Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

SABA-BULE RASA-BURJ JUNCTION

Bill of material quantity


Employer: Eel-Wayye Road and Logistics Office
Contractor: Not yet specified
Prepared By: DATU Engineering PLC
Project: Saba-Bule Rasa-Burj Juction
Amount Unit rate Amount
Pay item no Description Unit
A B C=A*B
SERIES 2000 SETTING OUT AND SITE CLEARANCE
DIVISION 2100 Removing the debris and clearing the site
21.01 Remove the debris and clear the top soil up to 200mm ha 15.42 31.674 488.41
DIVISION 2100 CARRIED TO SUMMARY 488.41
SERIES 3000 EARTHWORK
DIVISION 3100 Establishment of vertical alignment
31.01 Establishment of vertical alignment m 1674.2 1.716 2,872.93
31.02 Excavation to level and compaction -
a Soft material (cut-fill) m3 142,326.00 31.674 4,508,033.72
b Intermediate material (soft rock) cut-fill m3 46.669 -
c Hardrock (cut-fill) m3 12,000.00 148.953 1,787,436.00
31.03 Construction of embankment
I Side borrow
Production of side borrow fill, spreading and
a m3 116,780.95 39.1 4,566,135.15
compaction
Borrow material production, loading, unloading,
transporting, spreading and compacting using dump
II
truck, tractor, animal cart , labor and loaded from a
distance of
a (0.4<x<5)km m3 116,780.95 100.433 11,728,661.15
b (5<x<10)km m3 111.522 -
c (10<x<15)km m3 139.869 -
d (15<x<20)km m3 148.866 -
e (20<x<25)km m3 157.863 -
f (25<x<35)km m3 166.86 -
DIVISION 3100 CARRIED TO SUMMARY 22,593,138.95

DIVISION 3200 CONSTRUCTION OF THE ROAD FORMATION

Side drain excavation and throwing to the center


of the road for use of camber formation if suitable
32,01
or cart away unsuitable/excess material at the
distance not less than 6m
a Soft material irrespective of depth m3 42,697.80 24.141 1,030,767.59
b Intermediate material irrespective of depth m3 48.271 -
c Hardrock (cut-fill) m3 3600 64.845 233,442.00
32.02 Spreading and compaction for camber formation -
Spread and throw to the center of the road and
a m3 77,163.00 2.992 230,871.70
compaction for the camber formation
DIVISION 3200 CARRIED TO SUMMARY 1,495,081.29

BILL OF MATERIAL QUANTITY


SABA-BULE RASA-BURJ JUNCTION

EXCAVATION FOR MINOR DRAINAGE


DIVISION 3300
STRUCTURE
33.01 Excavation for drainage structure
a Soft material irrespective of depth m3 54.89 25.81 1,416.71
b Intermediate material irrespective of depth m3 2280 62.30 142,044.00
c Hardrock excavation m3 1832.76 68.94 126,354.14
Backfilling using excavated materials including
33.02 m3 26.55 -
compaction (or structure)
33.03 Backfilling using selected granular materials
33.03 including compaction (using dump truck, Tractor, m3
loader from distance )
a (0.4<x<5)km m3 3301.442 209.14 690,463.58
b (5<x<10)km m3 198.99 -
c (10<x<15)km m3 224.659 -
d (15<x<20)km m3 250.328 -
e (20<x<25)km m3 275.997 -
f (25<x<35)km m3 301.666 -
G-20 capping layer with minimum 4days soaked CBR
33.04 of 20% (using Dump truck, Tractor, Loader from
distance
a (0.4<x<5)km m3 10,566.00 102.16 1,079,422.56
b (5<x<10)km m3 118.1 -
c (10<x<15)km m3 126.08 -
d (15<x<20)km m3 134.06 -
e (20<x<25)km m3 150 -
f (25<x<35)km m3 173.93 -
DIVISION 3300 CARRIED TO SUMMARY 269,814.85
DIVISION 3000 CARRIED TO SUMMARY 24,358,035.08
CONSTRUCTION OF CLASS "B" STONE
DIVISION 3400
MASONRY
34.01.Construction of Cemented stone masonry
34.01 transported (using dump truck) -For the pipe m3 89.0485 1,433.86 127,683.08
headwalling

DIVISION 3400 CARRIED TO SUMMARY 127,683.08


SERIES 3000 TOTAL SUM 397,497.93
SERIES 4000 CULVERT AND DRAINAGE WORKS
DIVISION 4100 PIPE LAYING
41.01 Pipe laying
Reinforced concrete pipe production and laying on
class B-bedding (C-25) production and laying on
Class-B Bedding
a)Nominal diameter 1060mm pcs 80 4,087.73 327,018.40
DIVISION 4100 CARRIED TO SUMMARY 327,018.40
MASONRY FOR MINOR DRAINAGE
DIVISION 4200
STRUCTURE
Construction of cemented mortared class ''B'' stone
42.01 m3
masonry (1:4) irrespective of stone source distance 103.68 995.06 103,167.82
Construction of cemented mortared class ''C'' stone
42.02 m3
masonry (1:6) for walls, fords, heads and wing walls, 122.76 650.40 79,843.10

DIVISION 4200 CARRIED TO SUMMARY 183,010.92


DIVISION 4300 Concrete for Minor drainage structures

BILL OF MATERIAL QUANTITY


SABA-BULE RASA-BURJ JUNCTION

DIVISION 4300 Concrete for Minor drainage structures


Minor drainage structure (inlet and outlet mass
43.01
concrete (class c) structure m3 180 2,179.17 392,250.60
DIVISION 4300 CARRIED TO SUMMARY 392,250.60
DIVISION 4700 DRIFT AND VENTED CAUSEWAYS
47.01 Ford drift (Reinforced concrete)
a) Concrete C-25 m3 67.5 2,179.17 147,093.98
b) Reinforcement bar Kg 12,989.58 61.20 794,962.11
47.02 Ford drift (stone pitching(hardcoring )
a) (0Km-4Km) m3 135 966.22 130,439.70
DIVISION 4700 CARRIED TO SUMMARY 1,072,495.79
SERIES 4000 TOTAL SUM 1,974,775.71
SERIES 8000 ROAD FURNITURE
DIVISION 8100 TRAFFIC SIGN
81.01 Traffic sign No 7 89.79 628.52
81.02 Guide and km posts No 33 1,316.73 43,451.93
81.03 Guardrails Lm 24 26.94 646.49
DIVISION 8100 CARRIED TO SUMMARY 44,726.93

BILL OF MATERIAL QUANTITY

You might also like