Building 84, 4.3a, 4.3b, 3 (PROPOSAL COSTING)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 26

BILL OF QUANTITIES

BUILDING 84

Project Name : CONSTRUCTION OF VARIOUS STRUCTURES AND FACILITIES WITHIN THE 100 HECTARE AREA AT BATAAN
TECHNOLOGY PARK, MORONG BATAAN ( PHASE 1 PACKAGE 2 )
Location : MORONG, BATAAN

TOTAL UNIT BUILDING 84


ITEM NO. DESCRIPTION UNIT COST
(Pesos) QUANTITY AMOUNT

STRUCTURAL EARTHWORK
803 (1) a Structure Excavation (Common Soil), includes Hauling and Disposal Cost cu.m. 420.00 1,695.53 712,122.60
803 (3) b Foundation Fill, Base Course cu.m. 1,102.50 342.00 377,055.00
515 (3) Structural Backfilling (using Excavated Materials) cu.m. 367.50 1,215.70 446,769.75
1000 (1) Soil Poisoning liters 105.00 203.38 21,354.90
SUB-TOTAL 1,557,302.25
Cast-In Place Concrete, 21 Mpa
900 (1) c1-a Structural Concrete, Column Footings, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 117.33 609,822.68
900 (1) c1-b Structural Concrete, Wall Footings, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 29.86 155,197.35
900 (1) c1-c Structural Concrete, Elevator Pit Footings, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 6.60 34,303.50
900 (1) c1-g Structural Concrete, Slab On Grade, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 168.65 876,558.38
900 (1) c1-i Structural Concrete, Ramp On Grade, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 1.47 7,640.33
900 (1) c1-j Structural Concrete, Concrete/Entry Steps, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 4.13 21,465.68
900 (1) c1-l Structural Concrete, Concrete Pad/Plinth on Grade, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 21.85 113,565.38
Cast-In Place Concrete, 28 Mpa
900 (8)-h Structural Concrete, RC Wall, 28 MPa @ 28 days cu.m. 5,932.50 4.84 28,713.30
900 (8)-n Structural Concrete, Footing-Tie-Beams, 28 MPa @ 28 days cu.m. 5,932.50 120.48 714,747.60
900 (8)-o Structural Concrete, Roof Beams/Suspended Beams/Girders, 28 MPa @ 28 days cu.m. 5,932.50 273.49 1,622,479.43
900 (8)-q Structural Concrete, Lintel Beam, 28 MPa @ 28 days cu.m. 5,932.50 10.10 59,918.25
900 (8)-r Structural Concrete, Bond Beam, 28 MPa @ 28 days cu.m. 5,932.50 4.66 27,645.45
900 (8)-s Structural Concrete, Columns/Planted Columns, 28 MPa @ 28 days cu.m. 5,932.50 120.06 712,255.95
900 (8)-t Structural Concrete, Stiffener Columns, 28 MPa @ 28 days cu.m. 5,932.50 97.42 577,944.15
900 (8)-u Structural Concrete, Suspended Slab/Roof Slab, 28 MPa @ 28 days cu.m. 5,932.50 187.94 1,114,954.05
900 (8)-y Structural Concrete, Concrete Ledge, 28 MPa @ 28 days cu.m. 5,932.50 10.62 63,003.15
900 (8)-z Structural Concrete, Suspended Stairs and Landing, 28 MPa @ 28 days cu.m. 5,932.50 5.05 29,959.13
Reinforcing Steel, Grade 40
902 (1) a-1 Reinforcing Steel, Column Footings, Grade 40 kgs. 74.03 2,923.48 216,410.61
902 (1) a-4 Reinforcing Steel, Concrete/Entry Steps, Grade 40 kgs. 74.03 50.07 3,706.43
902 (1) a-7 Reinforcing Steel, Suspended Beam/Roof Beam/Girders, Grade 40 kgs. 74.03 44.23 3,274.13
902 (1) a-9 Reinforcing Steel, Lintel Beam, Grade 40 kgs. 74.03 564.77 41,807.10
902 (1) a-14 Reinforcing Steel, Suspended Slab/Roof Slab, Grade 40 kgs. 74.03 8,003.24 592,439.84
902 (1) a-17 Reinforcing Steel, RC Wall, Grade 40 kgs. 74.03 156.92 11,616.00
902 (1) a-24 Reinforcing Steel, Concrete Ledge, Grade 40 kgs. 74.03 458.54 33,943.42
902 (1) a-25 Reinforcing Steel, Suspended Stairs and Landing, Grade 40 kgs. 74.03 595.11 44,053.02
Reinforcing Steel, Grade 60
902 (1) b-1 Reinforcing Steel, Column Footings, Grade 60 kgs. 77.18 10,603.84 818,351.35
902 (1) b-3 Reinforcing Steel, Wall Footings, Grade 60 kgs. 77.18 2,976.33 229,698.27
902 (1) b-4 Reinforcing Steel, Slab On Grade, Grade 60 kgs. 77.18 20,895.02 1,612,573.17
902 (1) b-5 Reinforcing Steel, Concrete/Entry Steps, Grade 60 kgs. 77.18 185.21 14,293.58
902 (1) b-6 Reinforcing Steel, Concrete Pad/Plinth on Grade, Grade 60 kgs. 77.18 1,702.07 131,357.25
902 (1) b-8 Reinforcing Steel, Footing Tie Beam, Grade 60 kgs. 77.18 16,141.99 1,245,758.08
902 (1) b-10 Reinforcing Steel, Suspended Beam/Roof Beam/Girders, Grade 60 kgs. 77.18 62,645.73 4,834,684.21
902 (1) b-12 Reinforcing Steel, Lintel Beam, Grade 60 kgs. 77.18 1,859.02 143,469.87
902 (1) b-13 Reinforcing Steel, Bond Beam, Grade 60 kgs. 77.18 622.72 48,058.42
902 (1) b-14 Reinforcing Steel, Columns, Grade 60 kgs. 77.18 63,629.89 4,910,636.76
902 (1) b-16 Reinforcing Steel, Stiffener Column, Grade 60 kgs. 77.18 13,522.60 1,043,606.66
902 (1) b-17 Reinforcing Steel, Suspended Slab/Roof Slab, Grade 60 kgs. 77.18 17,097.65 1,319,511.14
902 (1) b-21 Reinforcing Steel, Elevator Pit Footing, Grade 60 kgs. 77.18 715.86 55,246.50
902 (1) b-26 Reinforcing Steel, Ramp On Grade, Grade 60 kgs. 77.18 153.22 11,824.75
902 (1) b-30 Reinforcing Steel, Concrete Ledge, Grade 60 kgs. 77.18 561.57 43,339.16
902 (1) b-31 Reinforcing Steel, Suspended Stairs and Landing, Grade 60 kgs. 77.18 1,023.27 78,970.86
902 (1) b-35 Reinforcing Steel, RC Wall, Grade 60 kgs. 77.18 380.15 29,338.08
Formworks and Falsework
903 (2)-b Formworks and Falseworks, Column Footings sq.m. 682.50 202.90 138,479.25
903 (2)-d Formworks and Falseworks, Wall Footings sq.m. 682.50 28.20 19,246.50
903 (2)-e Formworks and Falseworks, Slab On Grade sq.m. 682.50 30.80 21,021.00
903 (2)-f Formworks and Falseworks, Concrete/Entry Steps sq.m. 682.50 5.29 3,610.43
903 (2)-g Formworks and Falseworks, Concrete Pad/Plinth on Grade sq.m. 682.50 11.26 7,684.95
903 (2)-i Formworks and Falseworks, Footing Tie Beam sq.m. 682.50 602.37 411,117.53
903 (2)-k Formworks and Falseworks, Suspended Beam/Roof Beam/Girders sq.m. 682.50 2,089.29 1,425,940.43
903 (2)-m Formworks and Falseworks, Lintel Beam sq.m. 682.50 167.08 114,032.10
903 (2)-n Formworks and Falseworks, Bond Beam sq.m. 682.50 61.69 42,103.42
903 (2)-o Formworks and Falseworks, Columns sq.m. 682.50 1,025.32 699,780.90
903 (2)-q Formworks and Falseworks, Stiffener Columns sq.m. 682.50 1,211.61 826,923.83
903 (2)-r Formworks and Falseworks, Suspended Slab/Roof Slab sq.m. 682.50 1,252.93 855,124.73
903 (2)-u Formworks and Falseworks, RC Wall sq.m. 682.50 34.24 23,368.80
903 (2)-z Formworks and Falseworks, Suspended Beam/Roof Beam/Girders sq.m. 682.50 8.04 5,487.30
903 (2)-ae Formworks and Falseworks, Ramp on Grade sq.m. 682.50 2.30 1,569.75
903 (2)-ai Formworks and Falseworks, Suspended Beam/Roof Beam/Girders sq.m. 682.50 64.24 43,843.80
903 (2)-aj Formworks and Falseworks, Suspended Stairs and Landing sq.m. 682.50 56.17 38,336.03
Preformed Sponge Rubber Joint Expansion
413 (3) a Preformed Expansion Joint Filler with Sealant, 12 mm thick cu.m. 2,152.50 0.55 1,183.88
413 (4) a Elastic Sealant on Ø12 mm Backing Rod l.m. 288.75 1,636.40 472,510.50
SUB-TOTAL 29,439,507.48
METAL WORKS
1047 (2) a Structural Steel, Purlins (LC Sections) kgs. 82.95 15,315.92 1,270,455.56
1047 (2) d-1 Structural Steel, Truss/Strut (Angle Bar Sections) kgs. 82.95 52,827.87 4,382,071.82
1047 (2) d-2 Structural Steel, Top Wall Support (Angle Bar Sections) kgs. 82.95 1,648.80 136,767.96
1047 (2) d-8 Structural Steel, Fascia Support/Frame (Angle Bar Sections) kgs. 82.95 2,303.85 191,104.36
Metal Structure Accessories, Connection Bolts, ∅12mm x 40 mm Connection Bolts w/ Std
1047 (3) a-1 ea. 183.75 2,260.00 415,275.00
Nuts & Washer, ASTM A325
1047 (3) a-8 Metal Structure and Acessories, Stud Anchor, ∅12mm w/ Std Nuts & Washer ea. 236.25 800.00 189,000.00
Metal Structure Accessories, Anchor Bolts, Ø16mm x 300mm w/ Std Nuts & Washer, ASTM
1047 (3) a-16 ea. 525.00 176.00 92,400.00
F1554 (depth of embedment = 200mm)
1047 (3) c.1 Metal Structure Accessories, Ø16mm Turnbuckles ea. 1,417.50 4.00 5,670.00
1047 (4) a Metal Structure Accessories, Ø16mm Cross Bracing kgs. 82.95 40.35 3,347.03
1047 (6) a Metal Structure Accessories, Base Plates (includes non-shrink grout) kgs. 82.95 414.48 34,381.12
1047 (6) c Metal Structure Accessories, Stiffener Plates kgs. 82.95 997.94 82,779.12
1047 (6) d Metal Structure Accessories, Bent Plates kgs. 82.95 532.23 44,148.48
1047 (6) e Metal Structure Accessories, Gusset Plates kgs. 82.95 7,357.89 610,336.98
1047 (7) b Metal Structure Accessories, Ø12mm Sagrods kgs. 82.95 655.16 54,345.52
Metal Structures and Accessories, Watch Tower for 3-units (includes HSS 5x5x0.375 Steel
Column, C4x4.5 Steel beam, C3x3 Steel Beam and Steel Rafter, LC100x50x15x2.0 Purlins,
1047 (12) lot 0.05 n/a
150x12 Hollow Steel Pipe for Kingpost, connection bolts, connection Plates and other items
to complete the works)

Metal Structures and Accessories, Catwalk, L=183.65m, W=1.30m ( includes A505MPU


1047 (13) Webforge Steel Grating, W8x12 Steel Beam, 2L100x100x8 Steel Support, Baseplates, Anchor lot 0.05 n/a
Bolts and other items to complete the works)
Metal Structures and Accessories, Steel Stairs ( includes A323MPU 32x3 Webforge Steel
1047 (14) Grating, HT152x151x8x11 Steel Column, C10x20 Stringer, Angle Bar Connections, lot 0.05 n/a
Baseplates, Anchor Bolts and other items to complete the works)
SUB-TOTAL 7,512,082.95
SUBTOTAL COST - STRUCTURAL WORKS 38,508,892.67

1002 PLUMBING WORKS -


Facial Mirror (6mm Thk with 25mm Thk Plywood Backing and 25x25mm Tubular Aluminum
1002 (20) a sq.m. 2,205.00 22.12 48,774.60
Trim)
1002 (38) Liquid Soap Dispenser set 367.50 8.00 2,940.00
1002 (40) Grab Bar set 3,150.00 4.00 12,600.00
1002 (41) Automatic Hand Dryer set 2,572.50 8.00 20,580.00
1002 (43) Urinal Partition, 20mm Thk x 400mm W X 1150mm H set 3,307.50 4.00 13,230.00
1002 (44) Robe Hook set 787.50 22.00 17,325.00
1003 CARPENTRY AND JOINERY -
1003 (1) a.3b Ceiling Finish: 6mm Thk Perforated Fiber Cement Board (Soffit of Eaves) sq.m. 1,921.50 276.90 532,063.35
1003 (1) e1.1 Ceiling,Gypsum Board on Metal Suspension System ;12mm Thk Ordinary Type sq.m. 1,123.50 2,106.57 2,366,731.40
1003 (1) e1.2 Ceiling, Gypsum Board on Metal Suspension System ;12mm Thk Moisture Resistant sq.m. 1,526.70 206.72 315,599.42
1003 (1) e1.6 12mm Shadow Gap l.m. 236.25 2,122.86 501,525.68
1003 (11) a.3.1 Fascia Board, using 15mm Thk Fiber Cement Boad, Painted Finish sq.m. 950.00 256.57 243,741.50
1003 (4) ON-FLOOR AND OVERHEAD CABINETS -
1003 (4) a.17 On- Floor Cabinets @ Pantry (Location: Bldg 84) ea. 23,034.38 1.00 23,034.38
1003 (4) b.17 Overhead Cabinets @ Pantry (Location: Bldg 84) ea. 23,034.38 1.00 23,034.38
1003 (4) a.18 On- Floor Cabinets @ Reception Counter (Location: Bldg 84) ea. 44,226.00 1.00 44,226.00
1003 (23) MODULAR PARTITION -
Toilet Partitions, 15mm Thk Solid Grade HPL with Hardware, fittings, fastening and
1003 (23) a.21 l.s. 382,725.00 1.00 382,725.00
anchoring system. (18 cubicles ; Location: Building 84)
1004 FINISHING HARDWARE -
1004 (2) b Lockset Series 3400 Function 53 (Entry), Grade 1 set 1,837.50 38.00 69,825.00
1004 (2) c Lockset Series 3400 Function 80 (Storeroom), Grade 1 set 1,312.50 20.00 26,250.00
1004 (2) q Lockset Series 4000, Lever Type, Function 76 (Privacy Lock), Grade 1 set 2,887.50 4.00 11,550.00
1004 (2) f Overhead Surface Door Closer, Grade 1 set 1,312.50 38.00 49,875.00
1004 (2) g Overhead Concealed Door Closer, Grade 1 set 1,312.50 2.00 2,625.00
1004 (2) h Panic Type Threshold set 2,887.50 11.00 31,762.50
1004 (2) k Butt Hinges 100mm x 100 x 3mm (4" x 4") set/pair 1,260.00 46.00 57,960.00
1004 (2) l Butt Hinges 100mm x 114 x 3mm (4" x 4 1/2") set/pair 1,260.00 96.00 120,960.00
1004 (2) n Fire Exit Rim Device (w/ Entry Trim) set 892.50 12.00 10,710.00
1004 (2) v Door Coordinator set 787.50 1.00 787.50
1006 STEEL DOORS AND FRAMES -
Fire Rated Fire Exit Steel Door (45mm Thk, 1 Hr. Fire Rating, including Door Jamb, Single
1006 (5) a.12 sq.m. 33,442.50 8.60 287,605.50
Leaf; Type F= 900mm W x 2100mm H )
Fire Rated Fire Exit Steel Door (45mm Thk, 1 Hr. Fire Rating, including Door Jamb, Single
1006 (5) a.18 sq.m. 26,355.00 21.50 566,632.50
Leaf; Type G= 900mm W x 1600mm H )
Fire Rated Fire Exit Steel Door (45mm Thk, Steel Louver Door with 1 Hr. Fire Rating,
1006 (5) a.23 sq.m. 33,442.50 8.60 287,605.50
including Door Jamb, Single Leaf; Type K= 900mm W x 2100mm H )
Fire Rated Fire Exit Steel Door (45mm Thk, 1 Hr. Fire Rating, including Door Jamb, Double
1006 (5) a.24 sq.m. 73,500.00 4.52 332,220.00
Leaf; Type J= 2000mm W x 2100mm H )
1007 ALUMINUM FRAMED GLASS DOOR -
Swing Type (12mm Thk Clear Tempered Glass, Aluminum Frame Powder Coated Finish,
1007 (1) b.6 sq.m. 7,827.30 18.06 141,361.04
Double Leaf, Type B= 2000mm W x 2100mm H
Swing Type (12mm Thk Clear Tempered Glass with 10mm Thk Tempered Glass Sidelight,
1007 (1) b.13 sq.m. 5,846.83 66.22 387,176.79
Aluminum Frame Powder Coated Finish, Single Leaf, Type C= 2800mm W x 2150mm H

Swing Type (12mm Thk Clear Tempered Glass with 6mm Thk Tempered Glass Fixed
1007 (1) b.27 Sidelights and Transom, Aluminum Frame Powder Coated Finish, Double Leaf, Type A= 2- sq.m. 4,742.40 12.60 59,754.24
4200mm W x 1500mm H

Swing Type (12mm Thk Clear Tempered Glass with 10mm Thk Tempered Glass Sidelight,
1007 (1) b.42 sqm. 7,013.26 84.11 589,885.34
Aluminum Frame Powder Coated Finish, Single Leaf, Type L= 3260mm W x 2150mm H

1008 ALUMINUM GLASS WINDOW -


1008 (1) b.1.14 Casement Type (6mm Thk Tempered Glass, 1 Panel, Type C= 1200mm W x 1200mm H) sq.m. 8,121.75 5.76 46,781.28

1008 (1) b.1.15 Casement Type (6mm Thk Tempered Glass, 3-Equal Panel, Type B= 3000mm W x 1200mm H) sq.m. 6,756.75 129.60 875,674.80

1008 (1) c.1.23 Awning Type (6mm Thk Clear Float Glass, 3 Equal Panels; Type D= 1500mm W x 600mm H) sq.m. 10,510.50 7.20 75,675.60

1008 (1) c.1.24 Awning Type (6mm Thk Clear Float Glass, 4 Equal Panels; Type E= 2000mm W x 600mm H) sq.m. 10,510.50 4.80 50,450.40

1008 (1) c.1.25 Awning Type (6mm Thk Clear Float Glass, 5 Equal Panels; Type F= 2500mm W x 600mm H) sq.m. 10,510.50 15.00 157,657.50

Fixed Type (6mm Thk Clear Float Glass; Combined Fixed and Awning Window with Transom,
1008 (1) d.1.80 sq.m. 4,766.12 21.60 102,948.30
8 Equal Panels, Type A= 9000mm W x 2400mm H)
1010 WOODEN DOORS AND WIINDOWS -
1010 (1) b Wooden Door Jamb (45mm x 800mm W x 2150mm H) set 2,610.56 12.00 31,326.75
1010 (1) c Wooden Door Jamb (45mm x 900mm W x 2150mm H) set 2,661.75 21.00 55,896.75
1010 (1) d Wooden Door Jamb (45mm x 1000mm W x 2150mm H) set 2,712.94 17.00 46,119.94
1010 (1) e Wooden Door Jamb (45mm x 1100mm W x 2150mm H) set 2,764.13 4.00 11,056.50
Wooden Doors, Wood Panel (45mm Thk Hollow Core, Single Leaf Type M= 1000mm W x
1010 (2) b.1.11 sqm. 14,332.50 7.00 100,327.50
2100mm H)
Wooden Doors, Wood Panel (45mm Thk Solid Wood Panel with Full Glass, Single Leaf Type
1010 (2) b.2.2 sq.m. 12,899.25 32.13 414,452.90
D= 900mm W x 2100mm H)
Wooden Doors, Wood Panel (45mm Thk Solid Core with Bottom Louver, 1 Hr. Fire Rated
1010 (2) b.2.10 sq.m. 11,466.00 35.28 404,520.48
Single Leaf, Type E= 800mm W x 2100mm H)
Wooden Doors, Wood Panel (45mm Thk Solid Core with Bottom Louver, 20 Mins Fire Rated
1010 (2) b.2.11 sq.m. 10,032.75 17.64 176,977.71
Single Leaf, Type F= 700mm W x 2100mm H)
Preformed Prepainted Metal Roofing, Galvalume Ga. 24, including Rain Drip Mould Stopper,
1014 (1) c.5 Ga.24, bended materials, flashings, ridge roll and other attachment accessories necessary to sqm. 1,706.25 1,938.87 3,308,196.94
complete work. (DN Hi Rib 1030)
1016 WATERPROOFING -
1016 (1) b.3 Waterproofing: Elastomeric Membrane Waterproofing (40 mils on Suspended Toilets) sq.m. 735.00 135.23 99,394.05

Waterproofing: Cementitous Capillary (Location: Concrete Canopies, Watertank, Elevaror


1016 (1) b.6 sq.m. 892.50 34.04 30,380.70
Shaft)
1016 (3) Concrete Sealer sq.m. 472.50 63.60 30,051.00
1018 CERAMIC/ GRANITE TILES -
1018 (2) a Unglazed Tiles (Floor Finish: Ceramic Tiles, 6mm Thk x 300 x 300mm) sq.m. 1,732.50 206.72 358,142.40
20mm Thk Natural Granite Countertop Slab with 200mm H Backsplash & 200mm Skirting
1018 (3) e l.m. 4,515.00 23.72 107,095.80
(Location: Toilets, if applicable)
20mm Thk Natural Granite Countertop Slab with 200mm H Backsplash & 60mm Skirting
1018 (3) h l.m. 4,515.00 11.20 50,568.00
(Location: Pantry/ Kitchen)
1018 (8) a Floor Finish: Homogeneous Tiles, 10mm Thk x 600 x 600mm sq.m. 1,995.00 2,560.43 5,108,057.85
1018 (8) c Floor Finish: HomogeneousTiles, 10mm Thk x 400 x 400mm sq.m. 2,205.00 194.57 429,026.85
1018 (8) h Wall Finish: Homogeneous Tiles, 10mm Thk x 300 x 300mm sq.m. 2,415.00 328.00 792,120.00
1018 (9) Base Finish: 100mm H Homogeneous Tile Base l.m. 420.00 1,119.79 470,311.80
1021 CEMENT FLOOR FINISH -
1021 (1) a Cement Floor Finish, Plain sq.m. 451.50 252.02 113,787.03
1027 CEMENT PLASTER FINISH/ DECORATIVE STONE -
1027 (1) a Cement Plaster Finish (on Concrete Masonry Units) sq.m. 661.50 7,801.51 5,160,698.87
1027 (1) a.1 Cement Plaster Finish (on Concrete Structural Members) sq.m. 661.50 1,032.14 682,760.61
1027 (1) c.1 Cement Plaster Finish: Exposed Construction, Soffit of Slab (Smooth Cement Finish) sq.m. 661.50 162.29 107,354.83
1030 ACOUSTIC CEILING - -
1030 (1) a.1 19mm Thk x 600 x 600mm Ceiling Panel sq.m. 997.50 791.64 789,660.90
1032 PAINTING, VARNISHING AND OTHER RELATED WORKS - -
1032 (1) a.2 Painting on Concrete, Exterior sq.m. 577.50 951.16 549,294.90
1032 (1) a.3 Painting on Concrete, Interior sq.m. 420.00 6,387.90 2,682,918.00
1032 (1) a.4.1 Painting on Masonry/ Concrete :100mm High Painted Strip l.m. 136.50 291.88 39,841.62
1032 (1) a.6 Painting on Concrete: Epoxy Floor Coating sq.m. 682.50 252.02 172,003.65
1032 (1) a.8 Painting on Masonry/ Concrete :Exposed Construction, Soffit of Slab sq.m. 420.00 162.29 68,161.80
1032 (1) b.1 Painting Works: Wood Works (Alkyd Type) sq.m. 787.50 251.93 198,394.88
1032 (1) c.1 Painting on Steel: Exposed Structural Metals sq.m. 787.50 886.21 697,890.38
1032 (1) c.2 Painting on Steel: Steel Doors and Louvers sq.m. 787.50 111.41 87,735.38
1032 (6) Painting Works: Painting on Gypsum Board Ceiling, Flat Finish sq.m. 420.00 2,313.29 971,581.80
1032 (8) Painting Works: Painting on Fiber Cement Board Ceiling sq.m. 420.00 533.47 224,057.40
1038 REFLECTIVE INSULATION -
Blanket Insulation, R= 19 with Wiremesh Reinforcement; With Foil on One Side (Rockwool
1038 (2) sq.m. 1,312.50 1,938.87 2,544,766.88
Insulation) (Location: Roofing)
1046 MASONRY WORKS -
1046 (2) a.1 CHB Non Load Bearing (including Reinforcing Steel), 100mm thk sq.m. 1,365.00 586.27 800,258.55
1046 (2) a.2 CHB Non Load Bearing (including Reinforcing Steel), 150mm thk. sq.m. 1,365.00 3,314.29 4,524,005.85
1047 METAL STRUCTURE -
Metal Structures, Ladder Rung: includes 16mm Ø Steel Rung; 30 x 10mm Thk Side Rail, and
1047 (11) k set 3,832.50 5.00 19,162.50
other accessories to complete item; Height= 4700mm. (Location: ACCU Deck, Bldg 84)

1047 (11) n Metal Structures, Brass Nosing l.m. 131.25 50.40 6,615.00
1047 (11) o Metal Structures, Aluminum Nosing with Carborundrum Strip l.m. 210.00 25.20 5,292.00
1051 RAILING -
Floor Mounted G.I. Pipe Railings, 38mm Ø Top Rail with 2-38mm Ø Sub-railing; 38mm Ø
1051 (5) v.1 Pipe Post, all fastening accessories needed to complete work; Painted Finish H=900mm l.m. 5,250.00 7.60 39,900.00
(Location: Main Staircase, Building 84)
Floor Mounted G.I. Pipe Railings, 38mm Ø Top Rail with 2-38mm Ø Sub-railing; 38mm Ø
1051 (5) v.2 Pipe Post, all fastening accessories needed to complete work; Painted Finish H=900mm l.m. 5,250.00 15.20 79,800.00
(Location: Fire Exit Staircase 1 & 2, Building 84)
Floor Mounted Stainless Steel Pipe Railings, 50mm Ø Top Rail with 3-50mm Ø Sub-railing;
1051 (5) v.3 38mm Ø Pipe Post, all fastening accessories needed to complete work; H=900mm l.m. 9,975.00 23.70 236,407.50
(Location: Main Entry and PWD Ramp, Building 84)

Floor Mounted G.I. Pipe Railings, 38mm Ø Top Rail with 2-38mm Ø Sub-railing; 38mm Ø
1051 (5) v.4 Pipe Post, 100mm x 10mm Thk Steel Toe Plate, all fastening accessories needed to complete l.m. 5,250.00 60.90 319,725.00
work; Painted Finish H=1000mm (Location: ACCU Deck, Building 84)

1053 CARPET FLOOR TILES - -


1053 (1) a Carpet Floor Tile, 500 x 500 x 5.3mm thk. sq.m. 1,575.00 116.01 182,715.75
1203 ELECTRIC ELEVATOR - -
1203 (2) b Lift Elevator , 1 Cab (Location: Building 84) lot 2,625,000.00 1.00 2,625,000.00
SUBTOTAL COST - ARCHITECTURAL WORKS 44,845,679.46
WATER SYSTEM
Hot & Cold Water Line
Polypropylene Random (PPR) Pipe Type 3 conforming EN ISO 15874, including pipe and
fittings, miscellaneous consumables and other necessary accessories to complete the
system
PPR Pipes including fittings
1002 (2) e3.1 50 mm dia. meter 1,086.88 6.00 6,521.29
1002 (2) b3.1 25 mm dia. meter 266.18 26.00 6,920.55
1002 (2) a3.1 20 mm dia. meter 172.13 18.00 3,098.28
1002 (2) 3.1 15 mm dia. meter 127.76 77.00 9,837.83
Polypropylene Random (PPR) Pipe Type 3 conforming EN ISO 15874, including pipe and
fittings, pipe supports, miscellaneous consumables and other necessary accessories to
complete the system
PPR Pipes (Above Ceiling) including fittings
1002 (2) e3.2 50 mm dia. meter 1,086.88 33.00 35,867.08
1002 (2) d3.2 40 mm dia. meter 692.06 37.00 25,606.04
1002 (2) c3.2 32 mm dia. meter 456.93 17.00 7,767.87
1002 (2) b3.2 25 mm dia. meter 266.18 22.00 5,855.85
1002 (2) a3.2 20 mm dia. meter 172.13 29.00 4,991.67
1002 (2) 3.2 15 mm dia. meter 127.76 29.00 3,705.16
Polypropylene Random (PPR) Pipe Type 3 conforming EN ISO 15874, including pipe and
fittings, pipe clamps, miscellaneous consumables and other necessary accessories to
complete the system
PPR Pipes (Riser) including fittings
1002 (2) d3.3 40 mm dia. meter 692.06 3.00 2,076.17
1002 (2) c3.3 32 mm dia. meter 456.93 4.00 1,827.74
Valves and devices including grooves/flanges, gaskets, bolts & nuts, adaptors, tagging,
sealant and all other necessary accessories to complete the system
1002 (28) a4 Gate Valve, 32 mm dia. each 1,724.81 2.00 3,449.63
1002 (28) a3 Gate Valve, 25 mm dia. each 1,207.37 6.00 7,244.22
1002 (28) a2 Gate Valve, 20 mm dia. each 862.41 2.00 1,724.81
Water Meter Assembly, 50 mm dia, includes Gate Valve, Check Valve, G.I Pipe and fittings
1002 (23) f.1 piece 23,008.33 1.00 23,008.33
and other accessories to complete the system
High Density Polyethelene (HDPE) Pipe PE-100 conforming AWWA C906-99, ISO 4427, SDR
11, including excavation, backfill, disposal, bedding, supports and other necessary
accessories to complete the system
HDPE Pipes including fittings
1002 (1) f.1 50 mm dia. meter 182.43 12.00 2,189.19
Testing and Disinfecting lot 6,825.00 1.00 6,825.00
SUB-TOTAL 158,516.69
SEWER SYSTEM
Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, miscellaneous consumables and other necessary accessories to complete
the system
uPVC Pipe including fittings
1001 (1) a3.1 100 mm dia. meter 527.91 178.00 93,968.65
1001 (1) a2.1 75 mm dia. meter 396.30 28.00 11,096.54
1001 (1) a1.1 50 mm dia. meter 184.84 56.00 10,351.25
Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, pipe supports, miscellaneous consumables and other necessary
accessories to complete the system
uPVC Pipe (Above Ceiling) including fittings
1001 (1) a3.2 100 mm dia. meter 527.91 56.00 29,563.17
1001 (1) a2.2 75 mm dia. meter 396.30 15.00 5,944.57
1001 (1) a1.2 50 mm dia. meter 184.84 18.00 3,327.19
Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, pipe clamps, miscellaneous consumables and other necessary accessories
to complete the system
uPVC Pipe (Stack) including fittings
1001 (1) a3.3 100 mm dia. meter 527.91 8.00 4,223.31
1001 (1) a2.3 75 mm dia. meter 396.30 8.00 3,170.44
Testing lot 6,825.00 1.00 6,825.00
SUB-TOTAL 168,470.12
VENT SYSTEM
Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, miscellaneous consumables and other necessary accessories to complete
the system
Vent Pipe including fittings
1001 (1) a2.4 75 mm dia. meter 396.30 20.00 7,926.10
1001 (1) a1.4 50 mm dia. meter 184.84 93.00 17,190.47
Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, pipe supports, miscellaneous consumables and other necessary
accessories to complete the system
Vent Above Ceiling including fittings
1001 (1) a4.5 150 mm dia. meter 1,131.24 -
1001 (1) a1.5 50 mm dia. meter 184.84 29.00 5,360.47
Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, pipe clamps, miscellaneous consumables and other necessary accessories
to complete the system
Vent Pipe (Stack) including fittings
1001 (1) a2.6 75 mm dia. meter 396.30 15.00 5,944.57
1001 (1) a1.6 50 mm dia. meter 184.84 9.00 1,663.59
Vent Stack Thru Roof including all necessary items to complete the system
1001 (1) k2 75 mm dia. set 1,638.00 2.00 3,276.00
1001 (1) k1 50 mm dia. set 1,296.75 2.00 2,593.50
SUB-TOTAL 43,954.71

High Density Polyethylene (HDPE) Pipe, SDR 13.6 conforming to ASTM D 3350, ASTM D
1238, ASTM F 714, and ASTM D 3261, including pipe and fittings, structural earthworks,
miscellaneous consumables and other necessary accessories to complete the system

Elevator Pit Pump Discharge Pipe including fittings


Leach Pit/Drywell including excavation, backfill, disposal, gravel bedding, concrete, rebars,
1001 (21) each 245,700.00 9.00 2,211,300.00
formworks, and othe
Testing lot 40,950.00 0.05 1,938.24
SUB-TOTAL 2,213,238.24
PLUMBING FIXTURES
1002 (14) a Lavatory (Wall Hung) including faucet, P-Trap, and other accessories set 8,557.50 4.00 34,230.00
1002 (15) a Lavatory (Undercounter) including faucet, P-Trap, and other accessories set 7,507.50 14.00 105,105.00
1002 (5) a Water Closet (Flush Tank) including other accessories set 14,385.00 18.00 258,930.00
1002 (9) b Urinal including Flush Valve and other items to complete the work set 7,507.50 8.00 60,060.00
1002 (21) Faucet including other necessary accessories to complete the system each 1,522.50 4.00 6,090.00
1002 (16) a1.1 Floor Drain, 50 mm dia. (TYPE A) each 945.00 28.00 26,460.00
1002 (16) a2.2 Floor Drain, 75 mm dia. each 1,155.00 4.00 4,620.00
1002 (35) a3 Floor Cleanout, 100 mm dia. each 1,732.50 14.00 24,255.00
1002 (35) a2 Floor Cleanout, 75 mm dia. each 1,417.50 9.00 12,757.50
1002 (35) b3 Ground Cleanout, 100 mm dia. each 1,732.50 6.00 10,395.00
1002 (35) d3 Wall Cleanout, 100 mm dia. each 1,732.50 2.00 3,465.00
1002 (35) d2 Wall Cleanout, 75 mm dia. each 1,417.50 2.00 2,835.00
SUB-TOTAL 549,202.50
SUBTOTAL COST (PLUMBING AND SANITARY WORKS) 3,133,382.25
MECHANICAL WORKS
1200 AIR CONDITIONING SYSTEM
FAN COIL UNIT/AIR COOLED CONDENSING UNIT - INVERTER SINGLE SPLIT TYPE

FCU/ACCU: 2.637KWr (0.75 TR), Wall Mounted DX unit c/w disconnect switch, thermostat,
1200 (13)a3.3 set 59,745.00 9.00 537,705.00
remote controller, equipment support and other standard accessories. 230V, 1ph, 60hz

FCU/ACCU: 10.55KWr (3.0 TR) 4 - Way Cassette Type DX Unit c/w disconnect switch,
1200 (13)a3.10 thermostat/remote controller, equipment support and other standard accessories. 230V, set 158,550.00 24.00 3,805,200.00
1ph, 60hz
FCU/ACCU: 17.58KWr (5.0 TR) 4 - Way Cassette Type DX Unit c/w disconnect switch,
1200 (13)a3.11 thermostat/remote controller, equipment support and other standard accessories. 230V, set 207,900.00 7.00 1,455,300.00
1ph, 60hz
FCU/ACCU: 10.55KWr (3.0 TR) Ceiling mounted type dx unit c/w disconnect switch,
1200 (13)a3.28 thermostat/remote controller, equipment support and other standard accessories. 230V, set 154,875.00 3.00 464,625.00
1ph, 60hz
MULTI SPLIT INVERTER TYPE - (OUTDOOR UNIT)
ACCU: 11.0KWr (3.13 TR) Floor standing condensing unit c/w inverter compressor,
condenser fan, isolating valves, filter dryer, moisture indicator, disconnect switch, electrical
1200 (13)b1.8 set 112,350.00 17.00 1,909,950.00
connection, equipment support, anti-corrosion protection and standard accessories.
3.24kW, 230V, 3ph, 60hz
MULTI SPLIT INVERTER TYPE - (INDOOR UNIT)
FCU: 3.22KWr (0.9TR) Wall Mounted Type Free Blow, c/w temperature controller, fan speed
1200 (13)b2.2.1 switch, thermostat, isolating valves, vibration isolator, equipment support & other standard set 306,808.95 23.00 7,056,605.85
accessories, 35W, 230V, 1Ø, 60hz
FCU: 5.08Kwr(1.44TR), Wall Mounted Type Free Blow, c/w temperature controller, fan
1200 (13)b2.7 speed switch, thermostat, isolating valves, vibration isolator, equipment support & other set 45,696.00 11.00 502,656.00
standard accessories, 45W, 230V, 1Ø, 60hz
DEDICATED OUTDOOR AIR SYSTEM - VRF SYSTEM (OUTDOOR UNIT)
ACCU: 28 kW (7.96TR) Floor Mounted Air Cooled Condensing Unit c/w condenser fan,
compressor, isolating valves, filter drier, moisture indicator, disconnect switch, electrical
1200 (13)b3.3 set 131,250.00 4.00 525,000.00
connection, equipment support and other std. accessories, to make the unit complete.
6.88kW, 400V, 3Ø, 60hz
DEDICATED OUTDOOR AIR SYSTEM - VRF SYSTEM (INDOOR UNIT)

DOAS: 28 kW (7.96TR) Ceiling Mounted DuctedType VRV/VRF Unit c/w washable filter, VFD,
1200 (13)b4.2 disconnect switch, thermostat, remote controller, vibration isolator,equipment support and set 341,250.00 4.00 1,365,000.00
other std. accessories, to make the unit complete. 638W, 230V, 1Ø, 60hz

Note: Standard accessories for the AC units are included (Remote controllers, filters, drain
Pump kits, filter chambers, Y-joints & T-joints).
1200 (15)a Refrigerant Copper Pipe, Type L, 6.4 mmØ meter 259.90 606.00 157,496.98
1200 (15)b Refrigerant Copper Pipe, Type L, 9.5mmØ meter 321.05 790.00 253,627.92
1200 (15)c Refrigerant Copper Pipe, Type L, 12.7 mmØ meter 508.33 480.00 243,996.48
1200 (15)d Refrigerant Copper Pipe, Type L, 15.88mmØ meter 726.18 534.00 387,780.12
1200 (15)f Refrigerant Copper Pipe, Type L, 22.2mmØ meter 1,158.07 112.00 129,703.39
1200 (17)a Pipe Cladding, Aluminum, 56.4mmØ meter 2,102.10 152.50 320,570.25
1200 (17)b Pipe Cladding, Aluminum, 59.5mmØ meter 2,205.00 107.50 237,037.50
1200 (17)c Pipe Cladding, Aluminum, 62.7mmØ meter 2,425.50 113.00 274,081.50
1200 (17)d Pipe Cladding, Aluminum, 65.88mmØ meter 2,646.00 50.00 132,300.00
1200 (17)f Pipe Cladding, Aluminum, 72.2mmØ meter 3,675.00 4.00 14,700.00
1200 (20) Thermostat set 1,837.50 81.00 148,837.50
1002 (7) a4 PVC Pipe (blue), 32 mmØ, Condensate Drain meter 92.20 237.00 21,851.02
1002 (7) a5 PVC Pipe (blue), 40 mmØ, Condensate Drain meter 106.19 210.00 22,300.49
1002 (7) a7 PVC Pipe (blue), 65 mmØ, Condensate Drain meter 238.73 108.00 25,782.62
1200 (22)c Drain Pipe Insulation, 19mm thick Closed Cell Rubber , 32mm Ø meter 510.85 237.00 121,072.49
1200 (22)d Drain Pipe Insulation, 19mm thick Closed Cell Rubber , 40mm Ø meter 526.38 210.00 110,539.30
1200 (22)f Drain Pipe Insulation, 19mm thick Closed Cell Rubber , 65mm Ø meter 701.72 108.00 75,785.67
1200 (23)a.2 Floor Cleanout, 65mmØ set 1,102.50 6.00 6,615.00
1200 (23)b.3 Cleanout, 32mmØ set 41.16 16.00 658.56
1200 (23)b.4 Cleanout, 40mmØ set 51.45 15.00 771.75
1200 (26) Refrigerant Piping and Equipment Connection set 58,800.00 145.00 8,526,000.00
1200 (27) Vacuum Cleaning and pipe charging meter 735.00 2,522.00 1,853,670.00
1200 (28) Roughing ins & Control wiring for Thermostat control meter 2,205.00 486.00 1,071,630.00
1200 (42) Testing and Commissioning for AC units lot 194,250.00 1.00 194,250.00
SUB - TOTAL 31,953,100.39
1200 VENTILATION SYSTEM
OF: Ceiling mounted propeller type orbit fan c/w fan speed selector/switch, security grille,
1200 (4)c.2 equipment supports, disconnect switch & other standard accessories. 5163 CMH (3037 set 49,350.00 4.00 197,400.00
CFM), 70.5W, 230V, 1Ø, 60HZ, ODP.
EF: Centrifugal Ceiling Cassette Type Exhaust Fan c/w backdraft damper, equipment
1200 (5)a.5.1 supports, intake grille, fan switch, vibration isolators & other standard accessories. set 9,082.50 13.00 118,072.50
170cmh(100 cfm) 0.25 in. Wg, 230V, 1ph, 60 hz.
EF: centrifugal ceiling cassette type exhaust fan c/w backdraft damper, equipment supports,
1200 (5)a.44 intake grille, fan switch, vibration isolators & other standard accessories. 263.1cmh(155 set 12,547.50 4.00 50,190.00
cfm) 0.5 in. WG, 19W, 230V, 1Ø,60hz, ODP
EF: Wall Mounted Propeller Type Exhaust Fan complete w/ backdraft damper, equipment
1200 (5)b.1 supports, fan selector switch, viration isolator, weatherhood and other std. accessories. set 8,331.75 2.00 16,663.50
170cmh(100cfm), 230V, 1ph, 60 hz, ODP.
EF: Wall Mounted Propeller Type Exhaust Fan complete w/ gravity shutter
1200 (5)b.30.1 damper,equipment supports, insect screen, disconnect switch and other std. accessories. set 8,946.00 2.00 17,892.00
425 CMH (250 CFM), 230V, 1Ø, 60HZ, ODP
EF: Wall Mounted Propeller Type Exhaust Fan complete w/ gravity shutter
1200 (5)b.32 damper,equipment supports, insect screen, disconnect switch and other std. accessories. set 8,331.75 2.00 16,663.50
272 CMH (160 CFM), 230V, 1Ø, 60HZ, TEFC.
EF: Wall Mounted Propeller Type Exhaust Fan c/w gravity shutter damper, fan grille, fan
1200 (5)b.43 switch, weatherhood w/ insect screen & other standard accessories. 340 CMH (200 CFM) set 8,946.00 2.00 17,892.00
220V, 1Ø, 60HZ, ODP.
EF: Wall Mounted Propeller type exhaust fan c/w gravity shutter damper, security grilles,
1200 (5)b.46 face grille, equipment supports, weatherhood with insect screen, fan switch, & other set 8,331.75 2.00 16,663.50
standard accessories. 255CMH (150CFM) 19W, 230V, 1Ø, 60HZ ODP
EF: Wall Mounted Propeller type exhaust fan c/w gravity shutter damper, security grilles,
1200 (5)b.47 face grille, equipment supports, weatherhood with insect screen, fan switch, & other set 9,135.00 3.00 27,405.00
standard accessories. 510CMH (300CFM) 29W, 230V, 1Ø, 60HZ ODP
EF: Cabinet Type Centrifugal Inline Ducted Exhaust Fan c/w equipment supports, intake
1200 (7)b.7 grille, fan disconnect switch, vibration isolators & other standard accessories. set 30,977.10 4.00 123,908.40
850cmh(500cfm), 230v, 1Ø, 60Hz, ODP.
EF: Cabinet type centrifugal inline ducted exhaust fan, c/w equipment supports, intake
1200 (7)b.25 grille, fan disconnect switch, vibration isolators, & other standard accessories. 510cmh(315 set 20,349.00 1.00 20,349.00
cfm) 230V, 1Ø,60hz, ODP
1200 (29)e Galvanized Steel Ductwork, Ga 24 sq.m. 285.87 121.10 34,618.70
1200 (29)f Galvanized Steel Ductwork, Ga 26 sq.m. 417.31 265.20 110,671.44
1200 (32)b PVC Duct, 150mm Ø meter 1,131.24 81.00 91,630.74
1200 (33)b Vent Cap w/ insect screen, 150mmØ set 2,457.00 11.00 27,027.00
1200 (34)c.5 Supply Air Register, 250 x 250 set 546.00 1.00 546.00
1200 (34)d.1 Outside Air Register, 150 x 150 set 546.00 37.00 20,202.00
1200 (34)d.2 Outside Air Register, 200 x 150 set 546.00 2.00 1,092.00
1200 (34)d.14 Outside Air Register, 300 x 300 set 887.25 6.00 5,323.50
1200 (34)e.2 Exhaust Air Register, 200 x 200 set 546.00 12.00 6,552.00
1200 (34)e.11 Exhaust Air Register, 500 x 300 set 1,774.50 4.00 7,098.00
1200 (34)g.3 Volume Damper, 150 x 150 set 614.25 16.00 9,828.00
1200 (34)g.10 Volume Damper, 300 x 300 set 1,023.75 8.00 8,190.00
1200 (34)m.7 Outside Air Louver, 450 x 250 set 1,638.00 1.00 1,638.00
1200 (34)o.26.4 Supply Air Louver, 1450 x 300 set 6,142.50 4.00 24,570.00
1200 (30) Flexible Duct Connector meter 1,174.75 9.00 10,572.78
1200 (43) Testing and Commissioning for Ventilation units lot 26,250.00 1.00 26,250.00
SUB - TOTAL 1,008,909.56
1202 FIRE PROTECTION SYSTEM
FE: 4.5 kg(10 lbs), ABC Dry Chemical, Siliconized Mono Ammonium Phospate Dry Chemical,
1202 (6) a1 Wall Mounted Multi-Purpose Portable \fire Extinguisher complete w/ Hose and Horn, wall set 7,121.05 22.00 156,663.04
bracket, ULFM approved.
FE: 4.5 kg(10 lbs), Electrically Non-conductive, non contaminating, odorless gas, Wall
1202 (6) a3.1 Mounted Carbon Dioxide Portable fire Extinguisher complete w/ Hose and Horn,UL Listed & set 7,121.05 4.00 28,484.19
FM approved.
1202 (39) Testing and Commissioning Fire Protection System lot 2,625.00 1.00 2,625.00
SUB - TOTAL 187,772.24
1202 FIRE SUPPRESSION SYSTEM NOVEC-1230

Provide and Install Novec 1230 Pre-engineered automatic fire suppression system using
1202 (48)a.6.1 novec 1230 clean agent, c/w agents container, container's supports, discharge spray set 546,000.00 9.00 4,914,000.00
nozzles, solenoid valves, actuator, control panel for detection, alarm devices, cross zoned
smoke detectors, controller, wiring, piping and other standard accessories, ul listed and fm
approved at Telecom [84-105] (24.68 cu.m.)

Provide and Install Novec 1230 Pre-engineered automatic fire suppression system using
1202 (48)a.6.2 novec 1230 clean agent, c/w agents container, container's supports, discharge spray set 546,000.00 1.00 546,000.00
nozzles, solenoid valves, actuator, control panel for detection, alarm devices, cross zoned
smoke detectors, controller, wiring, piping and other standard accessories, ul listed and fm
approved at Telecom [84-124] (24.68 cu.m.)

Provide and Install Novec 1230 Pre-engineered automatic fire suppression system using
1202 (48)a.6.3 novec 1230 clean agent, c/w agents container, container's supports, discharge spray set 546,000.00 1.00 546,000.00
nozzles, solenoid valves, actuator, control panel for detection, alarm devices, cross zoned
smoke detectors, controller, wiring, piping and other standard accessories, ul listed and fm
approved at Telecom [84-205] (24.68 cu.m.)

Provide and Install Novec 1230 Pre-engineered automatic fire suppression system using
1202 (48)a.6.4 novec 1230 clean agent, c/w agents container, container's supports, discharge spray set 546,000.00 1.00 546,000.00
nozzles, solenoid valves, actuator, control panel for detection, alarm devices, cross zoned
smoke detectors, controller, wiring, piping and other standard accessories, ul listed and fm
approved at Telecom [84-224] (24.68 cu.m.)
SUB - TOTAL 6,552,000.00
TOTAL COST - MECHANICAL WORKS 39,701,782.19
1103 LIGHTING SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 49.14 2,513.00 123,488.82
1100 (3)a Flexible Metal Conduit (FMC), 15mm dia. meter 31.20 250.00 7,800.00
1100 (3)b Flexible Metal Conduit (FMC), 20mm dia. meter 40.30 1,000.00 40,300.00
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 65.00 214.00 13,910.00
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 78.00 447.00 34,866.00
1100 (8)c Square Box, 101mm x 101mm x 54mm, Ga. 16 piece 130.00 37.00 4,810.00
1101 WIRES AND WIRING DEVICES (including connectors, tapes, etc.) -
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 40.56 6,766.00 274,428.96
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 40.56 2,834.00 114,947.04
1101 (3) Light Switch, 15A, 1P, 230V, 60Hz, One-Gang, Grounding Type set 188.50 78.00 14,703.00
1101 (4) Light Switch, 15A, 1P, 230V, 60Hz, Two-Gang, Grounding Type set 300.63 22.00 6,613.75
1101 (5) Light Switch, 15A, 1P, 230V, 60Hz, Three-Gang, Grounding Type set 412.75 2.00 825.50
1101 (6) a Three-Way Switch, One-Gang With 1 - 15A, 1P, 230V, 60Hz, Grounding Type set 295.75 6.00 1,774.50
1101 (15) Single Convenience Outlet/Receptacle (GT), 250V, 15A, 2P (For Emergency Light) set 362.38 53.00 19,205.88
1103 LIGHTING FIXTURES AND LAMPS
1103 (3)b Type " A1 ", Round Downlight with 16W LED, 230V, 60Hz, Recessed Mounted. set 3,000.00 225.00 675,000.00
1103 (3)d Type " B ", 10W LED Round Downlight, 230V, 60Hz, Surface Mounted. set 1,150.00 6.00 6,900.00
1103 (3)f.1 Type " D ", 30W LED Panel Light, 230V, 60Hz, Recessed Mounted. set 5,700.00 77.00 438,900.00
1103 (3)g Type " E ", Enclosed and Gasketed Luminaire with 19W LED, 230V, 60Hz, Surface Mounted. set 4,000.00 21.00 84,000.00

1103 (3)h Type " E1 ", Enclosed and Gasketed Luminaire with 40W LED, 230V, 60Hz, Surface Mounted. set 5,300.00 10.00 53,000.00

Type " J ", Troffer type luminaire with 2 x 17W LED tube and prismatic diffuser, 230V, 60Hz,
1103 (3)t set 4,100.00 130.00 533,000.00
recessed mtd
1103 (3)l Emergency Lighting Fixture, 2 x 2.5W LED Lamp, 230V, 60Hz. set 2,000.00 53.00 106,000.00
Exit Light in Aluminum Housing with High Grade Replaceable Acrylic Panel, Removable
1103 (3)m set 2,000.00 15.00 30,000.00
Directional Indicators, Letters 6" Height with 3/4" Stroke.
1103 (3) Testing and Commissioning lot 78,000.00 1.00 78,000.00
SUB - TOTAL 2,662,473.45
1102 POWER SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 46.80 3,432.00 160,617.60
1100 (6)b Polyvinyl Chloride Pipes (PVC/uPVC), 25mm dia. meter 70.63 1,287.00 90,905.10
1100 (2)c Intermediate Metal Conduit (IMC), 25mm dia. meter 265.36 18.00 4,776.41
1100 (2)f Intermediate Metal Conduit (IMC), 50mm dia. meter 520.15 9.00 4,681.37
1100 (2)g Intermediate Metal Conduit (IMC), 65mm dia. meter 868.66 27.00 23,453.70
1100 (2)h Intermediate Metal Conduit (IMC), 80mm dia. meter 1,402.15 129.00 180,877.87
1100 (2)j Intermediate Metal Conduit (IMC), 100mm dia. meter 1,532.56 42.00 64,367.58
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 65.00 248.00 16,120.00
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 78.00 76.00 5,928.00
1100 (8)c Square Box, 101mm x 101mm x 54mm, Ga. 16 piece 130.00 8.00 1,040.00
1101 WIRES AND WIRING DEVICES (including connectors, tapes, etc.) -
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 40.56 6,852.00 277,917.12
1101 (2) b3 Electric Wire, 5.5mm2 THHN/THWN-2 meter 62.26 534.00 33,246.63
1101 (2) b4 Electric Wire, 8.0mm2 THHN/THWN-2 meter 97.39 2,816.00 274,263.48
1101 (2) b5 Electric Wire, 14mm2 THHN/THWN-2 meter 165.76 84.00 13,923.44
1101 (2) b11 Electric Wire, 80mm2 THHN/THWN-2 meter 929.50 36.00 33,462.00
1101 (2) b12 Electric Wire, 100mm2 THHN/THWN-2 meter 1,057.26 124.00 131,100.74
1101 (2) b14 Electric Wire, 150mm2 THHN/THWN-2 meter 1,613.85 532.00 858,567.46
1101 (2) b15 Electric Wire, 200mm2 THHN/THWN-2 meter 2,031.58 176.00 357,558.57
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 40.56 3,426.00 138,958.56
1101 (2) b3.1 Electric Wire, 5.5mm2 TW (G) meter 62.26 1,659.00 103,288.68
1101 (2) b4.1 Electric Wire, 8.0mm2 TW (G) meter 97.39 21.00 2,045.29
1101 (2) b5.1 Electric Wire, 14mm2 TW (G) meter 165.76 9.00 1,491.80
1101 (2) b6.1 Electric Wire, 22mm2 TW (G) meter 256.88 95.00 24,403.60
1101 (2) b7.1 Electric Wire, 30mm2 TW (G) meter 376.87 69.00 26,004.03
1101 (2) b9.1 Electric Wire, 50mm2 TW (G) meter 608.40 44.00 26,769.60
1101 (15) Single Convenience Outlet/Receptacle (GT), 250V, 15A, 2P set 778.75 12.00 9,345.00
1101 (16) Duplex Conveniece Outlet/Receptacle (GT), 250V, 15A, 2P, Wall Mounted set 890.00 232.00 206,480.00
1101 (19) Duplex Conveniece Outlet/Receptacle (GT), 250V, 15A, 2P, Wall Mounted, Weatherproof set 2,000.00 2.00 4,000.00
1101 (22) Pop-up type/Floor Duplex Convenience Outlet/Receptacle (GT) set 4,300.00 4.00 17,200.00
POWER LOAD CENTER, SWITCHGEAR AND PANELBOARDS, AND OTHER OVERCURRENT
1102
PROTECTION DEVICES

Panelboard, 1MDP, Main: 800AT/800AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 65KAIC,


Branches: 1 - 350AT/400AF, 3P, MCCB, 1 - 300AT/400AF, 3P, MCCB, 1 - 250AT/400AF, 3P,
1102 (2)84.1 MCCB, 1 - 225AT/250AF, 3P, MCCB, 2 - 60AT/100AF, 3P, MCCB, 1 - 30AT/100AF, 3P, MCCB, set 95,174.27 1.00 95,174.27
1 - SPD, 240kA/Phase, complete with 1 - Digital Power Meter (DPM), 3 - Current Limiting
Fuse (CLF), 3 - Current Transformer 800/5A, in NEMA 1 Enclosure. (Located at Bldg # 84)

Panelboard, 1LP1 / 1LP2, Main: 60AT/100AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 10KAIC,
1102 (2)84.2 Branches: 20 - 20AT/100AF, 1P, MCCB, complete with 3 - Current Limiting Fuse, 3 - set 21,089.56 1.00 21,089.56
Indicating Lights (R,Y,B), in NEMA 1 Enclosure. (Located at Bldg # 84)

Panelboard, 1DP1, Main: 300AT/400AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 25KAIC,


Branches: 1 - 200AT/250AF, 3P, MCCB, 2 - 60AT/100AF, 3P, MCCB, 1 - 30AT/100AF, 3P,
1102 (2)84.3 set 37,692.82 1.00 37,692.82
MCCB, 1 - SPD, 120kA/Phase, complete with 3 - Current Limiting Fuse, 3 - Indicating Lights
(R,Y,B), in NEMA 1 Enclosure. (Located at Bldg # 84)

Panelboard, 1DP2, Main: 350AT/400AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 25KAIC,


Branches: 1 - 250AT/250AF, 3P, MCCB, 2 - 60AT/100AF, 3P, MCCB, 1 - 30AT/100AF, 3P,
1102 (2)84.4 set 37,692.82 1.00 37,692.82
MCCB, 1 - SPD, 120kA/Phase, complete with 3 - Current Limiting Fuse, 3 - Indicating Lights
(R,Y,B), in NEMA 1 Enclosure. (Located at Bldg # 84)

Panelboard, 1PP1, Main: 60AT/100AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 10KAIC,


1102 (2)84.5 Branches: 14 - 20AT/100AF, 1P, MCCB, complete with 3 - Current Limiting Fuse, 3 - set 21,089.56 1.00 21,089.56
Indicating Lights (R,Y,B), in NEMA 1 Enclosure. (Located at Bldg # 84)

Panelboard, 1PPAC1B, Main: 225AT/250AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 25KAIC,


Branches: 12 - 60AT/100AF, 1P, MCCB, 1 - 50AT/100AF, 1P, MCCB, 1 - 40AT/100AF, 1P,
1102 (2)84.6 set 29,466.58 1.00 29,466.58
MCCB, 2 - 30AT/100AF, 1P, MCCB, 2 - 20AT/100AF, 1P, MCCB, complete with 3 - Current
Limiting Fuse, 3 - Indicating Lights (R,Y,B), in NEMA 1 Enclosure. (Located at Bldg # 84)

Panelboard, 1PPAC2B, Main: 250AT/400AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 25KAIC,


Branches: 4 - 80AT/100AF, 1P, MCCB, 2 - 60AT/100AF, 1P, MCCB, 6 - 50AT/100AF, 1P,
1102 (2)84.7 MCCB, 1 - 40AT/100AF, 1P, MCCB, 2 - 30AT/100AF, 1P, MCCB, 2 - 20AT/100AF, 1P, MCCB, set 30,822.58 1.00 30,822.58
complete with 3 - Current Limiting Fuse, 3 - Indicating Lights (R,Y,B), in NEMA 1 Enclosure.
(Located at Bldg # 84)
Panelboard, 1PPAC1A, Main: 200AT/250AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 25KAIC,
Branches: 10 - 60AT/100AF, 1P, MCCB, 2 - 50AT/100AF, 1P, MCCB, 1 - 40AT/100AF, 1P,
1102 (2)84.8 set 29,466.58 1.00 29,466.58
MCCB, 2 - 30AT/100AF, 1P, MCCB, 1 - 20AT/100AF, 1P, MCCB, complete with 3 - Current
Limiting Fuse, 3 - Indicating Lights (R,Y,B), in NEMA 1 Enclosure. (Located at Bldg # 84)

Panelboard, 1PP2, Main: 60AT/100AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 18KAIC,


1102 (2)84.9 Branches: 14 - 20AT/100AF, 1P, MCCB, complete with 3 - Current Limiting Fuse, 3 - set 21,089.56 1.00 21,089.56
Indicating Lights (R,Y,B), in NEMA 1 Enclosure. (Located at Bldg # 84)

Panelboard, 1PPAC2A, Main: 250AT/400AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 25KAIC,


Branches: 3 - 80AT/100AF, 1P, MCCB, 3 - 60AT/100AF, 1P, MCCB, 8 - 50AT/100AF, 1P,
1102 (2)84.10 MCCB, 1 - 40AT/100AF, 1P, MCCB, 2 - 30AT/100AF, 1P, MCCB, 2 - 20AT/100AF, 1P, MCCB, set 30,822.58 1.00 30,822.58
complete with 3 - Current Limiting Fuse, 3 - Indicating Lights (R,Y,B), in NEMA 1 Enclosure.
(Located at Bldg # 84)
1102 (24) a2.2 Enclosed Circuit Breaker, 30AT/100AF, 1P, 230V, in NEMA 3R Enclosure set 5,825.98 8.00 46,607.81
1102 (24) a2.4 Enclosed Circuit Breaker, 50AT/100AF, 1P, 230V, in NEMA 3R Enclosure set 6,215.95 17.00 105,671.15
1102 (24) a2.5 Enclosed Circuit Breaker, 60AT/100AF, 1P, 230V, in NEMA 3R Enclosure set 6,363.77 27.00 171,821.87
1102 (24) a2.7 Enclosed Circuit Breaker, 80AT/100AF, 1P, 230V, in NEMA 3R Enclosure set 11,035.57 7.00 77,248.99
1102 (24) b5.3 Enclosed Circuit Breaker, 40AT/100AF, 3P, 400V, in NEMA 3R Enclosure set 5,825.98 4.00 23,303.90
1102 (33)a Remote Start / Stop Push Button, in NEMA 1 Enclosure set 6,500.00 2.00 13,000.00
1102 (36) Testing and Commissioning lot 78,000.00 1.00 78,000.00
SUB-TOTAL 3,962,854.23
1208 FIRE ALARM SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (2)a Intermediate Metal Conduit (IMC), 15mm dia. meter 120.76 1,080.00 130,425.98
1100 (3)a Flexible Metal Conduit (FMC), 15mm dia. meter 27.30 111.00 3,030.30
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 65.00 12.00 780.00
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 78.00 135.00 10,530.00
1100 (8)c Square Box, 101mm x 101mm x 54mm, Ga. 16 piece 130.00 12.00 1,560.00
1101 FIRE ALARM WIRES AND CABLES (including connectors, tapes, etc.) -
1101 (2)g1 1.25mm2 Twisted Pair Shielded Cable meter 23.40 922.00 21,574.80
1101 (2) b1 Electric Wire, 2.0mm2 THHN/THWN-2 meter 27.04 646.00 17,467.84
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 40.56 28.00 1,135.68
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 40.56 14.00 567.84
1208 FIRE ALARM DEVICES AND EQUIPMENT -
1208 (5) b Fire Alarm Control Panel (FACP) (2 - LOOPS), Fully Addressable set 190,000.00 1.00 190,000.00
1208 (2) Addressable Smoke Detector set 4,000.00 107.00 428,000.00
1208 (3) Addressable Heat Detector set 4,000.00 4.00 16,000.00
1208 (6) Addressable Manual Pull Station set 2,300.00 12.00 27,600.00
1208 (4) Addressable Fire Alarm Strobe with Sounder set 2,300.00 12.00 27,600.00
1208 (19)9 Testing and Commissioning lot 78,000.00 1.00 78,000.00
SUB-TOTAL 954,272.44
1105 NETWORK CABLING SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INs)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 46.80 243.00 11,372.40
1100 (6)b Polyvinyl Chloride Pipes (PVC/uPVC), 25mm dia. meter 70.85 654.00 46,335.90
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 65.00 132.00 8,580.00
1100 (8)c Square Box, 101mm x 101mm x 54mm, Ga. 16 piece 78.00 2.00 156.00

Wireway, 200mmW x 200mmD x 2400mmL, Ga. 16 (complete with cover, support, fittings,
1100 (8) e9 length 4,550.00 75.00 341,250.00
end plate and all fixing accessories like jointing plate, fixing nuts, and bolts and washers.)

1105 NETWORK WIRES AND CABLES (including connectors, tapes, etc.)


1105 (7) 0.57mm, 4 Pairs, Cat. 6, Shielded Twisted Pair Cable (STP) (1 roll = 500m) roll 36.40 12.41 451.72
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 40.56 92.00 3,731.52
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 40.56 46.00 1,865.76
1105 NETWORK CABLING DEVICES AND EQUIPMENT
1105 (14) a Single Work Station Outlet, Voice Line, Wall Mounted set 950.00 76.00 72,200.00
1105 (15) Double Work Station, Wall Mounted Outlet, Combination of Voice and Data set 1,060.00 56.00 59,360.00
1105 (17) Double Work Station, Floor Mounted Outlet, Combination of Voice and Data set 5,000.00 2.00 10,000.00

Main Distribution Frame (MDF) located at Bldg # 84, complete with the following: 1 set of
32 Port Patch Panel , 2 set of 32 Port POE Switch, 1 set of 8 Port CORE Switch, 1 set of
1105 (2)84.1 Network Video Recorder(NVR)-32TB, 1set of Power Supply complete with 8 Convenience set 95,000.00 1.00 95,000.00
Outlet, 1 set UPS 1KVA, 1Ø, 230V, 60Hz, 1set of 27U Free Standing Rack Cabinet and other
accessories needed to make the system complete and operational.

Intermediate Distribution Frame (IDF-1 / IDF-2/ IDF-3) located at Bldg # 84, complete with
the following: 1 set of 32 Port Patch Panel , 2 set of 32 Port POE Switch, 1 set of 8 Port CORE
1105 (2)84.2 Switch, 1 set of Network Video Recorder(NVR)-32TB, 1set of Power Supply complete with 8 set 65,000.00 3.00 195,000.00
Convenience Outlet, 1 set UPS 1KVA, 1Ø, 230V, 60Hz, 1set of 24U Free Standing Rack
Cabinet and other accessories needed to make the system complete and operational.

1105 (22) c Private Automatic Branch Exchange (PABX) - 60 Direct Lines, 20 Trunk Lines set 135,000.00 1.00 135,000.00
1105 (24)8 Testing and Commissioning lot 78,000.00 1.00 78,000.00
SUB-TOTAL 1,058,303.30
1106 CCTV SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 46.80 334.00 15,631.20
1100 (3)a Flexible Metal Conduit (FMC), 15mm dia. meter 27.30 15.00 409.50
1100 (13)a Straight Connector, 15mm dia. piece 20.80 58.00 1,206.40
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 78.00 29.00 2,262.00
1105 CCTV WIRES AND CABLES (including connectors, tapes, etc.)
1105 (7) 0.57mm, 4 Pairs, Cat. 6, Shielded Twisted Pair Cable (STP) (1 roll = 500m) roll 36.40 2.00 72.80
1106 CCTV DEVICES AND EQUIPMENT
1106 (2) IP Based Fixed Dome Type CCTV Camera, 2MP, Indoor set 4,200.00 29.00 121,800.00

CCTV Equipment located at Bldg # 84, consists of the following: 2 sets of 32" LED Moitor, 1
set Central Processing Unit (CPU) - Intel Core i7 Extreme Processor 3.2GHz, 16GB RAM
1106 (15)84.1 set 140,000.00 1.00 140,000.00
Memory, Windows 10 with 4-8TB HDD for Video Recording, Keyboard, Joystick, and other
accessories needed to make the system complete and operational.

1106 (16)8 Testing and Commissioning lot 80,000.00 1.00 80,000.00


SUB-TOTAL 361,381.90
1107 PUBLIC ADDRESS SYSTEM
1107(7) Testing and Commissioning lot 70,000.00 1.00 70,000.00
SUB-TOTAL 70,000.00
1108 ACCESS CONTROL SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 46.80 7.00 327.60
1100 (6)b Polyvinyl Chloride Pipes (PVC/uPVC), 25mm dia. meter 70.85 255.00 18,066.75
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 65.00 36.00 2,340.00
1101 WIRES AND CABLES (including connectors, tapes, etc.)
1105 (7) 0.57mm, 4 Pairs, Cat. 6, Shielded Twisted Pair Cable (STP) (1 roll = 500m) roll 36.40 0.04 1.46
1101 (2)g1 1.25mm2 Twisted Pair Shielded Cable meter 23.40 112.00 2,620.80
1101 (2) i 1.25mm2 TF meter 23.40 71.00 1,661.40
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 40.56 18.00 730.08
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 40.56 9.00 365.04
1108 (12) RS485 Cable meter 32.57 3.00 97.72
1108 ACS DEVICES
ACS Panel with built-in biometrics/recording , TCP Network ready complete with 1 kva UPS
1108(1) set
and all necessary accs needed to complete the system and operational.

Access Control Equipment consists of the following ACS Panel, Main ACS , Central Processing
Unit (CPU) - Intel Core i7 Extreme Processor 3.2GHz, 8GB RAM Memory, Windows 10 with
1108(2) set 175,500.00 1.00 175,500.00
1TB HDD, 1 set 32" LED Monitor, Keyboard, joystick, UPS, 1kVA, 1Ø, 230V, 60Hz and other
accessories needed to make the system complete and operational

1108 (4) Magnetic Door Contact set 585.00 6.00 3,510.00


1108(6) RM4 Auxiliary Reader Relay, Module for Card Readers set 19,500.00 6.00 117,000.00
1108(7) Electromagnetic Lock set 1,040.00 6.00 6,240.00
1108(8) Card Reader set 4,550.00 6.00 27,300.00
1108(9) Exit Push Button set 1,560.00 6.00 9,360.00
1108(10) Emergency Break Glass set 1,950.00 6.00 11,700.00
1108(13).1 Interfacing, Testing and Commissioning lot 84,500.00 1.00 84,500.00
SUB-TOTAL 461,320.85
1109 GROUNDING SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-IN)
1100 (6)b Polyvinyl Chloride Pipes (PVC/uPVC), 25mm dia. meter 70.85 84.00 5,951.40
1101 GROUNDING CONDUCTORS, ELECTRODES AND CONNECTIONS
1109 (4)k Bare Copper Wire, 60mm² Soft Drawn meter 494.07 378.00 186,759.03
1109 (6)e Ground Rod Copper Clad, 20mm dia. x 3m length 4,550.00 21.00 95,550.00
1109 (7) Grounding Test Well piece 7,800.00 2.00 15,600.00
1109 (8) Grounding Bus set 6,500.00 4.00 26,000.00
1109 (2) Exothermic Welded Connector set 8,450.00 42.00 354,900.00
Air Terminal, Lightning Arrester, ESE Type, 107m Radius of Protection (Complete with
1109 (3) Lightning Event Counter, Terminal Lugs, Mounting Mast Pole, and other accessories needed set 132,600.00 1.00 132,600.00
to make the system complete and operational.)
1109 (9).1 Testing and Commissioning lot 52,000.00 1.00 52,000.00

SUB-TOTAL 869,360.43

TOTAL COST - ELECTRICAL WORKS 10,399,966.60

GRAND TOTAL 136,589,703.17

General Requirements and Miscellaneaus Expences : 15.00% 20,488,455.48

Contingencies : 15.00% 20,488,455.48

Contractor's Profit & Overhead : 10.00% 13,658,970.32

Value Added Tax (VAT) : 12.00% 16,390,764.38

TOTAL PROJECT COST : 207,616,348.82


BILL OF QUANTITIES
Project Name : CONSTRUCTION OF VARIOUS STRUCTURES AND FACILITIES WITHIN THE 100 HECTARE AREA AT BATAAN TECHNOLOGY PARK,
MORONG BATAAN ( PHASE 1 PACKAGE 2 )
Location : MORONG, BATAAN
BUILDING 4.3A

UNIT COST BUILDING 4.3A


ITEM NO. DESCRIPTION UNIT (Pesos)
QUANTITY AMOUNT

STRUCTURAL EARTHWORK
803 (1) a Structure Excavation (Common Soil), includes Hauling and Disposal Cost cu.m. 420.00 88.71 37,258.20
803 (3) b Foundation Fill, Base Course cu.m. 1,102.50 19.96 22,005.90
515 (3) Structural Backfilling (using Excavated Materials) cu.m. 367.50 32.20 11,833.50
1000 (1) Soil Poisoning liters 105.00 12.73 1,336.65
SUB-TOTAL 72,434.25

Cast-In Place Concrete, 21 Mpa


900 (1) c1-a Structural Concrete, Column Footings, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 10.10 52,494.75
900 (1) c1-b Structural Concrete, Wall Footings, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 1.07 5,561.33
900 (1) c1-g Structural Concrete, Slab On Grade, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 11.58 60,187.05

Cast-In Place Concrete, 28 Mpa


900 (8)-n Structural Concrete, Footing-Tie-Beams, 28 MPa @ 28 days cu.m. 5,932.50 7.78 46,154.85
900 (8)-o Structural Concrete, Roof Beams/Suspended Beams/Girders, 28 MPa @ 28 days cu.m. 5,932.50 7.36 43,663.20
900 (8)-q Structural Concrete, Lintel Beam, 28 MPa @ 28 days cu.m. 5,932.50 1.53 9,076.73
900 (8)-r Structural Concrete, Bond Beam, 28 MPa @ 28 days cu.m. 5,932.50 1.88 11,153.10
900 (8)-s Structural Concrete, Columns/Planted Columns, 28 MPa @ 28 days cu.m. 5,932.50 4.67 27,704.77
900 (8)-t Structural Concrete, Stiffener Columns, 28 MPa @ 28 days cu.m. 5,932.50 5.44 32,272.80
900 (8)-aa Structural Concrete, Parapet Wall, 28 MPa @ 28 days cu.m. 5,932.50 0.94 5,576.55

Reinforcing Steel, Grade 40


902 (1) a-9 Reinforcing Steel, Lintel Beam, Grade 40 kgs. 74.03 107.60 7,965.09
902 (1) a-10 Reinforcing Steel, Bond Beam, Grade 40 kgs. 74.03 149.85 11,092.65

Reinforcing Steel, Grade 60


902 (1) b-1 Reinforcing Steel, Column Footings, Grade 60 kgs. 77.18 1,031.08 79,573.60
902 (1) b-3 Reinforcing Steel, Wall Footings, Grade 60 kgs. 77.18 100.37 7,746.05
902 (1) b-4 Reinforcing Steel, Slab On Grade, Grade 60 kgs. 77.18 759.29 58,598.21
902 (1) b-8 Reinforcing Steel, Footing Tie Beam, Grade 60 kgs. 77.18 1,576.27 121,648.64
902 (1) b-10 Reinforcing Steel, Suspended Beam/Roof Beam/Girders, Grade 60 kgs. 77.18 1,791.82 138,283.71
902 (1) b-12 Reinforcing Steel, Lintel Beam, Grade 60 kgs. 77.18 256.00 19,756.80
902 (1) b-13 Reinforcing Steel, Bond Beam, Grade 60 kgs. 77.18 138.19 10,664.81
902 (1) b-14 Reinforcing Steel, Columns, Grade 60 kgs. 77.18 1,556.10 120,092.02
902 (1) b-16 Reinforcing Steel, Stiffener Column, Grade 60 kgs. 77.18 844.69 65,188.95
902 (1) b-32 Reinforcing Steel, Parapet Wall, Grade 60 kgs. 77.18 170.42 13,152.16

Formworks and Falsework


903 (2)-b Formworks and Falseworks, Column Footings sq.m. 682.50 23.04 15,724.80
903 (2)-d Formworks and Falseworks, Wall Footings sq.m. 682.50 2.24 1,528.80
903 (2)-e Formworks and Falseworks, Slab On Grade sq.m. 682.50 7.05 4,811.63
903 (2)-i Formworks and Falseworks, Footing Tie Beam sq.m. 682.50 51.88 35,408.10
903 (2)-k Formworks and Falseworks, Suspended Beam/Roof Beam/Girders sq.m. 682.50 77.13 52,641.23
903 (2)-m Formworks and Falseworks, Lintel Beam sq.m. 682.50 24.98 17,048.85
903 (2)-n Formworks and Falseworks, Bond Beam sq.m. 682.50 27.56 18,809.70
903 (2)-o Formworks and Falseworks, Columns sq.m. 682.50 62.30 42,519.75
903 (2)-q Formworks and Falseworks, Stiffener Columns sq.m. 682.50 72.50 49,481.25
903 (2)-t Formworks and Falseworks, Parapet Wall sq.m. 682.50 12.57 8,579.03

Preformed Sponge Rubber Joint Expansion


413 (3) a Preformed Expansion Joint Filler with Sealant, 12 mm thick cu.m. 2,152.50 0.15 322.88
413 (4) a Elastic Sealant on Ø12 mm Backing Rod l.m. 288.75 221.78 64,038.98
SUB-TOTAL 1,258,522.79

METAL WORKS
Furnished, Fabricated and Erected
1047 (2) a Structural Steel, Purlins (LC Sections) kgs. 82.95 875.01 72,582.08
1047 (2) d-2 Structural Steel, Top Wall Support (Angle Bar Sections) kgs. 82.95 148.39 12,308.95
Metal Structure Accessories, Connection Bolts, ∅12mm x 40 mm Connection Bolts w/ Std
1047 (3) a-1 Nuts & Washer, ASTM A325 ea. 183.75 232.00 42,630.00

Metal Structure Accessories, Anchor Bolts, Ø12mm x 200mm w/ Std Nuts & Washer, ASTM
1047 (3) a-3 F1554 (depth of embedment = 150mm) ea. 525.00 232.00 121,800.00
1047 (3) a-8 Metal Structure and Acessories, Stud Anchor, ∅12mm w/ Std Nuts & Washer ea. 236.25 72.00 17,010.00
1047 (6) a Metal Structure Accessories, Base Plates (includes non-shrink grout) kgs. 82.95 273.18 22,660.28
Metal Structure Accessories, Steel Plates/Connector Plates/Cap Plates/Cover
1047 (6) b Plates/Through Plates/Anchor Plates/Cap Plates/Washer Plates/Shear Plates/Embedded kgs. 82.95 163.91 13,596.33
Plates/Extension Plates
1047 (7) b Metal Structure Accessories, Ø12mm Sagrods kgs. 82.95 15.71 1,303.14
Metal Structures and Accessories, Watch Tower for 3-units (includes HSS 5x5x0.375 Steel
Column, C4x4.5 Steel beam, C3x3 Steel Beam and Steel Rafter, LC100x50x15x2.0 Purlins,
1047 (12) 150x12 Hollow Steel Pipe for Kingpost, connection bolts, connection Plates and other items lot 0.00 n/a
to complete the works)

Metal Structures and Accessories, Catwalk, L=183.65m, W=1.30m ( includes A505MPU


1047 (13) Webforge Steel Grating, W8x12 Steel Beam, 2L100x100x8 Steel Support, Baseplates, Anchor lot 0.00 n/a
Bolts and other items to complete the works)
Metal Structures and Accessories, Steel Stairs ( includes A323MPU 32x3 Webforge Steel
1047 (14) Grating, HT152x151x8x11 Steel Column, C10x20 Stringer, Angle Bar Connections, lot 0.00 n/a
Baseplates, Anchor Bolts and other items to complete the works)
SUB-TOTAL 303,890.79

SUBTOTAL COST - STRUCTURAL WORKS 1,634,847.83

ARCHITECTURAL WORKS (ALL BUILDINGS)

1002 PLUMBING WORKS -


Facial Mirror (6mm Thk with 25mm Thk Plywood Backing and 25x25mm Tubular Aluminum
1002 (20) a sq.m. 16,691.85
Trim) 2,205.00 7.57
1002 (38) Liquid Soap Dispenser set 367.50 5.00 1,837.50
1002 (39) Toilet Paper Holder set 3,150.00 8.00 25,200.00
1002 (40) Grab Bar set 2,572.50 1.00 2,572.50
1002 (43) Urinal Partition, 20mm Thk x 400mm W X 1150mm H set 3,307.50 2.00 6,615.00
1002 (44) Robe Hook set 787.50 15.00 11,812.50
1003 (1) e1.2 Ceiling, Gypsum Board on Metal Suspension System ;12mm Thk Moisture Resistant sq.m. 1,526.70 98.49 150,364.68
1003 (23) MODULAR PARTITION -
Toilet Partitions, 15mm Thk Solid Grade HPL with Hardware, fittings, fastening and
1003 (23) a.5 anchoring system. (15 cubicles; Location: Building 4.3A) l.s. 318,937.50
318,937.50 1.00
1004 FINISHING HARDWARE -
1004 (2) c Lockset Series 3400 Function 80 (Storeroom), Grade 1 set 1,312.50 5.00 6,562.50
1004 (2) k Butt Hinges 100mm x 100 x 3mm (4" x 4") set/pair 1,260.00 5.00 6,300.00
1006 STEEL DOORS AND FRAMES -
Hollow Steel Door (45mm Thk, including Door Jamb, Single Leaf ; Type B= 900mm W x
1006 (1) a.2 sq.m. 63,206.33
2100mm H)) 33,442.50 1.89
Hollow Steel Door (45mm Thk, including Door Jamb with View Glass, Double Leaf ; Type B=
1006 (1) b.3 sq.m. 277,830.00
1800mm W x 2100mm H)) 73,500.00 3.78
1008 (1) c.1.49 Awning Type (6mm Thk Float Glass, 1 Panel, Type A= 1000mm W x 550mm H) sqm. 8,121.75 1.65 13,400.89
1010 WOODEN DOORS AND WIINDOWS -
1010 (1) d Wooden Door Jamb (45mm x 1000mm W x 2150mm H) set 2,712.94 3.00 8,138.81
Wooden Doors, Wood Panel (45mm Thk Flush Hollow Core with Louver, Single Leaf Type A=
1010 (2) a.1 900mm W x 2100mm H) sq.m. 73,138.75
12,899.25 5.67
1014 PREPAINTED METAL SHEETS -
Preformed Prepaintedl Metal Roofing, Galvalume Ga. 24, including Stainless Steel Gutter,
1014 (1) c.1 Ga.22, bended materials, flashings, ridge roll and other attachment accessories necessary to sq.m. 171,853.50
complete work. (DN Hi Rib 1030) 1,706.25 100.72
1016 WATERPROOFING -
1016 (3) Concrete Sealer sq.m. 472.50 12.60 5,953.50
1018 CERAMIC/ GRANITE TILES -
1018 (1) a Glazed Tiles (Wall Finish: Ceramic Tiles, 6mm Thk x 300 x 300mm) sq.m. 1,732.50 162.60 281,704.50
1018 (2) a Unglazed Tiles (Floor Finish: Ceramic Tiles, 6mm Thk x 300 x 300mm) sq.m. 1,732.50 87.30 151,247.25
1021 CEMENT FLOOR FINISH -
1021 (1) a Cement Floor Finish, Plain sq.m. 451.50 11.19 5,052.29
1027 (1) a Cement Plaster Finish (on Concrete Masonry Units) sq.m. 661.50 363.50 240,455.25
1027 (1) a.1 Cement Plaster Finish (on Concrete Structural Members) sq.m. 661.50 27.40 18,125.10
1027 (1) c.1 Cement Plaster Finish: Exposed Construction, Soffit of Slab (Smooth Cement Finish) sq.m. 661.50 12.60 8,334.90
1032 PAINTING, VARNISHING AND OTHER RELATED WORKS -
1032 (1) a.2 Painting on Concrete, Exterior sq.m. 577.50 141.74 81,854.85
1032 (1) a.3 Painting on Concrete, Interior sq.m. 420.00 86.57 36,359.40
1032 (1) a.6 Painting on Concrete: Epoxy Floor Coating sq.m. 682.50 11.19 7,637.17
1032 (1) a.8 Painting on Masonry/ Concrete :Exposed Construction, Soffit of Slab sq.m. 420.00 12.60 5,292.00
1032 (1) b.1 Painting Works: Wood Works (Alkyd Type) sq.m. 787.50 28.66 22,569.75
1032 (1) c.1 Painting on Steel: Exposed Structural Metals sq.m. 787.50 38.10 30,003.75
1032 (1) c.2 Painting on Steel: Steel Doors and Louvers sq.m. 787.50 15.10 11,891.25
1032 (6) Painting Works: Painting on Gypsum Board Ceiling, Flat Finish sq.m. 420.00 98.49 41,365.80
1034 (1) b Damp proofing : Polyethylene Sheet Vapor Barrier, 6mils sq.m. 200.00 98.49 19,698.00
1038 REFLECTIVE INSULATION -
Blanket Insulation, R= 19 with Wiremesh Reinforcement; With Foil on One Side (Rockwool
1038 (2) sq.m. 132,195.00
Insulation) (Location: Roofing) 1,312.50 100.72
1046 MASONRY WORKS -
1046 (2) a.1 CHB Non Load Bearing (including Reinforcing Steel), 100mm thk sq.m. 1,365.00 11.87 16,202.55
1046 (2) a.2 CHB Non Load Bearing (including Reinforcing Steel), 150mm thk. sq.m. 1,365.00 189.68 258,913.20
1047 METAL STRUCTURE -

SUBTOTAL COST - ARCHITECTURAL WORKS 2,529,317.82


PLUMBING AND SANITARY WORKS ( ALL BUILDINGS)
WATER SYSTEM
Hot & Cold Water Line
Polypropylene Random (PPR) Pipe Type 3 conforming EN ISO 15874, including pipe and
fittings, miscellaneous consumables and other necessary accessories to complete the
system
1002 (2) e3.1 50 mm dia. meter 1,086.88 15.00 16,303.22
1002 (2) d3.1 40 mm dia. meter 692.06 6.00 4,152.33
1002 (2) c3.1 32 mm dia. meter 456.93 10.00 4,569.34
1002 (2) b3.1 25 mm dia. meter 266.18 12.00 3,194.10
1002 (2) a3.1 20 mm dia. meter 172.13 50.00 8,606.32
1002 (2) 3.1 15 mm dia. meter 127.76 14.00 1,788.70
Valves and devices including grooves/flanges, gaskets, bolts & nuts, adaptors, tagging,
sealant and all other necessary accessories to complete the system
1002 (28) a6 Gate Valve, 50 mm dia. each 2,441.25 4.00 9,765.00
1002 (28) a4 Gate Valve, 32 mm dia. each 1,589.28 1.00 1,589.28
High Density Polyethelene (HDPE) Pipe PE-100 conforming AWWA C906-99, ISO 4427, SDR
11, including excavation, backfill, disposal, bedding, supports and other necessary
accessories to complete the system
HDPE Pipes including fittings
1002 (1) f.1 50 mm dia. meter 182.43 2.00 364.86
Testing and Disinfecting lot 26,250.00 1.00 26,250.00

SUB-TOTAL 76,583.15

SEWER SYSTEM
Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, miscellaneous consumables and other necessary accessories to complete
the system
uPVC Pipe including fittings
1001 (1) a3.1 100 mm dia. meter 668.59 55.00 36,772.31
1001 (1) a2.1 75 mm dia. meter 567.35 2.00 1,134.70
1001 (1) a1.1 50 mm dia. meter 404.69 32.00 12,950.00
Testing lot 15,750.00 1.00 15,750.00

SUB-TOTAL 66,607.01

VENT SYSTEM
Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, miscellaneous consumables and other necessary accessories to complete
the system
Vent Pipe including fittings
1001 (1) a1.4 50 mm dia. meter 404.69 72.00 29,137.50
Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, pipe supports, miscellaneous consumables and other necessary
accessories to complete the system
Vent Above Ceiling including fittings
1001 (1) a1.5 50 mm dia. meter 404.69 5.00 2,023.44
Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, pipe clamps, miscellaneous consumables and other necessary accessories
to complete the system
1001 (1) a2.6 75 mm dia. meter 567.35 3.00 1,702.05
1001 (1) k2 75 mm dia. set 1,523.55 1.00 1,523.55

SUB-TOTAL 34,386.54

STORM AND DRAINAGE SYSTEM


Unplasticized Polyninyl Chloride (uPVC) conforming to ASTM D2729 series 1000, including
pipe and fittings, structural earthworks, miscellaneous consumables and other necessary
accessories to complete the system
1001 (1) a3.7 100 mm dia. meter 668.59 10.00 6,685.88

Unplasticized Polyvinyl Chloride (uPVC) Pipe conforming to ASTM D2729, including pipe and
fittings, pipe clamps and other necessary accessories to complete the system

Downspout including fittings


1001 (1) a2.9 75 mm dia. meter 567.35 6.00 3,404.10

High Density Polyethylene (HDPE) Pipe, SDR 13.6 conforming to ASTM D 3350, ASTM D
1238, ASTM F 714, and ASTM D 3261, including pipe and fittings, structural earthworks,
miscellaneous consumables and other necessary accessories to complete the system

Elevator Pit Pump Discharge Pipe including fittings


Junction Box including excavation, backfill, disposal, gravel bedding, concrete, rebars,
1001 (7) a formworks, and other accessories to complete the works each 136,500.00
68,250.00 2.00
Testing lot 26,250.00 1.00 26,250.00

SUB-TOTAL 172,839.98

PLUMBING FIXTURES
1002 (14) a Lavatory (Wall Hung) including faucet, P-Trap, and other accessories set 8,557.50 1.00 8,557.50
1002 (15) a Lavatory (Undercounter) including faucet, P-Trap, and other accessories set 7,507.50 7.00 52,552.50
1002 (5) b Water Closet (Flush Valve) including other accessories set 11,760.00 8.00 94,080.00
1002 (9) b Urinal including Flush Valve and other items to complete the work set 7,507.50 2.00 15,015.00
1002 (19) Shower including other necessary accessories to complete the system set 20,422.50 8.00 163,380.00
1002 (32) a Instantaneous Electtric Water Heater (3.5 kw) set 8,085.00 8.00 64,680.00
1002 (21) Faucet including other necessary accessories to complete the system each 5,827.50 1.00 5,827.50
1002 (16) a1.1 Floor Drain, 50 mm dia. (TYPE A) each 945.00 9.00 8,505.00
1002 (16) a2.2 Floor Drain, 75 mm dia. each 1,181.25 1.00 1,181.25
1002 (16) a1.3 Shower Drain, 50 mm dia. each 1,050.00 8.00 8,400.00
1017 (1) b.1 Roof Strainer, 75 mm dia. each 1,522.50 2.00 3,045.00
1002 (35) a3 Floor Cleanout, 100 mm dia. each 1,837.50 8.00 14,700.00
1002 (35) b3 Ground Cleanout, 100 mm dia. each 1,837.50 2.00 3,675.00
SUB-TOTAL 443,598.75
SUBTOTAL COST (PLUMBING AND SANITARY WORKS) 794,015.43
MECHANICAL WORKS (ALL BUILDINGS)
MECHANICAL WORKS
1200 (42) Testing and Commissioning for AC units lot 85,000.00 1.00 85,000.00
SUB - TOTAL 85,000.00
1200 VENTILATION SYSTEM

EF: Wall Mounted Exhaust Fan complete w/ backdraft damper, fan switch,weatherhood and
1200 (5)b.51 other std. accessories. 80cmh(47cfm), 220V, 1ph, 60 hz, TEFC. set 5,722.50
5,722.50 1.00

EF: Wall Mounted Exhaust Fan complete w/ backdraft damper, fan switch,weatherhood and
1200 (5)b.52 set 5,722.50
other std. accessories. 85cmh(50cfm), 220V, 1ph, 60 hz, TEFC.
5,722.50 1.00

EF: Wall Mounted Exhaust Fan complete w/ backdraft damper, fan switch,weatherhood and
1200 (5)b.53 set 16,852.50
other std. accessories. 589cmh(346cfm), 220V, 1ph, 60 hz, TEFC.
16,852.50 1.00

EF: Wall Mounted Exhaust Fan complete w/ backdraft damper, fan switch,weatherhood and
1200 (5)b.54 other std. accessories. 790cmh(464cfm), 220V, 1ph, 60 hz, TEFC. set 19,687.50
19,687.50 1.00

EF: Wall Mounted Exhaust Fan complete w/ backdraft damper, fan switch,weatherhood and
1200 (5)b.55 set 20,907.60
other std. accessories. 875cmh(514cfm), 220V, 1ph, 60 hz, TEFC.
20,907.60 1.00
1200 (43) Testing and Commissioning for Ventilation units lot 26,250.00 1.00 26,250.00
SUB - TOTAL 95,142.60
1202 FIRE PROTECTION SYSTEM
Equipment, See schedule for specifications (to include all other necessary works to make
the unit complete and operational.)
FE: 4.5 kg(10 lbs), ABC Dry Chemical, Siliconized Mono Ammonium Phospate Dry Chemical,
1202 (6) a1 Wall Mounted Multi-Purpose Portable \fire Extinguisher complete w/ Hose and Horn, wall set 14,242.10
bracket, ULFM approved. 7,121.05 2.00
FE: 4.5 kg(10 lbs), Electrically Non-conductive, non contaminating, odorless gas, Wall
1202 (6) a3.1 Mounted Carbon Dioxide Portable fire Extinguisher complete w/ Hose and Horn,UL Listed & set 7,121.05
FM approved. 7,121.05 1.00
1202 (39) Testing and Commissioning Fire Protection System lot 26,250.00 1.00 26,250.00
SUB - TOTAL 47,613.14
1202 FIRE SUPPRESSION SYSTEM NOVEC-1230
TOTAL COST - MECHANICAL WORKS 227,755.74
ELECTRICAL WORKS ( ALL BUILDINGS)
1103 LIGHTING SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 49.14 126.00 6,191.64
1100 (3)a Flexible Metal Conduit (FMC), 15mm dia. meter 32.76 14.00 458.64
1100 (13)a Straight Connector, 15mm dia. piece 42.32 54.00 2,285.01
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 68.25 23.00 1,569.75
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 81.90 20.00 1,638.00
1100 (8)c Square Box, 101mm x 101mm x 54mm, Ga. 16 piece 136.50 10.00 1,365.00
1101 WIRES AND WIRING DEVICES (including connectors, tapes, etc.) -
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 42.59 379.00 16,140.85
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 42.59 150.00 6,388.20
1101 (3) Light Switch, 15A, 1P, 230V, 60Hz, One-Gang, Grounding Type set 197.93 7.00 1,385.48
1101 (5) Light Switch, 15A, 1P, 230V, 60Hz, Three-Gang, Grounding Type set 433.39 2.00 866.78
1101 (15) Single Convenience Outlet/Receptacle (GT), 250V, 15A, 2P (For Emergency Light) set 380.49 7.00 2,663.46
1103 LIGHTING FIXTURES AND LAMPS -
1103 (3)a Type " A ", Round Downlight with 7W LED, 230V, 60Hz, Recessed Mounted. set 1,638.00 17.00 27,846.00
1103 (3)b Type " A1 ", Round Downlight with 16W LED, 230V, 60Hz, Recessed Mounted. set 3,412.50 3.00 10,237.50
1103 (3)h Type " E1 ", Enclosed and Gasketed Luminaire with 40W LED, 230V, 60Hz, Surface Mounted. set 65,520.00
6,552.00 10.00
1103 (3)l Emergency Lighting Fixture, 2 x 2.5W LED Lamp, 230V, 60Hz. set 2,047.50 7.00 14,332.50
1103 (3) Testing and Commissioning lot 40,950.00 1.00 40,950.00
SUB - TOTAL 199,838.80
1102 POWER SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 49.14 213.00 10,466.82
1100 (2)d Intermediate Metal Conduit (IMC), 32mm dia. meter 356.28 12.00 4,275.31
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 68.25 25.00 1,706.25
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 81.90 5.00 409.50
1101 WIRES AND WIRING DEVICES (including connectors, tapes, etc.) -
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 42.59 247.00 10,519.24
1101 (2) b3 Electric Wire, 5.5mm2 THHN/THWN-2 meter 65.37 204.00 13,336.01
1101 (2) b7 Electric Wire, 30mm2 THHN/THWN-2 meter 395.71 56.00 22,159.96
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 42.59 124.00 5,280.91
1101 (2) b3.1 Electric Wire, 5.5mm2 TW (G) meter 65.37 102.00 6,668.00
1101 (2) b4.1 Electric Wire, 8.0mm2 TW (G) meter 102.26 14.00 1,431.70
1101 (16) Duplex Conveniece Outlet/Receptacle (GT), 250V, 15A, 2P, Wall Mounted set 380.49 7.00 2,663.46
Single Convenience Outlet with Ground Fault Circuit Interrupter, 250V, 15A, 2P for Water
1101 (26) set 38,220.00
Heater (WH) 4,777.50 8.00
Single Convenience Outlet with Ground Fault Circuit Interrupter, 250V, 15A, 2P for Hand
1101 (26) set 14,332.50
Dryer (HD) 4,777.50 3.00
1101 (27) Duplex Convenience Outlet with Ground Fault Circuit Interrupter, 250V, 15A, 2P set 5,733.00 5.00 28,665.00
1101 (19) Duplex Conveniece Outlet/Receptacle (GT), 250V, 15A, 2P, Wall Mounted, Weatherproof set 4,095.00
2,047.50 2.00
Panelboard, PP-SR, Main: 100AT/100AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 25KAIC,
Branches: 1 - 30AT/100AF, 3P, MCCB, 8 - 30AT/100AF, 1P, MCCB, 10 - 20AT/100AF, 1P,
1102 (2)4.3A.1 MCCB, 1 - SPD, 240kA/Phase complete with 1 - Digital Power Meter (DPM), 3 - Current set 25,374.75
Limiting Fuse (CLF), 3 - Current Transformer 100/5A, in NEMA 1 Enclosure. , in NEMA 1
Enclosure. (Located at Bldg # 4.3A)
25,374.75 1.00
1102 (36) Testing and Commissioning lot 40,950.00 1.00 40,950.00
SUB-TOTAL 230,554.40
1208 FIRE ALARM SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (2)a Intermediate Metal Conduit (IMC), 15mm dia. meter 126.80 54.00 6,847.36
1100 (3)a Flexible Metal Conduit (FMC), 15mm dia. meter 28.67 3.00 86.00
1100 (13)a Straight Connector, 15mm dia. piece 21.84 6.00 131.04
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 68.25 1.00 68.25
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 81.90 5.00 409.50
1100 (8)c Square Box, 101mm x 101mm x 54mm, Ga. 16 piece 136.50 1.00 136.50
1101 FIRE ALARM WIRES AND CABLES (including connectors, tapes, etc.) -
1101 (2)g1 1.25mm2 Twisted Pair Shielded Cable meter 24.57 44.00 1,081.08
1101 (2) b1 Electric Wire, 2.0mm2 THHN/THWN-2 meter 28.39 31.00 880.15
1208 FIRE ALARM DEVICES AND EQUIPMENT -
1208 (2) Addressable Smoke Detector set 4,777.50 3.00 14,332.50
1208 (6) Addressable Manual Pull Station set 2,457.00 1.00 2,457.00
1208 (4) Addressable Fire Alarm Strobe with Sounder set 2,457.00 1.00 2,457.00
1208 (19)9 Testing and Commissioning lot 81,900.00 1.00 81,900.00

SUB-TOTAL 110,786.38

1105 NETWORK CABLING SYSTEM


1105 (24)8 Testing and Commissioning lot 250,000.00 1.00 250,000.00

SUB-TOTAL 250,000.00

1106 CCTV SYSTEM


1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 49.14 16.00 786.24
1100 (3)a Flexible Metal Conduit (FMC), 15mm dia. meter 28.67 1.00 28.67
1100 (13)a Straight Connector, 15mm dia. piece 21.84 2.00 43.68
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 81.90 1.00 81.90
1105 CCTV WIRES AND CABLES (including connectors, tapes, etc.) -
1105 (7) 0.57mm, 4 Pairs, Cat. 6, Shielded Twisted Pair Cable (STP) (1 roll = 500m) roll 19,110.00 0.03 573.30
1106 CCTV DEVICES AND EQUIPMENT -
1106 (2) IP Based Fixed Dome Type CCTV Camera, 2MP, Indoor set 5,050.50 1.00 5,050.50
1106 (16)8 Testing and Commissioning lot 68,250.00 1.00 68,250.00

SUB-TOTAL 74,814.29
1107(7) Testing and Commissioning lot 65,000.00 1.00 65,000.00
SUB-TOTAL 65,000.00
1108(13).1 Interfacing, Testing and Commissioning lot 50,000.00 1.00 50,000.00
SUB-TOTAL 50,000.00
1101 GROUNDING CONDUCTORS, ELECTRODES AND CONNECTIONS
1109 (4)k Bare Copper Wire, 60mm² Soft Drawn meter 518.78 9.00 4,668.98
1109 (6)e Ground Rod Copper Clad, 20mm dia. x 3m length 4,777.50 3.00 14,332.50
1109 (7) Grounding Test Well piece 8,190.00 1.00 8,190.00
1109 (2) Exothermic Welded Connector set 8,872.50 4.00 35,490.00
1109 (9).1 Testing and Commissioning lot 25,000.00 1.00 25,000.00

SUB-TOTAL 87,681.48

TOTAL COST - ELECTRICAL WORKS 1,068,675.34

GRAND TOTAL 6,254,612.15

General Requirements and Miscellaneaus Expences : 15.00% 938,191.82

Contingencies : 15.00% 938,191.82

Contractor's Profit & Overhead : 10.00% 625,461.22

Value Added Tax (VAT) : 12.00% 750,553.46

TOTAL PROJECT COST : 9,507,010.47


BILL OF QUANTITIES
CONSTRUCTION OF VARIOUS STRUCTURES AND FACILITIES WITHIN THE 100 HECTARE AREA AT BATAAN TECHNOLOGY PARK, MORONG
Project Name : BATAAN ( PHASE 1 PACKAGE 2 )

Location : MORONG, BATAAN


BUILDING 4.3B

UNIT COST BUILDING 4.3B


ITEM NO. DESCRIPTION UNIT (Pesos)
QUANTITY AMOUNT

STRUCTURAL EARTHWORK
803 (1) a Structure Excavation (Common Soil), includes Hauling and Disposal Cost cu.m. 420.00 7,190.10 3,019,842.00
515 (3) Structural Backfilling (using Excavated Materials) cu.m. 367.50 374.18 137,511.15
SUB-TOTAL 3,157,353.15
CONCRETE WORKS
Cast-In Place Concrete, 21 Mpa
900 (1) c1-h Structural Concrete, Bottom Slab, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 403.81 2,098,802.48
Cast-In Place Concrete, 28 Mpa
900 (8)-h Structural Concrete, RC Wall, 28 MPa @ 28 days cu.m. 5,932.50 226.83 1,345,668.98
Cast-In Place Concrete, 10 Mpa
901 (1) Structural Concrete, Lean Concrete, 10 Mpa cu.m. 3,638.25 135.39 492,582.67
Reinforcing Steel, Grade 60
902 (1) b-25 Reinforcing Steel, Bottom Slab, Grade 60 kgs. 77.18 80,762.00 6,232,807.35
902 (1) b-35 Reinforcing Steel, RC Wall, Grade 60 kgs. 77.18 119,244.00 9,202,655.70
Formworks and Falsework
903 (2)-a Formworks and Falseworks, Lean Concrete sq.m. 682.50 15.68 10,701.60
903 (2)-u Formworks and Falseworks, RC Wall sq.m. 682.50 1,441.21 983,625.83
903 (2)-ad Formworks and Falseworks, Bottom Slab sq.m. 682.50 46.91 32,016.07

SUB-TOTAL 20,398,860.67

METAL WORKS
Metal Structures and Accessories, Watch Tower for 3-units (includes HSS 5x5x0.375 Steel
1047 (12) Column, C4x4.5 Steel beam, C3x3 Steel Beam and Steel Rafter, LC100x50x15x2.0 Purlins, lot 0.02 n/a
150x12 Hollow Steel Pipe for Kingpost, connection bolts, connection Plates and other items
to complete the works)

Metal Structures and Accessories, Catwalk, L=183.65m, W=1.30m ( includes A505MPU


1047 (13) Webforge Steel Grating, W8x12 Steel Beam, 2L100x100x8 Steel Support, Baseplates, Anchor lot 0.02 n/a
Bolts and other items to complete the works)
Metal Structures and Accessories, Steel Stairs ( includes A323MPU 32x3 Webforge Steel
1047 (14) Grating, HT152x151x8x11 Steel Column, C10x20 Stringer, Angle Bar Connections, lot 0.02 n/a
Baseplates, Anchor Bolts and other items to complete the works)
SUB-TOTAL 0.00

OTHERS FOR SWIMMING POOL -


Underwater Egress Pool (Provisional Cost) lot 1.00 -
Jumping Platform, including Stairs (Provisional Cost) lot 1.00 -
Zip Line (Provisional Cost) lot 1.00 -
Steel Beam including RC Post (Provisional Cost) lot 1.00 -
In Ground Viewing Area (Provisional Cost) lot 1.00 -
Overhear Catwalk (Provisional Cost) lot 1.00 -
SUB-TOTAL 0.00

SUBTOTAL COST - STRUCTURAL WORKS 23,556,213.82

ARCHITECTURAL WORKS (ALL BUILDINGS)

1016 WATERPROOFING -
1016 (1) b.6 Waterproofing: Cementitous Capillary (Location: Concrete Canopies, Watertank, Elevaror sq.m. 1,051,891.58
Shaft) 892.50 1,178.59
1016 (1) b.8 Fiber Mesh Tile Underlay (Alkali Resistant) sqm. 1,338.75 1,178.59 1,577,837.36
1018 CERAMIC/ GRANITE TILES -
1018 (1) e Glazed Tiles (Wall Finish: Ceramic Tiles, 6mm Thk x 300 x 300mm) (Mariwasa White and sq.m. 807,674.18
Blue for Swimming Pool) 1,732.50 466.19
1018 (2) e Unglazed Tiles (Floor Finish: Ceramic Tiles, 6mm Thk x 300 x 300mm) (Mariwasa White and sq.m. 1,234,233.00
Blue for Swimming Pool) 1,732.50 712.40

SUBTOTAL COST - ARCHITECTURAL WORKS 4,671,636.11


PLUMBING AND SANITARY WORKS ( ALL BUILDINGS)
WATER SYSTEM
Testing and Disinfecting lot 5,250.00 1.00 5,250.00

SUB-TOTAL 5,250.00

SEWER SYSTEM
Testing lot 5,250.00 1.00 5,250.00
SUB-TOTAL 5,250.00

STORM AND DRAINAGE SYSTEM


Testing lot 5,250.00 1.00 5,250.00

SUB-TOTAL 5,250.00

PLUMBING FIXTURES
SUBTOTAL COST (PLUMBING AND SANITARY WORKS) 15,750.00
MECHANICAL WORKS (ALL BUILDINGS)
MECHANICAL WORKS
1200 (42) Testing and Commissioning for AC units lot 157,500.00 1.00 157,500.00
SUB - TOTAL 157,500.00
1200 VENTILATION SYSTEM
1200 (43) Testing and Commissioning for Ventilation units lot 26,250.00 1.00 26,250.00
SUB - TOTAL 26,250.00
1202 FIRE PROTECTION SYSTEM
1202 (39) Testing and Commissioning Fire Protection System lot 15,750.00 1.00 15,750.00
SUB - TOTAL 15,750.00
1202 FIRE SUPPRESSION SYSTEM NOVEC-1230
TOTAL COST - MECHANICAL WORKS 199,500.00
ELECTRICAL WORKS ( ALL BUILDINGS)
1103 (3) Testing and Commissioning lot 31,500.00 1.00 31,500.00
SUB - TOTAL 31,500.00
1102 POWER SYSTEM
1102 (36) Testing and Commissioning lot 31,500.00 1.00 31,500.00
SUB-TOTAL 31,500.00
1208 FIRE ALARM SYSTEM
1208 (19)9 Testing and Commissioning lot 31,500.00 1.00 31,500.00
SUB-TOTAL 31,500.00
1105 NETWORK CABLING SYSTEM
1105 (24)8 Testing and Commissioning lot 31,500.00 1.00 31,500.00
SUB-TOTAL 31,500.00
1106 CCTV SYSTEM
1106 (16)8 Testing and Commissioning lot 31,500.00 1.00 31,500.00
SUB-TOTAL 31,500.00
1107 PUBLIC ADDRESS SYSTEM
1107(7) Testing and Commissioning lot 31,500.00 1.00 31,500.00
SUB-TOTAL 31,500.00
1108 ACCESS CONTROL SYSTEM
1108(13).1 Interfacing, Testing and Commissioning lot 31,500.00 1.00 31,500.00
SUB-TOTAL 31,500.00
1109 GROUNDING SYSTEM
1109 (9).1 Testing and Commissioning lot 31,500.00 1.00 31,500.00

SUB-TOTAL 31,500.00

TOTAL COST - ELECTRICAL WORKS 252,000.00

GRAND TOTAL 28,695,099.93

General Requirements and Miscellaneaus Expences : 15.00% 4,304,264.99

Contingencies : 15.00% 4,304,264.99

Contractor's Profit & Overhead : 10.00% 2,869,509.99

Value Added Tax (VAT) : 12.00% 3,443,411.99

TOTAL PROJECT COST : 43,616,551.89


BILL OF QUANTITIES
CONSTRUCTION OF VARIOUS STRUCTURES AND FACILITIES WITHIN THE 100 HECTARE AREA AT BATAAN TECHNOLOGY PARK, MORONG
Project Name : BATAAN ( PHASE 1 PACKAGE 2 )
Location : MORONG, BATAAN
BUILDING 3

UNIT COST BUILDING 3


ITEM NO. UNIT (Pesos)
QUANTITY AMOUNT
STRUCTURAL EARTHWORK
803 (1) a Structure Excavation (Common Soil), includes Hauling and Disposal Cost cu.m. 420.00 425.64 178,768.80
803 (3) b Foundation Fill, Base Course cu.m. 1,102.50 105.95 116,809.88
515 (3) Structural Backfilling (using Excavated Materials) cu.m. 367.50 468.50 172,173.75
515 (3) a Structural Backfilling (using Excavated Materials Taken from other Structures) cu.m. 551.25 42.96 23,681.70
1000 (1) Soil Poisoning liters 105.00 73.66 7,734.30
1404 (2) Filter Aggregates Materials (Gravel Filter) cu.m. -
SUB-TOTAL 499,168.43

Cast-In Place Concrete, 21 Mpa


900 (1) c1-a Structural Concrete, Column Footings, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 34.20 177,754.50
900 (1) c1-b Structural Concrete, Wall Footings, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 6.52 33,887.70
900 (1) c1-e Structural Concrete, Plant Box Footings, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 1.64 8,523.90
900 (1) c1-g Structural Concrete, Slab On Grade, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 50.87 264,396.83
900 (1) c1-i Structural Concrete, Ramp On Grade, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 1.25 6,496.88
900 (1) c1-j Structural Concrete, Concrete/Entry Steps, Class A (fc=21 MPa) @ 28 days cu.m. 5,197.50 10.73 55,769.18

Cast-In Place Concrete, 28 Mpa


900 (8)-n Structural Concrete, Footing-Tie-Beams, 28 MPa @ 28 days cu.m. 5,932.50 27.01 160,236.83
900 (8)-o Structural Concrete, Roof Beams/Suspended Beams/Girders, 28 MPa @ 28 days cu.m. 5,932.50 68.39 405,723.68
900 (8)-q Structural Concrete, Lintel Beam, 28 MPa @ 28 days cu.m. 5,932.50 2.67 15,839.78
900 (8)-r Structural Concrete, Bond Beam, 28 MPa @ 28 days cu.m. 5,932.50 9.70 57,545.25
900 (8)-s Structural Concrete, Columns/Planted Columns, 28 MPa @ 28 days cu.m. 5,932.50 21.13 125,353.72
900 (8)-t Structural Concrete, Stiffener Columns, 28 MPa @ 28 days cu.m. 5,932.50 37.49 222,409.43
900 (8)-u Structural Concrete, Suspended Slab/Roof Slab, 28 MPa @ 28 days cu.m. 5,932.50 55.74 330,677.55
900 (8)-w Structural Concrete, Concrete Canopy, 28 MPa @ 28 days cu.m. 5,932.50 2.71 16,077.07
900 (8)-z Structural Concrete, Suspended Stairs and Landing, 28 MPa @ 28 days cu.m. 5,932.50 6.76 40,103.70

Reinforcing Steel, Grade 40


902 (1) a-4 Reinforcing Steel, Concrete/Entry Steps, Grade 40 kgs. 74.03 90.26 6,681.50
902 (1) a-9 Reinforcing Steel, Lintel Beam, Grade 40 kgs. 74.03 177.76 13,158.68
902 (1) a-10 Reinforcing Steel, Bond Beam, Grade 40 kgs. 74.03 64.80 4,796.82
902 (1) a-22 Reinforcing Steel, Ramp On Grade, Grade 40 kgs. 74.03 55.32 4,095.06
902 (1) a-25 Reinforcing Steel, Suspended Stairs and Landing, Grade 40 kgs. 74.03 30.25 2,239.26
902 (1) a-26 Reinforcing Steel, Concrete Upstand, Grade 40 kgs. -

Reinforcing Steel, Grade 60


902 (1) b-1 Reinforcing Steel, Column Footings, Grade 60 kgs. 77.18 2,590.56 199,926.47
902 (1) b-3 Reinforcing Steel, Wall Footings, Grade 60 kgs. 77.18 641.95 49,542.49
902 (1) b-4 Reinforcing Steel, Slab On Grade, Grade 60 kgs. 77.18 2,723.82 210,210.81
902 (1) b-5 Reinforcing Steel, Concrete/Entry Steps, Grade 60 kgs. 77.18 644.90 49,770.16
902 (1) b-8 Reinforcing Steel, Footing Tie Beam, Grade 60 kgs. 77.18 5,134.06 396,221.08
902 (1) b-10 Reinforcing Steel, Suspended Beam/Roof Beam/Girders, Grade 60 kgs. 77.18 14,299.11 1,103,533.81
902 (1) b-12 Reinforcing Steel, Lintel Beam, Grade 60 kgs. 77.18 495.75 38,259.51
902 (1) b-13 Reinforcing Steel, Bond Beam, Grade 60 kgs. 77.18 1,139.93 87,974.10
902 (1) b-14 Reinforcing Steel, Columns, Grade 60 kgs. 77.18 12,273.72 947,224.34
902 (1) b-16 Reinforcing Steel, Stiffener Column, Grade 60 kgs. 77.18 4,234.55 326,801.40
902 (1) b-17 Reinforcing Steel, Suspended Slab/Roof Slab, Grade 60 kgs. 77.18 5,103.32 393,848.72
902 (1) b-18 Reinforcing Steel, Concrete Canopy, Grade 60 kgs. 77.18 396.20 30,576.73
902 (1) b-23 Reinforcing Steel, Plant Box Footings, Grade 60 kgs. 77.18 198.59 15,326.18
902 (1) b-31 Reinforcing Steel, Suspended Stairs and Landing, Grade 60 kgs. 77.18 770.16 59,437.10

Formworks and Falsework


903 (2)-b Formworks and Falseworks, Column Footings sq.m. 682.50 62.40 42,588.00
903 (2)-e Formworks and Falseworks, Slab On Grade sq.m. 682.50 23.36 15,943.20
903 (2)-f Formworks and Falseworks, Concrete/Entry Steps sq.m. 682.50 22.55 15,390.38
903 (2)-i Formworks and Falseworks, Footing Tie Beam sq.m. 682.50 179.57 122,556.53
903 (2)-k Formworks and Falseworks, Suspended Beam/Roof Beam/Girders sq.m. 682.50 558.32 381,053.40
903 (2)-m Formworks and Falseworks, Lintel Beam sq.m. 682.50 46.07 31,442.78
903 (2)-n Formworks and Falseworks, Bond Beam sq.m. 682.50 129.46 88,356.45
903 (2)-o Formworks and Falseworks, Columns sq.m. 682.50 273.00 186,322.50
903 (2)-r Formworks and Falseworks, Suspended Slab/Roof Slab sq.m. 682.50 412.84 281,763.30
903 (2)-s Formworks and Falseworks, Concrete Canopy sq.m. 682.50 26.21 17,888.33
903 (2)-ab Formworks and Falseworks, Plant Box Footing sq.m. 682.50 11.20 7,644.00
903 (2)-ae Formworks and Falseworks, Ramp on Grade sq.m. 682.50 2.47 1,685.78
903 (2)-aj Formworks and Falseworks, Suspended Stairs and Landing sq.m. 682.50 36.16 24,679.20
413 (3) a Preformed Expansion Joint Filler with Sealant, 12 mm thick cu.m. 682.50 0.39 266.18
413 (4) a Elastic Sealant on Ø12 mm Backing Rod l.m. 682.50 496.73 339,018.23
SUB-TOTAL 7,417,018.42
METAL WORKS
1047 (2) a Structural Steel, Purlins (LC Sections) kgs. 82.95 3,310.36 274,594.36
1047 (2) d-1 Structural Steel, Truss/Strut (Angle Bar Sections) kgs. 82.95 11,537.09 957,001.62
1047 (2) d-2 Structural Steel, Top Wall Support (Angle Bar Sections) kgs. 82.95 634.61 52,640.90
1047 (2) d-11 Structural Steel, Steel Stair (Angle Bar Sections) kgs. 82.95 188.53 15,638.56
1047 (3) a-1 Metal Structure Accessories, Connection Bolts, ∅12mm x 40 mm Connection Bolts w/ Std ea. 183.75 948.00 174,195.00
Nuts & Washer, ASTM A325
1047 (3) a-8 Metal Structure and Acessories, Stud Anchor, ∅12mm w/ Std Nuts & Washer ea. 236.25 624.00 147,420.00
Metal Structure Accessories, Anchor Bolts, Ø20mm x 400mm w/ Std Nuts & Washer, ASTM
1047 (3) a-21 F1554 (depth of embedment = 250mm) ea. 525.00 174.00 91,350.00
1047 (6) a Metal Structure Accessories, Base Plates (includes non-shrink grout) kgs. 82.95 4,370.88 362,564.50
Metal Structure Accessories, Steel Plates/Connector Plates/Cap Plates/Cover
1047 (6) b Plates/Through Plates/Anchor Plates/Cap Plates/Washer Plates/Shear Plates/Embedded kgs. 82.95 435.82 36,151.27
Plates/Extension Plates
1047 (6) c Metal Structure Accessories, Stiffener Plates kgs. 82.95 122.09 10,127.37
1047 (6) d Metal Structure Accessories, Bent Plates kgs. 82.95 418.60 34,722.87
1047 (6) e Metal Structure Accessories, Gusset Plates kgs. 82.95 2,878.37 238,760.79
1047 (7) b Metal Structure Accessories, Ø12mm Sagrods kgs. 82.95 124.89 10,359.63
Metal Structures and Accessories, Watch Tower for 3-units (includes HSS 5x5x0.375 Steel
1047 (12) Column, C4x4.5 Steel beam, C3x3 Steel Beam and Steel Rafter, LC100x50x15x2.0 Purlins, lot 0.02 n/a
150x12 Hollow Steel Pipe for Kingpost, connection bolts, connection Plates and other items
to complete the works)

Metal Structures and Accessories, Catwalk, L=183.65m, W=1.30m ( includes A505MPU


1047 (13) Webforge Steel Grating, W8x12 Steel Beam, 2L100x100x8 Steel Support, Baseplates, Anchor lot 0.02 n/a
Bolts and other items to complete the works)
Metal Structures and Accessories, Steel Stairs ( includes A323MPU 32x3 Webforge Steel
1047 (14) Grating, HT152x151x8x11 Steel Column, C10x20 Stringer, Angle Bar Connections, lot 0.02 n/a
Baseplates, Anchor Bolts and other items to complete the works)
SUB-TOTAL 2,405,526.86

SUBTOTAL COST - STRUCTURAL WORKS 10,321,713.70

ARCHITECTURAL WORKS (ALL BUILDINGS)


1002 PLUMBING WORKS -
1002 (20) a Facial Mirror (6mm Thk with 25mm Thk Plywood Backing and 25x25mm Tubular Aluminum sq.m. 31,487.40
Trim) 2,205.00 14.28
1002 (38) Liquid Soap Dispenser set 367.50 7.00 2,572.50
1002 (40) Grab Bar set 3,150.00 1.00 3,150.00
1002 (41) Automatic Hand Dryer set 2,572.50 6.00 15,435.00
1002 (43) Urinal Partition, 20mm Thk x 400mm W X 1150mm H set 3,307.50 4.00 13,230.00
1002 (44) Robe Hook set 787.50 2.00 1,575.00
1002 (45) Soap Dish set 367.50 1.00 367.50
1003 (1) e1.1 Ceiling,Gypsum Board on Metal Suspension System ;12mm Thk Ordinary Type sq.m. 1,123.50 203.43 228,553.61
1003 (1) e1.2 Ceiling, Gypsum Board on Metal Suspension System ;12mm Thk Moisture Resistant sq.m. 1,526.70 75.69 115,555.92
1003 (1) e1.5 25mm Shadow Gap l.m. 236.25 513.89 121,406.51
1003 (1) e1.8 Cove Ceiling, using 12mm Thk Ordinary Gypsum Board, H= 200mm x Depth= 200mm, l.m. 30,427.50
Painted Finish 750.00 40.57
1003 (11) a.3.1 Fascia Board, using 15mm Thk Fiber Cement Boad, Painted Finish sq.m. 950.00 85.27 81,006.50
1003 (1) e2 Prepainted Metal Panel, Metal Spandrel Ceiling sq.m. 1,050.00 133.74 140,427.00
1003 (23) a.1 Toilet Partitions, 15mm Thk Solid Grade HPL with Hardware, fittings, fastening and l.s. 106,312.50
anchoring system. (5 cubicles; Location: Building 3) 106,312.50 1.00
1004 (2) a Lockset Series 3400 Function 50 (Office), Grade 1 set 1,837.50 2.00 3,675.00
1004 (2) b Lockset Series 3400 Function 53 (Entry), Grade 1 set 1,837.50 3.00 5,512.50
1004 (2) e Lockset Series 4000, Lever Type, Function 81 (Entrance Lock), Grade 1 set 2,887.50 9.00 25,987.50
1004 (2) f Overhead Surface Door Closer, Grade 1 set 1,312.50 27.00 35,437.50
1004 (2) h Panic Type Threshold set 2,887.50 6.00 17,325.00
1004 (2) k Butt Hinges 100mm x 100 x 3mm (4" x 4") set/pair 1,260.00 4.00 5,040.00
1004 (2) l Butt Hinges 100mm x 114 x 3mm (4" x 4 1/2") set/pair 1,260.00 54.00 68,040.00
1004 (2) n Fire Exit Rim Device (w/ Entry Trim) set 892.50 6.00 5,355.00
1004 (2) w Deadbolt set 850.00 9.00 7,650.00
1004 (2) x Stainless Steel Push Plate (100 x 250 x 2mm thk) set 1,050.00 9.00 9,450.00
1004 (2) aa Door Stopper set 300.00 9.00 2,700.00
1004 (2) cc Stainless Steel Door Pull, 16mm Ø with Kick Base Plate (100mm W x 250mm H x 2mm Thk) set 1,050.00 9.00 9,450.00
1004 (3) c Building Signage; with Text: using 300mm H x 3mm thk Powder Coated Cast Aluminum Sign set 85,000.00
Lettering, fastening and accessories, Bldg 3 85,000.00 1.00
1006 (1) a.2 Hollow Steel Door (45mm Thk, including Door Jamb, Single Leaf ; Type B= 900mm W x sq.m. 126,412.65
2100mm H)) 33,442.50 3.78
1006 (2) b.4 Hollow Steel Door (45mm Thk Flush, with Louver, including Door Jamb, Single Leaf ;Type D= sq.m. 63,206.33
900mm W x 2100mm H)) 33,442.50 1.89
1006 (2) b.5 Hollow Steel Door (45mm Thk Flush, with Louver, including Door Jamb, Single Leaf ;Type D= sq.m. 249,704.00
800mm W x 2100mm H)) 29,726.67 8.40
1006 (2) b.6 Hollow Steel Door (45mm Thk Flush, with Louver, including Door Jamb, Single Leaf ;Type D= sq.m. 114,707.78
700mm W x 2100mm H)) 26,010.83 4.41
1006 (5) a.3 Fire Rated Fire Exit Steel Door (45mm Thk, 1 Hr. Fire Rating, including Door Jamb, Single sq.m. 149,822.40
Leaf; Type C= 800mm W x 2100mm H ) 29,726.67 5.04
1006 (5) a.7 Fire Rated Fire Exit Steel Door (45mm Thk, 1 Hr. Fire Rating, including Door Jamb, Single sq.m. 468,195.00
Leaf; Type E= 1000mm W x 2100mm H ) 37,158.33 12.60
1007 ALUMINUM FRAMED GLASS DOOR -
1007 (1) b.32 Swing Type (6mm Thk Tempered Glass with Frosted Decal, Aluminum Frame Powder Coated sq.m. 48,984.00
Finish, Double Leaf, Type G= 2100mm W x 2150mm H 5,424.58 9.03
Swing Type (6mm Thk Tempered Glass with Frosted Decal, Aluminum Frame Powder Coated
1007 (1) b.33 Finish, Single Leaf, Type H=900mm W x 2150mm H sq.m. 31,090.80
8,033.80 3.87
1007 (1) b.43 Swing Type (12mm Thk Tempered Glass with Frosted Decal, Aluminum Frame Powder sq.m. 38,726.17
Coated Finish, Single Leaf, Type A=2300mm W x 2375mm H 7,092.70 5.46
1008 ALUMINUM GLASS WINDOW -
1008 (1) a.1.2 Sliding Type (6mm Thk Tempered Glass, 2 Equal Panels; Type C= 1600mm W x 1500mm H ) sq.m. 253,344.00
6,597.50 38.40
1008 (1) a.1.3 Sliding Type (6mm Thk Tempered Glass, 4 Equal Panels; Type D= 3600mm W x 1500mm H ) sq.m. 68,328.00
6,326.67 10.80
1008 (1) c.1.26 Awning Type (6mm Thk Tempered Glass, 1 Panel, Type A= 800mm W x 1500mm H) sq.m. 6,597.50 15.60 102,921.00
1008 (1) c.1.28 Awning Type (6mm Thk Tempered Glass, 1 Panel, Type B= 600mm W x 600mm H) sq.m. 9,360.00 2.52 23,587.20
1008 (1) d.1.4 Fixed Type (6mm Thk Tempered Glass, with Transom; 5 Equal Panels, Type A= 4250mm W x sq.m. 31,397.14
2300mm H) 3,210.34 9.78
1008 (1) d.1.5 Fixed Type (6mm Thk Tempered Glass, with Transom; 3 Equal Panels, Type E= 2950mm W x sq.m. 38,641.05
2300mm H) 5,690.88 6.79
1008 (1) d.1.6 Fixed Type (6mm Thk Tempered Glass, with Transom; 4 Equal Panels,Type F= 3700mm W x sq.m. 40,523.60
2300mm H) 4,761.88 8.51
1010 WOODEN DOORS AND WIINDOWS -
1010 (1) c Wooden Door Jamb (45mm x 900mm W x 2150mm H) set 2,661.75 3.00 7,985.25
Wooden Doors, Wood Panel (45mm Thk Flush Hollow Core, Single Leaf Type F= 800mm W x
1010 (2) a.24 2100mm H) sq.m. 173,365.92
11,466.00 15.12
1014 PREPAINTED METAL SHEETS -
Preformed Prepainted Metal Roofing, Galvalume Ga. 24, including Rain Drip Mould Stopper,
1014 (1) c.5 Ga.24, bended materials, flashings, ridge roll and other attachment accessories necessary to sqm. 15,052,803.68
complete work. (DN Hi Rib 1030) 33,442.50 450.11
1016 WATERPROOFING -
1016 (1) b.1 Waterproofing: Elastomeric Membrane Waterproofing, Burried Type (60 mils) sq.m. 1,102.50 141.73 156,257.32
1016 (1) b.2 Waterproofing: Elastomeric Membrane Waterproofing, Exposed Type (Traffic Type) sq.m. 1,102.50 54.33 59,898.83
1016 (1) b.3 Waterproofing: Elastomeric Membrane Waterproofing (40 mils on Suspended Toilets) sq.m. 28,885.50
735.00 39.30
1016 (3) Concrete Sealer sq.m. 472.50 43.06 20,345.85
1018 CERAMIC/ GRANITE TILES -
1018 (1) a Glazed Tiles (Wall Finish: Ceramic Tiles, 6mm Thk x 300 x 300mm) sq.m. 1,732.50 217.76 377,269.20
1018 (2) a Unglazed Tiles (Floor Finish: Ceramic Tiles, 6mm Thk x 300 x 300mm) sq.m. 1,732.50 75.85 131,410.13
1018 (3) e 20mm Thk Natural Granite Countertop Slab with 200mm H Backsplash & 200mm Skirting l.m. 60,501.00
(Location: Toilets, if applicable) 4,515.00 13.40
1018 (8) a Floor Finish: Homogeneous Tiles, 10mm Thk x 600 x 600mm sq.m. 1,995.00 613.50 1,223,932.50
1018 (8) c Floor Finish: HomogeneousTiles, 10mm Thk x 400 x 400mm sq.m. 2,205.00 70.63 155,739.15
1018 (9) Base Finish: 100mm H Homogeneous Tile Base l.m. 420.00 41.45 17,409.00
1021 CEMENT FLOOR FINISH -
1021 (1) a Cement Floor Finish, Plain sq.m. 451.50 112.60 50,838.90
1021 (14) b 50mm thk. Concrete Topping with Wiremesh Reinforcement sq.m. 835.18 128.68 107,471.03
1027 CEMENT PLASTER FINISH/ DECORATIVE STONE -
1027 (1) a Cement Plaster Finish (on Concrete Masonry Units) sq.m. 661.50 1,547.97 1,023,982.16
1027 (1) a.1 Cement Plaster Finish (on Concrete Structural Members) sq.m. 661.50 255.09 168,742.04
1027 (1) b.1 Cement Plaster Finish: 20mm Ø Groove Liner l.m. 150.00 50.28 7,542.00
1027 (1) c.1 Cement Plaster Finish: Exposed Construction, Soffit of Slab (Smooth Cement Finish) sq.m. 661.50 123.25 81,529.88
1027 (1) d.4 Cement Plaster Finish: Drip Mould, 20mm Ø l.m. 150.00 61.91 9,286.50
1027 (3) a Decorative Stone Wall Cladding (Natural Finish) sq.m. 2,500.00 163.68 409,200.00
1030 ACOUSTIC CEILING -
1030 (1) a.1 19mm Thk x 600 x 600mm Ceiling Panel sq.m. 997.50 440.82 439,717.95
1032 PAINTING, VARNISHING AND OTHER RELATED WORKS -
1032 (1) a.2 Painting on Concrete, Exterior sq.m. 577.50 457.32 264,102.30
1032 (1) a.3 Painting on Concrete, Interior sq.m. 420.00 895.57 376,139.40
1032 (1) a.6 Painting on Concrete: Epoxy Floor Coating sq.m. 682.50 112.60 76,849.50
1032 (1) a.8 Painting on Masonry/ Concrete :Exposed Construction, Soffit of Slab sq.m. 420.00 123.25 51,765.00
1032 (1) b.2 Painting on Works, Ducco Finish sq.m. 420.00 43.34 18,202.80
1032 (1) c.2 Painting on Steel: Steel Doors and Louvers sq.m. 787.50 101.56 79,978.50
1032 (6) Painting Works: Painting on Gypsum Board Ceiling, Flat Finish sq.m. 420.00 279.12 117,230.40
1034 DAMP PROOFING -
1034 (1) b Damp proofing : Polyethylene Sheet Vapor Barrier, 6mils sq.m. 200.00 509.70 101,940.00
1038 REFLECTIVE INSULATION -
1038 (2) Blanket Insulation, R= 19 with Wiremesh Reinforcement; With Foil on One Side (Rockwool sq.m. 590,769.38
Insulation) (Location: Roofing) 1,312.50 450.11
1039 ALUMINUM CLADDING -
1039 (1) Aluminum Cladding, 4.0mm Thk sq.m. 3,500.00 34.10 119,350.00
1041.0 GYPSUM BOARD -
1041 (1) a Gypsum Board for Walls (1-16mm Thk Ordinary Gypsum Board Wall on 100mm thk Metal sq.m. 156,674.59
Stud Framing, 2-Face) with 75mm Thk Sound Attenuation Blanket 1,146.88 136.61
1041 (1) c Gypsum Board for Walls (1-16mm Thk Ordinary Gypsum Board Wall on 100mm thk Metal sq.m. 5,239.06
Stud Framing, 1-Face) 748.44 7.00
1046 MASONRY WORKS -
1046 (2) a.1 CHB Non Load Bearing (including Reinforcing Steel), 100mm thk sq.m. 1,365.00 515.02 703,002.30
1046 (2) a.2 CHB Non Load Bearing (including Reinforcing Steel), 150mm thk. sq.m. 1,365.00 513.92 701,500.80
1047 METAL STRUCTURE -
1047 (11) p Metal Structures, 38 x 38 x 3mm Thk Angular Bar Steel Nosing l.m. 131.25 56.30 7,389.38
1051 RAILING -
Floor Mounted Stainless Steel Pipe Railings, 38mm Ø Top Rail with 3-38mm Ø Sub-railing;
1051 (5) a.1 38mm Ø Pipe Post, all fastening accessories needed to complete work; H=1075mm l.m. 51,072.00
(Location: Fire Exit Stair 1 & 2, Building 3) 9,975.00 5.12
Floor Mounted Stainless Steel Pipe Railings, 38mm Ø Top Rail with 3-38mm Ø Sub-railing;
1051 (5) a.2 38mm Ø Pipe Post, all fastening accessories needed to complete work; H=1000mm l.m. 51,072.00
(Location: Fire Exit 1 & 2, Building 3) 9,975.00 5.12
Floor Mounted Stainless Steel Pipe Railings, 38mm Ø Top Rail with 1-38mm Ø Sub-railing;
1051 (5) a.3 38mm Ø Pipe Post, all fastening accessories needed to complete work; H=900mm (Location: l.m. 62,842.50
PWD Ramp and Entry Porch, Building 3) 9,975.00 6.30
SUBTOTAL COST - ARCHITECTURAL WORKS 26,320,954.23
PLUMBING AND SANITARY WORKS ( ALL BUILDINGS)
WATER SYSTEM
Hot & Cold Water Line
1002 (2) e3.1 50 mm dia. meter 1,074.94 18.00 19,348.88
1002 (2) d3.1 40 mm dia. meter 684.45 3.00 2,053.35
1002 (2) c3.1 32 mm dia. meter 451.91 5.00 2,259.56
1002 (2) b3.1 25 mm dia. meter 263.25 16.00 4,212.00
1002 (2) a3.1 20 mm dia. meter 170.24 24.00 4,085.64
1002 (2) 3.1 15 mm dia. meter 126.36 41.00 5,180.76
1002 (2) e3.2 50 mm dia. meter 1,074.94 2.00 2,149.88
1002 (2) d3.2 40 mm dia. meter 684.45 11.00 7,528.95
1002 (2) c3.2 32 mm dia. meter 451.91 2.00 903.83
1002 (2) b3.2 25 mm dia. meter 263.25 11.00 2,895.75
1002 (2) a3.2 20 mm dia. meter 170.24 24.00 4,085.64
1002 (2) 3.2 15 mm dia. meter 126.36 30.00 3,790.80
1002 (28) a5 Gate Valve, 40 mm dia. each 2,121.10 2.00 4,242.20
1002 (28) a4 Gate Valve, 32 mm dia. each 1,576.78 1.00 1,576.78
1002 (28) a3 Gate Valve, 25 mm dia. each 1,178.75 1.00 1,178.75
1002 (28) a2 Gate Valve, 20 mm dia. each 913.39 3.00 2,740.17
1002 (23) f.1 Water Meter Assembly, 50 mm dia, includes Gate Valve, Check Valve, G.I Pipe and fittings piece 22,755.49
and other accessories to complete the system 22,755.49 1.00
1002 (1) f.1 50 mm dia. meter 180.43 3.00 541.28
Testing and Disinfecting lot 25,000.00 0.02 532.59

SUB-TOTAL 92,062.29

SEWER SYSTEM
1001 (1) a3.1 100 mm dia. meter 522.11 72.00 37,592.10
1001 (1) a2.1 75 mm dia. meter 391.95 32.00 12,542.40
1001 (1) a1.1 50 mm dia. meter 182.81 32.00 5,850.00
1001 (1) a3.2 100 mm dia. meter 522.11 20.00 10,442.25
1001 (1) a2.2 75 mm dia. meter 391.95 7.00 2,743.65
1001 (1) a1.2 50 mm dia. meter 182.81 8.00 1,462.50
1001 (1) a3.3 100 mm dia. meter 522.11 5.00 2,610.56
1001 (1) a2.3 75 mm dia. meter 391.95 5.00 1,959.75
1001 (1) a1.3 50 mm dia. meter 182.81 1.00 182.81
Testing lot 25,000.00 0.02 532.59

SUB-TOTAL 75,918.62

VENT SYSTEM
1001 (1) a1.4 50 mm dia. meter 182.81 64.00 11,700.00
1001 (1) a1.5 50 mm dia. meter 182.81 66.00 12,065.63
1001 (1) a2.6 75 mm dia. meter 391.95 8.00 3,135.60
1001 (1) j1 50 mm dia. set 1,620.00 1.00 1,620.00
1001 (1) k2 75 mm dia. set 1,282.50 1.00 1,282.50

SUB-TOTAL 29,803.73

STORM AND DRAINAGE SYSTEM


1001 (1) c6.1 250 mm dia. meter 2,827.74 1.00 2,827.74
1001 (1) a5.7 200 mm dia. meter 1,715.51 38.00 65,189.48
1001 (1) a4.7 150 mm dia. meter 1,118.81 43.00 48,108.94
1001 (1) a4.8 150 mm dia. meter 1,118.81 3.00 3,356.44
1001 (1) a4.9 150 mm dia. meter 1,118.81 17.00 19,019.81
1001 (1) f1 50 mm dia. meter 182.81 5.00 914.06
Junction Box including excavation, backfill, disposal, gravel bedding, concrete, rebars,
1001 (7) a formworks, and other accessories to complete the works each 573,300.00
81,900.00 7.00
Testing lot 25,000.00 0.02 532.59

SUB-TOTAL 713,249.06

PLUMBING FIXTURES
1002 (14) a Lavatory (Wall Hung) including faucet, P-Trap, and other accessories set 8,525.00 2.00 17,050.00
1002 (15) a Lavatory (Undercounter) including faucet, P-Trap, and other accessories set 7,475.00 10.00 74,750.00
1002 (5) a Water Closet (Flush Tank) including other accessories set 14,325.00 11.00 157,575.00
1002 (9) b Urinal including Flush Valve and other items to complete the work set 7,475.00 5.00 37,375.00
1002 (11) a.2 Kitchen Sink (Single Bowl) including P-trap, and other accessories set 7,375.00 2.00 14,750.00
1001 (19) a Grease Trap Cap = 5 gpm set 11,700.00 1.00 11,700.00
1002 (16) a1.1 Floor Drain, 50 mm dia. (TYPE A) each 937.50 13.00 12,187.50
1017 (1) d.2 Roof Drain, 150 mm dia. each 2,192.50 2.00 4,385.00
1017 (4) d.1 Deck Drain, 150 mm dia. each 2,192.50 2.00 4,385.00
1017 (5) a Planters Drain, 50 mm dia. each 1,510.00 2.00 3,020.00
1002 (35) a3 Floor Cleanout, 100 mm dia. each 1,825.00 18.00 32,850.00
1002 (35) a2 Floor Cleanout, 75 mm dia. each 1,510.00 7.00 10,570.00
1002 (35) b5 Ground Cleanout, 200 mm dia. each 1,825.00 1.00 1,825.00
1002 (35) d4 Wall Cleanout, 150 mm dia. each 2,192.50 4.00 8,770.00
1002 (35) d3 Wall Cleanout, 100 mm dia. each 1,825.00 1.00 1,825.00
SUB-TOTAL 393,017.50
SUBTOTAL COST (PLUMBING AND SANITARY WORKS) 1,304,051.20
MECHANICAL WORKS (ALL BUILDINGS)
MECHANICAL WORKS
1200 AIR CONDITIONING SYSTEM

1200 (13)a3.3 FCU/ACCU: 2.637KWr (0.75 TR), Wall Mounted DX unit c/w disconnect switch, thermostat, set 118,790.00
remote controller, equipment support and other standard accessories. 230V, 1ph, 60hz
59,395.00 2.00
FCU/ACCU: 5.28KWr(1.5TR), Wall Mounted Inverter Type c/w temperature controller, fan
1200 (13)a3.5 speed switch, remote thermostat, eqpt. support, and other std. accessories, 230V, 1ph, set 375,567.50
60hz 75,113.50 5.00
FCU/ACCU: 6.4KWr(1.82TR), Wall Mounted Inverter Type c/w temperature controller, fan
1200 (13)a3.7 speed switch, remote thermostat, eqpt. support, and other std. accessories, 220V, 1ph, set 163,849.70
60hz 81,924.85 2.00
FCU/ACCU: 10.5 KWr (3.0 TR) Ceiling Cassete Type Indoor Unit, c/w 3-speed selector, Fresh
1200 (13)a3.11.12 Air Inlet and Wireless remote Contorl. Standard accessories to make the unit complete & set 2,007,850.00
the unit shall be the same manufacturer of ACCU. 154,450.00 13.00
1200 (13)a3.16 FCU/ACCU: 10.55KWr (3.0TR) Floor Mounted DX Unit c/w disconnect switch, set 495,742.50
thermostat/remote controller, equipment support and other standard accessories. 165,247.50 3.00
FCU/ACCU: 10.55KWr (3.0 TR) Ceiling mounted type dx unit c/w disconnect switch,
1200 (13)a3.28 thermostat/remote controller, equipment support and other standard accessories. 230V, set 4,422,600.00
1ph, 60hz 157,950.00 28.00
MULTI SPLIT INVERTER TYPE - (OUTDOOR UNIT) -
MULTI SPLIT INVERTER TYPE - (INDOOR UNIT) -
ACCU: 22.4KWr (6.37 TR) Floor mounted VRF air cooled condensing unit complete with
1200 (13)b3.4 condenser fan, compressor, isolating valves, filter dryer, moisture indicator, disconnect set 378,795.00
switch, electrical connection, equipment support, anti-corrosion protection and standard
accessories.
189,397.50 2.00
ACCU: 14.0KWr (3.98 TR) Floor mounted VRF air cooled condensing unit complete with
1200 (13)b3.5 condenser fan, compressor, isolating valves, filter dryer, moisture indicator, disconnect set 483,300.00
switch, electrical connection, equipment support, anti-corrosion protection and standard
accessories.
161,100.00 3.00
DEDICATED OUTDOOR AIR SYSTEM - VRF SYSTEM (INDOOR UNIT) -
DOAS: 14.0KWr (3.98 TR) Ceiling mounted ducted type VRV/VRF unit c/w vfd, disconnect
1200 (13)b4.4 switch, thermostat, remote controller, equipment support and other standard accessories set 491,400.00
to make the unit complete. 245,700.00 2.00
Note: Standard accessories for the AC units are included (Remote controllers, filters, drain -
Pump kits, filter chambers, Y-joints & T-joints).
1200 (15)a Refrigerant Copper Pipe, Type L, 6.4 mmØ meter 256.36 158.00 40,504.88
1200 (15)b Refrigerant Copper Pipe, Type L, 9.5mmØ meter 316.68 414.00 131,105.52
1200 (15)c Refrigerant Copper Pipe, Type L, 12.7 mmØ meter 501.41 174.00 87,245.34
1200 (15)d Refrigerant Copper Pipe, Type L, 15.88mmØ meter 716.30 390.00 279,357.00
1200 (16)a Refrigerant Copper Pipe, Rubber Insulation, 19mm thick x 6.4 mmØ meter 45.24 198.00 8,957.52
1200 (16)b Refrigerant Copper Pipe, Rubber Insulation, 25mm thick x 9.5 mmØ meter 67.18 414.00 27,813.10
1200 (16)c Refrigerant Copper Pipe, Rubber Insulation, 25mm thick x 12.7 mmØ meter 80.24 174.00 13,962.53
1200 (16)d Refrigerant Copper Pipe, Rubber Insulation, 25mm thick x 15.88 mmØ meter 103.68 390.00 40,433.25
1200 (17)a Pipe Cladding, Aluminum, 56.4mmØ meter 1,951.95 60.00 117,117.00
1200 (17)b Pipe Cladding, Aluminum, 59.5mmØ meter 2,047.50 192.00 393,120.00
1200 (17)c Pipe Cladding, Aluminum, 62.7mmØ meter 2,252.25 54.00 121,621.50
1200 (17)d Pipe Cladding, Aluminum, 65.88mmØ meter 2,457.00 180.00 442,260.00
1200 (20) Thermostat set 1,812.50 25.00 45,312.50
1002 (7) a3 PVC Pipe (blue), 25 mmØ, Condensate Drain meter 64.96 36.00 2,338.56
1002 (7) a4 PVC Pipe (blue), 32 mmØ, Condensate Drain meter 90.94 24.00 2,182.66
1002 (7) a5 PVC Pipe (blue), 40 mmØ, Condensate Drain meter 104.75 24.00 2,513.95
1002 (7) a7 PVC Pipe (blue), 65 mmØ, Condensate Drain meter 235.48 36.00 8,477.28
1200 (22)b Drain Pipe Insulation, 19mm thick Closed Cell Rubber , 25mm Ø meter 387.62 36.00 13,954.26
1200 (22)c Drain Pipe Insulation, 19mm thick Closed Cell Rubber , 32mm Ø meter 503.90 24.00 12,093.70
1200 (22)d Drain Pipe Insulation, 19mm thick Closed Cell Rubber , 40mm Ø meter 519.22 24.00 12,461.18
1200 (22)f Drain Pipe Insulation, 19mm thick Closed Cell Rubber , 65mm Ø meter 692.17 36.00 24,918.19
1200 (23)a.2 Floor Cleanout, 65mmØ set 1,087.50 1.00 1,087.50
1200 (23)b.4 Cleanout, 40mmØ set 50.75 4.00 203.00
1200 (26) Refrigerant Piping and Equipment Connection set 54,600.00 50.00 2,730,000.00
1200 (27) Vacuum Cleaning and pipe charging meter 682.50 1,176.00 802,620.00
1200 (28) Roughing ins & Control wiring for Thermostat control meter 2,047.50 600.00 1,228,500.00
1200 (29)f Galvanized Steel Ductwork, Ga 26 sq.m. 303.67 63.59 19,310.38
1200 (29)g.1 Duct Insulation, 25 mm thick, rigid mineral fiber 32kg/m3 density w/ Aluminum Foil sq.m. 210.25 63.59 13,369.80
1200 (34)d.1 Outside Air Register, 150 x 150 set 580.00 9.00 5,220.00
1200 (34)d.14 Outside Air Register, 300 x 300 set 942.50 2.00 1,885.00
1200 (34)g.3 Volume Damper, 150 x 150 set 580.00 9.00 5,220.00
1200 (34)g.5 Volume Damper, 200 x 150 set 580.00 1.00 580.00
1200 (34)g.9 Volume Damper, 300 x 150 set 942.50 1.00 942.50
1200 (34)m.18 Outside Air Louver, 850 x 300 set 4,640.00 1.00 4,640.00
1200 (42) Testing and Commissioning for AC units lot 150,000.00 1.00 150,000.00
SUB - TOTAL 15,729,222.80
1200 VENTILATION SYSTEM
EF: Centrifugal Ceiling Cassette Type Exhaust Fan complete w/ backdraft damper,
1200 (5)a.2.1 equipment support, fan Switch, vibration isolator and other std . accessories. 85cmh(50 set 34,800.00
cfm) 0.25 in. Wg, 230V, 1ph, 60 hz. 6,960.00 5.00
EF: Centrifugal Ceiling Cassette Type Exhaust Fan c/w backdraft damper, equipment
1200 (5)a.5.1 supports, intake grille, fan switch, vibration isolators & other standard accessories. set 18,015.00
170cmh(100 cfm) 0.25 in. Wg, 230V, 1ph, 60 hz. 9,007.50 2.00
EF: Centrifugal Ceiling Cassette Type Exhaust Fan c/w backdraft damper, equipment
1200 (5)a.10 supports, intake grille, fan switch, vibration isolators & other standard accessories. set 33,349.20
340cmh(200cfm), 47w, 230v, 1Ø, 60Hz, ODP. 16,674.60 2.00
EF: Centrifugal ceiling cassette type exhaust fan c/w backdraft damper, equipment supports,
1200 (5)a.38 intake grille, vibration isolators, & other standard accessories. 170cmh(100 cfm) 0.25 in. set 18,015.00
Wg, 230V, 1ph, 60 hz, TEFC. 9,007.50 2.00
EF: Centrifugal ceiling cassette type exhaust fan c/w backdraft damper, equipment supports,
1200 (5)a.39 intake grille, vibration isolators, & other standard accessories. 306cmh(180 cfm) 0.25 in. set 24,945.00
Wg, 230V, 1ph, 60 hz, ODP. 12,472.50 2.00
EF: Wall Mounted Propeller Type Exhaust Fan complete w/ gravity shutter
1200 (5)b.31 damper,equipment supports, insect screen, disconnect switch and other std. accessories. set 16,513.50
119 CMH (70 CFM), 230V, 1Ø, 60HZ, ODP. 8,256.75 2.00
1200 (32)a PVC Duct, 100mm Ø meter 45.00 -
1200 (32)b PVC Duct, 150mm Ø meter 1,118.81 30.00 33,564.38
1200 (33)a Vent Cap w/ insect screen, 100mmØ set 2,025.00 9.00 18,225.00
1200 (33)b Vent Cap w/ insect screen, 150mmØ set 2,430.00 30.00 72,900.00
1200 (43) Testing and Commissioning for Ventilation units lot 25,000.00 1.00 25,000.00
SUB - TOTAL 295,327.08
1202 FIRE PROTECTION SYSTEM

Fire Hose Cabinet: Class II, Recessed Mounted, made from Gage 18 steel construction
housing w/ alum frame and glass door, continuous steel hinge. Cabinet shall contain Ø40
cast brass angle valve w/ 30m of Ø40 Polyurethane single lined jacketed fire hose, spray fog
1202 (5)a.2 nozzle, brass nipple and coupling, hose rack swivel type with pin and water stop, NST thread set 62,775.00
for fire hose cabinet to contain one(1) 4.5 kg ABC Chemical Fire Extinguisher OF 4A:80B:C UL
Rating, Pick Head Fire Ax w/ Fiber Glass Handle .'
20,925.00 3.00
FE: 4.5 kg(10 lbs), ABC Dry Chemical, Siliconized Mono Ammonium Phospate Dry Chemical,
1202 (6) a1 Wall Mounted Multi-Purpose Portable \fire Extinguisher complete w/ Hose and Horn, wall set 42,621.28
bracket, ULFM approved. 7,103.55 6.00
FE: 4.5 kg(10lbs),C02,Chromed Brass EPA Approved Clean Agent, Wall Mounted Multi-
1202 (6) a3.2 purpose Portable Fire Extinguisher complete w/ Hose and nozzle, wall bracket, UL Listed & set 35,244.16
FM approved. 17,622.08 2.00
FE: 15.19kg(33.5lbs), Wet Chemical,10B:C, Potassium Acetate based agent wet chemical
1202 (6) a7 wall mounted Portable Fire Extinguisher c/w hose and spray nozzle, wall bracket, UL Listed set 57,824.25
& FM approved. 28,912.12 2.00
Underground Fire Water HDPE Pipes SDR 9 -
1202 (62)c HDPE Pipes SDR 9, 160mmØ meter 277.99 6.00 1,667.95
1202 (40) Warning Tape meter 47.25 6.00 283.50
1202 (67)c2 Steel Ring Flange, 150mmØ ea. 952.53 1.00 952.53
1603 (2)e.2 HDPE / Steel Adaptor Coupling, 160mmØ ea. 1,700.54 1.00 1,700.54
1202 (63)c Elbow, 160mmØ x 90 deg. ea. 2,786.40 1.00 2,786.40
1202 (67)d1 Bolts, Nut & washer, 7/8 inches dia. ea. 60.75 16.00 972.00
Civil Works -
103 (1) a8 Structure Excavation, Common Soil (Mechanical Works), includes Hauling Cost cu.m. 420.00 12.32 5,174.40
515 (3) Structural Backfilling (using excavated materials) cu.m. 367.50 8.57 3,149.48
407 (8) Lean Concrete, Class B, 16.50 Mpa cu.m. 3,638.25 0.04 145.53
404 (1) a Reinforcing Steel, Grade 40 kgs. 74.03 2.42 179.14
B.I. Steel Pipe, ERW, Sched 40 -
1202 (11)d B.I. Steel Pipe, ERW, Sched 40, 40mmØ meter 488.20 6.00 2,929.20
1202 (11)f B.I. Steel Pipe, ERW, Sched 40, 65mmØ meter 1,071.06 48.00 51,411.02
1202 (11)i B.I. Steel Pipe, ERW, Sched 40, 150mmØ meter 3,929.69 6.00 23,578.13
1202 (14)c 4-Way Sway Brace, 150mmØ ea. 1,620.00 1.00 1,620.00
1202 (15)c Clevis Hanger, 40mmØ ea. 64.80 3.00 194.40
1202 (15)e Clevis Hanger, 65mmØ ea. 103.28 14.00 1,445.85
1202 (16)e Mechanical Groove Coupling, 65mmØ ea. 492.08 1.00 492.08
Alarm Check Valve Assembly -
Valves and Accessories -
1202 (7)a Siamese Fire Dept. Connection, Ø65 x Ø65 x Ø100 set 16,809.00 1.00 16,809.00
1202 (20)h Check Valve, 100mmØ set 16,365.90 1.00 16,365.90
1202 (38) Pipe paintings & singnages sq.m. 607.50 15.00 9,112.50
1202 (39) Testing and Commissioning Fire Protection System lot 15,000.00 1.00 15,000.00
SUB - TOTAL 354,434.25
1202 FIRE SUPPRESSION SYSTEM NOVEC-1230
Equipment, See schedule for specifications (to include all other necessary works to make
the unit complete and operational.)
Provide and Install Novec 1230 Pre-engineered automatic fire suppression system using
novec 1230 clean agent, c/w agents container, container's supports, discharge spray
1202 (48)a.1.1 nozzles, solenoid valves, actuator, control panel for detection, alarm devices, cross zoned set 485,940.00
smoke detectors, controller, wiring, piping and other standard accessories, ul listed and fm
approved at Records Room [3-113] (18.85 cu.m.).
485,940.00 1.00

Provide and Install Novec 1230 Pre-engineered automatic fire suppression system using
novec 1230 clean agent, c/w agents container, container's supports, discharge spray
1202 (48)a.1.2 nozzles, solenoid valves, actuator, control panel for detection, alarm devices, cross zoned set 546,000.00
smoke detectors, controller, wiring, piping and other standard accessories, ul listed and fm
approved at Records Room [3-205] (20.34 cu.m.).
546,000.00 1.00

Provide and Install Novec 1230 Pre-engineered automatic fire suppression system using
novec 1230 clean agent, c/w agents container, container's supports, discharge spray
1202 (48)a.1.3 nozzles, solenoid valves, actuator, control panel for detection, alarm devices, cross zoned set 546,000.00
smoke detectors, controller, wiring, piping and other standard accessories, ul listed and fm
approved at Telecom Room [3-213] (23.52 cu.m.).
546,000.00 1.00
SUB - TOTAL 1,577,940.00
TOTAL COST - MECHANICAL WORKS 17,956,924.12
ELECTRICAL WORKS ( ALL BUILDINGS)
1103 LIGHTING SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 49.14 765.00 37,592.10
1100 (3)a Flexible Metal Conduit (FMC), 15mm dia. meter 74.39 377.00 28,045.97
1100 (13)a Straight Connector, 15mm dia. piece 21.84 502.00 10,963.68
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 68.25 99.00 6,756.75
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 81.90 225.00 18,427.50
1100 (8)c Square Box, 101mm x 101mm x 54mm, Ga. 16 piece 136.50 9.00 1,228.50
1101 WIRES AND WIRING DEVICES (including connectors, tapes, etc.) -
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 42.59 2,508.00 106,810.70
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 42.59 1,191.00 50,722.31
1101 (3) Light Switch, 15A, 1P, 230V, 60Hz, One-Gang, Grounding Type set 624.75 28.00 17,493.00
1101 (4) Light Switch, 15A, 1P, 230V, 60Hz, Two-Gang, Grounding Type set 715.31 3.00 2,145.94
1101 (5) Light Switch, 15A, 1P, 230V, 60Hz, Three-Gang, Grounding Type set 805.88 1.00 805.88
1101 (3) Light Switch, 15A, 1P, 230V, 60Hz, One-Gang, Grounding Type For EF set 624.75 15.00 9,371.25
1101 (15) Single Convenience Outlet/Receptacle (GT), 250V, 15A, 2P (For Emergency Light) set 765.19 26.00 19,894.88
1103 LIGHTING FIXTURES AND LAMPS -
1103 (3)a Type " A ", Round Downlight with 7W LED, 230V, 60Hz, Recessed Mounted. set 1,638.00 66.00 108,108.00
1103 (3)b Type " A1 ", Round Downlight with 16W LED, 230V, 60Hz, Recessed Mounted. set 3,412.50 40.00 136,500.00
1103 (3)d Type " B ", 10W LED Round Downlight, 230V, 60Hz, Surface Mounted. set 887.25 9.00 7,985.25
Type " J ", Troffer type luminaire with 2 x 17W LED tube and prismatic diffuser, 230V, 60Hz,
1103 (3)t recessed mtd set 496,314.00
4,914.00 101.00
1103 (3)x Type " L ", 75W surface mtd wall lamp, 230V, 60Hz. set 6,142.50 9.00 55,282.50
1103 (3)l Emergency Lighting Fixture, 2 x 2.5W LED Lamp, 230V, 60Hz. set 2,047.50 26.00 53,235.00
1103 (3)m Exit Light in Aluminum Housing with High Grade Replaceable Acrylic Panel, Removable set 18,427.50
Directional Indicators, Letters 6" Height with 3/4" Stroke. 2,047.50 9.00
1103 (3) Testing and Commissioning lot 81,900.00 1.00 81,900.00
SUB - TOTAL 1,268,010.70
1102 POWER SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 49.14 1,425.00 70,024.50
1100 (2)c Intermediate Metal Conduit (IMC), 25mm dia. meter 278.62 15.00 4,179.36
1100 (2)f Intermediate Metal Conduit (IMC), 50mm dia. meter 546.16 12.00 6,553.91
1100 (2)j Intermediate Metal Conduit (IMC), 100mm dia. meter 1,609.19 18.00 28,965.41
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 68.25 84.00 5,733.00
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 81.90 52.00 4,258.80
1101 WIRES AND WIRING DEVICES (including connectors, tapes, etc.) -
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 42.59 1,640.00 69,844.32
1101 (2) b3 Electric Wire, 5.5mm2 THHN/THWN-2 meter 65.37 1,294.00 84,592.12
1101 (2) b6 Electric Wire, 22mm2 THHN/THWN-2 meter 269.72 60.00 16,183.44
1101 (2) b11 Electric Wire, 80mm2 THHN/THWN-2 meter 975.98 40.00 39,039.00
1101 (2) b16 Electric Wire, 250mm2 THHN/THWN-2 meter 2,745.33 124.00 340,420.79
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 42.59 820.00 34,922.16
1101 (2) b3.1 Electric Wire, 5.5mm2 TW (G) meter 65.37 662.00 43,276.65
1101 (2) b6.1 Electric Wire, 22mm2 TW (G) meter 269.72 10.00 2,697.24
1101 (2) b7.1 Electric Wire, 30mm2 TW (G) meter 395.71 31.00 12,267.12
1101 (15) Single Convenience Outlet/Receptacle (GT), 250V, 15A, 2P set 712.69 7.00 4,988.81
1101 (16) Duplex Conveniece Outlet/Receptacle (GT), 250V, 15A, 2P, Wall Mounted set 5,134.50 77.00 395,356.50
1102 POWER LOAD CENTER, SWITCHGEAR AND PANELBOARDS, AND OTHER OVERCURRENT -
PROTECTION DEVICES

Panelboard, DPHB, Main: 400AT/400AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 36KAIC,


Branches: 1 - 300AT/400AF, 3P, MCCB, 3 - 60AT/100AF, 3P, MCCB, 1 - 30AT/100AF, 3P,
1102 (2)3.1 MCCB, 1 - 400AF, SPACE, 1 - SPD, 240kA/Phase, complete with 1 - Digital Power Meter set 42,654.61
(DPM), 3 - Current Limiting Fuse (CLF), 3 - Current Transformer 400/5A, in NEMA 1
Enclosure. (Located at Bldg # 3)
42,654.61 1.00
Panelboard, GF-PPHB, Main: 60AT/100AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 18KAIC,
1102 (2)3.2 Branches: 18 - 20AT/100AF, 1P, MCCB, complete with 3 - Current Limiting Fuse, 3 - set 22,144.04
Indicating Lights (R,Y,B), in NEMA 1 Enclosure. (Located at Bldg # 3) 22,144.04 1.00
Panelboard, 2F-PPHB, Main: 60AT/100AF, 3P, 4W + G, 400/230V, 60Hz, MCCB, 18KAIC,
1102 (2)3.3 Branches: 14 - 20AT/100AF, 1P, MCCB, complete with 3 - Current Limiting Fuse, 3 - set 22,144.04
Indicating Lights (R,Y,B), in NEMA 1 Enclosure. (Located at Bldg # 3) 22,144.04 1.00

Panelboard, ACU-PPHB, Main: 300AT/400AF, 3P, 4W + G, 230V, 60Hz, MCCB, 25KAIC,


1102 (2)3.4 Branches: 1 - 30AT/100AF, 3P, MCCB, 15 - 60AT/100AF, 1P, MCCB, 10 - 40AT/100AF, 1P, set 39,577.46
MCCB, 2 - 20AT/100AF, 1P, MCCB, 1 - SPD, 240kA/Phase, complete with 3 - Current Limiting
Fuse, 3 - Indicating Lights (R,Y,B), in NEMA 1 Enclosure. (Located at Bldg # 3)
39,577.46 1.00
1102 (24) a3.3 Enclosed Circuit Breaker, 40AT/100AF, 1P, 230V, in NEMA 4X Enclosure set 5,230.60 9.00 47,075.36
1102 (24) a3.5 Enclosed Circuit Breaker, 60AT/100AF, 1P, 230V, in NEMA 4X Enclosure set 5,664.97 15.00 84,974.56
1102 (32) a1.1 Disconnect Switch, 20A, 1P, 230V, Rotary Knob Type in NEMA 1 Enclosure set 2,100.00 2.00 4,200.00
1102 (36) Testing and Commissioning lot 68,250.00 1.00 68,250.00
SUB-TOTAL 1,494,323.19
1208 FIRE ALARM SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (2)a Intermediate Metal Conduit (IMC), 15mm dia. meter 126.80 360.00 45,649.09
1100 (3)a Flexible Metal Conduit (FMC), 15mm dia. meter 28.67 22.00 630.63
1100 (13)a Straight Connector, 15mm dia. piece 21.84 44.00 960.96
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 68.25 5.00 341.25
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 81.90 36.00 2,948.40
1100 (8)c Square Box, 101mm x 101mm x 54mm, Ga. 16 piece 136.50 5.00 682.50
1101 FIRE ALARM WIRES AND CABLES (including connectors, tapes, etc.) -
1101 (2)g1 1.25mm2 Twisted Pair Shielded Cable meter 24.57 267.00 6,560.19
1101 (2) b1 Electric Wire, 2.0mm2 THHN/THWN-2 meter 28.39 235.00 6,672.12
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 42.59 28.00 1,192.46
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 42.59 14.00 596.23
1208 FIRE ALARM DEVICES AND EQUIPMENT -
1208 (5) d Fire Alarm Control Panel (FACP) (4 - LOOPS), Fully Addressable set 190,000.00 1.00 190,000.00
1208 (2) Addressable Smoke Detector set 4,000.00 20.00 80,000.00
1208 (3) Addressable Heat Detector set 4,000.00 2.00 8,000.00
1208 (6) Addressable Manual Pull Station set 2,300.00 5.00 11,500.00
1208 (11) Zone Addressable Module set 7,140.00 4.00 28,560.00
1208 (4) Addressable Fire Alarm Strobe with Sounder set 2,300.00 5.00 11,500.00
1208 (19)9 Testing and Commissioning lot 78,000.00 1.00 78,000.00

SUB-TOTAL 473,793.84

1105 NETWORK CABLING SYSTEM


1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INs)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 49.14 69.00 3,390.66
1100 (6)b Polyvinyl Chloride Pipes (PVC/uPVC), 25mm dia. meter 74.39 102.00 7,588.04
1100 (2)c Intermediate Metal Conduit (IMC), 25mm dia. meter 278.62 93.00 25,912.01
1100 (2)d Intermediate Metal Conduit (IMC), 32mm dia. meter 356.28 81.00 28,858.35
1100 (6)f Polyvinyl Chloride Pipes (PVC/uPVC), 63mm dia. meter 218.40 60.00 13,104.00
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 68.25 48.00 3,276.00

1100 (8) e6 Wireway, 150mmW x 100mmD x 2400mmL, Ga. 16 (complete with cover, support, fittings, length 228,501.00
end plate and all fixing accessories like jointing plate, fixing nuts, and bolts and washers.)
2,457.00 93.00
1105 NETWORK WIRES AND CABLES (including connectors, tapes, etc.) -
1105 (7) 0.57mm, 4 Pairs, Cat. 6, Shielded Twisted Pair Cable (STP) (1 roll = 500m) roll 19,110.00 1.79 34,206.90
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 42.59 16.00 681.41
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 42.59 8.00 340.70
1105 NETWORK CABLING DEVICES AND EQUIPMENT -
1105 (14) a Single Work Station Outlet, Voice Line, Wall Mounted set 614.25 1.00 614.25
1105 (14) a Single Work Station Outlet, Data Line, Wall Mounted set 764.40 38.00 29,047.20
1105 (15) Double Work Station, Wall Mounted Outlet, Combination of Voice and Data set 6,142.50 9.00 55,282.50

Main Distribution Frame Panel (MDF-HB) located at Bldg 3, consists of the following: 1 set
of 24U Free Standing Rack Cabinet, 3 sets of 24 port Patch Panel, 3 sets of 24 Port POE
1105 (2)3.1 Switch, 1 set of Network Video Recorder (NVR)-32TB, 1 set of 8 Port CORE Switch, 1 set of set 109,200.00
3KVA UPS, 1Ø, 230v, 60Hz, 1 set of Power Supply with 4 Outlets, STP Patchcord, and other
accessories needed to make the system complete and operational.
109,200.00 1.00
1105 (23) Telephone Terminal Cabinet set 68,250.00 1.00 68,250.00
1105 (22) a Private Automatic Branch Exchange (PABX) - 30 direct/local lines, 10 trunklines set 129,675.00 1.00 129,675.00
1105 (24)8 Testing and Commissioning lot 68,250.00 1.00 68,250.00

SUB-TOTAL 806,178.02

1106 CCTV SYSTEM


1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 49.14 41.00 2,014.74
1100 (3)a Flexible Metal Conduit (FMC), 15mm dia. meter 28.67 11.00 315.32
1100 (13)a Straight Connector, 15mm dia. piece 21.84 14.00 305.76
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 81.90 7.00 573.30
1105 CCTV WIRES AND CABLES (including connectors, tapes, etc.) - -
1105 (7) 0.57mm, 4 Pairs, Cat. 6, Shielded Twisted Pair Cable (STP) (1 roll = 500m) roll 19,110.00 0.11 2,102.10
1106 CCTV DEVICES AND EQUIPMENT -
1106 (2) IP Based Fixed Dome Type CCTV Camera, 2MP, Indoor set 5,050.50 7.00 35,353.50
CCTV Equipment located at Bldg # 3, consists of the following: 1 set of 32" LED Moitor, 1
1106 (15)3.1 set Central Processing Unit (CPU) - Intel Core i7 Extreme Processor 3.2GHz, 16GB RAM set 163,800.00
Memory, Windows 10 with 6-6TB HDD for Video Recording, Keyboard, Joystick, and other
accessories needed to make the system complete and operational.
163,800.00 1.00
1106 (16)8 Testing and Commissioning lot 68,250.00 1.00 68,250.00

SUB-TOTAL 272,714.71
1107 PUBLIC ADDRESS SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1107(7) Testing and Commissioning lot 68,250.00 1.00 68,250.00
SUB-TOTAL 68,250.00
1108 ACCESS CONTROL SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-INS)
1100 (6)a Polyvinyl Chloride Pipes (PVC/uPVC), 20mm dia. meter 49.14 91.00 4,471.74
1100 (6)b Polyvinyl Chloride Pipes (PVC/uPVC), 25mm dia. meter 74.39 30.00 2,231.78
1100 (8)a Utility Box, 101mm x 54mm x 54mm, Ga. 16 piece 68.25 21.00 1,433.25
1100 (8)b Octagonal Junction Box, 101mm x 101mm x 54mm, Ga. 16 piece 81.90 7.00
1100 (8)c Square Box, 101mm x 101mm x 54mm, Ga. 16 piece 136.50 21.00 2,866.50
1101 WIRES AND CABLES (including connectors, tapes, etc.)
1105 (7) 0.57mm, 4 Pairs, Cat. 6, Shielded Twisted Pair Cable (STP) (1 roll = 500m) roll 19,110.00 0.01 191.10
1101 (2) i 1.25mm2 TF meter 24.57 40.00 982.80
1101 (2) b2 Electric Wire, 3.5mm2 THHN/THWN-2 meter 42.59 193.00 8,219.48
1101 (2) b2.1 Electric Wire, 3.5mm2 TW (G) meter 42.59 97.00 4,131.04
1108 (12) RS485 Cable meter 34.20 186.00 6,361.85
1108 ACS DEVICES

Access Control Equipment consists of the following ACS Panel, Main ACS , Central Processing
1108(2) Unit (CPU) - Intel Core i7 Extreme Processor 3.2GHz, 8GB RAM Memory, Windows 10 with set 184,275.00
1TB HDD, 1 set 32" LED Monitor, Keyboard, joystick, UPS, 1kVA, 1Ø, 230V, 60Hz and other
accessories needed to make the system complete and operational
184,275.00 1.00
1108 (4) Magnetic Door Contact set 614.25 7.00 4,299.75
1108(6) RM4 Auxiliary Reader Relay, Module for Card Readers set 20,475.00 7.00 143,325.00
1108(7) Electromagnetic Lock set 1,092.00 7.00 7,644.00
1108(8) Card Reader set 4,777.50 2.00 9,555.00
1108(9) Exit Push Button set 1,638.00 7.00 11,466.00
1108(10) Emergency Break Glass set 2,047.50 7.00 14,332.50
1108(13).1 Interfacing, Testing and Commissioning lot 88,725.00 1.00 88,725.00
SUB-TOTAL 494,511.78
1109 GROUNDING SYSTEM
1100 CONDUITS, BOXES & FITTINGS (CONDUIT WORKS / CONDUIT ROUGH-IN)
1100 (6)b Polyvinyl Chloride Pipes (PVC/uPVC), 25mm dia. meter 74.39 24.00 1,785.42
1101 GROUNDING CONDUCTORS, ELECTRODES AND CONNECTIONS
1109 (4)k Bare Copper Wire, 60mm² Soft Drawn meter 518.78 194.00 100,642.36
1109 (6)e Ground Rod Copper Clad, 20mm dia. x 3m length 4,777.50 14.00 66,885.00
1109 (7) Grounding Test Well piece 8,190.00 3.00 24,570.00
1109 (8) Grounding Bus set 6,825.00 3.00 20,475.00
1109 (2) Exothermic Welded Connector set 8,872.50 33.00 292,792.50
Air Terminal, Lightning Arrester, ESE Type, 107m Radius of Protection (Complete with
1109 (3) Lightning Event Counter, Terminal Lugs, Mounting Mast Pole, and other accessories needed set 139,230.00
to make the system complete and operational.) 139,230.00 1.00
1109 (9).1 Testing and Commissioning lot 54,600.00 1.00 54,600.00

SUB-TOTAL 700,980.28

TOTAL COST - ELECTRICAL WORKS 5,578,762.54

GRAND TOTAL 61,482,405.80

General Requirements and Miscellaneaus Expences : 15.00% 9,222,360.87

Contingencies : 15.00% 9,222,360.87

Contractor's Profit & Overhead : 10.00% 6,148,240.58

Value Added Tax (VAT) : 12.00% 7,377,888.70

TOTAL PROJECT COST : 93,453,256.81