MASTER SCHEDULE
HALLIBURTON's WAREHOUSE, WORKSHOP & OFFICE PROJECT
ID Task Name Duration Start Finish 2023 2024 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
46 IMB 0 days Fri 10/05/24 Fri 10/05/24 10/05
47 SLF 30 days Fri 25/07/25 Sat 23/08/25 25/07 23/08
48 4.COST ESTIMATE & TENDER/ PROCRUREMENT 422 daysTue 19/09/23 Wed 27/11/24
49 QS Concept/Preliminary Cost Analysis 14 days Tue 19/09/23 Mon 02/10/23 19/09 02/10
50 BQ & Tender Document - Consultant QS 30 days Thu 08/02/24 Fri 08/03/24 08/02 08/03
51 Land Fill Tender and Award 30 days Fri 15/12/23 Sat 13/01/24 15/12 13/01
52 Pilling Supplier & Contractor Tender & Award 50 days Sat 30/12/23 Sat 17/02/24 30/12 17/02
53 Main Contractor SAP Tender & award 90 days Sat 09/03/24 Thu 20/06/24 09/03 20/06
54 Rebar Supplier Tender & Award 90 days Sat 09/03/24 Thu 20/06/24 09/03 20/06
55 Steel Structure Contractor Tender & Award 90 days Sat 09/03/24 Thu 20/06/24 09/03 20/06
56 MEP Contractor Tender & Award 90 days Thu 02/05/24 Tue 30/07/24 02/05 30/07
57 Roofing & Cladding Contractor Tender & Award 90 days Mon 22/04/24 Sat 20/07/24 22/04 20/07
58 Power Generator Supplier Tender & Award 120 daysWed 31/07/24 Wed 27/11/24 31/07 27/11
59 CONSTRUCTION PHASE 522 daysSun 14/01/24 Thu 17/07/25
60 Land Fill Works 94 days Sun 14/01/24 Tue 30/04/24
61 Mobilization Equipment & Join Survey 3 days Sun 14/01/24 Tue 16/01/24 14/01 16/01
62 Land Clearing 50 cm 4 days Sun 14/01/24 Wed 17/01/24 14/01 17/01
63 Existing Soil Compacting + CBR/ Sand Cone 90 days Thu 18/01/24 Tue 30/04/24 18/01 30/04
64 Indicator & Pilling Works 146 daysThu 22/02/24 Tue 30/07/24
65 Indicator Pile Casting 30 days Thu 22/02/24 Fri 22/03/24 22/02 22/03
66 Indicator Piling 30 days Mon 18/03/24 Tue 30/04/24 18/03 30/04
67 Main Pile Casting 80 days Mon 22/04/24 Wed 10/07/24 22/04 10/07
68 Pilling Works 86 days Mon 06/05/24 Tue 30/07/24 06/05 30/07
69 PDA Test 28 days Wed 03/07/24 Tue 30/07/24 03/07 30/07
70 Loading Test 28 days Wed 03/07/24 Tue 30/07/24 03/07 30/07
71 Upper Structure 352 daysTue 16/07/24 Thu 17/07/25
72 Main Contractor (SAP) Works 352 daysTue 16/07/24 Thu 17/07/25 16/07 17/07
73 Steel Structure Works 290 daysTue 16/07/24 Fri 16/05/25 16/07 16/05
74 ME Works 292 daysSat 14/09/24 Thu 17/07/25 14/09 17/07
75 Roofing & Cladding Works 245 daysSat 14/09/24 Sat 31/05/25 14/09 31/05
76 Power Generator 168 daysThu 16/01/25 Thu 17/07/25 16/01 17/07
77 GO LIVE - Handover to Operation 7 days Fri 18/07/25 Thu 24/07/25 18/07 24/07