APPENDIX 10C

(PAM2018 - Pin. 5/2022)

CERTIFICATE OF DELAY AND EXTENSION OF TIME NO 1

Reference MCP2022/19/407A Modern Concept Properties Sdn Bhd


Lot 3481, Kueh Hock Kui Commercial
Centre, Jalan Tun Ahmad Zaidi Adruce,
93400 Kuching, Sarawak

Date 29 July 2023


To Pembinaan Mutiara Unik (PMU) No. 7089,
Blok 9, MTLD, Jalan Dato’ Mohd Musa, Kota
Samarahan, Samarahan,
94300, Sarawak

(Contractor)

Contract No. M C P 2 6 3 1 / 4 4 7 / 2 0 3 A / C C

Contract for Proposed Mixed Commercial and Residential Development at Taman Uni-Modern on
Lot 2631, Jalan Datuk Mohammad Musa, 94300 Kota Samarahan, Sarawak.

Section 1 & 2

I hereby certify that the progress and completion of the Section 1 & Section
2 of the Works as mentioned above is likely to be delayed beyond the Date for Completion stated
in the Appendix to the Conditions of Contract or beyond the extended Date for Completion
previously approved 30 November 2023 for section 1 and 31 May 2024 for section 2
due to the following reason/reasons:

Reason/reasons Clause+ Period of Delay and


Extension of Time++

1. Inclement of Weather Clause 23.8 (b) PAM 2018 4 days


1. Landslides Clause 23.8 (a) PAM 2018 3 days
2. Late in recieving AI Clause 23.8 (b) PAM 2018 14 days
3. Delay in receiving goods Clause 23.8 (b) PAM 2018 11 days
4. Delay by Artist Clause 23.8 (b) PAM 2018 7 days

16
Total 39 days
APPENDIX 10C (Cont’d)

2. In accordance with Clause 23 of the Conditions of Contract, I hereby grant you an extension
of time of 39 days for the completion of the Section of the Works* under
this Contract.

3. The Date for Completion which has been fixed on 30 November 2023 for section 1 and 31 May
2024 for section 2 is nowtherefore extended to 8 January 2024 for section 1 and 9 July 2024 for
section 2.

Abraham
....................................................
Architect

(Ar. Prof. Robert Abraham Pires)

Designation: Project Manager of Modern Concept


Properties Sdn Bhd

* Delete if not applicable


+ State Clause reference by which the Contractor is entitled to extension of time

++ State Period of Delay and Extension of Time recommended (Whether concurrently or consecutively)
17