HARGA
NO URAIAN SAT.
( Rp )
A UPAH:
1 Kepala tukang h/o 135,000.00
2 Tukang h/o 130,000.00
3 Tukang kayu h/o 130,000.00
4 Tukang listrik h/o 130,000.00
5 Tukang pipa h/o 130,000.00
6 Pekerja h/o 110,000.00
7 Mandor h/o 115,000.00
B BAHAN:
1 Semen Kg 1,300.00
2 Semen putih(40 kg) Zak 125,000.00
3 Semen warna Kg 15,000.00
4 Tanah urug M3 60,000.00
5 Pasir M3 125,000.00
6 Batu belah / batu dasar M3 112,500.00
7 Batu belah 15 - 20 cm M3 150,000.00
8 Batu pecah 5 - 7 M3 300,000.00
9 Batu pecah 3 - 5 M3 250,000.00
10 Batu pecah 2 - 3 atau 1 - 3 M3 225,000.00
11 Batu pecah 1 - 2 atau 0.5 - 1 M3 312,500.00
12 Besi beton polos 14 Kg 9,695.51
13 Besi beton polos 8 Kg 6,909.28
14 Besi beton polos 10 Kg 7,146.71
15 Besi beton ulir Kg 13,557.90
16 Kawat beton Kg 17,000.00
17 Besi hollow 40.40.1 UJG 149,767.50
18 Besi hollow 40.20.1 UJG 88,284.00
19 Besi hollow 40.40.05 UJG 36,785.00
20 Besi hollow 40.20.05 UJG 28,902.50
21 Kawat las Kg 25,224.00
22 Kayu kelas II M3 4,500,000.00
23 Kayu kelas III M3 1,400,000.00
24 Bambu BTG 18,392.50
25 Dolken kayu BTG 93,013.50
26 Formite/penjaga jarak bekisting/spacer BH 15,765.00
27 Minyak bekisting Ltr 7,882.50
28 Paku Kg 15,000.00
29 Paku triplex Kg 16,816.00
30 Paku beton Kg 19,969.00
31 Tripleks 9 mm Lb 116,000.00
32 Teakwood 6 mm Lb 95,000.00
33 Panel GRC 4 mm Lb 99,845.00
34 Lem kayu Kg 50,000.00
35 Kawat diameter 4" Kg 26,275.00
36 Atap Onduline M2 130,000.00
37 Nok Atap Onduline M' 65,000.00
38 Nok samping genteng metal M' 36,785.00
39 Flashing atap genteng metal M' 39,412.50
40 Paku genteng metal Kg 26,275.00
41 Zincalum gelombang 0.27 mm Lb 60,432.50
42 Plat zincalum 0.27 mm Lb 59,907.00
43 Seng gelombang BJLS 20 Lb 46,244.00
44 Seng gelombang BJLS 25 Lb 60,432.50
45 Seng plat 0.25 mm Lb 57,805.00
46 Seng gelombang BJLS 30 Lb 73,570.00
47 Seng plat 0.30 mm Lb 70,942.50
48 Paku seng Kg 22,071.00
49 Bata Bh 735.70
50 Rooster beton 20 x 20 Bh 13,137.50
51 Rooster beton 20 x 40 Bh 26,275.00
52 Rooster keramik 20 x 20 Bh 47,295.00
53 Rooster keramik 40 x 40 Bh 68,315.00
54 Kosen aluminium silver M' 110,355.00
55 Profil aluminium pintu M' 126,120.00
56 Aluminium strip M' 36,785.00
57 Profil kaca M' 78,825.00
58 kawat nyamuk M2 47,295.00
59 Jendela / vent. casement alum. silver M' 225,965.00
60 Sekrup fixer bh 157.65
61 Sealant tube 36,785.00
62 Kosen + pintu PVC + engsel & kunci Bh 420,400.00
63 Kaca rayban 5 mm M2 183,925.00
64 Kaca bening 5 mm M2 157,650.00
65 Kaca bening 3 mm M2 78,825.00
66 Engsel pintu 3 x 4" Bh 26,275.00
67 Engsel jendela 2 x 3" Bh 23,647.50
68 Tarikan jendela Bh 47,295.00
69 Kait angin jendela Bh 31,530.00
70 Grendel pintu Bh 47,295.00
71 Grendel jendela Bh 15,765.00
72 Grendel ventilasi spring knive Bh 22,071.00
73 Besi hollow 40 x 40 gypsum Btg 23,122.00
74 Metal furing 20 x 40 M2 36,785.00
75 Gypsum 9 mm Lb 68,315.00
76 Paku gypsum Kg 21,020.00
77 Paku Kayu Kg 10,510.00
78 Paku sekrup Kg 23,647.50
79 Paper tape M' 525.50
80 Compound gypsum Kg 14,714.00
81 Wall paper m 73,570.00
82 Lem wallpaper kg 42,040.00
83 Keramik lantai 40 x 40 Bh 13,242.60
84 Keramik lantai 20 x 20 Bh 4,090.91
85 Keramik dinding 20 x 25 Bh 3,363.20
86 Carpet M2 289,025.00
87 Carpet under layer M2 47,295.00
88 Lem Ehabond Kg 31,530.00
89 Plamur tembok Kg 15,765.00
HARGA
NO URAIAN SAT.
( Rp )
87 Amplas Lb 2,627.50
88 Cat tembok Kg 26,275.00
Cat Dulox 2.5 Kg Kg 120,000.00
89 Kwas Bh 18,392.50
90 Kabel NYM 3 x 2,5 mm M' 7,882.50
91 Kabel NYM 2 x 1,5 mm M' 5,255.00
92 Lampu SL 9 - 23 watt Bh 25,749.50
93 Vetting tempel segi empat Bh 8,408.00
94 Vetting down light Bh 29,953.50
95 Vetting down light Bh 89,335.00
96 Lampu SL 18 - 23 watt + vetting DL Bh 55,703.00
97 Lampu SL 9 - 23 watt + vetting tempel Bh 34,157.50
Lampu RM 2 x 36 W Bh 175,000.00
98 Saklar tunggal Bh 45,000.00
99 Saklar double Bh 50,000.00
100 Saklar triple Bh 44,000.00
101 Stop kontak Bh 50,000.00
102 Stop AC Bh 105,100.00
103 Sub panel ( box MCB )12 group Bh 115,610.00
104 MCB 10 A Bh 42,040.00
105 Splitzen Bh 47,295.00
106 Tiang splitzen GIP 1" M' 18,918.00
107 Kawat BC 35 mm2 Kg 18,392.50
108 Pipa PVC 1/2" kelas AW M' 5,625.00
109 Pipa PVC 3/4" kelas AW M' 8,250.00
110 Pipa PVC 1" kelas AW M' 11,250.00
111 Pipa PVC 3" kelas AW M' 45,000.00
112 Pipa PVC 4" kelas AW M' 60,000.00
113 Pipa PVC 1-1/4" kelas D M' 8,933.50
114 Pipa PVC 2" kelas D M' 25,224.00
115 Pipa PVC 3" kelas D M' 32,581.00
116 Pipa PVC 4" kelas D M' 44,142.00
117 Kloset Jongkok toto Unit 2,500,000.00
118 Urinoir Bh 1,313,750.00
119 Wastafel Bh 2,100,000.00
Cermin+Assesoris biasa Bh 750,000.00
120 Gate valve 1/2" Bh 63,060.00
121 Gate valve 3/4" Bh 84,080.00
122 Gate valve 1" Bh 120,865.00
123 Floor drain stainless steel Bh 315,300.00
124 Shower bidet Bh 289,025.00
134 Exhaust fan 8" unit 650,000.00
125 Kran tembok 1/2" Bh 48,346.00
126 Kran zink 1/2" Bh 89,335.00
127 Tanki air stainless steel 1M3 Bh 4,500,000.00
128 Pompa air ; Suction 15 M, Head 40 M Bh 12,000,000.00
129 Ijuk Kg 99,845.00
130 Air Ltr 150.00
131 Solar Ltr 5,780.50
132 Minyak pelumas Ltr 36,785.00
133 Pintu PVC / Kamar Mandi Unit 750,000.00
HARGA JUMLAH
URAIAN KUANTITAS
( Rp ) ( Rp )
PEKERJAN PERSIAPAN
1 M2 Membersihkan lapangan dan peralatan 16,750.00
Pekerja 0.1000 h/o 110,000.00 11,000.00
Mandor 0.0500 h/o 115,000.00 5,750.00
Jumlah bahan dan upah 16,750.00
1 M' Pengukuran dan pasang bouwplank 106,100.00
Kayu 5/7 0.0120 M3 1,400,000.00 16,800.00
Papan 3/20 0.0070 M3 1,400,000.00 9,800.00
Paku biasa 2"-5" 0.0200 KG 225,000.00 4,500.00
Pekerja 0.4000 h/o 110,000.00 44,000.00
Tukang 0.2000 h/o 130,000.00 26,000.00
Kepala tukang 0.0200 h/o 135,000.00 2,700.00
Mandor 0.0200 h/o 115,000.00 2,300.00
Jumlah bahan dan upah 106,100.00
PEKERJAN TANAH DAN URUGAN
1 M3 Galian tanah sedalam < 2 m 104,175.00
Pekerja 0.9000 h/o 110,000.00 99,000.00
Mandor 0.0450 h/o 115,000.00 5,175.00
Jumlah bahan dan upah 104,175.00
1 M3 Galian tanah biasa sedalam < 1 m 85,375.00
Pekerja 0.7500 h/o 110,000.00 82,500.00
Mandor 0.0250 h/o 115,000.00 2,875.00
Jumlah bahan dan upah 85,375.00
1 M3 Urugan Tanah kembali 8,100.00
Pekerja 0.0667 h/o 110,000.00 7,333.33
Mandor 0.0067 h/o 115,000.00 766.67
Jumlah bahan dan upah 8,100.00
1 M3 Urugan pasir 64,150.00
Pasir 0.3000 M3 100,000.00 30,000.00
Pekerja 0.3000 h/o 110,000.00 33,000.00
Mandor 0.0100 h/o 115,000.00 1,150.00
Jumlah bahan dan upah 64,150.00
PEKERJAN PONDASI DAN BETON
1 M3 Pondasi Telapak T = 1.95cm 1,801,850.09
1. Beton mutu f'c = 19,3 Mpa (K 225), slump (12 +/ 2) cm, w/c 0,58 1,049,807.54
Semen 371.0000 Kg 1,300.00 482,300.00
Pasir 0.4986 M3 125,000.00 62,321.43
Batu pecah 2 - 3 atau 1 - 3 0.7756 M3 312,500.00 242,361.11
Air 215.0000 LTR 150.00 32,250.00
Pekerja 1.6500 h/o 110,000.00 181,500.00
Tukang 0.2750 h/o 130,000.00 35,750.00
Kepala tukang 0.0280 h/o 135,000.00 3,780.00
Mandor 0.0830 h/o 115,000.00 9,545.00
Jumlah bahan dan upah 1,049,807.54
2. Pembesian dengan besi dia 14 u 530,076.53
Besi Dia 14mm 37.8800 kg 9,695.51 367,266.03 20
Kawat beton 9.4700 kg 17,000.00 160,990.00 7
Pekerja 0.0070 h/o 110,000.00 770.00
Tukang 0.0070 h/o 130,000.00 910.00
Kepala tukang 0.0007 h/o 135,000.00 94.50
Mandor 0.0004 h/o 115,000.00 46.00
Jumlah bahan dan upah 530,076.53
3. Pembesian dengan besi dia 8 56,905.28
Besi Dia 8mm 3.9500 kg 9,695.51 38,297.28 10
Kawat beton 0.9875 kg 17,000.00 16,787.50 5
Pekerja 0.0070 h/o 110,000.00 770.00
Tukang 0.0070 h/o 130,000.00 910.00
Kepala tukang 0.0007 h/o 135,000.00 94.50
Mandor 0.0004 h/o 115,000.00 46.00
Jumlah bahan dan upah 56,905.28
4. Bekisting untuk pondasi 165,060.75
Kayu kelas III 0.0435 M3 1,400,000.00 60,900.00
Paku 5 cm - 10 cm 0.3915 KG 15,000.00 5,872.50
HARGA JUMLAH
URAIAN KUANTITAS
( Rp ) ( Rp )
Minyak bekisting 0.1000 LTR 7,882.50 788.25
Pekerja 0.5200 h/o 110,000.00 57,200.00
Tukang 0.2600 h/o 130,000.00 33,800.00
Kepala tukang 0.0260 h/o 135,000.00 3,510.00
Mandor 0.0260 h/o 115,000.00 2,990.00
Jumlah bahan dan upah 165,060.75
HARGA JUMLAH
URAIAN KUANTITAS
( Rp ) ( Rp )
1 M3 Pasang pond. batu kali, 1 Pc : 5 Ps 780,750.00
Batu belah / batu dasar 1.1000 M3 112,500.00 123,750.00
Semen 100.0000 Kg 1,300.00 130,000.00
Pasir 0.5440 M3 125,000.00 68,000.00
Pekerja 1.5000 h/o 110,000.00 165,000.00
Tukang 0.7500 h/o 130,000.00 97,500.00
Kepala tukang 0.0750 h/o 135,000.00 10,125.00
Mandor 0.0750 h/o 115,000.00 8,625.00
Jumlah bahan dan upah 603,000.00
1 M3 Pasang pondasi batu kosong 177,750.00
Batu belah / batu dasar 1.1000 M3 112,500.00 123,750.00
Pasir 0.4320 M3 125,000.00 54,000.00
Jumlah bahan dan upah 177,750.00