
when combine 'testing of extension together with old GIS' and 'testing of extension together with part
of old GIS' as shown in Table 3.8 below.
Table 3.8 Testing practices after GIS extension ([B2] table 6-32)
The return of experience gathered by the Working Group shows specific case examples of GIS
extensions experienced by a significant number of users and OEMs, and international standards
provide basis for testing of the extensions. [B75] may be considered as clear in requirement for HV
testing of the interface with ‘reduced test voltage level’ as described in [B7] annex C.3.2 only for those
cases that no agreement between OEM and user is possible. However, the same recommendation to
test all sections involved and all newly installed part of a GIS is recommended where feasible in [B7].
There are however potential variations for the test procedure to be applied to the interface of the old
and new GIS.
A number of user specifications have stated the requirement for HV testing of any existing GIS
equipment affected by the extension or modification works. However, especially for old equipment,
even if tested in accordance with original specification, the power-frequency test withstand value could
be lower than for the newer GIS equipment considering the evolution of the standards over times. This
particularity for the HV test of at border of the extension or interface that will affect existing equipment
76
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
may be subject to specific power-frequency voltage test values that might be reflected in the user
technical specifications [B47], [B48].
In the case examples seen by the Working Group the documentation or records of the user of the
existing GIS may be a vital requirement to assess the insulation design values of the existing
equipment which may not be directly related to the rated operating voltage. Extensions of older GIS
which may no longer be supported by any OEM and insufficient records exist can be a concern for
OEMs and persons responsible for carrying out the on-site testing in this regard and choice of the test
voltage level must be carefully assessed. The treatment of the interface is shown to differ significantly
in the user cases examined by the Working Group. As shown below in the summary Table 3.9 of the
cases examined, while the test method of the extension was conducted generally in accordance with
the user specification for new GIS, the treatment of the interface joining the new to the old and test
methods are numerous.
Table 3.9 GIS extension - user case examples
User case examples of extensions to existing GIS and HV testing are illustrated in Chapter 4 and
detail the test procedure used to minimise the impact on the availability of the existing GIS for the
user.
Users may require that opening and installation of the interface pieces is to be avoided to limit gas
works on site and possibility of introducing particles. In another case example all installation works,
including the interface were completed before HV testing commenced. In these cases the testing
procedure and voltage level that the interface will be subjected to must be reviewed and agreed with
the OEM and responsibilities clarified.
77
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Additional care is required where the GIS is to be extended by a GIS of different technology, or even
by a different OEM. [B75] provides a useful reference for users to consider in extension scenarios and
treatment of the interface in addition to similar service continuity considerations as outlined in [B7]
Annex F. The test method and procedure to be used surrounding the interface for on-site HV tests
should be risk assessed by users with experience of the history and performance of the GIS design.
Refer to Chapter 2.1.3 for information on aging of GIS insulation.
3.6.4 Specification for GIS retrofit or repair
User requirements for the scenarios of retrofit or repair of components of the GIS may differ and be
distinct from that of the new and extension scenarios, whereby GIS extensions are often treated same
as 'new'. In many cases the extent of any repairs or interventions onto the GIS, if there is no
disturbance to HV conductors, partitions and/or support insulators may be deemed to be minor and
dielectric verification tests unnecessary, i.e. gas system repairs not requiring intrusion onto HV parts
[B10].
HV testing after repairs are often required, as noted by the Working Group according to some user
specifications, where the repairs are deemed major. ‘Major failure repair’ as referenced in CIGRE
reliability studies is considered the consequential work required to repair after a MaF has taken place.
However, as per [B61] major failure resulting in a function not being able to be met by the equipment
may not be related to parts comprising the HV conductor or dielectric insulation. The test procedures
are considered to be the same as the user specifications for new and extension scenarios where
feasible.
When considering GIS and HV testing in the case of repairs or retrofit, consideration of how much of
the substation needs to be turned off to allow the testing to take place is often the largest
consideration of the user, after determining the extent of the impact and consequential risk for the user
in availability and security of supply for customers. This is an issue that requires to be considered
during the specification and procurement of the GIS itself by the user. Provision for this should be
made at initial project planning stage, especially if it can be foreseen that the substation is critical to
maintain the operation of the network and supply to customers.
User specifications reviewed by the Working Group found very few to have consideration toward the
retrofit or repair scenarios and HV testing requirement. This is likely due to the evolving nature of the
user’s networks and limited visibility of the future of the potential criticality and availability of outages
for each installation once in operation. In most cases the decision for requirement of HV testing in
these scenarios will fall initially to the user to consider the feasibility of conducting a test in conjunction
with the OEM or third party to advise on the implications of the test for adjacent equipment, timescale
to realise, limitations that may be presented for the test voltage level, sensitivity of PD measurement
or limitations of the test equipment if the connection of the test voltage generator is located far away
from the section to be tested. The approach required is that of a risk assessment by the user to initially
assess the feasibility and impact of performing a HV test and then review the proposed procedure with
the OEM and third party.
In addition to the minimum requirements as detailed in Chapter 4 the site test procedure may
additionally include the following:
• Specification of which of the sections of the GIS will be tested and in which order, to consider
o Maximum allowed test voltage level(s) and times that existing parts can be subjected
to,
o Limitations of the test equipment,
o Operational considerations to keep parts of the GIS installation in operation during
testing,
o Minimising the number of components that could be subjected to multiple tests,
o Minimising the number of test voltage generator displacements if several components
and locations require to be tested,
o Dielectric condition of the insulation (e.g. where existing PD source known or other
potential emission source),
• Test and inspection procedures to follow in case a (dielectric) test is not passed successfully
(e.g. method of evaluation and identification/localisation minimising risk to existing GIS).
78
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Typical repairs in user experience demonstrated to the Working Group involved circuit breaker or
interrupter compartment dielectric failures and repairs. These typical ‘major failure repair’ scenarios
may require replacement of the interrupter, or the entire compartment and subsequent on-site HV test
to verify the integrity of the repaired or replaced component.
79
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
the test parameters that could be appropriately applied to the on-site test of the interface. A
compromise test procedure was devised resulting in application of service voltage only to the interface
with UHF PD measurement [B71].
The test report submitted by the OEM, or third party should be subject to review and acceptance by
the user. In addition to the key details to be included in the test procedure as detailed in Chapter 4
additional key information that users may consider specifying to be included in the final report
following completion of the testing may be as follows:
• Environmental conditions and status of the installation under test,
• Reference to the testing protocol and testing procedure documentation (i.e. documentation
record number or title),
• List of the test equipment and measuring instruments used including manufacturer and type
model number,
• Certificates of calibration of measuring instruments or reference to calibration document,
• Results for the HV test including repeated test conditions and details if there were any
flashover events:
o Disruptive discharge event, if any (voltage reached before the discharge,
investigations results, corrective works done),
o Corrective works done including details of any parts replaced, location and serial
numbers and/or type identifiers of the parts,
• Results for the PD test including repeated test condition and details of:
o Measured background PD level,
o Measured PD level of the GIS section under test,
o Detected partial discharge activities, if any (measured PD level, inception and
extinction voltage, discharge pattern (phase-resolved partial discharge - PRPD),
investigation, corrective works performed),
• Signature and statement of completion by the test operator and OEM technical responsible
appointee.
For traceability by OEM / user / third party additional information may be included in the on-site test
reports [B71], in order to possibly allow in the future to confirm the ultimate limiting factors for any HV
tests – especially when type tested design ratings are different to the user’s specification (e.g.
requirements for rated service voltage of the installation, insulation withstand or minimum short time
and continuous thermal rating requirements).
80
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Prior to any works commencing on-site, and more typically defined at contract placement stage may
be the requirement for a project or site quality plan to be produced. This is generally a comprehensive
document detailing the overall objective of the project and the quality procedures that will be used at
each stage of design, construction, commissioning, and handover.
The HV test and PD test during the on-site dielectric test of the GIS is typically where witnessing by
the user is the most important as it is the ultimate step for the acceptance of the installation. It also
constitutes an initial signature of the condition of the GIS prior to its energisation. For the OEM, this
step is generally contractual as the final and crucial evaluation of the quality of works done during the
erection of the GIS installation. For the user, this is one of the last chances to perhaps discover and
remedy any potential future defects affecting the insulation integrity of the GIS or highlight other
concerns. The goal of the OEM and the user is to obtain a GIS completely free of insulation defects, or
‘PD free’ at least. PD measurement however often does not give black and white answers.
Involvement of the user and witnessing of the trend in relation to testing of similar sections or other
installations may provide some basis for agreement by the user and OEM to the acceptability or not of
the measurement result if doubtful or give the user information on likely areas to focus on in future for
evidence of PD activity. This would be of special importance in the extension or repair scenarios
where the discovery or detection of PD in existing sections of the GIS not effected by the works could
provide vital information to the user of the condition of their GIS under their responsibility and prompt
inspection or future investigation.
User specifications were also seen to require additional PD measurement on GIS equipment
reassembled after the on-site dielectric test. Specific tests were specified to measure PD at the rated
voltage and frequency of potential transformers and surge arresters that may have been reinstalled
after the power-frequency test with UHF PD measurement in order to have a footprint of the UHF PD
activities at the commissioning for maintenance purposes and for future measurements in service.
81
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
• Report on deviations from the test procedure or any incidents arising to the users' specialists,
• Where suitably experienced, assist in determination and resolution of any issues arising
during testing (e.g. confirmation of PD pattern or influence of external source).
The witnesses should act in the role of observer and not actively participate in performing any of the
test operations unless agreed before commencement of testing as part of the test procedure. The
witness on site can assist to facilitate continuation of testing in a timely manner by reporting directly
back to the user or owner on issues arising and obtaining provisional agreement or objection where
required should any requirement arise.
A log or diary of activities and events can be useful for the witnesses to record observations or notes
of the test sequence and events, including cleaning flashovers or test equipment issues. This can be
cross referenced by the user when the test report is compiled by the relevant test engineer or their
quality department to correlate any events or any queries by the user’s specialists who may be asked
to formally accept the report when submitted. In many cases the OEMs report may contain only results
or confirmation of a successful test and little detail to aid the user where queries arise or repeat testing
is to be performed in the future.
Witnesses are recommended to keep a record of cleaning flashovers and suspected locations or
sections on a compartment drawing for future reference which may aid in the localisation of potential
future investigations and kept by the user. In a user example when connecting a HV cable to a spare
bay installed and tested approximately four years previously, a flashover trace was discovered on a
barrier insulator of the cable enclosure compartment which had been removed to facilitate the
installation of the draw-in type HV cable termination. A review of site test reports recorded a ‘cleaning
flashover’ logged against the bay in question, however the voltage was then maintained on retest and
even with duration extended to 1.5 minutes at peak level. No PD was reported during the subsequent
measuring phase. The OEM who had performed the initial site tests and supervision of the cable
termination works some years later concluded that the insulator had suffered a cleaning flashover
during the original HV test but withstood the full test voltage on reapplication.
82
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
diagrams including gas compartments arose. Covered in Chapter 4 is the topic of 'principles of colour
coding'.
On site, where test engineers or witnesses may be working with paper copy diagrams and several
switching operations or test phases needed to perform the testing, the method of creating diagrams or
record of the test section is more easily created or amended with simpler hand techniques. While
requiring the use of visual graphic tools - this is a quick and clear method of creating a visual plan of
the section to be tested for confirmation with all persons on site and may also be adopted by
witnesses to record the configuration of the GIS when under HV test. See APPENDIX D for further
examples.
83
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
84
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
if a large GIS section or several bays are energised at the same time. Some detection methods may
require sampling of gas in the compartments to detect indication of breakdown having occurred.
Should the power available from the network be of sufficient strength, this method, while it may be
slow and tedious can be suitable for users to localise faulted compartments for visual inspection. For
this reason alone, some users, regardless of the size and time required to energise the GIS, may
subject each section when first energised to soak periods anywhere from 10 minutes up to 8 hours.
An illustration of a staged energisation sequence typical to many users is contained in APPENDIX F
for information.
85
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
GIS insulation design that may be encountered - filling pressure, insulation gas composition, solid
insulation design etc.
Discussed in the Working Group the topic of 'margin' or level of tolerance for irregularities can differ
between different GIS designs, regions, and applications. The term 'margin', can be interpreted with
different meanings, most universally may refer to the operating voltage of the GIS relative to its design
insulation rating. GIS employed for use with higher design ratings than the rated operating voltage of
the user will clearly possess a higher insulation margin. In such cases additional on-site dielectric
testing over and above common standard requirements may provide little additional value and non-
dielectric checks such as gas quality and assembly cleanliness adherence may be similarly efficient
means of establishing dielectric performance as shown in the case of Japanese utility practices.
The specification of additional type testing such as voltage withstand tests at lower gas pressures to
determine the insulation margin by some users is seen as an indicator of the tolerance that may be
expected in the event of the insulation being compromised due to gas leaks in service. A specific user
requirement for GIS requires type testing to prove the equipment can withstand 1.5 times the rated
phase-to-earth power-frequency voltage between phases and earth with the insulating gas at
atmospheric pressure or 0 bar gauge pressure [B80].
While not an on-site or routine test it is an example of a user specific type or design test which may
influence their operating and maintenance regimes as well as on-site testing requirements. It is
notable that at the time of compiling this brochure the global GIS market continues to evolve with the
introduction of new GIS designs for alternative insulating mediums. Users may likely continue to
evolve their specifications accordingly.
When more stringent on-site testing is performed (or not), there is not yet adequate evidence to prove
if this may lead to higher reliability for the user in all cases. In certain cases stricter on-site testing
regimes may not provide any additional reassurance or benefit. This may be a potential area to be
captured in future surveys or feedback.
Some users of the Working Group in their return of experience noted positive perception, or a higher
perceived level of confidence in GIS installations tested to higher requirements then the recommended
standard. In one user case of a 245 kV GIS the 100 % on-site HV test level was adopted rather then
the standard 80 % level of factory routine testing. During the on-site acceptance test by the OEM, two
breakdowns occurred during the power-frequency voltage withstand test in the course of the voltage
rise toward the 100 % level on two different phase sections. Both defects were localised to circuit
breaker compartments with traces of the flashover discovered on the underside of horizontal insulators
in both cases.
Figure 3.17 245 kV GIS on-site HV test - flashovers during 100 % of factory routine test value
The insulators were cleaned according to the OEMs internal instructions, compartments closed,
evacuated, and filled to nominal pressure. Both phase compartments were retested successfully at
100 % level (460 kV) with an extended duration of PD measurement at 1.1xUr for 60 minutes as per
the user specification with no PD occurrences. In discussions with the OEM no apparent root cause
was initially found. The circuit breaker compartment had been routine tested in the factory and
remained sealed during transport and assembly on site. The change of state of the insulation could
not be traced to gas quality, therefore particles on the conductors were assumed as cause of the
breakdown, despite the breakdown being on the underside of the horizontal orientated insulator.
86
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
In both cases, it cannot be excluded that the flashover may have occurred anyway at the standard 80
% level given the tolerance or uncertainty of the measuring equipment. From the user’s point of view
the voltage had exceeded the 80 % level and concluded that this was a potential in-service failure that
was successfully discovered and averted as a result of the enhanced site testing.
Testing the GIS on-site to its full rated insulation withstand level was therefore deemed an appropriate
measure by the user. Although the exact voltage level at the time of the breakdown could arguably be
adjudged equivalent to the 80 % value, the change in state of the withstand capability of the insulation
between testing in the factory and transport, installation on site of a sealed compartment provides a
reminder of the importance of on-site HV testing to verify dielectric integrity.
87
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
88
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
2. Mid-term preparations before tests start (nominally some / few weeks before HV testing
period):
a. Confirm power supply suitable for test set (e.g. guide: 415 V three phase, 100 A),
b. Obtain necessary licences, certificates, work permits and access clearances for
(overseas-) staff,
c. Clarify responsibilities and authorities on site: organisation chart validates site
responsibilities,
d. Prepare Environment, Health, and Safety (EHS) risk assessment and test
implementation plan; need to be updated in regular intervals and when changes
occur,
e. For energised installations (GIS repair or extension): Confirm outage windows and
'return-to-service' time requirements,
f. For air-insulated HV test sets, space and safety requirements should be considered
as early as possible.
It may be important to consider on-site HV testing activities already in the 'pre-tendering' project
phase. The preparation period as described above is related to the time span for the preparation,
conduction, and evaluation of the on-site HV test (see Figure 4.1).
The items listed above must be agreed somewhere in the time span of user specifications for test
equipment. Special testing applications (e.g. for remote locations of GIS, limitations to building
spaces) may require special planning efforts.
89
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
90
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
for the safety of personnel and the protection of equipment. Correct earthing will also help to perform a
better measurement with less background noise for the purpose of PD measurements.
A safe and successful undertaking of HV testing requires good housekeeping near and around the
switchgear to be tested. This includes fences or barriers to prevent unauthorised access to the testing
area and an allowance of sufficient space for laydown areas. Particularly for new installations, where
construction activities may still be ongoing, this may be a challenge that has to be managed carefully.
4.1.4 Space requirements related to HV test equipment and HV injection
Planning of a GIS layout must include considerations for all aspects of testing requirements. While this
is usually less constrained where connection points are bushings, space may be more limited where
encapsulated test voltage generators are directly connected to the GIS enclosure, particularly for
indoor installations. The GIS layout must be set out such that access to HV injection points is not
obstructed and has sufficient clearance to walls, columns, or other plant. General arrangement
drawings must therefore identify suitable space requirements for HV test voltage generators and
associated test equipment, including enclosure adapters.
Additionally, sufficient clearance for installation and disassembly of the test voltage generator should
be considered, considering different sizes of test voltage generators. Not only can different set-ups be
used between manufacturers, but one supplier can have different sizes of test equipment available. It
is recommended to carefully examine whether the floor is strong enough to support the weight of the
HV test voltage generators and auxiliary equipment. Also, it needs to be verified that entrance doors
allow the equipment transport inside, and that possible obstacles (e.g. platforms, railings, or stairs)
can be (temporarily) removed.
Where space restrictions are confined to the switch room only, and external access is possible,
consideration for HV test connection via gas-insulated bus-duct (GIB) or cable (limited to specific rated
voltage levels) should be considered in the initial station design and construction. Specific design
considerations may involve access doors or hatches into the switchgear room. Where GIS is
constructed within transportable containers for offshore platforms or rapid build / deployment
substations, similar considerations may be required. Mechanical construction of the container should
be coordinated with the layout of the GIS to ensure access hatches or doors are suitably positioned to
allow installation and connection of the test adapter.
If overhead cranes are part of the building, sufficient reach of the crane must be considered to cover
for lifting test voltage generators during installation and disassembly on the GIS. Similarly, the weight
of the test set must be considered in the crane's specification (for new projects) or before using an
existing crane (for testing after repair or extensions). For all other cases, sufficient space must be
allowed for mobile lifting equipment to allow handling, installation, and removal of test voltage
generators. Depending on the size and configuration of the GIS, several different HV injection points
may have to be identified on the layout drawing, all of which require the same principles for access
and clearance as outlined above [B22].
The following photos show some examples for gas-insulated HV injection points in relation to
substation crane accessibility. Please note, these photos are taken during installation phases of the
test voltage generators.
91
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 4.2 Example for gas-insulated HV injection point considering the range of the substation crane
[B22]
Special consideration has to be given to situations in which an overhead line connects to the GIS by
means of SF6-air bushing especially if the test set has to be connected to the same SF6-air bushing. In
this case often AIS components (e.g. overhead line, surge arresters, capacitive or inductive voltage
transformers, etc) must be disconnected from the GIS. When AIS parts or overhead lines in or near
the substation remain under live voltage, due care has to be taken that sufficient clearance between
GIS bushings and test set on one side, and live AIS or overhead line structure on the other side is
maintained.
If a disruptive discharge inside the GIS installation occurs during testing, voltage surges with high
amplitudes and steep wave fronts can occur inside the GIS. These waves could reflect on certain
points of changing surge impedance inside the GIS installation or at an open end. In a worst-case
situation this causes doubling of the wave crest value. Depending on the calculation method and
safety margins applied, safe air clearance distance for a 420 kV GIS tested with lightning impulses
between 8 metres and 11 metres may be determined [B81]. For higher voltage levels, even larger air
clearances between test set or GIS bushings and live AIS or overhead line parts should be
maintained.
92
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 4.3 Example for air-insulated HV injection point with outdoor HV test set connected via GIB [B41]
The following points should be considered when applying HV test equipment to the GIS:
• Gas-insulated HV injection point:
o An adapter to match the GIS enclosure may be required,
o Ensure that both ends of the adapter fit, e.g. GIS at connection point(s) and test set,
o Different connection points on a GIS may have different sizing,
o Careful connection of the active part (in particular when PD testing is performed; a
loose connection on the active part may be the cause of PD activity).
• Air-insulated HV injection point:
o Connection via a SF6-air bushing, either an existing bushing of the GIS installation or
a testing bushing for tests only,
o Access for testing via extended test adapter (e.g. gas-insulated busduct),
o Sufficient clearance is required to the exposed test voltage; specific consideration
must be given to exposed shapes, leading to high field strengths; these can lead to
discharging disturbance during test (external flashover or corona); corona shields
(also makeshift) may be required to treat sharp exposed geometries,
o Avoid also unearthed metallic objects nearby.
• Cable socket HV injection point:
o The cable socket test adapter to match the GIS cable socket should be sufficiently
rated for the required test voltage,
o Capacitance of the cable and length should be included in the load calculations of the
test set.
93
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
The latter injection technique allows a high flexibility for the placement of the HV test set to locations,
where enough air clearance for the test voltage and minimal risk / obstruction of pathway for personnel
is available. Current experience shows reliable function with numerous plug cycles of cable socket test
adapters for testing GIS up to 245 kV rated voltage with test voltage levels up to 380 kV. Cable socket
test adapters are a universal solution, since the HV test voltage generator can be placed in suitable
locations of the substation within the reach of the cable length of the test adapter.
The examples in Figure 4.4 till Figure 4.10 show different HV injection techniques (air-insulated and
cable socket) in combination with the applied test set type and the necessary space requirements.
94
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
(Test voltage 380 kV; UHF PD measurement 294 kV for at least 30 minutes;
left: view from GIS;
right: view showing the HV test set;
air clearance of top toroid of test set reactors to cavern ceiling 1.2 m)
Figure 4.6 Example of cable socket HV injection point for testing of a 245 kV GIS in a cavern of a pump
storage plant in the Swiss mountains
(Test voltage 325 kV; UHF PD measurement at 204 kV for at least 30 minutes)
Figure 4.7 Example of cable socket HV injection point for testing of a 170 kV GIS in an underground
substation in Zurich [B53]
Already in the planning phase of this project, an opening in the floor towards the cable cellar was
foreseen for the application of the 'cable socket HV injection' technique.
In certain cases, the HV test set can even be positioned outside the GIS building, as illustrated in
Figure 4.8.
95
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
(Test voltage 40 kV; equipped with a coupling capacitor for conventional PD measurement)
Figure 4.10 Example of cable socket HV injection point for testing of a 24 kV GIS
An ideal situation occurs when all sections of the GIS can be tested, and no further opening is
necessary following the HV test. This includes also testing of the VTs with the specified test
parameters of the MV GIS, using a frequency-tuned resonance test set and applying the test voltages
with a suitable frequency for the VTs. Testing experience has shown that the PD defect type ‘particle
96
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
97
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
test. Sections and/or phases that are not involved in the test, must be isolated and/or earthed. This
also applies to the situation in which the GIS is equipped with air-insulated bushings. In this case, it
may be necessary to remove the overhead line or wire from the GIS bushing and the other end may
be grounded if necessary. Also, the phases not under test are typically (externally) earthed at the
bushings.
4.2.2 Principles of 'colour coding'
Different methods are used by OEM / user / third party to prepare ‘shut down’ plans. The following
sub-section provides more insight into situations, the use of ‘colour coding’ and switching
configurations.
Safety at work has the highest priority. An important point to ensure safety for on-site works is
respective instructions and drawings to explain and visualise working steps. Different conditions or
situations can be clarified by means of colours. Different colour codes were used to illustrate technical
conditions. To harmonise different existing approaches, it is proposed to align with the following
colours based on [B83].
During the lifecycle of a GIS, many activities can be the reason to de-energise parts of the GIS for
opening gas compartments. These activities can be:
• Maintenance / repair work on a GIS or on parts of it,
• Extension of a GIS,
• Retrofit of a GIS.
All these activities require a ‘shut down’ plan for the involved GIS sections. The preparation of a ‘shut
down’ plan is not a straightforward task. Typically, two different quantities must be considered
simultaneously while preparing a ‘shut down’ plan:
• Voltage (live section, point of isolation, earthed section),
• Pressure (required status of gaseous insulation in gas compartments).
Figure 4.11 Two colour code options - harmonized in CIGRE WG B3.51 and B3.50
Both options shown in the figure above were discussed and established by the CIGRE Working
Groups WG B3.50 (Concepts for on-site HV testing of GIS after installation, extension, retrofit or
repair) and WG B3.51 (Service Continuity Guide for HV GIS above 52 kV).
During the mentioned discussions it was found that preference for either option can be (strongly)
dependent on the current time position of a GIS project. So, for the GIS project phase when 'service
continuity aspects' are considered relevant, both options in the figure above can be generally used.
One can interpret the figure above also in terms of a given order. But this is not intended nor valid.
One can also interpret the order of application like 'traffic lights' (yellow must always be between a red
and green section). This could also increase the safety aspect in terms of switching conditions.
4.2.3 Switching configuration - GIS after installation
A detailed test procedure is part of every test preparation. The test procedure includes a single line
diagram with (coloured) visualization of the desired configuration of all switching devices prior to the
98
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
test to ensure a safe working situation and to be able to connect the HV test set. This includes the
switching configurations (e.g. switching plan), step by step, during the test.
A new GIS will normally be HV tested before any part of the GIS is energised and before any HV cable
is connected. The absence of any energised part(s) reduces the risk during test and simplifies the
preparation of the switching plan.
The number of switching configurations depends on the capability of the test voltage generator, the
number of HV injection points and the agreement between user / OEM / third party. In some situations,
the complete GIS is tested with only one HV injection point as shown in Figure 4.12. This advantage is
contradictory to the number of components that are unduly subjected to multiple tests and the test
generator displacement [B24]. In other cases, the test set will need to be moved to another or even
multiple HV injection point(s), which can be also considered contradictory when a minimization of HV
injection points is intended.
Figure 4.12 HV test switching configuration with one HV injection point for complete 170 kV GIS
99
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
In general, retrofits contain replacement of parts (often major parts like active modules) with new parts
of enhanced functionality and/or enhanced specification. This activity is also often related to
upgrading/uprating of technical data of the affected part [B84].
There are two practical examples showing different approaches for the HV test after a retrofit and
refurbishment of the GIS.
The first example is a single-phase enclosed 170 kV GIS (air) where a refurbishment was planned,
and the circuit breakers were exchanged for SF6 retrofit breakers. Performing the HV test after the
retrofit circuit breakers are installed, is a commonly used procedure. This GIS is equipped with double
gap disconnectors, whereby the disconnector is earthed directly in the open position. To perform the
HV test, the test set needs to be connected to the HV injection points, which is - in this case - located
on the single-phase enclosed busbars. This entails that the test set would have to be moved from
busbar to busbar during the work at one bay. The retrofit of the GIS is performed bay by bay, so this
also means that the test set is replaced multiple times.
In addition to the fact that this takes an enormous amount of time, this also means that a lot of work is
necessary to release and pressurize the busbar with dry air insulating gas. It was agreed between
user and OEM to not perform the HV test after the retrofit circuit breaker was installed into the circuit
breaker compartment.
Instead, the on-site HV test and PD measurement have been performed on the interrupter unit next to
the GIS in a separate circuit breaker compartment. After a successful test, the circuit breaker unit was
removed from the test compartment and placed in the circuit breaker compartment. The on-site HV
testing parameters have been agreed between OEM and user with some deviations compared to the
original standard referring to the retrofitted GIS generation (e.g. withdrawn IEC 517) with having:
• HV test voltage 325 kV / 1 min. (100 %),
• After adjustment of the test set-up,
o PD pre-stress voltage 208 kV / 10 sec.,
o PD measurement with coupling capacitor 187 kV / 10 sec.
Figure 4.13 Single-phase on-site test set-up next to the 170 kV GIS
If it is necessary to perform an HV test on the single-phase busbar (e.g. after repair of a busbar
disconnector) a test adapter to access the test section needs to be placed in the circuit breaker
compartment of the coupling bay (see Figure 4.14).
For this, the circuit breaker with drive mechanism must be removed from the circuit breaker
compartment to install the test adapter, because of non-availability of HV injection points in the busbar
compartment. So, risks for contamination increase under the given circumstances.
100
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 4.14 Single-phase on-site AC test voltage generator with test adapter and switching plan for the
busbar disconnector in CLOSE position on 170 kV GIS
Another example is the refurbishment of a 170 kV GIS where a spare circuit breaker is used as a
swappable replacement circuit breaker. The user requirement states that for circuit breakers in its own
enclosure with its own gas compartment, on-site HV-tests do not have to be performed if the
corresponding factory acceptance test of the circuit breaker is carried out in its own or test housing at
100 % test voltage level and at minimum filling pressure.
The circuit breaker is removed horizontally from its compartment during the refurbishment of the bay.
To be able to quickly use the complete bay again for operation in case a problem in the network takes
place, a spare circuit breaker (which has already been refurbished) is placed in the circuit breaker
compartment.
In this case, the circuit breaker is transported to the factory for refurbishment. The OEM has a
prepared circuit breaker compartment in the factory where an HV test is performed on the overhauled
circuit breaker. After finishing HV test and PD measurement the circuit breaker is afterwards
transported to the location where the circuit breaker is used as swap for the refurbishment of the next
circuit breaker. During this refurbishment, no HV test or PD measurement is performed on-site [B85]
4.2.5 Switching configuration - GIS after extension
Dealing with GIS extensions or stepwise replacement of an existing GIS, in almost all cases parts of
the GIS are in service – contrary to new GIS installations.
Since flashovers with service voltage when GIS is connected to the network are much more
destructive than flashovers with test voltages as the test equipment has limited power, special
precautions must be taken. When live air-insulated bushings come close to testing bushings, safety
distances have to be chosen which prevent a flashover from tested parts to live parts. Large potential
differences between the service voltage and the test voltage occur periodically due to phase
opposition. On top of these large potential differences transient overvoltage cannot be excluded on the
101
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
test voltage as well as on the service voltage side. Calculation of an adequate safety distance may be
found e.g. in [B21], [B81].
At new GIS installations typically place for spare feeders is planned which can be used for connection
of an HV test set. If no additional place is planned for the installation of a HV test set the spare feeder
space is missing when it is used for the extension of the GIS. One possibility to overcome place
problems are test cables, which can be applied when feeders are equipped with pluggable cable
connections.
Within the GIS it is strongly recommended to always have an earthed section between live and tested
parts. However, publication [B86] describes a different approach, which is considered very
controversial according to the Working Group opinion. Therefore, this is disregarded and not reflecting
the current state of the art.
Another important point to consider for GIS extensions and their switching configurations is
represented by the determined test voltage level in respect to the age of the existing installation.
For instance, when HV tests are performed on the interface between the extension and the existing
GIS, a part of the existing GIS (e.g. up to the first separation option on the existing GIS) will be
submitted to the test voltage which has been defined for the extension. If the existing components
could not support the rated test voltage value of the extension, the interface will have to be tested with
a reduced test voltage value. The chosen configuration of the test circuit should minimize the
extension that will be tested at this reduced test voltage value. This could be achieved by selecting an
appropriate HV injection point for the test voltage generator when testing the interface, or by
performing the dielectric test of the extension contained in the interface test circuit in two stages - first
at a reduced test voltage value and second at rated test voltage value [B23].
Due to the need to keep parts of the GIS in service and the limited flexibility in adaption of the
switching configuration to the test procedure, detailed planning and alternative scenarios have to be
included in case faults are found during the test causing delays. Especially spare parts for both types
of GIS together with personnel familiar with exchanging possible faulty parts have to be right at hand
in order to avoid any further delays.
Additional work before tests for an installation of an extension to an existing GIS can include:
• Evaluate the requirements and possibilities of the connection of new and existing GIS parts,
o Is an outage of the existing part possible or is there a minimal configuration to stay in
service?
o Find a date that allows maximal duration for the required minimal service
configuration
• Allocate personnel and spare parts for possible defect removal or repair in new and existing
GIS part (important point if new and existing GIS part are of different type or OEM),
• Elaborate detailed switching plan for the connection and testing of new and existing GIS
including possible configurations in case of delay by defect removal or repair in new and
existing GIS parts,
• Allocate additional time for the preparation and execution of the extension, since:
o Mechanical mismatch and different mechanical details of the existing GIS part due to
e.g. incomplete documentation can cause delays,
o The connection of new and existing parts (especially the secondary circuits) can
require time consuming checks to prevent unintended tripping of safety circuits.
In the following, two practical examples are presented showing different approaches for the switching
configuration in case of GIS extensions and even replacements [B76].
At first in Figure 4.15 an extension of a single-phase encapsulated GIS with a three-phase
encapsulated GIS is shown:
102
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 4.15 Example of an intermediate stage at the connection of a GIS extension [B76]
The busbar on the rear is already connected, the one in the front is not yet connected. The different
stages of the connection of new and existing GIS are illustrated in the following schematic figure.
Figure 4.16 Example of possible stages in the connection and testing of new and existing GIS [B76]
After the new feeders of the extension are tested in step A, the lower busbar is connected to the
existing GIS (step B). The lower busbar is tested in step C followed by the connection of the upper
busbar to the existing GIS (step D). Finally, the upper busbar is tested in step E and the extended GIS
can be given over to service in step F.
At an on-site HV test of an extension with similar stages - as described in Figure 4.16 - two PD defects
in the existing installation were detected and successfully removed which included the replacement of
a disk insulator. The test voltage level of the new GIS and the existing GIS were equal and
corresponded to the 80 % voltage withstand test according to IEC. The UHF PD measurement was
performed at 1.2xUr for at least 30 minutes.
After that, it is shown how the replacement of an existing GIS with a new GIS can be optimised in
terms of reopening of gas compartments after site acceptance tests. Figure 4.17 illustrates an
example of a test sequence applied for the stepwise replacement of an old GIS with a new GIS,
keeping parts of the substation in service.
103
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 4.17 Sequence of a replacement of a GIS without reopening of gas compartments after site
acceptance test [B76]
In a first step, a minimal GIS configuration was installed allowing to keep the substation running at the
required minimal level. The number of bays was restricted by the available place in the GIS hall. This
GIS configuration was tested in step A with a cable test adapter (e.g. cable socket HV injection) and
air-insulated test set via cable feeder with pluggable cable connection.
After site acceptance test of part 1, the cables were moved from the existing GIS to the new GIS part
1 and the existing GIS was dismantled. In a second stage, part 2 of the new GIS was installed and
connected to part 1. Due to part 1 of the new GIS being in service, the site acceptance test of the
second part was divided into two test sections as indicated in phase B and C of Figure 4.17 in order to
make sure to have an earthed section between the service and the test voltage.
The gas compartment of the longitudinal busbar disconnector in step A stayed untouched for the
connection of the new GIS part 2 which results in a full test of the entire busbar not leaving opened
gas compartments untested. The application of a test cable allowed great flexibility in test voltage
injection, placement of the test set as well as leaving all gas compartments untouched after the
successful site acceptance test.
The on-site HV testing parameters agreed between OEM and user for that 170 kV GIS having a test
frequency between 135 Hz and 155 Hz:
• Conditioning: 50 kV / 10 min.; 100 kV / 1 min.; 210 kV / 1 min.; 270 kV / 30 sec.,
• HV testing: 325 kV / 1 min. (100 %),
• UHF PD measurement: 204 kV / 30 min. (1.2xUr).
In an additional practical example, a 420 kV GIS from OEM no.2 was installed to extend an existing
HV GIS from OEM no.1. Some general testing parameters as well as some special aspects when HV
GIS from different OEM are connected are presented [B77].
The on-site HV testing parameters agreed between OEM no.2 and user were:
• Conditioning: 291 kV for approx. 15 min.; 420 kV for 3 min.,
• HV testing: 515 kV for 1 min.,
• PD-measurement: 291 kV.
The testing equipment used encompassed a frequency-tuned resonant test set and UHF PD detection
equipment. Overall, four test sections were planned and agreed between OEM and user to cover the
relevant on-site HV testing. Figure 4.18 displays the test sections in more detail.
104
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
section 1
section 2
105
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
section 3
section 4
Figure 4.18 Different test sections for 420 kV GIS extension [B77]
Test section 1 2 3 4
Connection of HV test set bushing –Z1 at bushing –Z1 at bushing –Z1 at bushing –Z1 at =Q06
=Q05 =Q05 =Q06
Details of test section =Q05.A, =Q05.B BB 2B, =QB5.C, =Q06.B, =Q06.C BB 2A, =Q06.A, =Q07A,
=Q07.C =Q07.B
106
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Both types of HV GIS have been permanently connected by a so-called 'connection module', which
has to be designed for this situation by OEM no.2. The challenging task in this case was to perform
the dielectric design without complete knowledge of some relevant design values of the partition to
which a connection of the inner conductor was necessary. This module was not removed after the HV
test. It remained installed permanently. The following figure shows some more details of different
substation and section views.
107
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
be considered to ensure successful testing. The availability of the test equipment can be very critical
due to tight planning. Disturbance can be caused by calibration or repair of the test set-up, logistics
(transportation around the world, e.g. ATA-Carnet, customs clearance, etc) or the availability of the
aforementioned four elements. Some margin will also have to be maintained in the planning for
unforeseen events during the test.
HV equipment is expensive and must be taken care of. Depending on the agreement between OEM
and utility, the HV test set of the OEM, a third party or the utility’s will be used. Experience shows that
users order adaptation modules and parts with the original GIS so as not to be dependent on the
supplier. This will be stored and must be transported to the station by the owner.
108
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 4.20 On-site HV testing experience after GIS extension ([B2] figures 6-16 and 6-17)
The known dielectric condition of the existing substation section involved in the test is another relevant
historical data to collect. This might ensure a better preparation for the dielectric test of the interface
and anticipation of the problems and consequences that might be revealed by the test. When the
dielectric condition of the existing substation is known to have deteriorated significantly (e.g. confirmed
presence of PD activities that could not be eliminated in advance of the planned HV test) the content
of the test procedure might be adapted in order to avoid the presence of those PD sources in the test
circuit. The latter is sometimes not possible due to various reasons (e.g. technical limitations or
operational restrictions).
However, if this is still possible or by retrofit with (temporary) external PD sensors for the dielectric
test, a better discrimination or even isolation and elimination of the PD defect during the dielectric test
between old and new part of the substation can be possible. In general, if an existing PD source in the
old GIS may not be avoided or removed for the dielectric test, the test personnel will have to seek a
solution. This might affect the acceptance criteria of the test itself. When the dielectric condition of the
existing substation is unknown, it can be helpful to consider doing some additional PD measurements
(e.g. as service activity or part of the test procedure itself) in the existing part of the GIS in advance of
the planned on-site HV test of the GIS extension to allow a better assessment of the dielectric
condition of the existing substation [B47].
4.4.3 Applied test method
HV test and/or PD measurements on extension bays were often tested stand alone. So busbars were
not coupled while executing the on-site HV test. Afterwards, the busbars were coupled to the existing
GIS.
However, requirements have changed in recent years and users are much more likely asking to
perform a HV test after coupling the busbars. Nowadays, it is common that users consider that an
extension must be possible and to perform an HV test after coupling. Experiences of an OEM between
2016 and 2019 show that 21 extensions have taken place on installations that are several years old
(1978 - 2016). In 80 % of these cases no HV test or PD measurement was performed after coupling to
existing GIS. In 10 % of the cases, an HV test and PD measurement was performed and in 10 % of
the cases only a PD measurement.
Table 4.2 Return of experience for HV test methods of GIS extensions [B72]
109
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Besides the return of experience on the applied test methods after GIS extension, also the situation
after GIS repair or refurbishment displays a wide variation between the applied test methods.
Constraints which lead to the applied test methods in the end might vary greatly [B22].
Table 4.3 Return of experience for HV test methods after GIS repair or refurbishment [B22]
(1980, 1982, indoor 1992 repair & 220 - initially AC HV, but 30 min.
1988, 2004) refurbishment changed to AC ‘soak
test’ with rigid QA
regime
In general, refurbishment activities are considered as major works on GIS subassemblies to ensure
the original functionality but for an extended period than without refurbishment. These works are
typically planned in the long-term and would be done after GIS mid-life onwards [B84].
Sometimes, the return of experience regarding applications of PD measurements in conjunction with
on-site HV testing activities trigger intensive discussions between OEM and user. For instance, user
specifications can require complementary PD measuring methods (e.g. conventional and non-
conventional). Technically this can be possible depending on sensor availabilities on the GIS under
test as well as on noise situations for that specific substation. However, in this case it should be clear
that one test method is leading, the other test method is for information only. Nevertheless, this can be
helpful for the substation operational maintenance as the PD testing results can act as reference
situation e.g. after GIS installation, repair, or extension [B47].
4.4.4 Specific situations (HV GIS and HV cable)
In general, the discussion towards an agreement between OEM / user / third party on a HV test
procedure can be quite controversial, and some negotiation could be necessary to conclude in a
coordinated and consolidated basis (e.g. in case of HV GIS that needs to be tested on site together
with already connected HV cables).
The following paragraphs describe a user case as an example [B66], [B67]. In this case, several
situations have been described that are mainly related to the age of the cable or GIS, for which
generally 5 years of use are considered to determine whether the GIS or the cable is 'new' or
'existing':
• GIS:
o New GIS equipment shall be tested on site at the routine test voltage values
according to IEC 62271-1,
▪ This is a clear deviation of the recommendations in IEC 62271-203,
o Existing GIS equipment (> 5 years old) shall be tested at 80 % of the routine test
voltage values according to IEC 62271-1,
110
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
old cable • dielectric 'weakest link' determines the • GIS shall be AC HV tested separately
test voltage value prior to connection of cables
• Cables shall be AC HV tested after its
connection to GIS with their prescribed
test voltage values (parts of the GIS may
be subjected to lower test voltage
values though)
This situation also raises the following issues, to which no clear answer can be given yet [B66]:
1. (Re)connecting the HV cables poses a risk to the cable termination compartment of the GIS
(e.g. this compartment cannot be tested at the prescribed test voltages at this point),
2. If the HV cable disconnector is opened to separate HV cable and HV GIS, the cable side of
the GIS cable compartment may not be subjected to its prescribed test voltage. The GIS cable
termination will only be tested (to earth) with the specified cable test voltage, which could be
as low as 2xU0 (439 kV instead of 515 kV for a 420 kV GIS).
Considering the above issues, design recommendations for the GIS would cover these cases (e.g. a
removable link in the cable termination compartment). The risk that (parts of) the GIS cable
compartment will not be tested after cable installation will have to be evaluated or even minimized.
111
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
However, when an extension of a HV GIS has taken place and one or more HV cables are mounted
on the cable end terminations of the extended bays, it may be necessary to test the cable after laying.
When air-insulated switchgear is used on the other end of the cable, the cable can be tested from this
end. In case the cable is connected on both ends to GIS, an alternative HV injection point needs to be
found onto the GIS. An alternative HV injection point could be an encapsulated connection or a testing
bushing solution, an example is shown in Figure 4.21. This may result in increased heights to attach a
test adapter or similar, but it can be advantageous to take this already into account during the
substation design phase [B8], [B65].
In Switzerland it is reported as common practice to apply parts of the GIS with the cable test voltage to
check the dielectric integrity of the cables including the GIS cable connection in the plugged-in
condition. [B7] Annex C.3.2 gives (non-normative) guidelines for 'practical situations' where a reduced
site test voltage could be considered. This should be agreed between user and manufacturer before
the test. In the situation of numerous cable connections to the GIS, connecting the cables together via
the GIS, and testing them from one HV injection point, can offer time and cost savings. In case a
voltage transformer is in the section under test, it is advisable to disconnect the VT possibly via a built-
in disconnector. If this is not possible the test frequency of the (resonant) test system can be
increased to prevent core saturation of the connected VT. Consequently, the VT can remain in the test
section. As a last measure – e.g. if cable of very long length in combination with high testing voltage
limit the application of a test voltage with sufficient high frequency – the VT must be removed. It is
considered that the test voltage levels for cables are lower compared to those for GIS, and therefore
do not pose any problem for the GIS itself.
Figure 4.21 Examples for test adapter used for HV testing of cables already connected to a GIS [B8], [B65]
112
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
o The padlocked earthing switch in CLOSE position that allows the test circuit to be
protected against induced voltage or accidental refeeding from the network,
o All switching equipment under test in CLOSE position,
o All earthing switch under test in OPEN position,
o The dismantling of the removable link at the interface of power cables and/or power
transformer bushing and the earthing of those equipment, if any,
o The positioning and HV injection point of the HV test voltage generator,
o One earthing switch in CLOSE position used to earth the test section (typically, an
appropriate earthing switch is defined in advance for this task).
• Requirements for secondary wiring of CT, VT or connection of SA or VT (in case of 'test
frequency'-based reasons),
• General information on the HV test set-up (e.g. encapsulated or via bushing etc.) as well as
requirements of the connection power of the HV test set-up,
• Information on clearances for HV injection point (e.g. the HV injection via bushing, so
connected OHL needs to be disconnected and switched off and earthed),
• General information on the PD measurement setup (e.g. conventional or non-conventional
method, and which sensors will be used in each case),
• A check list for the preparational works to do before the HV tests,
• Safety procedure to follow before, during and after the HV tests,
• Final verifications and actions to perform before starting the HV test (e.g. verification of
switching configuration, safety meeting with people involved with HV test, etc),
• Roles and responsibilities before and during the HV tests between OEM / user / third party,
Test report
The other part is prepared by the OEM or a third party and provided to the user after finishing the HV
test. Often this documentation is named as ‘test report’.
The content of the test report documenting in detail the test results of each test section. Typically, the
test parameters to be applied, and the test results are listed. Sometimes, additional short
documentation could be given, such as information regarding certificates of testing equipment or
'cleaning flashovers' within the conditioning phase. In case of irregularities, the test report should refer
or be extended with an annex or attachment, depending on the cause, which may describe the cause
and measures carried out and serve as a historical reference.
113
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
• Selection of a suitable test set type (e.g. if voltage transformers have to be tested with the
GIS).
The voltage measurement shows a valid calibration for its use on site. It can be advisable to verify the
voltage measurement using a voltage transformer installed on the GIS, if available.
4.6.1 Technical requirement for testing equipment
In general, testing equipment may be stored and transported in transport boxes. Equipment must be
properly secured in these boxes and protected by foam or similar protection to avoid damage by
impact and transport by road or air (see Figure 4.22).
114
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
In normal operation the higher (low-frequency) test current can be carried by the cable, and in case of
a disruptive discharge the transient (high-frequency) current can be carried by the copper foil.
Using the grounding system of the test object itself as a reference earth can also be advantageous, as
usually the grounding system of the test object (e.g. GIS, cable termination) has the best connection to
on-site earth.
4.6.2 Qualification of test engineers
In addition to technical knowledge, the test engineer should preferably have more skills. This can be
divided in further technical and communication skills. In any case the test engineer must have
attention for his own health and safety during testing and all other personnel involved in testing. In
general the test engineer needs to have knowledge in, or have experience with:
• Language skills,
• Cultural sensitivity,
• Leadership skills (e.g. instruction to troubleshoot / pressure resilient / understanding for
quality).
Before conducting on-site dielectric testing on his own, a new test engineer is traditionally educated by
experienced test engineers by accompanying high voltage tests and leading them under the
supervision of the experienced engineer (e.g. learning on the job).
Users may have requirements in their specifications about codes of conduct or specific regulations
that may have to be followed regarding safety, certification, task definition and agreement related to
labour union demands, etc. This may affect the realization of the on-site dielectric test. Those
requirements may affect the roles and the responsibilities of the user and the OEM at the different
phase of the on-site dielectric test from the preparation, realization, and completion of the test. The
implications for the test engineer of those requirements may extend the duration of the test, impose
formation and certification of their personnel, result in exclusive tasks that may have to be done by or
done jointly by the user employees or their representative, etc.
In general, the test engineer could come from:
• OEM,
• User,
• A third party.
The following list gives an overview about possible relevant tasks for the test engineer:
• (Supervision of) unloading, erection and functional testing of HV testing equipment,
• Managing site preparation (kick-off meeting) (e.g. check of testing area; identification of
obstacles),
• Set-up and disassembly of testing equipment (or instructing site personnel regarding the
(dis-)assembly and (dis-)connection of testing equipment),
• Specific knowledge of the GIS installation to be tested, especially with regard to:
o Operation of switching devices,
o Assembly knowledge of GIS components (e.g. assembly works for connection of tests
adapters),
o Presence of components that may not be subjected to test voltage, like inductive
voltage transformers and surge arresters, and/or the proper way to disconnect them
from the test circuit,
o Terminal treatment for CTs and VTs (short-circuited or open, burdens, fuses of VT
burden, etc).
• Knowledge about the relevant standards or agreements between OEM and user,
• If applicable: installation and set-up of PD measuring equipment; knowledge of basic PD
theory, calibration of coupling capacitor or sensitivity check for UHF, usage of PD monitoring
system,
115
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
116
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
117
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
118
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
continuity of existing substations due to the large outage zones that are generally required with this
technology of testing generator [B47].
The present return of experience covers occasional deviations between the plannings confirmed in the
test procedure and the situation on site in the preparation of installing the testing equipment, as OHL
outages may not be provided and so making some kind of adaption of the test procedure necessary at
short notice.
The following example for on-site HV testing of HV GIS after retrofit (e.g. conversion of OHL feeder to
cable feeder and addition of shunt reactor) describes some manifold challenges for which applicable
solutions must be realized (long-term planning and short-term on-site activity). Often, on-site HV tests
in live substations suffer from several constraints, such as:
• Constraint of obtaining an outage during the scheduled test period,
• Extensive time consumption due to phase-by-phase test procedures in case of single-phase
encapsulated HV GIS,
• Installation restrictions of adjacent live bays for induced voltage (user specification, user
safety regulations),
• Maintaining safety clearances (user specification, user safety regulations),
• Space constraint in gantry area.
In the shown case the main constraint has been a low safety clearance of one phase of the section
under test towards an OHL in the gantry area. So, a special solution and arrangement must be
developed and installed. The main feature is the simultaneous application of the HV test voltage to all
phases of the single-phase encapsulated HV GIS. So, an adapter module to connect one testing
bushing to the section under test was installed (see Figure 5.1).
Figure 5.1 Example for restricted safety clearance to OHL in gantry area [B73]
119
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Often, the situations on-site facing air-insulated HV injection points are characterised by having to
place the HV test equipment outdoor at reasonable and sometimes challenging locations. The
following examples display some of these extraordinary places for positioning of HV test equipment
outdoors (see Figure 5.2, Figure 5.3).
Figure 5.2 Outdoor positioning of HV test equipment on roof of transport container [B87]
Figure 5.3 Outdoor positioning of HV test equipment with noisy background for PD measurement [B87]
But this connection technique is also applicable indoor when special space requirements or specific
GIS layouts are given. The following examples show some of these situations in Figure 5.4, Figure
5.5.
Figure 5.4 Indoor installation of HV test equipment for air-insulated HV injection point [B87]
For some HV GIS substation layouts with 'cable bay design' only, special 'cable test adapters' can be
designed to incorporate testing bushings offering a connection point to the HV test equipment [B8].
120
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
These adapters are used for HV testing of cable systems after initial laying, repair or diverting and are
typically developed by both the OEM and the user in conjunction.
Figure 5.5 Cable test adapter for HV tests on cable systems [B8]
Sometimes, circumstances related to 'time windows' resulting from network constraints or delays in
the project timeline for performing on-site HV tests can also lead to different variants when installing
the HV test set. Therefore, connecting all three phases in a single-phase encapsulated HV GIS to run
an on-site HV test are realized from time to time. Figure 5.6 displays such a test set-up.
Figure 5.6 Example for installation of HV test set with constraint [B88]
In this case, one should be aware of an unfavourable situation for the dielectric insulation of the non-
affected phases when a flashover occurs (in an affected phase). Also, in [B21] some information is
121
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
given, that this kind of test set-up can occur. However, a proper installation of HV test sets including
PD measurements is displayed in Figure 5.7 considering some residual construction works.
Figure 5.8 User case study of specific HV testing situation - tests with air-insulated HV injection (‘outside
to inside’)
A further case study presents some impressions concerning the distances between test voltage
generator and testing bushing which must be bridged by ‘PD-free’ HV connections.
122
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 5.9 User case study of specific HV testing situation - tests with air-insulated HV injection via long
distances [B94]
123
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
• Standard socket can be used as power supply (e.g. three-phase, 400 V, 20 A),
• No gas handling at site needed for HV test preparation.
Besides having a higher functionality of a HV GIS also some disadvantages need to be considered.
These are seen in higher investment costs for the 'Power VT' (compared to VT) itself, possible
limitations for conventional PD measurement facilities, and restrictions for load cycles to allow
sufficient cooling time, leading to the overall HV testing time being longer. Nevertheless, the
capacitance of the GIS section under test is typically limited to a few nF, and the conditioning
procedure in conjunction with the on-site HV test can be different too. This can result in shorter
durations for the applied HV test voltages on the specified voltage levels compared to e.g. frequency-
tuned or inductance-tuned resonant HV test equipment.
Therefore, the applicability of 'Power VTs' is quite typical for rated voltages up to 145 kV or 170 kV.
They can also be used for rated voltages up to 245 kV equipment, which provide testing capabilities
with test voltage levels up to 380 kV / 50 Hz / 1 min. / approx. 1000 pF.
An example overview is given in Table 5.1 to indicate some possible test loads.
Table 5.1 Example overview of test loads for 'Power VT' [B64]
Furthermore, in Figure 5.10, Figure 5.11 a sketch for a basic circuit diagram and some examples for
'Power VT' positioning in different GIS layouts are displayed.
Figure 5.10 Basic diagram for HV testing with 'Power VT' [B90]
124
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 5.11 Examples for 'Power VT' positioning in different GIS layouts [B90]
125
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
However, the switching condition for the different test circuits needs to be finally confirmed before HV
tests commence.
In an agreed test procedure typically some of the following information have been listed (see
Chapter 4.5:
• The padlocked disconnector switches and the power connection removal that allow the test
circuit to be isolated from the network (e.g. in case of GIS repair or extension),
• The padlocked earthing switches in CLOSE position that allow the test circuit to be protected
against induced voltage or accidental refeeding from the network,
• All the switching equipment under test in CLOSE position (for special tests of switching
equipment in OPEN position particular consideration within the test procedure should be paid
to),
• All earthing switches under test in OPEN position,
• The operation of removable links of power cables and power transformer bushings including
the earthing of those equipment, if any,
• An assigned earthing switch in CLOSE position used to earth the test circuit when not running
the test sequence.
The access to the GIS in preparation for the HV test, to the test voltage generator and to the partial
discharge measuring instrument is often limited to personnel involved in the tests. For air-insulated
test voltage generators, a zone with restricted access can be erected to protect personnel against high
voltage. It can be beneficial to position dedicated personnel to supervise the access to those zones for
the GIS under test [B24].
Despite having intended a very close and detailed test procedure from one perspective, the return of
experience from another perspective has shown that some level of flexibility for spontaneous
decisions on site at short notice also allow time-optimised processes during the on-site HV test. Also,
some decision-making freedom to adapt to specific testing situations and to enable other (e.g. simpler)
test procedures to be applied in some regions has been found advantageous to conduct on-site HV
testing in a safe and efficient manner.
126
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Transport condition to the final destination of the HV test set can occasionally be challenging
regarding mechanical impacts on the different parts of the test set. Some example situations with
rough conditions are shown in Figure 5.12.
127
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
128
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
repositioning of acoustic sensors for which occasionally suitable lifting platforms (e.g. GIB feeders) or
gantries are necessary to access already installed and commissioned online PD monitoring systems.
However, for non-conventional PD measurements additional time needs to be considered for
performing a sensitivity check on site to demonstrate a sufficient detection sensitivity under the
existing background noise situation. All of these steps are considered to take longer compared to
conventional PD measurements, although the specific cases can vary dependent on the systems
finally used.
A quite common installation setup of various devices for on-site PD measurements on GIS can be
seen in Figure 5.15.
Figure 5.15 Example for installation set-up of various PD measuring equipment on site [B87]
In case of UHF PD measuring equipment typically a verification of the measurement chain is
performed at first. Sometimes user specifications might have technical requirements regarding
positioning of internal UHF sensors in GIS to achieve sufficient PD detection sensitivity for UHF PD
measurements [B47].
A good orientation regarding PD detection sensitivity is given in [B7], [B31]. However, PD detection
sensitivity can also be influenced by the options provided by the UHF PD measuring equipment itself
(e.g. technical data of amplifiers, soft- or hardware-based setting of amplifiers, filter units) [B47].
In some cases when using frequency-tuned resonant systems, the components and circuits in the
feeding part used to provide the HV test voltage at the load-dependent test frequency might generate
some interferences which may disturb sensitive conventional PD measurements. Often, they have
been caused by LV signals with short rise and fall times triggering parasitic resonant circuits in the
feeding part. These interference signals are typically periodical to the sine waveshape (e.g. two or four
times per period) and depend also on the ratio of the used exciter transformer and the earthing
condition Figure 5.16. Some test equipment offers, especially for this effect, gating options to suppress
such unwanted signals for an adjustable time period (e.g. a few micro-seconds), which need to be
adapted for each test situation.
129
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 5.16 Example for noise signals originating from HV test set
130
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
earthing switch for the earthing of the section under test should be identified and left in the CLOSE
position until the beginning of the dielectric test [B24].
5.6.2 Position of switching devices in the circuit under test
The goal of the dielectric test is to test the GIS insulation phase to earth, so usually the switching
devices (circuit breakers and disconnectors) are HV tested on site in the CLOSE position. However,
switching apparatus that has undergone on-site refurbishment, repair or maintenance can sometimes
be prepared for HV testing on site in the OPEN position according to test procedure agreements
between OEM / user / third party. The latter is occasionally aligned to voltage application procedures
relevant for HV routine testing.
Any switching equipment, especially if equipped with insulator or capacitance across its main contacts,
that undergoes refurbishment or repair of its active parts, or any spare switching equipment used for
repairing an existing GIS with an unknown or questionable insulating condition could be dielectrically
tested on site also in the OPEN position according to agreement between OEM / user / third party
(e.g. as pre-test before the ‘official’ test in the CLOSE position commences).
The condition assessment of switching equipment to be able to undergo an on-site test is another
example of situation where a dielectric test in the OPEN position may have to be performed.
It may also be good practice that prior to the dielectric test every switching device and earthing switch
has undergone a pre-defined number of CO operations. In addition to the verification of the stability of
the operating mechanism, those operations may also reveal some internal problems related to active
parts (i.e. abnormal generation of particles or incorrect fixation of electrode shields), that could
possibly be further detected by the dielectric test [B24].
5.6.3 Temporary isolation or dismantlement of devices for HV testing
Some parts of the GIS contained within the test section may need to be separated from the section
under test, as they are not part of the equipment to be tested (e.g. HV cable, power transformer), or
technically not designed to withstand certain dielectric stresses (e.g. conventional voltage
transformers). To avoid saturation of voltage transformer the dielectric test must be performed at a
frequency higher than the minimum one specified by OEMs. If this minimum frequency cannot be
reached for the dielectric test because of the characteristic of the test circuit or the type of testing
generator used, the voltage transformer must be isolated by an isolating device or dismantled before
the test [B24].
HV cables typically may need to be disconnected before the dielectric HV test (e.g. test voltage levels
of HV GIS test are higher compared to that for HV cables, and HV test voltage generators might not
be able to cover high capacitive loads of HV cables). This is done by retrieving the cable or by
dismantling its removable link within the GIS. Specific corona shields may need to be installed for the
dielectric HV test and the HV cable pothead needs to be earthed for safety issues by appropriate
means to avoid induced potential that may result from a disruptive discharge or stray capacitances.
Refer also to 4.4.4.
Even though surge arresters are very often installed outdoors, any existing GIS surge arrestors that
are part of the test circuit should be disconnected for the dielectric HV test.
All removable links within the GIS transformer boxes under test have to be dismantled. To withstand
the dielectric test voltage, electrodes might be added to the main circuit from either side of the
removed links. The transformer bushing of the transformer box has to be earthed, for safety reasons,
by appropriate means in order to avoid induced potential that may result from a disruptive discharge or
stray capacitances [B24].
5.6.4 Testing a new installation and 'stand alone’ bay in case of extension (GIS not in
service)
In case of HV testing of new GIS installations a less extensive ‘switching plan’ can be helpful to
illustrate which parts of the complete installation belong to the specific section under test considering
that the installation is not connected to the network, which gives more autonomy to OEM and
personnel involved in testing to perform the different actions required to proceed with the dielectric test
[B24].
5.6.5 Testing an existing installation after repair or extension (GIS partly in service)
In case of HV testing at substations with sections remaining in service, some specific safety aspects
need to be considered. They generally require an earthed section between the section under test and
131
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
the section in service. Moreover, all adjacent sections to the section under test, which are not included
in the HV testing procedure need to be earthed too.
A more extensive ‘switching plan’ typically needs to be made including information on any apparatus
to disconnect from the network or the GIS section under test before the dielectric tests begin (e.g.
power transformers, cables, overhead lines, voltage transformers, surge arresters, shunt reactors).
Often, disconnectors used to isolate the section under test from the network are padlocked and, in an
ideal case, should neither be included in any part of a test circuit nor be subjected to dielectric test
voltages. But in practical situations the referred disconnector is often the last disconnector of a section
under test in the bus bar, secured and padlocked in OPEN position. The adjacent section is
subsequently earthed, and the earthing switch secured and padlocked in CLOSE position. The
disconnector positioned between section in service and earthed section is then secured and
padlocked in OPEN position. This can result in HV test voltage application to that specific
disconnector, which is part of the test section. All earthing switches that allow the GIS test circuit to be
protected against induced voltage or accidental refeeding from the network need to be in CLOSE
position and padlocked.
A final verification of the required switching configuration for the GIS test circuit should be done on site
at least by two persons to validate its conformity to the test procedure. Especially, the delimitation of
the section under test and the remaining sections of the substation including a confirmation of the
position of circuit breakers, disconnectors, and earthing switches [B24], [B92].
132
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
with AC, so that consequently a second HV test voltage generator is required on site. Nevertheless,
HV testing situations can exist when the conditioning phase is conducted with impulse voltage
waveforms as well. Therefore, the specific test procedures are agreed between OEM / third party and
user long before the start of the HV test too. The challenges involved with LI (OLI) test voltage
waveforms are often considered appropriately within the approved test procedures.
As the connection of the HV test voltage generator for this HV testing scenario is typically realised by
air-insulated HV injection points, a suitable time planning within the project management is absolutely
necessary to confirm a suitable location for the on-site installation of the HV test voltage generator
including its accessories (e.g. separate voltage divider, test circuit inductance, earthing) under
consideration of the required air clearances. Additionally, as the involved assembly works in case of
installation of a testing bushing at the GIS section under test which originally has no bushing installed,
constitutes a potential risk of irregularities (e.g. contamination, insufficient gas quality like pressure,
purity, or moisture), so extra care has to be taken.
In principle, a test run including voltage application to verify the correct functionality of the LI (OLI) test
voltage generator installation can then be performed without its connection to the GIS section under
test. In this case the test load is represented mainly by the voltage divider. When doing so, it has to be
considered afterwards that the interaction of the test voltage generator with the capacitance of the GIS
section under test influences the time parameters and the test voltage level of the applied impulse test
voltage. Therefore, commonly the already mentioned test run for verification of the functionality of the
installed test circuit is often conducted on a completely installed test circuit at a specified (e.g.
beforehand in the approved test procedures) lower test voltage level. This can be done for example at
50 % of the specified test voltage level.
Moreover, it is common to apply some pre-impulses with lower test voltage values before approaching
the specified test voltage level. The details of this method are also part of the approved test
procedures. The LI (OLI) on-site HV test is successful, if for each polarity 3 consecutive impulses are
applied, and no disruptive discharge occurs [B23].
133
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
decrease of the current test voltage level, as well as switching operations within the GIS test section
under test or evaluation of other locating diagnosis. The latter procedure happens mostly at test
voltage levels below a voltage level where a disruptive discharge can be avoided.
In the course of a repetition of the conditioning phase after a disruptive discharge, it could be helpful to
adapt the rate of voltage rise to the readings of the applied PD measuring equipment to be aware if
possibly irregularities continue. Regarding localization measures after a disruptive discharge, it could
help to consider especially those gas compartments which have been part of on-site assembly works.
However, if a first disruptive discharge can be located and assessed to originate from along the
surface of a solid insulation (which is technically challenging), or if a second disruptive discharge can
be assessed to the same location (e.g. gas compartment) occurring already at a lower test voltage
level as the previous flashover, the complete test sequence of the GIS section under test needs to be
stopped, and the affected gas compartment must be opened for further clarification and removal of the
origin of the observed flashovers. The latter can already apply to irregularities during the conditioning
phase. If the latter scenario applies to the AC HV test, the test has failed, and a repetition is only
possible after successful elimination of the corresponding root cause. When a second disruptive
discharge can be assessed to the same location (e.g. gas compartment) occurring at a higher test
voltage level than the previous flashover, the complete test sequence of voltage application is typically
repeated again.
Sometimes, it is considered that disruptive discharges along the surface of a solid insulation start to
deteriorate the dielectric performance of the solid. This applies not in general, as the design and
composition of solid insulating materials vary as well as the discharge energy provided by the
capacitance under test and the test voltage generator. But this aspect is occasionally discussed
controversial between OEM / third party and user, so that specific procedures for this scenario are
often agreed and approved within the test agreement in advance of the on-site HV testing activities.
The technical principle behind the above-described procedure is that if a disruptive discharge
originates from a surface defect of a solid insulation, it will deteriorate it even more, decreasing the
dielectric withstand to a lower level than it was for the first test attempt. In contrary, if the disruptive
discharge occurs in the gas, there will be no deterioration of solid insulation and no decrease in the
expected dielectric withstand for a second test attempt. In Chapter 3.4.1 additionally some user return
of experience is presented for scenarios when the withstand voltage test duration is extended in a
slight deviation to IEC.
GIS design dependent accessibility towards solids in assembly units, as well as material composition
of solids itself, can favour or restrain further surface treatment after disruptive discharges by 'polishing'
or 'buffing' with appropriate OEM specific materials.
OEM specific recommendations - which are based on their long-term experience on the GIS design
and material in use - towards this process exist and can vary.
In general this technical detail may also be divided into different cases, such as:
• Flashover on solids including traces with high visibility,
• Flashover in the gaseous insulation in the immediate vicinity of the solid including material
deposits with low visibility,
• Flashover base points on conductor and enclosure.
All this may initiate different possibilities and actions for handling of 'flashover traces'. However, the
return of experience also showed that sometimes extensive discussions between the involved parties
on this have occurred with potential misinformation or non-considerations of relevant details leading
occasionally towards controversial positions [B23]. See also information given in Chapter 2.
LI (OLI) on-site HV test
The conduction of a repetition procedure for this kind of voltage waveform application does not differ
much in detail compared to that for AC test voltages. So, after a first flashover a discrimination is
necessary to establish its possible discharge path. Commonly, it is very challenging to distinguish
between along the surface of a solid insulation or in the gaseous insulation. So, a further application of
several impulses with test voltages at the specified test voltage level or below is typical to further
elaborate the nature of the discharge path.
In case of a further disruptive discharge in the course of this test procedure the complete LI (OLI) test
sequence is considered as failed, and an inspection of the affected gas compartment including
134
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
opening is required. After removal of the flashover origin, repetition commences including the specified
test procedure for the conditioning phase [B23].
5.8.3 Detection of partial discharge
Typically, immediately after completing the test duration of the specified AC HV test voltage level, the
test voltage is decreased to the specified PD test voltage level. Once this test voltage level is
established, the reading and assessment of possible PD activities commences.
The return of experience shows that concerning the test duration different opinions exist. But when
considering overall various standard requirements the test duration is defined as a minimum of 1
minute. It can be advantageous to observe the current readings a little longer to ensure detection of
PD activities which need some statistical time lag to start. Often the specific test duration for the PD
measurement is agreed in advance within the test procedure by OEM / third party / user.
As the different conventional and non-conventional PD measurement methods offer various
opportunities to come across on-site testing challenges like ambient noise, disturbances, calibration
aspects, measuring sensitivity and locating feasibilities, the specific actions while conducting the PD
test itself can vary significantly.
However, in case a GIS section under test includes a bushing, non-conventional PD measurements
(e.g. UHF method) provide some advantages to locate a possible PD source and discriminate them
from disturbances. This is commonly done by amplitude comparison of phase-related PD activity
along the several internal UHF sensors of the GIS section under test or comprehensive setting of the
frequency-based signal-to-noise ratio. Various returns of experience exist on how to approach a
convenient way to identify, suppress or evaluate this kind of PD activity.
Nevertheless, if the current PD activity is above the specified PD level or exhibits a phase-related
pattern, the main actions are focused on locating the PD source. Common steps to investigate this are
de-sectionalizing the GIS section under test, several test voltage applications with voltage decrease
and voltage increase to record PD inception and extinction voltages and verify their stability. Re-rising
the test voltage level again after de-sectionalizing the GIS section under test need then to be
performed up to the observed PD inception voltage level to re-start PD activity. Additionally, the
evaluation of the recorded phase-related PD pattern (e.g. with the help of software-based expert data
or the level of experience of the 'testing team' itself) can guide towards a possible identification of the
irregularity. Sometimes, different simultaneous applied non-conventional PD measurement techniques
based on electromagnetic and acoustic methods can support the success of the locating activities, as
well as mechanical vibration of a distinct area of interest can reveal presence of metallic particles.
After successful localization of the PD source, commonly a risk assessment is performed by the
'testing team' to find out how to proceed. Mostly relevant factors like PD activity level, PD inception
voltage level, phase-related PD pattern, location of the PD source including GIS parts possibly
affected and OEM and user return of experience help to decide on the next step.
Generally, it should be excluded, that potentially harmful defects for the GIS operation remain within
the GIS.
Investigation of the affected gas compartment including opening, cleaning, repair or possibly
exchange of parts can be an outcome of the risk assessment, as well as in case of assessing a low
risk for a safe operation of the GIS to not open the affected gas compartment and observe this GIS
section afterwards while the GIS is in operation with permanent, temporary permanent or periodic PD
measurements (e.g. UHF method). This allows to recognize any changes of the PD activity over a
longer time, and OEM and user collaborate closely for the final conclusion. The latter procedure is not
so common and only applicable if a PD source is active at service voltage level, but sometimes
external circumstances (e.g. time or network constraints) do not allow for a complete removal of a PD
source with a low risk assessed [B23].
In the end, a well-balanced procedure locating possible PD defects compromising flexibility and
stringency can offer a feasible approach. Therefore, it can sometimes be helpful to have a procedural
orientation on hand. An example for this is presented in Figure 5.17.
135
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure 5.17 'Flow chart decision tree for irregularities while PD testing' [B93]
This flowchart applies only for conventional PD measurement. In case of UHF PD measurement, no
quantities of pC can be measured. A common practice is the requirement for 'no phase correlated' PD
measured at the PD measurement voltage.
PD findings which occur after applying the test voltage at the PD measurement voltage are
recommended to be localized and eliminated. If the PD source vanishes during the examination phase
or the PD signal can no longer be measured, extended measuring times (typically 3 - 5 minutes)
should be used to check whether the PD does not appear again. In the case of intermittent PD signals,
which frequently occur with floating metallic particles, it is also suitable to check the PD by slightly
shaking the system by switching circuit breakers, earthing switches, or disconnectors and then re-
measuring. If the PD source can no longer be detected, the measurements should be documented in
the test report (for comparison with any measurements later).
The principle applies that no PD findings should remain in the GIS without scientifically founded
certainty regarding the harmlessness for operation. This certainty can rarely be achieved since GIS is
a closed system and the partial discharge signals are of a stochastic nature - i.e. always with slightly
different characteristics. The assessment of the effective operational hazard of a partial discharge
finding is very complex and can often only be adequately described after opening the GIS,
identification of the exact location, nature, and dimension of the defect.
Since the critical length of particles starts at 1...2 mm (CIGRE JWG 33/23.12: Insulation co-ordination
of GIS - return of experience, on-site tests and diagnostic techniques, Electra No. 176, 1998, pp. 67-
97) and the GIS dimension is many times larger, it is possible that nothing definite is found when the
GIS is opened, but the critical particle was removed when the gas compartment was cleaned with
cleaning cloths and vacuum cleaners. In this case, the defect cannot be clearly identified, but the
cause of the PD has been eliminated.
136
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
137
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
detected which may result from a defective installation of a non-tested component, often further defect
locating activities commence.
Additional user recommendations may be implemented following the energisation of the GIS, which
can result in a complete ‘UHF scan’ of the installation at the energisation phase, or within a few weeks
after that period in order to detect preventively new PD signals if any, and to monitor the evolution of
unknown or uncategorized PD signals detected during the dielectric HV tests or to have a footprint of
UHF measurement at service voltage for further references.
OEMs may also support users with some guidance for the after-energisation phase of a new GIS
installation [B24].
138
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
2. Extension of partially equipped bays (usually equipped with disconnector switches for both
busbars in double busbar layouts, and/or only one disconnector switch for single busbar into
full bay),
3. Replacement of partially equipped bays by full new bays,
4. Adding of new bays in a space previously assigned in the existing busbar.
5.10.3.1 Tests of new installed GIS bay(s)
The following example for an on-site HV testing procedure according to a user specification is defined
for a replacement of partially equipped bays of a HV GIS with completely new bays. This might
become necessary due to the following constraints [B13]:
• It is not possible (without unreasonable effort) to extend the partially equipped bays with
equipment from a different OEM,
• Additional effort has to be considered for construction and testing of customized adapters,
• In some cases non-production of the existing HV GIS type make it obsolete.
The interface facilitates for installation and on-site HV testing of the extension, and also limits the part
of the existing HV GIS to be re-tested. In this example the connection to the existing HV GIS remains
without further complete on-site HV testing, and restriction is permitted.
Figure 5.18 Replacing partially equipped bays with completely new bays [B73]
139
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
• On-site HV test is conducted as per new equipment complying with full voltage (80% of FAT
value) and PD measurement,
• New bays are coupled to the existing system by availing busbar (by busbar shutdown and
afterwards subjected to a ‘soak test’ for 2...24 hours),
• Based on the importance of busbar requirement in the network, a relaxation of the ‘soak test’
duration is also applied,
• 2 hours ‘soak test’ associated with links of the two systems can also be performed.
Figure 5.19 Addition of new bay(s) at the end of an existing busbar [B73]
Another example on this specific HV testing situation is described in Figure 4.16.
5.10.3.3 Tests of GIS interfaces with same test voltage values as new installed GIS
In some cases of HV GIS extension projects, the assigned OEM for extension works might face
technical difficulties handling the existing partially equipped bay, especially if the existing HV GIS is
from a different OEM than the newly assigned one. Since the task might be complicated and will
require a special custom-made adapter, or sometimes the type of existing partially equipped bay is
obsolete and out of the regular production line. Hence, the new OEM tends to consider the option of
supplying and manufacturing a completely new bay and replace the already existing partially equipped
bay from another OEM. As per standard requirements the interface incorporates facilities for
installation and HV testing of the extension HV GIS to limit the part of the existing HV GIS to be re-
tested, and to allow the connection to the existing HV GIS without further full dielectric testing without
any restriction [B13].
5.10.3.4 Test of GIS interfaces with reduced test voltage values as new installed GIS
The following example for an on-site HV testing procedure according to a user specification is defined
for extension of partially equipped bays of a GIS with the same OEM GIS. Typically, these are located
at both ends of a busbar system to cover future needs. They consist of both busbar disconnector and
earthing modules. The initial partially equipped bay converts to a completely equipped bay according
to the network needs. For the coupling process of the new parts it can be GIS design dependent if - in
case of a double-busbar system - both or only one busbar needs to be shutdown. In some cases the
reduction of the on-site HV test voltage for the interface between new and old parts of the GIS might
be compensated by a longer test duration (e.g. 120 seconds instead of 60 seconds) [B73].
140
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
141
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Abbreviation Definition
MTTR Mean Time To Restoration
MTBF Mean Time Between Failures
MaF Major Failure
MRE Maintenance, Repair or Extension
EPC Engineering Procurement Commissioning
EHS Environment, Health, and Safety
OPEX Operational Expenditure
142
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
APPENDIX B. References
[B1] CIGRE JWG 33/23.12: Insulation co-ordination of GIS - return of experience, on-site
tests and diagnostic techniques, Electra No. 176, 1998, pp. 67-97
[B2] CIGRE technical brochure 514: Final report of the 2004 - 2007 international enquiry on
reliability of high voltage equipment part 6 – Gas-insulated switchgear (GIS) practices,
2012
[B3] CIGRE TF 15.03.07 of WG 15.03, Long-term performance of SF6-insulated systems,
CIGRE session 2002, paper 15-301
[B4] Neumann C., Rusek B., Balzer G., Jeromin I., Hille C., Schnettler A.: End of life
estimation and optimisation of maintenance of HV switchgear and GIS substations,
CIGRE session 2012, paper A3-202
[B5] CIGRE WG B3.50, IWD 12, Saida T.: On-site HV test for GIS (over 52 kV) in Japan,
2018
[B6] Hidaka K., Saida T., Goshima H., Yoshiike S., Takami J., Matsushita Y.: Principles of
insulation coordination and recent activity on reduction of insulation level in Japan,
CIGRE session 2014, paper C4-206
[B7] IEC 62271-203: High voltage switchgear and controlgear – part 203: Gas-insulated
metal-enclosed switchgear for rated voltages above 52 kV, 2022
[B8] CIGRE WG B3.50, IWD 05, Vosse R.: Experiences with HV tests on GIS, 2019
[B9] CIGRE WG B3.50, IWD 06, Wolf Ch.: On-site / commissioning HV tests - GIS, 2018
[B10] CIGRE WG B3.50, IWD 08, Canhoto A.: REN - Experiences with HV tests on GIS,
2019
[B11] CIGRE WG B3.50, IWD 14, Gao K.: The introduction of on-site test of GIS in SGCC,
2019
[B12] CIGRE technical brochure 562: Field tests for UHV substations, 2013
[B13] CIGRE WG B3.50, IWD 34, Ahli A. M.: User experience in TRANSCO with some
scenario of HV testing, 2021
[B14] CIGRE technical brochure 360: Insulation coordination related to internal insulation of
gas-insulated systems with SF6 and N2/SF6 gas mixtures under AC condition, 2008
[B15] IEC 62271-200: High voltage switchgear and controlgear – part 200: AC metal-
enclosed switchgear and controlgear for rated voltages above 1 kV and up to and
including 52 kV, 2021
[B16] IEEE C37.20.9: IEEE standard for metal-enclosed switchgear rated 1 kV to 52 kV
incorporating gas insulating systems, 2019
[B17] IEEE C37.20.2: IEEE standard for metal-clad switchgear, 2022
[B18] DL/T 593: Common specifications for high voltage switchgear and controlgear, 2016
[B19] CIGRE WG B3.50, IWD 44, Neuhold S.: On-site HV testing and PD measurement on
MV GIS - existing standards (IEC) and state of the art, 2021
[B20] GB 50150: Electric equipment installation engineering - standard for hand over test of
electric equipment, 2016
[B21] IEEE C37.122.7: IEEE guide for field testing of gas-insulated substations rated above
52 kV, 2021
[B22] CIGRE WG B3.50, IWD 20, Laubi A.: Situation of HV GIS in AU and NZ and return of
experience, 2019
[B23] CIGRE WG B3.50, IWD 31, Laberge S.: Test of GIS after extension, 2021
[B24] CIGRE WG B3.50, IWD 33, Laberge S.: Test of GIS after repair, 2021
143
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
[B25] CIGRE technical brochure 509: Final Report of the 2004 –2007 international enquiry
on reliability of high voltage equipment part 1 - Summary and General Matters, 2012
[B26] CIGRE JWG 33/23.12: Insulation co-ordination of GIS - questions on the influence of
on-site tests and dielectric diagnostics, CIGRE session 1992, paper 23/33-03
[B27] Hauschild W., Lemke E.: High voltage test and measuring techniques, Springer
International Publishing, ed. 2, 2019
[B28] CIGRE technical brochure 502: High voltage on-site testing with partial discharge
measurement, 2012
[B29] Hinterholzer T.: Der Durchschlag in SF6 unter Einfluss der Raumladungsstabilisierung,
doctoral thesis, Lehrstuhl für Hochspannungs- und Anlagentechnik, Technische
Universität München, 2002
[B30] Hinterholzer T., Boeck W.: Breakdown in SF6 influenced by corona-stabilization; IEEE
Conf. on Electrical Insulation and Dielectric Phenomena (CEIDP), 2000, pp. 413-416
[B31] CIGRE technical brochure 525: Risk assessment on defects in GIS based on PD
diagnostics, 2013
[B32] Schurer R.: Der Einfluss von Störstellen auf Stützeroberflächen auf die elektrische
Festigkeit von Isolieranordnungen in SF6-isolierten Anlagen, doctoral thesis, Institut für
Energieübertragung und Hochspannungstechnik, Universität Stuttgart, 1999
[B33] Diessner A., Luxa G.F., Mosca W., Pigini A.: HV testing of SF6-insulated substations
on-site, CIGRE session 1986, paper 33-06
[B34] Bernasconi F., Zaengl W. S., Vonwiller K.: A new HV series resonant circuit for
dielectric tests, ISH Milan, 1979, paper 43.02
[B35] Schichler U., Wurster M.: HV testing of GIS - application of frequency tuned resonant
test sets and return of experience from on-site tests, Int. Conf. on Properties and
Applications Dielectic Materials (ICPADM), 2006, pp. 297-300
[B36] Wei S., Dejun L., Schichler U., Suermann B.: Performance of GIS epoxy insulators
and related tests, International Conference on High Voltage Engineering and
Application, Shanghai, China, 2012, pp. 273-276
[B37] CIGRE WG B3.50, IWD 38, Gao K.: Series resonant gas-insulated metal-enclosed
voltage withstanding test device and its application in China, 2021
[B38] CIGRE WG B3.50, IWD 37, Gao K.: Two insulation test cases of 1100 kV and 550 kV
GIS in Shanghai Power Grid, 2021
[B39] CIGRE WG B3.50, IWD 42, Bensberg D.: AC conditioning procedure for on-site HV
testing of HV GIS, 2022
[B40] CIGRE WG B3.50, IWD 41, Schenk Ch.: Various methods for conditioning and HV
testing, 2021
[B41] CIGRE WG B3.50, IWD 25, Dorgan D.: GIS site testing requirements - ESB
International GIS projects, 2021
[B42] Reid A.J., Judd M.D.: Ultra-wide bandwidth measurement of partial discharge current
pulses in SF6, Journal of Physics D: Applied Physics, vol. 45, iss. 16, 2012
[B43] Neuhold S., Bruegger T., Braeunlich R., Behrmann G., Schlemper H.D., Riechert U.,
Mueller P., Lehner M., Schneiter E., Sigrist P.: Return of experience: The CIGRE UHF
PD sensitivity verification and on-site detection of critical defects, CIGRE session
2018, paper D1-304
[B44] Niemeyer L., Fruth B., Gutfleisch F.: Simulation of partial discharges in insulation
systems, ISH Dresden, 1991, paper 71.05
[B45] Koch H. J. et al: Gas-insulated substations, John Wiley & Sons Ltd., 2014
[B46] Schmitt C., Hermann L., Pancheshnyi S., Adili S., Franck C.: X-ray triggered PD
measurements in small sized spherical voids at the detection limit, IEEE Conf. on
Electrical Insulation and Dielectric Phenomena (CEIDP), 2014, pp. 150-153
144
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
[B47] CIGRE WG B3.50, IWD 30, Laberge S.: Evolvement of user specifications, 2021
[B48] Hydro-Quebec - SN-25.1d: Appareillage sous enveloppe métallique à isolation
gazeuse (SF6) de tensions assignées supérieures à 72.5 kV, 2014
[B49] Hampton B., Meats R. J.: Diagnostic measurements at UHF in gas-insulated
substations, IEE Proceedings C – Generation, Transmission and Distribution, vol. 135,
no. 2, 1988, pp. 137-145
[B50] Behrmann G., Gross D., Neuhold S.: Limitations of attempting calibration of partial
discharge measurements in VHF and UHF ranges, IEEE Conf. on Electrical Insulation
and Dielectric Phenomena (CEIDP), 2020, pp. 164-168
[B51] Behrmann G., Wyss K., Weiss J., Schraudolph M., Neuhold S., Smajic J.: Signal delay
effects of solid dielectrics on time-of-flight measurements in GIS, IEEE Trans. on
Dielectrics and Electrical Insulation, vol. 23, no. 3, 2016, pp. 1275-1284
[B52] CIGRE WG B3.50, IWD 52, Becker G.: Case study for failure during on-site PD testing
of a 115 kV GIS, 2022
[B53] Mueller P., Thelar D., Diggelmann T., Hengstler J., Hyrenbach M., Zache S., Mann M.,
Neuhold S.: Betriebserfahrung der ersten 170-kV- und 24-kV-GIS mit alternativem
Isolationsmedium basierend auf Ketonen, Stuttgarter Hochspannungs-Symposium,
2016
[B54] Zhang L., He C., Guo R., Yuan W., Li J.: Research on effectiveness of lightning
impulses with different parameters for detecting protrusion defects in GIS, IEEE Trans.
on Dielectrics and Electrical Insulation, vol. 27, no. 4, 2020, pp. 1354-1362
[B55] Wu Z., Zhang Q., Ma J., Li X., Wen T.: Effectiveness of on-site dielectric test of GIS
equipment, IEEE Trans. on Dielectrics and Electrical Insulation, vol. 25, no. 4, 2018,
pp. 1454-1460
[B56] Feser K., Sun R., Eriksson A., Froehlich K.: On-site dielectric testing of GIS -
theoretical and practical considerations, IEEE Trans. of Power Delivery, vol. 6, no. 2,
1991, pp. 615-625
[B57] CIGRE WG B3.50, IWD 04, Li J.: Impulse test for GIS on-site, 2018
[B58] Schichler U.: Vor-Ort-Prüfung an gasisolierten Schaltanlagen (GIS, HIS) und
Übertragungsleitungen (GIL), HIGHVOLT colloquium 2003, paper 7-3
[B59] CIGRE WG B3.50, IWD 21, Li J.: Cases of on-site impulse test for GIS in China, 2019
[B60] Wen T., Zhang Q., Ma J., Liu X., Wu Z., Zhang L., Zhao J., Shimomura N.: Research
on the detecting effectiveness of on-site lightning impulse test for GIS equipment with
insulation defects, IEEE Trans. on Dielectrics and Electrical Insulation, vol. 25, no. 2,
2018, pp. 551-558
[B61] CIGRE technical brochure 513: Final report of the 2004 - 2007 international enquiry on
reliability of high voltage equipment part 5 – Gas-insulated switchgear (GIS), 2012
[B62] CIGRE WG B3.50, IWD 29, Neuhold S.: Agreement of HV test procedures…OEM-
user, 2021
[B63] Neuhold S., Heizmann T., Braeunlich R., Koechli D., Riechert U., Dehne C.:
Experiences with UHF PD detection in GIS using external capacitive sensors on
windows and disk-insulators, ISH Ljubljana, 2007, paper T7-480
[B64] CIGRE WG B3.50, IWD 46, Koetz H.: Power Voltage Transformer (‘Power VT’) -
conventional inductive GIS VTs with on-site HV test functionality, 2023
[B65] Dorgan D.: GIS factory and site test requirements for HV and EHV cables, CIGRE SC
A3 & B3 joint colloquium, Nagoya, 2015, paper 334
[B66] CIGRE WG B3.50, IWD 11, Evertz E.: Comments on minutes of meeting hold 9-11
April 2018, 2018
[B67] CIGRE WG B3.50, IWD 18, Evertz E.: Comments on minutes of meeting hold 29-31
October 2018, 2019
145
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
[B68] CIGRE technical brochure 605: Feasibility of a common, dry type plug-in interface for
GIS and power cables above 52 KV, 2015
[B69] IEC 62271-209: High voltage switchgear and controlgear – part 209: Cable
connections for gas-insulated metal-enclosed switchgear for rated voltages above
52 kV – Fluid-filled and extruded insulation cables – Fluid-filled and dry-type cable
terminations, 2019
[B70] IEC 62067: Power cables with extruded insulation and their accessories for rated
voltages above 150 kV (Um = 170 kV) up to 500 kV (Um = 550 kV) - Test methods
and requirements, 2022
[B71] CIGRE WG B3.50, IWD 26, Schenk C.: Experiences with HV tests on GIS extensions,
2019
[B72] CIGRE WG B3.50, IWD 24, Bensberg D.: HV test after GIS extension, 2019
[B73] CIGRE WG B3.50, IWD 35, Ahli A. M.: HV testing on GIS equipment, 2021
[B74] CIGRE WG B3.50, IWD 40, Gao K.: Site testing requirements for MV GIS in Chinese
standards, 2021
[B75] IEEE Std C37.122.6: Recommended practice for the interface of new gas-insulated
equipment in existing gas-insulated substations rated above 52 kV, 2013
[B76] CIGRE WG B3.50, IWD 36, Neuhold S.: HV testing of GIS extensions, 2021
[B77] CIGRE WG B3.50, IWD 09, Reuter M.: On-site AC HV test including PD measurement
on a HV GIS extension from different OEM than original HV GIS, 2018
[B78] CIGRE WG B3.50, IWD 03, Laubi A.: Comments on ToR from Asia Pacific B.3 panel
and general remarks, 2018
[B79] CIGRE technical brochure 125: User guide for the application of gas-insulated
switchgear (GIS) for rated voltages of 72.5 kV and above, 1998
[B80] National Grid - TS 3.02.14 (RES): Technical specification gas-insulated switchgear,
2014
[B81] Braeunlich R., Bruegger T., Storf G., Straumann U., Koetz H.: Safety clearance
between high voltage test systems and parts of air-insulated substations in operation,
VDE Hochspannungstechnik online conference, ISBN 978-3-8007-5353-6, 2020, pp.
608-612
[B82] Neuhold S.: On-site tests of GIS, HIGHVOLT colloquium 2011, paper 2-2
[B83] IEC 60073: Basic and safety principles for man-machine interface, marking and
identification - Coding principles for indicators and actuators, 2002
[B84] CIGRE technical brochure 499: Residual life concepts applied to HV GIS, 2012
[B85] CIGRE WG B3.50, IWD 50, Vosse R.: User cases showing switching configuration for
new GIS and for GIS after repair or retrofit, 2023
[B86] Zhao P., Wang J., Yan X., Wang Q., Shen C., Shen Z., Xiao Q., Long Y.: AC voltage
withstand test method and risk suppression measures of energized GIS based on
phase-frequency control", IEEE Trans. on Power Delivery, vol. 37, no. 3, 2022, pp.
1734-1744
[B87] CIGRE WG B3.50, IWD 49, Koetz H.: Installation of on-site HV testing equipment and
PD measuring equipment, 2023
[B88] CIGRE WG B3.50, IWD 45, Bensberg D.: Assembly variant for on-site HV test set
under consideration of constraints, 2021
[B89] CIGRE WG B3.50, IWD 51, Laberge S.: Case studies of specific HV testing situations
- tests with air-insulated HV injection and post HV testing of VT and SA links with
service voltage, 2023
[B90] CIGRE WG B3.50, IWD 48, Reuter M.: On-site HV testing of GIS using ‘Power VT’,
2022
146
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
[B91] Lundgaard L. E., Skyberg B., Schei A., Diessner A.: Method and instrumentation for
acoustic diagnoses of GIS, CIGRE session 2000, paper 15-309
[B92] CIGRE WG B3.50, IWD 10, Schenk C.: Proposal for HV GIS shut down procedure,
2018
[B93] CIGRE WG B3.50, IWD 47, Koetz H.: Flow chart decision tree for irregularities while
PD testing, 2023
[B94] CIGRE WG B3.50, IWD 27, Ginting C.: On-site HV test, 2019
[B95] CIGRE WG B3.50, IWD 43, Reuter M.: Method statement / colour code example for
HV GIS extension including on-site HV test, 2022
[B96] IEC TS 62478: High voltage test techniques – Measurement of partial discharges by
electromagnetic and acoustic methods, 2016
147
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
148
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
• GIL size approx. 420 kV and above: The load can be significantly higher than a relatively
compact GIS (e.g. with typical 60 pF/m and 1 km length this results in a total capacity of
60 nF).
In Europe (EU), typical power supply ratings for three-phase 400 VAC systems are:
• 32 A →400 V/√3 x 32 A x 3 = 22.2 kVA,
• 63 A →400 V/√3 x 63 A x 3 = 43.6 kVA,
• 125 A →400 V/√3 x 125 A x 3 = 86.6 kVA.
Due to the very low losses of series resonant test circuits of often below 1 % of the apparent power, it
is typically possible to test average sized GIS (i.e. load range 5 nF…15 nF) with a 63 A supply rating.
Experience has shown that for a variable frequency resonant test set a 63 A rating for a three-phase
400 V supply is sufficient for most of the HV GIS testing applications.
Additional loads in parallel to the GIS are often applied to control the frequency variation when
reducing the test section length due to fault investigation. The total load in these test circuits (together
with a capacitive divider) adds up to approx. 15 nF…20 nF. A power supply of 32 A is usually sufficient
for tests below a rated voltage level of 245 kV – even with long duration PD measurement (0.5…1
hour) at a test voltage level of 1.2xUr.
Moreover, experience has also shown that in only very rare cases (test voltage levels of 420 kV or 550
kV GIS in combination with very long distances from the test set-up to the HV injection point and
associated dissipation of electrical energy (e.g. thin wires not suitable for PD measurements resulting
in corona losses), a 125 A supply rating is not sufficient.
Example calculation for series resonant HV test sets with variable frequency is shown with the data in
the table below:
Table C.1 Example data for calculation for series resonant HV test sets with variable frequency
Subject Value
GIS load 10 nF
Additional load 3 nF
Example 1
Resonant Frequency (100% GIS load) 13 nF with 220 H 94 Hz
HV current (100% GIS load) 515 kV with 13 nF and 94 Hz → 4A
Reactive load 515 kV with 4 A → 2 MVA
Power needed to compensate losses 2 MVA / 100 → 20 kW
Example 2
Resonant frequency (1% GIS load) 3.1 nF with 220 H →192 Hz
HV current (1% GIS load) 515 kV with 3.1 nF and 192 Hz →1.9 A
Reactive load 515 kV with 1.9 A →1 MVA
Power needed to compensate losses 1 MVA / 100 →10 kW
149
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
These calculations show that a 32 A power supply would be sufficient. However, considering further
factors (e.g. losses in the frequency converter and inrush currents in the insulation transformer) a 63 A
supply may be more prudent.
As an example, a circuit diagram for the power supply of a frequency-tuned resonant test set is shown
below.
Figure C.2 Example circuit diagram for power supply of a frequency-tuned resonant test set
In the United States (US) most utilities have standardised on the following station auxiliary power
voltages for their substations:
• 120 V / 240 V single-phase,
• 208 V / 120 V three-phase.
There are some cases, especially for large transmission substations, where the station auxiliary power
voltage sources are 480 V / 277 V three-phase. These are basically for the larger power transformer
auxiliary power needs. The general station auxiliary power voltages at those large substations would
still also be 120 V / 240 V single-phase or 208 V / 120 V three-phase. For HV testing of GIS when a
specific auxiliary power source is needed at voltages (e.g. 400 V three-phase) most US utilities will
bring in a portable generator for use during HV testing.
Figure C.3 Example circuit diagram for power supply of a power-frequency test set
The power supply for 50 Hz / 60 Hz HV test transformers is typically suitable for both short-time
operation and continuous operation. But thermal capabilities of the used insulation system are typically
very limited, so that allowable load cycles are defined by the OEM of the HV test transformer.
150
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Inductive power compensation used on the LV side of the feeding unit can be applied to reduce the
impact of those constraints.
The figure below shows an example of how the value of an inductance used for power compensation
is changing dependent on the test capacity and the test frequency.
Figure C.4 Example of inductance for power compensation dependent on test capacity
151
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
152
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
153
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
154
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
155
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
156
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
157
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure D.19 Gas pressure and switching positions during extension works at bay D07-BB1
158
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
159
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure D.24 After installation of new bays connected to BB1 prepare gas works for installation works at
BB2
Figure D.25 Overview after installation of new bays connected to BB1 (phase L1)
Figure D.26 Overview after installation of new bays connected to BB1 (phases L2, L3)
160
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure D.27 Gas pressure and switching positions during extension works at bay D07-BB2 (phase L1)
Figure D.28 Gas pressure and switching positions during extension works at bay D07-BB2 (phases L2,
L3)
161
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
162
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
163
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
General information:
Gas compartment =D06 -Q25 has also reduced gas pressure, and =D06 -Q25 is in closed position.
After BB link installation referring gas compartments do not have to be HV tested again as these gas
compartments are small, and all areas have good accessibility for visual inspection of cleanliness.
164
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
165
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure E.1 Photos showing HV test set-up for investigation of 'PD calibration' procedures
166
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
Figure E.2 Electric circuit diagram for investigation of 'PD calibration' procedures
Calibrator injection Calibration S1 S1G S2 S2G S3 S3G Injection point of the Measured PD level
level in pC done at PD signal in pC
10 S1G C C O O C C S1G 10
20 S1G C C C C C C S1G 20
20 S2G C C C C C C S2G 20
20 S3G C C C C C C S3G 20
Table notes:
Note 1: The calibrator is connected between the isolated earthing switch (S1G, S2G or S3G) in closed position and earth
Note 2: PD have been measured in the frequency range of 40 kHz to 800 kHz
Note 3: Switching device position C=CLOSE O=OPEN
167
TB 920 - Concepts for on-site HV testing of GIS after installation, extension, retrofit or repair
168
ISBN : 978-2-85873-625-6
TECHNICAL BROCHURES
©2023 - CIGRE
Reference 920 - December 2023