Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Project Title: CCK Waterworks C2 Process Upgrade Works Date: 15-FEB-17

Contract No: 1160370

Subject: Detail Assessment of Quantum PLC changes to M580 PLC

Quantum PLCs Procurement Status

Scheduled Delivery Status

PLC Hardware (Quantum Series) PLC Hardware Delivery Scheduled Status


Approval Date

1st Batch of Delivery (Sodium Hypo and 2 x existing 16-Dec-16 Mid of February-2017 Target to receive delivery of PLC systems for
EICs Process) Sodium Hypo by End of FEBRUARY.

On Hold (2 x existing EICs Process PLC system)

2nd Batch of Delivery (3 x Existing EIC Process) Mid of March 2017 On Hold

3rd Batch of Delivery (The rest of existing EICs as well Mid of May 2017 On Hold
as new plants under C2 contract)
Project Title: CCK Waterworks C2 Process Upgrade Works Date: 15-FEB-17

Contract No: 1160370

Subject: Detail Assessment of Quantum PLC changes to M580 PLC

Detail Assessment Table

Design Change Summary Remark


Option A: Change Quantum CPU to M580 CPU with Existing Quantum PLC program can be re-used with conversion to make
Technical Quantum RIO System compatible with M580: Additional engineering effort required.
Assessment (Applicable to Existing Plant EIC systems & New Process
Areas) Minor impact on SCADA Upgrading Work due to I/O mapping differences and
new diagnostic features.

Option B: Change Quantum CPU to M580 CPU with x80 Existing Quantum PLC program can be re-used with conversion to make
RIO System compatible with M580: Additional engineering effort required.
(Applicable to Existing Plant EIC systems & New Process
Areas) Re-designing will be required to transfer Quantum IO Platform to x80 IO
Platform (such as wirings, panel design work, IO addressing and etc.)

Minor impact on SCADA Upgrading Work due to I/O mapping differences and
new diagnostic features.
Project Title: CCK Waterworks C2 Process Upgrade Works Date: 15-FEB-17

Contract No: 1160370

Subject: Detail Assessment of Quantum PLC changes to M580 PLC

Impact Summary Remark

Cost Impact Materials Cost No Schneider promised to keep same pricing for either changes on CPU only or
the whole platform changes.

S$31,200
Administration Yes (with Option A) Due to changes, there will be additional administration cost which involves
/Engineering Cost Cancelation of existing PO and the whole process of purchase activities as well
S$44,800 as project discounts. And additional engineering costs due to design changes
(with Option B) as per engineering work impact.

(Additional man-day requirements for administration works : 5-days) -


$S800/day

(Additional man-day requirements: 3-days for each process area [Total - 17]) -
$S800/day

Option A:
- Engineering work to develop/convert existing Quantum PLC program
to M580 PLC including new diagnostic feature of M580 PLC Platform.
(1-Man Day)
- Additional engineering work for internal testing of newly developed
M580 program to make sure it is working as per existing Quantum PLC
program. (1-Man Day)

Option B:
- Re-engineering work to re-design drawings (wirings/schematic) for
M580 PLC platform. (1-Man Day)
Project Title: CCK Waterworks C2 Process Upgrade Works Date: 15-FEB-17

Contract No: 1160370

Subject: Detail Assessment of Quantum PLC changes to M580 PLC

Schedule Yes 3 Months Planned schedule (as attached) will be pushed back by 3 months’ time due to
Impact 6 to 8 weeks (Schneider) delivery lead-time as well as administrative work on
purchase activities.

Planned schedule

3 months delay of
work due to changes

You might also like