MASTER SCHEDULE - OPSI 1 (AWARDING CIP APPROVAL - MAY 24)

HALLIBURTON's WAREHOUSE, WORKSHOP & OFFICE PROJECT

ID Task Name DurationStart Finish 2024 2025


Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 HALLIBURTON's WAREHOUSE, WORKSHOP & OFFICE PROJECT 684 days 28/04/24 27/03/26
2 1. PRE-DEVELOPMENT ACTIVITY 80 days 28/04/24 16/07/24
3 Corporate Investment Proposal (CIP) Approval 14 days 20/05/24 02/06/24 20/05 02/06
4 Land Acquistion 37 days 09/06/24 16/07/24
5 Down Payment 0 days 09/06/24 09/06/24 09/06
6 Due Delligence 30 days 10/06/24 09/07/24 10/06 09/07
7 Pengembalian Batas Tanah (Joint Survey dengan BPN) 14 days 26/06/24 09/07/24 26/06 09/07
8 Flood Peil 14 days 03/07/24 16/07/24 03/07 16/07
9 Appointment of Consultant (Topo, Design & QS) 50 days 28/04/24 16/06/24
10 Tender Topography & Soil Investigation 14 days 03/06/24 16/06/24 03/06 16/06
11 Tender Design Consultant 44 days 28/04/24 10/06/24
12 Architecture Consultant 8 days 28/04/24 05/05/24 28/04 05/05
13 Structure Consultant 8 days 03/06/24 10/06/24 03/06 10/06
14 MEP Consultant 8 days 03/06/24 10/06/24 03/06 10/06
15 Tender QS Consultant 8 days 28/04/24 05/05/24 28/04 05/05
16 Tender Permit Consultant 8 days 03/06/24 10/06/24 03/06 10/06
17 2. DESIGN - PLANNING 152 days 06/05/24 04/10/24
18 Topography & Soil Investigation 30 days 17/06/24 16/07/24 17/06 16/07
19 Concept Design 14 days 06/05/24 19/05/24 06/05 19/05
20 Schematic/Analityc Design 30 days 17/07/24 15/08/24 17/07 15/08
21 Design Development 30 days 16/08/24 14/09/24 16/08 14/09
22 Tender Drawing 10 days 15/09/24 24/09/24 15/09 24/09
23 Forcon Drawing 10 days 25/09/24 04/10/24 25/09 04/10
24 3.PERMIT 641 days 10/06/24 27/03/26
25 PPJB (Perjanjian Pengikutan Jual Beli) 15 days 10/06/24 24/06/24 10/06 24/06
26 AJB (Akte Jual Beli) 15 days 25/06/24 09/07/24 25/06 09/07
27 Pilling Permit 30 days 09/09/24 08/10/24 09/09 08/10
28 Izin Lokasi (IPPL) 7 days 10/07/24 16/07/24 10/07 16/07
29 KRK BKPRD 30 days 17/07/24 15/08/24 17/07 15/08
30 AMDAL 28 days 16/08/24 12/09/24
31 Pertimbangan Teknis BPN 28 days 16/08/24 12/09/24 16/08 12/09
32 Dewatering 28 days 16/08/24 12/09/24 16/08 12/09
33 PLB (Peil Lantai Bangunan)/ Peil Banjir 28 days 16/08/24 12/09/24 16/08 12/09
34 ANDALALIN 28 days 16/08/24 12/09/24 16/08 12/09
35 KA ANDAL 28 days 16/08/24 12/09/24 16/08 12/09
36 ANDAL 28 days 16/08/24 12/09/24 16/08 12/09
37 Izin Lingkungan 28 days 16/08/24 12/09/24 16/08 12/09
38 IPPR (Ijin Prinsip Pemanfaatan Ruang) 12 days 13/09/24 24/09/24 13/09 24/09
39 KRK (Keterangan Rencana Kota) Definitif 7 days 25/09/24 01/10/24 25/09 01/10
40 TABG AP 12 days 02/10/24 13/10/24
41 Perjanjian Pemenuhan Kewajiban IPPR 12 days 02/10/24 13/10/24 02/10 13/10
42 Pengesahan GPA (TABG AP) 12 days 02/10/24 13/10/24 02/10 13/10
43 TABG SG 12 days 14/10/24 25/10/24 14/10 25/10
44 IIPAL 28 days 26/10/24 22/11/24 26/10 22/11
45 IMB Pondasi 20 days 23/11/24 12/12/24 23/11 12/12
46 IMB 0 days 12/12/24 12/12/24 12/12
47 SLF 30 days 26/02/26 27/03/26 26/02 27/03
48 4.COST ESTIMATE & TENDER/ PROCRUREMENT 422 days 06/05/24 16/07/25
49 QS Concept/Preliminary Cost Analysis 14 days 06/05/24 19/05/24 06/05 19/05
50 BQ & Tender Document - Consultant QS 30 days 25/09/24 24/10/24 25/09 24/10
51 Land Fill Tender and Award 30 days 01/08/24 30/08/24 01/08 30/08
52 Pilling Supplier & Contractor Tender & Award 50 days 16/08/24 04/10/24 16/08 04/10
53 Main Contractor SAP Tender & award 90 days 25/10/24 22/01/25 25/10 22/01
54 Rebar Supplier Tender & Award 90 days 25/10/24 22/01/25 25/10 22/01
55 Steel Structure Contractor Tender & Award 90 days 25/10/24 22/01/25 25/10 22/01
56 MEP Contractor Tender & Award 90 days 04/12/24 03/03/25 04/12 03/03
57 Roofing & Cladding Contractor Tender & Award 90 days 24/11/24 21/02/25 24/11 21/02
58 Power Generator Supplier Tender & Award 120 days 04/03/25 16/07/25 04/03 16/07

Page 1
MASTER SCHEDULE - OPSI 1 (AWARDING CIP APPROVAL - MAY 24)
HALLIBURTON's WAREHOUSE, WORKSHOP & OFFICE PROJECT

ID Task Name DurationStart Finish 2024 2025


Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
59 CONSTRUCTION PHASE (based on GFA 48,274 m2) 522 days 31/08/24 18/02/26
60 Land Fill Works 94 days 31/08/24 02/12/24
61 Mobilization Equipment & Join Survey 3 days 31/08/24 02/09/24 31/08 02/09
62 Land Clearing 50 cm 4 days 31/08/24 03/09/24 31/08 03/09
63 Existing Soil Compacting + CBR/ Sand Cone 90 days 04/09/24 02/12/24 04/09 02/12
64 Indicator & Pilling Works 146 days 09/10/24 03/03/25
65 Indicator Pile Casting 30 days 09/10/24 07/11/24 09/10 07/11
66 Indicator Piling 30 days 03/11/24 02/12/24 03/11 02/12
67 Main Pile Casting 80 days 24/11/24 11/02/25 24/11 11/02
68 Pilling Works 86 days 08/12/24 03/03/25 08/12 03/03
69 PDA Test 28 days 04/02/25 03/03/25 04/02 03/03
70 Loading Test 28 days 04/02/25 03/03/25 04/02 03/03
71 Upper Structure 352 days 17/02/25 18/02/26
72 Main Contractor (SAP) Works 352 days 17/02/25 18/02/26 17/02 18/02
73 Steel Structure Works 290 days 17/02/25 18/12/25 17/02 18/12
74 ME Works 292 days 03/05/25 18/02/26 03/05 18/02
75 Roofing & Cladding Works 245 days 03/05/25 02/01/26 03/05 02/01
76 Power Generator 168 days 04/09/25 18/02/26 04/09 18/02
77 GO LIVE - Handover to Operation 7 days 19/02/26 25/02/26 19/02 25/02