Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Features

THE DISTINCTION BETWEEN DISRUPTION


AND PROLONGATION CLAIMS
Colin Russell, HKA

Of the types of claims made for losses under elements are priced and paid for in different but also ends up remaining on site longer?
construction contracts, generally more atten- manners. The pricing and payment for the It is under a disruption claim that a
tion is paid to claims for prolongation costs than actual work is based on the volume of work contractor will seek to recover these additional
that of disruption, yet a claim for disruption can undertaken (eg, the amount of wall constructed) direct costs and this would be a relatively simple
be substantial in comparison to prolongation. whereas the indirect cost are, on the most part, calculation if the additional cost to the labour
So, what are disruption claims and how do they on the basis of time (eg, rental charges for site and plant were as a result of a suspension to the
differ from prolongation claims? hutting). work. However, this is rarely the case of most
A contractor is normally paid on the basis of A claim for prolongation costs is, in theory, disruption claims which become more compli-
the works carried out plus its on-site overhead relatively simple to prepare. To do so, the cated when, although delayed, the contractor’s
costs, commonly called ‘Preliminaries’ (i.e. site contractor’s time related indirect costs (its labour and plant is producing some amount
management staff, site huts, etc). In addition, Preliminaries) during the alleged employer’s of work and being paid for this work as it is
it is paid head office overheads and profit. The delay periods are quantified using accounts completed.
contractor’s costs in relation to the actual work records. A prolongation cost claim endeavours This situation is complicated further when
undertaken are referred to as ‘direct costs’ to establish the additional costs of the contractor the contractor suffers delay to areas of work that
whereas those for the Preliminaries are referred remaining on site for longer than planned, but are not on the critical path of its programme.
to as ‘indirect costs’. how does a contractor recover the additional Such a delay would not entitle the contractor
It is important to understand when making cost (loss and expense) of labour and plant (i.e. to an extension of time, as the completion date
the distinction between claims for prolongation the contractor’s direct cost) that is undertaking would have not been delayed and therefore
and disruption that the direct and indirect cost the physical works or indeed variation works, prolongation costs could not be claimed.

whoswholegal.com 1
Research

In such situations, a contractor could still production, productivity and efficiency that is delayed, the rate at which the contractor
have suffered a loss as the result of actions by construction work is priced. For example, a produces the work slows, its efficiency falls and
the employer but is unable to recover these blockwork walling rate would typically be priced therefore the contractor’s productivity falls. This
costs, through a prolongation claim, as the losses in the following manner: can be caused by a number of factors for which
suffered would not be to the contractor’s indirect either the contractor or the employer can be
costs but instead to its direct costs. However, as Blockwork rate per m2 = Labour per m2 responsible including variations causing out
the contractor is being paid for undertaking the + Equipment per m2 + Materials per m2 of sequence working, incorrect or late design
works on the basis of the amount of work under- causing stacking of trades, shortages of mate-
taken, why would this lead to a loss when the The labour cost is calculated on the time taken rials or skilled labour, etc.
contractor will ultimately be paid for the works to lay 1m2 of blockwork multiplied by the hourly For example, if a contractor has assumed
completed and, therefore, why is it necessary for rate of that labour. Likewise, the equipment that a blocklayer can lay 20m2 of blockwork in
the contractor to claim for disruption? cost is calculated using the amount of time the an hour at a labour rate of $25 per hour then
In order to answer these questions, we labour needs to construct 1m2 of blockwork the labour cost is $1.25 per m2. However, if as a
need to understand what form of losses a multiplied by the cost per hour of the equip- result of delays, the blocklayer was only able to
disruption claim seeks to recover. The Society ment. The material cost is simply the cost of the lay 15m2 of blocks in an hour then the contrac-
of Construction Law (SCL) Delay and Disruption materials needed to construct 1m2. tor’s cost would rise to $1.67 per m2 because
Protocol distinguishes disruption from delay and of the fixed labour cost. As the contractor
defines it as “a disturbance, hinderance or inter- had assumed $1.25 per m2 in its tender, the
pretation to the Contractor’s normal working contractor would lose $0.42 for every m2 of
methods, resulting in lower efficiency”. Further, delayed blockwork. The essence of a disruption
the SCL advises that disruption claims “relate to claim is to recover such a loss due to a produc-
loss of productivity in the execution of particular tivity reduction.
work activities” and that because of disruption “The main issue with This loss against productivity is also the
“these work activities are not able to be carried basis of a claim for acceleration costs as an
out as efficiently as reasonably planned (or
preparing a disruption increase in productivity would also, usually,
possible)”. The SCL notes that where disruption claim is the detail of result in a drop in efficiency compared to that
events are the contractual responsibility of the set within the contractor’s rates. As productivity
other party, the loss and expense incurred due
information needed increases due to acceleration measures, effi-
to the loss of productivity may be compensable. to carry out the ciency decreases due to additional labour gangs
In order to understand this definition, it and crews working on multiple work fronts, out
is first necessary to understand the terms
calculations to a level of sequence working, increased supervision
‘production’, ‘productivity’ and ‘efficiency’ and that adequately shows etc. In other words, to quote an old English
their importance in the pricing of construction proverb “too many cooks spoil the broth”. As
contracts.
a drop in efficiency or with a disruption claim, it is the loss against the
Production is the act of making or manufac- lost productivity.” assumed efficiency and rate of production that
turing something and it identifies the number is claimed.
of items produced in a given time. Production In principle, a disruption claim should
is measured as a number of outputs, eg, 20m2 be relatively simple to calculate. So why are
of blockwork wall. On the other hand, produc- disruption claims regarded with such trepida-
tivity is how many items are produced within tion leading to them being often neglected and
a given time. It is measured as the number of presented in very basic manners, such as actual
items produced divided by the time to produce When work is priced as per the example labour costs less planned labour costs?
the items. So, if a blocklayer can lay 20m2 of above, in order to produce the unit output (in The main issue with preparing a disruption
blocks in an hour, the blocklayer’s productivity this case 1m2 of blockwork), the productivity of claim is the detail of information needed to carry
is 20m2 per hour. the labour and equipment are used in the rate out the calculations to a level that adequately
Unlike production and productivity, which calculation. By pricing the work on this basis, a shows a drop in efficiency or lost productivity.
both can be considered as quantitative measure- contractor assumes a level of productivity for its The different methods of preparing disruption
ments, efficiency is more a qualitative indicator labour and equipment. By assuming a set level claims all rely on calculating losses against
as it is the measure of the ability to do or produce of productivity, the contractor is also assuming productivity to some extent and the method
something without wasted materials, time or a set level of efficiency. So, if the contractor is chosen is normally driven by the information
energy. In effect, it is how well something is able to undertake the work more efficiently, that is available for its preparation. Whilst the
produced in terms of time and effort or, in other its productivity will increase meaning a better example above appears simple, a bill of quan-
words, how ‘good’ productivity is. Although effi- return against the priced rate. By contrast, if the tities can, even on relatively simple projects,
ciency can be described as qualitative in nature, contractor’s efficiency goes down, its expected include hundreds if not thousands of rates.
it can be measured quantitively as a percentage return against the priced rate will reduce. Disruption claims need thought, time for
ratio between input and output. For example, a The rates assumed by the contractor at the detailed analysis and most of all adequate
typical car engine is 35% efficient meaning that tender stage will have been set at a level of effi- records from which to prepare the calculations.
due to inefficiency, 65% of the fuel’s potential ciency that is near to or at the optimum level as Unfortunately, disruption claims are often
energy is lost. a contractor will want to complete the works regarded as an afterthought once the opportu-
These terms are important to the construc- as quickly and efficiently as possible (at least nity to create these records during the progress
tion industry because it is on the basis of in theory). In the situation where a contractor of the works has been lost.

2 whoswholegal.com
Research

Construction projects are extremely complex contractor beyond that of the contractor’s
and, in reality, disruption occurs on all projects assumed tender productivity level. For example,
at some level. In view of the fact the majority of a on a new motorway project, a contractor was
contractor’s costs lie in its direct costs as opposed able to show from its records that the non-dis-
the indirect costs (the 80:20 rule approximately rupted road construction was progressed at
applies), it would make sense for a contractor to a considerably higher level of efficiency than
record what its labour and plant is doing, where assumed at tender. As a result, the employer
it is doing it and when it is doing it, regardless of was required to compensate the contractor for
whether it wants to raise claims or not. not being able to achieve this higher level of
Such records would assist the contractor efficiency as a result of the disruption caused
to counter an employer’s usual rejection of the by the employer’s failure to provide site access
claim on the basis that the assumed level of to parts of the roadway.
efficiency and productivity was wrong at tender In order to assist the tribunal, an appointed
stage, and that no allowance for the contractor’s quantum expert will need to provide an opinion
own inefficiency had been made. in relation to the quantum claimed for the loss Colin Russell
With adequate records in place, the of productivity arising from the alleged disrup-
contractor should be able to compare the tion events. To do this, the expert will focus on just accepting a head count as is often seen. This
difference in its actual efficiency achieved for the records in relation to the time spent by the would allow the employer, for its own protection,
non-disrupted work activities to that of the labour and plant as well as its supervision in to ensure that an appropriate analysis is under-
disrupted work activities and thereby extin- undertaking the work activities. This is to estab- taken to correctly value the loss (if any).
guishing the employer’s criticism. An employer lish whether the reduction in productivity has In summary, a disruption cost claim calcu-
will often demand that such an analysis (the occurred and the quantum of any associated loss. lates the loss to a contractor’s direct costs due
‘measured mile’) is undertaken but it can have If an employer is found to be culpable of to a drop in efficiency and a reduction in produc-
a sting in the tail for the employer. As the losses causing a loss to the contractor’s productivity, tivity caused by the employer. It differs from a
in such an analysis are claimed on the difference the sums claimed can be substantial. It would prolongation claim, which is based on the losses
between the actual disrupted productivity and therefore also be prudent for the employer to to the contractor’s indirect cost as a result of
actual non-disrupted productivity, the employer insist that the contractor adequately records its remaining on site longer than planned, again,
may find that it is required to reimburse the resources in reporting progress as opposed to due to the employer.

whoswholegal.com 3

You might also like