Download as pdf or txt
Download as pdf or txt
You are on page 1of 216

Change Orders

Productivity
Overtime
2016 EDITION
FEATURING NEW CONTENT ON INTEGRATED,
COOPERATIVE, AND COLLABORATIVE CPM SCHEDULING

A PRIMER FOR THE CONSTRUCTION INDUSTRY


Change Orders, Productivity, Overtime:
A Primer for the Construction Industry

© 2016, Mechanical Contractors Association of America, Inc.


All rights reserved. The material contained herein is owned by the Mechanical Contractors
Association of America, Inc. (MCAA) and is protected under the copyright laws of the United
States of America (Title 17, United States Code) as well as the copyright laws of other jurisdictions.
The duplication, reproduction, storage in a retrieval system, exhibition, dissemination, or
transmission in any form by any means—mechanical, electronic, photocopying, recording,
or otherwise—without prior written permission of MCAA is strictly prohibited.

Mechanical Contractors Association of America, Inc.


1385 Piccard Drive
Rockville, MD 20850–4340
Foreword

Change Orders, Productivity, Overtime: A Primer for the Construction Industry was developed to
assist construction contractors, their customers, and others involved in construction projects
in determining the costs associated with unplanned events, circumstances, and factors that
may impact the outcome, productivity, and schedule of those projects. This primer is intended
to be a planning tool and not a source for absolute percentages or costs.
The contents of this primer were prepared and peer reviewed by construction industry
professionals and expert consultants to the industry. MCAA wishes to thank members of the
Management Methods Committee for their contributions of time, insight, and experience.
MCAA thanks Paul Stynchcomb of Vero Construction Consultants Corp. for his numerous
contributions to this primer.

i
Change Orders
Productivity
Overtime
A PRIMER FOR THE CONSTRUCTION INDUSTRY

Table of Contents
Change Orders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
How to Identify and Manage Change Orders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
How to Organize and Submit a Claim . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .37
Integrated, Cooperative, and Collaborative CPM Scheduling…a Roadmap to Success . . . . . . . . . . . . . . . . . . . . . .51
Time Impact Analysis—Measuring Project Delay . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .73

Productivity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .85
Maintaining Control of Labor Productivity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .85
Factors Affecting Labor Productivity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .99
Connecting the “Cause” and “Effect” in Loss of Productivity Claims . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .101
How to Use the MCAA Labor Factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .103
How to Apply the Measured Mile Method of Productivity Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .127
How to Estimate the Effects of Cumulative Impacts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .147

Overtime . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .185
How to Estimate the Impacts of Overtime on Labor Productivity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .185
Shift Work and its Effects on Productivity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .203

iii
Change Orders

How to Identify and Manage


Change Orders
Introduction eral contractors and subcontractors, as well as
Changes on a construction project should be owner-caused changes that flow down to sub-
anticipated and can have a significant effect on contractors. For brevity, most of the narrative is
a contractor’s performance, productivity, and in the context of a project owner and general
profitability. Although changes are common, contractor, but most of the same principles
misunderstanding and disagreement can occur apply to contracts between general contractors
when it comes to identifying whether a change and subcontractors. References to “contractor”
has occurred, pricing a change, and determin- apply to general contractors and specialty trade
ing the time impact of a change. Detailed doc- subcontractors. General guidance is provided
umentation of events related to changes can related to common change order circumstances,
significantly reduce disputes and overall proj- however, specific contract laws, working condi-
ect risks. Changes also may result in a claim tions, and practices can vary among jurisdic-
under the contract’s disputes clause if the tions and geographic locations. Contractors and
owner and contractor, or the general contrac- owners are encouraged to seek advice from
tor and subcontractor, do not agree as to enti- their in-house contracts manager and/or legal
tlement to and/or the dollar amount of the counsel as to their respective rights and obliga-
change. However, a significant number of tions associated with the contracts they sign,
claims and disputes can be avoided by follow- including change orders which are contract
ing the changes provisions, or changes clauses, modifications. Construction professionals such
in the contract; preparing detailed documenta- as other in-house personnel, construction con-
tion during the course of the project; and sultants, and legal counsel with cost and time
maintaining active communication among the impact experience may be helpful in evaluating
various parties involved in a capital project. the cost and time impacts associated with
change orders.
This chapter suggests approaches to the effec-
tive management of change orders with the
objective of increasing contemporaneous agree- Types of Events Leading to a
ments between owners and contractors that Change
resolve the price and time associated with a A variety of events may result in changes to a
change and avoid change order disputes. These contractor’s actual work from what was
approaches also apply to changes between gen- planned and set forth in the contract docu-

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 1
Change Orders

ments, regardless of the project delivery can create a schedule impact and/or change
methods used. Some of the issues and events the sequence of work, thus impacting the pro-
that may cause changes include: ductivity of the base contract work.
■ Owner-driven scope changes that cause In contrast, constructive changes occur from
an increase or decrease in the amount of any events that are not owner directed or
work from the scope of work outlined in that have the effect of implicitly requiring
the original contract; the contractor to modify the scope set forth
in the original contract. Constructive
■ Changes in the methods of performance or
changes are often more difficult to identify
the materials or equipment to be installed;
because they are actions or inactions of an
■ Changes that modify the planned owner without the explicit acknowledgment
sequence in which the work was to be of any change by an owner. Whether the
performed; contract in question is a private or a govern-
■ Differing site conditions not anticipated ment contract, verbal communication
in the original contract price; among owner, general contractor, and sub-
contractors can sometimes be viewed as a
■ Constructability issues; change. Contractors are encouraged to fol-
■ Changes in performance specifications; low up in writing if they believe a construc-
tive change has occurred. Some of the com-
■ Changes to correct errors, omissions, or
mon types of constructive changes are:
inconsistencies in the specifications or
drawings; ■ Defective contract documents;

■ Changes in the time for performance; ■ Over-inspection;

■ Changes resulting from extraordinary, ■ Changes in methods of performance;


unexpected natural events; and ■ Changes in construction sequence;
■ Changes due to the actions or inactions ■ Misinterpretation of specifications;
of other trades working on the project.
■ Incomplete owner or architect/engineer
The changes described above fall within two responses to contractor information
general categories: directed changes and con- requests; and
structive changes. Directed changes are usually
easier to recognize and resolve. In this kind of ■ Differing site conditions.
change, the owner specifically directs the con- Defective specifications are often cited as a
tractor to make a change. A directed change cause of constructive changes. The term
can add to or reduce the contract price and it “defective specifications” covers a multitude
also may involve a change in the construction of latent change-causing circumstances that
sequence or schedule. Owners typically have result from inaccurate or incomplete specifi-
the contractual right to initiate any change. cations. Examples of defective specifications
Owner changes often impact the contractor’s are discussed in the following paragraphs:
scope of work. However, changes in a project’s
size, configuration, or space requirements also

2 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

Incomplete specifications. Incomplete speci- subsurface soil conditions or conditions within


fications exist when the contract documents the existing site or facility that are materially
do not provide adequate information neces- different from what was shown on the con-
sary to execute the work as planned. These tract documents or materially differ from con-
types of changes often occur when the plans ditions that are clearly evident and observable.
and specifications fail to coordinate construc-
Nondisclosure. Nondisclosure can be either
tion details between different design disci-
intentional or unintentional. In either case,
plines, such as architectural and mechanical,
a change occurs when the contractor is not
resulting in conflicts that require resolution.
given all of the critical design or construc-
Facility space constraints. Conflicts occur tion information necessary to facilitate
when the project design provides insufficient proper project performance.
space for all of the elements in an area. For
Changes required by regulatory agencies/
mechanical work, there can be conflicts in
using agency. The owner’s design team nor-
shaft and in-wall installation, with above-ceil-
mally has the responsibility to ensure that the
ing mechanical, and with structural, electrical,
project design meets all applicable building
and plumbing elements that require resolu-
code and regulatory requirements. Added work
tion. Some of these conflicts can be resolved
or changes required to meet code or regulatory
during the coordination process; others may
requirements should result in a change order.
be so significant as to require a re-routing of
work or an adjustment in the size of the space Value engineering. In what is sometimes
in order to properly install the work. referred to as value engineering, a contractor
may point out changes when superior methods
Design discrepancies. Design discrepancies
or materials become apparent, or when the
occur due to differences between the plans
same design result can be achieved at a lower
and specifications, differences between
cost. Contracts frequently allow for shared sav-
details, dimensional errors, or differences
ings associated with such improvement, how-
between planned equipment details and
ever the cost of reengineering can offset any
actual equipment cut sheets. A design dis-
savings while potentially delaying progress.
crepancy may also be found when the same
When improved methods or materials are nec-
item is specified in different sections of the
essary to overcome an owner-caused problem,
contract documents with different require-
such as to mitigate a delay impact, the contrac-
ments in each section. Additionally, a design
tor should be compensated for such changes.
discrepancy can occur when details are omit-
ted from the contract documents or when Tools to mitigate or avoid changes. Use of
there are inconsistencies among the construc- tools that can be utilized to mitigate or avoid
tion drawings associated with different trades. costly change conditions in the field is
becoming more widespread. For example,
Latent conditions. This term refers to existing
tools such as 4D Building Information Model-
differing site or subsurface conditions,
ing (BIM) and Integrated Project Delivery
unknown at the time of bidding, that affect
(IPD) processes help coordinate the develop-
the contractor’s performance. Change orders
ment of design drawings, and can reduce the
for latent conditions usually result from either
number of instances of conflicts in drawings

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 3
Change Orders

and incomplete specifications. With 4D BIM, recognizes the condition giving rise to the
the Critical Path Method (CPM) schedule is claim, whichever is later. This provision con-
integrated into a 3D model of the drawings so tinues that the contractor shall submit notice
that the project can be visualized from both a before proceeding with the work, except in
constructability sense and a project execution the case of an emergency, and shall have
perspective before the project is started. twenty-one (21) days after giving notice to
Updates are provided throughout construc- submit claim documentation, and then the
tion to reflect as-built conditions as a refer- owner must provide a written acceptance or
ence point for planning and analyzing the denial within fourteen (14) days after receipt
work still to be completed. The time and costs of the contractor’s documentation.
associated with implementing tools such as
When a change is identified, detailed docu-
BIM on a specific project can be tracked and
mentation of the change should be prepared.
treated as a direct cost of the work in both the
Typical documentation includes a description
initial contract and any changes.
of the reason for the change or description of
events causing the need for a change order.
What To Do When a Change is Documentation should also include a narra-
Identified tive description of the schedule impacts after
completing a time impact analysis of the
When a change is identified, one of the first
work scope that has changed.
things a contractor should do is provide
notice to the owner. Notice provisions are Since constructive changes do not emanate
common contract provisions and the parties from a directed owner change, it is particu-
should follow the applicable contract guide- larly important for contractors to identify that
lines for providing change notices. For a change has occurred, document the details
mechanical contractors and other subcontrac- of the changed condition(s), and notify the
tors, not only is notification to the general owner of the changed condition in a timely
contractor important, but knowledge of any manner. Some contract forms do not include
flowdown provisions from the owner to the provisions for constructive changes, so a con-
general contractor and, in turn, to the sub- tractor needs to be clear with the owner about
contractors are important. Subcontractors proceeding with any work related to a con-
should be aware of any notice requirements structive change and documenting such work
that may be part of such flowdown provisions in a written change order. If a contractor is
that are incorporated by reference in the sub- directed to proceed with the work before a
contract. For example, the notice provision in change order is agreed to and signed, the con-
the changes clause of the ConsensusDocs 200 tractor needs to carefully document the costs
form contract between owner and contractor and time associated with the change and take
states that except for certain delay circum- the following steps to facilitate the resolution
stances covered in a different contract provi- of the change with the owner:
sion, the contractor shall give the owner writ- ■ Research the contract documents thor-
ten notice within fourteen (14) days after the oughly to confirm that a changed condi-
occurrence giving rise to the claim or within tion exists.
fourteen (14) days after the contractor first

4 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

■ Prepare and submit a change order contractor should pay particular attention to
request proposal, giving the owner a clear the contract requirements for submitting
and detailed description of the change. requests for extensions of time, as well as the
scheduling requirements for the project. Fail-
■ Be alert to any notice requirements and
ure to adhere to these requirements could
respond properly.
affect the contractor’s ability to obtain a time
■ Issue notice of intent to file a claim if the extension.
change order is denied.
Separate cost coding. The contractor should
■ Inform the owner of any applicable determine whether it is practical to document
schedule impacts. the costs of a change using separate project job
■ If the change is not resolved, follow the dis- cost coding. In some instances, it may not be
pute resolution procedures in the contract. possible to separately track impacted costs or
costs associated with an individual changed
While the owner-directed change is easiest to condition contemporaneously as the impacted
identify, the contractor must consider sched- work progresses. This could occur if the
ule and productivity impacts in the analysis impacted work is an integral part of the base
and pricing of the change. Time and produc- contract work, such that the base contract
tivity impacts often are not the subject of ini- work is more difficult to perform and/or takes
tial negotiations regarding the scope, but longer. In other situations it may be feasible to
these topics should be incorporated into the separately track the costs associated with a
negotiation process. Failure to consider these change via separate cost coding from the base
impacts at the time of the change can result contract cost coding in the contractor’s job cost
in a waiver of a contractor’s ability to recover reporting system. When it is impractical to sep-
additional time and money. Contractors arately track costs associated with the change
should consider their need to reserve rights due to effects on the base contract scope
associated with impacts if they are not quanti- and/or cumulative impacts associated with
fied and included in a change order price at multiple changes, it is helpful to document the
the time of each change order negotiation. impacts and costs through additional contem-
Schedule time impact analysis arising from poraneous notes in the daily project logs,
change orders. Each change order should be timesheets, or other daily reports so that the
carefully evaluated to determine whether an portions of the work that are impacted can be
extension of time is warranted. The chapter more clearly identified in the absence of sepa-
entitled “Time Impact Analysis—Measuring rate cost coding. However, when possible, it is
Project Delay” contains a detailed description recommended that contractors use separate job
of the manner in which a time extension cost coding to track changed work.
analysis should be performed using the con-
temporaneous project schedules and proce-
Impacts Arising From Change
dures set forth therein. This chapter should
be consulted whenever the contractor identi- Orders—Losses Of Productivity
fies an impact that could affect any aspect of In addition to the direct costs associated with
the schedule. As noted in the chapter, the a change, the contractor should be aware of

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 5
Change Orders

various factors that can have an adverse effect ■ Performing work in a different season, i.e.,
on labor productivity, both in the perform- summer work shifted to winter work
ance of the changed work and as an impact
■ Contaminated air
on the base contract scope of work, depend-
ing on the scope of the change and depend- ■ Constructability problems with plans and
ing on the activities being performed. In specifications
order to recover such costs, a contractor must ■ Unusual and unplanned changes in the
establish the cause and effect between the sequencing of the work
event and a quantified loss of productivity.
Some causes include the following: ■ Unplanned protection of existing facili-
ties, completed portions of construction,
1. Worker overtime. Unscheduled overtime furniture, fixtures, machinery, stock, or
may lower both work output and efficiency, finished surfaces
depending on the amount of overtime being
incurred and the duration of the overtime. ■ Unplanned daily clean-up of tools and
Evaluating the extent to which a loss of pro- work area
ductivity has occurred resulting from sus- ■ Unexpected interference by owners,
tained overtime, along with the premium employees, or other trades
costs, is a factor that contractors should con-
■ Accessibility to material stores, changes in
sider when pricing change orders.
laydown areas or tool lockers
2. Manpower availability to perform the
■ Unexpected poor lighting
changed work. High volume of construction
activity in a concentrated geographic area may ■ Work in tight spaces with unsure footing,
create a shortage of skilled workers which, in interfering tie wires, piping, ducts, hang-
turn, can affect labor costs depending on the ers, etc. not originally planned
type of skilled work that is required and the
■ Frequent repair work from trade damage
level of worker training. The additional costs of
such labor, such as hourly or daily premiums to ■ Acceleration
attract skilled workers from other locations, Consideration of the above factors should
including the cost of travel and lodging, should enable the contractor to more discretely
be considered in change order pricing. price and explain any added costs of per-
3. Other considerations that may affect pro- forming changed work when preparing
ductivity. Other conditions and circumstances change order requests.
should be considered when evaluating the cost
of performing changed work. These circum-
Pricing Change Orders
stances could include things such as:
It is important to identify whether the pricing
■ Excessive heat, cold, precipitation, or of a change is to be developed on a forward-
other forms of severe weather (especially pricing lump-sum estimate or if the pricing
unexpected intermittent changes) should be partially or completely based on ac-
tual costs plus applicable mark-ups. In the situ-
ation of forward pricing change orders, estimat-

6 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

ing the amount of the change order typically is prepare budgets in sufficient detail, along with
conducted in the same way that a contractor the corresponding job cost coding work break-
prepares other lump sum estimates. However, down structure, so that variances can be used
the manhours required to complete a change to effectively quantify project impacts.
order may be similar to or different from the
In government contracting, costs must also be
productivity and manhours incurred under
“reasonable,” “allocable,” and “allowable.”
normal unimpacted conditions. Adjustments
Although an exhaustive analysis of change
must be considered for abnormal or less-than-
order pricing on government contracts is
optimal conditions at the jobsite. Some addi-
beyond the scope of this publication, briefly, as
tional factors to be considered are whether the
stated in Federal Acquisition Regulation (FAR)
schedule has been or will be delayed, or if
31.201-3, “A cost is reasonable if, in its nature
schedule acceleration efforts are underway, for
and amount, it does not exceed that which
example. These factors may call for considera-
would be incurred by a prudent person in the
tion of labor productivity impacts when pricing
conduct of a competitive business.” Factors to
a change.
consider when evaluating the reasonableness of
A common step when evaluating the impact costs include: whether the costs are ordinary
of changed work and evaluating the planned and customary, whether the costs are based on
versus actual financial performance of a con- an arm’s-length transaction rather than a
tract, is to analyze cost underruns and over- related-party transaction, and whether the costs
runs by comparing the actual costs to the proj- reflect what a prudent person would be
ect budget. Budget variances can be analyzed expected to incur. FAR 31.201-4 states, “A cost
by comparing the actual costs to-date to the is allocable if it is assignable or chargeable to
current contract budget adjusted for the per- one or more cost objectives on the basis of rela-
cent complete on the project, or by comparing tive benefits received or other equitable rela-
the forecasted costs at completion to the total tionship.” This FAR provision further states that
contract budget. The contractor’s fee should be a cost is allocable if it, “(A) Is incurred specifi-
subtracted from the overall contract budget cally for the contract; (b) Benefits both the con-
when analyzing underruns and overruns on a tract and other work, and can be distributed to
cost-to-cost basis. Analysis of budget variances them in reasonable proportion to the benefits
can be used effectively to evaluate the impact received; or (C) Is necessary to the overall oper-
of changed work. For example, analyzing the ation of the business, although a direct rela-
amount of planned versus actual labor over- tionship to any particular cost objective cannot
time on a project and then isolating when the be shown.” FAR 31.201-2 states in part, “The
overtime was incurred and what caused the factors to be considered in determining
overtime to be incurred can provide very use- whether a cost is allowable include the follow-
ful information when evaluating the impact of ing: (1) Reasonableness. (2) Allocability. (3)
changed conditions. The usefulness of budget Standards promulgated by the CAS Board, if
variance analyses are dependent on the quality applicable; otherwise generally accepted
and level of detail in the original estimate. accounting principles and practices appropriate
Contractors are advised to maintain good doc- to the particular circumstances. (4) Terms of
umentation of how budgets are derived and to the contract. (5) Any limitations set forth in

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 7
Change Orders

this subpart.” Contractors must be very careful activities are all examples of direct costs when
when preparing a change order involving a contractors track them to a particular project.
government contract to avoid myriad pitfalls. These types of costs are frequently tracked in
Pricing data, per the FAR, must be “current, ac- general conditions, but sometimes are tracked
curate and complete” as of the date of the in one consolidated direct job cost code and
agreement on price. sometimes are allocated to jobs as a percentage
of labor or some other allocation basis. These
Contractors and owners are encouraged to
examples demonstrate that some direct costs
reach advance agreements on items of cost and
like trade labor are almost universally accepted
mark-ups that will be allowable in change
and defined as a direct cost, but some costs can
orders and specify these agreements in detail in
be coded as either a direct or indirect cost and
the contract documents. For example, labor
need to be analyzed to determine their proper
rates to be used for change order pricing can be
categorization. Although general conditions
established at the time of negotiating and sign-
costs are sometimes also referred to as “field
ing the contract rather than treating labor as a
overhead,” which may imply an indirect
cost reimbursable item which can be the sub-
nature to this cost grouping, in reality, these
ject of costly auditing and disagreement. For a
costs are direct costs of the work. General con-
summary guide to the allowable versus unal-
ditions costs support various aspects of the
lowable costs described in FAR 31.205, please
project and therefore are often allocated at the
refer to Exhibit 18 at the end of this chapter.
project level in a change order situation, or
Direct Costs Arising From Change Orders. treated as a daily cost in a delay or suspension
Direct costs are any costs that support one cost situation, but the costs are still directly related
objective, meaning that they are directly to a given contract. Such definition and catego-
related to a specific, identifiable task. Materials, rization can also be important when it comes
equipment, and subcontract costs are usually to drafting contracts so that the pricing terms
identifiable to specific tasks and are generally are clearly defined for the benefit of the parties
treated as direct costs. However, some costs and to avoid costly disputes after the contract
may appear to be indirect because they are allo- is signed. For example, there can be challenges
cable to multiple activities, but are still direct with determining the actual cost of using
costs related to the performance of the base owned equipment so frequently owners and
work or changed work. For example, fuel, oil, contractors will agree on stipulated rates for the
and grease are necessary to support the use of use of equipment in the contract.
equipment to perform direct construction
activities, but seldom would these types of
costs be separately tracked and coded to indi- Common Categories of Change
vidual work tasks or job cost codes. It is com- Order Pricing Elements
mon for fuel, oil, and grease to be accumulated The common categories of construction and
in one code, even though they support multi- change order pricing elements are:
ple work activities on a project, or even across
■ Direct and indirect job costs,
multiple projects or contracts. Small tools, con-
sumables, QA/QC activities, localized labor ■ General and administrative overhead, and
supervision, detailing, BIM, and scheduling ■ Profit.

8 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

Direct and Indirect Job Costs k. Worker’s compensation


The elements of direct and indirect job costs l. Payroll taxes
vary depending on the type of building con-
m. Other agreed-upon payments similar
struction and can also vary depending on the
to those above
size of the contractor. Care must be taken to
treat projects consistently within a contrac- 2. On-site Supervision
tor’s organization so that certain cost areas 3. Small Tools and Consumables
(e.g., superintendents, yard costs, machine
shops, etc.) are treated as either direct or indi- 4. Permanent Materials
rect and not subject to double charging. This 5. Project Equipment and Systems incorpo-
is especially true for contracts being per- rated in to the project (elevators, HVAC
formed in the federal government contract- systems, etc.)
ing arena. Direct costs are the costs of labor,
materials, supplies, equipment, and subcon- 4. Construction Equipment
tracted work that go into, and which can be 5. Subcontractor Costs
clearly identified with, a particular segment,
6. Other Project Costs, such as:
phase, or unit of a project. Indirect costs are
those costs that cannot be attributed to a sin- a. Job insurance
gle item or unit of a project. Indirect costs are b. Equipment rental
generally divided into two categories—jobsite
overhead and general and administrative c. Job supplies and facilities (ice water,
overhead. General conditions is another term ice, portable toilets, etc.)
commonly used to describe jobsite overhead. d. Cell phones and radios
Examples of direct and indirect costs include:
e. On-site office equipment (telephones,
1. Labor, including: computers, copies, fax machines, etc.)
a. Wages f. Sales taxes
b. Overtime premium pay g. Construction and performance bonds
c. Union health and welfare benefits h. Permits
d. Apprenticeship training i. Temporary services and facilities
e. Journeyman training fund j. Miscellaneous costs (instruction man-
f. Retirement fund uals, tags, move on/move off expenses,
certification, etc.)
g. Vacation
k. Safety
h. Jury duty, sick pay, or other leave
allowances l. Costs of developing a change order

i. Per diem allowances m. Drug testing

j. Travel expenses n. Material handling and re-stocking costs

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 9
Change Orders

o. Clean-up, dumpsters, and garbage Profit


hauling Profit should be applied as a separate percent-
p. Surveying and layout age figure. It should be applied after all costs
are included, with the appropriate addition
q. QA/QC
for G&A overhead. Sometimes the percentage
r. Crane and hoisting equipment for profit is stipulated in the contract docu-
s. Scheduling ments. Like G&A, disputes can be avoided by
stipulating a profit rate for change orders in
t. Document control clerk the contract. In other instances, a “fee” per-
u. Expeditors centage is specified which is intended to
cover both home office overhead and profit.
v. Site security
w. Temporary jobsite electricity/lighting
Other Considerations in the
x. Shop drawings, blueprints, reprograph- Pricing of Change Orders
ics, and photography
Additions and/or deductions:
y. Mobilization and demobilization 1. Where additions only are involved, the
contractor is entitled to an addition to the
z. Temporary heating and temporary
contract sum in the amount of direct and
weather protection
indirect job costs, plus home office overhead
and profit. If requested, the contractor may
General and Administrative be obligated to provide a detailed break-
Overhead down to verify the quotation or, depending
General and administrative (G&A) costs, on the contract provisions, the contractor
sometimes called home office overhead, are may be subject to an audit.
not charged directly to a job cost report; they 2. Where deductions only are involved, the
are corporate indirect costs that typically contractor should calculate the reduction to
support more than one contract at a time. the contract sum only in the amount of the
G&A costs commonly contain essential func- reduction in direct and indirect job costs
tions that are necessary for a company to unless other, more specific guidelines are pro-
conduct operations, fulfill specific contract vided in the contract.
obligations, and even perform change order
3. When both additions and deductions are
work. Sometimes the allowable percentage
involved, each should be calculated as sepa-
for G&A is stipulated in the contract docu-
rate change orders in accordance with 1 and
ments. It is often a useful practice to negoti-
2 above. If both omitted work and added
ate a G&A overhead rate for change orders at
work is involved in the same change order,
the beginning of a project and incorporate
the total amount of the change order will be
the rate in the contract. In the context of
equal to the difference between the additions
federal government contracts, FAR Part 31
and the deductions in accordance with 1 and
provides guidance on the types of G&A costs
2 above, unless more specific guidance is pro-
that are allowable in a change order.

10 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

vided in the contract. Sometimes the contract identified by the contractor by notifying the
stipulates that overhead and profit, especially owner. However, each of these form contracts
when it is a fixed-fee project, will not be have nuances as to the prescribed approach
reduced for deductive changes; this should be for determining the price and time associated
considered when pricing a combination of with the change. The following paragraphs
additive and deductive changes. address the pricing methodologies among
these contracts, but do not address all of the
Unaccepted change orders: If the schedule
procedural differences. The parties to the con-
and associated pricing of an owner-initiated
tract are strongly encouraged to read and
change order is not accepted and authorized,
understand all contract and change order lan-
the contractor may wish to seek reimburse-
guage before signing these documents and to
ment for all costs incurred in the preparation
seek professional legal assistance when neces-
of the quote. The contractor should have a
sary. For example, the ConsensusDocs, AIA,
prior understanding in the contract with the
EJCDC, and CMAA forms all include notice
owner regarding the reimbursement and
provisions, however the number of specific
allowability of such costs.
days varies from contract to contract, as do
Comparison of contract forms and change the specified days for submittal of changes
order provisions: Multiple references are made and owner response times.
in this chapter to change order provisions in
The following table provides a summary com-
the contracts governing the work. Much of the
parison of the pricing provisions in these four
specific change order pricing approach and
different form contracts, with further discus-
contractor submittal process is determined by
sion about the pricing provisions in the para-
the change order provisions in a subject con-
graphs that follow.
tract. There are several commonly-used form
contracts that frequently serve as the basis or
starting point for negotiating contracts Change Order Pricing Alternatives
between owners and contractors. An overview Unit Mutual Cost of
of the similarities and differences among the Prices Accept- the Work
change order provisions in these commonly ance of a Plus a Fee
used contracts is provided in this chapter. Lump Sum

The contract forms that are compared in this ConsensusDocs 200


X X X
(Article 8)
chapter are the ConsensusDocs, which is
endorsed by MCAA and other trade contrac- AIA (A201 2007) X X X
tors among others; the American Institute of
Architects (AIA) 2007 form contracts; the Engi- EJCDC (Articles
X X X
neers Joint Contract Documents Committee 10 - 12)
(EJCDC) forms; and the Construction Manage- CMAA (General
X X X
ment Association of America (CMAA) forms. Conditions Article 11)

All of these form contracts are similar in that


ConsensusDocs1 – Article 8. The Consensus-
they provide for a change to be initiated by
Docs call for expeditious negotiation of time
the owner in the form of a directed change or

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 11
Change Orders

and price when the owner issues an interim mination of cost, overhead, and profit and
directed change. This form contract does not provides guidance on unit price determina-
provide detailed guidance on the determina- tions in the event owner and contractor are
tion of cost, overhead, or profit when pricing is unable to reach agreement as to the change
based on cost of the work plus a fee, but rather order price. Parties using this form of contract
leaves the determination of these pricing ele- are encouraged to consult the specified provi-
ments to the negotiating parties. In the event sions in Articles 10–12.
the parties cannot reach agreement, this con-
CMAA4 – Article 11. When the cost-plus-fee
tract generally provides for pricing to be deter-
method of change order pricing is used, the
mined based on “reasonable and actual
CMAA change order pricing provisions provide
expenses and savings.” If unit pricing is used,
distinct definitions for “cost of the work” with
and the quantity or unit items are so different
additional guidance for the quantification of
from the original unit prices to cause substan-
labor, materials, subcontractors, and several
tial inequity to owner or contractor, the unit
other types of costs. The CMAA change order
prices are to be equitably adjusted. Also, in the
provisions also provide guidance on the quan-
event of a directed change, when pricing can-
tification of the contractor’s fee, which consists
not be agreed upon, the contract provides that
of overhead and profit. The change provisions
50 percent of the estimated cost of the work
state that the contractor shall be entitled to a
shall be paid on an interim basis.
mutually acceptable fixed-fee amount. If that
AIA2 – Article 7. This form contract does not amount cannot be agreed upon, then the fee
provide detailed guidance on the determina- shall be 15 percent of payroll and materials
tion of cost, overhead, or profit when pricing plus 5 percent on subcontractor change work,
is based on cost of the work plus a fee, but subject to other detailed exceptions and proce-
rather leaves the determination of these pric- dures specified in the contract.
ing elements to the negotiating parties,
except when agreement cannot be reached,
in which case Article 7.3.7 provides guidance
Change Order Procedures and
on the elements of cost and guidelines for the Forms
determination of overhead and profit. If unit Authorization procedures. It is incumbent on
pricing is used, and the quantity or unit the contractor to ascertain in writing, either
items are so different from the original unit from a review of the contract documents or
prices to cause substantial inequity to owner through a written request to the owner, the
or contractor, the unit prices are to be equi- specific individuals who have the authority to
tably adjusted. accept and implement change orders. Often a
contract will identify the authorized representa-
EJCDC3 – Articles 10–12. This form of con-
tives for both the contractor and owner. When
tract provides detailed guidance on the deter-

1 3
From ConsensusDocs 200 – Standard Agreement and From EJCDC C-700 Standard General Conditions of
General Conditions Between Owner & Contractor © the Construction Contract © 2007.
2007. 4
From CMAA Form CMAR-3 General Conditions of the
2
From AIA A201 – 2007 General Conditions of the Construction Contract Between Construction Manager
Contract for Construction © 2007. and Contractor © 2005.

12 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

negotiating the cost, time, and any specific guage. Such language is designed to make the
terms and conditions associated with a change written change order a full and final agreement
order, it is recommended that the authorized on the applicable cost and time associated with
representatives for both the contractor and the subject change. A bilateral signing of a
owner thoroughly review the documentation change order with this language could bar the
associated with the change before signing the recovery of any additional costs associated with
change order. Otherwise, the owner may con- the change order, such as loss of productivity,
tend that the individual who authorized the delay-related costs, and/or cumulative impacts.
alleged changed work did not have authority The actual wording will vary, but is likely to be
to issue a change. If the contractor believes that similar in substance to the following:
the actions of a party within the owner’s con-
The execution of this Change Order repre-
trol, such as the architect/engineer, took action
sents the Contractor’s total and final costs for
that constitutes a constructive change to its
all impacts, both direct and indirect, arising
work, the contractor should give timely written
from this Change Order. A time extension (if
notice to the owner that it considers such
any) granted with this Change Order repre-
action a constructive change directive, and will
sents the total impact of all delays, both direct
perform the work as a change order and pro-
and indirect, to the project schedule.
vide a cost accounting of the change when the
work is complete. An example of such a writ- Courts and boards have found that such lan-
ten notice of change is: guage may bar the contractor from additional
recovery. If there is concern that productivity
Contractor has received the Engineer’s Response
impacts, cumulative impacts of multiple
to Request for Information (RFI) 213, which has
changes, and delay-related costs cannot be
rerouted the piping from that shown on Drawing
quantified for individual changes, the con-
M.402.We have assigned Proposed Change Order
tractor should consider reserving its rights to
5000 to this item.We will be charging costs for
make a claim for such impacts separate from
labor, material, services, and equipment to this
individual change orders. An example of such
change order cost code and will provide you with
reservation language follows:
a complete accounting in a formal change order
request when the work is complete. The execution of this Change Order represents
the Contractor’s estimate of direct costs only.
Time for acceptance: Except as specified in a
The Contractor expressly reserves the right to
contract, the time limitation for acceptance
submit, at a later date, added costs, applicable
of a change order should be stipulated by the
mark-ups and time extensions attendant to this
contractor in a change request. If not
change order arising from, but not limited to:
accepted within the stipulated time, it should
extended field and home office overhead, labor
be stated that the quoted price may be sub-
inefficiency, disruptions, impacts to the critical
ject to escalation.
path, schedule re-sequencing and/or acceleration.
“Full accord and satisfaction” language.
Again, legal counsel should be consulted
Contractors should be alert to any change
before signing a change order that contains
order they are requested to execute that
either accord and satisfaction language or
includes “full accord and satisfaction” lan-
reservation of rights language.

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 13
Change Orders

Dispute resolution. In the event that a all expenditures to allow verification of reim-
change order cannot be mutually agreed bursable costs. These costs may be invoiced
upon with a bilateral signing, some changed periodically as the work commences, or, on
work may still proceed with a directed shorter-duration changes, invoiced on com-
change or a unilaterally issued change order. pletion of the work.
In the event that the parties have exhausted
Unit-price contracts specify the unit prices
all possible remedies under the changes pro-
associated with various types of work. In
visions of a contract, they may need to turn
some instances, the parties may agree that,
to the dispute resolution provisions of the
on changes above a specified percentage of
contract. Occasionally, change orders ulti-
the base work (for example, 25 percent), the
mately become resolved through the dispute
contractor has the ability to charge on a
resolution provisions of the contract. It is
time-and-materials basis. In these instances,
beyond the scope of this chapter to discuss
the contractor may be allowed to charge
the details of resolving claims outside of the
actual costs rather than being limited to
change order clauses in contracts.
charging the unit prices that were established
in the contract. Unit prices, in most
Change Order Forms instances, include direct costs, indirect costs,
Having outlined a variety of considerations G&A, and profit.
when faced with changed work, the follow- The forms and procedures (Exhibits 1
ing forms are recommended for use in esti- through 18) are tools for documenting and
mating and for tracking the costs of such tracking costs, determining time impacts, and
changes. There are three typical types of pricing change orders.
change order pricing:
Part 1 deals with lump-sum changes and Part
■ Lump sum, 2 is for cost-plus changes. Included in Part 2
■ Time-and-material, and is a Field-Authorized Change Order Form.
Designed primarily for field use, it provides a
■ Unit price. means not only for tracking costs but also for
In a lump-sum change, the contractor’s origi- obtaining written authorization for additional
nal estimate for the change must include all work, when necessary. Before adopting the
items needed to do the work. Lump-sum pric- procedures presented here, evaluate them
ing is frequently used when pricing changes carefully and revise them as necessary to
before the changed work has commenced, meet the requirements of local conditions
meaning that the change is “forward priced.” and your company’s operating procedures.
Contractors bear the risk of overruns and Part 1: Lump-sum (fixed amount) changes.
receive the benefit of underruns. Lump-sum changes are advantageous to the
In time-and-materials changes, such risks are contractor for two reasons: (1.) they allow
eliminated and both the contractor and the the contractor to estimate all costs and mark-
owner get a clear picture of the profit that ups before work begins. If the contractor
will be earned by the contractor. Time-and- includes all items necessary for the work as
materials changes require accurate tracking of well as applicable and contractually allowed

14 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

mark-ups, the probability of making a rea- (Exhibit 4) and a Materials Cost Estimate
sonable profit is enhanced. (2.) they require Sheet (Exhibit 5). Because changes usually
far less tracking and paperwork in the field involve relatively small amounts of materials,
than time-and-material changes. Despite and therefore do not qualify for large volume
these advantages, lump-sum changes must discounts, it is suggested that all materials be
be handled properly to ensure that all cost estimated using standard over-the-counter
and time impacts are properly estimated and discount prices. Restocking charges should be
included. The following procedures and considered where credits might be involved.
forms will help make that handling accurate Be sure to estimate required quantities of all
and efficient. items and to calculate the materials cost
subtotal using the figures in the total cost
columns. Also consider lead times required
Recommended Procedures for ordering materials and equipment and the
1. The key document in controlling change potential need for expediting materials and
order activity is the Change Order Status equipment, which may involve additional
Sheet (Exhibit 1). The project manager should costs. Add to subtotals all additional costs,
record any potential change on the Change such as sales taxes, drayage charges, war-
Order Status Sheet as soon as the possibility ranties, start-ups, etc.
of a change is identified. Formal changes
should be numbered sequentially and 5. Estimate all miscellaneous direct job costs
recorded on the Change Order Status Sheet. on an Other Direct Job Costs Estimate Sheet
(Exhibit 6). Once computed, the labor cost
2. Prepare a Change Order Proposal (Exhibit 2) estimates on this form should be transferred
and use it as a cover letter when submitting to the Labor Summary Sheet (Exhibit 9) and
your change order cost estimate to the project the materials costs to the Change Proposal
owner or general contractor. Be sure the pro- Cost Summary Sheet (Exhibit 3).
posal letter states that you reserve the right to
modify your estimate if additional work not 6. Complete an Equipment and Tool Rental
covered by the proposal is required. Also state Estimate Sheet (Exhibit 7).
a time limit for the owner’s or general contrac- 7. Complete a Vehicle Operating Cost Esti-
tor’s acceptance of the proposal if there are no mate Sheet (Exhibit 8), including all gasoline
time limits already specified in the contract. and oil costs anticipated for each vehicle.
3. Exhibit 3 is a Change Proposal Cost Sum- 8. Itemize all labor costs on the Labor Sum-
mary Sheet. The sheet is used to summarize mary Sheet (Exhibit 9). Rates, fringe benefits,
all estimated costs from the detailed cost esti- payroll taxes, insurance, travel allowances,
mate sheets in Exhibits 4 through 13. Keep a etc. for the various labor categories should be
copy of all change order pricing sheets and shown in the matrix at the top of Sheet #1 of
related documentation readily available for the Labor Summary Sheets. Use items 13–22
review with the approving authority should (Exhibit 9) and 23–40 (Exhibit 10) to indicate
questions arise. any applicable increases or decreases to the
4. Itemize estimated equipment and materials labor estimate due to factors affecting produc-
costs on an Equipment Cost Estimate Sheet tivity. Once you have itemized the various

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 15
Change Orders

labor factors, calculate and total the esti- 5. Notification to owner (date and person)
mated labor costs using items 41–52 on
6. Pertinent records and documents, such as:
Exhibit 10.
• Affected plans or sketches
9. List all subcontractors and subcontract
quotes and total the estimated cost of sub- • Daily reports
contracts on a Subcontracts Summary Form • Meeting minutes
(Exhibit 11).
• Letters, notes, memos, and telephone
10. On an Extended Overhead Cost Sheet logs
(Exhibit 12), compute all overhead costs not
included on the other estimate forms. • Payroll records

11. Use the Special Inclusions and Exclusions • Equipment reports


Form (Exhibit 13) to list any additional items • Material invoices
that should be part of the change order, as
• Photographs
well as specific items that should be excluded
from the change order pricing. Be sure that • Subcontractor/supplier cost and
items listed on this form are referenced in schedule impacts
either the Change Order Proposal Form
• Impacted schedules
(Exhibit 2) or a special cover letter to the
proper project authority. 7. Notification to subcontractors/suppliers
12. The key to effective change order man- 8. Notification to bonding company (if
agement is documentation. While contractors required)
have been reacting to the present litigious By using the above procedures and the
atmosphere in construction with more atten- exhibit forms, a contractor’s estimate for a
tion to documentation, it is still not a tool lump-sum change order should cover all the
that most contractors use effectively. Good necessary items and maximize the contrac-
documentation of the events leading to and tor’s ability to recover a reasonable profit
supporting a contractor’s contention that a while at the same time avoiding a loss in the
change has occurred can mean the difference performance of the additional work. In addi-
between settling a change order and filing a tion, the completed estimate forms provide a
claim. As a guide to proper documentation, a thorough and complete set of documentation
contractor should, at a minimum, include the to present to the contractor and/or owner
following information on every change: during change order review and negotiations.
1. Date of discovery Part 2: Time and Material Change Orders.
2. Person and/or company making discovery A time-and-material change order requires
that the contractor carefully track all expen-
3. Detailed description of changed condi-
ditures on a change while doing the work.
tions
This requires the field personnel to keep accu-
4. Documents supporting assertion that a rate records. The following steps can help to
change exists enhance accurate recordkeeping:

16 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

1. Use a Field-Authorized Change Order Form


(Exhibit 14) and Work Authorization Form
(Exhibit 15) for all time-and-material changes
to ensure that change work is properly
authorized and costs are tracked.
2. Incorporate the Sample Instructions for
Field-Authorized Changes (Exhibit 16) into
your company’s operations, modifying them
as necessary.
3. Educate on-site supervisory personnel
about time-and-material change orders and
the proper use of the Field-Authorized
Change Order Form. In particular, emphasis
must be placed on the importance of control-
ling and recording all expenditures, and
accountability for performing this task prop-
erly. There is no reason to lose money on
time-and-material changes if your company
has established policies for managing such
changes and procedures to ensure that your
personnel follow those procedures.
4. Exhibit 17 provides a checklist of FAR
allowability of costs to be used when pricing
time-and-material change orders.
5. Exhibit 18 provides a template for the pric-
ing of unit-price change orders.

Prepared by Paul Ficca, CPA, CMA, CFE, CFF of FTI


Consulting, with contributions from Louie Wu, CPA,
CFF, also of FTI Consulting. Peer review performed by:
Robert Beck, President of John W. Danforth Company;
Michael R. Cables, Executive Vice President of Kinetics
Systems Inc.; James Durant, President and CEO of
Trautman & Shreve; Richard Freeman, Vice President of
Stromberg Metal Works; William Goodrum, CFO of
John J. Kirlin, LLC; Matthew Hahr, Senior Vice Presi-
dent of Kirlin Mid-Atlantic, LLC; Michael Loulakis, Esq.,
President/CEO of Capital Project Strategies; Michael
Mack, Executive Vice President of John J. Kirlin, Inc.;
and Adam Snavely, President and CEO of The Poole &
Kent Corporation.

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 17
EXHIBIT 1
CHANGE ORDER STATUS SHEET

18
JOB NAME: JOB NO: 101 CONTRACT DATE: Contract Date

Location: Owner: Address: Our Job Phone:

Gen’l Cont: Address: Phone: G.C. Proj. Mgr.: G.C. Supt:

Cont.No. & Start Date: Compl. Date: Penalty: Priority: G.C. Job Phone:

Architect: Engineer:

Scope:

Clarifications:

Base Contract Price:

Change Order - Description Requested Quoted Authorized Change Order Change Order Contract
By Date Date By Date No. Date Amount Revised

(1) Piping changes per schedule A-1 Smith 8/31 Smith 9/10 6 9/11 $5000.00 $140,000.00

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
EXHIBIT 2
SAMPLE CHANGE ORDER PROPOSAL FORM

TO: GC/Owner’s Name


RE: 101
Job No. __________________________________
Job Name ______________________________
Proposed Change No. ____________________

Gentlemen:

We enclose a breakdown of costs for the changes requested by ______________________________________


Owner or A/E
on ________________________ , designated as ____________________ , Change No. ______________________

We were furnished the following drawings and specifications:


Number and Date

We propose to:

We do not include any of the following:


List exclusions specifically. Don’t include work of other crafts.

The total net change to our contract is as follows:

Total adds per breakdown: ______________________________________________________.

Total deducts per breakdown: ____________________________________________________.

Net Change: ____________________________________________________________________.

This change proposal covers only the direct costs associated with the change order work described above.
We reserve the right to assess the impact of this change order at a later date and to submit these costs as
they become known.

It is anticipated that all work required by this change will be done on a straight time basis. Overtime work, if
required, will be billed as an additional item.

Sales tax is/is not included in this proposal.

This proposal is for acceptance within _________days and is subject to escalation thereafter.

An extension of time of _________ calendar days is required.

We are proceeding with the changes listed above per your instructions.

-OR-

Please advise as soon as possible if we are to proceed.

Yours very truly,

Project Manager’s Name

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 19
EXHIBIT 3
CHANGE PROPOSAL COST SUMMARY SHEET
Company No. ______________
G.C. No. ______________
Owner No. ______________
Contract __________________________________ No. ________________________________PM ____________________________________
Date Requested __________________________ Date Submitted ____________________PM ____________________________________
Description of Change ____________________________________________________________________________________________________
__________________________________________________________________________________________________________________________

DESCRIPTION OF COSTS LABOR MATERIALS TOTALS

1. Equipment
2. Material
3. Subtotal: Item 1 + 2
4. Freight, other delivery charges
5. Subtotal: Item 3 + 4
6. Material Return and Cancellation Costs
7. Other Direct Costs
8. Equipment Rental
9. Gas & Oil
10. Subtotal
11. Labor Costs
12. TOTAL COSTS BEFORE SUBCONTRACTS
13. Subcontracts
14. Home Office Overhead @ _________%
15. Field Office Overhead @ _________%
16. Profit @ __________ % on
17. Profit @ __________ % on
18. TOTAL COSTS AND PROFITS BEFORE BONDS, INSURANCE & OTHER COSTS
19. Bonds, Subcontractors
20. Bonds, Performance and Payment
21. Financing Costs
22. Special Insurance and Other Charges
23. Extended Overhead
24. TOTAL PRICE OF CHANGE PROPOSAL
25. Extension of time because of this Change Order is _______ Workdays ❑ deferred* to be applied
in proper Schedule Sequence to each Category of Work
26. This proposal is based on ❑ Straight Time ❑ Overtime ❑ Shift Work
27. This proposal is void unless a written Change Order or Written Notification to Proceed is
received by ____________ (45 calendar days if no date shown)
28. Extended Overhead Cost: ❑ Included ❑ Deferred* ❑ Not Applicable
Submitted By: ________________________________ Date: ____________________________
Signature Title
Approved By: ________________________________ Date: ____________________________
Signature Title

*If deferred, cover letter should describe.

20 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
EXHIBIT 4
EQUIPMENT COST ESTIMATE SHEET
Date: ______________

QUANTITY EQUIPMENT UNIT COST TOTAL COST

SUBTOTAL EQUIPMENT

Sales Tax 0.00 %


_________

Drayage 0.00 %
_________

Escalation 0.00 %
_________

Warranty 0.00 %
_________
0.00 %
Start-up, Test & Punch _________

Total Costs

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 21
EXHIBIT 5
MATERIALS COST ESTIMATE SHEET
Date: ______________

QUANTITY EQUIPMENT UNIT COST TOTAL COST

SUBTOTAL EQUIPMENT

Sales Tax 0.00 %


_________

Drayage 0.00 %
_________

Consumables 0.00 % (of Labor)


_________

Escalation 0.00 %
_________

Warranty 0.00 %
_________
0.00 %
Start-up, Test & Punch _________

Total Costs

22 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
EXHIBIT 6
OTHER DIRECT JOB COSTS ESTIMATE SHEET
Date: ______________

OTHER DIRECT COSTS LABOR MATERIALS

Resident Management and Expenses


Superintendent and Expenses
Other Nonmanual Labor Supervision Expenses
Field Office Management and Expenses
Estimating & Cost Analysis and Expenses
Labor Planning (SLP) and Expenses for Update
Field Engineering, Detailing, Reproduction, Supplies, Expenses
Purchasing, Expediting, Traffic and Expenses
Inventories, Management and Expenses
Tools & Equipment Management and Expenses
Payroll Management, Time Keepers, and Expenses
Secretaries, Clerk Typists and Expenses
Welding Qualification and Expenses
Welding Inspection & Testing (NDE)
Instruction of Owner’s Personnel
CPM Scheduling or Update
Revising As-built Drawings
Progress Photos
Parking Expenses (other than on direct labor)
Permits, Licenses, Fees, Dues
QA/QC Expenses
Extraordinary Estimating Expenses
Engineering or Design Expenses
Deliveries, Company
Special Freight Charges
Temporary Wiring
Temporary Power
Temporary Heat
Temporary Water
Temporary Toilets
Temporary Air
Temporary Weatherproofing
Temporary Site Work
Safety Officer and Related Expenses
Safety Barricades, Gates, Other materials
Ventilation
Tags, Charts, Identification
Office Furniture and Office Equipment
EDP Cost
Prefabrication Facilities
Storage Facilities - On-site
Storage Facilities - Off-site
Office Heat and Electricity
Office Telephones
Copier Expense and Office Supplies
Warranty Reserve
Contingencies
Sales Tax on Applicable Items Above

Total Costs

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 23
EXHIBIT 7
EQUIPMENT AND TOOL RENTAL ESTIMATE SHEET
Project __________________________________ Type of Work __________________________ Date ____________________________
Location __________________________________ Estimated By __________________________

EQUIPMENT/TOOLS COST UNIT


PER MONTH TOTAL COST

Automobile _______ mos. @

SUV _______ mos. @


Pick-up Truck _______ mos. @
Stake Body Truck - 1-1/2 Ton _______ mos. @
Stake Body Truck - 1-1/2 Ton w/A-Frame & Winch _______ mos. @
Flat Bed Truck - 2-Ton _______ mos. @
Hydralift Truck _______ mos. @
American Crane - 18-Ton with 30 ft. Boom _______ mos. @
Austin Western Crane _______ mos. @
Motor Crane - 25-Ton _______ mos. @
D-6 Crawler Tractor _______ mos. @
Backhoe _______ mos. @
Trenching Machine _______ mos. @
Air Compressor _______ mos. @
Gasoline Driven Welding Machine _______ mos. @
Electric Motor Driven Welding Machine _______ mos. @
Hellarc Welding Machine _______ mos. @
Acetylene Rigs Complete _______ mos. @
8” Pipe Machine _______ mos. @
4” Pipe Machine _______ mos. @
2” Pipe Machine - Power Vise _______ mos. @
Pipe Bending Machine _______ mos. @
Metal Cutting Band Saw _______ mos. @
Cut-Off Saw _______ mos. @
Power Hoist _______ mos. @
Water Pump _______ mos. @
Trailer Van _______ mos. @
Portable Building _______ mos. @
Dewatering Equipment _______ mos. @
Fork Lift _______ mos. @
Portable Hoist _______ mos. @
Scaffolding _______ mos. @
Other _______ mos. @

EQUIPMENT & TOOLS TOTAL COSTS: ____________________

24 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
EXHIBIT 8
VEHICLE OPERATING COST ESTIMATE SHEET – GASOLINE AND OIL
Project __________________________________ Type of Work __________________________ Date ____________________________
Location __________________________________ Estimated By __________________________

EQUIPMENT/TOOLS COST UNIT


PER MONTH TOTAL COST

Automobile _______ mos. @

SUV _______ mos. @


Pick-up Truck _______ mos. @
Stake Body Truck - 1-1/2 Ton _______ mos. @
Stake Body Truck - 1-1/2 Ton w/A-Frame & Winch _______ mos. @
Flat Bed Truck - 2-Ton _______ mos. @
Hydralift Truck _______ mos. @
American Crane - 18-Ton with 30 ft. Boom _______ mos. @
Austin Western Crane _______ mos. @
Motor Crane - 25-Ton _______ mos. @
D-6 Crawler Tractor _______ mos. @
Backhoe _______ mos. @
Trenching Machine _______ mos. @
Air Compressor _______ mos. @
Gasoline Driven Welding Machine _______ mos. @
Water Pump _______ mos. @
Fork Lift _______ mos. @

GASOLINE & OIL TOTAL COSTS ____________________

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 25
EXHIBIT 9
LABOR SUMMARY SHEET
Page 1 of 2
1. Project and No. __________________________________________________ 2. Estimate No. ____________________________________
3. Owner and/or Architect-Engineer
Change Order Request Number __________________________________ 4. Date ____________________________________________

HOURLY RATES
5. 6. 7. 8. 9. 10. 11. 12. 13.
Job Description Base Rate Fringes Payroll Taxes Park/Travel Wage Escal. Zone Pay Total
& Insurance Subsistence
as Applicable

Fitter/Plbr. Journeyman

Fitter/Plbr. Foreman

Fitter/Plbr. General
Foreman

Sheet Metal Journeyman

Sheet Metal Foreman

Sheet Metal General


Foreman

Laborer

Labor Foreman

Operator

Teamster

Millwright

BIM/CAD

Other

JOURNEYMAN HOURS
13. Fitter/Plbr. Journeyman Hours Hours ____________________________________
14. Sheet Metal Journeyman Hours Hours ____________________________________
15. Material Handling ______ % of Lines 13 & 14 Hours ____________________________________
16. Non-Productive Labor (Relief Break, Tool Pick-up, etc.) Hours ____________________________________
______ % of Lines 13 & 14
17. Safety ______ % of Lines 13 & 14 Hours ____________________________________
18. Clean-up ______ % of Lines 13 & 14 Hours ____________________________________
19. EEO Implementation & Training ______ % of Lines 13 & 14 Hours ____________________________________
20. Equipment Repair ______ % of Lines 13 & 14 Hours ____________________________________
21. Height Factor Hours ____________________________________
22. Base Journeyman Hours Hours ____________________________________

26 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
EXHIBIT 10
LABOR SUMMARY SHEET
Labor Corrections
Page 2 of 2

Date: ______________

AFFECTED MHRS OF MANHOURS OF


CURRENT CONTRACT PROPOSED CHANGE
23. Percentages are applied to the total
affected manhours of the current contract, MHrs __________________________
and to the labor of the proposed change As of __________________________ ____________________________(A)

NEGATIVE PRODUCTION FACTORS % of Loss MHRS Lost % of Loss MHRS Lost

24. Fatigue

25. Stack of Trades

26. Morale and Attitude

27. Reassignment of Manpower

28. Crew Size Inefficiency

29. Concurrent Operations

30. Dilution of Supervision

31. Learning Curve

32. Errors and Omissions

33. Beneficial Occupancy

34. Joint Occupancy (Other Trades)

35. Site Access

36. Logistics

37. Ripple

38. Overtime Adjustment

39. (B) (C)

40. B + C -MHrs = Adjusted direct MHrs Move to Line 41

HOURS AND LABOR AMOUNT


41. Journeyman (with corrections) ______________ Hours @ ____________= $ ____________
42. Foreman ( % of Journeyman hours) ______________ Hours @ ____________= $ ____________
43. Gen. Foreman ( % of Journeyman hours) ______________ Hours @ ____________= $ ____________
44. Laborer ( % of Journeyman hours) ______________ Hours @ ____________= $ ____________
45. Laborer Foreman ______________ Hours @ ____________= $ ____________
46. Operator ______________ Hours @ ____________= $ ____________
47. Teamster ______________ Hours @ ____________= $ ____________
48. Millwright ______________ Hours @ ____________= $ ____________
49. Other ______________ Hours @ ____________= $ ____________
______________ Hours @ ____________= $ ____________
50. TOTAL DIRECT LABOR
51. Total Replacement ______ % of Line 50 $ ____________
52. TOTAL LABOR COSTS $ ____________
$ ____________

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 27
EXHIBIT 11
SUBCONTRACTS SUMMARY FORM
Job No. ________________________________________________________ Date __________________________________________________

Project__________________________________________________________ Type of Work __________________________________________

Location ________________________________________________________ Estimated by __________________________________________

SUBCONTRACTS QUOTE

Temperature Control

Insulation

Fire Protection

Air & Water Balance

Excavation

Rigging

Painting

Electrical

Demolition

Core Drilling

Nondestructive Testing

Other

TOTAL COSTS

Note: Similar supporting documentation, described in the other exhibits, may be used for subcontractor detailed cost estimates that
are summarized on this form.

28 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
EXHIBIT 12
EXTENDED OVERHEAD COST SHEET
Job No. ________________________________________________________ Date __________________________________________________

Project__________________________________________________________ Type of Work __________________________________________

Location ________________________________________________________ Estimated by __________________________________________

EXTENDED OVERHEAD COST TOTAL

TOTAL COSTS

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 29
EXHIBIT 13
SPECIAL INCLUSIONS AND EXCLUSIONS FORM
Date:

Special Inclusions and Exclusions

30 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
EXHIBIT 14
FIELD-AUTHORIZED CHANGE ORDER
Purchaser Change No. ____________

Change No. __________

Purchaser ______________________________________________________ Date __________________________________________________

____________________________________________________________________________ Job No. ______________________________________________

Address ________________________________________________________ Job __________________________________________________

__________________________________________________ Work Complete ______________________________ Sheet ______________________

QTY MATERIAL PRICE EA. AMOUNT DESCRIPTION OF WORK

EQUIPMENT & TOOLS

______ Shop Deliveries @ __________

______ hrs Backhoe @ __________

______ hrs Weld Machine @ __________

______ hrs Truck @ __________

______ Miles Travel @ ______/mile

______ @ ______

______ @ ______

TOTAL EQUIPMENT & TOOLS

LABOR & LABOR BURDEN

______ hrs Supt. @ ________/hr

______ hrs Foreman @ ________/hr

______ hrs Mechanic @ ________/hr

______ hrs Operator @ ________/hr

______ hrs Laborer @ ________/hr


______ hrs @ ________/hr

______ hrs @ ________/hr

TOTAL LABOR, FRINGES, TAXES

TOTAL MATERIALS COST

TOTAL EQUIPMENT COST

TOTAL LABOR COST

SUBTOTAL

PLUS _____ % OVERHEAD

TOTAL MATERIALS COST TOTAL COST

PLUS ______% TAXES PLUS _____ % PROFIT

TOTAL MATERIALS & TAXES TOTAL BILLING


Supervisor who authorized the work. Authorized By
PURCHASER’S REPRESENTATIVE

______________________________________________ Company ____________________________________________

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 31
EXHIBIT 15
FIELD-AUTHORIZED CHANGE ORDER FORM
WORK AUTHORIZATION # ___________
SHEET NO. _____ of _____

DATE __________________________________________________________ CUSTOMER ORDER NO. ________________________________

PROJECT ______________________________________________________ JOB NO. ______________________________________________

WORK PERFORMED BY __________________________________________ FOR __________________________________________________

AUTHORIZED BY ________________________________________________ TITLE__________________________________________________

DESCRIPTION OF WORK __________________________________________________________________________________________________

__________________________________________________________________________________________________________________________

__________________________________________________________________________________________________________________________

LABOR MATERIAL

ACTUAL HOURS WORKED

NAME TRADE STRAIGHT PREMIUM DESCRIPTION QTY


TIME TIME

EQUIPMENT & TOOLS

DESCRIPTION TIME DESCRIPTION TIME

REMARKS: ______________________________________________________________________________________________________________
ARCHITECT
CONTRACTOR ______________________ OWNER ______________________ SUBCONTRACTOR ______________________
BY ______________________ BY ______________________ BY ______________________
ADDRESS ______________________ ADDRESS ______________________ ADDRESS ______________________
______________________ ______________________ ______________________
JOB COMPLETED ❑ YES ❑ NO
NOTE: COMPLETE A SEPARATE DAILY WORK ORDER FOR WORK AUTHORIZATION NOT SIGNED BECAUSE:
(1) EACH JOB AND (2) EACH DAY. ❑ UNABLE TO CONTACT REPRESENTATIVE
DO NOT ATTEMPT TO COMBINE JOBS OR DAYS. ❑ AUTHORIZED BY PHONE
❑ FORM ISSUED FOR RECORD PURPOSES ONLY
❑ AUTHORIZATION IN DISPUTE

32 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
EXHIBIT 16
INSTRUCTIONS FOR FIELD-AUTHORIZED CHANGES (FAC)

1. Call the office and get approval from your Project Manager before starting ANY FAC work.
2. When you call to get approval, be prepared to tell the Project Manager:
• What work is to be done?
• Who will pay for the work?
• To whose attention should the bill be sent?
• Who is authorizing the work?
• How long will the job last?
• What material will be needed?
• Can you get a written purchase order? If not, will the buyer’s representative sign your daily
sheets?
3. The Project Manager will assign a number to the FAC work. If the number starts with 8 (example:
8125) it is a completely separate job. You must turn in a separate time sheet for an 8000 series
job.
4. FAC sheets are like service tickets—EVERYTHING YOU USE MUST BE LISTED ON THE SHEET.
This includes material from your truck stock, material already on your job, or special ordered
items such as plumbing fixtures, or equipment. If you don’t list an item on the sheet, we won’t be
paid for it. Don’t forget consumables such as welding rod, solder, flux, oxygen, acetylene, etc. Be
sure to list subcontractors, if any are used.
5. List the number of delivery trips from the shop.
6. List all the equipment and tools used, except hand tools.
Examples of chargeable equipment are:
Air Compressors Fork Lift Set Transit
Backhoe Generator Trench Jacks
Bantam Grinders Trucks
Boom Truck Hilti Drill Warning Barricades
Comealongs Hole Dawg Welding Machine
Copper Cleaning Mach. Line Up Clamp Whacker
Core Drill Pavement Breakers Zipall Gun
Cutoff Saw Pipe Benders
Cutting Rig Railroad Jacks
Ditch Pump Rigid 300 Pipe Machine
Ditch Witch Roustabout Lift
7. Describe the work done as specifically as you can under “Description of Work.”
8. Under “Labor,” don’t fill in any rates unless the customer insists on having a price before signing.
If you need a rate for labor, call your Project Manager. THIS RATE IS NOT THE SCALE; IT
INCLUDES TAXES, INSURANCE, FRINGES, ETC. Enter the total number of hours worked for each
classification. For example, if you have 4 men working 8 hours each, enter 32 hours.
List straight time and overtime hours on separate lines. Be sure to include your time spent
surveying the job, calling the Project Manager, ordering the material—all the time spent on the
FAC. Where applicable, include time for the General Superintendent.
9. Under Job Completed, enter “YES” or “NO.”
10. Number the sheets consecutively.
11. Make three copies of the FAC form. MAIL THE ORIGINAL DAILY WITH YOUR TIME SHEETS. DO
NOT WAIT UNTIL THE WORK IS FINISHED TO MAIL THE SHEETS IN.
Give the second copy to the customer.
Keep the third copy for your use.

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 33
EXHIBIT 17
SUMMARY OF FAR COST ALLOWABILITY
Job No. __________________________________ Date __________________________________
Project ____________________________________ Change Order Request (COR) No. ________
Location __________________________________ Prepared by ____________________________

FAR 31.205 ALLOWABLE OR APPLICABILITY JOB COST REPORT


REFERENCE DESCRIPTION UNALLOWABLE TO SUBJECT COR CODE REFERENCE
1 Public relations & advertising AR
3 Bad debts Un
4 Bonding costs A
6 Compensation for personal services AR
7 Contingencies AR
8 Contributions or donations UE
10 Cost of money A
11 Depreciation AR
12 Economic planning costs A
13 Employee morale, health, welfare, food service AR
14 Entertainment costs Un
15 Fines, penalties, & mis-charging UE
16 Gains & loses on disposition of property A
17 Idle facilities UE
18 Research & development AR
18 Bid and proposal costs AR
18 Deferred research & development UE
19 Insurance & indemnification AR
20 Interest & other financial costs UE
21 Labor relations A
22 Lobbying costs UE
23 Losses on other contracts Un
25 Manufacturing & production engineering costs A
26 Material costs A
27 Organization costs Un
28 Select other business expenses A
29 Plant protection costs A
30 Patent costs AR
31 Plant reconversion costs UE
32 Precontract costs A
33 Professional & consultant service costs AR
34 Recruitment costs A
35 Relocation costs AR
36 Rental costs AR
37 Royalties & other costs for use of patents A
38 Selling costs UE
39 Service & warranty costs A
40 Special tooling & test equipment costs A
41 Taxes A, Un
42 Termination costs AR
43 Trade, business, tech & professional costs A
44 Training & education AR
46 Travel costs AR
47 Legal & other proceeding costs A, Un
49 Goodwill Un
51 Alcoholic beverages Un
52 Asset valuations from business combinations AR

KEY: A = Allowable; Un = Unallowable; AR = Allowable, but with certain restrictions; UE = Unallowable, but with certain exceptions
Source: www.acquisition.gov/far

34 Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved.
EXHIBIT 18
UNIT PRICE CHANGE ORDER PRICING FORM
Job No. __________________________________ Date __________________________________
Project ____________________________________ Type of Work __________________________
Location __________________________________ Prepared by ____________________________

UNIT OF UNIT DOLLAR


DESCRIPTION MEASURE QUANTITY X PRICE = AMOUNT

$__________

TOTAL AMOUNT $__________

Management Methods Bulletin CO1 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 35
Change Orders

How to Organize and Submit


a Claim
Introduction claim under the Contract Disputes Act of 1978
What is a construction claim? This term is until certified2 as required by the Act.
widely used to describe anything from a Beyond these formal definitions, the term
request for equitable adjustment (or change “claim” has taken on a meaning based on its
order request) to a formal lawsuit demanding common use in the construction industry.
relief from some court or governmental According to this meaning, a claim is a de-
agency. However, “claim” has recognized def- mand for relief, usually as to cost and/or time,
initions in our industry: by a contractor to another party, such as a gen-
According to the American Institute of Archi- eral contractor or owner. In this sense, a claim
tects Glossary of Construction Industry Terms: is filed only after negotiations for a fixed-price
change order fail, or after the reviewing party
A demand or assertion by one of the parties has formally denied the change order request.
seeking, as a matter of right, adjustment or Thus, in the vernacular, a claim is equated to a
interpretation of Contract terms, payment of dispute between the parties that remains after
money, extension of time or other relief with negotiations to modify the contract have
respect to terms of the Contract (Ref: AIA failed. When an issue is resolved by a change
Document A201.)1 order to the contract, usually no claim results.
As defined by the Federal Acquisition Regula- Most change order requests do not require for-
tion (FAR) Subpart 2.1, 2,101 (b)(2): mal certification. However, claims of over
Claim, means a written demand or written $100,000 on federal government projects must
assertion…seeking, as a matter of right, the include a certification signed by the claimant
payment of money in a sum certain, the adjust- with language consistent with the require-
ment or interpretation of contract terms, or ments of the Contract Disputes Act. Thus, for
other relief arising under or relating to the projects contracted under the FAR, a “claim” of
contract. However, a written demand or writ- over $100,000 is differentiated from a change
ten assertion by the contractor seeking the order request by the required certification. The
payment of money exceeding $100,000 is not a
2
The issue of claim certification is not the subject of
1
“The Architect’s Handbook of Professional Practice” this chapter and is a topic that should be addressed by
Volume 3, AIA Press. the claimant’s construction counsel.

Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved. 37
Change Orders

issue of claim certification requires careful thoroughly the potential risks and liabilities
review and consideration by the claimant’s that would result from this decision.
upper management and construction counsel
and is not the subject of this chapter.
Steps to Preserve the
As noted above, a claim typically is filed when Contractor’s Right to File a
negotiations to execute a change order to the
contract have not been fruitful. Many contract
Claim
documents contain critical timing clauses that If a contractor determines that claims will
set forth the time frame within which a con- inevitably be filed on a project, due perhaps to
tractor must give formal written notice of a the exceptionally poor quality of the construc-
claim and further deadlines as to when a claim tion documents or the general contractor’s or
must be filed in order to be considered by the owner’s improper scheduling or project man-
reviewing party, such as a government agency. agement, certain steps should be considered to
Contractors should pay close attention to tim- preserve the contractor’s right to file a claim.
ing deadlines and content requirements. If they 1) Many change order forms used by general
do not, claims may be dismissed or rejected out contractors and owners contain broad
of hand by the reviewing party for failure to “accord and satisfaction” language that
file the claim in a timely fashion or with the seeks to bar the contractor from recovering
proper information and in the proper form. time and/or costs for a change in scope
The content of a mechanical contractor’s over and above the remedies specifically
claim typically will be dictated by the terms prescribed within the change order itself.
and conditions of the contract or by govern- Such language has been strictly interpreted
ing regulations, such as the FAR. The and as such, the contractor executing a
claimant should carefully review all submis- change order with broad accord and satis-
sion requirements in the contract to ensure faction language may be held to the bar-
that the timing and content of the claim are gain defined by change order scope and
in conformance with the contract terms. pricing. In the event the contractor is faced
with such language on the change order
Many mechanical contractors have the phi- forms, the appropriate course of action
losophy that claims must be avoided at all should be formulated by upper manage-
cost. While it is certainly desirable to avoid ment aided by construction counsel.
distracting and time-consuming disputes or
costly litigation, the failure of a contractor to 2) Monthly payment applications often con-
file a claim in a timely fashion may forever tain broad waiver language that seeks to
bar the contractor from relief (i.e., costs bar contractors from recovering unsettled
and/or time extensions) to which the con- claims that are not expressly listed as
tractor is otherwise entitled. Before a exceptions on the payment application
mechanical contractor makes a decision to form itself. Frequently, these forms are not
delay or to avoid filing a claim, the com- processed by the contractor’s field manage-
pany’s upper management should evaluate ment and thus they are unaware of this
waiver language. All outstanding claims
and unapproved change orders should be

38 Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

expressly listed within the exceptions sec- relief. While a notice letter sets forth a set of
tion of the payment application form conditions that have occurred or may occur,
every month. In the event the owner or usually giving the other party an opportunity
general contractor do not provide an to remedy or mitigate the adverse effects of
exceptions section on the payment appli- the condition, a claim letter usually includes
cations form, the mechanical contractor the time and cost impacts of the events. The
should insert its exceptions on the form notice letter generally precedes the prepara-
prior to submitting it for payment. tion of a claim. The timing and content of
notice letters and claim documents are often
3) In the event the project is nearing com-
provided for in the contract and the claimant
pletion with claims still outstanding, the
should refer to the contract prior to submit-
claimant should not accept final payment
ting either a notice or a claim document to
for the project or execute final releases
ensure proper content and timing.
until all claims are fully settled.
Typically, a claim is a demand for specific relief
or remedy and is filed after the impacting
Differentiating a Notice from event has occurred so that its effects are
a Claim known; and after change order negotiations
A notice of an event involving a claim is not, have failed to provide for an equitable adjust-
in and of itself, a claim. Notices and claims are ment. Since a formal claim document usually
typically two different documents with vary- follows the quantification of the impact, one
ing content. Notice refers to the transmission component of a claim should be specificity—a
by a contractor to another party (i.e., the gen- number of days of extended contract perform-
eral contractor or owner) of a document that ance time, an amount of money for direct
asserts that a delay and/or added costs may be, costs, an amount of money for indirect costs,
or have been, encountered on a construction and other components of contract changes
project. A notice is designed to alert the gen- that are being requested by the claimant. If the
eral contractor or owner to a condition that claim does not contain specific requests for
requires remediation or special attention. Most contract modification, the claim may be
notice letters are written when the details of denied based on a lack of specificity.
the impacting event are not fully known and
the outcome in terms of delay and added
costs, if any, is uncertain. Most contracts The Components of a Claim
include provisions outlining the required com- Proof of entitlement and quantum normally
ponents of a proper filing of notice. These lies with the contractor making the claim
requirements may include specific descrip- (the claimant), meaning it is the contractor’s
tion(s) of the thing or things causing the time obligation to prove the elements of its claim.
and/or cost impact, estimates of the time There are several common components in a
and/or cost impacts, and other specific require- contractor’s claim. These may include,
ments that may be set forth in the contract. depending on the nature of the claim:

Notice letters do not typically contain the ■ A Critical Path Method (CPM) schedule
same elements that are included in a claim for impact analysis. Such analyses can

Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved. 39
Change Orders

include fragnets, or time impact analyses events such as unanticipated adverse weather,
(TIA), a windows analysis, and/or as- unanticipated added impacts arising from
planned versus as-built schedule analysis previously executed change orders, and other
to support any claim for a time extension. important concepts are frequently discussed
in the contract terms. Other important fac-
■ Craft-level analyses showing as-planned
tors such as waiver language on payment
versus as-built craft curves.
applications, “full accord and satisfaction”
■ Inefficiency studies identifying and quan- language regarding change orders, and “no
tifying losses in labor productivity. damages for delay”3 clauses that attempt to
■ An accounting of the direct costs arising limit time-related cost impacts for delays may
from the claimed conditions. be included in the contract. Contractual time
limits for providing notice and for submis-
■ An accounting of the indirect costs arising sion of a claim are important elements to
from the claimed conditions. consider. The contract must be fully reviewed
■ A narrative of the cause and effect nexus to ensure that a claim is in compliance with
that can include a written description of the contract terms or, if not, why the particu-
the events, photographs, contract docu- lars of the contract may not apply to the
ments such as letters and electronic corre- claim being filed.
spondence, requests for information (RFI), A thorough review of the contract terms,
change directives, and other proofs that results of the schedule and labor productiv-
demonstrate the changed nature of the ity analyses, and damages calculations
work, the resulting damage, and a sum- should be performed before finalizing the
mary of the desired relief. entitlement and damages portion of the
The exact content and format of the claim claim narrative. The contract and applicable
should be thoroughly reviewed by the regulations should be carefully reviewed in
claimant’s senior management and, if appro- order to ensure that the form of the claim is
priate, by the firm’s legal counsel and the chief consistent with the requirements set forth
financial officer or outside accountant. As therein, including timing, addressee, con-
noted, the timing, form, and content of a tents, and certification. Generally, the claim
claim can be critical elements in the claim’s package should be transmitted to the
acceptance or rejection by the reviewing party. reviewing party or agency by registered mail

Read the Contract Before 3


Contact language that attempts to limit a contractor’s
right to make a claim for a certain element of cost or time
Filing a Claim impact may not be applicable in all circumstances. By
As noted above, various contract documents way of example, in some cases a “no damages for delay”
may contain language that seeks to limit a clause may not have its intended efficacy, given actual cir-
cumstances on a project. However, such clauses cannot be
contractor’s right to recover delay time and ignored by the claimant and must be carefully considered
the costs arising from delay and inefficiency. when a claim is prepared. Review of the contract, in con-
Important time- and cost-related issues such junction with the claim, by the contractor’s counsel is
advised in order to ensure harmony between the require-
as labor and material escalation, force majeure
ments of the contract and the claim being submitted.

40 Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

or by other means that result in a signed jurisdictions require that, in order for a
and dated proof of receipt. claim to be validly served, it must be
addressed to a specific individual, within a
specific department, within a specific time
Content and Order of the Claim frame. Copies of the claim also may be sent
It is true that, to some extent, how seriously to other project-related individuals, such as
the claim is viewed by the party receiving it the project manager or resident engineer,
can be determined by the professional but to be valid, the claim must be transmit-
appearance and completeness of the claim ted to the specific, named party listed in the
document and its supporting exhibits. If the contract documents. When a contractor is
claim is poorly organized, incomplete, or contemplating a claim, in addition to atten-
contains a narrative that is vague or confus- tion to the content of the claim itself, care-
ing and lacking in compelling facts to con- ful attention must be paid to the contrac-
nect cause and effect, the claim has a greater tual and regulatory requirements of filing a
chance of being dismissed out of hand. valid claim.
However, if the claim package is compelling
in its narrative and comprehensive in its Typically, a summary stating the basis of the
supporting documentation, then the claim is essential. This summary, or claim
chances of an equitable settlement are narrative, should lay out the contractual
increased significantly. foundation for making the claim and for the
resulting damage. It should directly connect
The content and order of the claim should the basis of the claim to the resulting dam-
be designed to compel the reader, by the ages—this is called the “cause and effect”
weight of the facts, to adopt the claimant’s nexus. A citation to contract and/or schedule
position and to issue an equitable adjust- requirements is usually appropriate in the
ment to the contract. Thus, the claimant summary or narrative. It is important to con-
should include in the claim package a com- sider two general concepts when preparing
prehensive and comprehensible narrative the summary or claim narrative: a chrono-
that sets forth the bases of the requests for logical and sequential presentation of the
remedy that can include both an extension events; and addressing the questions of who,
of time and added costs. If the reader cannot what, where, when, why, how, and how
reasonably navigate through the claim or much, as appropriate. Specificity is key to a
understand the basis of the demand, a rejec- properly constructed claim document.
tion of the claim can be expected.
The damages portion of a claim may include
Addressing the claim to a specific person such components as:
and/or entity may be of vital importance
depending on the jurisdiction in which the ■ Days of delay and the attendant time
claim is submitted. This consideration is in extension request;
addition to the time restrictions for filing a ■ Costs for added performance time due to
claim that may be contained in the contract delays (field and home office overhead
or other governing regulations. For costs)4;
instance, public works contracts in some

Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved. 41
Change Orders

■ Direct acceleration costs (payroll differen- prepared to assimilate the facts, then the doc-
tial costs for overtime, shift work, or umentation and calculations can be pre-
added supervision and equipment atten- sented to support the claim narrative.
dant to an increased crew size);
■ Indirect labor inefficiency costs such as Sample Claim Narrative
overtime inefficiency, crew disruption, Summary
stacking of trades, or other labor produc-
A claim narrative can be provided in sum-
tivity factors;
mary form, as shown on the next page, as
■ Labor wage rate escalation; long as the summary denotes each major
■ Material cost escalation; category of impact. The documentation sup-
porting each category can be provided in
■ Extended warranties; accompanying exhibits. However, a more
■ Equipment “inefficiency”; exhaustive and comprehensive written claim
narrative is usually presented. A comprehen-
■ Added detailing or drafting/building sive claim narrative can provide a chrono-
information modeling (BIM) and schedule logically-ordered description of the impact-
update costs; ing events with citations to the drawings,
■ Supervision or management added to mit- specifications, the contract or other perti-
igate labor inefficiencies or to process a nent documents such as letters, purchase
large quantity of scope changes; orders, or site photographs. A well-written,
comprehensive claim narrative can lead the
■ Subcontractors’ claimed amounts;
way for expanded understanding of the
■ Finance charges; claimant’s position by the reviewer and can
■ Bond costs; and also result in an equitable adjustment to the
contract. It is much more economical for
■ Overhead (unless claimed separately) and the contractor to expend appropriate
profit. resources in the preparation of its claim nar-
Once the particulars of the issues have been rative and supporting documentation than
introduced in a comprehensive and com- to later become involved in costly litigation
pelling manner so that that the reviewer is because the claim was denied due to lack of
supporting documentation.
4
The components of a compensable delay claim (i.e., Also note from the sample on the next page
extended field office overhead) are frequently large in that the claim contains elements of compen-
number and can include the daily costs of on-site project sable delay and loss of labor productivity. A
management and supervision, the daily costs of office
compensable delay is one that entitles the
and storage trailers and warehouses, trucks, fuel, tele-
phones, and other time-related costs. In certain instances, claimant to compensation for each day of
home office overhead may be recoverable. What may or extended general condition costs. All delays
may not be claimed as to delay costs is frequently pre- are not necessarily compensable. Some delays
scribed in the contract, the FAR, generally accepted ac-
counting procedures, or in other related documents. Refer
are excusable only, meaning that the
to “How to Identify and Manage Change Orders” for claimant is relieved from liquidated damages
more specific information on damages calculations.

42 Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved.
EXHIBIT 1
SAMPLE CLAIM NARRATIVE SUMMARY

Amalgamated Mechanical Contractors


1 Central Street
Any City, USA
Mr. John Smith (Today’s Date_____________)
Contracting Officer
Department of Construction Services
1 Public Works Square, Any City, USA

Reference: Public Office Building Project, Contact No. 100-00-100

Subject: Claim for Recovery of Added Costs and Contract Time Extension

Dear Mr. Smith:

Pursuant to the Contract, Amalgamated Mechanical Contractors (“AMC”) herewith submits its claim for
recovery of costs and for a time extension on the above captioned project. A summary of the claim, as
supported by the enclosed exhibits, is as follows:

On May 1, 2xxx, AMC discovered a differing site condition involving unforeseen and unsuitable soils that
prevented AMC from timely and efficiently installing its underground plumbing and mechanical piping sys-
tems. AMC provided timely and proper notice of this condition. Reference Exhibit A containing AMC’s
notices, site photographs, daily reports showing craft and equipment usage and other documentation. AMC
claims $_____________ in direct costs for labor, materials and subcontractor costs to remove the unsuitable
materials and replace those materials with the prescribed stone and backfill.

This differing site condition critically delayed the approved project schedule by seventy-five (75) calendar
days. AMC requests a 75 calendar day compensable time extension to its contract. Reference Exhibit B
containing AMC’s CPM schedule time impact analysis demonstrating AMC’s entitlement to a 75 calendar
day extension of time. AMC’s claimed costs for delay amount to $____________.

During the discovery period from March 1, 2xxx to June 1, 2xxx, AMC’s crews were made inefficient by the
piece-meal nature of the work during the period the Government was investigating the differing site condi-
tions. Additionally, AMC was required to demobilize its crews during the remediation period and then
remobilize its forces once remedial steps had been completed. Reference Exhibit C containing AMC’s loss
of labor productivity analysis. AMC’s claimed costs for labor inefficiency amount to
$________________.

With appropriate support costs, profit, bond and other appropriate costs, AMC’s claimed damages total
$_________________ for which AMC herewith submits for payment. AMC’s summary of damages is included
herein at Exhibit D. AMC also requests a time extension of 75 calendar days. This reflects the identifiable
cost and time impact associated with this claim. AMC expressly reserves the right to amend this claim as a
result of the unforeseeable collateral impacts resulting from this differing site condition, as such impacts
become known.

Yours truly,

_______________________________
Executive Vice President of Operations

Management Methods Bulletin CO2 - 2011; replaces 1976, 1987, and 2005 versions. © 2016 MCAA. All rights reserved. 43
Change Orders

but receives no compensation for the delay. summaries of this analysis can be included in
Some delay may be a combination of non- the claim, as shown on the next page.
excusable, excusable, and compensable time.
If the claimant has included a component of
A compensable schedule analysis is nor- damages arising from labor inefficiencies
mally considerably more complex than a caused by the impacting event, the computa-
schedule analysis focusing only upon excus- tions for this component can be added as an
able delay. For an excusable delay analysis, exhibit to the claim. There are several meth-
the claimant must prove that it was not the ods of quantifying a contractor’s loss of labor
sole cause of critical path delay. For exam- productivity. These include the: total cost or
ple, if the claimant caused the project to modified total cost method; measured mile
finish late by 30 days through its own fault, method; and industry study method, such as
and another party (e.g., the owner or the by the use of the MCAA labor inefficiency fac-
prime contractor) independently caused the tors. An example of an inefficiency exhibit
project to finish 30 days later than allowed supporting the claimant’s loss of labor produc-
by the contract, the claimant would still be tivity component may appear as on page 46.
entitled to a 30-day excusable, non-com-
It is well acknowledged in the construction
pensable delay.
industry that proving labor inefficiency is dif-
However, in order for a compensatory analy- ficult. In computing a labor inefficiency
sis to prevail, the claimant must demon- claim, exactness is not a requirement. How-
strate through a CPM scheduling analysis ever, connecting the causes with the effects is
that its own delays, if any, were not control- generally a necessary element in any claim
ling critical path delays and as such, did not submission for loss of labor productivity.
independently or concurrently cause the There are indicia of labor inefficiencies that
project to finish late. A compensable delay many experts look for when preparing a labor
can have many facets that must be analyzed inefficiency claim. These indicia can include:
and explained and is frequently a very com- unexpectedly high crew sizes, fluctuations in
plex analysis best assigned to scheduling crew sizes, disruption in the productive flow
experts. The contract terms, accepted prac- of crews, a high percentage of scope changes
tice in the industry, combined with a tech- as a ratio of changes to base contact labor
nically competent CPM schedule analysis hours, unanticipated stacking of trades,
generally determine whether project delay is unreasonable limitations to site access, and
compensable, excusable, or in some cases, many other categories of impacts. Once the
non-excusable. causes are established, then the claimant
must estimate or calculate the resulting dam-
In addition to the claim narrative, supporting
ages in terms of lost labor hours.
documentation can be provided as exhibits to
assist the reviewer in reaching the desired Field labor is not the only type of labor that
conclusion. If a schedule analysis has been may be susceptible to inefficiencies. The pro-
performed to support a claim for an excusa-
ble and/or compensable time extension,5 5
For a more detailed review of the methods of schedule
impact analysis, refer to the chapter on “Time Impact
Analysis—Measuring Project Delay.”

44 Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

ductivity of coordination, or the BIM6 sive clash identification and remediation.


process, can also be adversely affected by Often, the coordination process is adversely
events on the project. Coordination, or BIM affected by an excessive number of requests
labor, can become inefficient if the plans and for information that slows the progress of
specifications are defective, leading to exces- the BIM activities and makes such activities
inefficient though the effects of piece-meal-
ing of the coordination work and other dis-
6
Building Information Modeling, usually a three- ruptions. Coordination labor should be care-
dimensional model of the project showing the elements
of the work by the various trade contractors. The BIM fully analyzed by the claimant in order to
process generally occurs at the early stages of the proj- ensure that this component of construction
ect and labor overruns may be not be properly included is not improperly omitted from a delay
in an inefficiency analysis. The claimant should be care-
and/or inefficiency claim.
ful to assess BIM labor overruns to determine if such
overruns were occasioned by inefficiencies caused by Claims for loss of labor productivity can be
defective plans and specifications or other non-contrac-
tor caused impacts.
quantified by several means as described

Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved. 45
Change Orders

above. A more exhaustive discussion regard- a piece of equipment may become elongated
ing the identification and quantification of on the project. If it can be shown the a piece of
loss of labor productivity claims can be equipment (either rented or owned by the
found in the chapter detailing “How to Use claimant) was required to be on site longer
the MCAA Labor Factors.” than planned, or if equipment had to be added
to the project due solely to the inefficiencies
Furthermore, many contractors recognize a
claimed for the labor portion of the project, the
phenomenon sometimes called “equipment
attendant costs can be recovered in the claim.
inefficiency.” Equipment, in and of itself, is not
inefficient.7 The labor to use the equipment
may be made inefficient by a host of causes. 7
It may be argued that a newer and more fully fea-
Presumably, the labor required to operate a tured piece of equipment is more efficient or cost
piece of equipment would be evaluated in a effective when compared with an older or less robust
typical labor inefficiency claim. However, due model of the same item. However, as it is used herein,
efficiency is a function of output over input for a
to labor inefficiencies, the time required to use given piece of equipment.

46 Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

It is therefore important to record planned and Home office overhead as a component of a


actual equipment usage on the project to deter- delay claim may or may not be recoverable as
mine if inefficient conditions have caused an a matter of contract provisions, or as a matter
unplanned increase in the cost of equipment. of the current trends in reported cases. At the
time of this writing, the ability to recover
Damages calculations are an important com-
unabsorbed home office overhead is limited
ponent of a claim. As noted, the claim should
to those situations where the contractor can
contain a sum certain (i.e., a specific dollar
demonstrate that:
amount for damages) that is being sought by
the clamant as a result of the impact event(s) 1) The excusable delay period represents a
described in the narrative. Damages calcula- suspension of the work, not just an elon-
tions must conform to accepted accounting gation of the duration of work activities,
practices and to the governing authorities effectively placing the claimant in a
such as the contract or the FAR, as applica- “stand-by” mode;
ble.8 The damages portion of a claim also
2) The “stand-by” period is of an uncertain
may be the subject of a review by the con-
duration; and
tractor’s counsel and its chief financial officer
or accountant, particularly if a component 3) The claimant can demonstrate that it did
for extended home office overhead is not obtain, and could not have reason-
included. The claimant should anticipate that ably obtained, new work to absorb the
a claim will be the subject of a full audit and home office overhead not being absorbed
should prepare accordingly. by the project on which the claim is
being filed due to the suspension of work.
The use of allocation-related formulae, such
as the Eichleay9 formula, is common in com-
puting a contractor’s home office overhead
for the purposes of including those costs in a
delay claim. The Eichleay formula allocates a
contractor’s corporate home office overhead
to a particular project and then computes the
daily home office overhead allocable to that
project. The daily home office allocated rate
times the number of days of compensable
delay equals the home office overhead com-
ponent of compensable delay claim.

8
For a more detailed review of the methods of quantify-
ing impacts, refer to the chapters on “Time Impact
Analysis—Measuring Project Delay,” “How to Identify
and Manage Change Orders,” and “How to Use the
MCAA Labor Factors.” The pricing format for a change
order request and a claim are essentially identical.
9
Reference Appeal of Eichleay Corporation, ASBCA No.
5183, 60-2 BCA ¶ 2688 (1960).

Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved. 47
Change Orders

Other methods of computing home office denied with a written or oral evaluation or
overhead have been utilized by contractors rebuttal, it is incumbent upon the claimant to
with varying degrees of success. The recovery carefully review the bases for denial and make
of home office overhead is challenging due to a determination as to any corrections that
the limitations currently imposed by the courts may be needed to the original claim submis-
and boards and the decision by the contractor sion. It is possible that the reviewer may find
whether or not to seek recovery of home office disallowed costs or raise questions as to enti-
overhead costs should be aided by the advice tlement or the factual events described in the
of the contractor’s counsel and accountant. claim. The claimant should timely and con-
structively respond to those issues with correc-
On public contracts, expect to be audited once
tions or explanations as to the issues raised by
the claim is submitted. Audits can be per-
the reviewer. If a constructive dialogue can be
formed by such agencies as the Inspector Gen-
established between the claimant and the
eral’s Office, the Defense Contract Audit
reviewing party, the potential of an equitable
Agency, or other audit groups affiliated with
settlement of the claim increases.
the governmental department with which the
contract was executed. A public contract audit In some cases, a reviewer will dismiss the
of a contractor’s claim is not a mere technical- claim out of hand and without any reasoned
ity. Many audits probe the contractor’s finan- basis for the rejection. Further, the rejection
cial and accounting records for possible dis- may not be accompanied by a written or oral
crepancies between the claimed amounts and rejoinder or rebuttal; simply the other party’s
the entries shown in the contractor’s books and deafening silence. The contractor should take
records. While simple entry or arithmetic errors written exception to this sort of “construc-
can be corrected or explained, audits can have tive” denial and, where appropriate, file an
serious ramifications to the claimant should appeal in the manner prescribed by the con-
the audit uncover apparent improprieties in tract. When a claim is formally denied, it
the claimant’s books and records as they are would be prudent to have the claim and its
compared with the claimed damages. Apart denial reviewed by a construction attorney to
from an audit of the claimant’s monetary dam- ensure that the form of the original claim was
ages, an audit can challenge methodologies uti- correct (if this step was omitted prior to the
lized by the claimant in the preparation of the original submission of the claim) and to pre-
claim. Audits can be far reaching and have sig- pare the appeal of the denial.
nificant impact on how the claim is processed
A “deemed” or “constructive” denial of a
or if the claim is simply denied in its entirety
claim occurs when the party receiving the
for lack of support or proper record keeping.
claim does not respond to the claim in any
fashion, or in the prescribed or reasonable
Actual or Deemed amount of time. As noted, in some cases the
(Constructive) Denial of a recipient of the claim may have no response
at all. It is usually appropriate to expect a
Claim response within 30 to 90 calendar days of the
Regardless of how well a claim is prepared, date of submission of the claim. If, after a rea-
some claims will be denied. When a claim is sonable period, or the contractually pre-

48 Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved.
Change Orders

scribed period, of time has elapsed without a that, somehow, disputes will simply resolve
response to the claim, a second demand letter themselves by working out the differences on
should be transmitted requesting a response the jobsite. This can lead to unanticipated
to the claim within a reasonable (i.e., 30 results when the contractor comes to realize
days) period of time. If no response is that the only suitable resolution available is
received, the claimant, aided by counsel, may that prescribed in the contract documents. If
decide to file a notice of deemed or construc- the contractor has made a decision not to file
tive denial of the claim. In this fashion, the a claim in accordance with the terms of the
claimant has documented its reasonable contract, its rights and remedies may have
assumption that the reviewing party has con- been irretrievably waived and thus, its ability
structively denied the claim. If this course of to be equitably compensated may have
action is taken, it may trigger contract terms passed by.
and other issues may arise, such as having to
The proper and timely preparation and sub-
constructively accelerate the work to over-
mission of a claim can be viewed simply as
come any claimed excusable delay.
prudent management. A claim is an avenue
The concept of a “deemed denial” of a con- to receive a remedy that is provided for in
tractor’s claim is principally a matter of fed- most contracts. The filing of a claim is not,
eral contracts, such those executed by the on its face, an adversarial act. It is a business
General Services Administration or the U.S. decision that is recognized as the contractor’s
Army Corps of Engineers. That does not right under most contracts. It may, in fact, be
mean that if a non-federal owner or prime a business obligation to ensure fair and equi-
contractor refuses to acknowledge a contrac- table payment for work performed over and
tor’s claim, the general concept of construc- above the base contract scope of work or
tive denial does not apply. However, the issue work performed in a most costly and unantic-
of “deemed denial” can be a complex legal ipated manner.
issue and may be based on the terms and
conditions of the contract, thus this matter is
Prepared by Paul L. Stynchcomb, CCM, PSP, CFCC of
the subject of careful consideration by experi-
Vero Construction Consultants Corp. and Charles
enced construction counsel. Choyce, PSP, PMP, CFCC of FTI Consulting with peer
review performed by: Robert Beck, President of John W.
Danforth Company; Michael R. Cables, Executive Vice
Conclusions President of Kinetics Systems, Inc.; James Durant, Presi-
dent and CEO of Trautman & Shreve; Richard Freeman,
A mechanical contractor should carefully
Vice President of Stromberg Metal Works; Matthew
assess all options when considering whether Hahr, Senior Vice President of Kirlin Mid-Atlantic, LLC;
or not to file a claim. However, the time Michael Loulakis, Esq., President/CEO of Capital Project
restrictions contained in many public and Strategies; Michael Mack, Executive Vice President of
John J. Kirlin, Inc.; and Adam Snavely, President and
private contracts do not allow the contractor CEO of The Poole & Kent Corporation.
significant latitude as to when a claim can be
filed, thus the contractor is normally forced
to make this decision promptly. Often, a con-
tractor decides not to file a claim believing

Management Methods Bulletin CO2 - 2011; replaces 1973 Bulletin No. 32 and 2005 versions. © 2016 MCAA. All rights reserved. 49
Change Orders

Integrated, Cooperative, and


Collaborative CPM Scheduling…
a Roadmap to Success
On the majority of larger and/or more com- CPM scheduling should be an inclusive,
plex construction projects, the prime con- cooperative and collaborative process on a
tractor and/or the owner’s construction construction project. The original sched-
manager (“prime/CM”) has the responsibil- ule—the “baseline CPM schedule”—should
ity to prepare a detailed, baseline critical reflect the knowledge and planning of all of
path method (“CPM”) schedule at the out- the major trade contractors. In simple
set of the project. At set intervals, usually terms, the baseline CPM schedule should, if
monthly, the prime/CM is required to followed, be the “roadmap to success” on a
update the accepted baseline schedule with construction project. For the development
progress. Most contract specifications also of a reliable and useful baseline schedule to
require that time impacts, known as time occur, it must be prepared by persons expe-
impact analyses (“TIAs”) or Fragnet analy- rienced in the construction industry and
ses, be inserted into the updated schedules with training or extensive experience in the
to identify and quantify potential delaying development of CPM schedules. Such indi-
events. The subject of TIAs is addressed in a viduals may also have had training in the
separate chapter within this publication common scheduling software systems uti-
entitled “Time Impact Analysis—Measuring lized in the industry. However, the key ele-
Project Delay.” As explained in that chapter, ments in the development of useful and
updates to the accepted baseline CPM accurate schedules are the knowledge of the
schedule must contain properly developed construction process in general, an under-
TIAs, otherwise the forecasts contained in standing of the particular details of the
those schedule updates may be seriously project being scheduled and significant
flawed. This chapter is devoted to the devel- experience with the application of critical
opment of the baseline CPM schedule. path methodologies.
Common scheduling terms utilized in this
Although contract specifications vary from
chapter are defined in the chapter cited
project to project, usually the mechanical
above and, in most cases, will not be
and/or plumbing subcontractor (“M/P sub-
defined herein.
contractor”) is required either to provide

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 51


Change Orders

the prime/CM with the M/P subcontractor’s What is a Baseline CPM


proposed schedule (sometimes called a
Schedule?
“sub-network”), or the M/P subcontractor is
A “baseline CPM schedule” is a reasonably
required to participate in schedule develop-
detailed2 project schedule prepared using crit-
ment meetings with the prime/CM.1
ical path method technology and formulae
Notwithstanding the method of informa-
called the forward and backward pass, usually
tion delivery by the M/P subcontractor to
input into a software system such as Primav-
the prime/CM, this step should be taken
era® or Microsoft® Project® that computes
with the utmost attention to detail and
the critical path or paths within the schedule
accuracy. The project CPM schedule (the
network and identifies the non-critical activi-
baseline schedule and the updates) is usu-
ties. The baseline CPM schedule sets forth the
ally considered a contract document of
M/P subcontractor’s (as well as the other con-
record, and as such, deserves a significant
tractors’) base contract activities, the esti-
amount of focused input to ensure that the
mated durations for those activities, the logi-
prime/CM is properly advised as to the M/P
cal restraints between the activities (i.e., CPM
subcontractor’s individual activities,
schedule logic ties) and which activities con-
sequence, activity durations and crew plan-
trol the project milestone and/or completion
ning on the project. Before any schedule
date(s). These logic restraints set forth the
development meeting with the prime/CM,
M/P subcontractor’s sequence of performance
the M/P subcontractor should be thor-
in terms of its crew flow and the order in
oughly knowledgeable regarding the project
which its work activities will be performed.
to be constructed, including the contract
The baseline CPM schedule depicts the origi-
terms, drawings, specifications and the M/P
nal intent of the construction team to meet
subcontractor’s own labor plan. To the
the various requirements of the contract that
fullest extent possible, the M/P subcontrac-
includes achieving completion dates set forth
tor should develop an understanding of the
in the contract. As such, the baseline CPM
prime/CM’s contractual requirements for
schedule on a construction project should
schedule development, submissions, and
reflect an efficient and profitable plan to
updating. Knowing the prime/CM’s contrac-
achieve the contract requirements, and reflect
tual obligations to the owner regarding the
an orderly and efficient sequence of events.
CPM schedule can be very valuable when
negotiating with the prime/CM regarding Some contract specifications require that the
having access to the complete schedule and CPM schedule be “resource loaded,” which
its updates. means that the contractors must provide the
number of trade workers per activity that will

1 2
The timing and method of schedule information shar- Often times, the contract specifications set forth the
ing between the M/P subcontractor and the prime/CM level of scheduling detail that is required on the project
may vary depending upon the contractual delivery and may also provide a maximum duration that can be
method. However, with both the design-build and the assigned to a schedule activity. It is important for the
design-bid-build delivery methods, the baseline CPM M/P subcontractor to obtain, and to review, the
schedule is of the utmost importance, as is the input of prime/CM’s contractual scheduling requirements before
the M/P subcontractor into the scheduling process. finalizing the baseline CPM schedule.

52 Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved.


Change Orders

be required to perform the base contract strates the identification of an error in the
work. Other contract specifications may estimate. In cases where the M/P subcontrac-
require that the CPM schedule be “cost tor encounters a labor over-run on the proj-
loaded,” which means that the M/P subcon- ect, it may be difficult to recover those labor
tractor’s total contract billing value must be losses that are comprised of the difference
divided between the various schedule activi- between the labor hours in the M/P subcon-
ties so that the total of the individual activity tractor’s estimate and the labor hours con-
billing values equals the M/P subcontractor’s tained in the M/P subcontractor’s baseline
total contract amount. CPM schedule, even if an inadvertent error is
claimed. Always ensure that the labor hours
When the contract specifications require that
shown in the baseline schedule never exceed
the M/P subcontractor “resource load” the
the original estimate or job plan, unless an
baseline schedule, great care should be taken
admitted estimating error has occurred on
to ensure that the resulting crew curves for
the part of the M/P subcontractor.
both the early and late dates (i.e., curves cre-
ated by the scheduling software that present A CPM schedule has two sets of calculated
the resource data as number of workers, or dates: earliest start and finish dates and latest
labor hours, on the y axis depicted over time start and finish dates. The mathematical differ-
on an x axis) calculated in the CPM schedule ence between the earliest and latest dates is
never represent more labor hours than were known as “total float.” Total float is the num-
present in the M/P subcontractor’s original ber of days that a particular activity within a
estimate or job plan. Some specifications even CPM schedule can slip in time without impact-
require the M/P subcontractor to differentiate ing an interim milestone date(s) and/or a final
between “fitters,” “welders,” “plumbers,” project completion date(s). Activities that have
and/or “sheet metal workers” within each zero total float are said to be on the “critical
erection activity in the baseline CPM sched- path.” If a critical path (zero total float) activity
ule. The M/P subcontractor should use great is delayed by even a day, it has a day-for-day
care to ensure that each trade’s baseline CPM impact on finish milestones or final comple-
schedule planned labor hours never exceed tion dates. In fact, if collateral impacts are pres-
the hours for each trade that was carried in ent, a one-day delay to a critical path activity
the M/P subcontractor’s estimate or job plan. may result in more than a day’s delay to the
project’s end date. It is often the case that the
If the M/P subcontractor includes more labor
M/P subcontractor does not, or is not permit-
hours (expressed in hours or in the number
ted to, link the activities in the baseline CPM
of craft persons by activity) in the baseline
schedule to demonstrate the M/P subcontrac-
CPM schedule than were contained in the
tor’s planned crew flow and crew restraints.
original estimate or job plan, this condition is
When this is the case, the schedule may be
usually the result of an inadvertent data
invalid due to “false float,” which is a calcula-
input error or carelessness on the part of the
tion of float that is erroneous because planned
M/P subcontractor in providing the resource
crew flow (i.e., proper activity sequencing) is
data. In some cases, reflecting more labor
not considered in the CPM schedule’s mathe-
hours in the schedule than are contained in
matical analysis.
the M/P subcontractor’s estimate demon-

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 53


Change Orders

Because this is a frequently committed error, on an impacted project, may be rendered


the M/P subcontractor must ensure that the unreliable and not useful in a delay impact
number of craft workers shown within the analysis.
baseline CPM schedule never exceeds the
In order to provide accurate and reliable input
expected peak curves for both the early start
to the prime/CM, the M/P subcontractor
dates and the late start dates. The M/P subcon-
should thoroughly review the contract specifi-
tractor should also focus attention on resource
cations, drawings, and its own bid and plan-
loading specialty activities such as welding or
ning documents to gain a detailed under-
other activities that use limited availability
standing regarding the scope of work, time of
skills or equipment to ensure that the individ-
performance, interim milestones (if any),
ual resource usage on an activity-by-activity
planned crew sizes, and crew flow and other
basis does not exceed the estimated quantities.
requirements contained in the contract. For
On many projects where the M/P subcontrac- instance, the M/P subcontractor may be
tor does not input, or is not allowed by the required to provide early energization of
prime/CM to input, crew restraints into the HVAC equipment for acclimatization of spaces
baseline CPM schedule logic, the late start in the building, or other special requirements
date resource curve may far exceed the num- that are usually defined in the contract docu-
ber of craft persons that were planned to be ments. Such special milestones or other con-
utilized on the project because of “false siderations (e.g., delivery of owner-furnished
float.” Examples of crew restraints will be furniture, fixtures, and equipment) should be
provided later in this chapter. included in the schedule logic and thereby,
become a part of the M/P subcontractor’s
The baseline CPM schedule is, or should be, a
baseline scheduling considerations.
reflection as to how the project is planned to
be constructed. That plan includes proper Additionally, the M/P subcontractor should
resource allocations that may be input into the carefully consider the timing of its construc-
scheduling software. This baseline CPM sched- tion activities with regard to the potential
ule may be used to compare the construction effects of weather. In certain areas of the
team’s planned performance with actual per- country, historical weather events such as
formance by inputting actual start and finish severe winter conditions or seasons of intense
dates, or actual start dates along with progress heat or heavy rains may adversely affect the
information for active activities, thus it is productivity of the crews and cause delay. To
imperative that the baseline schedule reflect, the extent possible, the M/P subcontractor’s
to the fullest extent possible, the most eco- schedule sequencing should take those histor-
nomical and realistic model of how the project ical (potential) climatological conditions into
is being planned to be constructed. Once sub- account. In some cases, these historical
mitted and approved or accepted by an owner weather seasons may require the construction
or its authorized representatives, it is difficult team to take special actions, such as installing
to go back in time to revise a defectively pre- temporary building enclosures or temporary
pared baseline CPM schedule. Further, compar- roof systems (i.e., temporary building dry-in
isons between a defectively prepared baseline as a predecessor to water sensitive activities).
CPM schedule and future updates, particularly These considerations should be made when

54 Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved.


Change Orders

the baseline schedule is being prepared. The This is certainly not an exhaustive list of
M/P subcontractor should also evaluate when important scheduling considerations. On some
the work of other trades is planned to occur, projects, computerized BIM is not a require-
such as the milestone for providing perma- ment, or commissioning may be a minimal
nent power to the project. This may be partic- effort, or may be provided by a party other
ularly important to the commissioning work than the M/P subcontractor. However, on most
that may fall under the M/P subcontractor’s larger and more complex projects, the M/P sub-
scope of work. Further, the provision of tem- contractor may have some, or a significant
porary hoisting and crew lifting equipment amount of, liability as to prefabrication BIM
should be included in the baseline schedule. activities and final commissioning activities.
Depending on the type of contract delivery Furthermore, there may be many project-spe-
method, the M/P subcontractor should also cific considerations, such as owner-furnished
ensure that the baseline schedule includes equipment and fixtures and training of the
milestone dates by which decisions are made owner’s personnel that occur near the comple-
as to the acceptance or rejection of bid alter- tion of the project and should be included in
nates and the receipt of 100% complete con- the project CPM schedule as discrete activities.
struction documents.
Virtually all construction projects require care-
At a minimum, there are three areas of spe- ful consideration of crew flow and crew size
cial consideration that, on most larger proj- restraints that should be included in the base-
ects, require a detailed analysis by the M/P line CPM schedule. The M/P subcontractor’s
subcontractor when preparing the baseline crew flow should be demonstrated by actual
CPM schedule or when participating in logic ties or restraints input into the baseline
schedule development meetings. These are: CPM schedule. The resulting crew loading
curves for both the early and late dates should
1. Detailed logic reflecting the requirements
be analyzed to ensure that the planned crew
and timing of Building Information
sizes meet the M/P subcontractor’s reasonable
Modeling (“BIM”) and its relationship to
expectations and labor planning.
piping and sheet metal prefabrication
activities that are, in most specifications, While some M/P subcontractors may not be
successor activities to the approval of the responsible for performing the commissioning
coordinated drawings. activities, on many projects the detailed
requirements for commissioning fall within the
2. Consideration of logic ties that reflect the
contractual responsibility of the M/P subcon-
M/P subcontractor’s planned crew flow,
tractor. In such cases, the M/P subcontractor
crew size restraints, and general sequenc-
should ensure that an accurate and properly
ing of the M/P subcontractor’s activities.
sequenced commissioning logic chain be pres-
3. Detailed logic reflecting the requirements ent at the outset of the project, in the baseline
for building commissioning, including CPM schedule. Even when commissioning is
identification of milestone dates for the provided by another party, the commissioning
involvement of the owner’s third party activities should be included in the baseline
commissioning agent in order to forecast CPM schedule by the prime/CM so that the
accurate commissioning events. timing of the performance of the predecessor

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 55


Change Orders

mechanical activities will have realistic fore- and prefabrication of the mechanical and
casted completion dates and total float values. plumbing systems. Whether conventional
drafted coordination drawings or computer-
The three important topics to be considered
ized BIM, these crucial activities must be
in the baseline schedule, in addition to the
included in the development of the baseline
actual erection activities, are described in
CPM schedule.
more detail below.
Frequently, the contract specifications or the
subcontract documents set forth the require-
Defining the BIM (or ment that the M/P subcontractor receive
Conventionally Drafted) approval or acceptance of the coordinated
Coordination Process and the drawings by some party (e.g., the owner’s engi-
Dependent Prefabrication neer of record, the construction manager, or
another party) prior to commencing prefabrica-
Activities in the Baseline CPM
tion activities, such as the prefabrication of pip-
Schedule ing systems. Because the approval or accept-
In today’s prefabrication and computer model- ance of fully coordinated drawings is usually
ing environment, many project specifications required prior to the M/P subcontractor com-
contain a requirement for the M/P subcontrac- mencing prefabrication work, including these
tor to participate in, or take the lead in, the prefabrication activities in the baseline CPM
coordination process, whether achieved by schedule is essential. The details of this process
way of BIM or conventional drafting methods. should be agreed upon at an early stage in the
When BIM is required and is undertaken as a project planning, such as at the kick-off meet-
collaborative process, developing a three di- ing or at the time when the flow and sequence
mensional model of the mechanical, plumb- of the BIM or manually drafted coordination
ing, sheet metal, electrical, fire protection, and process is established by the construction team.
other key systems in spaces such as ceiling ple- Omitting the prefabrication activities that are
nums and interstitial spaces can solve spatial the logical successors of the acceptance of the
conflicts prior to the commencement of fabri- coordinated drawings will result in false float
cation and can reduce construction delays and within the schedule and may render the base-
costs. Even if coordination on a project does line CPM schedule inaccurate and unreliable.
not include the utilization of a computerized
BIM product, and instead utilizes conventional The M/P subcontractor should carefully review
drafted coordination drawings, the need for a all coordination (by way of BIM or other
collaborative process remains an essential ele- methodologies) requirements in the contract
ment of a productive and successful planning documents prior to commencing the prepara-
process. Moreover, the timing of both BIM and tion of the baseline CPM schedule. This is a
conventionally drafted coordination drawings crucial step in the schedule development pro-
is critical to success on the project. The various cess because the coordination logic (i.e., the
coordination methods in use today must be BIM activities, activity durations and logic
commenced early enough in the project to ties), coupled with the M/P subcontractor’s
allow for timely pre-planning, procurement, prefabrication activities, will, in most cases,
establish the M/P subcontractor’s critical path

56 Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved.


Change Orders

in the baseline CPM schedule, defined as the little or no usable information within the oth-
longest chain of interlinked activities which, if erwise reasonably detailed baseline CPM
delayed by even a day, will equivalently delay schedule. Such conditions should be avoided
either the project end date, or at least the end in the planning process.
date of the M/P subcontractor’s work.3 All too
Based on the contract documents, which vary
often, the BIM or other coordination activities,
from project to project, a baseline BIM logic
with their estimated durations and logic ties to
chain for a discrete portion (i.e., Area A, Lev-
approvals and then the commencement of
els 1–4) of a hypothetical project could
prefabrication activities, are totally omitted
appear as shown in Figure 1.
from the prime/CM’s baseline schedule, or in
other cases, the coordination scope of work is In this hypothetical example, the baseline
scheduled in such a summary level that it adds CPM schedule should contain a milestone
activity for production of the CAD back-
grounds provided by the owner’s design team
3
The M/P subcontractor’s critical path (i.e., its longest to the M/P subcontractor. This milestone
connected chain of activities) may be different from that activity commences a chain of events that
of the prime/CM. In some schedules, the M/P subcontrac-
tor’s work is shown to finish earlier than the prime/CM’s
includes the development of the first set of
work, and if the M/P subcontractor is delayed from its background drawings that contain base con-
planned finish date, it may be possible to recover delay tract activities such as plumbing piping, duct-
costs. The theory that a mechanical subcontractor can work, mechanical piping, electrical activities,
recover its delay costs (i.e., “delay” as between the
mechanical subcontractor’s planned finish date and its and the fire sprinkler work within discrete
actual finish date) on a construction project, even when areas of the project’s ceiling plenums, as
the prime contractor completed on time, was successfully defined by floor levels and/or physical areas.
litigated in the case of E.R. Mitchell Construction Co., Appel-
lant, v. Richard J. Danzig, Secretary of the Navy, Appellee, 175 On particularly large or complex projects, it
F.3d 1369 (Fed. Cir. 1999). may be desirable to add detail to the coordina-
Figure 1

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 57


Change Orders

tion (computerized BIM or drafted) logic sub- and receive formal approval from the designer
network. For instance, in the case of projects of record for any changes in system routing
utilizing BIM, it may be advisable to add dis- and/or sizing that resulted from the BIM
crete activities for the receipt of BIM drawings process.
provided by other trade contractors, for the
After approval, the prefabrication of the pip-
clash detection and correction steps, and more
ing systems can commence. This is a crucial
detailed activities describing the engineer of
logic tie that will ensure that the schedule
record’s review and acceptance of the BIM
will not depict the commencement of pipe
drawings prior to the commencement of pre-
fabrication until the authorized party (usually
fabrication activities. In most cases, the level of
the designer of record) approves the coordi-
BIM sub-network detail will be dictated by the
nated drawings. It is very important to prop-
contract specifications and the complexity of
erly depict the coordination logic, whether by
the project. If the M/P subcontractor suspects
BIM or other processes, with reasonable dura-
that the project may suffer from an incomplete
tions, in the baseline CPM schedule.
design or defective design, it may behoove the
M/P subcontractor to add detail to the baseline
BIM schedule sub-network so that added BIM
work causing impacts to the schedule can be 4
Copyright 2013 by the MCAA, the Mechanical Con-
more easily identified. On projects that are not tracting Education and Research Foundation, NECA, the
fully designed at the time of contract execu- New Horizons Foundation, and SMACNA.
tion, the milestone date for the receipt by the
M/P subcontractor of 100% complete construc-
tion documents should appear in the baseline
CPM schedule. In all cases, the BIM sub-net-
work must be inserted into the master baseline
CPM schedule and not be analyzed apart from
the overall CPM schedule.
Often the M/P subcontractor is the contractu-
ally responsible party to incorporate clash cor-
rections identified by a host of other subcon-
tractors (e.g., electrical, sheet metal, fire
protection) into a final set of coordinated BIM
drawings. Once clash free, the BIM drawing
files may be required to be approved by the
engineer of record. This is an essential activity
in the schedule since any BIM coordination
efforts that change the locations or sizes of pip-
ing, duct work, electrical and similar systems
must be reviewed and approved by the de-
signer of record. In order to reduce liability
risks, the M/P subcontractor should request

58 Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved.


Change Orders

The M/P subcontractor may wish to reference of normal and expected coordination cited in
an industry publication in the preparation of Section 5.1 of the referenced publication)
the detailed BIM logic in the baseline schedule, extend beyond the expected norm and thus
entitled Achieving Spatial Coordination Through take longer than reasonably planned, the
BIM.4 This publication, pictured above, was schedule slippage and critical path delay, if
prepared by representatives of the MCAA, any, can be demonstrated.
SMACNA and NECA, and is available through
the named associations’ administrative offices.
Mechanical and/or Plumbing
With regard to project scheduling, particular Crew Restraints in the
attention should be paid to Section 4.3,
“Schedules,” and Section 5.1, “Establishing
Baseline CPM Schedule
Norms for the Project,” in the above refer- On the vast majority of construction projects,
enced publication. The former section refers the M/P subcontractor has not estimated, or
to important considerations when preparing planned upon, providing unlimited resources.
the BIM activities and logic ties within the As crew sizes are increased beyond a reason-
baseline CPM schedule. The latter section con- able plan, the M/P subcontractor must pro-
tains the definition of normal and expected vide added tools, equipment and supervision,
coordination for a specialty contractor, which which can result in significant and unantici-
definition has also been published by the pated added costs. Therefore, the M/P sub-
National Institute of Building Sciences build- contractor must ensure, to the fullest extent
ingSMART alliance™ in the Journal of Building permitted by the prime/CM, that reasonable
Information Modeling, Fall 2011 edition. M/P and supportable crew restraints are present in
subcontractors should carefully review and the baseline CPM schedule. The absence of
consistently apply the published guidelines reasonable and supportable crew restraints in
regarding what can be reasonably expected by the baseline schedule will, in most instances,
the contracting team when a BIM require- result in false float and may render the entire
ment is present on a construction project. baseline schedule unreliable and fatally
When these reasonable and published expec- flawed.
tations are not met due to design issues, and There are three principal reasons why M/P sub-
the results are added cost and time of per- contractor’s crew restraints (i.e., actual logic ties
formance, the M/P subcontractor should eval- inserted between activities in the CPM sched-
uate the damage and, if appropriate, seek an ule database) are omitted in the prime/CM’s
equitable adjustment to the subcontract. baseline CPM schedule. These are: 1) the M/P
Having detailed BIM coordination logic in subcontractor’s lack of understanding regarding
the baseline CPM schedule will facilitate the importance of installing crew restraints into
more accurate and meaningful comparisons the baseline schedule; 2) the M/P subcontrac-
between the baseline plan and the actual exe- tor’s lack of resource planning that would allow
cution of the BIM process. Should the clash for the definition of crew flows in the CPM
identification and correction process (with schedule by way of logic ties or restraints; and
three such clash detection and correction 3) the prime/CM’s refusal to allow the M/P sub-
steps expected, consistent with the definition contractor to insert crew restraints into the

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 59


Change Orders

schedule by way of logic ties or restraints. In on construction law, however the prime/CM’s
most instances, the M/P subcontractor must duty to cooperate and not to unreasonably
specifically request, preferably in writing, that hinder or financially harm a subcontractor is
the prime/CM permit crew restraints to be in- well established. To the fullest extent possi-
serted into the baseline CPM schedule. Also, in ble, the M/P subcontractor should assert its
most cases, the prime/CM will not know the right, and duty, to insert appropriate crew
M/P subcontractor’s crew flow or restraints.5 restraints into the baseline CPM schedule in
This information must come from the M/P order to assist in the preparation of a reliable
subcontractor and the preparation of this vital and usable schedule document (i.e., one that
information can only result from a reasonable does not contain false float due to the
and well thought out labor plan and crew absence of proper crew restraints).
flow analysis.
Assume the following in this hypothetical
At times, the prime/CM may instruct the M/P example: 1) a cast in place concrete structure
subcontractor that crew restraints in the CPM on a large high rise medical research building;
schedule are unnecessary because the M/P 2) a sizable quantity of specialty stainless steel
subcontractor’s form of contact requires the welded pharmaceutical grade piping; 3) a lim-
M/P subcontractor to supply whatever labor itation on the number of qualified stainless
may be required to meet the prime/CM’s steel welders and orbital welding equipment;
CPM schedule. This chapter is not a treatise 4) five physical “Areas” are designated per
floor slab, A through E; and 5) once a floor
slab is placed and stripped, all mechanical
5
A schedule “restraint” can include by examples: (i) piping mains can (by the laws of physics and
physical restraints such as having site areas, mechanical assuming unlimited resource availability)
rooms, or slab surfaces available; (ii) crew or labor commence at the same time.
restraints such that the schedule will not depict early or
late date crew curves in excess of the M/P subcontractor’s The schedule example below (Figure 2) was
estimated labor plan; (iii) equipment restraints such as
prepared without any crew flow or crew
the planned number of welding machines, cranes, or
other major equipment items; (iv) BIM and prefabrication restraint logic. As a result of the lack of crew
restraints to the commencement of prefabrication activi- restraints, the stacking of critical stainless pipe
ties; and (v) procurement restraints from the delivery of erection and welding activities is improperly
material and/or equipment to the installation of those
items as shown in the construction schedule.
depicted as the M/P subcontractor’s baseline

Figure 2

60 Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved.


Change Orders

plan. In this hypothetical example, the num- rate crew curves and float computations. If, in
ber of qualified orbital stainless steel welders, the Figure 2 example above, the M/P subcon-
and orbital welding machines, is very limited. tractor receives a change in scope that elon-
Without any consideration for the planned gates activity 20, “Install Pipe Mains &
crew flow, the schedule allows for the concur- Branches Area A” by 8 days, the effect of this
rent installation of the stainless steel piping in change does not ripple through to the other
each area by floor. If the M/P subcontractor is mechanical piping activities that will utilize
unable to staff the floor with five welding this scarce welding resource. However, in the
crews and five orbital welding machines, the example below, if activity 20 is elongated due
schedule will exhibit false float and a false to a change, or for that matter, any reason
planned crew curve. including the M/P subcontractor’s own pro-
duction issues, those delay effects will be
However, if the M/P subcontractor actually has
shown to ripple through all dependent activi-
only one planned stainless steel orbital weld-
ties. Thus, the proper effect of schedule
ing crew and one welding machine and inputs
impacts will be depicted much more accu-
finish to start crew restraints in the baseline
rately throughout the CPM schedule network.
schedule to demonstrate that planned limita-
Moreover, the resulting planned crew curve
tion, the baseline schedule will show a remark-
that results in the baseline schedule will accu-
ably different crew curve, expected early and
rately depict the M/P subcontractor’s plan to
late finish dates and float values. While the
install the base contract scope of work.
example above may be physically possible, it is
not reflective of how the M/P subcontractor The logic ties between the various M/P subcon-
plans to execute its contract work scope. More- tractor’s activities are finish to start logic ties
over, if the M/P subcontractor only planned that have been inserted into the baseline CPM
on utilizing one stainless steel welding crew, schedule. Such logic ties must be provided to
Figure 2 represents improper crew stacking the prime/CM by the M/P subcontractor. The
that was not contemplated by the M/P sub- absence of proper crew restraints in the base-
contractor in its original estimate. line CPM schedule will, in virtually all cases,
result in a flawed and unreliable baseline CPM
The example (Figure 3) depicting the M/P sub-
schedule. In cases where the M/P subcontractor
contractor’s plan to have only one specialty
is prevented from inputting proper crew
stainless steel welding crew, provides for accu-
Figure 3

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 61


Change Orders

restraint logic ties in the baseline schedule, the ceilings and doors installed), and by the limi-
M/P subcontractor should notify the prime/ tation of specialized commissioning techni-
CM, in writing, that the schedule does not cians (i.e., TAB and CX crew restraints). If the
reflect the M/P subcontractor’s plan to accom- M/P subcontractor is not familiar with per-
plish the work and that the resulting schedule forming TAB and CX tasks on a complex proj-
is unacceptable to the M/P subcontractor. ect, the technical representatives who will
actually perform the TAB and CX tasks should
be engaged early in the planning and schedul-
Test & Air Balance (“TAB”) ing process so that the baseline CPM schedule
and Commissioning (“CX”) in will accurately reflect the level of effort that
the Baseline CPM Schedule will be required to complete the project.
Many construction contracts require the M/P As can be seen in the summary flow chart (Fig-
subcontractor to fully commission the project. ure 4), the general TAB and CX may, depend-
In such cases, even if the M/P subcontractor ing on the specifications and type of systems,
issues a subcontract to a separate commission- overlap in time. However, by area of a build-
ing agent or contractor, the scheduling of the ing, there is generally a finish to start relation-
commissioning process still falls upon the M/P ship between the TAB and CX activities. As
subcontractor. In many baseline CPM sched- noted above, the TAB and CX activities are
ules, the M/P subcontractor is not asked to pro- logically preceded by such activities as perma-
vide detailed TAB and CX input to the nent power on line, building envelope com-
prime/CM during the development of the base- plete and certain interior finishes in place (e.g.,
line CPM schedule. This may lead to improp- doors, ceiling system, and windows). These
erly shortened CX schedule sub-networks that logic restraints must be present in the baseline
result in delays at the conclusion of the project CPM schedule. The absence of the proper logic
because the TAB and CX work was not prop- restraints from the work of other trades, such
erly depicted in the schedule (e.g., by way of as the availability of permanent power, may
improperly short activity durations and/or cause the schedule updates to incorrectly iden-
incorrect and missing logic ties). tify the M/P subcontractor as the cause of
The first step in the creation of an accurate commissioning delays, when, in fact, such
and reliable TAB and CX sub-network that
will be inserted into the prime/CM’s baseline
Figure 4
CPM schedule is to read the technical provi-
sions of the contract to ascertain what level of
TAB and CX is required on the project. On
some types of projects, CX is little more than
traditional startup operations. However, on
many projects, TAB and CX work are a com-
plex, interrelated series of activities that are
driven both by the completion of building
features and systems (e.g., permanent power
available, glass and glazing complete, finished

62 Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved.


Change Orders

delay may be the result of the failure of other difficulty factor (e.g., taking into consideration
trades to timely perform their activities. height above the finished floor), and crews to
be assigned must all be evaluated when the
When developing the baseline CPM sched-
activity duration is estimated. Additional con-
ule, particularly for a complex process
siderations include the following.
mechanical and electrical project such as a
manufacturing or research facility, a much
more detailed TAB and CX activity sub-net- Developing the M/P Subcontractor’s
work will be required, potentially comprised Activity Descriptions
of many activities. It is essential that a rea- Carefully defining the activity’s description,
sonably complete TAB and CX schedule be which allows the project team to know what
prepared and included in the baseline sched- work is contained within the CPM schedule
ule. Even if this sub-net has to be refined or activity, is a crucial step in preparing a useable
revised as the TAB and CX specialists and useful baseline CPM schedule. Proper
become engaged in the project, having rea- activity descriptions, in addition to a definition
sonable logic restraints and time slots for of scope, may include locations by floor, area,
the TAB and CX activities are very impor- or phase that further define the location of the
tant to the production of a reasonable base- work. For erection activities, the M/P subcon-
line schedule. Time spent at the outset of a tractor should be able to reference the activity
project to properly plan and sequence the description in the CPM schedule and then
TAB and CX requirements, and to incorpo- locate the scope of work on the contract docu-
rate those sub-networks into the baseline ments. By way of example, an activity descrip-
CPM schedule, will result in a much more tion should include system type and location,
reliable project management tool. The such as: “Install CHWS/R Mains from CL 1 –
absence of accurate TAB and CX activity 10 Level 4, Area C.” This specific description
identification, durations and logic ties will includes the system type (CHWS/R) and the
result in an inaccurate and unreliable base- specific location of the work by floor and col-
line CPM schedule. umn lines. It is also a good practice to limit
activity descriptions, and the resulting scopes
or work, to one primary trade. Thus, mechani-
Other Important Baseline cal piping activities should be separated from
Schedule Considerations plumbing activities, and from sheet metal duct
In addition to the three areas of focus described installation. Developing specific activity de-
above, the M/P subcontractor must evaluate scriptions allows the M/P subcontractor to bet-
the activity descriptions, estimated durations ter estimate the activity’s planned duration and
and logic ties that comprise the flow of the crew requirements in the baseline CPM sched-
work under the subcontract. Duration esti- ule and will also aide in the progress reporting
mates should be derived from the relationship in the subsequent schedule updates. As a guide-
between the quantity of work, the number of line, durations for work activities6 should fall in
craft persons assigned to the activity and an
estimated production rate. The linear feet of
piping, number and type of joints, inherent 6
Shop drawing preparation and procurement activities
may have significantly longer durations.

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 63


Change Orders

a range of between 3 and 22 work days, but In a CPM schedule, there are four possible
may be further defined by terms of the con- logic ties: finish to start (“F/S”), start to start
tract specifications. (“S/S”), finish to finish (“F/F”) and start to
finish (“S/F”). Within the vast majority of
In many cases in which the M/P subcontractor
construction schedules, all logic relation-
has not been involved with the development
ships in the CPM schedule are defined by
of the baseline CPM schedule, activities such as
the first three types; S/F logic ties are very
“MEP Ceiling Rough-in” or similarly vague
seldom used in construction CPM schedules.
activities, frequently appear in the schedule.
“MEP” refers to “mechanical, electrical and F/S logic ties define a relationship wherein
plumbing” system rough-in work. Such de- the preceding activity must finish before its
scriptions result in forecasting errors in the successor can start. S/S logic ties define a
baseline CPM schedule. In this common exam- relationship wherein the preceding activity
ple, on most projects, the mechanical piping, must start on a date on or before its succes-
ductwork, plumbing and electrical systems are sor (dependent) activity can start. F/F logic
not installed in the ceiling plenums at the ties define a relationship wherein the pre-
same time and concurrently in the same build- ceding activity must finish on a date on or
ing area. These sorts of “short cut” activities do before its successor activity can finish. In
not properly define the scope of work (in this addition to these three basic types of logic
example, potentially four different trades) ties or restraints, the scheduler can impose
required by the contact drawings. “lead” and “lag” durations, commonly
referred to simply as “lag durations.”7 These
lag durations further define the S/S and/or
Open Starts and Ends (“Dangles”)
F/F overlaps between the predecessor and
Within the CPM Schedule Network
successor activities and, like activity dura-
Some schedulers improperly prepare a baseline
tions, are estimated durations of overlap.8
CPM schedule as if it were a loosely tied bar
chart. Usually, in such circumstances, the
scheduler ties the starts of activities but fails to
tie the finishes. This represents incomplete
7
logic within the CPM schedule and results in “Lead” durations are placed on S/S relationships and
“lags” are placed on F/F relationships. It is generally
unreliable and inaccurate schedules. It is a basic improper to place a lag duration on a F/S relationship.
tenet of CPM scheduling that there can be only Such cases usually represent the scheduler’s attempt to
two activities that either have no predecessors define, for example, a concrete curing duration or some
or successors. Those two generic activities are other place holder. In virtually every case, a F/S relation-
ship with a lag implies that the scheduler has failed to
“Notice to Proceed” that commences the proj- define the event, such as procurement of an item or con-
ect and “Project Complete” that denotes the crete curing, that could better be defined as a discrete
final finish of the contract work. Other than activity within the CPM schedule.
the activities that denote the commencement 8
Another derivation of the common lag is called a neg-
of the overall project and the completion of ative lag and is allowed by certain scheduling software
systems. The use of negative lags to define activity over-
the overall project (notwithstanding what the
laps is discouraged since lead durations on S/S relation-
activities are called by the scheduler), with very ships may be different from lag durations on F/F rela-
few exceptions, all other activities must have tionships, and these lead and lag durations affect total
logic ties at the start and end of the activity. float in the CPM schedule.

64 Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved.


Change Orders

The three most utilized logic ties appear impacting event, it may be possible for the
graphically as follows: pipe mains to finish later, or in some cases sig-
nificantly later, than the branch piping that
Figure 5
connects to the mains. Also, unless a separate
logic tie is introduced into the schedule, the
pipe main installation activity would be an
“end dangle,” also called an open end. If the
pipe main installation activity is not tied from
its finish to another logical activity, such as to
the finish of the branch piping in the same
area, then the finish float value of the pipe
main activity will be unrealistic.
The omission of a F/F logic tie in the presence
of a S/S logic tie between two related activi-
ties is the most frequently committed techni-
cal error in CPM scheduling. The M/P sub-
contractor should, to the fullest extent
In the examples above, the three most com-
possible, review the baseline schedule to
mon CPM scheduling restraints are depicted.
ensure that complete logic is depicted, as
In the top graphic, the pipe mains must be
described above. The absence of proper and
completed before the branch piping can com-
complete logic ties will most likely result in
mence (a finish to start relationship where
inaccurate schedules, and unreliable results
pipe mains are the predecessor and pipe
when the schedule is progressed and when
branches are the successor). In some cases,
TIAs are introduced into the schedules to
overlapping of work activities may be desir-
quantify the effects of changes in scope and
able and possible (by the laws of physics and
other delaying events.
based on available crews and equipment). In
the bottom graphic, a S/S logic tie with lag
duration and a F/F logic tie with lag duration Contractual Considerations
have been utilized to show that 8 work days Regarding the Baseline CPM
of the pipe main installation must be started Schedule for the M/P Subcontractor
before the branch piping can commence (a Some contracts require that the prime/CM
start to start relationship with an overlap, or receive from each major subcontractor a
lag duration, of 8 work days). When a S/S “sign off” signifying approval of the baseline
logic tie is utilized to define the relationship schedule so that this record of acceptance can
between the start dates of two activities, in be provided to the owner. The M/P subcon-
the vast majority of cases, a F/F logic tie must tractor should not sign off with an approval
also be utilized. The F/F logic tie prevents the of a baseline schedule until that schedule has
successor activity from finishing before the been thoroughly vetted by the M/P subcon-
predecessor activity completes, with an over- tractor. If the M/P subcontractor does not
lap in this example of 4 work days. If the F/F possess the technical scheduling experience
logic tie is omitted and in the presence of an to perform a detailed review of the project

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 65


Change Orders

baseline schedule, a construction scheduling sequencing agreement as described above, the


expert or consultant should be retained to M/P subcontractor must carefully review the
assist in the review process. From time to baseline CPM schedule to ensure that the logic
time, subcontracts between the prime/CM restraints that reflect this sort of agreement are
and the M/P subcontractor contain a “mutu- present, and correctly linked, in the schedule.
ally agreed-to schedule” clause. Such clauses This sort of restraint could appear as shown in
can be very helpful to the M/P subcontractor. the following example:
A “mutually agreed-to schedule” clause
Figure 6
means that the prime/CM expressly commits
to expend its best efforts to develop a CPM
schedule that is mutually agreed to with
other contractors, such as the M/P subcon-
tractor, as to activities, logic ties including
crew restraints, and performance dates. In the
absence of such a clause and during subcon-
tract negotiations, the M/P subcontractor
should negotiate with the prime/CM to have
this important requirement added to the final
contract documents. The requirement to pro-
duce a “mutually agreed-to schedule” is in
the best interests of the prime/CM and the
M/P subcontractor.
In this example, the CPM schedule logic
On some projects, agreements are made that
reflects the agreement that mechanical piping
affect the subcontract price and timing of cer-
mains must “lead” the start of the dependent
tain facets of the work. A very common exam-
non-fire rated wall erection by, in this example,
ple of such an agreement is a commitment by
10 work days, and that the dependent non-fire
the prime/CM to withhold the erection of
rated partitions must “lag” the finish of the
interior non-bearing or non-fire rated parti-
pipe mains by 5 work days. The lead and lag
tions (masonry and/or stud walls) until some
durations are very important and should be
measurable portion of the M/P subcontractor’s
reached by mutual agreement between the M/P
overhead piping mains and/or branch piping
subcontractor and the prime/CM. Obviously,
has been installed. It is a well-known fact in
the example above can be modified and
the industry that when interior walls are
applied to plumbing piping, sheet metal duct,
erected prior to the installation of overhead
electrical feeders, or other affected activities.
mechanical and plumbing piping systems, the
M/P subcontractor’s labor productivity suffers
a decline. When interior partitions are erected Shop Drawing, Engineer’s Review,
in a wholesale fashion before overhead piping and Procurement Activities in the
systems are commenced, the loss of labor pro- Baseline CPM Schedule
ductivity and time impacts can be substantial. In addition to installation activities, the M/P
Because of this fact, and in the presence of a subcontractor should consider incorporating

66 Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved.


Change Orders

its shop drawing or submittal package devel- ough review and comment session. The most
opment, the owner’s review of the shop effective means to accomplish a trade con-
drawing or submittal package and the pro- tractor’s review of a CPM schedule is for the
curement (manufacturing and delivery) activ- prime/CM to provide the native scheduling
ity that precedes the installation of equip- file to any of the subcontractors who have
ment or material items such as chillers, the means (internally or through a schedul-
boilers, air handling units, pipe supports, pip- ing consultant) to read a native schedule file.
ing, and piping appurtenances. These pro- Two of the most widely utilized scheduling
curement activities should commence in con- software systems, Primavera and Microsoft
junction with the notice to proceed, or in Project, export the complete schedule files in
conjunction with the appropriate BIM step in formats that can be opened and reviewed on
the coordination process. computers that utilize those software systems.
The activity durations for the preparation of Only by having the native schedule data file
the shop drawings or submittal package and can a complete and thorough review of the
the durations for the fabrication and delivery durations and logic be performed.9 While
of equipment and materials should be some prime/CMs have corporate policies that
derived from, or at least verified with, the prevent the field management staff from
vendors. To the extent that certain stages in sharing the native schedule files with the sub-
the BIM coordination process affect when contractors, this is counterproductive and
submittal preparation or procurement activi- does not represent a cooperative approach to
ties can occur, these logic restraints must be utilize one of the most important manage-
present in the baseline CPM schedule. Most ment tools on the project—namely the CPM
construction contracts provide a minimum schedule. It is unfortunate that many
duration that the contractor must allow to prime/CM’s take the position that the base-
the designers/engineers for review of the con- line CPM schedule and the subsequent
tractors’ shop drawings. These minimum updates, in their native forms, constitute pro-
durations should be included in the baseline prietary information that cannot be shared
schedule for the “review and approval” activ- with the prime/CM’s partners on the proj-
ity in the procurement logic. In some cases, ect—the various the trade contractors.
as with complex mechanical and plumbing
In cases where the M/P subcontractor has the
systems, a resubmittal and a re-review set of
capability to open and read the native sched-
activities should be considered within the
uling program files, and wishes to perform a
baseline schedule in order to provide a more
thorough schedule review on a project, a
realistic overall duration to obtain acceptance
request for the native scheduling files should
of such submittals.
be made, in writing, to the prime/CM. This
request letter should be positive and con-
Obtaining the Baseline CPM
Schedule from the Prime/CM
9
Obviously, it benefits every trade on a con- Although it may be claimed that a thorough logic
struction project when the prime/CM pro- review can be performed utilizing only a tabular report,
on larger projects, this is highly impractical and overly
vides the complete CPM schedule for a thor- burdensome and may, in fact, be an impossibility.

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 67


Change Orders

structive. In the cases where the prime/CM able. The M/P subcontractor should also
refuses to provide the native schedule files, request meetings to review the schedule and
and instead only provides static PDF “pic- to offer corrective suggestions so as to assist
tures” of the schedule or portions thereof,10 the prime/CM with the preparation of an
the M/P subcontractor should object in writ- acceptable baseline CPM schedule.
ing, asserting that the only means of fully
analyzing a CPM schedule, with its myriad of
Early Finish in the Baseline CPM
logic ties and potential lag values, is by use of
the native schedule files.
Schedule
The contract documents on most construc-
Unfortunately, when the prime/CM refuses tion projects contain an overall project com-
to provide to the M/P subcontractor the pletion date11 by which the work must be
native schedule files (assuming that there is substantially complete. Often, the contact
no contractual requirement for these files to contains a liquidated damages provision
be provided to the trade contractors), the whereby the owner may assess a stipulated
only non-litigious step the M/P subcontrac- amount for each calendar day the project is
tor can take is to document this action in inexcusably delayed beyond the contract
writing, taking strong but professional completion date. The M/P subcontractor
objection to this obfuscation of the project should determine the contractual finish date
CPM schedule. In cases where the of the project and know the amount of liq-
prime/CM refuses to provide reasonable uidated damages that may be assessed for
access to the CPM schedule, the M/P sub- certain kinds of delay.
contractor must put the prime/CM on writ-
Some prime/CMs employ a strategy to
ten notice at the outset of the project and
reduce the bid or proposal price of the proj-
with each schedule update, requesting the
ect by preparing a baseline schedule that
native schedule files in order to perform a
contemplates completing the work earlier
competent review of the baseline CPM
than the required contract completion date.
schedule and the subsequent updates. If the
This strategy reduces the number of weeks
M/P subcontractor can determine, from the
or months a prime/CM plans to expend
printed (PDF) versions of the schedule that
field and home office overhead costs, which
may be provided by the prime/CM, that the
on some projects are substantial. This is
schedule is incorrect as to activities, dura-
called an early finish schedule. Such sched-
tions, float values and/or dates, the M/P
ules can impose upon the M/P subcontrac-
subcontractor should notify the prime/CM,
tor a finish date that is earlier than the proj-
in writing, that the schedule is not accept-
ect completion date shown in the contract.
If the baseline schedule has been prepared
10
It has become a standard practice in the industry for cooperatively, then the prime/CM will have
the prime/CM to only provide to the trade contractors
PDF images of the schedule or portions thereof, and in
many instances, the late start and finish dates and total
float values are suppressed in the PDF schedule snap- 11
The contract may contain other required completion
shots. This sort of limited schedule presentation gives dates on interim milestones or specific phases of the
the reviewer little or nothing to use as a means to evalu- work and the M/P subcontractor should be aware of all
ate logic ties, lag values, late dates, and float values. contractually required finish dates.

68 Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved.


Change Orders

shared this strategy with the M/P subcon- can be used by either the owner or the con-
tractor so that the work can be planned tractor with impunity. The M/P subcontrac-
within the early finish schedule. This early tor should consider the potential financial
finish schedule may require expedited deliv- risks versus the rewards of submitting an
ery of equipment and materials, added early finish baseline schedule.
crews and/or the use of overtime. In any
event, the M/P subcontractor should care-
Documenting Issues with the
fully review the baseline schedule to ensure
that the project completion date(s) comport
Prime/CM’s CPM Schedule
Most subcontracts between a prime/CM and
with those contained in the contract, or
a M/P subcontractor require that notices of
those which have been agreed upon
potential impacts be transmitted in writing
between the prime/CM and the M/P sub-
and within a specified period of time. Such
contractor at the outset of the project.
requirements extend to scheduling issues,
In cases where the M/P subcontractor has such as the absence of a reliable schedule, or
not been involved in the development of in the case that the M/P subcontractor’s
the baseline CPM schedule, and where the review of the prime/CM’s schedule reveals
prime/CM has unilaterally included an substantial defects that prevent the M/P sub-
unacceptable early finish date for the work, contractor from accepting the baseline CPM
the M/P subcontractor should notify the schedule. It is recommended practice that
prime/CM accordingly. If the early finish the M/P subcontractor respond in writing to
schedule could result in added costs to the each and every schedule submittal provided
M/P subcontractor, the prime/CM must be by the prime/CM to the M/P subcontractor,
notified in writing of the potential for such which include draft schedules, the baseline
unanticipated and added costs, and that CPM schedule, and each and every update
a request for equitable adjustment will to the baseline CPM schedule. Such evalua-
be submitted at a future date to recover tions and notices of deficiencies should be
these costs. written in a constructive fashion and should
The M/P subcontractor should also evaluate include specific examples of unacceptable
the risk of not being able to recover the scheduling practices that can include: 1)
costs of delay to an early finish schedule missing or incorrect activities; 2) unrealistic
prepared by the prime/CM. While there activity durations; 3) improper sequencing
have been reported cases that support a con- (e.g., lack of crew restraints, out of sequence
tractor’s right to finish earlier than a con- work); 4) questionable total float values; 5)
tract finish milestone date, and to recover inaccurate progress reporting in the updates
extended general condition costs for other- to the baseline schedule; and 6) the absence
wise compensable delays to that early finish of the schedule itself (i.e., when the sched-
date, in many instances the owner will ule is not provided to the M/P subcontrac-
refuse to recognize this right to finish early tor). As previously noted, all requests for
and will consider the duration between the schedule data, including requests for the
contractor’s scheduled early finish and the native schedule electronic media, should be
contractual finish date as total float which in writing.

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 69


Change Orders

In some cases, even when the prime/CM caused event. Also, the M/P subcontractor
refuses to provide the native electronic should encourage the prime/GC to avoid
scheduling files or even sufficiently detailed signing unmodified13 contract documents
and complete print-outs of the schedule, the such as change order forms and monthly
M/P subcontractor may be able to determine payment applications that may contain
that the schedule is defective. In this event, waiver language.
the M/P subcontractor should notify the
Even when the prime/CM does not respond
prime/CM, in writing, that the schedule is
to the M/P subcontractor’s notifications
not acceptable. Even when the M/P subcon-
and/or TIAs, such non-responsiveness does
tractor cannot ascertain the reasonableness
not relieve the M/P subcontractor of its con-
of the prime/CM’s baseline CPM schedule
tractual duties and responsibilities. In cases
due to the lack of sufficient data, the M/P
where the M/P subcontractor detects that the
subcontractor should notify the prime/CM,
CPM schedule (baseline or updated) has been
in writing, that a thorough schedule review
modified and is thereafter directed to proceed
has not been possible, accompanied by a
with changed work scopes or sequencing14
reservation of rights to recover any damages
that the M/P subcontractor believes may, or
that may arise from attempting to adhere to
will, adversely affect its timing and/or costs,
the CPM schedule.
before proceeding with the revised schedule
The M/P subcontractor must carefully read the M/P subcontractor must provide proper
all provisions of the contract documents, and timely notice of such conditions.
giving consideration to the notice provisions
Management of a construction project
and any waiver language that may appear
requires vigilance by the M/P subcontractor
within the contract or that is included in
as to the timing and sequence of the work.
change order forms or within the payment
That requirement of vigilance extends to the
application documents.12 Notifications of
development and use of the CPM schedule.
potential or actual schedule and/or cost
impacts must be transmitted to the appro-
priate party or parties in strict accordance 13
In some cases, and in the presence of waiver language
with the applicable provisions of the con- on contract forms, the M/P subcontractor should attempt
tract. To the fullest extent possible, the M/P to have the prime/GC utilize revised language that reduces
the M/P subcontractor’s risks, and/or provide any qualify-
subcontractor should confirm that that ing information, such as a listing of unexecuted scope
prime/GC is timely forwarding the schedul- changes on payment application forms that contain restric-
ing and cost impact notices and REAs to the tive language. This is a very important issue that should be
addressed by the M/P subcontractor’s construction counsel.
owner, in accordance with the contract pro-
14
visions, so as not to waive the M/P subcon- Most contracts allow the prime/CM to direct the M/P
subcontractor to perform added or changed work prior
tractor’s rights to an equitable adjustment in
to the execution of a change order. While in most cases
the event that the impact is an owner- the M/P subcontractor must proceed with this modified
work, the prime/CM must be notified in writing that
the prosecution of the modified work is being per-
12
Examples of waiver language, such as change order formed under protest and that a request for equitable
“full accord and satisfaction” clauses and payment adjustment will follow as soon as the time and/or cost
application waiver language, are addressed in other impacts can be ascertained. Note that the resulting
chapters within this publication. impacts can include a loss of labor productivity.

70 Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved.


Change Orders

In addition to the comprehensive CPM As such, the M/P subcontractor must be


schedule, many prime/CMs also utilize short proactive regarding the development and use
interval schedules, usually of two, four or six of the project CPM schedule. Should the M/P
weeks in duration, Lean® project control subcontractor ignore the schedules provided
methods, and scheduling “pull” planning ses- by the prime/CM and offer no written
sions. These management methods can be responses to the prime/CM’s schedules, fail to
effective in focusing the construction team request the complete schedule in writing, fail
on near term control of the construction to follow the schedule when possible or to
process. However, in no case should these notify the prime/CM when adherence to the
complementary project control methods schedule is not possible or not practicable,
replace the overall project CPM schedule or the M/P subcontractor will be diminishing
the periodic updates to the total project CPM the ability to protect its contractual position
schedule. Only by the use of the updated, and its planned profitability. The M/P sub-
total project CPM schedule can time impacts contractor should attempt to convince the
be reliably computed and assessed in terms of prime/CM of the value of using the CPM
their potential impact to interim milestones schedule as a cooperative and powerful man-
or to the final completion date of the project. agement tool. In the absence of cooperation
It is essential to maintain the total project by the prime/CM regarding the distribution
CPM schedule in an accurate and updated and use of the CPM schedule, the M/P sub-
condition in order to comply with most con- contractor must take all reasonable precau-
tract scheduling requirements, and to provide tions, in a timely and professional manner, to
for total project progress and impact analyses, advise the prime/CM of the potentially dele-
the latter of which cannot be accomplished terious results that may be arise from its con-
in the absence of an updated, reliable, and duct regarding the CPM schedule.
comprehensive CPM schedule that depicts
the entire project scope of work. The absence
Prepared by Paul L. Stynchcomb, CCM, PSP, CFCC of
of vigilance on the part of the M/P subcon-
Vero Construction Consultants Corp. with peer review
tractor with regarding to the CPM schedule performed by: Robert Beck, President of John W. Dan-
will often come at a substantial cost. forth Company, Charles F. Mitchell, General Counsel of
The Kirlin Group, Richard Freeman, Vice President of
Stromberg Metal Works, Inc., Robert Turner,
Conclusion President/CEO of Tucker Mechanical, An EMCOR Com-
pany and Robert N. Lindbloom, Account Executive at
The CPM schedule is one of the most Apollo Mechanical Contractors.
dynamic, collaborative and vital project man-
agement tools available to the construction
team. It does not profit the construction team
for the prime/CM to refuse to distribute the
CPM schedule in its native form to the larger
trade contractors. However, this appears to be
the norm in today’s construction market-
place, not the exception.

Management Methods Bulletin CO4. © 2016 MCAA. All rights reserved. 71


Change Orders

Time Impact Analysis —


Measuring Project Delay
Introduction of your contract specifications carefully
Schedule delays are a frequent occurrence before any work is performed on the project.
on many construction projects and can have It is not unusual to find terms and conditions
immense cost consequences. Without the such as:
remedy of a time extension, mechanical Contractor’s failure to submit its time
contractors are often forced to work overtime impact analysis, with all supporting documen-
and may be required to increase crews and tation and within the time period provided
supervision to mitigate delays, even when for in this contract, will constitute a full and
caused by others. Mechanical contractors final waiver of the contractor’s right to an
may also be assessed liquidated damages for extension of time arising from the alleged
delay, along with possibly having to defend changed condition. Absent the timely and
against delay claims from the prime contrac- complete submission of the contractor’s time
tor or other trades. In some instances, a impact analysis as required by this contract,
mechanical contractor is not made aware of it is mutually agreed that the alleged changed
delaying events until it is too late to remedy condition has no effect on the critical path of
the delay without incurring added costs that the project schedule.
can be substantial.
The method of delay impact analysis
The purpose of this chapter is to alert described in this chapter is known as the
mechanical contractors to several of the key “contemporaneous windows” method of
elements of schedule usage and the develop- analysis. The windows method measures
ment of time impact analyses to identify and delay at specific time windows throughout
quantify project delays. An important first the project. The contemporaneous windows
step in this process is the mechanical contrac- in time used for this type of analysis are usu-
tor’s thorough review of the contract docu- ally the dates of the monthly update of the
ments. The specifications generally contain project schedule. While there are other meth-
the scheduling requirements for the project. ods of construction delay analysis, such as
Within this section of the specifications is the “impacted as-planned,” the “as-built,” or
often found the provisions governing timely the “collapsed as-built” methodologies,
notice and the requirements for a schedule none offer the ability to evaluate the project
impact analysis. Read the general conditions at specific windows of time throughout the

Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 73
Change Orders

duration of the work. Moreover, some Critical Path Method (CPM) Scheduling—a
methodologies, including the “impacted formalized, and usually computerized,
as-planned” technique, have been generally method of construction scheduling. This
discredited or strongly critiqued by courts dynamic construction management tool
and boards in reported cases. requires the development of activities and
interconnecting logic restraints. The activities
Many modern contract specifications require
are analyzed to determine how each interre-
the “contemporaneous windows” method
lates to other activities on the overall project
of delay impact analysis. This bulletin will
with regard to performance dates. Logic
describe this method of analysis using the
restraints are created between the activities to
terms employed by contract specifications
create the CPM schedule network, which is
that are encountered on many public and
the graphic representation of the overall
private construction projects.
schedule showing the activities and the inter-
connecting logic restraints. The CPM schedule
Terms and Concepts Used in should demonstrate the most efficient and
Delay Analysis profitable means of completing the project
Activity—the basic unit of work in a con- within the performance time set forth in the
struction schedule. The activity is the unit of contract.
work1 into which the overall project is Critical Path—the longest connected chain
divided for the purposes of tracking and (or chains, in the case of multiple critical
managing time and labor during the con- paths) of activities in a CPM schedule that, if
struction process. The overall project is delayed, will have an equivalent impact on
divided into activities during the job plan- the end date of the project.
ning phase. Each activity is defined by spe-
Total Float—the number of days an activity
cific geographic or contract boundaries such
can be delayed from its earliest start date, or
as phase, building, floor, and sectors; and by
its earliest finish date, without causing delay
other designations, such as column lines,
to the completion of the project. Activities on
systems, rooms, crew codes, or other defini-
the critical path have zero (0) total float.2
tions that will allow specific identification of
Total float is a computation that is derived
the work on the contract drawings. Each
from the CPM schedule network and is
activity is given an estimated duration and
dependent on the duration of the activities
is linked to other activities in the schedule
and the logic restraints that are input by the
by the use of logic restraints. Logic restraints
scheduler. Total float can change with each
(i.e., finish to start, start to start, finish to
progress update or modification made to the
finish, and start to finish) define the rela-
original schedule.
tionship between activities in a construction
schedule and are input by the scheduler to Most contract specifications contain a
develop the overall Schedule Network. “shared total float” clause. Such clauses state

1 2
A “unit of work” includes all elements of field installa- It is possible for the most critical path to have positive
tion as well as submittal preparation, engineer’s submit- float, a concept which is not discussed herein.
tal review, and prefabrication.

74 Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Change Orders

that total float is a commodity to be shared evolving fragnet is a term of art that
between the parties to the contract. In the describes a process of identifying, defining,
case of a delaying event, a time extension and developing over time, the discrete activi-
will be granted only to the extent that the ties that form a potential impact to the proj-
delay first consumes the entire available ect schedule. Maintaining contemporaneous
total float and, thereafter, causes a delay to documentation supporting the details of each
the critical path. Impact events, which only delay activity is important in developing and
consume positive float when analyzed in the supporting the TIA, or gapless evolving frag-
CPM schedule, will usually not result in the net. The terms “TIA” and “fragnet” will be
granting of a time extension. used interchangeably herein.
Time Impact Analysis (TIA)—a series of
activities and logic restraints that define what The Project Schedule
is known about a changed condition,3 such While this bulletin does not cover the means
as work added by a scope change or work and methods of CPM schedule development,
occasioned by a differing site condition. As updating, and maintenance, some commen-
the conditions change, or as more informa- tary concerning the scheduling process is
tion is known about the potential delay, the useful. If the mechanical contractor is also
TIA must be modified (evolved). The TIA has the prime contractor on the project, the
become a term of art in the industry and is development and control of the schedule
referenced in many contract specifications should not pose a problem. The prime
regarding project scheduling, notice, and mechanical contractor is usually tasked with
delay analysis. TIAs are input into the CPM the same type of overall scheduling responsi-
schedule as soon as the changed condition bilities as would a typical general trades con-
is recognized and are inserted into the CPM tractor or construction manager. In such
schedule update with a status, or “data date,” cases, the prime mechanical contractor will
closest in time to the date of the initiation be fully aware of the requirements of the
or discovery of the potential impact event. project schedule and will know when TIAs
Fragnet—another term of art in the construc- are required to be developed and input into
tion industry having the same definition as the overall project schedule.
the TIA. The fragnet is a fragmentary portion The majority of mechanical contractors,
of an overall project CPM schedule network however, are in the role of subcontractor to
that depicts the activities and logic associated a prime contractor or construction manager.
with a potential schedule impact. The gapless In such cases, the mechanical subcontractor
3
may not have unfettered access to the prime
TIAs are generally created at the outset of a potential
contractor’s schedule. When that is the case,
delay and, as such, will not contain a complete delay
analysis because the entire scope of the TIA will not be the mechanical subcontractor must take
apparent. Therefore, the TIA must be evolved from some affirmative steps regarding participation
month to month to show the development of the in the scheduling process. It is recommended
potential delay. This evolution requires the addition of
new activities to the TIA, such as responses to RFIs,
that the following minimum steps be fol-
approval of a change order, direction to proceed, and lowed on every project:
definition of the actual work involved in the change.

Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 75
Change Orders

■ Request the opportunity to participate in the ■ Timely submit any TIAs in accordance with
development of the project schedule. the contract documents.

It is essential that the mechanical subcon- With or without the prime contractor’s
tractor request that it be given a full and assistance and cooperation, the mechanical
complete opportunity to participate in the subcontractor must submit its TIAs in accor-
development of the overall project schedule dance with the requirements of the specifi-
prepared by the prime contractor or construc- cations. The fact that a prime contractor may
tion manager. Furthermore, the mechanical not utilize the TIA, or properly insert the
subcontractor may, from time to time, be TIA into the overall project schedule, does
asked by the prime contractor to review, or not relieve the mechanical subcontractor
to provide input into, the overall project from fulfilling, to the fullest extent possible,
schedule. The mechanical contractor should its contractual obligations, if so specified, to
respond competently, comprehensively, and develop and submit TIAs for events affecting
in a timely fashion to such requests. the work of the mechanical contractor.
■ Request electronic copies of the project ■ Utilize crew and equipment restraints to
schedule and all updates. avoid “False Float” and possible stacking of
trades or crew size inefficiencies.
It is often difficult, if not impossible, to
conduct a meaningful schedule review using False float is an important concept to grasp
only a paper copy of the project schedule or for the mechanical contractor because the
updates thereto. Thus, the mechanical sub- presence of false float may result in under-
contractor should request in writing a mag- stated time impact analysis. Many contractors
netic media copy4 of the prime contractor’s do not take into consideration the limitations
baseline schedule and each progress update of available crews or equipment items, such
thereto. The mechanical subcontractor is as cranes, and fail to insert crew and equip-
then able to perform a much more detailed ment restraints into the logic of the CPM
and thorough review of the prime contrac- schedule. The absence of these vital logic
tor’s schedule. On public projects, when restraints can create false float5 which, in the
requests for the electronic scheduling files event of a delay, may improperly consume
are denied by the owner, construction man- the impacts when a TIA is inserted into the
ager, or prime contractor, such files can project schedule. When mechanical crew
sometimes be obtained through a Freedom and equipment restraints are missing, a delay
of Information Act (FOIA) or “public infor- impact may show no delay computation in
mation act” request filed by counsel.
5
“False Float” is relative float (relative to the float on
the controlling critical path) that is improperly shown
in a CPM schedule, usually arising from the absence of
proper crew and equipment restraints. In many cases,
4
All scheduling software systems, such as Primavera®, False Float incorrectly absorbs the time impacts of frag-
allow the electronic schedule files to be written onto nets inserted into the schedule, resulting in no measur-
transferable media such as compact discs. The elec- able delaying effect on the project end date. False float
tronic scheduling files can also be easily transmitted by can deprive a contractor of its entitlement to an other-
e-mail. wise excusable delay event.

76 Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Change Orders

the project schedule due to false float. In fact, Contractor shall submit its time impact
because of the lack of crew and equipment analysis within seven (7) calendar days after
restraints, the mechanical subcontractor’s the initiation of the event that causes the
activities may become improperly “stacked” alleged delay. The seven calendar day period
in the schedule in a manner that was totally shall begin at the point in time when the
unanticipated, in turn, leading to unplanned delaying event was known, or should have
increases in crew or equipment requirements been known, to the contractor. The contrac-
and their associated inefficiency and financial tor shall submit its time impact analysis in
impact to the mechanical subcontractor. the form of a CPM schedule fragnet analysis
that will be inserted into the approved sched-
ule update closest to the initiation of the
Contractual Obligations to delaying event. Failure of the contractor to
Submit the TIA submit its time impact analysis within the
Most current contract specifications contain time limits set forth herein will result in a
requirements that the contractors submit a waiver by the contractor of any entitlement
TIA, or fragnet analysis, in order to demon- to an extension of time to the contract. By
strate the impact of changes or delays to the failing to submit its time impact analysis in
project schedule. Since most prime contrac- the format and within the time requirements
described herein, the contractor agrees that
tors include “flow down” provisions6 in their
no time extension is required by the alleged
subcontracts with mechanical subcontractors,
change in scope or event and forevermore
the mechanical subcontractor bears the same,
waives its rights to claim for such delay or
or even a greater,7 burden as does the prime
impact of any sort or type.
contractor in order to demonstrate the
impact of changes, delays, and other disrup- ■ Notice requirements for TIAs should be
tions to its work. strictly followed.

An illustrative example of the clauses that The time element imposed by the contract is
typically appear in many contract specifica- dependent upon the specific project—some
tions is the following: specifications allow as little as three (3) cal-
endar days, some as much as thirty (30) cal-
endar days or more. Notwithstanding the
6
A “flow down” provision contains language that relatively short period allowed by many
places the same requirements and obligations on the
subcontractor as the prime contractor has with the
specifications to provide written notice and
owner or construction manager. a TIA, such clauses may be enforceable under
7
In many subcontracts, the mechanical subcontractor
the controlling laws and, thus, cannot be
is required to provide its notice of delay, or TIA, in taken lightly by the mechanical subcontrac-
such a manner that the prime contractor can meet its tor. To vault the dual hurdles of delay identi-
timing obligations for notice and quantification with fication and timely notice is a formidable task
the owner in its contract. Essentially, this requirement
means that the mechanical contractor must submit its for the mechanical contractor. It is foolhardy
TIA or notice in less time than the prime contractor is to rely upon assurances from the prime con-
provided in its contract with the owner or construc- tractor or construction manager’s employees
tion manager to submit its TIA or notice.
that such requirements will not be enforced

Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 77
Change Orders

or that issues of delay and associated costs Development of the TIA


will “be dealt with” at the end of the job. In As described herein, many contract docu-
order to accommodate the rigid requirements ments (usually a section in the scheduling
of many current specifications, the mechani- specifications within the general conditions)
cal subcontractor must strictly adhere to the require that fragnets, or TIAs, be inserted into
CPM scheduling techniques described in the the project schedule as delay events are
contract specifications. known. These TIAs are to be placed into the
■ Contract conditions, payment applications, update of the schedule closest in time to the
and change orders should be reviewed by the notice to proceed of the changed condition,
contractor and/or its legal counsel to avoid or in the update closest to the start of the
waiving valuable rights. impact of the changed condition. Since most
TIAs are prepared and submitted before all of
With more and more contract specifications
the potentially delaying events are known,
being written with strict waiver clauses
the TIA must be evolved from update to
regarding notice and TIAs, it is a wise and
update. The steps to prepare an evolving TIA
prudent investment for the mechanical
are generally as follows:
contractor and/or its construction counsel to
review carefully the contract general ■ Draw out the TIA logic, in detail, to include
conditions, payment application forms, and all discrete activities that are known at the
change order forms.8 Such a review at the time the potential impact is identified, or can
outset of the project is critical to alerting the be reasonably predicted as a result of the
project management team as to its responsi- impact event.
bilities and obligations regarding these cru- Such information may include the issuance
cial issues. of an RFI, the waiting period for a response,
the analysis and pricing of the response and a
forecast of change order processing time, pro-
curement of any materials and equipment
required by the impact event, and the actual
8
The regular monthly payment application form pro- work to address the event. Each of these
vided to the mechanical contractor by the prime con- items should be designated as a separate
tractor, construction manager, or owner may contain activity in the TIA.
waiver language that must be addressed with each and
every monthly payment application in order to pre- ■ Ensure that there are no unidentified gaps in
serve the contractor’s rights for compensation for such time within the fragnet.
things as unsettled change orders and impact events
that are known, but not covered, by a formal change in From the start date of the fragnet event until
scope. Some prime contractors’ monthly payment it finishes, or is forecast to finish, every sig-
application forms contain full or partial release lan-
guage that attempts to bar the subcontractor’s recovery nificant period in time must be identified as
of unexecuted changes in scope or delay and impact an activity within the TIA. For instance, if the
claims. Similarly, the change order form used on the contractor must wait for five (5) weeks for the
project may contain “full accord and satisfaction”
owner’s response to an RFI, then the five (5)
language that may severely limit or restrict the con-
tractor’s rights to seek additional relief beyond what is week period would be identified as an activ-
explicitly set forth in the change order. ity, such as “Contractor Waiting for Owner’s

78 Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Change Orders

Response to RFI No. 50.” The TIA must be tive, it is essential in meeting many of the
gapless—every day must be accounted for by specification requirements now being
an activity describing the events of each time included in contracts. Contemporaneously,
period, whether “waiting” for a response, maintaining notations or other records that
“negotiating” the change documents, or support these forecasts of future events that
actually performing the changed work scope. are depicted in the TIA can provide an impor-
tant historical record. In addition, including
■ The actual start and finish dates for historical
the latest information regarding the TIA in
portions of the TIA (those activities that have
the most current schedule update allows the
been completed) should be verified against
mechanical contractor to manage the work
the project records and the source of all
to mitigate the impact of the delay.
actual dates and durations should be noted
for future reference. ■ As the contractor looks forward in the CPM
schedule to the point at which the potential
■ Starting with the first update in which the
delay event will affect the base contract
impact of the fragnet is identified, the TIA
work, it is important to tie the ending activ-
should include those portions of the fragnet
ity of the TIA into the earliest base contract
that are known at the time of that update as
activity which could be affected by the TIA
historical data. All forecasted information
logic.
(activities not yet accomplished that are part
of the TIA) should be entered into the sched- This tie point from the TIA into the base
ule update as new activities. contract schedule is extremely important
and should be established with care. With
■ The existing base contract activity(ies) that
regard to new scopes of work arising from
are, or may be, affected by the TIA must be
the TIA that must be defined as activities, it
identified. The TIA is then logically tied to
is essential that these new activities be
the affected activity(ies) in the CPM schedule
sequenced within the existing logic of the
to determine what, if any, impact has been
schedule so as to maintain the contractor’s
caused by the event.
planned crew restraints.
The mathematical analysis of the schedule
■ With each update, the scheduler can note
update can be rerun and the scheduler can
the effects of the various TIAs on the overall
determine if the fragnet has changed the
Critical Path of the project schedule.
critical path by comparing the pre-impacted
schedule with the impacted version. The Critical Path impacts, if any, will evolve
along with the input and updating of the TIA
■ Each succeeding month after the first update
data. In fact, the impact of the TIA on the
into which the TIA has been inserted, the TIA
Critical Path may change from month to
can be “evolved” with information as it
month as other job conditions also change.
becomes available regarding the scope and
timing of the TIA Activities. ■ If the impacts of the TIA are expected to
include labor inefficiencies, these estimated
Although the step of forecasting activities in
inefficiencies can be forward priced using
the evolving TIA (also known as the gapless
“Factors Affecting Labor Productivity” and
evolving fragnet) may be somewhat subjec-
“How to Use the MCAA Labor Factors.”

Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 79
Change Orders

To the extent that the mechanical contractor By including this consideration, where possi-
must, or desires to, include all of the poten- ble, in the overall TIA, the mechanical con-
tial impacts in a forward looking TIA, the tractor may be more fully compensated for
contractor must consider if the TIA will impacts arising from changes in scope. “How
impact the productivity of the base contract to Use the MCAA Labor Factors” explains
work. If the contractor will be required to how the estimated durations of schedule
bring in new workers that may be unfamiliar activities can be impacted using the ineffi-
with the project, work overtime, or work in ciency factors contained in “Factors Affecting
an unanticipated manner concurrently with Labor Productivity.”
other trades, the scope change work and the
■ If a change order is executed regarding an
base contract work could be adversely
evolving TIA (i.e., is executed before the
affected in terms of labor productivity. In
delay impacts are actualized), the contractor
such cases, the mechanical contractor should
should reserve its rights as to any future
reference “Factors Affecting Labor Productiv-
impacts of the evolving delay events.
ity” on page 99 and “How to Use the MCAA
Labor Factors” on page 103 to estimate the Assuming that the delay event is recognized
potential loss of labor productivity to the as a change in scope to the mechanical con-
scope change work and possibly to the base tractor’s contract, a formal change order
contract work as well.9 This loss of produc- may be executed. The change order form
tivity will be manifested in either added may contain “full accord and satisfaction”
labor to overcome the effects of the ineffi- language that is designed to bar the con-
ciencies, overtime, or longer activity dura- tractor from receiving any further compen-
tions that can result from inefficiency. sation (time and/or money) arising from the
change. If the mechanical contractor is
For example, if a base contract activity of 18
required, or decides, to execute such change
planned work days for the installation of
order forms before the full effect of the TIA is
piping branches is expected to sustain a loss
known, it is essential that the estimates for
of productivity of 20 percent caused by
future impacts of the TIA to the schedule be
“stacking of trades” because it will be per-
very carefully assessed.10 Once the mechani-
formed in a different working environment
cal contractor executes a “full and final”
resulting from the time slippage demon-
change order, it may be difficult or impossi-
strated by a TIA, the duration of the activity
ble for the contractor to later make a claim
can be increased to 22 work days (18 x 1.2).
for added costs arising from the change,
such as longer than anticipated procurement
9
The concept of impacts of multiple changes to the
base contract work is known as a “cumulative impact
10
claim” and care must be taken to price comprehen- If the mechanical contractor is required to execute
sively the effects of changes to the base contract hours. “full accord and satisfaction” change orders before
The contractor should provide exculpatory language on delay impacts are actualized by, among other things,
the change proposal in the event that comprehensive the threat of non-payment for the change work, it is
pricing is not possible. It is recommended that “How to prudent for the contractor to consult with legal counsel
Use the MCAA Labor Factors” be consulted for a more as to options that may limit or qualify the “full accord”
detailed explanation of this condition. language.

80 Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Change Orders

Labor Inefficiency Arising from Changed Conditions Can Adversely Affect


the Project CPM Schedule (Exhibit A)

times or for inefficiencies arising from a dis- room depicted in a CPM schedule for-
ruption to the crews performing the work. mat. Note that this example contains
properly developed CPM schedule activi-
The aforementioned steps that describe the
ties that describe discrete scopes of work
TIA process are graphically depicted in this
within a definable geographic area of the
bulletin and they are as follows:
project. The ability to identify the limits
■ Step 1: The process starts with a properly of a schedule activity by referring to the
developed CPM schedule (one which contract drawings is essential in the
includes a reasonable level of detail, proper assignment of potential impacts
mechanical crew, and equipment arising from the insertion of the TIA.
restraints). A faulty CPM schedule11 will Unless the scope of work in the schedule
serve little purpose in managing the 11
If the mechanical contractor has reason to believe
project or in analyzing the effects of
that the prime contractor’s CPM schedule is defective,
changes as they occur. The graphic in written notice of this determination should be transmit-
step 1 shows a portion of the base con- ted to the prime contractor with regard to the baseline
tract work in a mechanical equipment (original as-planned schedule) and each successive
update thereto.

Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 81
Change Orders

activities is known, it will be difficult to perform the scope change. The new activ-
identify where, in the CPM schedule ities are added to the TIA and now suffi-
logic, a potential impact event restrains cient information is available for the
specific base contract activities. mechanical contractor to understand
what work must be accomplished in the
■ Step 2: In this example, assume that the
field to carry out the scope change. As
mechanical contractor discovers a differ-
such, the contractor has added the fore-
ing condition or design deficiency. By
cast for the required equipment relocation
way of example, assume that structural
for 10 days and has identified 10 days of
elements of the building conflict with the
work that must be added to the base con-
physical location of major mechanical
tract work for the relocation of CHWS/R
equipment in a mechanical room. The
branch piping.
mechanical contractor prepares and sub-
mits an RFI upon discovering this condi- ■ Step 4: The TIA has been evolved to the
tion and must await the owner’s response. extent that the mechanical contractor
Note that, in the example shown in Step can tie the TIA logic into the base con-
2, the contractor has prepared a TIA start- tract activity(ies) in the master CPM
ing with an activity that describes the schedule. In Step 4, the TIA activity for
submittal of the RFI, the period awaiting equipment relocation for 10 days will be
a response, and the date on which the performed by a separate rigging crew and
response was received; all of which are thus can begin as soon as the change
historical dates in this example. However, order is approved. However, the addi-
from this point forward, the contractor tional 10 days of work associated with
may not know the scope of the change relocation of the branch piping will be
nor does the contractor have authority performed by the mechanical contractor’s
to proceed with a modified scope of work. existing piping crew. Therefore, the TIA
Therefore, in this TIA example, the con- activity that describes the added work for
tractor has estimated a period of 20 work CHWS/R branch piping must be inserted
days for the owner to define the scope of within the existing crew flow12 for the
the changed condition and agree upon a piping work.
cost for the added work. Having complete
In this manner, the schedule will main-
and detailed information concerning all
tain the planned flow of the crews and
of the elements of a TIA is not a condi-
will not depict added crews that the con-
tion precedent to the development of an
tractor did not anticipate. The failure to
evolving TIA.
integrate TIA activities into the existing
■ Step 3: Within the next update period,
the TIA is evolved by the mechanical 12
This operation assumes that the mechanical con-
contractor. By schedule update No. 2, as tractor plans to execute the scope change work with
shown on the graphic, the mechanical the crews already on site. In the event that the con-
tractor mobilizes new or separate crews to perform
contractor and owner have defined the
scope change work, it may not be necessary to con-
modified scope of work and the contrac- sider the disruption of the TIA Activities to the exist-
tor has received a notice to proceed to ing crew flow.

82 Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Change Orders

logic with regard to crew flow may result In order for this potential benefit of “real
in false float and no impact, or incor- time” impact settlements to be realized how-
rectly attenuated impact, to the CPM ever, the subcontractors, prime contractor,
schedule. and construction managers/owners must
make the CPM schedule a mutually shared
By inserting the TIA activity that is to be
commodity. If the prime contractor holds
performed by the base contract crew (in
the scheduling information under lock and
this graphic example, the added work for
key and does not encourage, or allow, the
relocation of the CHWS/R branch piping)
mechanical contractor to participate in the
within the existing crew flow, the depend-
development of the baseline schedule and in
ent activity of CHWS/R piping drops to
the maintenance and updating of the sched-
the chillers and pumps is impacted by 10
ule as the project moves forward, the goal of
work days. To the extent that this base
obtaining “real time” impact settlements
contract work was on the critical path of
will remain elusive.
the CPM schedule, the mechanical con-
tractor would be entitled to a time exten- In most instances, the terms and conditions
sion of 10 work days, or 14 calendar of the contract will dictate what the
days. This time extension could be both mechanical contractor must do with regard
excusable and compensable. to development and submission of TIAs.
Unfortunately, in some cases this means
Conclusion that the mechanical contractor may have to
While it would be desirable for all of the prepare its TIAs without the assistance or
impact events to become historical (actual- cooperation of the prime contractor. That
ized) before a change order is initiated to notwithstanding, in today’s litigious envi-
cover the effects (costs and time) of a delay ronment, the mechanical contractor cannot
impact, the current specifications in wide use afford to ignore any of the requirements
today attempt to provide a means for scope contained within the general conditions of
changes to be fully executed early in the life the contract and must take every reasonable
of a time impact so that all of the time and step to preserve its right to be fairly com-
cost impacts are included in the change pensated for impacts and delays.
order. This goal, if achieved, can reduce the
incidence of “after-the-fact” claims that are Prepared by Paul L. Stynchcomb, CCM, PSP, CFCC of
submitted at the conclusion of the project. If Vero Construction Consultants Corp., with peer
review performed by: Ronald Pearson, President/CEO
properly and cooperatively implemented, of The NewMech Companies; Matthew Hahr, Senior
“real time” TIA analyses that lead to the set- Vice President of Kirlin Mid-Atlantic, LLC; Richard
tlement of delay events, such as changes in Freeman, Vice President of Stromberg Metal Works,
scope, can mutually benefit the contracting Inc.; Robert Cox, Esq. of Watt, Tieder, Hoffar & Fitzger-
ald; and Roger Jones, Esq. of Huddles & Jones, P.C.
community and owners. Unfortunately, the
contemporaneous settlement of “real time”
TIAs is the exception, not the rule, in the
construction industry.

Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 83
Change Orders
Four Step Fragnet Example (Exhibit B)

84 Management Methods Bulletin CO3 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

Maintaining Control of Labor


Productivity
Introduction tion. Generally, most large mechanical con-
In the mechanical contracting sector of the tractors maintain an estimating department
construction industry, as with all labor inten- comprised of estimating professionals that
sive trades, once the project has been bought will not, in the final analysis, be held respon-
out and the material and equipment pur- sible for the final labor expenditures on the
chase orders have been entered into the job project. Therefore, it is important to conduct
cost system, the largest single variable (and in-house project initiation meetings wherein
the most volatile component) that controls the estimators can explain, in detail, what
profit on the project is the expenditure of was included and excluded in the estimate
labor hours. Therefore, one of the keys to as well as defining any assumptions that
profitability on a project-by-project basis is were made in the preparation of the esti-
maintaining control of labor productivity. mate. Furthermore, the basis of the labor
estimate, along with any factors or special
Surprisingly, many labor intensive contractors productivity rates that were used by the esti-
do not make any attempt to monitor and mators, can be communicated to the project
control labor hour expenditures during the management team.
life of a construction project. All labor
charges are recorded to one or two general With so much profit or loss at stake, it is
project codes, such as “field labor” or “shop important that labor-intensive contractors
labor.” This method of labor control may be make a management decision to track labor
adequate for small and very simple projects expenditures on a specific and identifiable
with limited risks of labor overruns. However, basis on every major construction project. As
on large and complex projects that offer a set forth in this bulletin, the reasons offered
mechanical contractor the potential to lose for not tracking field labor are varied and
thousands, or perhaps tens of thousands, of generally lack substance. One excuse that is
labor hours, a system of general and sum- frequently put forth regarding the contempo-
mary level labor tracking results in an unac- raneous tracking of labor by element of work
ceptable level of risk. is the difficulty in the field with ensuring rea-
sonably accurate reporting, such as dissemi-
It is not standard practice in our industry for nating to the labor managers the meaning of
the team that prepared the original estimate the various labor codes. Since the reporting
to also be the team that manages its installa-

Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 85
Productivity

may be unreliable, a contractor may elect not construction equipment that is required to
to maintain reasonably detailed labor records. complete each unit of work.
Other labor managers simply aver that track-
Activity—the basic unit of work in a con-
ing labor by multiple-labor codes on a regular
struction job plan (and in the construction
basis is too much work and the investment
schedule). The activity is the unit of work
of resources is not sufficiently rewarded by
into which the overall original estimate is
the value of the information gained in the
divided for the purposes of tracking and man-
process.
aging craft labor during the construction
This bulletin will explore the arguments sup- process. The original estimate is divided into
porting more specific and defined labor track- activities during the job planning phase. Each
ing and some of the methods of achieving activity is defined by specific geographic or
greater control over the expenditure of craft contract boundaries such as: phase, building,
labor on construction projects. floor, sectors and by other designations such
as by column lines, systems, rooms, crew
Terms and Concepts Used in codes or other definitions that will allow
specific identification of the work on the
Project Planning and Labor contract drawings. Each activity should be
Tracking given a detailed and specific description of
Original Estimate—the collection of bid up to 48 characters in length2 in order to
forms, take off sheets, labor adjustment comport with critical path method (“CPM”)
sheets,1 material, equipment and labor pric- schedules that are typically developed from
ing documents and other, similar material the job plan activity listing.
that comprise the bases for the final labor
The recommended size of the activity (i.e.,
estimate included in the lump sum bid for
the amount of work that is included in an
the project. Obviously, an important histori-
cal set of documents regarding the original activity), and the resulting duration for the
estimate are the bid set of drawings and activity, are based on the principle of opti-
specifications. mized tracking. Optimized tracking refers to
the greatest reasonable degree of reporting
Job Planning (the Job Plan)—the process accuracy that can be expected during the
whereby the estimators and/or the construc- course of the project. The concept of opti-
tion managers divide the original estimate mized tracking dictates the size of the activ-
into identifiable units of work to which can ity in the job plan, as well as in the project
be assigned the materials and equipment
that must be installed and the labor and
2
In today’s construction environment, the most widely
used CPM scheduling software system is Primavera®.
This software system allows activity descriptions of up
1
For the purpose of increasing the competitive nature to 48 characters in length, however the software allows
of a bid, many mechanical contractors “discount” the for many additional fields into which the planner may
detailed labor estimate by some factor or percentage. place area, floor, column line, crew identification, or
Any such adjustments should be carefully documented other code information in order to track the activity
in the bid file. with greater particularity.

86 Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

CPM schedule. In scheduling, the general plumbing piping and duct work within the
guideline regarding the durations of erec- same area, each principal trade would have
tion activities3 for optimized tracking sug- its work identified by separate activities.
gests a range of between three to 22 work Similarly, if the mechanical contractor has
days for the majority of the activities large bore weld joint carbon steel pipe,
defined in the job plan. Obviously, some socket weld small bore pipe and thin wall
activities will be only one or two days in stainless steel pipe work, all in the same area
length by necessity. However the majority or phase of the project, it is useful to divide
of the activities in the job plan and sched- this work into three discrete activities by
ule should have durations that fall within type of piping system based on the crews
the range of 3 to 22 work days. This range that will perform the installation work.
or duration for the activities used in the
Furthermore, the activity should be defined
schedule also provides for optimized track-
during the job planning phase such that the
ing when these activities are also used in
work can be commenced and not halted
the job plan reporting system.
until the activity is completed. This is one of
The duration of an activity is calculated by the characteristics of an efficiently planned
estimating the number of labor hours that construction project; namely that the activi-
will be required to complete the activity and ties express continuity of work such that
by estimating the crew size for the work. there is no planned “start-stop-start” disrup-
The duration is derived by dividing the total tion contemplated in the baseline job plan
estimated labor hours by the hours required or CPM schedule.
for the crew per day. For instance, if the
Once the mechanical contractor has devel-
activity will consume 640 labor hours and
oped its activities, this information should be
the contractor plans to utilize a crew of four
shared with the prime contractor for integra-
mechanics (i.e., totaling 32 hours per day),
tion into the project master schedule. If the
the resulting duration for the activity would
prime contractor has already prepared the
be 20 work days.
overall master schedule, the mechanical con-
Obviously and within reason, the more spe- tractor must determine if the activities cre-
cific the activity data, the more valuable is ated in its job plan comport with the
the reporting information. Therefore, it is mechanical activities created by the prime
advisable to differentiate between the types contractor. If the activity durations of the
of systems that may occur within the same prime contractor do not comport with those
geographic area, resulting in more than one contained in the mechanical contractor’s job
activity in an area. For instance, if the plan, then a written request should be sub-
mechanical contractor has HVAC piping, mitted to the prime contractor requesting the
required modifications. If the prime contrac-
3
“Erection Activity” as opposed to procurement
tor refuses the reasonable schedule modifica-
activities, such as “Fabricate and Deliver Chiller,” tion requests of the mechanical contractor,
which may have a duration of many months and will the prime contractor should be placed on
not be assigned field erection labor in the job plan or
notice that the baseline master schedule is
in the schedule.

Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 87
Productivity

not reasonable. Specifics should be provided version of the LPR. The LPR can take on
in the written notice as to the activities many different forms and is called by differ-
and/or logic that are incorrect or inconsistent ent names by various mechanical contractors,
with the mechanical contractor’s reasonable but for the purpose of this bulletin, the report
plan to prosecute its base contract work. that provides the labor tracking information
will be known as the LPR. One example of an
Activity Identification (“ID”) Code—the
LPR is shown below.
unique numeric, or alphanumeric, identifier
that is given to each activity. The application The code fields are identified from left to
of activity IDs may be dictated by the con- right as follows:
tractor’s job costing system, the labor per- Activity ID Code—the unique identifier for
formance software in use and by the schedul- each activity
ing software that may be employed on the
project. In order to simplify the overall labor Activity Description—the definition of the
tracking operation on a construction project, work that is to be performed
it is important to utilize the same codes for Planned Hours—the originally estimated (or
all cost, labor and schedule tracking software re-estimated hours)4 hours to perform the
systems. Having one single set of activity IDs work
for all control systems used on a project will
increase the accuracy of the reporting and CO Hours—estimated change order, or scope
reduce the overhead costs to develop and change, hours
update the systems.
Labor Performance Report (“LPR”)—the 4
Some mechanical contractors require that the con-
report format that provides the planned and struction team “re-plan” the project once it has been
the actual performance data for use by field transferred from the estimating department. The con-
and office management during the life of the struction team may find differences in the “construc-
tion estimate” as opposed to the original estimate. The
project. There is not a single, “best” form of job plan should reflect the planned hours determined
this report and many mechanical contractors by the team that will actually take responsibility for
have developed their own, highly effective, the profitability of the project.

The Labor Performance Report (Example of Detailed Activities)

Activity Activity Planned CO Rev Last Current Earned PT C Act Wk Wk Cw


ID Code Description Hours Hrs Plan %C %C Hours AH Hrs -2 -1

7550 Inst CHWS&R 500 500 30 50 250 300 450 –75 –150 –200
Mains
Area B

7570 Inst CHWS&R 700 50 750 10 20 150 120 200 –40 –45 –50
Brnchs
Area B

7590 Connections 100 100 10 15 15 10 12 0 0 3


@ Mech
Equip

88 Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

Revised Plan—the total of the original esti- changes in scope); (ii) the actual hours from
mated hours and estimated change order payroll information; and (iii) the percent
hours complete of the activity. In return for the
input of the above-listed data, the project
Last Percent Complete—the progress of the
team has at its disposal a powerful tool that
activity at the previous reporting period5
allows management to review with speci-
Current Percent Complete—the progress ficity the areas of labor expenditure that
of the activity at the current reporting exceed the budgeted job plan labor hours.
period Most importantly, it permits the project
Earned Hours—the “should have spent” management team to identify specific activ-
hours (Revised Plan ✕ Current Percent ities of work that are indicating unproduc-
Complete) tive progress before the activity is complete,
thus allowing the project management team
Previous Total Actual Hours—the actual to proactively address the forecast labor
hours charged as of the last reporting period overrun before it becomes an historical loss.
Current Actual Hours—the actual hours
charged through the current reporting
The Purposes of, and
period
Methodologies for, Tracking
Variance Week –2—the craft hour variance
Labor
as of two weeks prior to the current period
The single, best reason to maintain better
Variance Week –1—the craft hour variance control of field labor expenditures is to
as of one week prior to the current period increase profit. There are other sound
Current Week—the current period craft reasons for a higher degree of labor control
hour variance (– over budget / + under budget) on construction projects, which include:

By maintaining a current and accurate job ■ Establishing, or verifying, the accuracy of


plan, the productivity of each activity of the contractor’s bidding units
work can be measured on a period-by- ■ Developing an early warning system that
period basis (usually measured by pay will allow proactive management inter-
period). Once the activity ID codes, activity vention
descriptions and the planned hours have
■ Mitigating, or documenting, the ineffi-
been input at the outset of the project, the
ciencies associated with non-contractor
regular input data consists of: (i) any revi-
caused impacts as well as accurately
sions to the original job plan hours (i.e.,
quantifying the associated costs
In fact, these reasons to track labor expen-
5
The frequency of the reporting periods is generally ditures contribute to the concept of main-
governed by the frequency of the pay periods of the field taining, or increasing, profit on the project.
craft labor, which is usually weekly or twice monthly.
The longest effective reporting period in terms of labor The job plan should be developed with the
tracking and trending is approximately monthly. input and direct assistance of the field labor

Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 89
Productivity

supervisors (sometimes called the labor Documenting the elements of an activity is


superintendent or general foreman). The an essential ingredient in achieving accurate
inclusion of the principal labor managers labor reporting. One means of meeting this
will increase the opportunity for accurate goal is to mark the outlines or boundaries of
labor reporting. An essential element of each activity on a set of contract drawings.
accurate labor reporting is the clear defini- The graphic example below shows how
tion of the work included in an activity. depicting the extents of a specific job plan

Activity Boundaries Marked on the Contract Drawings

Activity 7550 - Mechanical Room Mains Column Lines 11-15/A-B

90 Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

activity can provide relevant documentation each set, or task, which will be required to
that can be constantly referenced during the complete the activity. Such records can
life of the project.
In addition, other forms can be utilized to 6
Many mechanical contractors find it very valuable,
capture the details of each activity that can and highly profitable, to have the construction team
be referenced during the project to ensure perform a re-estimate of the project before commence-
ment of the work. While time-intensive, this operation
that the actual labor hour reporting is accu- provides an invaluable learning experience for the proj-
rate. The form shown below has been used ect team concerning the particulars of their specific
on large and complex projects to document project and will provide for a reasonably detailed job
plan that relates to the manner in which the project
the labor, equipment and material required
team will actually prosecute the work. Another benefit
to perform each activity. The form allows of this process is the identification of long lead-time
the contractor’s planning team6 to record procurement items.

Activity Planning Form

Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 91
Productivity

substantially improve the quality and It is simply reduced to the will of the
accuracy of actual labor hour reporting in mechanical contractor to track the expendi-
the field. ture of its most valuable and volatile
resource—field labor.
Any project reporting system requires an
investment in terms of management With an accurate LPR, the project manage-
resources. If a contractor expects to derive ment team can readily and effectively evalu-
valuable management information from any ate the productivity of defined areas of the
reporting system, whether cost or labor effi- project including specific crews, labor man-
ciency, attention to detail and accuracy are a agers or other defined features of the work.
necessity. A “corporate culture” that sup- Often, inspection of the updated job plan
ports accurate cost and labor reporting is activity ID codes will alert the project man-
essential. agement team to inefficient labor trends
that can be investigated by physically
Once the initial data has been input and
observing the work and interviewing the
collected, the contractor has the following
labor foremen to determine whether the
data that must be accurately coded and
deteriorating labor productivity has been
input on a period-by-period basis:
caused by changed conditions, unanswered
■ Actual field craft labor hours charged to RFIs, other impact events beyond the con-
each activity ID code trol of the mechanical contractor or self-
■ Estimated scope change hours that must induced inefficiencies.
be input to update the job plan However, if the contractor does not insti-
■ Current period percent complete tute quality control checks and reviews of
progress by activity ID code the data and the period-by-period coding of
the actual labor hours to the job plan activ-
The foregoing represents the ongoing data ity ID codes, the resulting inaccuracies aris-
that must be collected and entered into the ing from this neglect may render the LPR
LPR to allow the report to provide a variety unreliable. For instance, some mechanical
of output data that can be used by the proj- contractors offer a bonus to labor managers
ect management team proactively to address for hours saved on the project. This pro-
productivity “events” that serve to reduce gram may have the unintended effect of
profits and/or cause delays to the construc- promoting the “balancing” of actual labor
tion schedule. The software cost for imple- hour charges each reporting period. If the
menting and maintaining a labor tracking craft labor manager sees an activity ID code
and trending system is not the limiting fac- decreasing in efficiency (i.e., the negative
tor for the use of such systems. Reporting variance increases each period), there may
systems as described herein can now be be a temptation to improperly reassign
accomplished using some of the more craft hours from the inefficient code to a
advanced features of Microsoft Excel®. labor code that is reporting highly produc-
Therefore, the actual costs of the software tive work. This sort of “balancing” renders
and computer platform to run such systems the LPR information suspect and unreli-
are no longer a bar to their implementation. able.

92 Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

Every reasonable effort should be engaged Labor Productivity Trending


to ensure that the craft labor managers who In order to grasp quickly the overall labor
generally decide to which activity ID code productivity on a construction project, it is
actual labor hours are assigned are charging essential that the data be presented in a for-
the hours to the correct activity ID codes. mat that can be readily acted upon by the
This may even entail changing the contrac- management team. Various summary reports
tor’s bonus incentive plans to move away and trending curves can be produced from
from bonuses granted purely on incremen- the LPR. For instance, from the summary of
tal reporting of labor efficiency. In addi- the LPR, the total project (or the mechanical
tion, the labor managers must be given the portion thereof) can be computed on a
time and clerical support to allow for accu- period-by-period basis. This data, in combi-
rate collection of the necessary data. What- nation with the variances computed within
ever steps are employed to ensure accurate the LPR, can be combined to create a curve
charging of actual labor hours will be effort or trend of labor productivity, as can be seen
well spent in terms of providing an invalu- in the example below:
able tool for the project management team
to detect potential losses of labor produc- From this sample curve, the trend of the
tivity before they become significant. labor expenditures can be plotted and
quickly evaluated by the project manage-
The primary goal of the labor tracking and ment team. On this example, the total
trending methods described herein is to project percent complete, labor hours
increase profit. The mechanism by which over/under budget and percent variance are
that goal is achieved is known as “proactive shown on one chart. These types of easily
management.” Simply put, this sort of man- assimilated graphic presentations can be
agement occurs when a project team is able augmented with other types of “roll up”
to identify negative trends within its labor trending reports that have their data derived
budgets early enough to allow the manager from the LPR without any further input by
to identify the discrete work activity in the project team. Other sorts of “roll up,”
which the inefficiency is occurring and to summary level reporting that can be gener-
take steps to totally remedy or mitigate, or ated from the data described previously
at least identify the source and location of, herein includes the following example:
the productivity loss. Assuming that the
activity has been properly developed, it will
have definable and specific geographical
boundaries such that the labor manager can
walk onto the project and “stand” in the
area of the activity. The presence of such
specific labor tracking and trending can
allow the manager to evaluate the potential
causes of the reported inefficiencies and take
the appropriate action before the loss
becomes project-wide.

Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 93
Productivity

Labor Productivity Variance Tracking & Trending Curve

Such summary level reports require no ■ The progress (by percent complete) that
further input from that described herein and must be achieved by period
can provide valuable management informa-
■ Required crew size at the planned rate of
tion.
performance
From the above example, the following data
■ Required crew size at the actual rate of
can be derived:
performance
■ Total hours ahead or behind the job plan
■ Historical reporting on the activities that
■ Total project percent complete in terms of have been completed
labor hours
■ Trending of the active activities
■ Progress gained by period in terms of
labor hours

94 Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

Labor Performance Summary


Issue 12/10 12/17 12/24 12/31 1/7 1/14 1/21 1/28 2/4 2/11 2/18

Mechanical Work
Planned Hours 17908 18208 18208 17848 17848 18526 18526 18526 18526 19882 19882
Completed Hours 5867 6510 7190 7596 8075 8718 9280 9919 10602 11554 12310
Actual Hours 5734 6256 6941 7409 7902 8606 9282 10062 10870 11704 12491
Hours This Week 585 522 685 468 493 699 676 780 808 722 787
Variance (Hours) 133 254 249 187 173 112 –2 –143 –268 –150 –181
Variance (%) 2% 4% 3% 2% 2% 1% 0% –1% –3% –1% –1%
Effective Crew Size 16 15 19 13 14 19 19 22 22 20 22
Current & Complete 33% 36% 39% 43% 45% 47% 50% 54% 57% 58% 62%
Progress This Week (%) 3% 3% 4% 3% 3% 2% 3% 3% 4% 1% 4%
Progress: 4 Week Average 3% 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%
Required % Comp./Wk 4% 4% 4% 4% 4% 4% 4% 4% 4% 5% 4%
Weeks Available Left 18 17 16 15 14 13 12 11 10 9 10
Job End Date 4/14 4/14 4/14 4/14 4/14 4/14 4/14 4/14 4/14 4/14 4/28
Req. Crew @ Plan Rate 20 20 19 19 19 21 21 22 22 26 21
Req. Crew @ Actual Rate 19 19 18 19 19 21 21 22 23 26 21
95–100% Activities (Plan) 420 420 420 420 861 2478 3095 4582 5559 6067 6749
95–100% Activities (Actual) 434 434 434 434 830 2419 2933 4600 5864 6065 6810
100% Better/Worse (Hrs.) 14% –14% –14% –14% 31% 59% 162% –18% –305% 2% –61%
100% Better/Worse (%) –3% –3% –3% –3% 4% 2% 5% 0% –5% 0% –1%

5–95% (Plan) 11842 12142 13792 15272 15272 10078 9428 8014 8111 9073 9196
% of Mech. Plan Action 66% 67% 76% 86% 86% 54% 51% 43% 44% 46% 46%

These data can provide further insight into recovery from a prime contractor or owner.
the typically non-linear expenditure of labor Each year, MCAA member firms incur hun-
hours on a construction project and within dreds of millions of dollars in unplanned
each discrete activity. The object of any labor expenditures due to loss of productiv-
reporting methodology and output report- ity impacts not caused by the mechanical
ing is to increase profits and eliminate the contractor. To the extent that it can be
end-of-project labor loss “surprise” that demonstrated that the mechanical contrac-
afflicts a large number of otherwise sophisti- tor was not the cause of such losses, it may
cated and successful mechanical contractors. be necessary to develop a loss of productiv-
ity claim. In some cases, the very survival of
the contractor may depend on the success of
When Loss of Labor such a request for equitable adjustment.
Productivity Claims Arise
Once the mechanical contractor’s estimate
On some projects, the mechanical contrac-
has been eliminated as the source of the
tor sustains a substantial loss of labor pro-
loss, the mechanical contractor should
ductivity for which the contractor seeks

Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 95
Productivity

determine what other events cause the loss period basis. However, the materials and
of productivity. Some commonly overlooked conditions of installation can be readily
items are the impacts of RFI’s, field change analyzed by reviewing the historical data
directives and “field fit-to-suit” conditions, that supports the job plan and the LPR.
which are seldom incorporated into the Assuming the mechanical contractor has
compensation for change orders. After care- retained the records (such as contract draw-
ful evaluation of the events that adversely ings marked by activity ID code or the Activ-
affected the labor productivity on a project, ity Planning Form) that provide the basis of
the mechanical contractor has the option of each activity, the materials installed in the
either absorbing the loss or preparing a loss activity can be estimated or, if the Activity
of productivity claim. One of the acceptable Planning Form has been used, the material
methods of computing loss of productivity data are readily available without the need
is the “measured mile” method. This to reestimate the materials.7
method is described in the MCAA’s Publica-
Assuming that the contractor has accurately
tion “How to Use the MCAA Labor Factors.”
recorded the actual hours charged to each
Simply put, this methodology computes
activity ID code, the hours required to
inefficiencies by measuring a contractor’s
install the material and equipment within
actual productivity rate achieved in a time
an activity are identifiable. With that infor-
frame or area of lesser impact and compares
mation in hand, a contractor can compare
the contractor’s actual productivity in a time
the labor required to install systems in less
frame or area of representative impact.
impacted time frames or areas with the labor
Among other information that is necessary
required to install similar systems in the
in order to perform a measured mile analy-
impacted time frame or area. The measured
sis, the contractor must have available com-
mile method is not dependent upon the
parative data in order to compute the vary-
contractor’s estimate because it uses actual
ing production rates. If the contractor
installation rates achieved on that particular
maintained an LPR system similar to that
project site to form the basis of the produc-
described herein, then the data required to
tivity comparison.
perform a measured mile analysis can usu-
ally be compiled. As noted in “How to Use the MCAA Labor
Factors,” on some projects it will be impossi-
By referencing its estimate, or by taking off
ble to perform a measured mile analysis,
systems by activity ID codes, the contractor
even if proper labor productivity data is
can equate labor hours to the quantity of
available. On many projects, there is no
material installed. A measured mile analysis
identifiable unimpacted, or less impacted,
requires knowing the actual hours expended
period thereby preventing the contractor
to install a unit of material; for instance,
hours actually expended to install a linear
7
foot of 14" ASTM A-53 schedule 40 butt To the extent that change orders have been issued,
the original estimate for materials must be adjusted for
weld pipe by area or time frame. The vast
the material items added by the change orders to cre-
majority of mechanical contractors do not ate the “adjusted estimated quantities.” This is true for
track materials installed on a period-by- field labor as well.

96 Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

from applying a measured mile analysis. In Author’s Note


such cases, the MCAA factors described in Obviously, the labor tracking and trending
“Factors Affecting Labor Productivity” and concepts described herein were not originated
“How to Use the MCAA Labor Factors” can by the writer. I am compelled to credit many
be useful in estimating the cause and effect experienced and highly profitable mechanical
of various sources of inefficiency such as contracting firms, well known within the
“Reassignment of Manpower,” “Crew Size MCAA membership, for developing, testing
Inefficiency,” “Dilution of Supervision” and and proving the inestimable value of the
“Overtime Inefficiency.” This data and an labor tracking and trending systems described
explanation of what a loss of productivity in this bulletin. The writer had the privilege
claim entails are addressed in the other of having been employed by one such firm
MCAA publications as noted above. and had the opportunity, on a first-hand
basis, of experiencing the hard work develop-
Conclusion ing and maintaining an accurate LPR system
Measuring labor productivity during the and also of witnessing the material benefits
course of a construction project requires that resulted from this proactive manage-
discipline, dedication of the labor manage- ment concept.
ment team and an earnest desire to under- Paul L. Stynchcomb, CCM, PSP, CFCC
stand the somewhat ethereal and amorphous Vero Construction Consultants Corp.
concept of labor inefficiency. The pursuit of
this understanding, however, can lead to Prepared by Paul L. Stynchcomb, CCM, PSP, CFCC of
more profitable construction projects and Vero Construction Consultants Corp., with peer
avoidance of substantial losses that are review performed by: Ronald Pearson, President/CEO
occasioned by impacts causing loss of labor of The NewMech Companies; Matthew Hahr, Senior
Vice President of Kirlin Mid-Atlantic, LLC; Richard
productivity. Freeman, Vice President of Stromberg Metal Works,
Inc.; Robert Cox, Esq. of Watt, Tieder, Hoffar &
Fitzgerald; and Robert Windus, Esq. and Stuart Sakwa,
Esq. of Moore & Lee, LLP.

Management Methods Bulletin PD1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 97
Productivity

Factors Affecting Labor


Productivity
Instructions on the use of MCAA’s Labor Factors are provided in the section titled “How to Use
the MCAA Labor Factors.”

Percent of Loss per Factor


Factor
Minor Average Severe
1. STACKING OF TRADES: Operations take place within physically 10% 20% 30%
limited space with other contractors. Results in congestion of
personnel, inability to locate tools conveniently, increased loss of
tools, additional safety hazards and increased visitors. Optimum
crew size cannot be utilized.

2. MORALE AND ATTITUDE: Excessive hazard, competition for 5% 15% 30%


overtime, over-inspection, multiple contract changes and rework,
disruption of labor rhythm and scheduling, poor site conditions, etc.

3. REASSIGNMENT OF MANPOWER: Loss occurs with move-on, 5% 10% 15%


move-off men because of unexpected changes, excessive changes,
or demand made to expedite or reschedule completion of certain
work phases. Preparation not possible for orderly change.

4. CREW SIZE INEFFICIENCY: Additional workers to existing crews 10% 20% 30%
“breaks up”original team effort, affects labor rhythm. Applies to
basic contract hours also.

5. CONCURRENT OPERATIONS: Stacking of this contractor’s own 5% 15% 25%


force. Effect of adding operation to already planned sequence of
operations. Unless gradual and controlled implementation of
additional operations made, factor will apply to all remaining and
proposed contract hours.

6. DILUTION OF SUPERVISION: Applies to both basic contract and 10% 15% 25%
proposed change. Supervision must be diverted to (a) analyze and
plan change, (b) stop and replan affected work, (c) take-off, order
and expedite material and equipment, (d) incorporate change into
schedule, (e) instruct foreman and journeyman, (f) supervise work
in progress, and (g) revise punch lists, testing and start-up
requirements.

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 99
Productivity

Percent of Loss per Factor


Factor
Minor Average Severe
7. LEARNING CURVE: Period of orientation in order to become familiar 5% 15% 30%
with changed condition. If new men are added to project, effects
more severe as they learn tool locations, work procedures, etc.
Turnover of crew.

8. ERRORS AND OMISSIONS: Increases in errors and omissions 1% 3% 6%


because changes usually performed on crash basis, out of sequence
or cause dilution of supervision or any other negative factors.

9. BENEFICIAL OCCUPANCY: Working over, around or in close 15% 25% 40%


proximity to owner’s personnel or production equipment. Also
badging, noise limitations, dust and special safety requirements
and access restrictions because of owner. Using premises by
owner prior to contract completion.

10. JOINT OCCUPANCY: Change cause work to be performed while 5% 12% 20%
facility occupied by other trades and not anticipated under original bid.

11. SITE ACCESS: Interferences with convenient access to work areas, 5% 12% 30%
poor man-lift management or large and congested worksites.

12. LOGISTICS: Owner furnished materials and problems of dealing 10% 25% 50%
with his storehouse people, no control over material flow to work
areas. Also contract changes causing problems of procurement and
delivery of materials and rehandling of substituted materials at site.

13. FATIGUE: Unusual physical exertion. If on change order work and 8% 10% 12%
men return to base contract work, effects also affect performance
on base contract.

14. RIPPLE: Changes in other trades’ work affecting our work such as 10% 15% 20%
alteration of our schedule. A solution is to request, at first job meeting,
that all change notices/bulletins be sent to our Contract Manager.

15. OVERTIME: Lowers work output and efficiency through physical 10% 15% 20%
fatigue and poor mental attitude.

16. SEASON AND WEATHER CHANGE: Either very hot or very cold 10% 20% 30%
weather.

100 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

Connecting the “Cause” and


“Effect” in Loss of
Productivity Claims
By Gerson B. Kramer

Gerson B. Kramer began acquiring his vast experience in measuring differential productivity during his
first post-college job at the Department of Labor’s Bureau of Labor Statistics. After graduating from
George Washington University School of Law, Mr. Kramer joined the Justice Department’s Court of
Claims Section and later the Commerce Department’s Appeals Board. For ten years prior to his
retirement, Mr. Kramer served as chairman and chief administrative judge of the Department of
Transportation’s Contract Appeals Board. In that capacity, Mr. Kramer heard cases involving
contractors’ claims for loss of labor productivity and authored a reported decision on one of the
government’s largest inefficiency cases in the history of any major board of contract appeals.

The construction industry is one of the lead- irrespective of the portent of an inefficiency
ing capital industries that drive the U.S. econ- claim.
omy. As an industry, it depends to a great
One of the fundamental issues that a trier of
extent upon labor productivity to remain
fact considers in hearing a contractor’s ineffi-
profitable. Yet, many construction firms do
ciency claim is “cause and effect.” Important
not maintain the necessary records to supply
in the consideration is the question of
the quantification of its labor productivity.
whether or not the contractor’s claims as to
A contractor needs to maintain accurate con- productivity impacts comport with the quan-
temporaneous productivity records to man- tum being sought. In my experience, “pro-
age its labor forces and to serve as a founda- ductivity” can be summed up as the effi-
tion in the event of a productivity claim. ciency that contractors achieve in converting
While the courts and boards have established inputs to outputs. In the construction indus-
the principle that a contractor need not try, this usually means the conversion of
compute its loss of productivity with exact- labor hours to a quantity of installed materi-
ness, it would appear that accurate recording als, such as tons of steel erected, cubic yards
of a contractor’s productivity is simply a of concrete poured or linear feet of pipe
management necessity to ensure profitability, installed. However, where productivity is

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 101
Productivity

concerned, there is no general agreement and It is a fact that the MCAA factors have been
no “black letter” law as to how this is to be in use for over 30 years in furnishing a means
quantified. This is equally true of quantifying of estimating loss of productivity in construc-
the loss of productivity. Furthermore, stan- tion matters. One of the most beneficial and
dard cost accounting categories and standard advantageous facts is that the MCAA factors
monetary categories do not readily yield the require users to consider carefully the narra-
necessary quantifications of labor productiv- tive facts and project events or milestones
ity or loss of productivity. Neither the IRS nor with the trends shown by the numbers.
the vast majority of construction CFOs “How to Use the MCAA Labor Factors”
arrange for, or demand, the reporting of the repeatedly instructs users to assess carefully
necessary elements to calculate or quantify each and every element of fact along with
productivity or its loss. the use of the percentage factors provided by
“Factors Affecting Labor Productivity.” Direct
This lack of quantification on productivity or
and indirect impacts need to be quantified
its loss becomes problematical when disputes
carefully in conjunction with the specific
arise. The disputes process that is presented to
events of the project.
tribunals calls for magistrates to make find-
ings of fact on very specific matters. Although This process of matching the facts with the
there is currently no accepted empirical study claimed loss of productivity is designed to
that delineates a specific methodology or a provide the deciding tribunals with a degree
particular means of record keeping to prove of confidence necessary to reach the ulti-
productivity or the loss of productivity, one mate decisions. It is well recognized that a
method of labor productivity quantification contractor does not have to prove its loss of
that has achieved a relatively high level of productivity with mathematical exactitude;
acceptance is known as the “measured mile” however this does not relieve the contractor
analysis. This methodology is highly depend- from making a compelling case as to the
ent upon the contractor’s books and records specific causes of the impacts and to con-
and also upon the presence of an unimpacted nect then with a logical effect. In this
and impacted area or period by which a pro- regard, the MCAA factors have been found
duction ratio can be computed. While this to be a reliable means of estimating a con-
methodology has been well received by the tractor’s loss of productivity caused by indi-
courts and boards, it is also true that this vidual categories of causation. For this rea-
methodology cannot be applied on many son, “How to Use the MCAA Labor Factors,”
construction projects for a host of reasons, which outlines how to use the MCAA fac-
two being the lack of detailed productivity tors to arrive at a reasonable estimate of pro-
record keeping and the lack of suitable or ductivity or loss of productivity, should fur-
comparable unimpacted areas or time frames. nish much needed and useful guidance to
The inability to prepare a measured mile users who need to estimate productivity
analysis does not, in and of itself, bar a con- quantities and costs.
tractor’s loss of productivity claim. In such
cases, the contractor must apply a different MCAA thanks Judge Kramer for providing this
methodology to connect the cause and effect. introduction.

102 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

How to Use the MCAA Labor


Factors
Introduction This chapter has been prepared to assist the
Since 1971 the MCAA has offered “Factors contractor with the quantification of the loss
Affecting Labor Productivity” in its Manage- of labor productivity caused by occurrences
ment Methods Manual. Known as the “MCAA described by the various MCAA factors. Of all
factors,” they have been used by contractors construction-related subjects, the proof and
to forward price estimated losses of labor quantification of the loss of labor productiv-
productivity in change order proposals, and ity are recognized as among the most difficult
to retroactively price estimated losses of and complex to describe. An attempt has
labor productivity in the whole after the been made to avoid the overly scientific and
completion of a project. Since their intro- complex. It is understood that quantifying a
duction in 1971, the factor titles, descrip- loss of labor productivity is oftentimes based
tions and the percentage of estimated on an estimate of losses. However, by the
impacts have remained unchanged. very complex nature of the issue of the quan-
tification of labor productivity loss, detailed
“How to Use the MCAA Labor Factors” has explanations and qualifications of applica-
been developed to provide detailed explana- tions must be offered to the contractor.
tions suggesting the proper use of the MCAA
factors in estimating losses of labor produc- The MCAA factors have proven to be a reli-
tivity for both forward and retroactively able means of estimating the loss of labor
priced change requests and for performing productivity on construction projects for over
labor productivity analyses. 30 years. The specific values shown in the
factor tables must be applied with careful
Also included are some points of considera- consideration and a review of the facts sur-
tion when assessing change order conditions rounding the events, which caused the loss of
and contract language that may affect the productivity. The applications of the various
contractor’s ability to recover its damages. MCAA factor percentages will vary as project
However, this chapter offers no legal opinions conditions dictate. This chapter will provide
or conclusions and the contractor should specific guidelines and examples of several
review all project documents and conditions methods of application for the proper use of
with counsel. the MCAA factors in calculating the loss of
labor productivity on construction projects.

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 103
Productivity

It is important to note that the MCAA fac- “Impact costs are additional costs occurring as a
tors have gained wide acceptance in the result of the loss of productivity; loss of produc-
construction industry and before various tivity is also termed inefficiency. Thus, impact
courts, boards of contract appeals and tri- costs are simply increased labor costs that stem
bunals of the American Arbitration Associa- from the disruption to labor productivity result-
tion. For example, reference the Appeal of ing from a change in working conditions caused
Clark Concrete.1 In this recent decision by by a contract change. Productivity is inversely
the General Services Board of Contract proportional to the manhours necessary to pro-
Appeals, the board wrote, in part: duce a given unit of work. As is self-evident, if
productivity declines, the number of manhours
“To assess the impact of unanticipated condi-
of labor to produce a given task will increase.”
tions on productivity … P&K used a manual
published by the Mechanical Contractors The board continued in its explanations of
Association of America (MCA). … P&K has inefficiencies:
used it on other projects to measure similar “Direct impact is generally characterized as the
impacts, and the publication is generally immediate and direct disruption resulting from
accepted in the mechanical industry for this a change that lowers productivity in the per-
purpose. … We have previously accepted the formance of the changed or unchanged work.
use of this manual for this purpose as well. Direct impact is considered foreseeable and
Stroh Corp., 96-1 BCA at 141.132; also see Fire the disrupting relationship to unchanged work
Securities Systems, Inc., VABCA 3086. 91-2 can be related in time and space to a specific
BCA 23,743 at 118.902. … The manual lists change. Cumulative impact is the unforeseeable
various types of impacts, and for each, a per- disruption of productivity resulting from the
cent of labor costs which represents loss of “synergistic” effect of an undifferentiated group
labor productivity under each of minor, aver- of changes. Cumulative impact is referred to as
age, and severe impacts.” the “ripple effect” of changes on unchanged
Coupled with credible testimony, the MCAA work that causes a decrease in productivity
factors can be useful to contractors, owners, and is not analyzed in terms of spatial or tem-
boards of contract appeals and other courts poral relationships. This phenomenon arises at
and tribunals for the purpose of estimating a the point the ripple caused by an indivisible
contractor’s loss of labor productivity. body on two or more changes on the pond of
a construction project sufficiently overlap and
There are many definitions for the impact
disturb the surface such that entitlement to
costs associated with a productivity loss on a
recover additional costs resulting from the
construction project. The Department of
turbulence spontaneously erupts. This overlap-
Veterans Affairs Board of Contract Appeals
ping of the ripples is also described as the
in one decision offered the following cogent
“synergistic effect” of accumulated changes.
explanation:
This effect is unforeseeable and indirect.
Cumulative impact has also been described in
terms of the fundamental alteration of the par-
1
Appeal of Clark Concrete, GSBCA 14340 99-1 BCA @ ties’ bargain resulting from the change.”2
630, 820 (1999).

104 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

The Armed Services Board of Contract ity caused by a change to the contract scope
Appeals has also found that two types of pro- of work, as well as the cumulative impact of
ductivity impacts can arise from changes to changes in scope to the unchanged work. In
the contract and the board wrote as follows: the past, many contractors have used the
MCAA factors only when “forward pricing” a
“It is undisputed that the costs of performing
loss of productivity component of a change
changed work include both (a) those costs
order proposal. In addition to providing
directly related to the accomplishment of the
updated general instruction on the uses of the
changed work, called ‘hardcore costs,’ and
MCAA factors, this chapter seeks to explain
(b) those costs arising from the interaction
how the MCAA factors can also be applied
between the changed work and unchanged
equitably and reasonably when retroactively
work or expended to offset inefficiencies
quantifying the cumulative effects of changes
experienced as a result of changes, called
on the productivity of a construction project.
‘impact.’ Viewed broadly, ‘impact’ embraces: the
man hours, labor costs, and material costs that
are expended to offset inefficiencies experi- General Discussion of Loss of
enced as a result of Government-caused or Labor Productivity
contractor-caused changes or other departures
To offer the lowest bid price or negotiated
from the plan. Included is the process by which
price for a construction project, labor intensive
the above inefficiencies in the performance of
contractors such as mechanical and electrical
contract work are created.
contractors must plan to control labor produc-
Among other things, ‘impact’ includes: inefficiencies tivity. Controlling the productivity of labor
due to overcrowding, over or undermanning, skill during construction is central to maintaining a
dilution, extended overtime, shift work, and local fair and reasonable profit. When events occur
and cumulative disruption. which could not reasonably be foreseen by a
contractor during the bidding or negotiating
‘Local [or direct] disruption’ refers to the direct
process, and which materially and negatively
impact that changed work has on other unchanged
impact the contractor’s labor productivity
work going on around it. Conceptually, for purposes
through no fault of the contractor, the con-
of this appeal, ‘cumulative disruption’: Is the disrup-
tractor should consider seeking recovery of the
tion which occurs between two or more change
costs of the loss of labor productivity.
orders and basic work and is exclusive of that local
disruption that can be ascribed to a specific change. For the purposes of this chapter, “owner” refers
It is the synergistic effect . … of changes on the to the party with whom the contractor exe-
unchanged work and on other changes.”3 cuted a “contract.” If a subcontractor, it could
be the general trade contractor; if a prime
It is clear that a contractor must consider both
mechanical/electrical contractor, it could be the
the direct impacts of a loss of labor productiv-
project “owner,” whether public or private.
2
Appeal of Centex Bateson Construction Co., Inc., VABCA- Contractors have long understood that adding
4613 and 5162-5165. new scopes of work to the original work plan
3
Triple “A” South, 94-3 BCA P 27, 194, ASBCA No. 46, can disrupt the flow and rhythm of the other-
866.
wise productive crews. The added work often

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 105
Productivity

comes at the peak of the planned effort on the of either not executing change orders due to
project, when craft levels are already at their the risk of waiving its rights or placing a “reser-
highest points on the labor curve. Also, added vations of rights” statement on each change,
scope often affects the schedule, available which can have the effect of holding open the
work spaces, ability of labor supervisors to option of making further requests for equitable
effectively manage base contract craft labor, adjustment should the contractor suffer pro-
material and equipment procurement and ductivity losses due to the cumulative impacts
many other productivity-related factors. Some- of changes in scope on the project.
times the effects of a scope change/change
Productivity loss recovery, which is sought at
order, or a series of such changes, on labor pro-
the end of a project phase or after the project
ductivity can be of a higher dollar value than
is concluded, is called a retroactive productiv-
the direct cost of the change itself.
ity loss analysis. Such retroactive productivity
Assuming that the contractor did not cause loss analyses take into account the total
the changed conditions, the contractor should impacts of all unanticipated categories of
seek to recover those losses in labor productiv- potential loss, such as the quantity (in terms
ity either within the change order, or, if neces- of added craft hours) of changes, resequenc-
sary, at the end of the project when all of the ing, schedule delays and disruptions, over-
effects of project-wide changes on the total time and shift work and increase in crew size
labor productivity can be measured. The courts over the optimum level.
have stated clearly that exact methods of loss
Many experts in the field of productivity loss
of labor productivity quantification are not a
analysis believe that the only means of recov-
condition precedent for recovery. Boards and
ering a significant portion of productivity loss
courts have recognized the difficulty of meas-
is to measure such losses in their totality, at
uring productivity loss and allow the contrac-
the end of the project, particularly when such
tor to use several methods, including the
losses are a result of a large number of scope
MCAA factors, to measure such losses.
changes,4 which add a significant number of
Often, contract language known as “full accord craft hours. This is believed to be true because
and satisfaction” language, contained in some it can be very difficult to evaluate fully the
change order forms, may require the contractor effects of productivity loss caused by one, sin-
to attempt to price all categories of productivity gle change in scope on the contractor’s entire
loss within the change itself, as estimated val- labor force, when it may not be known how
ues. This is called a forward priced productivity many changes will be forthcoming in a given
loss and the cost of this estimated loss can be time period and how the aggregate of those
included as a line item in the change order pro- potential impacts will increase the contrac-
posal. While it can be highly beneficial to
include all estimated impacts within a change
order, thus “closing out” the change, many 4
“Scope changes” refers to any changed condition that
owners refuse to recognize labor productivity is outside of the contractor's scope of work. These can
include added items of work over which there is no
impacts caused by scope changes or other fac- dispute (i.e., approved and pending change orders),
tors beyond the control of the contractor. This disputed scope items, differing site conditions, and
leaves the contractor in the unwanted position acceleration proposals.

106 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

tor’s overall productivity losses. Such claims While the trend at the boards of contract
are typically called “cumulative impact” appeals had been to define waiver language
claims and are a recognized phenomenon by contained in change order forms as only
the major boards of contract appeals. It is waiving all impacts (direct and indirect costs)
understood that on projects pervasively and that were “knowable” at the time the change
adversely affected by changes in scope, the order was signed, the current trend points to
only reasonable means of recovery may be much stricter and broader interpretations of
through a cumulative impact claim rather waiver language on change order forms. An
than a forward priced, or individually priced, example of a generally “unknowable” impact
loss of productivity quantification. is labor inefficiency caused by cumulative
impacts: those impacts arising from a multi-
Nevertheless, both methods of productivity
tude of unanticipated labor-intensive changes
loss—the forward priced and retroactively
in scope. Since cumulative impact labor inef-
priced—are valid, and each project may
ficiency claims can only be quantified when
demand the use of either, or both methods,
all of the changes are known and the work is
described herein.
complete, in the recent past it was success-
In terms of actually measuring a loss of labor fully argued that a contractor was not under-
productivity, several methods may be available stood to have waived its cumulative labor
to the contractor. A highly regarded method of inefficiency impact claim on executed change
measuring productivity loss is known as the order forms containing “full accord and satis-
“measured mile.” This approach utilizes actual faction” language since such impacts are not
productivity measurements taken in unaffected fully known while the project is active.
and affected portions of a project and, from
In line with the earlier cases, the recent U.S.
that data, a productivity ratio is established.
Court of Federal Claims case of Bell BCI Com-
However, many contractors do not maintain
pany v. United States, 81 Fed. Cl. 617 (2008)
labor hour tracking and material installation
upheld the proposition that cumulative
records needed to support this methodology
impact labor inefficiency claims were under-
and on some projects, there are no unimpacted
stood to be preserved even in the presence of
labor hours. In such cases, the MCAA factors
waiver language on change order forms.
can be very useful and have been accepted by
However, on appeal, this decision was
courts and boards as a reliable means of esti-
vacated in part by the U.S. Court of Appeals
mating a contractor’s loss of labor productivity.
for the Federal Circuit. The Court of Appeals
It must be stressed that the contractor should did not issue a finding as to whether or not
carefully study the contract general and special the contractor sustained a loss of productivity
conditions, the project schedule, change order caused by cumulative impact. Rather, the
forms and other, related documents to under- Court of Appeals found that the broad waiver
stand fully the rights, liabilities, obligations, language contained on the government’s
limitations and remedies which are provided change order form had released the govern-
for by the documents that comprise the overall ment from any and all liability beyond the
contract. These documents may dictate which express relief provided for in the change
method the contractor uses on a given project. order itself.

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 107
Productivity

The Appeals Court wrote, “The language [on changes in scope, the contractor must deter-
the change order form] plainly states that Bell mine if the change requires a departure from
released the government from any and all lia- the contractor’s otherwise productive work
bility for equitable adjustments attributable to flow. A change of very limited scope, which
Mod 93.” The Court further wrote, “if parties may affect only a small crew, and which may
intend to leave some things open and unset- occur in a limited and distinct area of the
tled, their intent to do so should be made man- overall project, may have little or no measura-
ifest.” As such, the contractor was barred from ble negative impact on productivity. However,
recovering its cumulative impact labor ineffi- such changes in scope are rare. Generally,
ciency costs for the contract modifications that changes occur in the most active areas, and at
contained the government’s waiver language. times when crews are at or near their peak.
These types of changes can have a significant,
Based on this appeal, it would be wise for a
negative effect on crew productivity.
contractor to assume that if broad waiver lan-
guage is present on the change order form, In order to estimate potential losses of pro-
such language will be viewed as a waiver of ductivity using the MCAA factors, questions
the contractor’s right to later claim for any can be posed to the contractor’s labor super-
added compensation, even for those costs visor(s) by management:
attributable to a cumulative impact claim that
cannot be quantified until the project has 1.a)Will this change in scope cause us to add craft
been completed. Thus, if a contractor believes workers to our current work force, and if so,
that a cumulative impact claim may be forth- how many workers will need to be added,
when will they be added and for how long?
coming due to a large volume of labor-inten-
sive changes in scope, change order forms con- 1.b)Answers to 1.a could lead to adding the
taining broad waiver language should only be appropriate percentage for MCAA factors
executed after careful weighting of the poten- such as:
tial cost impact of a waiver (i.e., waiver of Crew Size Inefficiency
future cumulative impact claims) and with the Learning Curve
advice of experienced construction counsel. Dilution of Supervision

Use of the MCAA Factors for


Forward Pricing Scope Changes
The MCAA factors can be applied to a pricing 2.a)Will this change move our crews into
sheet for a scope change on an itemized basis. unanticipated, severe cold, hot, rainy or
Once the direct costs of the change have been windy seasons?
estimated—the labor, supervision, material,
2.b)The answer to this question could lead to a
equipment and other such costs—the contrac- percentage for:
tor can apply one or more of the MCAA fac-
Severe Weather
tors to the change order breakdown sheet. In
order to evaluate properly the estimated,
potential impacts to labor productivity of

108 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

mated effects of the changed condition on


3.a)Will this change cause us to shift existing
the labor hours being analyzed; i.e., specific
crews to new areas, to stop work where we
are, remobilize in another area, then return hours within the total hours expended, or
to finish the original work scope? on the total hours expended on the project
depending on the approach being used.
3.b)The answer to this question could result in Also, the three levels of intensity allow the
the addition of multiple MCAA factors to the user to more specifically assign an estimated
change order pricing:
impact for each of the MCAA factor cate-
Reassignment of Manpower
Learning Curve gories being used, and like the categories
Dilution of Supervision themselves, should be applied with care and,
Stacking of Trades if at all possible, with input by those who
Concurrent Operations witnessed the conditions under evaluation.
While this chapter cannot provide for each
and every condition under which contractors
4.a)Will this change in scope cause us to work in will choose a particular MCAA factor or fac-
areas which were unanticipated, with other tors, or the level of impact intensity, it is obvi-
trades, which were not planned for in the ous that care must be taken to eliminate over-
same area, and for how long? lapping factors, to the fullest extent possible.
The unrestrained and ill considered choice of
4.b)Answers to 4.a could lead to adding the
multiple factors can lead to unreliable results.
appropriate percentages for MCAA factors
such as: For instance, the factor describing “Morale and
Stacking of Trades Attitude” is a valid, but somewhat amorphous,
Site Access
category of inefficiency. The effects of a decline
Concurrent Operations
Logistics in workplace morale and attitude can be
Ripple embodied in several other MCAA factors, such
Reassignment of Manpower as stacking of trades, overtime fatigue and reas-
Learning Curve signment of manpower. It would be impossible
to determine what portion the impact percent-
age caused by stacking of trades, overtime
These are the types of conditions, for the
fatigue and reassignment of manpower is
purposes of examples, which can result from
attributable to the attendant decrease in worker
the issuance of changes in scope, and which
morale and attitude. Thus, by way of the above
can cause a loss of labor productivity. The
example, when using other factors that may
contractor must apply the appropriate factor
already include in the loss of productivity fac-
categories and percentages.
tor a consideration for decreased worker morale
“Factors Affecting Labor Productivity” and attitude, it may be advisable to avoid
includes three levels of potential productiv- applying a potentially duplicative factor such
ity impacts—“Minor,” “Average,” and as “Morale and Attitude.”
“Severe.” Each level of impact intensity car-
Another example to consider when striving
ries its own loss of productivity percentage.
to avoid factor duplication is the “Ripple
The three impact levels indicate the esti-

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 109
Productivity

Effect.” This term of art has been used in sev- unchanged for over 30 years, provides gener-
eral board decisions and is a well recognized ally ample explanation of the type of impact
phenomenon in the construction industry. described in each MCAA factor category.
This MCAA factor describes the downstream
It is important to understand that the MCAA
effect on the mechanical contractor of
factors provide a basis for developing reason-
impacts caused to predecessor trades. For
able estimates of loss of labor productivity
example, the mechanical contractor’s sched-
and not for developing a loss with exactness.
ule may be compressed because the building
Thus, when the MCAA factors and their
structure was erected late. In order to mitigate
respective impact percentage are chosen, it
the structural delay, the general trade contrac-
must be with the intent to connect the cause
tor may accelerate the follow on trades by
or causes of the inefficiency with the reason-
stacking the crews of the various subcontrac-
able effects. The MCAA factor descriptions
tors, or forcing the subcontractors to work on
represent the “cause” and the impact inten-
an overtime basis. In such cases, the loss of
sity percent represents the “effect” that can
productivity may be better classified by the
result from the conditions described by each
events that result from the ripple effect, such
MCAA factor. However, care must be taken to
as “Stacking of Trades” or “Overtime Fatigue.”
consider potential duplication and overlap-
On some projects, a mechanical contractor ping when the factor categories are chosen.
may add labor supervision in order to mitigate
Likewise, the assignment of the impact
a loss of productivity caused by an unplanned
intensity percentage must be chosen with
requirement to substantially increase its work
care. For instance, if the change in scope is
force. In such cases, the contractor generally
of a limited nature, on a project with a rea-
submits a request for equitable adjustment for
sonably small crew size with little or no
its added supervisory costs. Such additions of
schedule impact (as opposed to productivity
supervision usually do not totally eliminate
impact), then a “minor” category can be
the contractor’s labor inefficiencies. The con-
chosen. However, if the change is significant
tractor may have suffered inefficiencies such as
in its scope and requires major rescheduling
“Stacking of Trades,” “Logistics,” or “Reassign-
and/or resequencing, crew size increases,
ment of Manpower,” which the added labor
overtime, shifting of work areas, piece-
supervision could not mitigate or eliminate.
mealing of the work and general disruption
However, where the contractor’s supervisory
of the rhythm of the crews, then “average”
forces are effectively increased, it may be
or “severe” impacts could be the result.
duplicative for the contractor also to assert
productivity losses arising from the MCAA fac- When the factor for “Crew Size Inefficiency”
tor “Dilution of Supervision.” is used, it is most helpful to have on hand a
planned craft level chart based on the esti-
Indiscriminate assignment of the MCAA factors
mate or the project plan. When attempting
can result in estimates that may be overstated
to demonstrate that conditions beyond the
and unreliable. Therefore, careful “testing” of
contractor’s control resulted in a loss of
each MCAA factor and its impact intensity
productivity, it is very helpful to show
must be carried out by the contractor. The
graphically what the contractor reasonably
description of each factor, which has remained

110 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

expected. Therefore, an estimated/planned tively priced methods). Another highly


versus actual craft curve is often helpful in regarded method of measuring productivity
graphically depicting the effects of loss is the “measured mile.” This approach
unplanned crew size growth. utilizes actual productivity measurements
taken in unaffected and affected portions of a
The percent values for each category chosen
project, and from that data, a productivity
are additive in the change order pricing.
ratio is established. However, as previously
Once all of the factors have been carefully
noted herein, many contractors do not main-
evaluated for each changed condition caused
tain labor hour tracking and material installa-
solely by the proposed change in scope, the
tion records needed to support this methodol-
percentages are added together. The total per-
ogy and on some projects, there are no
cent is then multiplied against the estimated
unimpacted labor hours. In such cases, the
craft labor hours for the change. For instance:
MCAA factors can be very useful in estimating
the contractor’s loss of labor productivity.
Change order estimated craft
labor hours: 2,750 hours
MCAA factor: Modified Forward Pricing for
Crew Size Inefficiency 10% Estimating Labor Loss of
Learning Curve 5% Productivity on the Changed
Reassignment of Manpower 5% and Unchanged Work
Total 20%
It is a well understood principle that when sig-
Estimated Loss of Productivity nificant changes in scope are issued to a con-
(2,750 x 20%) 550 hours
tractor, a loss of labor productivity may affect
Subtotal, Craft Labor Hours: 3,300 hours
the change order labor hours and the base con-
tract labor hours. Previously herein, a method
As stated previously, this methodology prices was described which only measured a loss of
the estimated loss of productivity caused by productivity on the estimated change order
project conditions only on the estimated hours. This segment deals with estimating the
change order hours. But what about the effects of significant and pervasive changes in
impacts of change order work on the scope on the contractor’s entire labor forces,
unchanged hours? It is infrequent that a both those working on the changed work and
change in scope is so segregated from the base those working on base contract labor; known
contract work that it has no effect on the as “the effects of changes in scope to the
crews performing unchanged, base contract unchanged, or base contract, work.”
work. How does the contractor recover the The principle is the same as is often employed
cost of a productivity loss caused by changes to describe the overarching effects of overtime
in scope to the unchanged work? There are fatigue as it impacts the overtime hours and
several ways to estimate the impacts to labor the straight time hours worked by the overtime
productivity of changes to the unchanged crews. Obviously, if a crew works for eight
work, two of which use the MCAA factors weeks of scheduled overtime, 10 hours per day
(i.e., the modified forward priced and retroac- for six days per week, the fatigue and its result-

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 111
Productivity

ing effects impact both the straight time and The “time specific” method is used for both
the overtime hours worked by that crew. There this modified forward pricing method and
is no way to segregate the impacts of this sort the retroactive pricing method (with slightly
of loss of productivity factor between straight different rules), which will be described later
time activities and overtime activities. in this chapter. The “time specific” method
also requires significantly more information
Similarly, if the owner issues a major scope
than does the standard forward pricing
change, or issues many changes in scope in
method, but it attempts to quantify loss of
the same general time frame, it may be impos-
labor productivity to both the change order
sible for the contractor to segregate the loss of
and base contract hours.
labor productivity to the change order work
from the loss of productivity imposed on the This method has some requirements, which
base contract work by the changes in scope. may not be possible to meet because of
problems inherent with the issuance of
As an example, a crew of nine pipe fitters is
change orders. Some of the field conditions
working productively on base contract work.
which can restrict or eliminate the effective
The owner issues a change, which requires four
use of this method include:
of this crew to move to scope change work.
The craft supervisor for this crew must now 1) Unknown timing of owner’s approval of
divert his attention from the total crew per- the change order “notice to proceed;”
forming base contract work to setting up the
2) Lack of foreknowledge on the part of the
new “sub-crew” performing the scope change
contractor regarding pending changes in
work. The remaining five workers’ productivity
scope which are to be released by the
on the base contract work suffers because work
owner for pricing;
is not being laid out as it was when the super-
visor was focused only on the planned work of 3) Performance of the scope change work
the single crew; answers to workers’ questions without change order execution; and
take longer to resolve and materials and tools 4) Not knowing what existing crews will be
are frequently “borrowed” from contract work affected by the change order work.
to perform scope change work. These impacts
are defined by “Dilution of Supervision,” “Reas- Since these conditions are very prevalent on
signment of Manpower” and perhaps other construction projects, the contractor may
MCAA factor categories. This is only one exam- still be left with only three options: 1) use
ple of how a change in scope can affect the the method which limits loss of productivity
productivity of both the change order hours estimates to the change order hours only; 2)
and the base contract hours. wait until the project is over and perform an
overall loss of productivity analysis; or 3)
When attempting to estimate and recover forego making any attempt to recover the
such losses in labor productivity when loss of productivity costs from the party
changes of a significant magnitude affect making the change.
the base contract work force, a modified
approach can be employed. It is called a However, if the project conditions allow the
“time specific” MCAA factor method. use of the modified approach, the general
format is as follows:

112 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

1) The time frame of when the change In this example, a specific time frame has
order work will be performed must be been evaluated for estimated impacts. This
known or estimated—in days, weeks, or more specific method permits the contractor
at most, monthly increments. to make MCAA factor applications, which
can vary as estimated conditions vary. This
2) The conditions of the change in scope
is actually more realistic and compares well
must be known—what types and mag-
with what actually happens in the field
nitudes of impacts are anticipated.
when changes are issued, or when accelera-
3) The planned craft hours for the affected tion or other impacts occur. In reality, as
period must be ascertained from esti- time and conditions in the field change, the
mates, labor plans or other labor forecast MCAA factors can change as well and the
reports. estimate should reflect this fact.
4) The crews which could be affected by the For instance, if the MCAA factor “Learning
change must be known (i.e., some Curve” is applied to a change, which is esti-
changes may only affect certain physical mated to have a long term effect, this factor
areas of an overall project, and therefore, may only be applicable for the first two to
not the entire work force). four weeks of the impact, as new workers
5) A table is prepared with planned hours become familiar with the work area. This
per period (day, week or month) across methodology allows for a more precise esti-
the top, including the estimated change mation of loss of labor productivity impacts.
order hours. The appropriate MCAA Similar to the concept of performing time
factors are listed along the “y” axis of the specific analyses, it is also appropriate to deter-
table. Under each time period, the mine if the contractor’s entire crew will be
appropriate MCAA factor percentage is affected by the changes. If a change in scope
estimated. The percentages may change only affects a separate and discrete area of the
from period to period based on the esti- project, it may not be appropriate to impact
mated impacts. The percentages are then the total crew hours by a loss of productivity
totaled and multiplied against the total, factor. It is generally appropriate to use the
estimated/planned craft hours. MCAA factors on only those crews that will
6) An example of a resulting table follows: be affected by the changed condition.

C.O. Impact Period Week 1 Week 2 Week 3 Week 4 Week 5 Week 6


Orig Planned Hours 400 400 600 600 720 800
Est C.O. Hours 80 160 320 400 400 160
Revised Planned Hrs 480 560 920 1,000 1,120 960
Learning Curve 5% 5% 5% 0% 0% 0%
Dil of Supervision 0% 10% 10% 10% 10% 10%
Crew Size Ineff 0% 0% 10% 10% 10% 0%
Total MCAA factor 5% 15% 25% 20% 20% 10%
Est Loss of Productivity 24 84 230 200 224 96
Total 858

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 113
Productivity

Unfortunately, many owners simply do not and with such care so as to accommodate the
recognize the effects of significant or numer- loss of productivity, the work activities will
ous changes on the productivity of the base take longer than planned.
contract labor. However, virtually all contrac-
In this example, the 18-day planned activity
tors recognize this condition as a costly loss
in the series will take approximately 22 days
of labor productivity. Therefore, the contrac-
each to perform, given an estimated loss of
tor is frequently left with only one option, a
productivity of 20 percent. The adjustment of
post-project measurement of productivity loss
the project schedule for estimated losses in
caused by conditions that are not the fault or
productivity can have a significant impact on
responsibility of the contractor.
the critical path, and on forecasted job costs.
As can be seen in the graphic on page 115,
Impacting the Project Schedule the extension of a duration of a planned
Using the MCAA Factors activity by adjusting the duration for an esti-
mated loss in productivity using the MCAA
This chapter does not deal with the develop-
factors can materially affect the schedule.
ment of the schedule time impact analysis
(“TIA”) or “fragnet.” However, contractors
should impact the current project schedule Retroactively Pricing Losses of
activities with the loss of productivity esti- Labor Productivity Using the
mates derived from using the MCAA factors.
MCAA Factors
For instance, a contractor originally planned In many instances, the only option for a
a series of activities as shown below. One of contractor attempting to recover a loss of
the activities was adversely affected due to a labor productivity caused by changed con-
change, resulting in a 20% impact to pro- ditions is to wait until the project is over
ductivity. Inefficiency can impact schedule and review the actual loss; planned versus
durations and as such, the duration of the actual. Such claims are sometimes known as
affected work must also be factored. Unless “cumulative impact” claims. The “plan” can
crews are added, the originally planned be the original estimate of craft hours or the
duration for “Piping Branches” would preconstruction target plan. Before a con-
increase from 18 days to 22 days as a result tractor makes a claim for a loss of labor pro-
of the 20 percent impact to productivity. ductivity at the conclusion of a project, sev-
The loss of labor productivity will, in general, eral obvious considerations must be made,
cause planned activities to take longer to per- including:
form, because the productivity ratio of 1:1, 1. Was the estimate/plan of craft hours
which was most likely used as the basis of the accurate and reasonable?
activity duration estimate, is no longer accu-
rate. The contractor will no longer receive 2. Were the conditions, which caused the
one hour’s production for an hour planned, loss of productivity, reasonably foresee-
but rather some production rate less than the able when the project was bid/negotiated?
plan. Therefore, unless crews and supervision 3. Did the contractor cause this loss of
are added to the schedule in such numbers productivity?

114 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

4. Were the principal causes for the loss of actions and/or inactions to the contractor’s
productivity the responsibility of injury. This chapter assumes that the contrac-
identifiable parties? tor has already determined liability and causa-
tion, and is attempting to quantify the “resul-
5. Will the potential cost of recovery
tant injury” by the use of the MCAA factors.
exceed the loss?
Assuming that the contractor is satisfied that
There are a series of important legal
the loss of productivity is significant and is
considerations which could be added to this
principally the fault of another identifiable
list which can only be addressed between the
party, and that party is legally accessible for
contractor and his construction counsel, and
redress, then the contractor must prepare
which are not the subject of this chapter.
the cause and effect analysis.
Additionally, this chapter addresses several
methods of calculating a loss of productivity Frequently, contractors use the MCAA fac-
using the MCAA factors; however it does not tors to retroactively price the cumulative
address the means and methods of proving effects of changes in scope. Often, the
the impacts, often known as the “triad of method used by contractors is to multiply
proof,” which includes proving (a) liability; the cumulative percentage of losses of pro-
(b) causation; and (c) resultant injury. This is ductivity as derived from the MCAA factors
also known as the “cause-and-effect” connec- against the total, actual hours expended,
tion, which is necessary in linking an owner’s sometimes with, and sometimes without,

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 115
Productivity

change order hours included in the total.5 ering the impact caused by the executed
change orders;
This methodology of multiplying the MCAA
factor percent against the actual hours is 5. Hours expended by crews that were not
incorrect. The actual hours against which the affected by a loss of productivity;
MCAA factors are frequently multiplied in a
6. Other types of productivity losses for
contractor’s retroactively priced claim for loss
which the contractor is responsible (i.e.,
of productivity already include the contrac-
bid errors)
tor’s loss of productivity; therefore multiply-
ing the MCAA factors against the actual hours Also, some contractors simply apply the total
overstates the loss of productivity. Only by MCAA factor percentage to the total actual
removing the theoretically efficient hours hours for the entire project duration. This can,
from the contractor’s actual hours can the in some instances, lead to inaccurate results
MCAA factors be properly applied in a retroac- because the effects of labor inefficiency can
tively priced request for equitable adjustment. change during the life of the project.
The actual hours must be further adjusted to The MCAA factor percentages sometimes
deduct: change as actual project conditions change.
Therefore, it can be useful to assign the MCAA
1. Time and materials hours;
factors to the specific impacted time frames
2. Hours spent to repair the contractor’s within the overall project duration. In some
defective work; cases, multiplying an MCAA factor against the
total hours expended for the total duration of
3. Change orders on which a loss of pro-
the project will result in a distortion (on the
ductivity has already been calculated; (If
high side) of the forecasted loss of productivity.
the contractor has included “forward
priced” loss of productivity in individual, The loss of productivity categories described
executed change orders, and then seeks by the MCAA factors can occur in a non-
to recover global losses at the end of the linear fashion across the entire duration of a
project, these incremental, per change project. To more accurately demonstrate the
order loss estimates must be factored out retroactive loss of productivity on a project,
of the computations.) it may be desirable to divide the project into
months (or, if possible weeks) and to assign
4. Hours associated with executed change
loss of productivity percentages by MCAA
orders, where it has been determined
categories by time periods, based on the
that the contractor is barred from recov-
accounts of eye witnesses (field managers,
labor supervisors and other fact witnesses) or
on documents prepared contemporaneously.
5
As noted herein, it is imperative that the contractor Consideration of the areas of the project and
carefully read the contract, including all general and the crews working in those areas is very
special conditions, as well as the change order forms important in performing this analysis. Only
offered for execution by the owner. The contract terms
set forth in such documents will, in most cases, dictate the crew hours that have been impacted by
the contractor’s rights of recovery and obligations for the changed conditions should be included
timely notice of delay and inefficiency claims.

116 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

in the loss of productivity computations. 3. Craft hours deducted for time and
This is similar to the format for the modified material ticket work, the contractor’s own
forward pricing method, described previ- deficient work (rework), any estimated,
ously. self-inflicted productivity losses, crew
hours that the contractor believes were
When it is possible to apply this procedure,
not affected by the changes in scope, such
the types of losses described by the MCAA
as crews working in areas of the project
factors can be more accurately assigned to
not proximate to the areas where the
discrete time periods. The following table
changed work was performed, and change
shows an example of this type of time-
order adjustments as described herein.
specific assignment of MCAA factors. Differ-
ent MCAA factor categories can affect differ- 4. The resulting “revised actual hours.”
ent periods of a project and at different
5. The list of the MCAA factor categories
percentages of impact intensity. As stated, it
being applied.
may be inaccurate to globally apply the
cumulative MCAA factors against the total 6. The resulting estimated loss of produc-
hours expended on a project. It may, tivity for each time period.
depending on the specific circumstances, be Note that the total MCAA factor percentage
more accurate for the contractor to evaluate has not been multiplied against the revised
the loss of productivity on a periodic, rather craft hours. Instead, the percentages have
than on a total project, time scale. been totaled, the adjusted hours divided by
The following table demonstrates the as-built, one plus the decimal percent (i.e., 1.05 for
retroactive loss of productivity analysis using the first period in the table), and that result
the MCAA factors, the rows indicate: subtracted from the total, adjusted hours.
One significant difference between forward
1. The actual work period being measured
estimated and retroactively estimated pro-
for impacts.
ductivity loss is that the contractor’s actual
2. The actual, payroll craft labor hours labor hours already include the loss of pro-
(without supervision). ductivity. Therefore, it is necessary to calcu-
late the productive hours first to avoid over-
stating the loss of productivity.

Contract Period Week 40 Week 41 Week 42 Week 43 Week 44 Week 45


Actual Payroll Hours 1,600 1,600 1,800 2,400 2,400 3,200
Deducted Hours –80 –120 0 –120 –120
Revised Actual Hours 1,600 1,520 1,680 2,400 2,280 3,080
Reassignment of Mpw 5% 5% 5% 10% 10% 10%
Dil of Supervision 0% 10% 10% 10% 10% 10%
Crew Size Ineff 0% 0% 10% 10% 10% 10%
Total MCAA factor 5% 15% 25% 30% 30% 30%
Est Loss of Productivity 76 198 336 554 526 711

Total 2,401

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 117
Productivity

For instance, referencing the preceding The “Should Have Spent”


table, during week 42, the contractor actu-
Labor Hours in a Retroactive
ally expended 1,800 labor hours. However,
120 hours were spent on time and materials Loss of Productivity Calculation
work or repairing deficient work and were One of the foundations of a loss of labor
subtracted from the total, leaving 1,680 as productivity claim is to determine how many
the adjusted labor hours. After removing the hours the contractor should have spent to per-
contractor’s self-inflicted inefficiencies, if form the work had the contractor not been
any, hours not affected by the changes, or affected by events caused by others.
the hours for which the contractor was paid The purpose of dividing the actual,
for the inefficiency (i.e., T&M), what adjusted6 labor hours by 1.n, where n is the
remains are actual labor hours that already decimal % of the total of the selected MCAA
include the non-contractor caused losses of factors, is to derive the “should have spent”
productivity. hours on the project. Once the “should have
After interviewing the site personnel, if it is spent” hours have been calculated, then
determined that a 25 percent loss of produc- these hours can be subtracted from the total,
tivity occurred, then the contractor must adjusted actual hours to determine the
determine the number of hours that were hours of lost productivity. In a hypothetical
efficient based on that estimated loss. Thus, project, one without changes in scope, esti-
taking the 1,680 craft hours and dividing mate errors and contractor-caused inefficien-
that by 1.25 results in 1,344 efficient hours. cies, the calculated “should have spent”
Had the contractor not suffered any loss, hours should, theoretically, equal the origi-
1,344 hours should have been spent on the nal estimated hours. However, this hypo-
work. The difference of 336 hours are those thetical condition almost never exists.
attributed to the identified loss of productiv- The actual hours are affected by a series of
ity described by the MCAA factors. inextricably intertwined events, such as
With the above analysis, the hours the con- impacts of changes to the unchanged work,
tractor should have spent, if no loss of pro- impacts caused by the direct hours of change
ductivity had been encountered, have been order work to the changes themselves, and
calculated (1,344 hours). Since the contrac- other factors that affect the number of labor
tor has estimated that the workers were hours actually expended on a project. There-
impacted by a 25 percent loss, the resulting fore, it is highly unusual when the calculated
labor hours being claimed for recovery is “should have spent” hours equal the original
336. If the contractor simply multiplied the estimate of labor hours. The frequent inabil-
25 percent times the adjusted actual hours ity to match the original estimated hours
(1,680 x 25%), the resulting loss would be
estimated at 420 hours. The overstatement 6
Adjusted (reduced) to account for such items as the
of loss would have been 84 craft hours (420 contractor’s remedial work, forward priced inefficiencies
– 336) if the MCAA factor calculation had contained in change orders, contractor-caused ineffi-
been misapplied. ciencies and in some cases, the hours directly associated
with executed change orders.

118 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

with the “should have spent” hours only


demonstrates that many factors can enter 10,000 estimated/planned hours
into the total hours expended on a construc- 18,000 actual hours less the remedial work of
tion project, some of which can be difficult, 300 hours = 17,700 hours
or impossible, to identify and to quantify on
an individual basis. 17,700 adjusted, actual hours divided by
1.30 (1 + 30%, or 1.30) = 13,615 hours
Calculating the “should have spent” hours:
17,700 adjusted, actual hours less 13,615
“should have spent” hours =
Example:
4,085 inefficient hours
A contractor estimates a project to require
10,000 hours of field erection labor.
At the conclusion of the project, the con- The 4,085 hours represent the hours of lost
tractor determines that 18,000 hours of field productivity caused by all types of non-
labor were actually expended to construct contractor caused impacts as calculated
the project. using the MCAA factors. The 13,615 hours
are the “should have spent” hours if 17,700
The contractor determines that approxi- adjusted, actual hours were spent and the
mately 3,000 hours were expended on out- project suffered an overall productivity loss
of-scope work, which came in the form of of 30 percent.
change orders and/or scope changes. The
contractor also determines that approxi- From the above example the obvious question
mately 300 craft hours were spent removing arises—what comprises the difference of 3,615
and replacing work which was improperly labor hours between the original estimate and
installed by the contractor’s own forces. the calculated “should have spent” hours
(i.e.,13,615 “should have spent” hours—10,000
The contractor then reviews the project originally estimated hours)? The difference will
documents, interviews the management most likely be comprised of the hours
team, and determines that owner-caused expended on scope change/change order work,
problems, such as scope changes, disruptions the loss of labor productivity caused by the
and acceleration, have caused a loss of pro- change order/scope change work and all cate-
ductivity on the project. A review of the gories of contractor-caused issues other than
change orders themselves reveals no lan- the hours subtracted in the “adjustment” phase
guage which could bar the contractor from of the computation (in this example, the sub-
recovering losses of productivity caused by traction of 300 labor hours which were attrib-
the change orders. uted to the contractor’s own forces).
Using the MCAA factors, the contractor When the estimated 3,000 hours in scope
interviews the management team and change/change order work are subtracted
determines that the combined impacts from the “should have spent” hours of
caused by the owner, as described in the 13,615, the result is 10,615 hours. The
applicable MCAA factors, is estimated to be remaining 615 hours (i.e., 10,615—the
30 percent. In this simplified example: estimate of 10,000 hours) are unidentified,

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 119
Productivity

non-productive hours for which the con- guage. Therefore, it is absolutely essential that
tractor is not making claim. the contractor review with counsel all pro-
posed change order forms and other
It is often alleged by owners that contractors
contract documents7 that seek to limit the
do not account for their own inefficiencies
contractor’s right of recovery—before the
when calculating a loss of productivity claim.
contractor executes such documents.
The aforementioned calculation demonstrates
that the contractor has not made claim for In the event that the contractor, or the
615 labor hours, which can be characterized contractor’s counsel, determines that change
as non-productive labor hours for which the order hours will not be deducted from the
contractor has taken responsibility. By what- total, actual labor hours, it is necessary for
ever means chosen by the contractor, any the contractor to remove from the contrac-
contractor-caused loss of productivity must tor’s retroactively developed loss of produc-
be deducted from the total loss of productiv- tivity claim any forward priced loss of pro-
ity hours quantified in the contractor’s ductivity hours which were included in the
request for equitable adjustment. contractor’s executed change orders. This is
true because the MCAA factor calculation
In the above analysis, the performance of
should include all categories of productivity
change order work, as well as the contractor’s
losses, including those caused to the direct
base contract work, would be performed ineffi-
hours of the change orders themselves. To
ciently. Consequently, it could be appropriate
leave the forward priced productivity loss
for the contractor to recover losses of produc-
estimates in place when using the MCAA
tivity incurred in the performance of change
factors in a retroactive computation would
order work as a part of the contractor’s overall
be “double dipping.” In performing a total
retroactive loss of productivity analysis as
project, retroactive loss of productivity cal-
described above. However, as is discussed
culation, it is necessary to deduct the indi-
herein, it may be determined by the contrac-
vidual forward priced productivity losses,
tor’s counsel that “full accord and satisfaction”
which may have been included in the con-
language contained in executed change orders
tractor’s individual change orders proposals
bars the contractor from the recovery of pro-
submitted by the contractor to the owner.
ductivity losses on the direct change order
This deduction can be included when arriv-
hours. In such events, the contractor may
ing at the adjusted, actual labor hour total.
deduct the executed change order hours from
the total actual hours to arrive at the adjusted, The calculated “should have spent” hours
actual labor hours, as described in the appro- may include, in addition to the originally
priate section of this chapter. estimated hours: (i) actual change order/
scope change hours; (ii) inefficiencies caused
In some cases, the interpretation of the “full
to and by the out of scope work (subject to
accord and satisfaction” language is so broad
that the contractor’s cumulative impact claim
is barred in total or in part because such 7
Other contract documents such as the monthly
impacts are claimed to arise from the change payment requisition lien waiver and release forms
orders containing such exculpatory lan- must be reviewed carefully for exculpatory language
that may seek to limit or bar a contractor’s claims.

120 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

other possible limitations discussed herein);


(iii) contractor-caused losses of productivity; Total actual hours expended 18,000
(iv) contractor’s remedial work hours; and (Less) Estimated hours (10,000)
(v) estimating errors. Consequently, the (Less) Contractor’s remedial work (300)
comparison of the “should have spent” (Less) Change/scope change hours (3,000)
hours to the original estimate is generally Subtotal (hours) 4,700
not appropriate. What is important is that
(Less) Calculated MCAA factor
the owner is not being charged with the loss of productivity hours (4,085)
“should have spent” hours or for contractor-
Total of remaining hours 615
caused impacts in the retrospective produc-
tivity loss calculation as described in the
above example and elsewhere herein. The remaining 615 labor hours would be the
contractor’s productivity loss not claimed in
the contractor’s request for equitable adjust-
Modified Total Cost Method ment. These hours would remain as a poten-
Check of the Productivity Loss tially undefined, but unclaimed, loss of pro-
Calculations ductivity. Nevertheless, it could be concluded
that some portion of the 615 hours was
When using the retroactive productivity loss
attributable to a loss of productivity caused
analysis, it is prudent for the contractor to
by the 300 hours of remedial work. Thus,
check the estimated loss of productivity,
with this example, the contractor has taken
which results from using the MCAA factors
to its own account a loss of productivity
against the modified total cost method of
caused by its own actions and/or inactions.
calculating the loss of labor productivity.
The modified total cost method consists of a It is possible, however, for the remaining hours
very simple calculation: to be a negative number. If the remaining
hours are represented by a negative number, it
Actual expenditure in hours A would indicate that the contractor expected a
(Less) Estimated hours (B) savings in labor, as compared with the con-
tractor’s original estimate. While it is not
(Less) All types of contractor-
caused problems (C) impossible to put forth labor savings in a loss
of productivity claim, it does require an added
(Less) Change/scope change labor hours (D)
level of confirmation that savings in labor, as
Claimed loss of productivity hours E compared with the original estimate, would be
a reasonable expectation of the contractor.
This section will suggest a simple check on
The reasonable expectation could include a
the results of the loss of productivity calcu-
detailed analysis of the originally estimated
lations using the MCAA factors. This very
labor hours, a presence of an historical pattern
important calculation check is shown as an
of proven labor savings by the contractor on
example below using numbers from the
past projects, and a verification that the subject
“should have spent” example on page 119:
project lent itself to a higher-than-anticipated
productivity by such factors as the presence of

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 121
Productivity

a high degree of prefabrication or repetitive while the “full accord and satisfaction” lan-
work which was not fully addressed in the orig- guage contained on the executed change
inal estimate. If the remaining hours indicate orders barred the contractor from recovering
labor savings, the contractor will most likely retroactive, direct losses in productivity on the
have to demonstrate both the claimed losses change order work, it did not bar the contrac-
and the reasonability of labor savings, as com- tor from the board’s consideration of the
pared with the original estimate. alleged losses in productivity caused by the
change orders to the unchanged work.
Special Considerations for In the above referenced Veterans Adminis-
“Full Accord and Satisfaction” tration Board of Contract Appeals case, the
real party of interest was the electrical sub-
Change Orders when contractor. The electrical subcontractor did
Calculating the Loss of Labor not include any loss of productivity
Productivity “impact” costs in its change order pricing,
Many public and private owners are including and sought to recover loss of productivity in
in their change order forms language which its claim. The VA’s change order forms con-
attempts to bar the contractor from recover- tained “full accord and satisfaction”
ing, at a date after the execution of the language. Complicating the matter, there
change order, any added costs arising from was “reservation of rights” language on the
the change, such as loss of productivity. The part of the contractor also in evidence.
referenced language—that which attempts to The board ruled that it was the intent of the
bar the contractor from recovering additional parties to resolve all costs directly associated
costs arising from the change order after the with the executed change orders during the
execution of the change order—is called “full negotiations for change order pricing. How-
accord and satisfaction” language. The actual ever, the decision further stated: “We find that
wording varies from project to project, and Dynalectric’s claims for cumulative impact on
such language is best reviewed by the contrac- unchanged work … survive the accord and
tor’s counsel before the execution of the pro- satisfaction agreement.” The board found
ject’s first change order. that, whereas the electrical subcontractor was
Boards and courts have found that when such barred from recovery of productivity impact
language is included on executed change costs on the work directly covered by exe-
orders, the contractor may be barred from the cuted change orders, which contained the
recovery of added costs arising directly from “full accord and satisfaction” language, it
the change, after the execution of the change could attempt to recover the cumulative loss
order document. In some cases, the applica- of productivity impacts to the unchanged work.9
tion of exculpatory language is applied very
broadly to bar the contractor from any further
8
recovery arising from a change order contain- See: Appeal of Centex Bateson Construction Co., Inc.,
VABCA-4613 and 5162-5165.
ing such language. It is equally important to
9
note that, in a Veterans Affairs Board of Con- This determination by the board was in contrast to the
appellate decision in the more recent Bell BCI matter
tract Appeals case,8 the board found that described at page 107 herein.

122 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

Therefore, when the contractor’s counsel Court Acceptance of Loss of


finds that the contractor has executed
Productivity Calculations
change orders which contain enforceable
There are several court and board cases with
“full accord and satisfaction” language, the
published decisions which describe the use of
contractor may find it advisable to remove
the MCAA factors. The recent Appeal of Clark
from productivity loss calculations the hours
Concrete case, cited previously herein, clearly
(either estimated or actual) associated with
stated the board’s acceptance of the MCAA
the executed change orders. This deduction
factors publication in presenting a mechanical
would form a part of the adjusted, actual
contractor’s claim for loss of productivity. In S.
hour computation explained herein.
Leo Harmonay, Inc. v. Binks Manufacturing Com-
Many contractors do not maintain records pany, tried in the U.S. District Court, Southern
which memorialize the actual hours expended District of New York in 1984 (No. 82 Civ.
on change orders, or which identify when the 6868), Harmonay sued Binks to recover sev-
change order work was actually performed. In eral categories of project costs, including a loss
such cases, it is necessary to use the estimated of labor productivity. In the case, Harmonay’s
change order hours, and to further estimate fact witness testified to a productivity loss of
when the change order work was performed. 30 percent based on personal observations
This is best accomplished by the onsite man- and the use of the MCAA “manual.” The
agers, as the fact witnesses who saw the work court, in this portion of the case, decided for
being performed. An analysis which deducts Harmonay, stating in part, that:
the hours for executed change orders may
“… courts have often recognized that the
appear as shown below.
extent of harm suffered as a result of delay,
By using this example, the contractor’s deficient such as the loss of efficiency claim at issue, may
work and the change order work covered by be difficult to prove. Thus, courts have
executed change orders which contained “full recognized that a plaintiff may recover even
accord and satisfaction” language have been where it is apparent that the quantum of
factored out of the calculation. However, the damage is unavoidably uncertain, beset by
impacts of productivity loss caused by changed complexity, or difficult to ascertain, if the
events on the unchanged work remain. damage is caused by the wrong.”

Contract Period Week 40 Week 41 Week 42 Week 43 Week 44 Week 45

Actual Payroll Hours 1,600 1,600 1,800 2,400 2,400 3,200


Change Order Hours & Other Deductions –80 –120 0 –120 –120
Revised Actual Hours 1,600 1,520 1,680 2,400 2,280 3,080
Reassignment of Mpw 5% 5% 5% 10% 10% 10%
Dil of Supervision 0% 10% 10% 10% 10% 10%
Crew Size Ineff 0% 0% 10% 10% 10% 10%
Total MCAA factor 5% 15% 25% 30% 30% 30%
Est Loss of Productivity 76 198 336 554 526 711

Total 2,401

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 123
Productivity

This is an important case which established When a contractor has utilized the MCAA’s
that even though the loss of productivity labor inefficiency factors and then decides to
cannot be computed with exactness, the take its loss of labor productivity claim forward
impossibility of reaching an exact proof of for a hearing at arbitration, in a court or before
loss does not bar recovery.10 Also, in the a board of contract appeals, it is helpful to
Stroh case, which was previously cited, the know how the courts and boards have viewed
General Services Board of Contract Appeals this method of calculating labor inefficiency.
restated two important principals of pro- As noted previously in this chapter, the MCAA
ductivity loss claims; that exact measure- factors, if properly applied, have gained broad
ment of productivity loss is not a condition acceptance as a reasonable means of estimat-
precedent for recovery, and in loss of pro- ing a contractor’s loss of productivity. How-
ductivity claims, the claimant bears the bur- ever, that does not mean that boards of con-
den to clearly demonstrate that the cause tract appeals automatically find persuasive
(for which the claimant was not responsible) contractors’ inefficiency claims prepared using
resulted in the effect (loss of productivity). the MCAA factors. A contractor should expect
probative questioning regarding the factual
It is fortunate that courts and boards have rec-
basis of such claims, how the claim was pre-
ognized the difficult nature of quantifying
pared, who prepared it, and the qualifications
with exactness construction productivity
and independence of the person testifying on
losses and have not found the absence of pre-
the issue of labor inefficiency.
cise measurements as a bar to recovery. Fur-
thermore, the MCAA factors publication has From time to time, the source of the MCAA
been recognized as a useful and reliable tool factors may be questioned. This issue has
by which loss of productivity impacts can be been addressed by the MCAA in a Declaration
estimated, particularly when their use is cou- filed in 1999. While the records of the polling
pled with credible fact-witness testimony. and data collection process were not retained
in MCAA’s files, through historical research,
the means of preparation of the factors have
When a Contractor Must been memorialized. Pertinent excerpts from
Litigate an Inefficiency Claim MCAA’s Declaration follow:
It is usually in a contractor’s best business
The MCAA Factors apparently were developed by
interest to settle, or at least to mediate, a con-
the MCAA Management Methods Committee
struction dispute rather than to litigate or to
beginning in the late 1960s and continuing into the
take the matter to arbitration. The decision to
early 1970s. It is (MCAA's) informed belief that
litigate, or to arbitrate, means handing over
the committee was comprised of MCAA Member
the destiny of your case to others. It is usually
representatives who were experienced mechanical
a better business decision to control your des-
contractors. MCAA records show that in April
tiny and bring a contentious matter to an
1969 a “rough draft on the subject of Change
amicable settlement, if at all possible.
Orders in the Construction Industry” was pre-
sented to MCAA’s Board of Directors…. In May
1970, the Management Methods Committee
10
Luria Bros. & Co. Inc. v United States, 369 F.2d 701,
reported to the MCAA’s Board of Directors on a
712, 177 Cl.Ct 676 (1966).

124 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

“complete ‘in-depth’ study of the whole Change the Management Methods Committee and
Order concept as it affects the construction then formalized in the MCAA’s publication.
industry.” It is (MCAA's) informed belief that this
Not only were the factors prepared by experi-
is the predecessor of the current MCAA Factors.
enced and knowledgeable leaders in the
It is also (MCAA's) understanding that the sub-
mechanical construction industry, the factors
stance of this document has not changed since
have constantly been vetted in the industry
that time. It is now known as the “Factors Affect-
for the past 40 years and found to be reason-
ing Labor Productivity.”…the available documents
able and reliable. They have remained
indicate that the committee and its members
unchanged since their first publication and
were responsible for selecting the titles and
have been accepted by courts, various boards
descriptions for each of the factors and formulat-
of contract appeals and arbitration panels as
ing the percentage values that are set forth in the
useful in estimating a contractor’s loss of
document.To the best of MCAA’s current knowl-
labor productivity. Moreover, the MCAA fac-
edge, the information contained in the MCAA
tors have been formally adopted by the Sheet
Factors was gathered anecdotally from a number
Metal and Air Conditioning Contractors’
of highly experienced members of the MCAA’s
National Association (SMACNA) and have
Management Methods Committee. MCAA does
been utilized by the National Electrical Con-
not have in its possession any records indicating
tractors Association (NECA) and the Electri-
that a statistical or other type of empirical study
cal Contracting Foundation in its publication
was undertaken in order to determine the specific
entitled Factors Affecting Labor Productivity for
factors or the percentages of loss associated with
Electrical Contractors.
the individual factors.
In terms of preparing to utilize the MCAA
The process of collecting data such as that
factors in a litigation or arbitration to estab-
which appears in the MCAA factors’ table
lish a claim of lost labor productivity, it is
using a polling process is not unusual or pro-
vital that the contractor retain an experi-
scribed. Such methods have been used to
enced and independent expert to perform
establish losses of labor productivity by many
the inefficiency analysis, prepare the expert
trade associations other than MCAA. The fac-
report, and testify as an independent expert
tor descriptions were prepared in advance by
if necessary. In several recent cases in which
the Management Methods Committee. A
the MCAA factors were utilized, the Armed
form was created listing the factor descrip-
Services Board of Contract Appeals has indi-
tions and three levels of potential impact:
cated that the testimony regarding labor
“Minor,” “Average,” and “Severe.” The form
inefficiency quantification should not be
was then made available to the MCAA mem-
performed by an employee or principal of
ber firms for careful review. The intensity
the claimant, but rather by an independent
data, in the form of the expected impacts per-
labor productivity expert. That is not to say
cents, were filled in by the MCAA member
that credible fact witnesses, such as foremen,
firms. From this broad polling process, the
superintendents, and project managers
factor descriptions and the expected impact
should not testify as to the causes and effects
percentages were reviewed and finalized by
of issues adversely affecting labor productiv-
ity. Credible fact-witness testimony is very

Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 125
Productivity

important to establishing the cause and The use of the MCAA factors in forward
effect nexus. However, if various formulae pricing change orders can result in an over-
are to be applied during testimony in litiga- all acceptable recovery of potential loss of
tion or arbitration, including utilization of productivity in addition to the direct costs
the MCAA factors, then the use of an inde- of the change. Also, the use of the MCAA
pendent expert is highly recommended and factors can result in a more accurate forecast
may be mandatory if an analysis utilizing the of potential schedule impacts when dura-
MCAA factors is to be credible and reliable. tions of activities are factored for the esti-
mated productivity loss.
Even when an independent expert is uti-
lized, it must be underscored that the MCAA It is essential that contractors weigh the
factors should be applied in a reasoned man- value of recouping reasonable amounts for
ner, relying on the methodology set forth in the indirect costs of change orders along
this chapter. Outlandish and unsupportable with the direct costs against the potential of
inefficiency analyses will draw deserved gaining a greater recovery by waiting until
skepticism from courts and boards of con- the end of a project to assess the cumulative
tract appeals. If the MCAA factors are not effects of all changes issued during the life
applied in a proper manner as described in of the project.
this users’ manual, a contractor can expect
As described herein, in some instances, the
to face a high bar in its attempts to recover
only option available to the mechanical con-
its loss of labor productivity.
tractor may be a retroactively quantified loss
of productivity claim. In such cases, the
Conclusion MCAA factors can be applied to the
The loss of labor productivity is often diffi- adjusted, actual hours expended by the
cult to quantify with exactness. The MCAA contractor.
factors can be highly useful to contractors Productivity loss caused by changes in
seeking to recover losses in labor productiv- scope, including defective design, unfore-
ity due to events not the fault of the con- seen site conditions, delay and acceleration
tractor. The contractor facing a project that and change orders, can be real, provable and
shows the symptoms of delays and ineffi- recoverable. Using the MCAA factors cor-
ciencies should ensure that the contract rectly can materially improve the contrac-
terms and conditions for timely notice and tor’s ability to recover from such losses.
impact quantification are followed with
care. Many otherwise meritorious claims for
which the contractor is entitled to recover Prepared by Paul L. Stynchcomb, CCM, PSP, CFCC of
Vero Construction Consultants Corp. and Jarad Kriz,
its fair and reasonable costs are barred CCM, LEED® AP (BD+C), PSP of FTI Consulting, with
because the contractor failed to follow the peer review performed by: Wayne Day of John J. Kir-
contract terms as to notice and quantifica- lin, Inc.; Raymond Jung of The Poole & Kent Com-
tion, or failed to reserve the right to file a pany; Robert Gawne and Richard Freeman of
Stromberg Metal Works, Inc.; Herman Braude, Esq. of
delay or inefficiency claim at a point in time Braude & Margulies, P.C.; Robert Windus, Esq. of
after the execution of a change order. Moore & Lee, LLP; and Henry Danforth, Esq. of Watt,
Tieder, Hoffar & Fitzgerald, LLC.

126 Management Methods Bulletin PD2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Productivity

How to Apply the Measured


Mile Method of Productivity
Analysis
Introduction process of calculating the difference between
the “should have spent” labor hours and the
When the labor on a project exceeds the esti-
actual labor expended in the impacted areas
mate or job plan, the mechanical contractor
or time frames is referred to as the measured
often commences an analysis of the causes
mile method of labor productivity analysis.
for, and quantification of, its labor loss. This
sometimes leads the contractor to seek relief The more detailed and accurate the contrac-
from a third party, such as a prime contrac- tor’s labor expenditure records, the more
tor or owner. Frequently, the third party’s persuasive the measured mile analysis will
first line of defense will focus on assertions be. Contractors are advised to evaluate their
that the mechanical contractor’s original record keeping procedures to ensure that the
labor estimate was flawed. When properly information necessary for a measured mile
applied, the “measured mile” analysis is a analysis is being collected and maintained
very effective means of quantifying the loss on a regular basis.
of labor productivity. This method relies on a
This chapter offers a description of the
comparison of the contractor’s actual unit
measured mile method of productivity
rate ratios on the subject project, thus elimi-
analysis, discusses record keeping and pro-
nating concerns over bid errors.
vides examples of the analysis process itself,
The measured mile method compares actual along with ways in which the results can be
labor productivity in an impacted period or presented. When used properly, the meas-
area with productivity in an unimpacted (or ured mile analysis can offer a compelling
less impacted) labor period or area in order case for recovering a mechanical contractor’s
to establish what the labor production rates loss of labor productivity.
“should have been” in the impacted labor
periods or areas. To be effective, the work
performed in each area or period needs to be
Applying the Measured Mile
of a reasonably similar nature. The work per- Method to Quantify a Loss of
formed in the unhindered or less impacted Labor Productivity
area or time frame is frequently known as The measured mile method provides for a dif-
the “baseline” or “measured mile” labor. The ferential productivity comparison between

Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved. 127
Productivity

actual production rates achieved on the same On another project, one or more discrete
project.1 Because this methodology relies on areas could be constructed with reasonable
actual production rates, no reference or reliance productivity while other, similar areas were
upon the contractor’s estimate or labor plan is affected by substantial changes in scope,
required. This fact is one of the most important trade stacking, lack of owner-supplied materi-
sources of credibility for this methodology. als (logistics), site access limitations and other
identifiable factors. The differential measure-
ment between such areas can form the basis
Identifying the Measured Areas or
of a measured mile analysis.
Time Frames
In order to perform a measured mile analysis, One means of determining which method is
different areas or time frames must be identi- best for a project under study is to interview
fied. These should be contrasted, one from the site management (i.e., project managers,
another, by the inefficiency factors that have superintendents, and foremen) and seek their
been alleged to be the root cause of the con- input into what took place (or is taking place)
tractor’s loss of labor productivity. The choice and what areas or time frames were more
between utilizing physical areas of a project or productive and less productive. This inter-
time frames is at the discretion of the contrac- viewing process will also form the basis of the
tor based on the specific project conditions. cause-and-effect connection that will be
The fact pattern may be such that similar sec- required when proving and explaining the
tions of a building are definable with one or production rate differential.
more definable areas having been less adverse- Once this interview process has taken place,
ly affected by the productivity impact factors the observations of the staff can be tested
and with one or more definable areas having against the actual labor production records.
been more affected. These same conditions At this time, it may become obvious as to
could be ascribed to discrete time frames. which format will be most effective: an area
For instance, a project could progress to the 50 measurement or a time frame measurement.
percent complete point with reasonable pro- After the contractor has decided on whether
ductivity and then be subjected to a substan- the measured mile analysis will be made on
tial acceleration effort resulting in overtime an area or time frame approach, the collec-
work, stacking of trades, crew size inefficien- tion and analysis of the actual payroll labor
cies and reassignment of manpower for the hour and material/equipment installation
duration of the project. The aforementioned data can commence, as described in greater
case would suggest a time frame approach. detail below.

1
While this chapter focuses on the use of labor hours
Reasonable Similarity between
in quantifying labor inefficiencies, some contractors Materials and Work Environment
have chosen to use unit costs. The measured mile The measured mile method measures the
method does not proscribe the use of costs as a surro-
difference in actual productivity rates
gate for labor hours, however if costs are utilized, the
claimant must be careful to remove all factors, such a between sets of productivity impact condi-
wage increases, that would inherently unbalance the tions, one having little or no impacts and
measured mile comparison.

128 Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved.
Productivity

one having representative2 impacts. For this and 12” pipe of the same or similar material
measure to be “exact”3 (which is not a con- would be considered as reasonably similar.
dition precedent to use this methodology), Comparing the production rate for 2” carbon
the same material and/or equipment would steel threaded pipe to large bore mechanically
have be to installed by the same crew, under welded stainless steel pipe, if utilized in the
the same management, in the same work analysis, offers inherent dissimilarities that
environment, as measured between two will require a carefully considered production
areas or time frames that are similar in space adjustment and/or thorough explanation of
and time; with the remaining difference why the comparison is reasonable.
being the influence(s) of inefficiency being
Installing pipe under a roof slab 30’ from the
claimed by the contractor. The aforemen-
finished floor in a mechanical room can be
tioned conditions virtually never exist on a
more challenging than installing the same
construction jobsite. Only in an academic or
type of pipe system in a room with a 15’ ceil-
laboratory setting would these precisely
ing. Installing straight lengths of pipe on
matched conditions be found.
pipe racks in an open area can be inherently
The courts and boards of contract appeals more efficient than installing the same type
only expect that the areas or time frames of pipe in a crowded mechanical room where
under measurement be reasonably similar. the pipe system has frequent changes in
These reasonable similarities between the direction and may have valves and other
data being measured include: 1) material appurtenances that could represent a lower
and equipment types; 2) installation equip- production rate. Installing equipment during
ment and/or means and methods; 3) experi- the winter in an area open to the elements
ence, quality and quantity of supervision; 4) with exposure to lower temperatures and
experience and quality of the work force; 5) wind will most likely be inherently less pro-
inherent work environment including expo- ductive than installing similar equipment in
sure to weather factors and height of the a heated mechanical room (this assumes that
work being installed; and 6) any other factor the work was not delayed into an unantici-
that would inherently imbalance or skew pated adverse climatological period).
the productivity study.
Installing material with a seasoned journey-
For instance, comparing the installation of 4”, man crew with proven competent supervision
6” and 8” standard weight A-53 carbon steel in an unobstructed area will most likely be
butt weld pipe to the installation of 8”, 10” inherently more productive than installing
the same types of material in a congested area
with a measurably higher ratio of inexperi-
2
The term “representative” is used herein to mean enced workers, less effective supervision or in
impacts representing a reasonable and consistent level
of productivity loss arising from the alleged causes as more crowded or constrained conditions.
opposed to choosing a limited, particular area or time
All of the potentially inherent differences
frame that exhibited the most drastic impacts without
averaging or weighing the resulting inefficiencies with must be identified and evaluated when per-
other impacted areas or time frames. forming a measured mile analysis. The goal of
3
Luria Bros. & Co. Inc. v United States, 369 F.2nd 701, the analyst is to measure the differences in
712, 177 Cl. Ct. 676 (1966)

Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved. 129
Productivity

productivity rates caused by the productivity Such contemporaneous labor-tracking record


impact categories identified in the analysis keeping provides for valuable and timely pro-
(i.e., stacking of trades, overtime inefficiency, ductivity monitoring that requires little or no
disruption and other such categories), and to further adjustment in order to apply this data
be confident that the segment is reasonably to a measured mile analysis. However, most
free of differences that would have, on their mechanical contractors do not contemporane-
own, caused a measurable variation in the ously track the actual labor hours required to
contractor’s labor performance. install lengths of pipe, supports, fittings and
appurtenances or pieces of equipment in dis-
crete areas or time frames on a project. The
The Project Records
absence of contemporaneously maintained
An essential feature of the measured mile
actual labor installation records does not pre-
method is its absence of reliance on the con-
clude the use of a measured mile method.
tractor’s estimate or labor plan. This method
relies on the contractor’s actual unit rate ratio Many contractors maintain labor performance
of production achieved on the project in differ- reports. These are an earned value type of
ent areas or time frames of the same project or, reporting because the actual hours expended to
in some cases, highly similar projects. In order install a known quantity of work are compared
to establish the contractor’s actual unit rate to a plan or estimate. These reports typically
ratio, or productivity rate, records that set forth provide a variance between discrete activities of
the actual labor hours expended to install a work comparing the planned and actual hours
definable quantity of material and/or equip- on a regular basis, such as each payroll period,
ment is very helpful. They are not absolutely or monthly. Such labor performance reporting
required, however, as explained herein. is described in greater detail within the chapter
on “Maintaining Control of Labor Productiv-
A minority of contractors track, in a contem-
ity,” and a sample is shown on the next page.
poraneous fashion, the amount of material
and/or equipment installed by hour of labor. In the sample labor performance report shown
This sort of contemporaneous labor productiv- on the next page,4 current actual payroll hours
ity tracking is very meaningful, however it “C Act Hrs” are compared with an updated
usually requires a very substantial and costly plan “Rev Plan”5 to provide for weekly vari-
effort to track the actual material installed by ances. The “Earned Hours” are a function of
type and by labor hour. In some industries,
such as the sheet metal industry, the difficulty 4
For an explanation of the data columns shown in this
of tracking actual material installed by labor
sample report, refer to the chapter entitled “Maintaining
hour is being overcome by electronic means of Control of Labor Productivity” herein.
bar coding duct sections and tracking the duct 5
Many mechanical contractors do not track actual change
from manufacture to pre-assembly to final order hours by activity code. Some mechanical contrac-
installation in the field. Assuming the contrac- tors do not update the plan on an activity-by-activity basis
tor’s systems allow coding of actual labor to a for estimated change order hours. There is no established
standard in the industry in this regard. However, at some
section of duct, its actual manufacturing, pre- level, the contractor must know if the production rates
assembly and installation can be tracked with estimated to perform the work are being met on the proj-
a reasonable degree of accuracy. ect, either at the activity level or at the bottom line.

130 Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved.
Productivity

The Labor Performance Report (Example of Detailed Activities)

Activity Activity Planned CO Rev Last Current Earned PT C Act Wk Wk Cw


ID Code Description Hours Hrs Plan %C %C Hours AH Hrs -2 -1

7550 Inst CHWS&R 500 500 30 50 250 300 450 –75 –150 –200
Mains
Area B

7570 Inst CHWS&R 700 50 750 10 20 150 120 200 –40 –45 –50
Brnchs
Area B

7590 Connections 100 100 10 15 15 10 12 0 0 3


@ Mech
Equip

earned or reported percent complete multi- type (i.e., butt weld versus threaded, carbon
plied against the updated planned hours. steel versus cast iron, pipe installation versus
Thus, the contractor’s measure of performance equipment setting). Such differentiation will
using an earned value reporting system is enable the contractor to assign the actual
based on reported progress and the contrac- hours by general categories of pipe system,
tor’s estimate, adjusted to incorporate changes pipe type, equipment setting and other defin-
in scope in order to compute a current, revised able features of the work.
plan. This system enables the contractor to
The goal of an exercise such as that described
divide the overall plan into identifiable units
above is to assign actual labor hours
of work, called activities. These activities usu-
expended to discrete elements of the con-
ally have work boundaries that are defined by
struction process. This area-by-area compari-
the description of the activity, as shown in the
son method is one manner of preparing a
example on the next page.
measured mile analysis. Once the actual labor
Assuming the contractor has a labor perform- hours have been defined and the material
ance reporting system that sets forth defin- and/or equipment have been quantified, a
able features of the work (i.e., activities), the production rate ratio can be computed.
contractor can locate the activity boundaries
Assuming the contractor has been able to
on a set of contract drawings and from that
identify a nonimpacted or less impacted area
information, take off the material contained
or time frame, then the actual labor hours
in the activity. Provided the contractor has
and installed units can be measured. For
coded the actual labor hours by discrete activ-
example, a contactor measured 1,000 linear
ity, the contractor can assign actual hours
feet of 6” and 8” carbon steel butt weld pipe
expended to a definable quantity of installed
that required 575 labor hours to install6 in a
material and/or equipment.
definable area or time frame. From this data,
Due to the differences in expected production
rates between different piping and equipment
6
systems, it is helpful if the contractor has “Installation” needs to be uniformly defined within the
defined its activities by pipe size (i.e., small analysis such that categories of work such as material
handling and pipe support erection are consistently
bore versus large bore) and general material included or excluded.

Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved. 131
Productivity

Activity Boundaries Marked on the Contract Drawings

Activity 7550 - Mechanical Room Mains Column Lines 11-15/A-B

the contractor can compute a labor rate of The contractor must now identify a reasonably
.575 hours per linear foot, or 1.74 linear feet impacted area or time frame in which similar
of pipe per hour of labor actually expended. work was performed but was adversely affected
Although the contractor was unable to differ- by the conditions the contractor has identified
entiate the labor required to install the 6” sys- during the interview process described herein.
tem from the 8” system, the pipe systems For example, it was found that 1,500 linear
were sufficiently similar to arrive at a blended feet of 4” and 10” carbon steel butt weld pipe
production rate. required 1,250 hours to install. Once again,

132 Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved.
Productivity

the contractor could not differentiate between rate in the impacted area or time frame as
the 4” and 10” pipe as to actual labor hours was achieved in the more productive area or
required to install the pipe systems. The time frame; 1,500 linear feet of pipe ÷ 1.74
blended production rate equals .83 hours per linear feet per hour = 862 hours. The actual
linear foot or 1.2 linear feet of pipe per hour of hours expended in the impacted area; 1,250
labor actually expended. less the “should have spent” hours of 862 =
388 hours of lost productivity.
The measured mile method comparison would
be .575 hours per linear foot in the non/less When more than one sampling segment of
impacted area or time frame versus .83 hours work is included in the measured mile analysis,
per linear foot in the reasonably impacted area particularly when the amount of material (i.e.,
or time frame. Similarly, the methodology pipe lengths) varies significantly between the
would compare an actual production rate of segments of work being compared, it may be
1.74 linear feet per hour with an actual pro- advisable to use a weighted average, weighted
duction rate of 1.2 linear feet per hour. The on pipe lengths or other material considera-
productivity factor would then be computed tions. This process weights the production
as 31 percent. Those calculations appear as: averages based on the amount of material
being evaluated. Examples that follow include
0.575 ÷ .83 = .69; 1 - .69 = .31 x 100 = 31% a weighted average computation. Depending
or on the data, some samples using a simple arith-
metic average will produce the same, or nearly
1.2 ÷ 1.74 = .69; 1 - .69 = .31 x 100 = 31%
the same, results as using a weighted average.
However, in analyses with multiple and rela-
The loss of productivity factor of 31 percent is tively large sample groups, and with significant
then multiplied against the actual labor hours variances in the quantities of materials, a
expended in the impacted area or time frame weighted average approach based on material
for the work being measured, or 1,250 actual quantities or other measurement metrics can
hours x 31 percent = 388 labor hours lost due yield measurably different results as opposed to
to the productivity factors that impacted the a simple arithmetic average.
less productive area or time frame.
The results of this calculation also can be Unusual Study Observations Caused
used to compute the “should have spent” by Inconsistent Project Conditions
labor hours between areas or time frames. One of the goals of a measured mile analysis
From the example above, the contractor study is to evaluate differential productivity
demonstrated that it actually installed butt rates by comparing similar work being per-
weld carbon steel pipe at a rate of 1.74 linear formed under similar conditions, with the
feet per hour of labor in a less impacted area exception of identifiable categories of ineffi-
or time frame. There were 1,500 linear feet of ciency that affect one set of labor hours but
pipe in the affected area. Absent the produc- not the other set of labor hours, or at least to
tivity factors being complained of in the the same extent. Sometimes when perform-
affected areas, the contractor should have ing a measured mile analysis, an area or time
achieved approximately the same production frame under study shows a productivity rate

Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved. 133
Productivity

that is either much greater or much lower used in determining the weighted average of
than other unimpacted or less impacted areas the less productive areas.
or time frames. The contractor should care-
fully review these apparent anomalies and Step 3. Example Loss of Productivity
take appropriate action. One appropriate Calculations Using the Weighted Averages
action could be to exclude these apparent The contractor demonstrated a weighted
outliers as shown in the example below: average production rate of 2.54 linear feet of
pipe installed per labor hour expended in the
Step 1. Identification of Areas and Production less or nonimpacted segment of work.
Rates
The contractor did not include Area C due to
Assume all areas contain a mix of 4”, 6” and
apparent dissimilarities (an exceptionally
8” Std. Wt. B.W. pipe, 8-hour workday, 5 days
high production rate in comparison to the
per week, at approximately the same eleva-
other less impacted areas)
tion and work environments, but production
anomalies exist in one of the “better produc- The contractor’s demonstrated production
tivity” areas of the study (i.e., Area C). rate in the impacted areas averaged 1.82
LF/MH for 5,800 LF of pipe.
Areas that are expected to be more productive
and less productive can be calculated as shown Step 4, Option 1: Calculate the “Should Have
in the example at the bottom of the page. Spent” Hours
In the impacted areas, 5,800 LF of pipe
Step 2. Weighted Average Method should have been installed at the proven rate
In the example at the top of the next page, of 2.54 LF/hour. Samples of these calculations
Area C has been excluded from the weighted are provided on the facing page.
average because of its unusually high rate of
productivity. This type of exclusion is known as Step 4, Option 2: Calculate the Inefficiency
an “outlier” due to its unusually high rate of Factor
productivity compared with the other less A calculation of the production rate ratio
impacted areas and thus was not included in would look like the example on the next
the weighted average. The second box on the page.
following page provides sample calculations
Sample Calculations to Identify Expected More Productive Areas

Area A: 3,000 linear feet of pipe – crew of 4 for 38 days = 2.47 LF/MH
Area B: 4,300 linear feet of pipe – crew of 4 for 52 days = 2.58 LF/MH
Area C: 2,500 linear feet of pipe – crew of 2 for 30 days = 5.21 LF/MH

Example of Calculations Used to Identify Expected Less Productive Areas

Area D: 3,800 linear feet of pipe – crew of 4 for 68 days = 1.75 LF/MH
Area E: 2,000 linear feet of pipe – crew of 2 for 63 days = 1.98 LF/MH

134 Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved.
Productivity

Determining the Weighted Average of the More Productive Areas, Less Any "Outliers"

Area A: 3,000 linear feet of pipe – crew of 4 for 38 days = 1,216 hours = 2.47 LF/MH
Area B: 4,300 linear feet of pipe – crew of 4 for 52 days = 1,664 hours = 2.58 LF/MH
Area C: 2,500 linear feet of pipe – crew of 2 for 30 days = 480 hours = 5.21 LF/MH
7,300 2,880
Weighted Average = 7,300 ÷ 2,880 = 2.54 LF/MH

Calculating the Weighted Average for Less Productive Areas

Area D: 3,800 linear feet of pipe – crew of 4 for 68 days = 2,176 hours = 1.75 LF/MH
Area E: 2,000 linear feet of pipe – crew of 2 for 63 days = 1,008 hours = 1.98 LF/MH
5,800 3,184
Weighted Average = 5,800 ÷ 3,184 = 1.82 LF/MH

Sample "Should Have Spent" Hours Calculation

5,800 LF in the impacted areas ÷ 2.54 LF/hour = 2,284 “should have spent” hours
3,184 hours actually spent – 2,284 hours = 900 hours of productivity loss

Sample Inefficiency Factor Calculations

1.82 LF/Hour ÷ 2.53 LF/Hour = .72; 1.0 – .72 = .28 x 100 = 28 percent inefficiency
3,184 hours in the impacted areas x 28 percent inefficiency = 892 hours of productivity loss

The mechanical contractor’s result may vary ing assigned a particularly experienced or
depending on the option selected in Step 4. In hand selected crew to perform the work, or
the examples shown above, Option 1 results perhaps the physical work environment
in 900 hours of productivity loss, while the allowed the installation of the material to be
number of hours of lost productivity in performed much more efficiently than in
Option 2 is 892. other areas of the project. While there is no set
guide as to how much variance in a particular
As can be seen from the example, the contrac-
study segment should disqualify it from a
tor has removed the one study area that
measured mile method analysis, findings that
demonstrated an unusually high level of pro-
approach doubling or halving of productivity
ductivity. This may have been caused by hav-
in particular segments suggest that such seg-

Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved. 135
Productivity

ments could be outliers in the study. However, Area Measurement


there can be incidences where vastly different Area-based measurements are often used in a
productivity rates have a reasonable explana- measured mile analysis to quantify the loss of
tion, thus these sorts of apparent anomalies labor productivity on a construction project.
must be analyzed on a project-by-project basis. Area-based analyses can usually be derived
Additionally, if the contractor finds that its from earned value reports that divide the proj-
own management problems or crews caused ect into are spatially-based activities. Assuming
portions of the inefficiencies in the impacted that the productivity impacts can be segre-
areas or time frames, such self-inflicted ineffi- gated by building or project area, spatial divid-
ciencies must be identified, quantified and ing lines between impacted and less impacted
removed from the contractor’s request for equi- areas make logical study segments. It is impor-
table adjustment (REA). For example, a tant that the work environments be similar
mechanical contractor may have experienced from one area to the next, which includes the
delay caused by its own forces and, to mitigate height of the work off the finished floor eleva-
these impacts, embarked on unplanned over- tion, if applicable. There should not be any
time. This overtime schedule, depending on its inherent features of any of the areas that make
intensity and duration, can on its own cause them more productive or less productive—
labor inefficiency. In its measured mile analysis, only the inefficiency impact categories should
the contractor finds that it sustained a substan- form the significant differences between the
tial loss of productivity caused by owner areas, to the fullest extent possible.
changes and disruptions in a particular time As with a reasonable amount of time in a
frame of the project schedule. The contractor time frame-based measured mile quantifica-
also finds that this period of owner change and tion, there is debate within the construction
disruptions is concurrent with the time period industry and in academia regarding how
of contractor-initiated overtime. Assuming the large an area should be in order to offer a
same crews involved in the contractor-initiated credible measure of actual productivity. As
overtime were also affected by the owner of this writing, there does not appear to be
changes and disruptions in the same time any firm agreement on this question nor
period, the contractor must factor out of its have the courts offered any judicial guid-
claim the inefficiencies caused by the overtime ance. Generally, the area should be represen-
it chose to undertake to mitigate its own delay. tative of the overall work, not an isolated
Another adjustment that must be considered is segment of the work that would, by its
the payment by an owner or prime contractor nature, exhibit a much higher production
to the mechanical contractor for change orders rate than the balance of the project areas.
that include a loss of productivity that occurred The space within the areas should be reason-
in the impacted segment of the project. To the able—that is, the area should be large enough
extent that the contractor has been compen- for the crews to perform a sufficient amount
sated for labor and/or equipment inefficiencies of work to establish a measurable pattern of
during the impacted segment, these labor performance. Furthermore, the spaces
and/or equipment hours must be identified between the areas used in the comparison
and removed from the measured mile REA. should be similar or, if dissimilar, such differ-

136 Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved.
Productivity

ences should not have had an adverse effect project, or to an area, the productivity of the
on the underlying productivity. crews is expected to increase. If the time
frame is limited to the opening days or weeks
of a project, it may encompass this time of
Time Frame Measurement
lowered productivity due to the effects of
In terms of utilizing time frames rather than
learning curve. Conversely, if the measure-
physical areas, the application methodology
ment period is at the height of the project
is the same. Also, similar considerations have
such that workers have gained the benefit of
to be made when comparing the different
the learning curve effect, this alone could
time frames. Adverse weather may be a factor
increase productivity. The effects of the learn-
to consider; if the various measurement time
ing curve, both negative and positive, can in
frames fall into different climatological peri-
some instances be very slight and may not
ods and weather impacts are not one of the
affect the measured mile comparison, how-
categories of inefficiency being claimed, this
ever it should be taken into consideration
may require adjustment of the study. In fact,
when choosing the time frames to be meas-
any measurable inconsistencies between the
ured. If necessary, explain in the written nar-
time frames that could represent inherently
rative that will accompany the measured mile
more or less efficient performance need to be
quantification why the learning curve was, or
carefully evaluated. Reasonable care must be
was not, considered as a variable that could
taken to eliminate from the study any effects
affect the outcome of the study.
that are materially different between the time
frames being evaluated.
As with the proper amount of space when con-
What if the Contractor’s Earned
sidering an area-based measured mile quantifi- Value Records Are Not Available?
cation, there is an unresolved debate within Most mechanical contractors do not track
the construction industry and in academia material and equipment installed by labor
regarding how long a measured mile time hour on a contemporaneous basis. The rea-
frame should be in order to offer a credible sons this sort of detailed tracking does not
measure of actual productivity. In the writer’s usually occur include the level of complexity
opinion, the time frame should be long of most mechanical piping systems, the mix
enough for the crews to perform a sufficient of materials within areas or systems, and the
amount of work to establish a measurable pat-
tern of performance. The less impacted or 7
We note that the trend among many of the larger sheet
unimpacted time frames should not include metal contractors is to track the labor required to manu-
periods that experienced unusual or isolated facture, pre-assemble and erect duct work on a contempo-
spikes of high productivity that are not repre- raneous basis. This trend has been facilitated by comput-
sentative of the work on the overall project. erized sheet metal detailing and cutting systems and bar
coding on the duct segments that allow for efficient
For instance, the learning curve commences tracking of the material and correlation of the material
installed with the labor required to perform the work.
with lower productivity as workers arrive on
This mechanization has resulted in many sheet metal
the project at the outset of the contract, or contractors being able to perform measured mile analyses
begin work in very different surroundings. As while the project is on-going and with little additional
workers become more accustomed to the effort in data collection and labor hour correlation.

Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved. 137
Productivity

cost of having a “clerk of the work” tracking If the site management is available, a list of
the physical amount of material or equip- the categories of inefficiency impacts should
ment installed during each day of work, tied be compiled. If necessary, refer to the list of
to the hours spent to install those materials inefficiency categories contained in the chap-
or equipment.7 Where mechanical contrac- ter that addresses “Factors Affecting Labor Pro-
tors do perform this sort of contemporane- ductivity.” Discuss what areas or time frames
ous productivity measurement, the contrac- were adversely affected by these impact cate-
tor has already gathered the information it gories and what areas or time frames were less
needs to conduct a measured mile method impacted. Once the differential areas and/or
analysis. There is little or no need to refer to time frames have been identified, have the
earned value reports or to other data since knowledgeable individuals review the payroll
the actual production data is being collected time cards and other contemporaneous proj-
on a daily or weekly basis. ect data to see if the labor hours expended in
those areas and/or time frames can be identi-
The absence of contemporaneous labor and
fied using the workers’ names or crew coding.
material tracking is not an unusual condition
Often, area foremen or superintendents know
in the construction industry. While many
the workers by name and can identify which
contractors maintain some form of earned
workers performed the various activities on
value reporting, on some projects the con-
the project. This is more subjective than using
tractor may not have maintained any reports
a well-maintained earned value report, how-
that segregate the hours actually expended
ever it may enable a measured mile method
by physical areas or time frames within the
analysis to be performed.
project. There are other means of extracting
the needed information, albeit means that If the labor hours can be extracted from the
are much more time consuming and that payroll system by identifying the workers by
may be more subjective in nature. An alter- name and assigned to specific areas or time
nate method of data segregation involves the frames, then the materials installed in dis-
use of the contractor’s payroll system, time crete areas can be taken off and quantified
cards, daily reports8 and/or field diaries. The in that manner. As to time frame measure-
CPM schedule also may be used to determine ments, it may be necessary to review
when work was performed. progress records such as daily reports,
progress photographs, project schedules or
In such cases, the interview process is very
site diaries for descriptions of the work
important in order to locate the areas and/or
being installed. Some daily reports allow
time frames of better and lower productivity.
very specific entries of such progress infor-
mation and can be useful references to allow
8 From the outset of a project, the contractor’s manage- for the identification of workers and the
ment should review the superintendent’s or foreman’s material being installed by time and area.
daily field reports and/or progress diaries to ensure that The payment applications or CPM schedule
the contemporaneous entries contain sufficient detail, are
accurate and are in the proper format. At a minimum,
updates also may reveal vital information
daily reports or diaries should specify what work is being regarding when and where work was per-
performed, where the installation activities are taking formed, and to what extent it was complete
place by physical area of the project and by which crews. on a weekly or monthly basis. While this

138 Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved.
Productivity

sort of investigative analysis is very time Can Similar Projects Serve as


consuming, it may be the only way to Surrogates for Areas/Time Frames
extract the labor hour and material quantity on the Project Under Study?
information that is necessary to perform a The farther a contractor moves from com-
measured mile method analysis. parative measurements on the same project,
the less likely the analysis will be considered
What if the Less Impacted Area or a valid measured mile analysis. That does
Time Frame was Adversely not necessarily disqualify the use of very
similar projects to produce the comparative
Impacted?
areas or time frames. The two-project meas-
On some projects, there is no reasonably
ured mile approach is used when the base-
“unimpacted” area or time frame. This is not
line, or less impacted area or time frame on
unusual. Projects with pervasive defective
the project under study simply does not
design impacts can experience labor ineffi-
exist, or would have to be significantly
ciencies from the outset of the work, and in
adjusted to explain the inefficiencies in the
virtually all areas of the project. Projects that
less impacted area or time frame.
are the subject of enormous scope growth by
way of scope changes (i.e., cumulative impact) In some cases, it may make sense to offer two
can be similarly affected such that no area or measured mile analyses: one utilizing a modi-
time frame can be found that was immune fied baseline comparison as explained above
from measurable productivity impacts. and one utilizing two very similar projects.
However, there will be a need to demonstrate
One method of removing labor inefficiencies
that the crews, supervision, work environ-
from the less impacted area or time frame is
ments, types of productivity impacts and
to perform an MCAA labor inefficiency factor
other factors on the two projects were indeed
analysis on those labor hours (reference the
highly similar, one to the other. While a two-
chapter entitled, “How to Use the MCAA
project method is not proscribed, it is worth
Labor Factors”). If the less impacted area or
the extra effort on the part of the contractor
time frame has been impacted by others as a
to find similar areas or time frames on the sin-
result of unplanned trade stacking, disrup-
gle project under study.
tion, overtime or other recognized categories
of labor impacts, appropriate MCAA factors
can be applied to the less impacted area or Productivity Impacts to BIM/
time frame to set a revised baseline to be used Coordination and Pre-Fabrication/
in the measured mile comparison. All adjust- Sub-Assembly Operations and
ments to the less impacted baseline labor Equipment Inefficiencies
hours should be fully explained and justified. On projects that suffer from the effects of
If the contractor was responsible for its own multiple and significant changes in scope
inefficiencies in the baseline segment of the (i.e., cumulative impact), defective designs,
project, those have to be quantified and overall disrupted “start-stop-start” opera-
explained as well to demonstrate that the tions and/or delays to the schedule, the
contractor has not claimed inefficiencies aris- BIM/coordination and pre-fabrication/sub-
ing from its own mistakes and corrections. assembly operations can sustain significant

Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved. 139
Productivity

labor inefficiencies. The measured mile In order to capture measured mile information
method can be used to quantify inefficien- for use in the coordination/BIM, prefabrication
cies in these areas of a project. and sub-assembly operations, the mechanical
contractor should ensure that the workers are
When a mechanical contractor bids a project,
coding time to individual projects and, if pos-
labor hours are usually included for tradi-
sible, to discrete segments of the erection work
tional coordinated drawings or, on larger
or drawing. To the extent that there are areas
projects, computerized Building Information
of a project or discrete time periods which rep-
Modeling (BIM) drawings. The production of
resent reasonably productive work, actual
these drawings or computer models usually
hours required to produce a representative
leads to some amount of prefabrication or
drawing or set of drawings, or to prefabrication
sub-assembly of systems. A mechanical con-
or sub-assemble a known quantity of material
tractor can expect substantial labor savings if
should be maintained. This becomes the base-
this process is reasonably free of impacts from
line set of hours. As with the erection work,
large quantities of requests for information
the baseline productivity should be based
(RFI), changes, disruptions and delays.
upon a representative sample and not on
Many mechanical contractors include coor- unusually simple drawings or assemblies.
dination/BIM hours performed on change
Similarly, actual hours should be coded and
work within the change proposal itself by
collected on drawings by area or systems, or
way of percentages or direct hours required
during time periods which represent the
to address the changes. However, many of
effects of the disruptions, RFIs and changes.
the issues that affect coordination/BIM labor
The goal is to establish a differentiation
and the downstream prefabrication and sub-
between the labor hours required to produce
assembly operations never become a part of
coordinated or BIM computerized drawings
the contract as a change order. It is not
without the adverse effects of inefficiencies
unusual to find that a large percentage of
not caused by the mechanical contractor and
RFIs issued by a mechanical contractor dur-
the labor required to produce the drawings
ing the coordination/BIM stage never
given impacts on the project.
become change orders, thus the added time
and disruption to the coordination/BIM Actual prefabrication and sub-assembly opera-
process are not equitably compensated to tions can be measured for inefficiencies in the
the mechanical contractor. The result is an same fashion as field erection activities. In
undefined overrun in the coordination/BIM order to perform the comparative analysis, the
efforts. The disruption and inefficiency of contractor should have records of the time
the coordination/BIM operation then trick- required to perform prefabrication and sub-
les down to the prefabrication and sub- assembly work by definable segment, compar-
assembly operations, which can be addition- ing the production rates between more effi-
ally impacted by having to start, stop and cient and less efficient areas or time periods.
then restart operations due to the flow of
Construction equipment can also be subject to
the drawings, or due to “holds” placed on
a loss of productivity. Depending on how
prefabrication or sub-assembly work caused
equipment has been estimated, the inability to
by delays, RFIs and changes to the work.
utilize equipment in an efficient fashion can

140 Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved.
Productivity

add to the cost of construction. If the ineffi- nature of the equipment usage on the project.
ciency of construction equipment is the result A measured mile analysis can be performed on
of delays, disruptions, stop work orders or the equipment itself, by way of example con-
other adverse conditions outside of the control trasting the amount cubic yards of excavated
of the mechanical contractor, this component materials that were moved in unimpacted and
of added cost can be the subject of an REA. impacted segments of the project.
To the extent that usage records can be main- As with the erection activities, any appreciable
tained for any mechanized or motorized equip- inherent differences between segments being
ment, such as gas welding rigs, bulldozers, track measured, other than the inefficiency cate-
hoes, electrical welding packs and similar gories themselves, must be identified and fac-
items, these records can be coordinated with tored during the preparation of the measured
the contractor’s measured mile labor analysis to mile method analysis. Also, any contractor-
demonstrate the less efficient and/or delayed caused inefficiencies occurring in the impacted

Sample Productivity Chart by Area

Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved. 141
Productivity

Sample Productivity Graphic by Time Period

areas or time periods must be identified, quan- ten narrative report describing the conditions
tified and removed from the contractor’s REA that the mechanical contractor is asserting
along with any inefficient hours paid for in caused the harm and how the resulting dam-
change orders or by time and materials tickets. ages were quantified.
One effective means of communicating the
Presentation of the Analysis comparative variances that are at the center
and Graphic Charts of a measured mile analysis are graphic
charts depicting various productivity curves.
When presenting a change order proposal, or
These curves can convey the time lines and
REA, for loss of labor productivity, the
differences between the productivity that
claimant has the burden of proof regarding
was measured in the analysis. Two examples
the cause-and-effect nexus and the damages
are provided, one on the previous page, and
resulting from the causative events. Therefore,
one above.
it is helpful to prepare a comprehensive writ-

142 Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved.
Productivity

Oftentimes, the acceptance or rejection of a cific data should be divided and identified by
mechanical contactor’s REA for loss of labor individual system or piping material.
productivity can be affected by the quality of
The general guideline for the duration of activ-
the narrative describing the cause-and-effect
ities is from between 3 and 22 working days in
nexus, the supporting schedule analysis (if
order to allow for optimal tracking. Mechani-
appropriate), payroll and other project report-
cal activities should be created that can usually
ing, and the form and content of the measured
be accomplished by a single crew in the time
mile quantification. Presentation graphics, sup-
period noted above. Collection of the payroll
ported by well-prepared documentation, also
input then gives the contractor timely data as
can be persuasive in depicting the differential
to how each area performs in comparison to
productivity unit rate ratios derived by the
the original project plan, and in comparison
measured mile investigation.
with other similar areas on the project.
Since the contractor’s estimated/planned
Conclusions hours are used to populate the area-specific
The measured mile method is, without ques- labor-coded activity schedule and labor per-
tion, a very effective means of quantifying a formance report, the contractor has a record
contractor’s loss of labor productivity in the of performance compared to its estimate/
construction industry. In order for the meas- plan and to other similar work on the same
ured mile method to be reliable and success- project. Such record keeping can allow a
ful, however, it must be applied in an appro- mechanical contractor to perform a meas-
priate manner. The inappropriate application ured mile analysis while the project is still
of the measured mile method may result in a ongoing, and with that information, to
significantly reduced recovery or, in the work proactively to mitigate productivity
worst case, no recovery at all. However, losses, if at all possible.
many contractors have properly applied
When mitigation is not feasible or achiev-
sound and reasoned logic to prepare meas-
able, the mechanical contractor may be
ured mile method analyses that contain
placed in a position of recovering its produc-
comparisons of similar materials, equipment,
tivity losses by way of an REA. In its REA, the
environments, and crews and also contain
contractor will have to identify, justify and
any required adjustments between the seg-
quantify its loss of productivity component.9
ments as described herein.
A contractor has several choices in the selec-
Contractors who consistently pre-plan their tion of a method to quantify labor inefficien-
work and create a mechanical schedule in cies. Where possible, the contractor should
close coordination with the general contrac- consider the measured mile method as the
tor’s schedule can significantly improve track-
ing of the measured mile data. The mechani-
cal contractor, in coordination with its 9
The contractor should also endeavor to measure the
developed schedule, can create an area-spe- potential time impacts to the project schedule arising
cific labor-coded schedule of activities that from labor inefficiencies and, if applicable, include
those time impacts it its REA. The subject of potential
follows the logical construction sequence of
time impacts arising from labor inefficiencies is covered
the project. Whenever possible, this area-spe- elsewhere in this manual.

Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved. 143
Productivity

one that will, if properly applied, produce the analysis should be accompanied by a cogently
most compelling and acceptable results. written narrative that connects the causes with
the effects of the analysis and discusses why
Additionally, when a mechanical contractor
such impact causations were not the fault or
anticipates that it will sustain a loss of labor
responsibility of the mechanical contractor. A
productivity on a project and such labor pro-
well-prepared and well-documented measured
ductivity losses will, more than likely, not be
mile REA can be an important factor in avert-
equitably compensated in change orders, the
ing costly litigation and can offer the potential
contractor must preserve its rights to collect its
for a positive recovery of a mechanical contrac-
damages by other means, such as an omnibus
tor’s loss of labor (or equipment) productivity.
REA. Many change order forms issued by pub-
lic and private sector owners contain “full
accord and satisfaction” restrictive language. Appendix
On many projects, the prime contractor may
include waiver language on the monthly pay- Support at the Courts and
ment application release forms that attempt to
Boards of Contact Appeals for
bar a mechanical subcontractor from recovery
of any impacts that are not expressly excluded the Measured Mile Method
from the waiver provisions. These “full accord” Reported decisions from the boards of con-
and waiver provisions are explained in greater tract appeals and other tribunals can be
detail in other chapters within this manual, instructive in the preparation of a measured
however the mechanical contractor is remin- mile quantification of labor productivity loss.
ded to avoid executing any document that One of the frequently cited cases in favor of
seeks to limit the mechanical contractor’s rights the use of the measured mile method is the
to recover its delay and labor productivity im- Appeal of P.J. Dick1 at the Veterans Adminis-
pact costs, unless such terms have been review- tration Board of Contract Appeals. This deci-
ed and accepted by the mechanical contractor’s sion stated the following, in part:
senior management or construction counsel. …the efficiency factor calculated from the feeder
Finally, the more credible the measured mile work was used to adjust the budget for the
analysis, the greater the contractor’s REA recov- branch work. …the VA’s labor productivity
ery will be. To be credible, the contractor must expert, took exception to use of the measured
carefully apply the test of reasonability—rea- mile analysis using the feeder-branch circuit com-
sonably similar comparison areas or time parison because it violated a fundamental precept
frame, reasonably similar types of material of a measured mile analysis in that [the electrical
and/or equipment being installed, reasonable subcontractor’s expert’s] analysis does not meas-
record keeping or source data, reasonable ure the productivity for an activity in an unaf-
adjustments that may be required to the unim- fected period against the productivity for the
pacted and/or impacted segments, such as the same activity in the affected period. …[the elec-
removal of the contractor’s own inefficiencies trical subcontractor’s expert] indicated, there was
and inefficient hours compensated in change
order in the impacted segments, and reason-
1
Appeal of P.J. Dick VABCA Nos. 5597, 5836-37, 5839-50,
able conclusions drawn from the analysis. The
5951-65, 6017-24, 6483, 01-2 BCA ¶ 31,647

144 Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved.
Productivity

no period of branch conduit installation that was for differences in materials and joint types in
not impacted by either the design problems or the segments being compared.
acceleration. [The VA’s expert’s] principle objec-
The decision in W.G. Yates & Sons underscor-
tion to comparing feeder work to branch work
ing the acceptance of the measured mile
was the difference in crews and crew continuity.
method stated, in part:
Note that the government’s expert criticized
Yates, using the measured mile methodology, com-
the electrical subcontractor’s alleged im-
puted its alleged additional labor inefficiency costs
proper use of feeder conduit installation as
by comparing performance costs incurred prior to
compared with branch conduit installation
the defective specification disruption with per-
to form the measured mile as being too dis-
formance costs after the defective specification
similar to support a reasonable comparison.
disruption. …In DANAC, Inc., ASBCA No. 33394,
The Board rejected this criticism and the
92-2 BCA ¶ 29,184 this Board endorsed the
electrical subcontractor was awarded ineffi-
use of the measured mile methodology to
ciency damages based on its measured mile
measure the cost for labor inefficiency caused by
analysis comparing feeder conduit produc-
Government delay and disruption holding:
tion with that of branch conduit.
For labor inefficiency claims, “good period vs. bad
Moreover, in the Appeal of P.J. Dick the Board
period” analysis, comparing the cost of perform-
underscored the favored standing of the
ing work during periods both affected and unaf-
measured mile method to quantify a contrac-
fected by disrupted events “is a well estab-
tor’s loss of labor productivity and also recog-
lished method of proving damages.” U.S.
nized that measured mile quantification was
Industries, Inc. v Blake Construction Co. Inc. 671 F.2d
not required to be exact in order to be accept-
539, 547 (D.C. Cir. 1982) [emphasis supplied]
able as a basis of recovery. This decision mir-
rors the oft-cited Wunderlich Contracting Co.2 The contractor’s measured mile analysis may be
decision wherein the Court decided that a significantly reduced or even rejected by a
“claimant need not prove his damages with court or board of contract appeals if the con-
absolute certainty or mathematical exacti- tractor does not adjust the underlying produc-
tude…it is sufficient if he furnishes the court tivity rates for differences in the installation of
with a reasonable basis for computation, even the materials or other conditions not associated
though the result is only approximate ….” with the inefficiency categories upon which
the claim is based. Such inherent differences
However, the Wunderlich Contracting Co. deci-
can include material types, joint types, eleva-
sion cannot be taken to extremes and the
tion of the work, spatial limitations or other
requirement for establishing “a reasonable
physical conditions that would make the com-
basis for computation” [emphasis supplied]
cannot be ignored with impunity. Other cases
underscore the need for the claimant to 2
Wunderlich Contracting Co. v U.S. 173 Ct. Cl. 180, 351
adjust its measured mile analysis to take into F.2d 956 (1965)
account inherent dissimilarities between the 3
Danac, Inc., ASBCA No. 33394, 97-2 BCA ¶ 29,184
segments under study. Danac, Inc.3 and W.G. (1977)
Yates & Sons4 confirm the necessity for the 4
W.G. Yates & Sons Construction Co., ASBCA No. 49398,
claimant to make productivity adjustments 01-2 BCA ¶ 31,428 at 29 (2001)

Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved. 145
Productivity

parisons imbalanced. The goal of the measured tion methods do not necessarily prohibit the
mile method is to measure labor productivity use of a measured mile comparison, the
between two segments of reasonably similar claimant must make suitable adjustment in
work with the variable being the labor ineffi- the computations to account for inherent dif-
ciency factors identified by the contractor. ferences in the segments being compared.
This decision stated, in part:
The principal of “reasonably similar” compar-
isons in a measured mile analysis was clearly The record shows that welding in the impaired
defined in Clark Concrete Contractors, Inc. period was butt-welding on polyethylene pipes,
wherein a concrete contractor offered a meas- which takes only 15 seconds to 2 minutes per
ured mile analysis. The aforementioned deci- weld, whereas the welding done in the pre-dis-
sion was cited, in part, in the P.J. Dick decision: ruption period was steel welding, which may
take up to 2.69 hours per weld. …this evidence
We find no basis to conclude that either the
suggests that a comparison of the pre- and
productivity of the same crew or that exactly
post-disruption periods must take into account
the same work is a prerequisite for a valid
the difference in welding …
measured mile analysis to establish the amount
loss of productivity. We agree with the GSA Because the impaired rate accurately reflects
Board of Contract Appeals when it held in productivity during the impaired period, but
Clark Concrete, Inc., 99-1 BCA ¶ 30,280: does not accurately reflect productivity during
the ideal period, the court vacates the damage
[The Government] is correct in asserting that
award on lost productivity. The rates must
the work performed during the periods com-
account for the differences in welding and
pared by [the Contractor] was not identical in
trenching costs for the different pipes.
each period. We would be surprised to learn that
work performed in periods being compared is What can be taken away from the aforemen-
ever identical on a construction project, however. tioned cases and the other measured mile cases
And it need not be; the ascertainment of dam- in the industry is that the concept of reasonable
ages for labor inefficiencies is not susceptible to similarities is crucial in prevailing when utiliz-
absolute exactness [citation omitted]. We will ing a measured mile analysis. Also, these cases
accept a comparison if it is between kinds affirm the fact that the measured mile method
of work which are reasonably alike, such is the most widely accepted form of productiv-
that the approximations it involves will be ity measurement in the construction industry.
meaningful. [emphasis supplied]
However, in P.W. Construction, Inc.5 the con- Prepared by Paul L. Stynchcomb, CCM, PSP, CFCC of
tractor’s measured mile productivity analysis Vero Construction Consultants Corp. with peer review
was rejected because the contractor failed to performed by: Robert Beck, President of John W Dan-
forth Company; Michael R. Cables, Executive Vice
take into account very different pipe joining President of Kinetics Systems, Inc.; Stephen R. Dawson,
methods between the segments being meas- President, Harrell-Fish, Inc.; Richard Freeman, Vice
ured. While different materials and installa- President of Stromberg Metal Works; Michael A. Mack,
Executive Vice President, John J. Kirlin, Inc.; Charles F.
Mitchell, General Counsel of The Kirlin Group; Adam
5
Snavely, President and CEO of The Poole & Kent Cor-
P.W. Construction, Inc. v. The United States 2002 WL poration, An EMCOR Company; and Thomas
31780958 (Fed. Cir. 2002 Williams, President of Sustainable Builders.

146 Management Methods Bulletin PD3. © 2016 MCAA. All rights reserved.
Productivity

How to Estimate the Effects


of Cumulative Impacts
Executive Summary Contractors have long understood that
This chapter has been written as a resource when a project is subjected to a large num-
for the subcontracting industry with the pur- ber of changes in terms of labor hours, not
pose of helping the reader identify when necessarily dollar amounts, the productivity
cumulative impact has affected labor produc- of the contractor’s labor force can decrease
tivity and how to quantify the adverse effect substantially, even more so than the con-
in terms of inefficient labor hours. To the tractor may foresee at the time any single
extent that questions arise, contractors are change is priced. It is not the effect of a sin-
encouraged to seek the expertise of their gle change, but the cumulative effect of
legal and claims consulting resources. numerous labor-related changes in scope
that disrupts the rhythm of the project and
frequently results in stacking of trades,
Definition unplanned crew size increases, piece-meal
Cumulative impact of changes to a construction performance, and other types of inefficient
contract is the unforeseeable disruption of operations.
labor productivity resulting from the effect
The resulting loss of labor productivity may
of multiple changes to the contractor’s pool
be recoverable as an added cost of the multi-
of labor. Cumulative impact is referred to as
ple changes affecting the contractor’s labor
the “ripple effect” of changes on unchanged
pool. This loss is not attributable to a single
work, and on the change work itself, and
change and cannot be tied to a specific
causes a decrease in labor productivity. This
change by a traditional cause and effect
loss of productivity is usually not subject to
analysis. Rather, the contractor’s loss of
analysis in terms of spatial or temporal rela-
labor productivity is the result of the myriad
tionships because its source is not a single
changes radiating disruption and other
event, but arises from the multiple changes
adverse effects outward, resulting in a
issued on the project.1
decrease in the contractor’s overall labor
productivity on the project.
1
Paraphrased from the Veterans Affairs Board of Con- The contractor may quantify the effects of
tract Appeals reported decision in the matter of The
Appeal of Centex Bateson Construction Co., Inc. VABCA- cumulative impacts in several ways. The
4613 and 5162-5165. simplest means of quantification is the total

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 147
Productivity

cost method. This entails subtracting from of changes as correlating to the degree of
the contractor’s total labor hours its estimate impact caused by change to a construction
and change order labor hours. A variation contract. The Ibbs studies show that when
on this, called the modified total cost change is implemented early in a construc-
method, subtracts from the total actual tion schedule, the effects of these early
hours any of the contractor’s bid errors or changes can be less than the effects of
field retrofit caused by the contractor. These changes introduced during the “heat of bat-
are the least accepted methods of quantify- tle”—at a time when crew sizes and the
ing the contractor’s losses. The contractor number of activities being worked are at
may employ the MCAA labor inefficiency their maximum, and when much of the
factors to quantify the labor inefficiencies physical base contract work may have been
caused by cumulative impact. The most installed and may require modification or
widely accepted method of recovering loss removal and replacement as a result of
of labor productivity is the measured mile changes in scope. The resulting studies and
method, where the portion of the project the statistical analyses have now been pub-
impacted by others (i.e., change) is com- lished by the MCAA in a form that allows
pared with an undisrupted or less disrupted contractors to utilize the data to quantify
portion. The measured mile is the favored the effects of cumulative impact.
methodology because it is an empirical,
In the following chapter, contractors will
project-specific method of quantifying all
learn what constitutes cumulative impact,
types of labor productivity impacts. How-
how to explain the phenomenon, and,
ever, the conditions permitting the use of a
using the Ibbs curves, how to quantify the
measured mile analysis may limit the proj-
resulting loss of labor productivity. Exam-
ects on which it can be applied.
ples are provided that guide the contractor
Only recently have methods been made in selecting the appropriate timing curve,
available for a contractor to quantify the computing the necessary categories of labor
adverse productivity effects of cumulative hours and percent of change, and reaching
impacts utilizing statistical analyses per- a reasonable result in terms of the loss of
formed on other construction projects. labor productivity, expressed in labor hours.
William Ibbs, PhD, Professor of Civil and The graphic curves presented in this chapter
Environmental Engineering at the University allow the contractor to plot percent change
of California, Berkeley, has performed studies against the resulting loss of labor productiv-
of over 170 individual construction projects ity percentage. That correlation, derived
covering a wide variety of project types. from the graphic curves, is then utilized by
Those data have been assembled into fore- the contractor to compute an estimated
casting curves that predict, with reasonable number of inefficient labor hours resulting
accuracy, a contractor’s loss of labor produc- from the effects of cumulative impact. The
tivity given the labor intensity and timing of Ibbs methodology has been accepted by tri-
the implementation of the labor changes. ers-of-fact and thus, can be helpful in
resolving disputes arising from cumulative
Professor Ibbs’ studies have confirmed the
impact.
critical role of the timing of the performance

148 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

Introduction to Change and Because today’s construction projects are


complex, expensive, and sometimes risky
Cumulative Impact
investments for project owners, many own-
There are few subjects in the construction
ers seek to impose strict bidding or proposal
industry as widely discussed in the context
conditions and tight controls on their proj-
of identifying and quantifying losses in
ects. Projects sometimes have to go to mar-
labor productivity as the subject of cumula-
ket by way of competitive bidding early in
tive impact. A principal reason for this dis-
the development process, with plans and
cussion regarding cumulative impact stems
specifications that are latently incomplete or
from the fact that cumulative impacts are,
have errors, such as lack of a coordinated
in most instances, virtually impossible to
design among the trades. Often the addi-
identify while they are taking place.2 In
tional costs associated with incomplete
many cases, the effects of cumulative
design and/or design errors do not become
impact only become evident at, or near, the
apparent until the project is under construc-
conclusion of a project, when the effects of
tion. At the same time, there is fierce compe-
the individual changes have been recorded
tition in the marketplace as evidenced by the
in the contractor’s labor and cost reports.
large number of contractors pursuing the
Reasons for this may arise from a lack of
projects released for bidding. The result is an
detail in contemporaneous labor tracking
industry that is competitive and which cre-
and trending reports, the manner in which
ates tight profit margins for the builders.
labor reporting was maintained, or the late
Moreover, some projects are “economically
issuance of scope changes such that nega-
fragile” and susceptible, so when even mod-
tive trends do not appear in the labor
est change occurs, contractor profit margins
reporting until the project is at, or near,
and owner value propositions can be jeop-
completion.
ardized, or even evaporate.
Another cause can be attributed to the
Thus, in a challenging marketplace, it is
notion that a significant number of small to
important for the contractor to monitor the
medium-sized changes are difficult, if not
status of contract changes on a construction
impossible, to connect as causes to quantifi-
project. An important step in this process is
able and specific effects on an individual,
for the contractor to attempt to fully under-
change by change basis. It is not until these
stand the scope of work in the contract. Only
almost invisible and individual impacts of
by being aware of the base contract scope can
changes mount into a tidal wave that the
a contractor know that an owner is requiring
effects begin to become evident in the proj-
out-of-scope work to be performed. Unfortu-
ect records.
nately, at times contractors perform out-of-
scope work without realizing that the labor
hours they are expending are actually for
2
The impact of the cumulative effects of multiple work that is out of scope. They incorrectly
changes on a construction project has been described
assume that the labor hour overruns recorded
in one Board of Contract Appeals decision as amor-
phous (i.e., all but invisible, lacking definite form, on the labor reporting system must be caused
shapeless). Reference the Appeal of Centex Bateson by their own issues in the labor plan or by
Const. Co. Inc., 99-1 BCA ¶ 30153 (1998). inherently inefficient workers.3

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 149
Productivity

A second step in monitoring the change tiple changes often cannot be accurately
process is for the contractor to track the magni- captured within the contractor’s cost report-
tude and timing of change. Many contractors ing system. As noted by legal and account-
do not record actual labor hours expended on ing experts:
change orders or scope changes (i.e., by charg-
The advisable practice for capturing and reporting
ing actual hours to separate change work codes
claimable costs is to segregate the costs that are a
on labor reports) nor are actual start and finish
direct result of the events that impacted the proj-
dates for changed work tracked in the contrac-
ect….This argument has merit in theory but in
tor’s contemporaneous records. When changes
practice may be difficult to achieve. If the claimed
are performed, the contractor should create
event relates to additional activities or expanded
some form of documentation (e.g., RFIs, daily
scope of work that is readily identifiable and seg-
field reports, or superintendent’s diaries) that
regated from the original scope of work, then dis-
will denote when and where change work is
crete cost accounts can be established to capture
being performed and by what crew size. In the
the additional costs of direct labor, purchase
absence of this contemporaneous data, change
orders, or subcontractor change orders. Con-
work files should be maintained that docu-
versely, if the basis of the claim is…acceleration
ment the estimated labor hours required to per-
within the same activity, or changes affecting multi-
form the work, and, at a minimum, when the
ple work packages, then the associated extra costs
change work was estimated to have com-
may not be captured from the originally estab-
menced and when it was completed.
lished cost accounts. Because separating the addi-
However, even with identification and mon- tional costs may be difficult or impossible, the
itoring of the work scope accompanied by basis for substantiating these costs must be
reasonable efforts to segregate and account accomplished by other means.
for job costs, the cumulative impact of mul-
…Even with optimal planning and cost control
systems, contractors can still experience difficulty
3
in capturing all of their discrete cost damages…
At times the contractor will perform out-of-scope work
that is not identified as such until late in the project,
.Hidden costs may occur with a significant number
when a major labor overrun has been identified and the of changes to a project…and such delay and dis-
contractor’s management team undertakes a detailed ruption costs can snowball and not be discretely
comparison between the base contract work scope and the captured….The quantification of each change
work actually performed on the project. This comparison
can identify large quantities of labor expended on work order will fail to identify the cumulative impact or
not contained in, or contemplated by, the base contract “ripple effect” associated with multiple changes.
but which was required to actually build the project. A These…will have a negative compounding effect
common example is labor expended to install extra pipe
on construction productivity and are usually diffi-
and fittings not shown on the contract drawings but
which are necessary to overcome design deficiencies such cult to quantify discretely in the cost report.4
as improperly coordinated drawings. Because the labor was
not associated with a change in the contractor’s cost sys-
This chapter will describe methods for estab-
tem, it was never submitted for compensation as changed lishing a reasonable recovery of costs arising
work. Such lapses in the contractor’s control of the work
taking place on a project is lamentable, but should not
necessarily bar the contractor from an equitable recovery of 4
A. Overcash and J. Harris, “Measuring the Contractor’s
its reasonable costs, subject to the terms, conditions, and Damages by ‘Actual Costs’ – Can it Be Done?” The Con-
limitations set forth in the contract documents. struction Lawyer, Vol. 25, No. 1 (2005), pp. 34-36.

150 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

from the adverse effects of cumulative Cumulative impact is the unforeseeable disruption
impact. As a starting point, change is defined of productivity resulting from the “synergistic”
by the Construction Industry Institute (CII) effect of an undifferentiated group of changes.
as “any variation in a project’s scope, whether Cumulative impact is referred to as the “ripple
physical, administrative, commercial, or effect” of changes on unchanged work that causes
schedule.”5 For the purposes of this chapter, a decrease in productivity and is not analyzed in
change will refer to changes in the contract terms of spatial or temporal relationships.
scope, whether existing as formally approved This phenomenon arises at the point the ripple
change orders or unapproved scope changes caused by an indivisible body on two or more
submitted by the contractor to the appropri- changes on the pond of a construction project
ate contractual party (e.g., owner or prime sufficiently overlap and disturb the surface such
contractor). As will be discussed more fully that entitlement to recover additional costs
herein, unapproved scope changes used in resulting from the turbulence spontaneously
the computations contained in this chapter erupts. This overlapping of the ripples is also
must have a reasonable likelihood of being described as the “synergistic effect” of accumu-
approved as a change order, or have a reason- lated changes. This effect is unforeseeable and
able chance of being recognized as valid indirect. Cumulative impact has also been
changes by a neutral or trier of fact. described in terms of the fundamental alteration
When many changes occur, the situation is of the parties’ bargain resulting from the change.
further complicated and may result in what is The second paragraph of this board of con-
known as a cumulative impact condition. tract appeals decision defines several key ele-
This term has, perhaps, been best defined by ments of cumulative impact: 1) changes in
recent decisions issued by the major boards scope that can result in decreased labor pro-
of contract appeals and which are cited else- ductivity can be “undifferentiated” (i.e., the
where in this publication (reference “How to loss of productivity cannot be attributed to a
Use the MCAA Labor Factors” herein). Two specific change); 2) the effects of such
such definitions bear repeating here: changes can “ripple” outward adversely
Direct impact is generally characterized as the affecting the base contract, or unchanged
immediate and direct disruption resulting from a work, as well as other change work; and 3)
change that lowers productivity in the perform- changes in scope that affect labor productiv-
ance of the changed or unchanged work. Direct ity need not be related spatially or tempo-
impact is considered foreseeable and the dis- rally—they need not occur in the same time
rupting relationship to unchanged work can be frame and/or in the same physical area of a
related in time and space to a specific change. project. As a result of the inability to tie the
features of cumulative impact to a specific
5
event, time frame, or area of the project, it is
The Construction Industry Institute (CII) is an organi-
difficult, if not impossible, to capture the
zation comprised of more than 100 leading owner, engi-
neering-contractor, and supplier firms that sponsor additional costs associated with a specific
research into construction-related topics. Founded in impacting event even with standard project
1983, it has earned a reputation for conducting high control and accounting systems being utilized
quality, impartial research that enhances business effec-
tiveness and capital project sustainability.
by the management team.

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 151
Productivity

Finally, in the third paragraph, the board found ally, for purposes of this appeal, ‘cumulative dis-
that these “ripples” of inefficiency flow from ruption’: Is the disruption which occurs
the changed work onto the pond of the base between two or more change orders and base
contract, or unchanged work, as an indirect work and is exclusive of that local disruption
effect of the changes. Since these “ripples” are that can be ascribed to a specific change. It is
an indirect result, they may not be foreseeable the synergistic effect….of changes on the
at the time the change events are taking place. unchanged work and on other changes.
It follows that cumulative impacts—the While this chapter is not intended to serve as
destructive effects of multiple changes in scope a legal treatise on the subject of cumulative
on a construction project—cannot be meas- impact, it is frequently the published deci-
ured as the work moves forward, nor can such sions from the Boards of Contract Appeals
adverse effects be measured in individual and the U.S. Court of Federal Claims that
changes in scope. An estimator attempting to can provide some understanding regarding
forward price changes may not be able to fore- critical issues in the construction industry. It
see, let alone quantify, with reasonable accu- is apparent from these and other Board of
racy the productivity impacts to the overall Contract Appeals decisions that there is gen-
project arising from individual changes.6 eral agreement as to the existence and effects
Indeed, such impacts may not be identifiable of cumulative impact. However, there is less
or quantifiable until the end of a construction agreement regarding how to actually meas-
project, when measured within the entire uni- ure the effects of cumulative impact.
verse of change that was encountered during Addressing this challenging issue in the con-
the construction process. struction industry is the primary purpose of
this chapter.
Another definition of cumulative impact
offered by a major board of contract appeals
is also instructive: Underlying Causes and Nature
Among other things, ‘impact’ includes: inefficien- of Cumulative Impact
cies due to overcrowding, over or under man- Cumulative impact occurs when multiple
ning, skill dilution, extended overtime, shift changes in scope unforeseeably ripple out to
work, and local and cumulative disruption. cause disruption and a loss of productivity
to changed work and, potentially, to the
‘Local [or direct] disruption’ refers to the
base contract work itself. However, it is
direct impact that changed work has on other
understood in the construction industry
unchanged work going on around it. Conceptu-
that some change is inevitable on larger
construction projects—the question is how
6 much change to expect. It is generally
This chapter focuses on inefficient labor hours; how-
ever, losses of productivity can also affect other facets of agreed in the construction industry—and
construction costs, such as equipment that supports the substantiated by research—that projects with
work effort being analyzed (e.g., cranes, welding multiple, unanticipated labor hour changes
machines and excavation equipment for underground
often suffer a considerable loss of labor pro-
installations). Thus, productive use of equipment, which
is typically charged to the project in hourly units, can ductivity.
also be adversely affected by cumulative impact.

152 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

Thus it is important to establish what general the greater the impact that can be expected.
magnitude of change an experienced contrac- This impact may result from design changes,
tor should expect when bidding a construction differing site conditions, third party actions
project of any size or complexity. Studies con- or inactions, weather, or other causes that
ducted in the construction industry by govern- are not the responsibility of the labor-inten-
mental agencies have resulted in the data sive contractor.
shown in Figures 1-A and 1-B regarding expec-
Regardless of the source of the change, it is
ted changes in scope on construction projects.
generally not the dollar value of the change,
From the data shown in Figures 1-A, 1-B, or the number of executed change orders,
and 1-C,7 it is clear that contractors should that are the critical factors in determining
expect some amount of change on a sizable whether change may cause or contribute to
construction project. Obviously, the exact cumulative impact. Rather, it is the number
percentage of contract growth is not foresee-
able at the time of bidding each individual
7
project. However, ranges of potential change Figures 1-A through 1-C were extracted from the publi-
cation entitled “Construction Contract Modifications—
growth can be evaluated based on historical Comparing the Experiences of Federal Agencies with
data available in the industry. Other Owners” published in 1986 by the Committee on
Construction Change Orders, Building Research Board
Cumulative impact arises from multiple and the National Research Council. As of the date of
labor-related changes (whether directed or this publication, no more recent studies on the subject
constructive) being issued on a construction of expected change have been identified by the authors.
project. The more labor intensive the project,

Figures 1-A & 1-B

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 153
Productivity

Figure 1-C

of labor hours that will be required to per- reduced by the change. This situation must
form the changed work. A change order pre- be evaluated on a case-by-case basis.
sented to a mechanical contractor could have
Cumulative impact cannot be measured on
significant dollar impact to the overall con-
individual, discrete changes as each change by
tract value, but could be “all material” and
itself may not have a significant impact. Usu-
have little or no meaningful impact on labor
ally, cumulative impact is best measured near,
productivity. Thus, it is usually the labor
or at, the conclusion of a project because its
hours that really matter when attempting to
adverse impacts do not dissipate until the proj-
identify and quantify cumulative impact.
ect is completed, or is nearly completed.
Another characteristic of change, not just of
cumulative change, is that it can be either
additive or deductive. That is, a given change
Waiver Language in Contract
may enlarge a project’s scope or reduce it. Documents
Many owners find it difficult to accept, but This chapter does not offer a comprehensive
research clearly indicates that there are many review of the potential legal obstacles associ-
instances where a deductive change can be so ated with recovery of damages arising from
disruptive that the number of labor hours cumulative impact. However, it is important to
and costs actually increase despite the fact note that owners such as the federal govern-
that the physical quantity of work may be ment (e.g., GSA, VA) and many local agencies

154 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

and private developers are including waiver management. In general, the contractor
language in the various contract forms (e.g., should assume such waiver clauses are
change orders, payment releases, or in the con- enforceable unless advised to the contrary by
tract itself) that seeks to limit a contractor’s competent construction counsel.
right to recover any costs of change that are
In the alternative to executing payment appli-
not expressly included in the executed change
cations and change order forms that have
order. Recent trends at the federal level suggest
comprehensive waiver provisions, the contrac-
that a contractor must use extreme caution
tor may seek to bilaterally negotiate with the
when executing any contract document,
prime contractor or project owner alternative
including the contract itself, if the contractor
language that will appear on the forms them-
expects to preserve its rights to recover the cost
selves. Such alternative language often seeks to
of change (i.e., cumulative impact) that was
preserve a portion of the contractor’s rights to
not included in the executed change order.8
recover, at some future date, “unknowable”
Since cumulative impact is usually quantified (i.e., “unknowable” at the time individual,
near, or at, the conclusion of a project, by that “stand alone” changes are priced and executed
point in time the contractor may have exe- as change orders) impact costs such as those
cuted a host of monthly payment application arising from cumulative impact.
forms and change orders containing some
In the alternative, on projects where cumula-
form of waiver language. In many cases, these
tive impacts are expected to be substantial,
forms contain “full accord and satisfaction”
and where the owner refuses to alter the
language or other waiver provisions that may
waiver provisions on the various contract
seriously limit, or even bar, the contractor
forms, the contractor may decide to accept
from a cumulative impact claim arising from
unilateral change orders that pay for a portion
the adverse effects of changes that have been
of the change but do not require the contrac-
previously negotiated and bilaterally executed.
tor to execute documents that may waive the
Before executing the original contract or any right to later claim for unforeseeable or
of the various contract forms, such as unknowable impact costs such as those arising
monthly payment applications and change from cumulative impact. Another option is for
orders, the project management team should the contractor to proceed with the changed
review these documents with its executive work without payment (most contracts give
management team and seek legal advice if the owner the right to direct the contractor to
deemed appropriate. Executing such forms proceed without a settled change order) while
containing the aforementioned waiver provi- the parties address the change through the
sions, without an assessment of long term contractor’s dispute clause.
risk to the contractor, is not prudent project
The waiver of a contractor’s right to claim
for cumulative impact costs after the execu-
8 tion of changes bearing full accord and satis-
Reference Bell BCI Company v. United States, U.S. Court
of Appeals, Federal Circuit No. 2008-5087 570 F.3d 1337, faction language is a very serious financial
2009. For a related decision regarding cumulative impact
following the decision in Bell, reference Walsh/Davis Joint
and legal issue. It is strongly recommended
Venture v General Services Administration, Civilian Board of that mechanical contractors review all con-
Contract Appeals 1460, March 13, 2012.

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 155
Productivity

tract documents with competent legal coun- (i.e., the project data described in the examples
sel prior to mobilizing on the project and contained herein). However, the data collected
certainly prior to executing any document to produce the curves shown in this chapter
that could potentially bar the contractor were not prepared from the specific project to
from receiving full equitable adjustment to which the reader will apply the methodologies
its contract for all forms of impacts, includ- described herein. Thus, before a statistical
ing the cumulative impacts of change. approach is attempted, the claimant should
attempt to prepare a measured mile analysis
that derives its data directly from the affected
The Measured Mile Analysis project under study. The description of the
Methodology measured mile methodology is provided in
The measured mile method of quantifying a detail within this publication in the chapter on
loss of labor productivity on a construction “How to Apply the Measured Mile Method of
project is considered a project-specific, empir- Productivity Analysis.”
ical analysis methodology. Productivity data
There may be a host of valid reasons why a
is collected on the project under study com-
measured mile analysis cannot be applied on a
paring the production rates of similarly
construction project that is beset with multiple
skilled workers installing similar materials,
changes in scope. In order to prepare a meas-
but under different conditions; productive (or
ured mile analysis, there must be a non-
partially productive) and impacted. The role
impacted or less impacted area or time frame in
of the analyst is to identify the causes of the
which, or during which, the contractor’s actual
reduction in productivity between a less
productivity can be compared with the con-
impacted and a representatively impacted
tractor’s actual production in an impacted area
area or time frame on the project. The com-
or time frame. On many projects, change
parative production rate data produces the
begins at the outset of the project and contin-
productivity loss quantification.
ues almost to the time of commissioning or de-
Since the measured mile methodology is a mobilization, thus yielding no unimpacted or
project-specific means to quantify a loss of less impacted area or time frame for the com-
labor productivity, it is highly favored by parison. On other projects, the labor tracking
courts and arbitration tribunals. The cumula- records may not exist to perform a measured
tive impact data provided in this chapter are mile analysis. However, there are ways to mod-
not studies of the productivity rates actually ify the measured mile approach to accommo-
achieved on your company’s project. The date some of the obstacles often encountered
graphic models presented herein were pre- with the lack of a less impacted area or time
pared under statistical controls to offer accu- frame, or with the lack of robust recordkeeping.
rate predictions of productivity loss given a
Before any other type of productivity quantifi-
set of circumstances that existed on over 170
cation methodology is applied, the claimant
individual construction projects.
should first seek to utilize the measured mile
As will be described herein, the data lines method to quantify the loss of labor productiv-
shown on the graphs have a “good fit” as to ity. A successful measured mile analysis will
their ability to statistically predict with reason- capture the vast majority of the types of labor
able accuracy outcomes given certain input

156 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

inefficiencies that occur on construction proj- ingly in any of the cumulative impact models
ects. If a measured mile analysis cannot be per- that are presented in this chapter.
formed and the project has been adversely
As will be discussed herein, the actual number
affected by change, the methodology described
of change orders issued on a project may not
in this chapter may assist the contractor with
be relevant to the issue of labor inefficiency.
the preparation of a loss of productivity analy-
On some projects, an owner may bundle many,
sis that is derived from statistically reasonable
perhaps 10, 20 or more, individual scope
project studies as will be described herein.
changes into one omnibus change order. Thus,
it is not the number of executed change orders,
Defining “Scope Change” and or necessarily the timing of the issuance of the
“Change Order” formal change order documents, that most
adversely affect field labor productivity. It is the
When reviewing the available literature on the
number of change labor hours and their timing
subject of cumulative impact, the terms “scope
(in terms of when the work is actually per-
change” and “change order” are frequently
formed) that most profoundly affects a contrac-
used interchangeably when discussing the
tor’s labor productivity.
hours attributable to contract changes in
scope.9 “Change” includes unapproved scope
change labor hours and approved change order Identifying Labor Overruns in
hours, presuming these unapproved changes the Construction Industry
will stand the test of scrutiny regarding their
Labor overruns can have a variety of causes as
validity. Including labor hours arising from
their origins. One cause of labor overruns
questionable scope changes will reduce the
could be an inaccurate estimate. However, on
contractor’s credibility and potentially affect
projects fraught with a multitude of labor
the inefficiency computations and estimates.
intensive changes, labor overruns are fre-
If scope change hours (which by definition quently the result of cumulative impact. As
have not been formally approved as contract noted, a simple labor overrun shown in a
change orders) are included in the contractor’s labor production report is not necessarily an
cumulative impact loss of productivity compu- indicium of an inefficient project. Similarly,
tations, some special considerations have to be labor overruns on construction projects do not
made. If, during the process of vetting scope necessarily arise from inaccurate labor esti-
changes, the contractor withdraws a scope mates. A project which was based on an accu-
change and performs the work under its base rate, reasonable and carefully reviewed labor
contract, or the scope change is determined by estimate can have substantial labor overruns.
an authoritative tribunal or board to have been Therefore, it is necessary to investigate such
within the contractor’s base contract scope, the labor overruns carefully to ensure that the root
total “change” hours must be adjusted accord- cause is not an inaccurate labor estimate and
is, in fact, the result of labor inefficiencies
9
caused by identifiable events on the project.
“Design development” changes, a type of change
common in design-build projects, are a different type Labor overruns that result from an inaccurate
of change for which the design-build contractor is estimate usually arise from missed work scopes,
responsible.

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 157
Productivity

such as material and equipment items, not A potentially recoverable11 loss of labor pro-
being identified during the estimating process. ductivity condition is one that was not
As such, when it comes time to assign labor caused by the contractor in its estimating,
hours to material and equipment items, the management of the project, or other factors
labor hours required to install items that were ascribable to the contractor. Put another way,
missed in the estimate are not included in the but for the conditions that caused the ineffi-
total of labor hours required to construct the ciencies—conditions not caused by the acts
project. Another possible source of an improper or omissions of the mechanical contractor—
labor estimate is the labor factor(s) utilized by the mechanical contractor’s labor would have
the contractor as the achievable productivity at least met the planned production rates.
on a particular project and that will result in
Loss of productivity cannot be defined simply
the expenditure of the planned labor hours.
as actual labor hours for a specific scope of
For instance, if an estimator applies a 0.65 work, minus change hours, minus estimated
MCAA estimating labor factor for the installa- hours, equals inefficient labor hours for a par-
tion of pipe, valves, and fittings on a project ticular scope of work. Consider that a con-
because the field forces are known to the esti- tractor planned to install 40 linear feet of 10”
mator as productive, and these forces become diameter ASTM A53 schedule 40 carbon steel
unavailable when the project actually com- butt weld pipe and fittings in 8 labor hours.
mences, the actual labor forces may only However, it actually took 12 labor hours. The
achieve a 0.75 or higher MCAA estimating labor overrun cannot be ascribed to a loss of
labor factor. While this represents a form of labor productivity without the benefit of a
labor inefficiency (i.e., the actual labor force productivity cause and effect analysis. The
was inherently less productive than the esti- overrun of 4 labor hours could have been
mated labor force), such misassumptions in caused by a bid error, an inherently less effi-
the estimating process may not constitute a cient labor force, or the introduction of the
claim for labor inefficiency under most con- ripple effect of change to the project.
struction contracts.10
When cumulative impact occurs, it is the
When a project has been properly estimated effect of multiple changes to the work that
in terms of quantities and the original labor causes the majority of the loss of labor produc-
factors applied at the time of the bid, and the tivity, not each independent change itself. In
project sustains a measurable labor overrun, such cases, it is usually impossible to connect
then a condition resulting in a potentially an individual, single cause to a specific effect—
recoverable loss of labor productivity may on a change by change basis. However, the
have occurred. Such conditions should initi- contractor still must prepare a cogent narrative
ate a careful analysis of the project by the that provides the respondent with a logical
contractor’s management personnel.
11
“Recoverable” is a term that can be highly qualified
10
An excusable delay to the commencement of the or restricted by the terms and conditions of the con-
mechanical contractor’s work, such as by a differing site tract. Many contracts attempt to limit, or eliminate, a
condition that delays foundation and vertical construc- mechanical contractor’s right to recover labor ineffi-
tion, may justify such a loss of productivity claim based ciencies. Such contract terms should be the subject of a
on an assumed, reasonable overall production rate. careful legal review.

158 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

and factual basis for the contractor’s productiv- Evaluating the Potential
ity losses.12 If the cause can be identified as
Productivity Impacts of
arising from the impacts of multiple changes
on the project and not from the contractor’s Changes in Scope
self-inflicted acts and omissions, then the con- What are the potential constituents of cumu-
tractor should consider the application of the lative impact as we presently understand
studies and examples contained in this chapter them in the construction industry? In terms
to quantify the loss of labor productivity. commonly used in the construction industry,
cumulative impacts arising from a multitude
If the contractor is tracking its field erection of changes can include, without limitation,
labor by use of activity tracking or cost the following components:
account codes that divide the project into
identifiable segments, such as by buildings, ■ Stacking of Trades—congestion of
floors, rooms, or site facilities, management unplanned trades simultaneously working
can determine if the losses are project-wide or in limited spaces;
limited to certain specific areas or time frames. ■ Reassignment of Manpower—also
This sort of labor performance reporting is dis- known as labor disruption—the start-
cussed in much greater detail in the “Main- stop-restart condition frequently result-
taining Control of Labor Productivity” chapter ing from the introduction of new scopes
of this publication. Such contemporaneous of work into the existing labor plan, or
labor tracking is an important tool in forecast- the resequencing of activities to accom-
ing inefficient labor trends on a construction modate the introduction of other trades
project and can assist the management team in an unplanned fashion, or new activi-
in their efforts to connect causes with the ties (i.e., the scope change activities);
effects in terms of lost labor productivity.
■ Crew Size Inefficiency and Learning
Once a contractor determines that its crews Curve—resulting from the addition of
have sustained a measurable loss of labor pro- unplanned resources brought on site to
ductivity, and that such losses are not solely address the magnitude of the changed
the result of the contractor’s own acts or omis- work and their need to “learn” the project
sions, the contractor should seek to identify and assimilate into existing crews;
the source(s) of the productivity loss, mitigate
where practical, quantify the losses, and, if ■ Concurrent Operations—congestion
appropriate, seek recovery for those losses.13 caused by the stacking of the contractor’s
own forces to address the added change
activities;
12
“…it is clear that demonstrating an overrun in labor ■ Dilution of Supervision—redirection of
and the existence of numerous changes without some evi- field labor supervision’s attention from
dence linking the changes to the overrun is insufficient
proof of causation. Finally, there must be some proof of a
causal connection established showing that the undiffer-
13
entiated group of contract changes affecting the changed Even if the contractor determines that all or a portion
and the unchanged contract work resulted in the loss of of the loss of productivity has been caused by the con-
productivity on that work.” Reference the Appeal of Centex tractor, it is still essential for the contractor to identify
Bateson Const. Co. Inc., 99-1 BCA P 30153 (1998). the cause and to mitigate the loss wherever possible.

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 159
Productivity

managing base contract work to solving ficiently prior to the planning, coordination,
change scope issues—such as preparing fabrication, and installation of the affected
RFIs, directing crews performing changed work can be expected to have less impact than
work and ordering of materials arising changes that are issued in the heat of battle
from the changes; and and while the affected work is about to com-
mence or is already in progress. The impor-
■ Overtime—inefficiencies arising from an
tance of the timing of changes has been borne
unplanned overtime schedule required to
out by the research performed by the research-
mitigate the delaying factors arising from
ers at the University of California at Berkeley
changes to the work.14
and is demonstrated by the data contained in
The aforementioned categories, taken from this chapter.
the widely accepted MCAA table entitled “Fac-
It is helpful for contractors to record when
tors Affecting Labor Productivity” at pages 99
scope change work commences and is per-
through 100 herein, are among the list of pos-
formed. While the majority of contractors do
sible components of cumulative impact. On a
not code their actual field labor to scope
project with multiple changes, it can be diffi-
change or change order account codes, in
cult, or in some cases impossible, to segregate
some cases it is possible to track generally
the individual impact categories that caused
when changes are directed or otherwise
the loss of productivity arising from cumula-
authorized to commence and when the
tive impact. Thus, the data provided in this
changed work is performed.15 By tracking
chapter is presented to allow a contractor to
when scope change work is performed, a bar
estimate labor inefficiencies arising from
chart can be compiled demonstrating the tim-
cumulative impact in a more holistic fashion
ing of the scope change work. Such charts can
based on the manner in which the underlying
temporally depict the concurrent nature of
data was collected and analyzed.
multiple changes on a construction project
In addition to reviewing the labor tracking and aid in the preparation of a cumulative
records and interviewing the field supervision impact request for equitable adjustment.
in its investigation, the contractor should care-
It is a generally accepted axiom in the con-
fully assess the size, quantity in terms of labor
struction industry that the timing of changes
hours, and timing of changes in scope that
is important when considering the potential
have been issued. As will be described below,
effect of changes on labor productivity.
the timing of changes in scope is important in
Changes that occur early in the project and
the evaluation of the impacts of those scope
which affect downstream activities may not
changes to the base contract labor. Changes in
adversely affect the overall labor productivity.
scope that are issued early in a project and suf-
For example, if a scope change/change order
is issued near the outset of a two year project
14
The contractor should differentiate between short-
term “spot” overtime required to address immediate
15
scheduling needs and long term and unplanned over- When the cumulative impact arises from constructive
time that can cause a substantial loss of labor productiv- changes that are not recognized until after their per-
ity. Reference the chapter entitled “How to Estimate the formance or, in some cases, until the conclusion of the
Impacts of Overtime on Labor Productivity” herein on project, it may not be possible to track the start and stop
the subject of overtime inefficiency. dates of the change.

160 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

to modify piping on a vessel that is not minimal levels. Assuming these early changes
planned to be fabricated, installed, and piped allowed the contractor to easily incorporate
until the middle of the second year of con- the new or changed work into its planning,
struction, such changes may have a negligible coordination, fabrication and installation
effect on productivity because the influence of steps, an attenuated impact would be antici-
such changes can be assimilated into the nor- pated as compared with changes issued during
mal flow and rhythm of the work more easily. the peak crew periods. However, as the con-
tractor increases its crews and prosecutes mul-
However, most changes in scope are not issued
tiple work activities on several work fronts,
far enough in advance of the planning, coordi-
changes could be expected to have a substan-
nation, prefabrication, and installation of the
tial and increased adverse impact on the con-
work to allow the influences of the change to
tractor’s labor productivity. It is the labor-hour
be managed into an efficient work flow. Most
intensity of the change in scope, and its tim-
often, contractors are deluged with changes in
ing, that are the important considerations
scope as the work affected by those changes is
regarding the effects of the change on labor
being installed. When changes in scope are
productivity. The actual dollar value of the
identified and are required to be performed
change is not the determining factor as to its
during the “heat of battle,” when the crews are
potential impact on labor productivity.
ramping up or are at or near their peak, the
effects of such changes in scope on labor pro- An important feature of the inefficiency
ductivity can be devastating. study that underlies this chapter is its meas-
urement of inefficiencies arising from the
Figure 2 on the next page depicts the temporal
timing of the changes in scope. The studies
relationship between change, resource usage
and resulting data that underlie this chapter
and a value known as the Actual Contract
(i.e., the University of California at Berkeley
Labor Hours (ACLH). The ACLH calculation
Ibbs Study) were evaluated to determine the
and consumption curve will be explained in
effects of timing of the changed work, as
the next section of this chapter. The actual
crew size is shown on the z axis and, if desired,
the planned labor curve can be superimposed 16
These change work start and finish dates should be as
to show a contrast between planned and accurate as reasonably possible. As previously noted, the
actual. This is optional, but potentially very date on which a change order is executed may be totally
helpful information to show how the craft lev- irrelevant to the issue of labor productivity. A formal,
executed change order may “roll up” dozens of individ-
els responded to the addition of change work. ual scope changes and may not be approved until very
On the line graph, the contractor has plotted late in the project, thus shedding no light on when the
the dates on which scope change work actu- changed work scope was actually directed and per-
ally commenced and was performed16 and the formed. On some projects, an owner may never actually
execute any change orders and may direct the contrac-
rate of consumption of the ACLH. tor to perform added or changed work scope under the
applicable terms of the contract.
Figure 217 shows that certain scope changes
17
(SC), or interchangeably, change orders, were ACLH shown in this figure refers to Actual Contract
Labor Hours. This value is not simply direct payroll
directed to commence when the project was
hours; rather it is a computation of adjusted labor hours
in its early stages and when the crews were at that is fully described in the “Change and its Quantita-
tive Effect on Productivity” section of this chapter.

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 161
Productivity

Figure 2: Example of Scope Change Timing Chart with Craft Level Curve

well as the effects of the magnitude of the until recently there was little authoritative
ratio of changes to the base contract labor and reliable research into the quantitative
hours. In a following section of this chapter relationship between change and loss of labor
describing the use of the Ibbs cumulative productivity.18 This dearth of information led
impact curves, the manner by which the CII to fund an extensive, two-year study led
user can categorize a change as “early,” by Professor William Ibbs, PhD, a co-author
“median,” or “late” will be defined in detail. of this chapter, and his University of Califor-
nia at Berkeley research team.
Change and its Quantitative The study was funded by large, sophisticated
Effects on Productivity owners and contractors and was reviewed
and overseen by a balanced audience. The
Despite the fact that change clearly has meas-
published results were endorsed by represen-
urable and oftentimes adverse impacts on a
tatives of a majority of the stakeholders in a
construction project’s labor productivity,

162 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

typical construction project. The Berkeley with a general contractor or construction man-
researchers collected extensive amounts of ager at risk and 17 percent utilized a design-
data from 172 projects and tested various build delivery system. Seventy six percent of
research hypotheses by sophisticated statisti- the private projects were design-build, with 20
cal methods. Follow-up interviews were con- percent using a design-bid-build delivery sys-
ducted with the project participants to pro- tem and 4 percent utilizing a hybrid contract
vide quality control on the data and to delivery system. Of the public projects, 65 per-
understand the contexts of the projects. cent were lump sum, 31 percent were unit
price and 4 percent cost plus. Of the private
The projects ranged in size from $3.2 million
projects, 53 percent were lump sum and 40
to $15 billion, with a median value of $62
percent were cost plus. Eleven percent of the
million, and included both domestic and for-
public projects were multi-prime as were 8 per-
eign worksites. Ninety-two percent of the
cent of the private sector projects. Fifty-seven
sample projects were constructed in the
percent were new, greenfield projects and the
United States. Sixty-two percent of the sam-
balance renovation or expansion projects.
ple projects consisted of private sector proj-
ects and the remaining 38 percent were pub- The private projects in this database con-
lic sector projects. Of the public sector tained the following types of construction:
projects, 31 percent were highway and
■ Petrochemical . . . . . . . . . . . . . . . . . . .27%
bridge, 20 percent rail systems, 19 percent
commercial and school buildings and 15 per- ■ Power generation . . . . . . . . . . . . . . . . .19%
cent hospitals, with the balance consisting of ■ Heavy manufacturing . . . . . . . . . . . . .16%
airports and canals.
■ Light manufacturing . . . . . . . . . . . . . .12%
Forty-one percent of the sample projects were
design-build and the balance of the projects ■ Commercial buildings and
utilized a design-bid-build contract delivery sys- other types . . . . . . . . . . . . . . . . . . . . . .26%
tem. Fifty-two percent were fixed price (either Labor hour and labor, material, subcontrac-
lump sum or unit price) and 48 percent were tor, and overhead cost data were collected for
cost reimbursable projects. Eighty three percent the projects at the 25 percent, 50 percent, 75
of the public projects were design-bid-build percent, 80 percent, 85 percent, 90 percent,
95 percent and 100 percent completion
points in the design and construction phases.
18
Over 15 years ago, a cumulative impact study was
authored by Charles Leonard (the “Leonard Study”) and The data points representing each of the 172
was widely circulated in the construction industry. The total projects were analyzed and plotted as
Leonard Study found that the cumulative impact of mul- can be referenced in Figure 3 on the next
tiple changes on a construction project adversely affected
a contractor’s labor productivity. This study also found page. The curved line represents the best-fit,
that the timing of changes affected labor productivity. regression for the total projects under study
This study was later criticized in several court cases, pri- and the equation for that line is represented
marily for its manner of data collection and statistical
by the mathematical expression shown in the
analysis. The study utilized in this chapter was carefully
composed and monitored in order to avoid, and then to figure. The R² value19 is a measure of the line
correct, those data collection and statistical analysis
errors for which the Leonard Study was criticized.

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 163
Productivity

goodness for fit for the universe of projects in As described above and as shown in Figure
the study; R² = 0.72 indicates a good fit. 3, the data collected and analyzed by the
Ibbs Study research team were transferred
Percent Change as used in this chapter is
onto charts for use in the construction
defined as: change labor hours20 ÷ Actual
Contract Labor Hours (ACLH). Actual Con-
tract Labor Hours are the total number of 19
The R² value is known as the correlation coefficient and is
actual payroll field labor hours minus change used in statistical models whose main purpose is the pre-
labor hours and minus all appropriate con- diction of future outcomes based on other related infor-
mation. This value states the proportion of variability in a
tractor adjustments. These adjustments would data set that forms a statistical model, such as regression
include, without limitation, bid errors and analyses as utilized in the Ibbs models. The R² value pro-
contractor field mistakes. Examples of such vides a measure of how well future outcomes are likely to
be predicted by the model, thus within the range of 0 to
potential downward adjustments will be pro-
1, the closer the value is to 1, the more likely it will be
vided later in this chapter. that the prediction will resemble the result.

Figure 3

164 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

industry. From the extensive data that was presented herein represent the estimated
gathered, the research team identified three impacts to labor productivity when changes
separate data curves based on the timing of at a particular level are issued early, at a
the issuance of changes in scope. The data median point, or late in the project. These
terms, and the means by which projects are
20 categorized as “early,” “median,” or “late”
In order to offer a more conservative inefficiency esti-
mate, the labor hours contained in T&M tickets are not models, are fully defined and explained in a
included in the percent change computation for the later section of this chapter. The data
purpose of this chapter. By virtue of the way T&M resulted in the following three curves.
charge tickets are maintained, they usually have the
direct inefficiencies embedded within the T&M entries. These two variables, percent change and per-
We have taken the conservative approach of not includ- cent productivity, were compared, as can be
ing these hours in the computation of the percent
change value. However, if a significant portion of the seen in Figures 4 A-C. Each of the data
total change hours were recorded on T&M tickets, this points in these figures represent a project in
exclusion of T&M hours in the percent change compu- the Ibbs study. The R² values for the three
tation may be revisited by the contractor, since the
curves shown in Figures 4 A-C are as follows:
exclusion of a major portion of the change hours
recorded on T&M tickets could unfairly affect the out- 0.81 for the “early” timing curve, 0.63 for
come of the labor inefficiency estimate. the “median” timing curve and 0.76 for the

Figure 4-A

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 165
Figure 4-B

Figure 4-C

166 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

“late” timing curve. All provide for reason- tor’s planned productivity of approximately
able forecasts of labor inefficiencies that can 25 percent.
be expected at various ratios of changes to
In this portion of the Ibbs Study projects were
adjusted base contract hours.
ranked as having change at an early, median
Several points emerge. First, larger amounts point or late stage of the project. As to the
of change result in greater loss of productiv- timing of change, this study utilizes the total
ity. For instance, a project with 20 percent ACLH by establishing the mid-point of the
change (measured on the horizontal axis of project based on the actual utilization of one
the median curve) results in a loss of labor half of the ACLH, as depicted in Figure 6 on
productivity of approximately 25 percent. In the next page and as described below.
other words, the cumulative impact of
The Change Timing Designation Chart in Fig-
changes causes a reduction in the contrac-
ure 6 demonstrates how each of the three
timing models is defined. Follow these steps:

Figure 5

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 167
Productivity

Figure 6: Change Timing Designation Chart

1) compute the ACLH as described in this pute the percent of change hours expended
chapter, we will call that labor hour number prior to, and after, the ACLH midpoint.
X; 2) by referencing payroll or other labor
By way of example, the ACLH on a project
hour data,21 determine when, in time, one
was calculated to be 16,000 field craft labor
half of X was actually expended, this is
hours. The claimant would refer to payroll
known as the ACLH midpoint; 3) by referenc-
records to determine when 8,000 field craft
ing change pricing folders, time sheets or
hours had been expended on the project.
other data, determine when change work was
The date on which 8,000 field craft labor
performed; 4) from that data, determine how
hours had been expended would mark the
many change hours were expended before,
ACLH midpoint for the purpose of deter-
and after, the ACLH midpoint; and 5) com-
mining the timing categories of change. The
claimant would then determine when
21 change hours were expended and from that
For the purposes of this chapter, field craft labor
hours should not include non-working labor categories. data, compute the percent of change hours
Such non-working categories could include superintend- that were expended before, and after, the
ents, general foremen and foremen, depending on the ACLH midpoint.
size of the project, local union requirements and custom
and practice of the contractor.

168 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

Early change means that about 70 percent of Ibbs Study are not represented to be precise
change hours were expended before the ACLH computations. They are represented to be reli-
midpoint, median change means that about able estimates of productivity losses when
50 percent of the change hours were expended properly applied.
before the ACLH midpoint and “late” change
Example No. 1: A project was planned to uti-
means that about 70 percent of change hours
lize 16,500 field craft labor hours (excluding
were expended after the ACLH midpoint.
non-working supervision). At the conclusion
Note that in most cases, 100 percent of the of the project, the payroll reports show an
ACLH hours will be expended before the proj- actual expenditure of 30,000 field craft labor
ect has been completed. That is because the hours, excluding non-working supervision.
ACLH hours exclude various components such Upon careful investigation it was discovered
as bid labor hour mistakes, field retrofit caused that there was a bid error of 1,500 field craft
by the contractor and the change work, thus labor hours, errors in construction that
the ACLH will achieve 100 percent before all required 900 field craft labor hours to repair,
of the labor hours are consumed on a project. and 500 hours were recorded via T&M tickets.
Also note from Figure 6 that the ACLH mid- Moreover, the contractor estimated that 5,500
point will probably not match the midpoint of hours were expended on scope change work,
the overall project timeline measured by other other than the T&M time tickets noted above.
indices, such as billing values, total hours con- Based on the formula described above, the
sumed or work days accomplished. This is to Actual Contract Labor Hours would be com-
be expected. As previously noted, 100 percent puted as follows:
of the ACLH will be consumed prior to the
Total field craft labor hours actually
actual completion of the project.
expended on the project: . . . . . . . . 30,000
As can be seen in Figure 5, projects with
Bid error: . . . . . . . . . . . . . . . . . . . . . (1,500)
early recognition of change incurred less loss
of productivity than projects with median or Field errors: . . . . . . . . . . . . . . . . . . . . (900)
late changes. For example, at 20 percent T&M ticket time: . . . . . . . . . . . . . . . .(500)
change, the “late” projects suffered about
twice as much productivity loss as the Scope changes/change order
“early” projects. These curves reinforce the labor hours: . . . . . . . . . . . . . . . . . . .(5,500)
notion that it is better to address change Actual Contract Labor Hours . . . . .21,600
earlier in a project than to postpone resolu-
From the example above, it is clear that the
tion of the issues causing change.
Actual Contract Labor Hours are not simply
the actual payroll hours; the ACLH value has
Examples of Cumulative been derived by reducing the actual payroll
Impact Quantification hours by various factors such as bid errors or
Below are three examples of the use of the field retrofit. The factors will vary from proj-
cumulative impact studies. These studies pro- ect to project and must be determined by the
vide a basis to estimate a contractor’s loss of contractor’s management team. Once the
labor productivity caused by cumulative Actual Contract Labor Hours have been com-
impacts. The results gained from applying the puted, the timing of the labor expenditure

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 169
Productivity

must be plotted using the payroll or labor change work was performed. Also, the actual
performance reports. The date at which 50 (or estimated) labor hours of each change must
percent of the ACLH were expended (10,800 be determined utilizing payroll reports, field re-
hours of payroll labor expenditures out of cords or an estimate. By determining change
the total of 21,600 ACLH hours) is consid- hours performed before and after the midpoint,
ered the midpoint of the project for purposes the appropriate curve can be selected.
of assigning the proper curve to the ineffi-
In this example, it was determined that
ciency analysis that follows.
approximately 74 percent of the change hours
The next step would be to identify from the were expended by the midpoint, thus the first
actual records, or estimate if such records are graph (early) on the curve is chosen to calcu-
not available, the dates during which the late the impact to the labor productivity.

Figure 7

170 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

Figure 8

From the formulas provided above: Percent curve on Figure 8 it can be seen that 26 per-
Change = Change Labor Hours ÷ Actual Con- cent intersects the “early” curve at a produc-
tract Labor Hours. Percent Change = 5,50022 tivity loss of approximately 20 percent. A
÷ 21,600 = 25.46% = 26%. The percent loss of 20 percent of the ACLH of 21,600
change for this example is 26 percent. equals a loss of productivity of approxi-
mately 4,320 field craft labor hours.
From the example above, it was determined
that the project sustained a 26 percent Special Note: When performing a loss of pro-
cumulative change impact. From the “early” ductivity computation from industry studies, it
is advisable to test the results by way of a “mo-
22
The change hour totals in the examples included in
dified total cost” evaluation (in this case, labor
this chapter for the calculation of the percent change hours are substituted for the “cost” value). This
value do not include T&M ticket hours, as previously will allow the contractor to analyze the
explained herein. amount of labor hours being claimed as cumu-

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 171
Productivity

lative impact inefficiency in comparison with formula described above, the Actual Contract
the total unallocated labor loss on the project. Labor Hours would be computed as follows:
From Example No. 1 above, a modified total
Total field craft labor hours actually
labor hour calculation would appear as follows:
expended on the project: . . . . . . . . 20,000
Total field craft labor hours actually
Bid error: . . . . . . . . . . . . . . . . . . . . . (1,200)
expended on the project: . . . . . . . . 30,000
Field errors: . . . . . . . . . . . . . . . . . . . (1,000)
Original estimate: . . . . . . . . . . . . . (16,500)
T&M ticket time: . . . . . . . . . . . . . . . . (300)
Bid error: . . . . . . . . . . . . . . . . . . . . . (1,500)
Scope changes/change order
Field errors: . . . . . . . . . . . . . . . . . . . . (900)
labor hours: . . . . . . . . . . . . . . . . . . (4,000)
T&M ticket time: . . . . . . . . . . . . . . . . (500)
Actual Contract Labor Hours . . . . . 13,500
Scope changes/change order
Once the Actual Contract Labor Hours value is
labor hours: . . . . . . . . . . . . . . . . . . (5,500)
computed, the timing of the labor expenditure
Unallocated labor loss due to must be plotted using the payroll or labor per-
all causes: . . . . . . . . . . . . . . . . . . . . . 5,100 formance reports. The date at which 50 percent
of the Actual Contract Labor Hours were
Since the cumulative impact recovery com-
expended (6,750 hours of actual payroll-sup-
puted in this example was 4,320 hours, there
ported labor was expended of the total of
remains 780 hours of unallocated loss of
13,500 hours) is considered the “midpoint” of
labor productivity. This unallocated labor loss
the project for purposes of assigning the proper
can be explained in the contractor’s narrative
curve to the inefficiency analysis that follows.
as potential unclaimed losses caused by the
contractor’s own acts or omissions (so as not The next step would be to identify from the
to assert an otherwise perfect performance) or actual records, or to perform an estimate if
simply as an undefined, and unclaimed, such records are not available, the actual per-
amount of lost labor hours. formance dates of the change work. Also, the
actual (or estimated) labor hours of each
Example No. 2: A project was planned to uti-
change must be determined. As described in
lize 8,000 field craft labor hours (excluding
Example No. 1, the timing component is
non-working supervision). At the conclusion of
thereby computed and the appropriate curve
the project, the payroll reports show an actual
is chosen from the timing chart.
expenditure of 20,000 field craft labor hours,
excluding non-working supervision. Upon a As shown in Figure 9, it was determined that
careful investigation, it was discovered that approximately 50 percent of the scope change
there was a bid error of 1,200 field craft labor hours were expended by the “midpoint,” thus
hours, errors in construction that required the second graph (median) on the curve is cho-
1,000 field craft labor hours to repair, and 300 sen to calculate the impact to the labor produc-
hours were compensated by T&M tickets. tivity. Note on this example that the scope
Moreover, the contractor estimated that 4,000 change timing has been taken from field re-
hours were expended on scope change work cords or has been estimated by the project staff.
(net of the T&M ticket hours). Based on the Further, the number of field craft labor hours

172 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

Figure 9

(actual or estimated) has been determined for impact. From the “median” curve on Figure 10
each change. Thus, at the time approximately on the next page it can be seen that 30 percent
half of the change hours have been expended, intersects the median curve at approximately
the contractor has expended approximately 35 percent. A loss of 35 percent of the Actual
half of its Actual Contract Labor Hours. Contract Labor Hours of 13,500 equals a loss of
productivity of 4,725 field craft labor hours.
From the formulas provided above: Percent
Change = Change Labor Hours ÷ Actual Con- Example No. 3: A project was originally
tract Labor Hours. Percent Change = 4,000 ÷ estimated to utilize 8,200 field craft labor
13,500 = 29.6% = 30%. hours (excluding non-working supervision).
At the conclusion of the project, the payroll
From the above example, it was determined
reports show an actual expenditure of
that the project sustained a 30 percent change
40,000 field craft labor hours, excluding

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 173
Productivity

Figure 10

non-working supervision. Upon a careful Field errors: . . . . . . . . . . . . . . . . . . . (2,500)


investigation, it was confirmed that the bid
T&M ticket time: . . . . . . . . . . . . . . (1,000)
was accurate and complete, errors in con-
struction required 2,500 field craft labor Scope changes/change order
hours to repair, and 1,000 hours were com- labor hours: . . . . . . . . . . . . . . . . . (12,000)
pensated T&M tickets. Moreover, the con- Actual Contract Labor Hours . . . . . 24,500
tractor estimated that 12,000 hours were
expended on scope change work. Based on Once the Actual Contract Labor Hours are
the formula described above, the Actual computed, the timing of the labor expendi-
Contract Labor Hours would be computed ture must be plotted using the payroll or
as follows: labor performance reports. The date at which
50 percent of the Actual Contract Labor
Total field craft labor hours actually Hours were expended (12,250 hours of actual
expended on the project: . . . . . . . . 40,000 payroll-supported labor was expended of the

174 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

Figure 11

total of 24,500 hours) is considered the mined if the change model is “early,”
“midpoint” of the project for purposes of “median,” or “late.”
assigning the proper curve to the inefficiency
In this example from Figure 11, above, it
analysis that follows.
was determined that only approximately 28
The next step would be to identify from the percent of the scope change hours were
actual records, or to perform an estimate if expended by the “midpoint,” thus the
such records are not available, the actual third graph (late change) on the curve is
start date of the scope changes. Also, the chosen to calculate the impact to the labor
actual (or estimated) labor hours of each productivity. Note in this example that the
change must be determined. From this data scope change timing has been taken from
applied to the timing chart, it can be deter- field records or has been estimated by the
project staff. Further, the number of field

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 175
Productivity

craft labor hours has been determined tract Labor Hours. Percent Change = 12,000 ÷
(from charge records such as time sheets, 24,500 = 48.9% = 49%.23
contemporaneous field reports, or esti-
From the above example, it was determined
mated) for each change. Thus, at the time
that the project sustained a 49 percent cumu-
approximately half of the Actual Contract
lative change impact. From the late change
Labor Hours had been expended, only 28
curve within Figure 12 it can be seen that 49
percent of the change hours had been
percent intersects the late change curve at a
expended. Therefore, in the last half of the
productivity loss of approximately 61 percent.
project, 72 percent of the change hours
were expended, making this example a late
23
change project. Note that the data points do not support a Percent
Change value greater than 50 percent. No extrapolation
From the formulas provided above: Percent of the data lines should be performed to allow for Per-
Change = Change Labor Hours ÷ Actual Con- cent Change values in excess of 50 percent.

Figure 12

176 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

A loss of 61 percent of the Actual Contract shion as if a change, or series of unanticipated


Labor Hours of 24,500 equals a loss of produc- changes, were introduced into the project dur-
tivity of 14,945 field craft labor hours. ing the same performance period. The contrac-
tor would usually not be able to recover such
losses from a prime contractor or owner. In
Special Consideration for cases where this type of bid error has been
Projects with Substantial Bid identified, it is reasonable to treat this bid error
Mistake Adjustments Not in the same manner as a scope change or series
Identified Early in the Project of changes when preparing a cumulative
impact analysis.24
Schedule
Today’s computerized estimating and BIM coor- Example 4 offers an illustration of how a con-
dination processes that are undertaken before a tractor might address the impact of this type
contractor mobilizes on a project make it more of bid mistake:
likely that bid mistakes will be discovered Example No. 4: At the conclusion of a proj-
before the actual fabrication and construction ect, the contractor’s payroll reports show an
phases of the project commence. In the past, actual expenditure of 34,500 field craft labor
usually the only way a contractor could verify hours, excluding non-working supervision.
an estimate was to have the project team per- This amount exceeded the contractor’s labor
form a re-estimate of the project prior to mobi- plan by many thousands of hours. Upon a
lization. That process is still utilized by some careful investigation, it was discovered that
contractors who are not fully adapted to the there was a bid error of 2,500 field craft
more advanced technologies. labor hours. Moreover, the contractor esti-
When bid labor errors, even serious ones, are mated that 5,500 hours were expended on
recognized at the outset of a project such that scope change work. Based on the formula
the labor hours that were omitted from the bid described above, the Actual Contract Labor
are able to be assimilated into the labor plan Hours would be computed as follows:
before work commences, or very early in the Total field craft labor hours actually
project, the labor productivity impacts should expended on the project: . . . . . . . .34,500
be mitigated to a greater extent. Certainly, the
contractor will feel the direct financial impact Bid error: . . . . . . . . . . . . . . . . . . . . . (2,500)
of having to provide the labor hours that were Scope changes/change order
missed in the estimate; however, such estimat- labor hours: . . . . . . . . . . . . . . . . . . (5,500)
ing errors would not be expected to diminish
Actual Contract Labor Hours . . . . 26,500
the contractor’s overall field labor productivity.
As described in Examples 1 through 3, the
However, if a serious labor estimating error
next step is to identify from the actual
were to occur that was not diagnosed early in
the project and that required the expenditure
24
of a material number of labor hours in the The claimant would compute the loss of labor pro-
ductivity arising from such types of bid error and
midst of the project, the contractor’s productiv- demonstrate, in its request for equitable adjustment,
ity would be expected to suffer in the same fa- that these labor hours were not being claimed in the
total labor hours sought in the claimant’s recovery.

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 177
Productivity

records, or to perform an estimate if such “median” curve is chosen to calculate the


records are not available, the dates during impact to the labor productivity.
which the change work was performed. This
A revised formula can be applied in the case
special example also requires the contractor
of a major bid labor hour estimate error that
to know, or to estimate, the dates when the
was not discovered until the labor to per-
“missed” bid labor hours were added into the
form the “missed” work was actually
project schedule. In this case, the contractor’s
required: Percent Change = (Change Labor
bid error labor hours are treated just as if
Hours + Bid Error in Labor Hours) ÷ Actual
those hours were the result of change.
Contract Labor Hours. Percent Change =
In this example, it was determined that 8,000 ÷ 26,500 = 30.2% = 30%. The Percent
approximately 50 percent of the change Change for this example is 30 percent. This
hours and the “missed” labor hours were percent represents the total loss of productiv-
expended by the “midpoint,” thus the

Figure 13

178 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

ity caused by change and the contractor’s Application of Cumulative


bid error.
Impact Analyses on Projects
From the above example, it was determined with Very Limited Project
that the project sustained a 30 percent
Records
change ratio. From the “median” curve on
Sometimes on a limited number of construc-
Figure 13 it can be seen that 30 percent
tion projects, events occur that severely
intersects the “median” curve at a loss of
reduce the factual data that analysts may rely
productivity of approximately 38 percent. A
upon to perform an assessment of productiv-
productivity loss of 38 percent of the ACLH
ity. This condition may rise from the failure to
of 26,500 equals a loss of productivity of
contemporaneously maintain anything but
approximately 10,070 total field craft labor
the most rudimentary payroll records, or, in
hours arising from the changes and the con-
other cases, the loss of project records due to
tractor’s bid error.
changes in the management staff or computer
The claimant must apportion the total loss systems. With the inability to question mem-
of productivity of 10,070 field hours bers of the management team25 or to review
between the contractor and the respondent, change files or other contemporaneous data,
as follows: bid error of 2,500 hours; 2,500 the analyst is severely hampered in the use of
hours of contractor caused impact ÷ 8,000 the methods provided in this chapter. Sug-
hours of total change = 31% to the contrac- gested steps will be provided that may assist
tor’s account. Similarly, 5,500 hours of scope the analyst in the use of the methods
change hours ÷ 8,000 hours of total change included herein, however, as an alternative,
= 69% to the respondent’s account. The allo- the contractor should evaluate and consider
cation would therefore be: 10,070 hours of the use of the MCAA’s labor inefficiency fac-
lost production x 31% = 3,122 hours to the tors contained in the “How to Use the MCAA
contractor’s account and 10,070 hours of Labor Factors” chapter herein to estimate the
lost production x 69% = 6,948 hours to the adverse effects of cumulative impact.
respondent’s account. The contractor would
For the purposes of this subsection, the fol-
seek a recovery of 6,948 hours of loss of
lowing assumptions have been made:
labor productivity caused by cumulative
impact but would not claim the 3,122 hours ■ The management team, including the
of productivity impacts caused by its own project managers and field superintend-
bid errors that had to be remedied in an ents, are not available for interview or
unplanned fashion in the midst of the proj- offer very limited probative value;
ect. This approach can also be used to
■ The superintendents’ diaries and daily
address particularly sizable contractor instal-
reports are not available or are not useful;
lation errors that require the contractor to
introduce significant, unplanned labor hours
into the project during the course of con-
struction to re-install or repair the installa-
25
tion deficiencies. On some projects, the entire field office management
team is either terminated or terminates employment,
making the process of fact finding even more difficult.

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 179
Productivity

■ Change order files do not provide for tem- formed, the signature dates may be used to
poral tracking of the change order work; estimate its timing. With this information,
the change work can generally be determined
■ Basic payroll information is available
to be of the early, average, or late variety.
Given this difficult situation, the following
This estimate of the change hours can then
steps are recommended:
be compared to the number of labor hours in
A first step would be to consider retaining a the bid. (Adjustments need to be made for
competent loss of productivity expert who any bid errors as discussed earlier in this
can advise, in very preliminary terms, on the chapter.) Dividing the change hours by the
prospects of recovery given the limited data. bid hours yields a very gross percent change
Whether through an attorney or a consult- value. For illustrative purposes and using the
ant, the contractor can catalogue the avail- preceding formula, let us assume that this
able project information to develop the best project’s percent change is 10 percent.
strategy for a reasonable recovery. Depending on whether the project experi-
As the contractor’s team engages in the collec- enced early, median, or late change, the loss
tion of all pertinent support for the preparation of productivity would be between 4 percent
of the request for equitable adjustment, sub- and 10 percent, which is useful information,
contractors and vendors may be polled for as seen in Figures 4-A, 4-B, and 4-C.
information to support the timing of change. Those same figures also yield another piece of
The owner, designer and, if one was utilized, useful information. Inspection of those figures
construction manager may have key informa- reveals that all the projects in this database
tion (which probably will have to obtained which had 10 percent change experienced a
through the discovery process) by which the loss of productivity. This is demonstrated by
timing and scope of changes can be ascer- noting that none of the data points in those
tained. Other sources may be useful such as three figures were associated with a productiv-
building inspection and permitting authorities, ity index above 1.0. This means that not only
progress photographs maintained by the owner did the contractor have a productivity loss in
or architect, and even mapping services. the 4 percent to 10 percent range; it also
It is assumed for the purposes of the extreme means that there is a high probability that
condition of a dearth of contemporaneous such a loss was incurred.
records, that the change orders or change The discussion above has been focused on a
directive documents are available for review. project with virtually no extant records beyond
A reasonable estimate of the labor hours basic payroll information. This discussion ac-
involved in each of these changes can be centuates the need for the contractor to main-
derived from the pricing information by tain contemporaneous change records that
identifying or estimating the labor proportion may include the initiating RFI, change propos-
of the change order and dividing that labor als, photographs, related correspondence,
cost by an average hourly labor rate. If the diaries or notations citing when change work
description of the change work does not as performed and all associated contract modi-
identify when the change work was per- fication documents. Generally, the more robust

180 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

the recordkeeping, the more compelling will be tions, arbitrations and in trial courts.26 That
the resulting request for equitable adjustment. research clearly indicates there are strong cor-
relations between the amount of change and
the loss of productivity. The cited research
Summary and Conclusions indicates that the timing of change is a key
Virtually all projects, even the most compre- factor as well. The concepts of cumulative
hensively planned and designed and carefully impact and the timing influence of change
scoped, have change. Change can adversely have been accepted in international arbitra-
affect labor productivity, which in turn can tions as realities in the construction industry.
substantially reduce or even eradicate a con- The Ibbs Study also had been published in
tractor’s profit. Contractors deserve to be peer-reviewed scientific journals.27
timely and fairly compensated for change.
While many owners are willing to pay the Also, contractors should be aware that cumu-
direct costs of project change, often there is a lative impacts may result in critical path
resistance and reluctance to pay for the schedule impacts. Labor inefficiency can
impact costs of change. This resistance and cause growth in activity durations that may
reluctance can arise from the contractor’s lack erode total float or impact the critical path.
of documentation and the lack of proper cita- This chapter does not deal with project delay.
tion to industry-accepted means of impact Your attention is directed to the chapters
quantification. This chapter has addressed this entitled “Time Impact Analysis—Measuring
latter issue through the publication of a reli- Project Delay” and “How to Organize and
able method to estimate labor inefficiencies Submit a Claim,” which address potential
arising from cumulative impact. project delay caused by productivity impacts.

Contract change often results in disputes over As with all industry study applications, the
the quantitative impacts of the change, par- results should provide for a reasonable estimate
ticularly the impacts on labor productivity. As of the damage—not a precise computation.
previously stated, those impacts are discussed The contractor making a claim for cumulative
in this chapter and an approach to quantify- impact should perform an investigation of
ing these impacts is presented. This approach, the facts, provide a narrative explaining how
developed by one of the co-authors of this the magnitude of change adversely affected
chapter, has been used to resolve numerous the labor productivity28 and should apply the
disputes and has been accepted in media- Ibbs data and resulting curves in a proper

26
As of the date of this publication, there have been no 28
Construction productivity cases often mention the
published decisions citing the study that is the subject
need to establish the “cause-and-effect nexus,” how-
of this chapter.
ever the nature of cumulative impact renders it virtu-
27
“Evaluating the Cumulative Impact of Changes on ally impossible to tie individual changes to specific
Labor Productivity – an Evolving Discussion,” Dr. W. effects in terms of labor productivity impacts. How-
Ibbs and G. McEniry, Cost Engineering, Vol. 50/No. 12, ever, that does not relieve the contractor from evaluat-
December 2008, Association for the Advancement of ing its estimating, labor performance and documentary
Cost Engineering International; and Ibbs, William records to demonstrate that the impacts were not self-
(2005). “Quantitative Impacts of Project Change: Timing inflicted and to offer a narrative that describes the con-
Issues,” Journal of Construction Engineering and Manage- tractor’s plan and how that plan was disrupted by the
ment, ASCE, 131(11), November, 1219-1223. influences of multiple changes on the project.

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 181
Productivity

Figure 14: Sample Inefficiency Chart for Readers’ Use29

manner. The finding in S. Leo Harmonay, Inc. Every project and every dispute should be
(cited at page 123 herein) represents sound evaluated with the facts of the situation in
reasoning in this regard: mind. Applying the approach presented
herein without careful regard to the actual
... courts have often recognized that the extent
circumstances that took place on the project
of harm suffered as a result of delay, such as
could lead to errors in the quantification of
the loss of efficiency claim at issue, may be diffi-
the impacts that a project has incurred. How-
cult to prove. Thus, courts have recognized that
ever, if the contractor making claim for
a plaintiff may recover even where it is appar-
ent that the quantum of damage is unavoidably
uncertain, beset by complexity, or difficult to 29
This chart is provided for the contractor’s use in plot-
ascertain, if the damage is caused by the wrong. ting Percent Change and the resulting Percent Produc-
tivity. If desired, this chart may be copied and inserted
into the contractor’s request for equitable adjustment to
demonstrate the plotting of the data.

182 Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved.
Productivity

cumulative impact prepares a comprehensive Change timing chart showing the actual or
narrative report that describes the contractor’s estimated start and finish dates of the changes
reasonable plan for the work, how that plan to the original contract scope of work;
was disrupted and impacted by unanticipated
Application of the cumulative impact
change, and how the contractor estimated its
methodologies provided in this chapter utiliz-
loss of labor productivity by properly apply-
ing the appropriate curves and calculations;
ing the methodology provided in this chap-
ter, the contractor may improve its opportu- Proof of damages as recorded in job cost
nity to amicably and equitably resolve its reports or other accounting documentation
productivity loss claim. and a summary of damages that are sought as
the contractor’s recovery in its request for
The contractor should consider including in
equitable adjustment or claim document.
the submission of its cumulative impact
change request the following items: By properly applying the methodologies
described herein and by preparing a compre-
Review of all pertinent documents, such as
hensive narrative of the cause-and-effect
the contract, executed change order forms,
nexus, a mechanical contractor may enhance
and monthly payment applications, by the
its opportunities to recover cumulative
contractor’s executive management and/or
impact damages.
construction counsel to ascertain waiver risks,
if any, for recovering cumulative impact;
Prepared by Professor William Ibbs, PhD, University of Cali-
Modified total cost calculation showing the
fornia, Berkeley and Paul L. Stynchcomb, CCM, PSP, CFCC
unallocated loss of labor productivity; of Vero Construction Consultants Corp. with peer review
performed by: Michael R. Cables, Executive Vice President
Narrative of the contractor’s reasonable plan of Kinetics Systems, Inc.; Norman Escover, COO of Kinetics;
to construct the project within the labor Richard Freeman, Vice President of Stromberg Metal Works;
hours contained in its original, or revised, Charles F. Mitchell, General Counsel of The Kirlin Group;
labor estimate and a contrasting description and the members of MCAA’s Education Committee.

of what events took place to change that rea-


sonable plan—including comparative crew
curve graphics, as-planned and as-built sched-
ule analyses, photographs of impacting con-
ditions, pertinent daily reports and corre-
spondence, and other contemporaneous and
relevant proofs of the impacting conditions;
Description of all adjustments that have been
made in the computation of the contractor’s
loss of labor productivity including: estimate
errors, contractor’s field rework, and total
change hours;

Management Methods Bulletin PD4. © 2016 MCAA. All rights reserved. 183
Overtime

How to Estimate the Impacts


of Overtime on Labor
Productivity
Introduction chapter also will set forth some general guide-
The cost impact of unplanned extended over- lines for a mechanical contractor’s considera-
time work1 may exceed the increased costs of tion in assessing the labor inefficiency impact
the premium pay associated with an overtime of unplanned extended overtime. The princi-
work schedule. This impact comes in the ples set forth in this chapter can provide
form of reduced worker productivity as com- meaningful guidance in estimating the loss of
pared with the productivity of work per- labor productivity arising from overtime in
formed on a straight-time basis. A mechanical the forward pricing of change orders as well as
contractor confronting significant periods of in a retrospective application.
unplanned extended overtime work must Previous MCAA publications on overtime inef-
consider the reduced productivity associated ficiency included histograms that depicted loss
with working an overtime schedule. of labor productivity data based on various
A number of published studies attempt to overtime schedules. The histograms published
quantify the decrease in labor productivity in MCAA’s Bulletin Nos. 18-A and 20 were
associated with working extended overtime in based on the 1947 U.S. Department of Labor
the construction industry. This chapter will Bulletin No. 917, a study of prolonged over-
discuss the most frequently cited studies that time worked in the manufacturing sector. As
have been used to quantify overtime labor several courts and commentators have recog-
inefficiency in the construction industry. The nized, the 1947 Bulletin No. 917 has limited
application in the construction industry.2 As a
result, MCAA Bulletin Nos. 18-A and 20 have
now been superseded by this version. This cur-
1
We are unaware of any data showing the difference in rent publication is based on more recent stud-
impact, if any, between “planned” and “unplanned”
overtime. Generally, planned overtime has been
included in the base contract estimate and was
accounted for in the baseline CPM schedule. Unplanned 2
See, e.g. Appeal of J.A. Jones Constr. Co., 00-2 BCA ¶
overtime, which is the subject of this chapter, occurs 31000, ENGBCA Nos. 6386, 6387, 6390; 2000 WL
when no overtime, or only very limited overtime for 1044011 (Eng. BCA 2000) (“The study itself states that it
equipment setting or start-up tasks, was contemplated was based upon prolonged overtime schedules in manu-
under the terms of the base contract and is imple- facturing plants and that it may not be applicable to
mented during the course of construction. construction projects.”)

Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 185
Overtime

ies that provide a basis of estimating labor reduced productivity effects of overtime
inefficiencies utilizing data provided by con- schedules. These effects can include fatigue,
struction contractors or from quantitative data increased absenteeism, increased incidence of
actually measured on construction projects. accidents, reduced morale, and a more nega-
tive work attitude.
Background While many prime contractors and owners
Often mechanical contractors are directed may be willing to pay the mechanical con-
by an owner or general contractor to acceler- tractor’s direct cost of overtime if the acceler-
ate the work for a variety of reasons. Acceler- ation was not caused by the mechanical con-
ation can be achieved by adding crews, tractor’s delay, the mechanical contractor is
adding shifts, and/or working longer hours much more likely to be denied its ineffi-
over and above 40 hours a week for the pri- ciency costs for the overtime schedule. It is
mary crew. This latter form of acceleration is essential for the mechanical contractor to
known as “overtime,” and the direct costs of establish a range of inefficiencies that may
this process (i.e., the overtime payroll pre- arise as a result of embarking on an overtime
mium costs) are reasonably easy to compute. work schedule such that payment for the
However, the indirect effects of working an direct costs as well as the inefficiency costs
overtime schedule can be more difficult to can be reimbursed. This chapter seeks to pro-
quantify. The primary indirect effect of vide the mechanical contractor with esti-
working an overtime schedule is the loss of mated inefficiency rates for various overtime
labor productivity by the workers perform- schedules seen most frequently on construc-
ing the overtime work. The added cost in tion projects. The percent inefficiency values
terms of the loss of labor productivity may, offered herein are reasonable estimates of the
as noted above, exceed the direct payroll inefficiency impacts that can be sustained by
costs of supporting an overtime work sched- mechanical crews working various overtime
ule. The subject of this chapter is the added schedules. The inefficiency percentages are to
inefficiency costs of working overtime. be applied to all hours worked by a crew per-
While the MCAA has not prepared an forming on an overtime schedule and not
empirical study within this chapter, the bet- just the overtime hours.3
ter-known overtime inefficiency studies The construction industry generally uses
have been revisited herein and compared, three terms to describe different overtime
thus allowing the contractor to consider sev- scenarios: shutdown or turnaround projects,
eral sources of data in one set of tables. spot overtime, and extended overtime. Shut-
Overtime inefficiency is the most generally down or turnaround projects are those in
accepted category of labor inefficiency within which a system or plant is completely shut
the construction industry. That is true down for the project duration, and due to
because virtually everyone who has worked the production value of the system or plant,
extended hours—executives, managers, tech-
nical and support personal, as well as the 3
The well-accepted axiom is that the inefficiency effects
field labor forces—have personally felt the
of overtime affect the worker while he or she works the
straight-time schedule as well as the overtime schedule.

186 Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Overtime

the construction schedule is highly com- times without a planned return to a normal
pressed (often working 24/7 with multiple 40-hour week. Experience indicates that a
shifts) in order to minimize the duration of return to a normal 40-hour schedule tends
the shutdown. These working conditions are to “reset” the productivity of a crew, such
clearly understood during the bid/proposal that if the crew returns to an overtime
process, and the contractor should include schedule after a week or two of a normal
the associated inefficiencies in the mechani- schedule, the productivity loss would
cal contractor’s bid or proposal.4 “reset” to that of the first week of overtime.
Thus, when utilizing any of the data pro-
Spot overtime is short in duration (from as
vided herein, it is important to know the
little as one day to a week) and is generally
work schedule of the crews working over-
not planned in advance—it is usually caused
time. If using a study that shows a progres-
by a delay or other unanticipated event that
sively increasing loss of productivity over
requires the mechanical contractor to make
time, should a crew cease overtime and
up quantities or finish work that was not
return to a straight time schedule, the
completed during the preceding week.5 Spot
crew’s inefficiency upon resuming overtime
overtime is also normally worked by only a
work must be reset to normal production
few crews at a time—those responsible for
for the first measured period. Mechanical
the specific work scope in question. The
contractors should ensure that their bid or
impact of working periodic and infrequent
negotiated proposals clearly state that the
spot overtime is normally considered negli-
base price for the work does not include
gible in terms of inefficiency effects. As a
any overtime, if in fact, no overtime was
result, spot overtime is not normally calcu-
estimated. If overtime was estimated and its
lated in industry studies that attempt to
scope exceeds infrequent and limited spot
quantify the lost labor productivity due to
overtime, an inefficiency factor should be
unplanned extended overtime.
included in the price for the work using a
Unplanned extended overtime is a condi- prospective estimate of inefficiency
tion wherein the entire project, or a signifi- described in this chapter.
cant portion of the project (e.g., all
As previously noted, this chapter does not
mechanical crews), work an overtime sched-
offer an empirical study based on new over-
ule for an extended period of time, some-
time loss of productivity data. Rather, this
chapter reviews, analyzes, and summarizes
4
four existing studies that have gained recog-
Similarly, on a non-overtime-based project estimate,
the mechanical contractor should qualify in its bidding
nition in the construction marketplace and
documents if the bid excludes overtime work. have been utilized to prove claims for over-
5
The delay or event causing the mechanical contractor
time inefficiency. These studies are:
to engage in spot overtime may not arise from the fault 1) The November 1980 Business Roundtable
or negligence of the mechanical contractor. For
instance, the mechanical crews may be required to work publication entitled Schedule Overtime
spot overtime installing sleeves in slab pours because Effects on Construction Projects (hereinafter
the concrete contractor was delayed and was required to referred to as “BRT”);
accelerate, thus requiring the sleeving crew to work
alongside on an overtime basis.

Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 187
Overtime

2) The 1989 study published by the National line data in any of these studies have never
Electrical Contractors Association (NECA) been proven to be inaccurate. Moreover, the
entitled Overtime and Productivity in Electri- concept that a contractor’s work force becomes
cal Construction (hereinafter referred to as less efficient as unplanned extended overtime
“NECA”); is worked is generally recognized and has
never been disproved as an underlying fact.
3) The 1997 study published by Dr. H. Ran-
dolph Thomas of Penn State University, et The four studies presented in this chapter as a
al, entitled Schedule Overtime and Labor Pro- basis for estimating a contractor’s loss of labor
ductivity: Quantitative Analysis, published productivity show striking similarities in their
in the June 1997 Journal of Engineering and results. These studies and the resulting curves
Construction Management, which was based are not offered as precise or exact forecasts of
on data included in a 1994 Report to the impacts. Rather, they are reasonable guidelines
Construction Industry Institute entitled to be used to estimate a loss of labor productiv-
Effects of Scheduled Overtime on Labor Pro- ity caused by overtime. The courts and boards
ductivity: A Quantitative Analysis (here- of contract appeals have clearly set forth the
inafter referred to as “Thomas”); and principle that a contractor does not have to
prove its loss of labor productivity with mathe-
4) The July 1979 United States Army Corps of
matical precision, but can offer a reasonable
Engineers publication Modification Impact
estimate of its damages.8 These studies offer
Analysis Guide, Publication No. EP 415-1-3
just that—a source from which to prepare a
(hereinafter referred to as “the Corps”).
reasonable estimate of inefficiency damages
These studies have been in use in the construc- arising from unplanned extended overtime.
tion industry for many years and have been
generally accepted as reliable measures of lost
productivity due to unplanned extended over- 7
See, e.g., Hensel Phelps Const. Co. v. General Services
time.6 Each has its strengths and weaknesses, Admin, 01 BCA ¶ 31249, GSBCA No. 14744, GSBCA No.
including criticisms ranging from the use of 14877, 2001 WL 43961 (General Services BCA
2001)(“the Modification Impact Evaluation Guide of the
limited data sources to the withdrawal of Corps of Engineers is not recognized by GSA and,
reports from publication.7 However, the base- indeed, no longer used by the Corps.”) While the Corps
has removed its Modification Impact Evaluation Guide EP
415-1-3 from publication, it has not repudiated any of
the data contained in that publication.
6 8
See, e.g., Ace Constructors v. United States, 70 Fed.Cl. See, e.g., B.Bramble, et al, Construction Delay Claims,
253, 281-283 (Cl.Ct. 2006), aff’d, 499 F.3d 1357 (Fed.Cir. §5.07, p. 5-53(3d ed. 2000) (“Where the damages are
2007)(contractor entitled to recover lost productivity directly attributable to the breach, they are often recov-
due to overtime based on BRT); Appeal of Harbison & erable even though they are uncertain in amount.
Mahony, 68-1 BCA ¶ 6880, ENGBCA Nos. 2819, 2820, ‘Thus, courts have recognized that a plaintiff may
1968 WL 436 (Eng. BCA 1968)(allowing claim for over- recover even where it is apparent that the quantum of
time inefficiency based on NECA); Appeal of States Roof- damage is unavoidably uncertain…or difficult to ascer-
ing Co, 10-1 BCA ¶ 34356, ASBCA No. 54860, 2010 WL tain.’ The courts have recognized that ascertainment of
292732 (ASBCA 2010)(Thomas study recognized); Appeal damages, especially lost productivity, is not an exact sci-
of Sante Fe Engineers, Inc., 86-3 BCA P 19092, ASBCA No. ence. When the responsibility for damages is proven, it
29362, ASBCA No. 28058, 1986 WL 20062 (ASBCA is not essential that the amount of damages be ‘ascer-
1986), aff’d, 818 F.2d 856 (Fed.Cir. 1986)(allowing ineffi- tainable with absolute exactness or mathematical preci-
ciency claim using the Corps study). sion.’” (and cases cited therein).

188 Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Overtime

In some cases a measured mile analysis can period. The underlying data for NECA was
be performed that will compute, by use of gathered by surveying electrical contractors
the contractor’s project payroll and field who were members of the association.9 The
records of installed material, a comprehen- survey data was compiled and presented as
sive loss of labor productivity comparing tables and graphs showing expected over-
actual impacted and non-impacted produc- time productivity losses as “Low,” “Average,”
tion on the jobsite. When a measured mile and “High” for each one-week period. These
analysis can be performed, such an analysis categories allow the user to factor the weekly
usually subsumes all types of inefficiency inefficiency by gradients defining more pre-
categories on a project. Therefore, if a meas- cise levels of impacts. For instance, if the
ured mile labor productivity study is uti- contractor had been given substantial notice
lized, there is no need for a separate ineffi- of the implementation of overtime to allow
ciency analysis for overtime loss of some pre-planning to lessen the effects of
productivity using industry studies. the overtime, the contractor could select a
“Low” or “Average” impact. Alternatively, if
the overtime schedule imposed upon the
Discussion of the Four Studies contractor created havoc on the project site,
or if there was stiff competition for overtime
Business Round Table (BRT) on nearby projects, the contractor could
The BRT is a study of a Proctor & Gamble select a “High” impact category. Like BRT,
construction project that experienced over- NECA demonstrates decreasing labor pro-
time during the course of the work. The BRT ductivity as the overtime schedule extends
has been frequently cited as a reasonable in duration.
guideline to predict loss of labor productiv-
ity. While the BRT is sometimes criticized
because it is based on only one project, its Dr. H. Randolph Thomas, P.E.
critics have not undermined its underlying (Thomas)10
data. A positive facet of this study is that its Thomas compared various overtime ineffi-
data were based upon payroll records of the ciency data with those independently derived
workers compared to actual units of material from studies prepared under his supervision.
installed on the project by those workers. Interestingly, Thomas opined that: “…it is con-
This study provided overtime loss of produc- cluded that the BRT curve is a reasonable esti-
tivity data over a 12-week period at various
overtime intensity levels and demonstrated
that, in general, inefficiency increases as the 9
It is a generally accepted axiom in the construction
overtime schedule extends in duration. industry that inefficiency impacts sustained by the
mechanical trades are similar in nature to the ineffi-
ciency impacts sustained by the electrical trades given
National Electrical Contractors reasonably comparative adverse conditions.
10
Association (NECA) Dr. H. Randolph Thomas, P.E. is a professor of civil
engineering at Penn State University, author or co-author
NECA provides the user with various over-
of a series of well recognized published papers on labor
time models measured over a 16-week inefficiency, and frequent expert witness on the subjects
of labor productivity and construction management.

Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 189
Overtime

mate of the minimum loss of productivity. For ing data used in the overtime inefficiency
projects experiencing worsening degrees of dis- graph. Thus, the Corps study and curve are
tress and disruption, the loss of productivity included herein to compare its findings with
will probably be greater.”11 Thomas tracked those of other overtime charts.
labor inefficiency caused by overtime in the
mechanical and electrical trades. In order to
Presentation of Data
attempt to accurately isolate the effects of over-
The following charts present the loss of pro-
time on labor productivity, Thomas removed
ductivity as determined by the four refer-
projects where overtime occurred at the outset
enced studies. The loss of productivity is
of the work, projects that suffered from adverse
presented in terms of a Productivity Index,
labor action, and projects on which there were
or PI, such that
an “inordinate” number of changes in scope or
other conditions that would exacerbate the
inefficiencies arising strictly from overtime. Planned Activity
PI =
Actual Activity
Thomas’ comparative curve utilized in the
aforementioned study was based on data col-
lected on the project site by site personnel. where Productivity is in terms of work hours
expended per unit of work installed. In this
case, a PI of 1.0 indicates that the actual
The U.S. Army Corps of Engineers productivity was equal to the planned pro-
(“the Corps”) ductivity; a PI > 1.0 indicates that the actual
The United States Army Corps of Engineers productivity exceeded (was better than) the
(“the Corps”) study included an overtime planned productivity; and a PI < 1.0 indi-
loss of productivity graph showing predicted cates that the actual productivity was less
losses of labor productivity for various work than (worse than) the planned productivity.
schedules over a four-week period. Similar to
the other reports cited herein, the Corps In all cases, the PI during a normal 40-hour
showed declining productivity as the over- work week is assumed to be 1.0. The PI dur-
time schedule was extended. The Corps’ ing a given overtime schedule is then indi-
overtime inefficiency graph was widely used cated on the chart over a number of weeks
to calculate impact and inefficiency claims of consecutive overtime. If a chart indicates
until the Corps formally withdrew this pub- a PI of 0.90 for a given week, that shows a
lication several years ago for unspecified rea- 10% loss of productivity for that week (1.00
sons. It is noteworthy that Publication EP – 0.90 = 0.10, and 0.10 ÷ 1.00 = 10%).
415-1-3, which contained the Corps’ over-
time study, has never been repudiated by
the Army Corps of Engineers, but was with-
drawn without any criticism of the underly-

11
Thomas, et al, “Scheduled Overtime and Labor Pro-
ductivity: Quantitative Analysis” Journal of Construction
Engineering and Management, June 1997.

190 Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 191
192 Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 193
Overtime

Application 100% = 40%). In a prospective, or forward-


priced analysis, the resulting percentage of pro-
As noted above, the curves were generally ductivity loss is multiplied against the esti-
within the same relative order of magnitude. mated number of hours to be worked during
Using the average of the four studies, the that week to identify the estimated impact of
table of PI at the bottom of this page was working extended overtime. In a retrospective
developed. analysis (i.e., an analysis prepared after the fact
using actual labor hours), the formula for com-
The Prospective Application puting a conservative inefficiency estimate is
When the period(s) of extended overtime have discussed in a following subsection.
been determined, the mechanical contractor As described herein, the NECA tables list
can find the chart for the applicable work three impact intensity levels for each over-
schedule and determine a reasonable range of time schedule: “Low,” “Average,” and “High.”
productivity loss by reading the PI for the For the PI values shown in the following
given week of consecutive extended overtime table, the “Average” values listed in the NECA
and subtracting it from the “normal” value of tables were utilized. Where two different
1.0. For instance, a PI of 0.60 equates to a inef- work weeks resulted in the same number of
ficiency estimate of 40% (1.00 – 0.60 = .40 x total hours (e.g., a 60-hour work week result-

Week of
50 hrs/wk 54-56 hrs/wk 60 hrs/wk 63 hrs/wk 70-72 hrs/wk 84 hrs/wk
Extended OT
1 0.95 0.94 0.91 0.89 0.86 0.75
2 0.93 0.90 0.88 0.84 0.80 0.70
3 0.92 0.86 0.85 0.78 0.73 0.65
4 0.91 0.83 0.81 0.73 0.68 0.60
5 0.85 0.79 0.76 0.67 0.63 0.55
6 0.86 0.75 0.72 0.62 0.58 0.50
7 0.76 0.72 0.67 0.58 0.54 0.47
8 0.77 0.70 0.64 0.55 0.51 0.44
9 0.74 0.68 0.62 0.54 0.50 0.43
10 0.72 0.66 0.61 0.52 0.49 0.42
11 0.72 0.65 0.60 0.51 0.48 0.41
12 0.71 0.64 0.59 0.50 0.47 0.40
13 0.69 0.63 0.56 0.49 0.46 0.39
14 0.68 0.62 0.55 0.48 0.45 0.38
15 0.67 0.61 0.54 0.47 0.44 0.37
16 0.66 0.60 0.53 0.46 0.43 0.36

194 Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Overtime

ing from a 12-hour per day five-day schedule crews on overtime during construction of a
versus a 10-hour per day six-day schedule), processing plant. The contractor’s planned
the PI values derived from the source data working hours were a 40-hour week, and in
were averaged between the two working an effort to maintain schedule the contractor
schedules. Further, from weeks 13 through placed the mechanical crews on a five-day
16, only the NECA PI values were available. 10-hour shift over an 11-week period. In cal-
culating the retrospective (performed after
When inefficiency factors are applied to esti-
the fact) loss due to unplanned extended
mated hours in a forward priced or prospec-
overtime, the contractor should apply the
tive analysis, the user multiplies the factor
formula and procedures described below.
percentage against the estimated hours for
the overtime and for the straight time Most inefficiency tables, such as the MCAA’s
worked by the overtime crews. For instance, labor inefficiency factors, were prepared with
if a contractor expects to work a 50-hour the anticipation that these factors would be
work week with 25 mechanics for five applied to forward-priced change order
weeks, the computation appears in the for- requests.12 Thus, the percent inefficiency fac-
ward pricing table below. tor would be utilized as a multiplier against
the estimated hours to provide the forecast
Based on a forward priced, or prospective,
loss of productivity. However, when using
estimate of overtime inefficiency, the con-
tables and factors in a retrospective manner
tractor would request compensation for 552
(i.e., applying these factor percentages to
labor hours of lost labor productivity.
actual payroll hours), an adjustment must be

The Retrospective Application


12
Retrospective analyses are performed after the As a conservative approach, it has been assumed that
overtime hours have been spent. For a retro- the NECA overtime tables, as well as other published
tables designed for use as forward-pricing guides, require
spective example, let us assume that a con- the use of the retrospective formula when applying such
tractor was directed to put its mechanical factors to actual labor hours.

FORWARD PRICING TABLE

Total Hours
# Mechanics Loss (pct)
Act Hrs Subject Inefficient
Week Ending working over from 5/10
Worked to Loss Hours
40 hrs Table
Productivity
6-Feb-10 50 25 1,250 5% 63
13-Feb-10 50 25 1,250 7% 88
20-Feb-10 50 25 1,250 8% 100
27-Feb-10 50 25 1,250 9% 113
6-Mar-10 50 25 1,250 15% 188
TOTAL 552

Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 195
Overtime

made in order to eliminate overstating the Note that when the crew moved back to the
inefficient hours. The use of the retrospective normal 40-hour week, the “OT week clock”
formula adjusts for the fact that the ineffi- started over at Week 1 on March 27, 2010,
cient hours are already embedded within the and no hours were subject to any lost effi-
actual labor hours used in the retrospective ciency in the preceding two weeks. This was
computation. Multiplying the inefficiency due to the fact that the crew was able to
factor against the actual hours that also recover during the normal work weeks end-
include the inefficient hours results in an ing March 13 and 20. Thus, when overtime
overstatement of the estimated inefficiency. work resumed for the week ending March
27, 2010, the “Week 1” percentages were uti-
1) Identify the individual craft persons who
lized.
worked unplanned extended overtime.
2) Apply the applicable percentage tables above
The contractor’s payroll records should
for the applicable overtime period (in this
identify those individual craft labor who
case 5/10s) to the craft hours subject to lost
worked at least 50 hours a week during the
productivity due to unplanned extended over-
period of unplanned overtime. It should
time using the retrospective formula.
not be assumed that every worker recorded
on the daily craft report actually worked In this retrospective example using actual
overtime during a given week. Note that the payroll data, the result is as shown in the
number of workers working over 40 hours table at the top of the following page.
declines with each successive week, indicat-
In this example, the contractor lost 748
ing that some members of the crew did not
craft hours due to working unplanned
work 50 hours. The result of such a calcula-
extended overtime caused by the attendant
tion is shown in the table below.

Total Hrs
Mechanics Work-
OT Week Week Ending Hrs Worked Subject to Lost
ing Over 40 hrs
Productivity
Week 1 6-Feb-10 50 25 1,250
Week 2 13-Feb-10 50 24 1,200
Week 3 20-Feb-10 50 22 1,100
Week 4 27-Feb-10 50 22 1,100
Week 5 6-Mar-10 50 21 1,050
No OT 13-Mar-10 40 0 0
No OT 20-Mar-10 40 0 0
Week 1 27-Mar-10 50 25 1,250
Week 2 3-Apr-10 50 23 1,150
Week 3 10-Apr-10 50 23 1,150
Week 4 17-Apr-10 50 20 1,000

196 Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Overtime

RETROSPECTIVE PRICING TABLE

# Mechanics Total Hours


Week Act Hrs Loss (pct) from Inefficient
working over Subject to Loss
Ending Worked 5/10 Table Hours
40 hrs of Productivity
6-Feb-10 50 25 1,250 5% 59
13-Feb-10 50 24 1,200 7% 78
20-Feb-10 50 22 1,100 8% 81
27-Feb-10 50 22 1,100 9% 91
6-Mar-10 50 21 1,050 15% 137
13-Mar-10 40 0 0 0% 0
20-Mar-10 40 0 0 0% 0
27-Mar-10 50 25 1,250 5% 59
3-Apr-10 50 23 1,150 7% 75
10-Apr-10 50 23 1,150 8% 85
17-Apr-10 50 20 1,000 9% 83
TOTAL 748

overtime inefficiency over an 11-week Preparation of the Request for


period using a retrospective analysis
Equitable Adjustment
approach. In order to produce a conserva-
It is not unusual for a general contractor or
tive inefficiency estimate, it is recom-
owner to request that a mechanical contractor
mended that when actual labor payroll
provide a prospective cost proposal to acceler-
hours are used, as would be the case in a
ate a construction project. However, such
retrospective analysis, the retrospective for-
requests are often limited to the added payroll
mula should be utilized, as described below.
costs attendant to the overtime schedule.
The retrospective formula appears as: actual When a mechanical contractor is asked to sub-
labor hours - (actual labor hours ÷ (1 + the mit a proposal to engage in overtime on a
percent inefficiency factor)), or as an exam- prospective basis, the attendant estimated
ple from the table above: 1,250 – (1,250 ÷ labor inefficiencies must be added to the direct
1.05) = the inefficient hours, or 1,250 - payroll costs of the overtime schedule.
1,191 [the efficient hours] = 59 inefficient
Thus, in cases where a mechanical contractor
hours in a retrospective analysis. This for-
is asked to forward price an overtime change
mula solves for the efficient hours [1,191] in
order request, both the direct payroll and the
the equation and then allows the user to
inefficiencies should be included. The con-
subtract the efficient hours from the total,
tent of this chapter provides the guidelines
yielding the inefficient hours [59].
for forward pricing an overtime-inefficiency

Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 197
Overtime

change order request. In cases where the productivity estimate based on the overtime
extent of the overtime is unknown, the schedule that we have received from your firm.
mechanical contractor, at a minimum, The proposed overtime schedule provided by
should include an express reservations clause your office is the basis of our estimate for direct
in the change order proposal. and inefficiency costs associated with this change
order request. Amalgamated Mechanical Con-
For example:
tractors expressly reserves the right to submit a
This change order proposal represents the direct separate change order proposal in the event the
additional payroll costs arising from the requested overtime schedule changes in any manner from
overtime schedule. No overtime inefficiencies are that upon which we have relied in the pricing of
included in this proposal. Amalgamated Mechani- this proposed change order.
cal Contractors expressly reserves its rights to
It is recommended that the forward-priced
request compensation for labor efficiencies atten-
(prospective) overtime change order request
dant to the requested overtime schedule. A revi-
be treated, to the fullest extent possible, in
sion to this change order proposal containing the
the same manner as a “sticks and bricks”
costs for overtime labor inefficiencies will be for-
change would be priced. In a “sticks and
warded for processing as soon as these costs can
bricks” change order request, the contractor
be computed. We estimate that the labor ineffi-
takes off pipe, fittings, and appurtenances
ciencies arising from this overtime schedule will
based on a scope of added work provided by
not be less than ____ %.13
the general contractor or owner. The labor is
There may be occasions when the general derived there from and the final pricing is
contractor or owner denies the opportunity to added to the change order proposal.
supplement a change order request based on
In like fashion to the fullest extent possible,
future events. Such prohibitions also may be a
overtime change order requests should be
part of the contract or printed on the change
based on a fixed scope. A fixed scope means
order forms themselves as “full accord and
that the general contractor or owner will pro-
satisfaction” clauses. If the mechanical con-
vide the mechanical contractor with the num-
tractor is prohibited from submitting supple-
ber of days of overtime and the number of
mental change order requests, such as for
hours per day that are to be worked in order to
labor inefficiencies arising from an overtime
form a basis for the forward-priced change
schedule, then forward pricing of the over-
order. Once the fixed scope is known, then the
time inefficiencies may be the only option.
mechanical contractor can estimate the added
For example: payroll costs and the expected loss of labor
The overtime pricing contained herein includes productivity using the tables included herein.
the added payroll costs for the overtime sched- The tables refer only to estimated overtime
ule provided by your office. Furthermore, this inefficiency and do not include inefficiencies
change order proposal contains a loss of labor arising from other categories of impacts, such
as unanticipated trade stacking, reassignment
of manpower (“disruption”), lack of site access,
or other inefficiency factors. Refer to the chap-
13
The estimated inefficiency percent can be derived
ter titled “How to Use the MCAA Labor Fac-
from the data and tables contained in this chapter.

198 Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Overtime

tors” for a more complete listing of potential additional impacts can be separately esti-
inefficiency factors to consider when preparing mated using the MCAA inefficiency factors
a change order request or a claim. described in this manual.14
In summary, it is essential that the mechani- Crew considerations also can affect overtime
cal contractor define, in its proposal, what inefficiency levels. Such considerations
costs are and are not included in its over- include whether or not to place the entire
time change order request. Obviously, if the crew on overtime even if only a definable
general contractor or owner direct an over- portion of the work requires acceleration
time acceleration effort without a require- (i.e., the critical path activities), whether or
ment for a prospective change order pro- not rest intervals can be interspersed into
posal, and with only the requirement to the overtime schedule to allow for one or
provide the proof of overtime payroll costs more weeks of straight time work, or
for reimbursement, the mechanical contrac- whether certain activities that would be sub-
tor must make it clear that in addition to ject to overtime acceleration can be sched-
the actual payroll costs, a request for reim- uled for a second-shift crew. These sorts of
bursement of its overtime inefficiency costs considerations are made on a project-specific
will be submitted for payment. basis and can affect the amount of ineffi-
ciency sustained by a mechanical contractor
resulting from performing the work on an
Conclusions overtime schedule.
A sustained and unplanned overtime sched-
ule can result in a substantial loss of labor Mechanical contractors should not accelerate
productivity. The mechanical contractor to mitigate schedule slippage that was not
may be entitled to recover the associated caused by the mechanical contractor’s fault or
costs, in addition to the direct overtime pre- negligence on a voluntary basis. If a mechani-
mium payroll costs. The current available cal contractor is directed by a general con-
data on inefficiency resulting from tractor or owner to accelerate the work by
unplanned extended overtime, when prop- commencing an extended overtime work
erly utilized, provide the mechanical con- schedule in order to overcome delays not
tractor with a reasonable basis to estimate caused by the mechanical contractor, a spe-
such losses in either the prospective or for- cific notice is necessary. While most construc-
ward pricing of an original estimate or a tion contracts contain provisions that require
scope change, or in a retrospective applica- the mechanical contractor to follow the
tion. The inefficiency factor will vary
depending on the amount of overtime to be
14
performed, the number of mechanics The “Overtime” component (Item No. 15) listed on
required, and the duration of the unplanned the MCAA inefficiency factors table in the chapter on
“Factors Affecting Labor Productivity” herein was
extended overtime. Additionally, other inef- designed to give general guidance in forward-pricing
ficiency factors may occur simultaneously, overtime inefficiency. It is recommended that the more
such as stacking of trades, reassignment of specific estimates of impacts contained in this chapter
be applied to overtime inefficiency analyses due simply
manpower, or site access restrictions. Such
to the increased level of specificity offered by the studies
and tables contained in this chapter.

Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 199
Overtime

direction of a general contractor or owner to costs to mitigate the delay. One primary
accelerate the work,15 such direction and the means of delay mitigation is overtime. If the
ensuing acceleration must be accompanied mechanical contractor is being charged with
by clear and timely notice that includes a the acceleration costs, or the payment for
statement that the mechanical contractor is the direct and indirect costs of acceleration
proceeding under protest and that a claim are being withheld on the basis that the
will be filed for reimbursement of all costs as mechanical contractor was the responsible
soon as those costs can be computed. If a party, the contractor can employ a schedule
mechanical contractor is placed in a position time impact analysis to identify the party
of constructively accelerating16 a project to causing the critical path delay.
overcome delay that has not been caused by
A schedule analysis also may be helpful in
the acts or omissions of the mechanical con-
demonstrating, to the extent that the
tractor, the review of these conditions by the
mechanical contractor’s activities are not
contractor’s upper management and counsel
controlling the critical path of the current
is highly advisable.
project schedule, that overtime demanded
A schedule time impact analysis may be an by a general contractor or owner will have
essential factor in demonstrating that the no mitigating effect on the forecast end date
mechanical contractor is not critically delay- of the project. It is an accepted axiom of
ing a project. This is important in properly construction Critical Path Method (CPM)
deflecting responsibility for the costs of scheduling that reducing the duration (i.e.,
acceleration in that the party controlling the by way of overtime acceleration) of a path of
critical path in a delayed schedule is usually logic that does not control the critical path
the party that is found responsible for the has no effect whatsoever on the end date of
the overall project. Put another way, the end
date of a CPM schedule can only be fore-
15
A subcontractor’s refusal to comply with an accelera- shortened by accelerating work on the con-
tion directive provided by a general contractor or owner,
in the presence of contractual authority to issue such a trolling critical path. If the mechanical con-
directive, may result in a termination for default. Before tractor can demonstrate that its work is not
a direct, contractually proper acceleration order from a on, or even near, the controlling critical
general contractor or owner is disregarded, the mechani-
path, accelerating those non-critical activi-
cal contractor should consult with construction counsel
to evaluate the various courses of action. ties will have no mitigating effects on a proj-
16 ect that is behind schedule and will repre-
Constructive acceleration is a condition wherein a con-
tractor is directed to accelerate to mitigate a delay not sent potentially substantial economic waste.
caused by the contractor at no additional cost. In antici-
pation of a claim to recover the costs of the constructive
The mechanical contractor should clearly
acceleration, the contractor takes express exception to note in its bid or change order proposal
the acceleration directive, provides notice of a claim, whether or not overtime has been included
and then executes the acceleration as directed. The sub- in its lump-sum pricing, and if so, to what
mission of the claim for added costs occurs as soon as
the contractor can compute the added costs either while extent it was included. If a contractor
the acceleration is taking place, or after the acceleration includes extended periods of overtime in a
has concluded. The steps that should be taken to perfect lump-sum bid or change proposal, the atten-
a constructive acceleration claim are best set forth by
dant loss of labor productivity should be
the contractor’s counsel.

200 Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Overtime

evaluated and if deemed appropriate, the tive Vice President of Kinetics Systems Inc.; James
costs should be included in the lump-sum Durant, President and CEO of Trautman & Shreve;
Richard Freeman, Vice President of Stromberg Metal
price for the work. At a minimum, the con- Works; Matthew Hahr, Senior Vice President of Kirlin
tractor’s right to claim for such cost impacts Mid-Atlantic, LLC; Michael Loulakis, Esq.,
should be preserved. President/CEO of Capital Project Strategies; Michael
Mack, Executive Vice President of John J. Kirlin, Inc.;
Preservation of the contractor’s right to be and Adam Snavely, President and CEO of The Poole &
reimbursed for its overtime inefficiency Kent Corporation.
costs, on projects where the other party
refuses to pay for such overtime inefficiency
costs, is of paramount importance. As
described in greater detail in the chapter on
“Time Impact Analysis—Measuring Project
Delay,” many general contractors and own-
ers are including broad waiver language on
change order forms and on the monthly
payment applications. The contractor
should take great care to limit this waiver
language to matters that it deems have been
settled and take express exception to each
unsettled item, such as a pending ineffi-
ciency claim.
Overtime inefficiency costs for extended
periods of unanticipated overtime may
exceed the payroll costs of overtime pre-
mium. The mechanical contractor should
employ every reasonable management tool
including issuing proper and timely notice,
keeping comprehensive records, performing
schedule analyses, taking exception to broad
waiver language, and timely submittal of
change order requests to help ensure that
the contractor’s right to recover all of its
overtime costs are preserved and that pay-
ment will be forthcoming.

Prepared by Paul L. Stynchcomb, CCM, PSP, CFCC of


Vero Construction Consultants Corp., Dr. Mike Pappas,
P.E., PhD of Pappas Consulting, Inc. and Jarad Kriz,
CCM, LEED® AP (BD+C), PSP of FTI Consulting with
peer review performed by: Robert Beck, President of
John W. Danforth Company; Michael R. Cables, Execu-

Management Methods Bulletin OT1 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 201
Overtime

Shift Work and its Effects on


Productivity
The following paragraphs list factors that 3. Since both shifts use the same tools and
may affect productivity when work is done equipment, they will not be at the same
on a shift work basis. Most apply to “extra” place and in the same condition as a
shifts, although you should note that para- man leaves them when he completes his
graph B and C also affect costs on a regular shift. Extra time will be spent reorganiz-
shift. All factors may not apply to a particu- ing tools and equipment.
lar job.
4. Night work will result in work force
fatigue to a greater extent than daytime
Factors Affecting Shift Work work.
Productivity 5. Supervision will be diluted, since the
1. Additional Needs—Night versus Day. normal supervisory employees of the
Since the extra shift will be performing at company must be spread out over several
night, natural lighting will not be avail- shifts. Supervisory problems also include
able and good quality artificial lighting transferring information between shifts
may have to be provided. Even if the as to work completed, ordering of mate-
work is done inside a building, additional rials, deliveries, field orders, etc.
lighting in yards, storage areas, etc. would 6. Additional welders may have to be quali-
be required. It would also be expected fied for second shift operations, resulting
that the temperature and weather condi- in increased manhours for testing,
tions at night would be more severe than together with the cost of qualification
during the daytime period and additional tests.
heating would, therefore, be needed.
7. The men required for ancillary services,
2. Since both shifts will be working on the such as laborers and operating engineers,
same installation, there will be a certain whose time is normally distributed over
inefficiency in the transition from one a broader base of total pipefitter man-
shift to the other. The new shift must go power, will add disproportionally to the
through a learning period to become smaller work forces normally used on
familiar with the work done by the additional shifts.
previous shift.

Management Methods Bulletin OT2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 203
Overtime

8. When only one trade is working shifts, lar basis for coordinating, planning and
they probably will not be “pushed” to establishing relationships among shifts.
complete certain work, as they may be
during the regular shift.
Labor Costs
9. If the shift works 7 1/2 hours in lieu of 8
1. Hiring for Shift Work. If it is necessary
hours, the percentage of work hours
to hire additional personnel to man the
spent in starting, stopping, and coffee
shift, be aware that the productivity of
breaks becomes a greater proportion of
“new hires” may not be the same as for
the work shift.
the established crew. This may also
10. The social aspects of the tradesmen may depend on the employment levels and
have to be considered, such as the disrup- labor availability within your local juris-
tions on family life by working nighttime diction.
hours, and the effects on a man of having
to change his schedule, such as sleeping 2. Shift Premium Differential. Shift pre-
during regular daytime hours. mium differential should be a part of the
labor contract.
The following is an index of additional fac-
tors which should be considered as direct 3. Absenteeism. Absenteeism can run as
costs when pricing bids for shift work high as 30 percent during summer vaca-
operations. tion months, particularly on Fridays and
Sundays, and when holidays occur dur-
Additional Factors ing shift schedules.

4. Bodily Adjustment Period. An adjust-


Coordination Costs ment period can be from 30 to 60 days,
1. Overtime Supervisory Personnel. It may
with a productivity loss of 15 percent to
be necessary to overlap supervisory per-
25 percent during this time.
sonnel by 1–2 hours per shift.
2. Engineering Costs. Additional engineer- 5. Accident Rate. An accident rate increase
ing costs may be required for all shifts, at of up to 15 percent may be experienced,
least in the initial stages of the project. which would mean additional workers’
compensation costs.
3. Project Support and Communication.
A jobsite business office containing busi- 6. Efficiency Loss. From 10:00 p.m. to
ness machines, such as faxes, computers, midnight, there is up to a 25 percent loss
etc., may be necessary due to the need of efficiency.
for intense coordination, communica-
tion and information disbursement 7. Alcohol. Often there is an increased con-
among shifts. The lack of available per- sumption of alcohol before coming to
sonnel in the home office after regular work by shift workers.
shift hours may require supervisory per-
sonnel from all shifts to meet on a regu-

204 Management Methods Bulletin OT2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Overtime

8. Attitudes. Lack of productivity and qual- require additional resources to accommodate


ity workmanship can transfer from one the shift project and other projects in
shift to the next. progress could suffer drastically—a real hid-
den cost. Some of the added resources that
should be considered for sporadic shift
Job Costs
work:
1. Safety. Safety requires more emphasis
due to potential increase in the accident 1. Additional engineers for the other shifts
rate. and overlap with daytime engineers.

2. Heat. Heat in colder climates may be 2. Additional project managers for other
required to a greater extent on second shifts for continuity and resolution of
and third shifts. problems which surface on late shifts.

3. Lighting. Particularly when work is 3. Additional supervisory personnel, fore-


being performed outdoors, i.e., installa- men, etc.
tion of rooftop units, additional lighting
may be required.
Conclusions
4. Rental of Equipment. All shifts must After the contractor considers these items,
have adequate tools and equipment he should then determine the effects on
available. overall productivity and the cost of shift
work based upon overall productivity. He
5. Delivery Charges. If they are required, may also want to consider that during the
delivery costs can be costly outside of short-term, such as one through four weeks,
regular hours. the productivity of shift work will be differ-
ent than during the long-term, such as three
6. Material Availability. A crucial months or more.
scheduling consideration, depending on
In situations of a controlled environment,
schedules and productivity, may be the
such as a fabrication shop, there may be
requirement for accompanying shifts in
some advantages (or perhaps less disadvan-
the fabrication shop.
tages) to shift work other than for those out-
7. Tool Availability. Time required in lined above. These factors include using a
searching for and/or replacing tools can plant twice, thus cutting the fixed overhead
be staggering. Most companies provide a cost; fewer interruptions on the work force;
set of tools for each work shift. and less supervisory problems. The latter is
true since fabrication work tends to be pro-
duction-type work and information is nor-
Additional Resources mally passed directly to the tradesman by
When shift work is not the norm of the fabrication drawings or fabrication tickets.
company, all of the items described above
In some regions of the country, such as sum-
may apply. However, the company may also
mertime in the Southwest, weather and tem-

Management Methods Bulletin OT2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved. 205
Overtime

perature conditions may be such that it


would be an advantage to work shifts. If so,
this should be considered by the contractor.
If the contractor is in the position of being
able to make a decision as to whether to use
shift work or overtime, he should determine
a total productivity factor for shift work and
compare this with the productivity factor for
overtime work, as described in other Man-
agement Methods Bulletins. (See “Factors
Affecting Labor Productivity” on page 99
and “How to Estimate the Impacts of Over-
time on Labor Productivity” on page 185.)
This information should be used in making
the final decision.

206 Management Methods Bulletin OT2 - 2011; replaces 2005 version. © 2016 MCAA. All rights reserved.
Notes

207
Notes

208
Publication #M3

Mechanical Contractors Association of America, Inc.


1385 Piccard Drive, Rockville, MD 20850-4340
301-869-5800 ■ fax 301-990-9690 ■ www.mcaa.org

You might also like