Case Study Information Technology (IT) - Park, Nagpur (India)
Case Study Information Technology (IT) - Park, Nagpur (India)
Case Study Information Technology (IT) - Park, Nagpur (India)
Input:
Illustrative images
fig 1 fig 2
Scope of work:
3D BIM model creation at LOD 300 for
architectural, structural, and MEPF services
from CAD/PDF drawings, clash detection,
resolution, and coordination between
architectural and structural components of
the building.
4D scheduling of planned vs. actual on-site.,
5D included extraction of quantities (BOQ)
from the BIM model
Tagging for Facility Management
fig 3
www.excelize.com
Challenges: Benefit to the client:
The submission deadline was Enabled client to plan and schedule
approaching quickly, which made it
challenging to meet the tight
1 dependent activities like materials,
services, purchases
schedule 5D helped the site team with running bill
The design was complicated, and the verification and managing the material
received drawings were not properly resources based on the master project
coordinated
2 schedule
The design team took longer than Exported 2D plans and views to enable
expected to respond/provide a clients to prepare shop drawings
solution, causing a delay Excelize onsite BIM team assisted
contractors during the installation phase
3
Output:
Overall 3D view
fig 4 fig 5
Our Services:
BIM Consulting Architectural BIM BIM training
Scan to BIM MEP coordination Model auditing
Shop Drawings Landscape BIM BIM studio
www.excelize.com
ISO 19650 20+ years of 2500+
Certified BIM leadership projects
marketing@excelize.com | www.excelize.com