Manhole Specification

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

MATERIAL SUBMITTAL

CLAUSTRA BLOCKS

PROJECT : CONSTRUCTION OF 33/11KV SUBSTATION AND


ASSOCIATED FACILITIES
LOCATION : PLOT NO: 8470119, UMM ESELAY, DUBAI

CONSULTANT : M/s. AL HADARA

CLIENT : M/s. DEWA

MAIN CONTRACTOR : M/s. YUKON INTL CONTRACTING LLC

MANUFACTURER : M/s. ALCON CONCRETE PRODUCTS FACTORY LLC

MANF. CONT. NO. : +971 50 677 8440

SUBMITTAL REF. : AL/MS/CB/24/005/00


RFX # 2132300073

6. 13 Soakaways

Soakaways are to consist of suitably sized drainage pits dug at positions to be approved by the
Engineer.

The pits are to be taken to a sufficient depth to ensure dissipation of the effluent into the strata
concerned and are to be filled with rubble or broken rock such that the volume of voids remaining is
sufficient to receive the anticipated discharges.

These pits are to be blinded over at ground level with broken rock to match the remainder of the
surfacing.

6. 14 Septic Tanks

Septic tanks shall be of a design suitable for the maintenance free disposal of soil drainage. The
effluent is to consistently be of an acceptable purity, and is to be discharged into an appropriately
positioned soakaway. Facilities are to be incorporated to enable periodic sampling of the effluent for
testing, and the whole of the installation is to be to the approval of the Engineer.

6. 15 Cast Iron Covers and Gulley Gratings and Frames

Cast iron manhole covers, road gulley gratings and frames shall comply with an appropriate
National Standard approved by the Engineer, and shall be obtained from approved manufacturers
and shall be supplied coated in accordance with the appropriate National Standards unless otherwise
directed.

6. 16 Steps- irons

Step-Irons, which shall comply with an appropriate approved National Standard, shall be built into
the walls of manholes, chambers and the like in a manner approved by the Engineer.

In brickwork or in-situ concrete walls the step-irons shall be built in as the work proceeds. In the
case of manholes constructed with precast concrete rings step-irons shall be inserted into the rings
by the manufacturers and shall be positioned as required.

6. 17 Rodding Drainage Pipelines

Provision shall be made for rodding all pipelines. For this purpose manholes for burried pipelines
shall be not greater than 100 metres apart. Pipelines above ground level shall have access plates on
each bend or junction. Each rain water down pipe is to have an access plate 750 mm above ground.

6. 18 Excavation for Cable Ducting on Land

The bottom of every trench shall be carefully levelled and rammed. Where it is necessary to change
level, the bottom of the trench shall rise or fall gradually as the Engineer may direct, but in no case
at a slope greater than that given by the specified permissible deflections at joints. A minimum
cover of 1 metre shall be provided.

Dubai Electricity & Water Authority (PJSC) Page : SPEC-35

You might also like