Professional Documents
Culture Documents
Section 9
Section 9
Section 9
O.M.P. NO OF ______
IN THE MATTER OF
M/S ____________________
… PETITIONER
VERSUS
M/S ____________________
… RESPONDENT
INDEX
SNo. Particular Pages
PETITIONER
THROUGH
( )
ADVOCATE
ENROLLMENT NO………
ADDRESS:………………
EMAIL:…………………
MOB. NO………………
Place :_____
Signed on: ___________
Filed on :
Note – That the petitioner has already filed a Petition under Section 9
of the Arbitration & Conciliation Act 1996 and the same is
pending adjudication before Hon’ble Mr. Justice ______ and
is listed for ______.
IN THE HIGH COURT OF ______ AT ______
O.M.P. NO OF ______
IN THE MATTER OF
M/S ____________________
… PETITIONER
VERSUS
M/S ____________________
… RESPONDENT
To
URGENT APPLICATION
Sir,
PETITIONER
THROUGH
( )
ADVOCATE
ENROLLMENT NO………
ADDRESS:………………
EMAIL:…………………
MOB. NO………………
Place :_____
Signed on: ___________
Filed on :
IN THE HIGH COURT OF ______ AT ______
O.M.P. NO OF ______
IN THE MATTER OF
M/S ____________________
… PETITIONER
VERSUS
M/S ____________________
… RESPONDENT
MEMO OF PARTIES
M/s. _______,
having its Registered office: _______
_______ duly represented through
its Director, _______,
S/o _______, R/o _______
_______ _______ ….Petitioner
Versus
M/s. _______,
having its registered office at : _______
_____________________, through its Director
Mr. _______
Also at
_______
_______,
___________
And also at
M/s. _______,
C/o _______,
_______
_______
…. Respondent
PETITIONER
THROUGH
( )
ADVOCATE
ENROLLMENT NO………
ADDRESS:………………
EMAIL:…………………
MOB. NO………………
Place :_____
Signed on: ___________
Filed on :
IN THE HIGH COURT OF ______ AT ______
O.M.P. NO OF ______
IN THE MATTER OF
M/S ____________________
… PETITIONER
VERSUS
M/S ____________________
… RESPONDENT
C.P.C
Hon’ble Court. The contents of the same are not being reproduced here for
the sake of brevity but those may kindly be read as part and parcel of this
application.
alongwith the petition. The certified copies of the same are being applied
and those shall be filed in this Hon’ble Court as soon as they are received
kindly be heard on the strength of true/ photo copies of the documents and
the filing of certified copies may not be insisted upon at this stage, in the
Prayed accordingly.
PETITIONER
THROUGH
( )
ADVOCATE
ENROLLMENT NO………
ADDRESS:………………
EMAIL:…………………
MOB. NO………………
Place :_____
Signed on: ___________
Filed on :
IN THE HIGH COURT OF ______ AT ______
O.M.P. NO OF ______
IN THE MATTER OF
M/S ____________________
… RESPONDENTS
1996.
Managing Director
Registered Office at
__________, __________
__________
__________ (__________)
Holder _______.
__________, __________
(__________) duly
Holder __________.
as __________)
____________________________
_______________
Agreement under
appointment procedure
agreed upon by them.
Agreement ).
engaged in the business of real estate and has enviable goodwill in the
market.
who are husband and wife met _____, Managing Director of the Petitioner
No.1. Petitioner No. 2 represented to _____ that he was the owner of land
Deed No. ______ dated ______, Sale Deeds No. ______ dated ______,
Sale Deed No. ______ dated ______ and Sale Deed No. ______ dated
______ registered in the office of Sub Registrar, __________
was the owner of land admeasuring ______ app. ______ Acre i.e. ______
which was purchased by the Vendor vide Sale Deed No.______ dated
petitioner No. 1 company for sale of part of the said land. That in
furtherance thereof, the Petitioner No. 2, out of his total land of ______ sq
admeasuring ______ i.e. ______ sq yds with the petitioner No. 1, M/s
also at the same time stated that since the permission for change of land use
for construction of a ______ on the said land admeasuring ______ Sq. Yds.
had been granted by the Director Town and Country Planning ______
arrange finances from the bank/ Financial Institutions for the construction
finances to the projects of such large magnitude unless and until the same
was not in the names of Companies / Corporate . The petitioner no 2
parties further negotiated amongst them and thereafter the petitioner No.2
was agreed that the petitioner No. 1 would provide a built up area of
consideration thereof.
Shri __________ requested the petitioner No.1 that he was willing to sell
The petitioner no 1 then agreed to buy this area of ______ sq. ft. also, and
Sell with petitioner No. 2 and the petitioner No.1 bought the area of
the parties felt that since it was a time bound project therefore it would be
with the respondent company for the construction of ______ and the
Party. In the said Collaboration Agreement dated ______ the details of all
petitioner No.2 and petitioner No.3 were also mentioned for keeping the
record straight and also for clarity. On ______ the petitioners no 2 and 3
also gave respective possessions letters of the land to the petitioner No. 1
company and the petitioner No. 1 company in turn paid the entire
to Sell dated ______, dated ______ and ______. In other words the
accounts between the petitioners i.e. petitioner No.1, petitioner No.2 &
petitioner No.3 stood settled on ______ in all respects and Receipts for full
and final payments and the possession letters of the lands were duly handed
over by the petitioner No.2 & petitioner No.3 to the petitioner No. 1
company and as such the possession of the land was delivered to the
It may be pertinent to mention that out of his total lands of ______ sq. yds.,
the petitioner No. 2 __________ retained an area of ___ sq yds for setting
up a Petrol Pump.
f. The party of the first part was entitled to ______ sq.ft. of built up
area in the proposed ______ and the petitioner No. 1 was entitled to
“PROJECT LAND”.
Director, Town and Country Planning vide Memo dated ______ and
were valid upto ______ and it was further provided that extension of
______ and __________ at ______ and the Hon’ble High Court vide
its order dated ______ had granted the extension for construction of
dated ______ had extended the permission for change of land use
for a further period of three years from the date of issue of the said
memo. Thus for all purposes extension granted by the Hon’ble High
j. Third party i.e. the respondent was to start the development and
construction works within the period of ___ days from the said
k. The parties had also agreed that the built up and unbuilt up
Resort.
Resort.
charitable/social causes.
particularly when the plans were valid for only a period of ___ years from
______ and ______ at ______ vide it’s order dated ______ had extended
the permission for change of land use by three years only i.e. upto _____.
In this regard it is very pertinent to mention here that the said order dated
very purpose of the parties to get into the Collaboration Agreement dated
______ was to get the work executed in a time bound manner, as it was
clear to everyone that if the project is not completed within the stipulated
time period, then the extension of the permissions for change of land use
granted by the Hon’ble High Court would expire on ______ leaving the
rendering the said land of no value because after the expiry of the said
period no construction activity can be carried out on the said land and the
land use of the said land would restore back to its original land use i.e. for
agricultural purposes.
however kept on making promises that they were going to commence the
development and construction work at site very shortly, but despite their
said land. The petitioners reminded them the urgency involved in timely
activity, did not start the work. Soon it became clear that the respondent
resources to carry out the construction activities within the stipulated time
period.
7(ix) That the petitioners were clearly disappointed
and naturally very agitated because the respondent company had failed to
carry out its contractual obligations. The petitioners also got to know from
various sources that the respondent company perhaps never had adequate
financial and manpower resources to execute the work and the respondent
7(x) That the crucial time was fast running out for
Left with no other option, the petitioner No.1 vide legal notice dated
______ terminated the said collaboration agreement and cancelled the same
in all respects and also gave separate Notice for appointment of Arbitrator.
7(xi) That the petitioner No. 2 and also petitioner No. 3 gave their
separate legal notices on similar lines. The Petitioners also gave separate
legal notices to the respondent calling upon the respondent company and its
respondent company and also to not to act upon them in any manner.
agreement did not have any other option but to somehow start and complete
the construction activities either on their own or through any other third
party and that too in a time bound manner so that the entire construction
can take place on or before ______ i.e the said dead line given by the
other petitioners are making all possible effort to get the construction done
at the site, either on their own or any other third party under a fresh
planning.
construction activity which the petitioners are proposing to carry out either
loving and law abiding citizens and they want to complete the construction
they want to black mail the petitioners by coercing them to shell out heavy
amounts to them and that is the reason the respondent company and its
construction activity . The respondent perhaps know fully well that if they
accompli for the petitioners who then shall suffer irreparable loss and
damages.
herein have been wronged by the respondent and they have already suffered
It may be noted that if the respondent would have carried out the
construction work and had completed the entire project on time, then the
entire sale proceeds of the Project would have been almost to the tune of
Rs. ___ Crores calculated at the minimum rate of sale price of Rs. _____/-
per sq.ft. multiplied by the total area to be constructed which was ____
sq.ft. app. The petitioner, M/s ______( Petitioner No1 ) who is entitled to
___% of the sale proceeds under the Collaboration Agreement , would then
present calculations, besides a sum of Rs. _____ Crores towards the loss of
goodwill which the petitioner have suffered. Therefore the petitioner No. 1,
without prejudice to all other claims that may accrue in favour of petitioner
No. 1 in future, it is submitted that the petitioner No. 1 would have a claim
petitioner reserves its right to file a detailed statement of claims before the
cannot take away the favourable possession of the said land or disrupt the
arbitrator. The petitioners have already sent their legal notices through
their advocate for appointment of arbitrator and have proposed the name of
arisen between the parties. The said notices have been duly served on the
respondent. However the respondent company has not replied as yet to the
where they have hardly any choice but to get the construction done and
raise the construction either through their own or through some third party
with whom they can enter into a collaboration agreement. The respondent
on the other hand is nursing malafide intentions to delay the matter and
submit that today the real intention of the respondent company is to some
how make wrongful gains out of their own wrongs. The Respondent
company and its directors namely Shri ______and Shri ______ know very
well that further delay in construction could result in grave financial loss to
the petitioners. Therefore the respondent company and its directors are
petitioners themselves or through any other third party on the said land and
in this process they are trying to coerce the petitioners to cough up huge
sums of money to the respondent who are hell bent of making loss out of
petitioners that they shall take forcible possession of the land which is
presently with the petitioners and they shall also not allow any one else to
start construction if they are not given Crores of rupees by the petitioners.
The petitioners respectfully submit that it is clear cut case of not only
cheating, fraud but also of black mailing and taking unfair advantage of the
the respondent company and its officials will either try to take forceable
possession of the Project Land from the petitioners or else they would
rights.
protected.
It has also been held in catena of judgments of the Hon’ble Supreme Court
that Section 9 of the Arbitration and Conciliation Act 1996 only deals with
interim measures by the court and in a fit case where interest of parties
law, the Hon’ble Court may be graciously pleased to pass interim Order.
directors and petitioners 2 and 3 that they would not allow any
petitioners.
CLAIM
the present valuation, the petitioner No. 1, M/s ______ would at least have
company and the said claim may also go up in future and therefore without
ARBITRATION CLAUSE
Agreement.
COURT FEES
application.
13. That the petitioners have not filed any other or similar
India.
PRAYER
It is therefore most respectfully prayed that this Hon’ble Court may kindly
be pleased to:-
for and on their behalf from taking forcible possession of the project
(+) ___sq. yds. and ____ sq. yds. of the petitioners falling in Khasra
any one acting for and on behalf of the respondent company from
creating any hindrance or disrupting, disturbing, threatening to
petitioners.
(b) Pass any other or further order(s) as this Hon’ble Court may deem fit
and proper in the given facts and circumstances of the case in the
interest of justice.
Prayed accordingly.
PETITIONER
THROUGH
( )
ADVOCATE
ENROLLMENT NO………
ADDRESS:………………
EMAIL:…………………
MOB. NO………………
Place :_____
Signed on: ___________
Filed on :