Download as pdf or txt
Download as pdf or txt
You are on page 1of 125

REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

REQUEST FOR PROPOSAL FOR


RESIDENT CONSTRUCTION SUPERVISION
FOR
ESTABLISHMENT OF NAWAZ SHARIF INSTITUTE OF
CARDILOGY, SARGODHA

TENDER # 2024/RFP/33

INFRASTRUCTURE DEVELOPMENT AUTHORITY PUNJAB


(IDAP)
GOVERNMENT OF PUNJAB
50 B-3, Gulberg-III, Lahore

Page 1 of 125
IDAP

E- PROCUREMENT

SAVE PAPER, SAVE TREES, SAVE THE EARTH


Page 2 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Section 1. Letter of Invitation


Request for Proposal(s) (RFP)

Date: ………………..

1. The ‘Infrastructure Development Authority of the Punjab’ (IDAP) has been established as an
autonomous body under the Infrastructure Development Authority of the Punjab Act, 2016 (Act IV of
2016) by the Government of Punjab for planning, designing, construction and maintenance of
Infrastructure in Punjab in line with best international practices to cope with future development needs.

2. The Infrastructure Development Authority Punjab (IDAP) invites proposals through its E-Procurement
Portal for “RESIDENT CONSTRUCTION SUPERVISION FOR ESTABLISHMENT OF NAWAZ
SHARIF INSTITUTE OF CARDILOGY, SARGODHA”. Details on the services are provided in the
Terms of Reference

3. This Request for Proposal (RFP) is addressed to the competent and qualified Consulting Firms meeting
the Eligibility & Qualification Criteria as per Instruction to Consultant 21.1.

4. A firm will be selected under Quality & Cost Based Selection (QCBS) method and procedures described
in this RFP, in accordance with the Punjab Procurements Rules, 2014 and procedures described in this
RFP.

5. The RFP includes the following documents:


Section 1 - Letter of Invitation
Section 2 - Instructions to Consultants and Data Sheet
Section 3 - Technical Proposal - Standard Forms
Section 4 - Financial Proposal - Standard Forms
Section 5 – Eligible Countries
Section 6 – PPRAs Policy – Corrupt Practices
Section 7 - Terms of Reference
Section 8 - Standard Forms of Contract

Yours sincerely,

General Manager (Procurement & Contracts)


Infrastructure Development Authority of the Punjab (IDAP)
50 B-3, Gulberg III, Lahore
+92-42 99332631-42
procurement@idap.pk

Page 3 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Section 2. Instructions to Consultants and Data Sheet


A. General Provisions
1. Definitions (a) “Affiliate(s)” means an individual or an entity that directly or
indirectly controls, is controlled by, or is under common control
with, the Consultant.
(b) “Applicable Law” means the laws and any other instruments
having the force of law in the jurisdiction of the province of Punjab,
or in such other country as may be specified in the Data Sheet,
as they may be issued and in force from time to time.
(c) “Consultant” means individual consultant, a legally established
professional consulting firm or an entity that may provide or
provides the Services to the Procuring Agency under the
Contract.
(d) “Contract” means a legally binding written agreement signed
between the Procuring Agency and the Consultant and includes
all the attached documents listed in its Clause 1 (the General
Conditions of Contract (GCC), the Special Conditions of Contract
(SCC), and the Appendices).
(e) “Data Sheet” means an integral part of the Instructions to
Consultants (ITC) Section 2 that is used to reflect specific country
and assignment conditions to supplement, but not to override, the
provisions of the ITC.
(f) “Day” means a calendar day.
(g) “Experts” means, collectively, Key Experts, Non-Key Experts, or
any other personnel of the Consultant, Sub-Consultant/ Sub-
Contractor or Joint Venture/ Consortium member(s).
(h) “Joint Venture (JV)” means an association with or without a legal
personality distinct from that of its members, of more than one
Consultant where one member has the authority to conduct all
business for and on behalf of any and all the members of the JV,
and where the members of the JV are jointly and severally liable
to the Procuring Agency for the performance of the Contract.
(i) “Key Expert(s)” means an individual professional whose skills,
qualifications, knowledge and experience are critical to the
performance of the Services under the Contract and
(j) “ITC” (Section 2 of the RFP) means the Instructions to
Consultants that provides the Consultants with all information
needed to prepare their Proposals.

Page 4 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

(k) “LOI” (Section 1 of the RFP) means the Letter of Invitation sent
by the Procuring Agency to the shortlisted Consultants.
(l) “Non-Key Expert(s)” means an individual professional provided
by the Consultant and who is assigned to perform the Non-Key
Services or any part thereof under the Contract.
(m) “Proposal” means the Technical Proposal and the Financial
Proposal of the Consultant.
(n) “RFP” means the Request for Proposal to be prepared by the
Procuring Agency for the selection of consultants, based on the
STANDARD RFP.
(o) “Services” means the work to be performed by the Consultant
pursuant to the Contract.
(p) “STANDARD RFP” means the Standard Request For Proposal,
which must be used by the Procuring Agency as the basis for the
preparation of the RFP.
(q) “Sub-Consultant” means an entity to whom the Consultant sub-
contract any part of the Services while remaining responsible to
the Procuring Agency during the performance of the Contract with
prior approval of the Procuring Agency.
(r) “TORs” (Section 7 of the RFP) means the Terms of Reference
that explain the objectives, scope of work, activities, and tasks to
be performed, respective responsibilities of the Procuring Agency
and the Consultant, and expected results and deliverables of the
assignment.
2. Introduction 2.1 The Procuring Agency named in the Data Sheet intends to select
a Consultant in accordance with the method of selection specified in the
Data Sheet.
2.2 The Consultants are invited to submit a Technical Proposal and a
Financial Proposal, or a Technical Proposal only, as specified in the Data
Sheet, for consulting services required for the assignment named in the
Data Sheet. The Proposal will be submitted on IDAP’s E-Procurement
Portal only. The Proposal will be the basis for negotiating and ultimately
signing the Contract with the selected Consultant.
2.3 The Consultants should familiarize themselves with the local
conditions and take them into account in preparing their Proposals,
including attending a pre-proposal conference if one is specified in the Data
Sheet. Attending any such pre-proposal conference is optional and is at
the Consultants’ expense.

Page 5 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

2.4 The Procuring Agency will timely provide, at no cost to the


Consultants, the inputs, relevant project data, and reports required for the
preparation of the Consultant’s Proposal as specified in the Data Sheet.
3. Conflict of 3.1 The Consultant is required to provide professional, objective, and
Interest impartial advice, at all times holding the Procuring Agency’s interests
paramount, strictly avoiding conflicts with other assignments or its own
corporate interests, and acting without any consideration for future work.
3.2 The Consultant has an obligation to disclose to the Procuring
Agency any situation of actual or potential conflict that impacts its capacity
to serve the best interest of its Procuring Agency. Failure to disclose such
situations may lead to the disqualification of the Consultant or the
termination of its Contract and/or sanctions by the Authority.
3.2.1 Without limitation on the generality of the foregoing, the
Consultant shall not be hired under the circumstances set forth below:
a. Conflicting (i) Conflict between consulting activities and procurement of
activities goods, works or non-consulting services: a firm that has been
engaged by the Procuring Agency to provide goods, works, or
non-consulting services for a project, or any of its Affiliates, shall
be disqualified from providing consulting services resulting from
or directly related to those goods, works, or non-consulting
services. Conversely, a firm hired to provide consulting services
for the preparation or implementation of a project, or any of its
Affiliates, shall be disqualified from subsequently providing
goods or works or non-consulting services resulting from or
directly related to the consulting services for such preparation
or implementation.
b. Conflicting (ii) Conflict among consulting assignments: a Consultant (including
assignments its Experts and Sub-Contractors) or any of its Affiliates shall not
be hired for any assignment that, by its nature, may be in conflict
with another assignment of the Consultant for the same or for
another Procuring Agency.
c. Conflicting (iii) Relationship with the Procuring Agency’s staff: a Consultant
relationships (including its Experts and Sub-Contractors) that has a close
business or family relationship with a professional staff of the
Procuring Agency, or of a recipient of a part of the financing in
case the project is financed by some financing institution) who
are directly or indirectly involved in any part of (i) the preparation
of the Terms of Reference for the assignment, (ii) the selection
process for the Contract, or (iii) the supervision of the Contract,
may not be awarded a Contract, unless the conflict stemming
from this relationship has been resolved in a manner acceptable
to the Authority throughout the selection process and the
execution of the Contract.

Page 6 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

4. Unfair 4.1 Fairness and transparency in the selection process require that the
Competitive Consultants or their Affiliates competing for a specific assignment do not
Advantage derive a competitive advantage from having provided consulting services
related to the assignment in question. To that end, the Procuring Agency
shall indicate in the Data Sheet and make available to all shortlisted
Consultants together with this RFP all information that would in that respect
give such Consultant any unfair competitive advantage over competing
Consultants.
5. Corrupt 5.1 The Authority requires compliance with its Regulatory Framework in
Practices regard to corrupt practices as set forth in Section 6.
5.2 In further pursuance of this Regulatory Framework, Consultants shall
permit and shall cause their agents (where declared or not), sub-
Contractors, sub-Contractors, Consultants, suppliers, and personnel, to
permit the Procuring Agency to inspect all accounts, records and other
documents relating to any shortlisting process, Proposal submission, and
Contract performance (in the case of award), and to have them audited by
auditors appointed by the Procuring Agency.
6. Eligibility 6.1 Unless stated otherwise in the Data Sheet, The Procuring Agency
permits Consultants (individuals and firms, including Joint Ventures,
Consortium and their individual members from all countries (which fulfill the
required criteria and registered with relevant authorities) except (countries
to mentioned as per policy of the government) to offer consulting services
for the project.

6.2 Furthermore, it is the Consultant’s responsibility to ensure that its


Experts, Joint Venture/ Consortium members, Sub-Contractors, suppliers
and/or their employees meet the eligibility requirements.

6.3 As an exception to the foregoing Clauses 6.1 and 6.2 above:


a. Sanctions 6.3.1 A firm or a Consultant declared blacklisted by the
Procuring Agency or the Authority in accordance with the above
Clause 5.1 shall be ineligible to participate in the procurement
process or to be awarded a Contract, during such period of time as
determined in the Blacklisting Order or determined by the Authority
whichever is later. The list of debarred firms and individuals is
available at the electronic address specified in the Data Sheet.

b. Prohibitions 6.3.2 Firms and Consultants of a country or goods


manufactured in a country may be ineligible if so indicated in Section
5 (Eligible Countries).
c. Restrictions for 6.3.3 Government-owned enterprises or institutions shall also be
Government-owned eligible as per provisions of PPR-14.
Enterprises

Page 7 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

d. Restrictions for 6.3.4 Government officials and civil servants are not eligible to be
public employees included as Experts in the Consultant’s Proposal unless such
engagement does not conflict with any employment or other laws,
regulations, or policies of the Government. However, they are
eligible if they:
(i) are on leave, or have resigned or retired;
(ii) are not being hired by the same agency they were working for
before going on leave, resigning, or retiring
(in case of resignation or retirement, a period of at least two years, or the
period established by statutory provisions applying to civil servants or
government employees whichever is longer, should pass before working
as Consultants for the same agency); and
(iii) would not create a conflict of interest if hired.
B. Preparation of Proposals
7. General 7.1 In preparing the Proposal, the Consultant is expected to examine
Consideration the RFP in detail. Material deficiencies in providing the information
s requested in the RFP may result in rejection of the Proposal.
8. Cost of 8.1 The Consultant shall bear all costs associated with the preparation
Preparation of and submission of its Proposal, and the Procuring Agency shall not be
Proposal responsible or liable for those costs, regardless of the conduct or outcome
of the selection process. The Procuring Agency is not bound to accept any
proposal, and reserves the right to annul the selection process in
accordance with the procurement regulatory framework at any time prior to
Contract award, without thereby incurring any liability to the Consultant.
9. Language 9.1 The Proposal, as well as all correspondence and documents
relating to the Proposal exchanged between the Consultant and the
Procuring Agency, shall be written in the language(s) specified in the Data
Sheet.
10. Documents 10.1 The Proposal shall comprise the documents and forms listed in the
Comprising the Data Sheet.
Proposal
10.2 If specified in the Data Sheet, the Consultant shall include a
statement of an undertaking of the Consultant to observe, in competing for
and executing a Contract, the Procuring Regulatory Framework regarding
corrupt practices.
10.3 The Consultant shall furnish information on commissions,
gratuities, and fees, if any, paid or to be paid to agents or any other party
relating to this Proposal and, if awarded, Contract execution, as requested
in the Financial Proposal submission form (Section 4).

Page 8 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

11. Only One 11.1 The Consultant (including the individual members of any Joint
Proposal Venture/ Consortium) shall submit only one Proposal, either in its own
name or as part of a Joint Venture/ Consortium in another Proposal. If a
Consultant, including any Joint Venture / Consortium member, submits or
participates in more than one proposal, all such proposals shall be
disqualified and rejected. This condition also applies on a Sub-Consultant,
or the Consultant’s staff, Key Experts and Non-Key Experts not to
associate with more than one Consultant.
12. a. Proposal 12.1 Proposals shall remain valid for the period specified in the Data
Validity Sheet after the Proposal submission deadline prescribed by the Procuring
Agency.

12.2 During this period, the Consultant shall maintain its original
Proposal without any change, including the availability of the Key Experts,
the proposed rates and the total price.

12.3 If it is established that any Key Expert nominated in the


Consultant’s Proposal was not available at the time of Proposal submission
or was included in the Proposal without his/her confirmation, such Proposal
shall be disqualified and rejected for further evaluation, and may be subject
to blacklisting and debarment in accordance with Clause 5 of this ITC.

12.4 The Bid Security [to be is required to protect the Procuring Agency
against the risk of Consultant’s conduct which would warrant the
Consultant to face the blacklisting or debarment proceedings in
accordance with regulatory framework.

12.5 Any Technical Proposal not accompanied by a Bid Security shall


be rejected by the Procuring Agency as non-responsive.

12.6 The Bid Security of a Joint Venture/ Consortium must be in the


name of the Joint Venture/ Consortium submitting the Proposal.

b. Bid security 12.7 The successful Consultant’s /Bid Security will be discharged upon
signing of the Contract with the Successful Consultant.

12.8 A Consultant shall be suspended from being eligible for tendering


in any Contract with the Procuring Agency for the period of time indicated
in the Bid Data Sheet and Bid Security Bid Security shall be forfeited

(a) if the Consultant withdraws its Proposal, except as provided in ITC


12.6 or

(b) in the case of a successful Consultant, if the Consultant fails within


the specified time limit to sign the Contract,

c. Extension of 12.9 If considered necessary, an extension can be made in case of


Validity Period exceptional circumstances (beyond the control of the Procuring Agency)

Page 9 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

after recording the reason(s) in writing. Such extension should be


determined keeping in view of the circumstances under which such
extension is deemed to be necessary, however, the same shall not be more
than the original bid validity period or 180 days whichever is more. The
request and the responses shall be made in writing. Moreover, any such
extension shall be solicited and procured in advance prior to the expiry of
original (or initial) bid validity period.

12.10 If the Consultant agrees to extend the validity of its Proposal, it


shall be done without any change in the original Proposal and with the
confirmation of the availability of the Key Experts.

12.11 The Consultant has the right to refuse to extend the validity of its
Proposal in which case such Proposal will not be further evaluated.

d. Substitution of 12.12 If any of the Key Experts become unavailable for the extended
Key Experts at validity period or during the continuation of consultancy services, the
Validity Extension Consultant shall provide a written adequate justification and evidence
satisfactory to the Procuring Agency together with the substitution request.
Finally, the Procuring Agency shall decide whether to accept the substitute
or otherwise. In such case, a replacement Key Expert shall have equal or
better qualifications and experience than those of the originally proposed
Key Expert. The technical evaluation score, however, will remain to be
based on the evaluation of the CV of the original Key Expert.

12.13 If the Consultant fails to provide a replacement Key Expert with


equal or better qualifications, or if the provided reasons for the replacement
or justification are unacceptable to the Procuring Agency, such Proposal
will be rejected during validity/extended validity Period.

e. Sub-Contracting 12.14 The Consultant shall not sub-contract the whole of the Services.
13. Clarification 13.1 The Consultant may request a clarification of any part of the RFP
and to be received by the Procuring Agency at least three (03) days before the
Amendment of Proposals’ submission deadline thorough E-Procurement Portal . Any
RFP request for clarification must be sent thorough E-Procurement Portal using
the TAB “Clarification” to the Procuring Agency.. The Procuring Agency
will respond through E-Procurement Portal, and will send the response
(including an explanation of the query but without identifying its source) to
all shortlisted Consultants. Should the Procuring Agency deem it
necessary to amend the RFP as a result of a clarification or at its own
initiative, it shall do so following the procedure described below:
13.1.1 At any time before the proposal submission deadline, but
not later than three (03) Working Days prior to the Proposals’
submission deadline, the Procuring Agency may amend the RFP by
issuing an amendment in “Addendum” section of E-Procurement
Portal. The amendment shall be sent to all Consultants and will be
binding on them.

Page 10 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

13.1.2 If the amendment is substantial, the Procuring Agency


may extend the Proposal submission deadline to give the shortlisted
Consultants reasonable time to take an amendment into account in
their Proposals.
13.2 The Consultant who has already submitted the Proposal prior to
any amendments in the RFP, may submit a modified Proposal or a
modification to any part of it based on the respective amendment in the
RFP or even otherwise at any time prior to the Proposal submission
deadline. No modifications to the Technical or Financial Proposal shall be
accepted after the deadline.
14. Preparation of 14.1 An Association (Joint Venture/ Consortium or Sub-Contractors)
Proposals will only be allowed if expressly mentioned in the Expression of Interest or
the RFP, as the case may be.(as mentioned in Bid Data Sheet)
14.2 The Procuring Agency has indicated in the Data Sheet whether
the Contract would be “Lump Sum Contract” “Time Based Contract”
“Hourly or Daily Rates Contracts” and any other, based on combination of
the above. The method to be used for selection of Consultant is also
mentioned in the Data Sheet
14.3 For assignments under the “lump sum Contracts”, total available
budget, with an indication whether it is inclusive or exclusive of taxes, is
given in the Data Sheet, and the Financial Proposal shall not exceed this
budget. For time based Contracts, input time for the key experts may also
be indicatedA Procuring Agency may specify any other requirement related
to the assignment or Contract, where required, not contrary to the PPR-14.
15. Technical 15.1 The Technical Proposal shall not include any information
Proposal regarding Financial Proposal. A Technical Proposal containing material
Format and financial information shall be declared non-responsive.
Content
15.2 Consultant shall not propose alternative Key Experts. Only one CV
shall be submitted for each Key Expert position. Failure to comply with this
requirement will make the Proposal non-responsive.
15.3 Depending on the nature of the assignment, the Consultant is
required to submit a Full Technical Proposal (FTP), or a Simplified
Technical Proposal (STP) as indicated in the Data Sheet and using the
Standard Forms provided in Section 3 of the RFP.
16. Financial 16.1 The Financial Proposal shall be prepared using the Standard
Proposal Forms provided in Section 4 of the RFP. It shall list all costs associated
with the assignment, including (a) remuneration for Key Experts and Non-
Key Experts, (b) Direct expenses indicated in the Data Sheet.
a. Taxes 16.2 The Consultant and its Sub-Contractors and Experts are
responsible for meeting all tax liabilities arising out of the Contract unless
stated otherwise in the Data Sheet.

Page 11 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

b. Currency of 16.3 The Consultant may express the price for its Services in the
Proposal currency or currencies as stated in the Data Sheet. If indicated in the Data
Sheet, the portion of the price representing local cost shall be stated in the
national currency.
c. Currency of 16.4 Payment under the Contract shall be made in the currency or
Payment currencies in which the consultant is required to submit the financial
proposal

C. Submission, Opening and Evaluation


17. Submission, 17.1 The Consultant shall submit a signed and complete Proposal
Sealing, and comprising the documents and forms in accordance with Clause 10
Marking of (Documents Comprising Proposal). The submission will be done only
Proposals on E-Procurement Portal of Procuring Agency. If specified in the Data
Sheet, the Consultant has the option of submitting its Proposals
electronically.
17.2 An authorized representative of the Consultant shall sign the
original submission letters in the required format for both the Technical
Proposal and, if applicable, the Financial Proposal and shall initial all
pages of both. The authorization shall be in the form of a written power
of attorney attached to the Technical Proposal.

17.2.1 A Proposal submitted by a Joint Venture / Consortium shall be


signed by all members so as to be legally binding on all members, or by
an authorized representative who has a written power of attorney signed
by each member’s authorized representative. In case of foreign bidder,
who is part of the consortium or submitted its proposal independently,
the authorized person of the bidder should submit its power of attorney
duly attested by the foreign office.

17.3 Any modifications, revisions, interlineations, erasures, or


overwriting shall be valid only if they are signed or initialed by the person
signing the Proposal.

17.4 The Consultant shall submit Proposal on E-Procurement Portal


Comprising of Technical Proposal and Finical Proposal..

17.5
18. Confidentiality 18.1 From the time the Proposals are opened to the time the
Evaluation Report is published, the Consultant should not contact the
Procuring Agency on any matter related to its Technical and/or Financial
Proposal. Information relating to the evaluation of Proposals shall not
be disclosed to the Consultants who submitted the Proposals or to any
other party not officially concerned with the process, until the publication
of the Evaluation Report.

Page 12 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

18.2 Any attempt by shortlisted Consultants or anyone on behalf of


the Consultant to influence improperly the Procuring Agency in the
evaluation of the Proposals may result in the rejection of its Proposal,
and may be subject to the application of prevailing blacklisting
procedures.
18.3 Notwithstanding the above provisions, from the time of the
Proposals’ opening to the time of publication of evaluation report, if a
Consultant wishes to contact the Procuring Agency on any matter
related to the selection process, it should do so only in writing.
19. Opening of 19.1 The Procuring Agency’s Procurement committee shall conduct
Technical the opening of the Technical Proposals on E-Procurement Portal in the
Proposals presence of the Proposer Consultants’ authorized representatives who
choose to attend (in person, or online if this option is offered in the Data
Sheet). The opening date, time and the address are stated in the Data
Sheet. The envelopes with the Financial Proposal shall remain sealed
on E-Procurement Portal, until they are opened in accordance with
Clause 23 of the ITC.
19.2 At the opening of the Technical Proposals, the following shall
be read out: (i) the name and the country of the Consultant or, in case
of a Joint Venture / Consortium, the name of the Joint Venture/
Consortium, the name of the lead member and the names and the
countries of all members; (ii) any modifications to the Proposal
submitted prior to Proposal submission deadline; and (iii) any other
information deemed appropriate or as indicated in the Data Sheet.
20. Proposals 20.1 Subject to provision of Clause 15.1 of the ITC, the evaluators
Evaluation of the Technical Proposals shall have no access to the Financial
Proposals until the technical evaluation is concluded.
20.2 The Consultant is not permitted to alter or modify its Proposal
in any way after the proposal submission deadline. While evaluating the
Proposals, the Procuring Agency will conduct the evaluation solely on
the basis of the submitted Technical and Financial Proposals.

21. Evaluation of 21.1 The Procuring Agency’s evaluation committee shall evaluate
Technical the Technical Proposals on the basis of their responsiveness to the
Proposals Terms of Reference and the RFP, applying the evaluation criteria, sub-
criteria, and point system specified in the Data Sheet. Each responsive
Proposal will be given a technical score. A Proposal shall be rejected at
this stage if it does not respond to important aspects of the RFP or if it
fails to achieve the minimum technical score indicated in the Data
Sheet.
22. Financial 22.1 Following the ranking of the Technical Proposals, when the
Proposals for QBS selection is based on quality only (QBS), the top-ranked Consultant is
invited to negotiate the Contract.

Page 13 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

22.2 Only the Financial Proposal of the technically top-ranked


Consultant (as predefined in the Evaluation Criteria) is opened by the
Procuring Agency’s evaluation committee. All other Financial Proposals
are returned unopened after the Contract negotiations are successfully
concluded and the Contract is signed. In case of failure to sign the
contract with the highest ranked bidder provision of Rule-53(2) of PPR-
14 may be invoked and procuring agency may proceed with next
highest ranked bidder.
23. Public Opening of 23.1 After the technical evaluation is completed, the Procuring
Financial Agency shall issue the Technical Evaluation Report containing all the
Proposals (for information regarding responsiveness or non-responsiveness of the
QCBS and LCS Consultant along with the technical scores. The Financial Proposals of
methods) non-responsive Consultants will remain unopened on E-Procurement
Portal of Procuring Agency. The Procuring shall notify through E-
Procurement Portal those Consultants that have achieved the minimum
overall technical score and inform them of the date, time and location
for the opening of the Financial Proposals. The opening date should
allow the Consultants sufficient time to make arrangements for
attending the opening. The Consultant’s attendance at the opening of
the Financial Proposals (in person, or online if such option is indicated
in the Data Sheet) is optional and is at the Consultant’s choice.
23.2 The Financial Proposals shall be opened by the Procuring
Agency’s Procurement committee on E-Procurement Portal in the
presence of the representatives of those Consultants whose proposals
have passed the minimum technical score. At the opening, the names
of the Consultants, and the overall technical scores, including the break-
down by criterion, shall be read aloud. These Financial Proposals shall
be then opened on E-Procurement Portal, and the total prices read
aloud and recorded.
24. Correction of 24.1 Activities and items described in the Technical Proposal but not
Errors priced in the Financial Proposal, shall be assumed to be included in the
prices of other activities or items, and no corrections are made to the
Financial Proposal.
a. Time-Based Contracts 24.1.1 If a Time-Based Contract form is included in the RFP, in
case of discrepancy between (i) a partial amount (sub-total) and
the total amount, or (ii) between the amount derived by
multiplication of unit price with quantity and the total price, or (iii)
between words and figures, the former will prevail. In case of
discrepancy between the Technical and Financial Proposals in
indicating quantities of input, the Technical Proposal prevails and
the Procuring Agency’s evaluation committee shall correct the
quantification indicated in the Financial Proposal so as to make
it consistent with that indicated in the Technical Proposal, apply
the relevant unit price included in the Financial Proposal to the
corrected quantity, and correct the total Proposal cost.

Page 14 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

b. Lump-Sum Contracts 24.2 If a Lump-Sum Contract form is included in the RFP, the
Consultant is deemed to have included all prices in the Financial
Proposal. The total price, net of taxes understood as per Clause ITC 25
below, specified in the Financial Proposal (Form FIN-1) shall be
considered as the offered price. [Details to be provided by the procuring
agency]
25. Taxes 25.1 The Procuring Agency’s evaluation of the Consultant’s Financial
Proposal shall include applicable taxes and duties in accordance with
the instructions in the Data Sheet as the same are constant for all.
26. Conversion to 26.1 For the evaluation purposes, prices shall be converted to a
Single Currency single currency using the selling rates of exchange, source and date
indicated in the Data Sheet.

27. Combined Quality


and Cost
Evaluation
a. Quality- and Cost- 27.1 In the case of QCBS, the total score is calculated by weighting
Based Selection the technical and financial scores and adding them as per the formula
(QCBS) and instructions in the Data Sheet. The Consultant achieving the
highest combined technical and financial score will be invited for
negotiations.
b. Quality-Based 27.2 In the case of QBS, full weightage is given to Technical
Selection (QBS) Proposal only. The Consultant obtaining highest marks in technical
evaluation is selected and invited for negotiations, as per rule 53 of
PPR-14.

Page 15 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

c. Least-Cost 27.3 In the case of Least-Cost Selection (LCS), the Procuring


Selection Agency will select the Consultant with the lowest evaluated total price
among those Consultants that achieved the minimum required technical
score, and invite such Consultant to negotiate the Contract.

D. Negotiations and Award


28. Negotiations 28.1 The negotiations will be held at the date and address indicated
in the Data Sheet with the Consultant’s representative(s) who must
have written power of attorney to negotiate and sign a Contract on
behalf of the Consultant.
28.2 The Procuring Agency shall prepare minutes of negotiations
that are signed by the Procuring Agency and the Consultant’s
authorized representative.
a. Availability of Key 28.3 The invited Consultant shall confirm the availability of all Key
Experts Experts included in the Proposal as a pre-requisite to the negotiations,
or, if applicable, a replacement in accordance with Clause 12 of the ITC.
Failure to confirm the Key Experts’ availability may result in the rejection
of the Consultant’s Proposal and the Procuring Agency may proceed to
negotiate the Contract with the next-ranked Consultant.
28.4 Notwithstanding the above, the substitution of Key Experts at
the negotiations may be considered if due solely to circumstances
outside the reasonable control of and not foreseeable by the Consultant,
including but not limited to death or medical incapacity. In such case,
the Consultant shall offer a substitute Key Expert within the period of
time specified in the letter of invitation to negotiate the Contract, who
shall have equivalent or better qualifications and experience than the
original candidate.
b. Technical 28.5 The negotiations include discussions on the Terms of
negotiations Reference (TORs), the proposed methodology, the Procuring Agency’s
inputs, the special conditions of the Contract, and finalizing the
“Description of Services” part of the Contract. These discussions shall
not alter the original scope of services under the TORs or the terms of
the Contract, so that the quality of the final product, or the relevance of
the initial evaluation may not affect.
c. Financial 28.6 Cost may be reduced, as per rule 53 of PPR-14, and it may
Negotiations also include the clarification of the Consultant’s tax liability and how it
should be reflected in the Contract.

29. Conclusion of 29.1 The negotiations are concluded with a review of the finalized
Negotiations draft Contract, which shall then be initialed by the Procuring Agency and
the Consultant’s authorized representative.
29.2 If the negotiations fail, the Procuring Agency shall inform the
Consultant in writing of all pending issues and disagreements and

Page 16 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

provide a final opportunity to the Consultant to respond. If disagreement


persists, the Procuring Agency shall terminate the negotiations
informing the Consultant of the reasons for doing so; and the Procuring
Agency will invite the next-ranked Consultant to negotiate the Contract.
Once the Procuring Agency commences negotiations with the next-
ranked Consultant, the Procuring Agency shall not reopen the earlier
negotiations.
29.3 Grievance Period: The contract shall not be awarded earlier
than the expiry of the Grievance Period. The Grievance period shall be
ten (10) days. The Grievance period commences as per the Rule 67.2
from the day Procuring Agency has announced the bid evaluation
report.
29.4 Notification of Award: Upon expiry of the grievance period and
upon satisfactorily addressing any complaint that has been filed within
that period, the client shall, send a notification of award to the successful
consultant, confirming the client’s intention to award the contract to the
successful consultant and requesting the successful consultant to sign
and return the draft negotiated contract within 07 days after receipt of
such notification
30. Bid Security 30.1 All Consultant must attach scanned copy of Bid Security,
[if applicable] equal to amount mentioned in Bid Data on E-Procurement Portal in
the shape of Bank Guarantee (format of bank guarantee is provided in
Section no. 1 as Annexure-A) or deposit at call, issued by scheduled
bank in Pakistan, in favor of “Infrastructure Development Authority of
Punjab”, as part of Technical Proposal. However, Original Bid
Security must be submitted in the office of GM(P&C) before the
deadline for the submission of the Proposal, failure to submit bid
security with technical proposal shall result in rejection of the bid
Bid Securities of Unsuccessful bidders shall be returned upon the expiry
of the grievance period, but not later than 28 days after the expiration
of the period of bid validity:
30.2 Bid Security of the successful bidder shall be released after
signing of Contract Agreement
30.3 The proceeds of the bid Security shall be payable to the
Procuring Agency, on the occurrence of any of the following.
If the Consultant withdraws the bid during the bid validity period
specified in the Data Sheet

 If the Consultant, having been notified as the successful bidder


refuses to sign the Contract within the timeframe.

 If it is established, beyond any reasonable doubt, that the


Consultant has exploited the selection process by any means

Page 17 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

or divulged confidential information acquired during the


selection process.
31. Stamp Duty 31.1 Successful consultant shall be required to submit Stamp duty
under stamp duty act 1899 for signing of contract as specified in Data
Sheet.

Page 18 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Instructions to Consultants
E. Data Sheet

A. General
ITC Clause
Reference

2.1 Name of the Procuring Agency: Infrastructure Development Authority of the Punjab
(IDAP)
Method of selection: Quality & Cost Based Selection (QCBS)

2.2 Financial Proposal is to be submitted on E-Procurement Portal in separate section as per


the Single Stage Two Envelop Bidding Procedure

The name of the assignment is:


RESIDENT CONSTRUCTION SUPERVISION FOR ESTABLISHMENT OF NAWAZ SHARIF
INSTITUTE OF CARDILOGY, SARGODHA.

2.3 A pre-Proposal conference/meeting will be held: Yes

Date of Pre-Proposal conference/meeting: June 13, 2024

General Manager
Procurement & Contracts
Infrastructure Development Authority of the Punjab (IDAP)
+9242 99332631-42
procurement@idap.pk

2.4 The Procuring Agency will provide the following inputs, project data, reports, etc. to
facilitate the preparation of the Proposals: (N/A)

4.1 N/A

6.1 No Joint Venture/Consortium is allowed.

6.3.1 A list of debarred firms and individuals is available at the PPRA website:
ppra.punjab.gov.pk

B. Preparation of Proposals

9.1 The language of the Bid is English


All correspondence shall be in [specify the language.] English
The language for translation of supporting documents and printed literature is English

Page 19 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

10.1 The Proposal shall comprise the following:

Technical Proposal shall Comprise of :


GEN-1 Technical Proposal Submission Form along with Power of Attorney to sign the
Proposal.
GEN-2 General Information Form
GEN-3 Affidavit of Correctness
GEN-4 Litigation History

TECH-1 Financial Soundness

TECH-2 Consultant’s Experience (Summary of Similar Nature Project Completed in Last 10


Years)
TECH-3 Consultant’s Experience (Detail of Similar Nature Project Completed in Last 10
Years)

TECH-4 Consultant’s Experience (Summary of Similar Nature Project in hand)


TECH-5 Consultant’s Experience (Detail of Similar Nature Project in Hand)

TECH-6 Consultant’s Experience (Summary of Civil Works Consultancy & Resident


Construction Supervision Completed in Last 10 Years)
TECH-7 Consultant’s Experience (Detail of Civil Works Consultancy & Resident Construction
Supervision Completed in Last 10 Years)

TECH-8 Team Composition and Task Assignments.

TECH-9 Curriculum Vitae (CV) for Proposed Professional Staff.

TECH-10 Staffing Schedule

TECH-11 Work Schedule

Annexure- A: format of Bank Guarantee (if required)

Financial Proposal
FIN-1 Financial Proposal Submission Form
FIN-2 Summary of Costs
FIN-3 Breakdown of Renumartion
FIN-4 Breakdown of Reimbursable

11.1 Association of Sub-Contractors, Key Experts and Non-Key Experts with more than one
Consultant in a Proposal is not permissible.

Page 20 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

12.1 Proposals shall be valid for 120 days after the submission date

13.1 Clarifications may be requested no later than 03 (Three) days prior to the submission
deadline.

Clarification shall be requested on E-Procurement Portal by using TAB “Clarification”

14.1 An Association (Joint Venture/ Consortium) is not allowed.

14.2 Not Applicable


(do not use for
Fixed Budget
method)
[if applicable]

14.3 Not Applicable


for time-based
Contracts only
[if applicable]

14.4 and 27.2 Not Applicable


use for Fixed
Budget
method
[if applicable]

15.2 The format of the Technical Proposal to be submitted is: Full technical Proposal as per
attached forms.

Submission of the Technical Proposal in a wrong format may lead to the Proposal being
deemed non-responsive to the RFP requirements.

16.2 Consultant submitting bis is responsible for meeting all taxes. Proposal shall be
submitted inclusive of all applicable taxes and duties etc.

16.3 Price for all Services shall be submitted in Proposal in PKR only.

16.4 The Financial Proposal shall be stated in the following currencies: PKR

The Financial Proposal should state local costs in the Procuring Agency’s country
currency (local currency): Yes (PKR)

C. Submission, Opening and Evaluation

Page 21 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

17.1 The Consultants shall have the only option of submitting their Proposals electronically
using E-Procurement Portal of Procuring Agency

17.4 The Consultant must submit:


(a) Technical Proposal: one (1) (b) Financial Proposal: one (1)
On E-Procurement portal of Procuring Agency.

17.7 and 17.9 The Proposals must be submitted no later than:


Date: 24th June 2024

Time: 1500 hours

The Proposal submission address is:

Infrastructure Development Authority of the Punjab (IDAP)


50 B-3, Gulberg III, Lahore

19.1 An online option of the opening of the Technical Proposals is offered: Yes

“The online opening procedure shall be done on E-Procurement Portal. Technical


Proposal shall be opened on E-Procurement Portal of Procuring Agency.

The opening shall take place at:


“same as the Proposal submission address”

Date: same as the submission deadline indicated in 17.7.


Time: 1530 hours

19.2 In addition, the following information will be read aloud at the opening of the Technical
Proposals: No additional information

21.1 (i) Eligibility Criteria:


(for FTP) Provide all relevant data on E-Procurement Portal:
The Consultant fulfilling the following basic eligibility criteria shall only be considered for further
evaluation. (relevant documents to be attached):

i. Registration of firm with Pakistan Engineering Council (PEC).


ii. Valid legal entity of the firm e.g., Certificate of registration from SECP (along
with the latest certified copy of Form 29 and Form “A”) or Registrar of firms
(along with a Certified copy of Partnership Deed).
iii. Certificate of registration with Income Tax and Sales Tax under the relevant
Authority.
iv. Affidavit on non-judicial stamp paper (of value PKR 300/-) that non-
performance of a contract has not occurred within the last ten (10) years. The
Employer may, in case of poor performance of any Bidder as reported by the
employers of the previously awarded contracts, interalia, reject his proposal

Page 22 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

and/or refer the case to the concerned forum(s). Upon such reference, the
concerned forum(s) in accordance with its rules, procedures and relevant
laws of the land take such action as may be deemed appropriate under the
circumstances of the case including blacklisting of such Bidder and debarring
him from participation in future bidding for similar works.
v. Affidavit on non-judicial stamp paper (of value PKR 300/-) declaring
“Applicant/Company is currently not blacklisted/ defaulted by the Employer
and/or Procurement Regulatory Authorities in Pakistan all procuring
agencies.
vi. Provide a separate affidavit on non-judicial stamp paper (of value PKR 300/-
that the information supplied by the firm is correct. (Form GEN - 3)

Note: An Association (Joint Venture/ Consortium) is not allowed.

(ii) Qualification Criteria


Provide all relevant data on E-Procurement Portal
The qualification will be based on the Consultant’s meeting the following qualification criteria
regarding their financial soundness, experience record and quality of its personnel capabilities and
other relevant information as demonstrated by the Consultant’s response to this RFP.
Qualification criteria as mentioned below is applicable for applicants:

Category Description Marks

A Financial Soundness 10

B Experience Record 60

C Personnel Capabilities 30

Total 100
Marks shall only be given if the Forms are filled as per the instructions given in this Document.
No compromise shall be made on the minimum requirements of 50% marks in each
Category (A, B, C) and an overall minimum of 70% marks required to qualify in the
aforesaid qualification criteria.
Criteria, sub-criteria and marking system for the evaluation of Consultants shall be as under:

CATEGORY A: FINANCIAL SOUNDNESS

For financial soundness, audited financial statements for the last three financial
years shall be submitted. No marks shall be given if audited financial statements of
the last three financial years are not attached.
Marks shall be awarded on the basis of the following criteria:

Page 23 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

S. Marks
Category Criteria for Marks
No Assigned
Average Annual turnover for the  Full marks if the average annual turnover
last three financial years of the last three financial years is PKR
commencing from 1st July and 200 million or above.
ending on 30th June for each  For average annual turnover of less than
I year. 10 PKR 200 million, marks shall be
awarded as per the following formula: (A
Form TECH-01 shall be filled / 200) x 10
‘A’ is the average annual turnover
 No marks if the average annual
turnover is less than PKR 100 million.

Category ‘A’ Total 10


CATEGORY B: EXPERIENCE RECORD
Marks shall be awarded on the basis of the following criteria for evaluation of the experience of the
Consultant.
Sr. Description Marks Criteria for Marks Obtained
No Assigned
a) Projects of *similar nature  22 marks will be given if applicant has
of minimum **value PKR. 30 completed at least Four Projects.
Million each (or of equivalent  For Completed Projects less than Four,
US $ value) or more marks shall be awarded as per the following
Completed in last ten (10) formula: (No. of Completed Projects / 04) x
years.
22
*Similar nature project
25 03 additional Marks will be given to the
includes Resident
construction supervision applicant, if completed Resident construction
of Building projects. supervision of one or more hospital/ healthcare
Consultant should clearly building Project of ** value PKR 20 million or
state all these services above
provided in completed
projects.
For Completed Projects, Completion Certificate
** value means Total Cost of of respective project is mandatory along with
Resident Supervision proof of Consultancy Value. No marks shall be
Consultancy. awarded if the Completion Certificate and proof
(Form Tech 2 & 3 shall be of Consultancy Value is not attached along with
filled) Form Tech. 2 & 3.
In case, Project is scattered at different/more
than one location, Resident Construction
Supervision cost for one location shall be more
than PKR 30 Million.

Page 24 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

b) Projects of *similar nature of  18 marks will be given if the applicant has at


minimum **value PKR. 30 least two projects in hand.
Million each (or of equivalent  09 marks will be given if the applicant has
US $ value) or more in-Hand. one project in hand.
*Similar nature project
includes Resident
Construction Supervision 02 additional Marks will be given to the
of Building projects. applicant, if applicant has Resident
Consultant should clearly construction supervision of one or more
state all these services hospital/healthcare building Project of ** value
provided in in-hand projects. PKR 20 million or above in hand.

**value means Total Cost of 20


For in-hand Projects Letter of Award OR
Resident Supervision
contract Agreement of the respective project
Consultancy. along with proof of Consultancy Value is
(Form Tech 4 & 5 shall be mandatory. No marks shall be awarded if a
filled. Letter of Award or Agreement along with
proof of the Consultancy Value is Not
attached along with Form Tech 4 & 5.
In case, Project is scattered at
different/more than one locations, Resident
Construction Supervision cost for one
location shall be more than PKR 30 Million.
c) Design and Resident  Full marks will be given if the applicant has
Construction Supervision completed at least two Projects.
Projects of any civil  For Completed Projects less than two, marks
construction works of shall be awarded as per the following
minimum **consultancy formula: (No. of Completed Projects / 02) x
value PKR. 30 million each (or 15
of equivalent US $ value) or  No Marks will be given if the applicant has
more Completed in Last ten not completed any Project.
(10) Years. 15
For Completed Projects, Completion
** consultancy value means Certificate OR Contract Agreement of
Total Cost of Consultancy. respective project along with proof of
Consultancy Value is mandatory. No marks
shall be awarded if the Completion
Certificate or Contract Agreement along with
proof of Consultancy Value is Not attached
along with Form Tech-6 & 7.
Total 60

CATEGORY C: PERSONNEL CAPABILITIES


Marks shall be awarded on the basis of the qualification and experience of the staff. No
marks shall be awarded if Form TECH 8, 9, 10 & 11 are not filled. The following key
experts shall be evaluated:

Page 25 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Note:
1. Key professional staff proposed shall be permanent employees having a minimum stay with
the firm for such persons is Six months of the firm which shall be established by satisfactory proof
i.e., valid PEC certificate, Salary slips or any other document. No alternative to key professional
staff may be proposed and only one CV shall be submitted for each position. If the employment
of any Employee with the firm is less than 6 months or in the absence of the proof 33% marks
will be deducted.
*2. The Employer shall not consider the Key Personnel already proposed in other proposals
under evaluation with IDAP, or to be awarded/awarded recently/In-Hand by the IDAP. This will
affect adversely the marking of these professionals in the evaluation of the technical proposal.
Their secured points shall be liable to be reduced by 100% if their name appears in more than
one (01) proposal.
*It is only applicable to Key Personnel mentioned at Sr. no. (i) to (v)
No of Marks Education &
S. No. Description Professionals Experience (Mandatory
Assigned
Requirement)
C Key Personnel – Resident Construction Supervision
B.Sc. Civil Engineering with
minimum 15 years of relevant
experience OR Masters in
relevant field (Civil
Engineering/Project
i) Resident Engineer 01 04 Management etc.) with
minimum 13 years of relevant
experience. The individual
must be registered as
“Professional Engineer” with
the PEC.
B.Sc. Civil Engineering with
minimum 8 years of relevant
experience OR Masters in
relevant field (Civil
Engineering/Project
Assistant Resident
ii) 01 02 Management etc.) with
Engineer
minimum 6 years of relevant
(Civil)
experience. The individual must
be a Registered Engineer with
the PEC.

Page 26 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

B.Sc. Elec/Mech. Engineering


with minimum 8 years of
relevant experience (PEC
Registered) OR M.S in
Elec/Mech.
Assistant Resident
iii) 01 02 Engineering/Project
Engineer (MEP)
Management with minimum 6
years of relevant experience.
The individual must be a
Registered Engineer with the
PEC.

B.Sc. Civil
Engineering/Geological
Engineering with minimum 8
QA/QC & Material
iv) 01 02 years of relevant experience.
Engineer
The individual must be
registered with the Pakistan
Engineering Council.

B.Sc. Engineering with


minimum 8 years of relevant
experience on large scale
building projects OR M.S in
Planning & Project Engineering/Project
v) 01 02
Controls Specialist Management with minimum 6
years of relevant experience.
The individual must be
registered with the Pakistan
Engineering Council.

Page 27 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Bachelor's in Architecture or
Architectural Engineering with
minimum 10 years relevant
experience or Masters in
relevant discipline with
vi) Architect 01 02 minimum 08 years relevant
experience. The individual
must be registered with the
Pakistan Council for
Architects & Town Planners
(PCATP).

B.Sc. Computer Science/IT


with minimum 10 years of
IT/Networking relevant experience or
vii) 01 02
Specialist Masters in relevant discipline
with minimum 08 years of
relevant experience.

B.Sc. Biomedical/Electrical
Engineering with a minimum
of 10 years total experience or
Masters in relevant discipline
vii) Biomedical Specialist 01 02 with a minimum of 08 years
total experience. Total
experience shall include a
minimum of 06 years of
relevant experience.

Non-Key Personnel

B.Sc Civil Engineering with


i) Junior Engineer - Civil 01 01 preferably 03 years of
experience

Page 28 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

B.Sc Electrical Engineering


Junior Engineer -
ii) 01 01 with preferably 03 years of
Electrical
experience

DAE Civil with minimum 10


04 years of relevant experience,
Field/Site Inspectors
iii) 04 (01 Marks for OR B.Sc. Engineering with
(Civil)
each) minimum 06 years of relevant
experience.

DAE Elec/Mech. with minimum


10 years of relevant experience,
Field/Site Inspector
iv) 01 01 OR B.Sc. Engineering
(MEP)
(Elec/Mech.) with minimum 06
years of relevant experience.

02
DAE Civil with minimum 10
v) Quantity Surveyor 02 (01 Marks for years of relevant experience
each)

DAE Civil with a minimum of 10


vi) Surveyor 01 01 years of relevant experience.

Graduate with NEBOSH/OSHA


vii) HSE Officer 01 01 certification and minimum 03
years’ of relevant experience

Graduation with relevant


experience of three (03) years.
viii) Document Controller 01 01 Proficient user of MS office /
other equivalent software.

Sub-category C Total 30

The minimum technical score (St) required to pass is: 70

23.1 An online option of the opening of the Financial Proposals is offered: Yes

Page 29 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

“The online opening procedure shall be done publicly on E-Procurement Portal at least
five days after Technical Evaluation announcement to bidders in the presence of the
consultants’ representatives who choose to attend. One Time Password will be sent to
the bidder Authorized Email and/or SMS for Opening of Financial Proposal. Proposal will
be opened through that one Time Password.

25.1
Consultant’s Financial Proposal shall include all applicable taxes and duties in accordance with
the prevailing Laws, Rules, and Regulations.

26.1 Proposal shall be submitted in only PKR.

27.1 The lowest evaluated Financial Proposal (Fm) is given the maximum financial score (Sf)
(QCBS only) of 100.

The formula for determining the financial scores (Sf) of all other Proposals is calculated
as following:

Sf = 100 x Fm/ F, in which “Sf” is the financial score, “Fm” is the lowest price, and “F” the price
of the proposal under consideration.

The weights given to the Technical (T) and Financial (P) Proposals are:
T =80%, and
P =20%

Proposals are ranked according to their combined technical (St) and financial (Sf) scores using
the weights (T = the weight given to the Technical Proposal; P = the weight given to the Financial
Proposal; T + P = 1) as following: S = St x T% + Sf x P%.
The Consultant achieving the highest combined technical and financial score (S) will be
considered for award of the Contract.

D. Negotiations and Award

28.1 Expected date and address for Contract negotiations:


Will be communicated later to the Consultant achieving highest combined technical and
financial score (S).

30.1, 12.4, Amount of Bid Security shall be PKR 1,000,000 (One Million only)
12.5 & 12.6

31.1 Successful consultant shall be required to submit Stamp duty (under Stamp Duty Act 1899) within
Seven (07) days of the demand by the procuring agency for signing of contract.

Page 30 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Section 3. Technical Proposal – Standard Forms


[Notes to Consultant shown in brackets [ ] throughout Section 3 provide guidance to the Consultant to
prepare the Technical Proposal; they should not appear on the Proposals to be submitted.]

Page 31 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

CHECKLIST OF REQUIRED FORMS

GEN-1 Technical Proposal Submission Form along with Power of Attorney to sign the Proposal.
GEN-2 General Information Form
GEN-3 Affidavit of Correctness
GEN-4 Litigation History

TECH-1 Financial Soundness

TECH-2 Consultant’s Experience (Summary of Similar Nature Project Completed in Last 10 Years)
TECH-3 Consultant’s Experience (Detail of Similar Nature Project Completed in Last 10 Years)

TECH-4 Consultant’s Experience (Summary of Similar Nature Project in hand)


TECH-5 Consultant’s Experience (Detail of Similar Nature Project in Hand)

TECH-6 Consultant’s Experience (Summary of Civil Works Consultancy & Resident Construction
Supervision Completed in Last 10 Years)
TECH-7 Consultant’s Experience (Detail of Civil Works Consultancy & Resident Construction
Supervision Completed in Last 10 Years)

TECH-8 Team Composition and Task Assignments.

TECH-9 Curriculum Vitae (CV) for Proposed Professional Staff.

TECH-10 Staffing Schedule

TECH-11 Work Schedule

Annexure- A: format of Bank Guarantee (if required)

All pages of the original Technical and Financial Proposal shall be initialed by the same
authorized representative of the Consultant who signs the Proposal.

Page 32 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

FORM GEN-1

TECHNICAL PROPOSAL SUBMISSION FORM

{Location, Date}

To: [Name and address of Procuring Agency]

Dear Sirs:

We, the undersigned, offer to provide the consulting services for {Insert title of assignment} in
accordance with your Request for Proposal dated {Insert Date} and our Proposal. [Select appropriate
wording depending on the selection method stated in the RFP] We are hereby submitting our Proposal
on E-Procurement Portal of IDAP, which includes Technical Proposal and a Financial Proposal

{If the Consultant is a Joint Venture/ Consortium, insert the following:} We are submitting our
Proposal a Joint Venture/ Consortium with: {Insert a list with full name and the legal address of each
member, and indicate the lead member}. We have attached a Original copy of the JV/ Consortium
agreement signed by every participating member, which details the legal structure of and the confirmation
of joint and severable liability of the members of the said Joint Venture/ Consortium.

We hereby declare that:

(a) All the information and statements made in this Proposal are true and we accept that any
misinterpretation or misrepresentation contained in this Proposal may lead to our
disqualification by the Procuring Agency.

(b) Our Proposal shall be valid and remain binding upon us until {insert day, month and year
in accordance with ITC 12.1}.

(c) We have no conflict of interest in accordance with ITC 3.

(d) In competing for and, if the award is made to us, in executing the Contract, we undertake
to observe the laws against fraud and corruption, including bribery, in force in the
Province of the Procuring Agency.

(e) Except as stated in the Data Sheet, Clause 12.7, we undertake to negotiate a Contract
on the basis of the proposed Key Experts. We accept that the substitution of Key Experts
for reasons other than those stated in ITC Clause 12 and ITC Clause 28.4 may lead to
the termination of Contract negotiations.

Page 33 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

(f) Our Proposal is binding upon us and subject to any modifications resulting from the
Contract negotiations.

We undertake, if our Proposal is accepted and the Contract is signed, to initiate the Services
related to the assignment no later than the date indicated in the Contract.

We understand that the Procuring Agency is not bound to accept any Proposal that the Procuring
Agency receives.

We remain,

Yours sincerely,

Authorized Signature {In full and initials}:


Name and Title of Signatory:
Name of Consultant {Company’s name or JV’s/ Consortium name}:
In the capacity of:

Address:
Contact information {phone and e-mail}:

Page 34 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form GEN-2 General Information

Applicant applying for consultancy services is required to complete the information in this form.
Nationality information is also to be provided for foreign owners or Consultants who are forming part
of the Joint Venture as required under the PEC Bye-Laws for Joint Venture.

1. Name of Consultant

2. Head Office Address

3. Telephone

4. Fax

5. Type of Organization

6. Place of Incorporation/Registration Year of incorporation/registration

7. NTN#

8. Name, Designation and Mobile Number of Consultant’s Representative

Detail of Owners/ Directors

Name Designation Nationality

1.

2.

3.

4.

5.

Page 35 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form GEN-3 AFFIDAVIT FOR CORRECTNESS OF INFORMATION

(To be printed on PKR 100 Stamp Paper)

Name:

(Applicant)

I (we), the undersigned, do hereby certify that all the statements made in the Qualification Forms and in the
supporting documents are true, correct and valid to the best of my knowledge and belief and may be verified
by Employer if the Employer, at any time, deems it necessary.

The undersigned hereby authorizes and request the bank, person, firm or corporation to furnish any additional
information requested by the Infrastructure Development Authority of the Punjab (IDAP) deemed necessary to
verify this statement regarding my (our) competence and general reputation.

The undersigned understands and agrees that further qualifying information may be requested and agrees to
furnish any such information at the request of the IDAP.

Signed by an authorized Officer of the


firm

Title of Officer Name of


Firm Date

Page 36 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form GEN-4 Litigation History for the last 10 years

Name: (Applicant)

Name of
Client, Disputed Award FOR or
Cause of amount
Description of (Current value in PKR AGAINST Remarks by
Year litigation and
Contract or US$ equivalent) Applicant Applicant
matter in dispute

Attach an Affidavit on non-judicial stamp paper that non-performance of a contract has not occurred
within the last ten years based on information on all settled disputes or litigation.

Page 37 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form TECH-1 Financial Soundness

The consultant will provide financial information to demonstrate that they meet the requirements of the
Evaluation Criteria. If necessary, use separate sheets to provide complete information. A copy of the
audited financial statements of the past three (3) financial years must be attached.

Turnover
Year Rupees in Million
(in Actual Currency)
2022 – 2023
2021 – 2022
2020 – 2021
Average of above

Page 38 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form TECH-2 Consultant’s Experience


Summary of Similar Nature Project Completed in Last Ten (10) Years

Name of Applicant

Year of Value in PKR


Project Name Completion Location (Million)

*Each project provided in this form requires a corresponding Form TECH-3 and adequate documentary
evidence in order to be eligible for consideration

Page 39 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form TECH-3 Consultant’s Experience


Detail of Similar Nature Project Completed in the Last ten (10) Years

Name of Applicant

A separate form with adequate documentary evidence (Completion Certificate/ Contract Agreement
indicating Consultancy Cost) shall be provided for each project in Form TECH-2.

1. Name of Contract

Location

2. Name of Employer

3. Employer Address
....................................................................................................................

4. Nature of Works and special features of the consultancy Assignment

....................................................................................................................
....................................................................................................................

5. Contract Role (Tick One)

(a) Sole Consultant (b) Sub- Consultant (c) Member in a JV


Total Project Cost
6.
PKR USD

7. Value of the total Consultancy contract

PKR…………. USD……………

8. Date of Award

9. Date of Completion

10. Name of senior professional staff of your firm involved and functions performed in this
project (indicate most significant profiles such as Project Director/Coordinator, Team
Leader):

Page 40 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form TECH-4 Consultant’s Experience


Summary of Similar Nature Project in-Hand

Name of Applicant

Project Date of Expected Date Location Value in PKR


Name Award of Completion (Million)

*Each project provided in this form requires a corresponding Form TECH-5 and adequate
documentary evidence in order to be eligible for consideration.

Page 41 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form TECH-5 Consultant’s Experience


Detail of Similar Nature Project in-Hand

Name of Applicant

A separate form with adequate documentary evidence (Letter of Award/ Agreement indicating
Consultancy Cost) shall be provided for each project in Form TECH-4.

1. Name of Contract

Location

2. Name of Employer

3. Employer Address
....................................................................................................................

4. Nature of Works and special features of the consultancy Assignment

....................................................................................................................
....................................................................................................................

5. Contract Role (Tick One)

(a) Sole Consultant (b) Sub- Consultant (c) Member in a JV


Total Project Cost
6.
PKR USD

7. Value of the total contract

PKR…………. USD……………

8. Date of Award

9. Planned Date of Completion

Page 42 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

TECH-6 Consultant’s Experience


Summary of Civil Works Consultancy & Resident Construction Supervision Projects Completed
in the last 10 Years

Name of Applicant

Year of Value in PKR


Project Name Completion Location (Million)

*Each project provided in this form requires a corresponding Form TECH-7 and adequate documentary
evidence in order to be eligible for consideration

Page 43 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form TECH-7 Consultant’s Experience


Detail of Civil Works Consultancy & Resident Construction Supervision Projects Completed in
last 10 Years

Name of Applicant

A separate form with adequate documentary evidence (Completion Certificate/ Contract Agreement
indicating Consultancy Cost) shall be provided for each project in Form TECH-6.

1. Name of Contract

Location

2. Name of Employer

3. Employer Address
....................................................................................................................

4. Nature of Works and special features of the consultancy Assignment

....................................................................................................................
....................................................................................................................

5. Contract Role (Tick One)

(a) Sole Consultant (b) Sub- Consultant (c) Member in a JV


Total Project Cost
6.
PKR USD

7. Value of the total Consultancy contract

PKR…………. USD……………

8. Date of Award

9. Date of Completion

10. Name of senior professional staff of your firm involved and functions performed in this
project (indicate most significant profiles such as Project Director/Coordinator, Team
Leader):

Page 44 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form TECH-8 Team Composition and Task Assignments

Professional Staff

Name of Staff CNIC No./Passport Position


Firm Area of Expertise Task Assigned
No. Assigned

Page 45 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form TECH-9
Curriculum Vitae (CV) for Proposed Professional Staff

1. Proposed Position [only one candidate shall be nominated]:

2. Name of Consultant [Insert the name of firm proposing the staff]:

3. Name of Staff [Insert full name]:

4. Date of Birth: Nationality:

5. CNIC or Passport No: Contact No:

6. Education:

Degree Major/Minor Institution Date (MM/YYYY)

7. Membership of Professional Associations: [Attach Membership Certificates]

8. Other Training [Indicate significant training since degrees under 6 - Education were obtained]:

9. Languages [For each language indicate proficiency: good, fair, or poor in speaking, reading, and
writing]:
______________________________________

10. Employment Record [Starting with present position, list in reverse order every employment held by
staff member since graduation, giving for each employment (see format here below): dates of
employment, name of employing organization, positions held.]:
Employer Position From (MM/YYYY) To (MM/YYYY)

Page 46 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

11. Detailed Tasks Assigned

[List all tasks to be performed under this assignment]

12. Work Undertaken that Best Illustrates Capability to Handle the Tasks Assigned

[Among the assignments in which the staff has been involved, indicate the following information for
those assignments that best illustrate staff capability to handle the tasks listed under point 11.]

1) Name of assignment or project:


Year:
Location:
Client:
Main project features:
Positions held:
Activities performed:

2) Name of assignment or project:


Year:
Location:
Client:
Main project features:
Positions held:
Activities performed:

3) Name of assignment or project:


Year:
Location:
Client:
Main project features:
Positions held:
Activities performed:
13. Certification:

Page 47 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes my
qualifications, my experience, and myself. I understand that any wilful misstatement described herein may lead
to my disqualification or dismissal, if engaged.

Date:
[Signature of staff member] Day/Month/Year
Full name and signatures of authorized representative:

Page 48 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

FORM TECH-10 STAFFING SCHEDULE1

Full time input


Part time input
Year: ________
Name 28. Staff input (in the form of a bar chart)2
29. Total staff-
27. Sr. month input
No.
of
Staff1 Aug Sep Oct Nov Dec Jan Feb Mar April May June July Home Field3 Total
[Home]
1
[Field]
2

9
Total

1. For Professional Staff the input should be indicated individually; for Support Staff it should be indicated
by category (e.g.: draftsmen, clerical staff, etc.).
2. Months are counted from the start of the assignment. For each staff indicate separately staff input
for home and fieldwork.
3. Fieldwork means work carried out at a place other than the Consultant's home office.

Page 49 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form TECH-11 Work Schedule

Year:
__________
Months2
N° Activity1
Aug Sep Oct Nov Dec Jan Feb Mar April May June July
1
2
3
4
5

1. Indicate all main activities of the assignment, including delivery of reports (e.g.: inception, interim, and final
reports), and other benchmarks such as Employer’s review of reports and approvals. For phased
assignments indicate activities, delivery of reports, and benchmarks separately for each phase.
2. Duration of activities shall be indicated in the form of a bar chart.

Page 50 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Annex-A
BID SECURITY
(Bank Guarantee)

Security Executed on _______________________________________________________


(Date)
Name of Surety (Bank) with Address: ________________________________________
(Scheduled Bank in Pakistan)
Name of Principal (Bidder) with Address _______________________________________
________________________________________________________________________
Penal Sum of Security Rupees. _____________________ (Rs. _____________________)
Bid Reference No. _______________________________________________________
KNOW ALL MEN BY THESE PRESENTS, that in pursuance of the terms of the Bid and at
the request of the said Principal (Bidder) we, the Surety above named, are held and firmly bound
unto ______________________________________________________
(hereinafter called the 'Employer') in the sum stated above for the payment of which sum well
and truly to be made, we bind ourselves, our heirs, executors, administrators and successors,
jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Bidder has submitted
the accompanying Bid dated ______ for Bid No. _______ for_______(Particulars of Bid) to
the said Employer; and

WHEREAS, the Employer has required as a condition for considering said Bid that the Bidder
furnishes a Bid Security in the above said sum from a Scheduled Bank in Pakistan or from a
foreign bank duly counter-guaranteed by a Scheduled Bank in Pakistan, to the Employer,
conditioned as under:

that the Bid Security shall remain in force up to and including the date 28 days after the deadline
for the validity of bids as stated in the Instructions to Bidders or as it may be extended by the
Employer, notice of which extension(s) to the Surety is hereby waived;
that the Bid Security of unsuccessful Bidders will be returned by the Employer after the expiry
of the grievance period; and
that in the event of failure of the successful Bidder to execute the proposed Contract Agreement
for such work, the entire said sum be paid immediately to the said Employer pursuant to Clause
9.1 of the Instruction to Consultant for the successful Bidder's failure to perform.

NOW, THEREFORE, if the successful Bidder shall, within the period specified therefore, on
the prescribed form presented to him for signature enter into a formal Contract with the said
Employer in accordance with his Bid as accepted and proper fulfilment of the said Contract or
in the event of non-withdrawal of the said Bid within the time specified for its validity then this
obligation shall be void and of no effect, but otherwise to remain in full force and effect.

Page 51 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

PROVIDED THAT the Surety shall forthwith pay the Employer the said sum upon first written
demand of the Employer (without cavil or argument) and without requiring the Employer to
prove or to show grounds or reasons for such demand, a notice of which shall be sent by the
Employer by registered post duly addressed to the Surety at its address given above.

PROVIDED ALSO THAT the Employer shall be the sole and final judge for deciding whether
the Principal (Bidder) has duly performed his obligations to sign the Contract Agreement, or
has defaulted in fulfilling said requirements and the Surety shall pay without objection the said
sum upon demand from the Employer forthwith and without any reference to the Principal
(Bidder) or any other person.

IN WITNESS WHEREOF, the above bounden Surety has executed the instrument under its
seal on the date indicated above, the name and seal of the Surety being hereto affixed and these
presents duly signed by its undersigned representative pursuant to authority of its governing
body.
SURETY (Bank)

WITNESS: Signature

1. Name

Title

Corporate Secretary (Seal) Corporate Guarantor (Seal)

2.

__________________________
Name, Title & Address

Page 52 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Section 4. Financial Proposal - Standard Forms

{Notes to Consultant shown in brackets { } to provide guidance to the Consultant to prepare the Financial
Proposals; they should not appear on the Financial Proposals to be submitted.}

Financial Proposal Standard Forms shall be used for the preparation of the Financial Proposal according
to the instructions provided in Section 2.

FIN-1 Financial Proposal Submission Form

FIN-2 Summary of Costs

FIN-3 Breakdown of Costs by Activity

FIN-4 Breakdown of Remuneration

FIN-5 Direct expenses

Page 53 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

FORM FIN-1
FINANCIAL PROPOSAL SUBMISSION FORM

{Location, Date}

To: {Name and address of Procuring Agency}

Dear Sirs:

We, the undersigned, offer to provide the consulting services for {Insert title of assignment} in
accordance with your Request for Proposal dated [Insert Date] and our Technical Proposal.

Our attached Financial Proposal is for the amount of {Indicate the corresponding to the amount(s)
currency (ies)} {Insert amount(s) in words and figures},This amount is inclusive of all applicable taxes. .
{Please note that all amounts shall be the same as in Form FIN-2}.

Our Financial Proposal shall be valid and remain binding upon us, subject to the modifications
resulting from Contract negotiations, until [in accordance with ITC 12.1].

We understand you are not bound to accept any Proposal you receive.

We remain,

Yours sincerely,

Authorized Signature {In full and initials}:


Name and Title of Signatory:
In the capacity of:
Address:
E-mail: _________________________

Page 54 of 125
Appendices Lump-Sum

Form FIN-2 Summary of Costs

Costs
Item
Pak Rupees

Construction Supervision Phase

Defect Liability Phase

Total Costs of Financial Proposal1

PRA @16%

Total Costs of Financial Proposal


(Inclusive of PRA)

1. Indicate the total costs, including of local taxes, such total costs must coincide with the sum of the
relevant Subtotals indicated in all Forms FIN-3 provided with the Proposal.

Page 55 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form FIN-3 Breakdown of Costs by Activity1

Costs
Item
Pak Rupees

Remunerations
Construction Supervision Phase
(Inclusive of all taxes)
Direct Cost

Remunerations
Defect Liability Phase (Inclusive of all
taxes)
Direct Cost

Total Costs of Financial Proposal1


(Inclusive of all taxes)

1. Form FIN-3 shall be filled at least for the whole assignment. In case some of the
activities require different modes of billing and payment (e.g.: the assignment is
phased, and each phase has a different payment schedule), the Consultant shall
fill a separate Form FIN-3 for each group of activities. The sum of the relevant
Subtotals of all Forms FIN-3 provided must coincide with the Total Costs of Financial
Proposal indicated in Form FIN-2.
2. Names of activities (phase) should be the same as or correspond to the ones
indicated in the second column of Form TECH-11.
3. Short description of the activities whose cost breakdown is provided in this Form.
4. Remuneration and Direct Expenses must respectively coincide with relevant Total
Costs indicated in Forms FIN-4, and FIN-5.

Page 56 of 125
Appendices Lump-Sum

Form FIN-4 Breakdown of Remuneration1

Staff-month Total Input in Amount


Name2 Position3
Rate4 months
[Home]
[Field]

1. Professional Staff should be indicated individually; Support Staff should be indicated per
category.
2. Indicate separately staff-month rate and currency for home and fieldwork

Page 57 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Form FIN-5 Breakdown of Direct Expenses

N Description Unit Unit Cost

Page 58 of 125
Appendices Lump-Sum

Section 5. Eligible Countries

All the Consultants are allowed to participate in the subject procurement without regard to nationality, except
consultants of some nationality, prohibited in accordance with policy of the Government.

Following countries are ineligible to participate in the procurement process:


1. India
2. Israel

Ministry of Interior, Government of Pakistan has notified List of Business-Friendly Countries (BVL), Latest
information may be confirmed from the relevant quarter.

Page 59 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Section 6. Corrupt Practices


“Corrupt practices” in respect of procurement process, shall be as given in S-2 (d) of PPRA, Act,
2009:
[(d) “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value to
influence the action of a public official, bidder or Contractor in the procurement process or in
Contract execution to the detriment of the procuring agency; or misrepresentation of facts in order
to influence a procurement process or the execution of a Contract, collusive practices among
bidders (prior to or after bid submission) designed to establish bid prices at artificial,
noncompetitive levels and to deprive the procuring agency of the benefits of free and open
competition and any request for, or solicitation of anything of value by any public official in the
course of the exercise of his duty; it may include any of the following:
i. coercive practice by impairing or harming, or threatening to impair or harm, directly or
indirectly, any party or the property of the party to influence the actions of a party to
achieve a wrongful gain or to cause a wrongful loss to another party;
ii. collusive practice by arrangement between two or more parties to the procurement
process or Contract execution, designed to achieve with or without the knowledge of the
procuring agency to establish prices at artificial, noncompetitive levels for any wrongful
gain;
iii. offering, giving, receiving or soliciting, directly or indirectly, of anything of value to
influence the acts of another party for wrongful gain;
iv. any act or omission, including a misrepresentation, that knowingly or recklessly misleads,
or attempts to mislead, a party to obtain a financial or other benefit or to avoid an
obligation;
v. obstructive practice by harming or threatening to harm, directly or indirectly, persons or
their property to influence their participation in a procurement process, or affect the
execution of a Contract or deliberately destroying, falsifying, altering or concealing of
evidence material to the investigation or making false statements before investigators in
order to materially impede an investigation into allegations of a corrupt, fraudulent,
coercive or collusive practice; or threatening, harassing or intimidating any party to
prevent it from disclosing its knowledge of matters relevant to the investigation or from
pursuing the investigation, or acts intended to materially impede the exercise of
inspection and audit process
Blacklisting & Debarment:
Blacklisted Consultants and those found involved in “Corrupt Practices” are not
allowed to participate in bidding.

Substantial Requirements & Procedure for Blacklisting & Debarment:

Page 60 of 125
Appendices Lump-Sum

As per S-17A of PPRA, Act, 2009:


17A. Blacklisting.– (1) A procuring agency may, for a specified period and in the
prescribed manner, debar a bidder or Contractor from participating in any public
procurement process of the procuring agency, if the bidder or Contractor indulges
in corrupt practice or any other prescribed practice.
(2) The Managing Director may, in the prescribed manner, debar
a bidder or Contractor from participating in any public procurement process
of all or some of the procuring agencies for a specified period.
(3) Any person, aggrieved from a decision of a procuring agency,
may within prescribed period prefer a representation before the Managing
Director.
(4) A procuring agency or any other person, aggrieved from a
decision of the Managing Director, may within prescribed period prefer a
representation before the Chairperson whose decision on such
representation shall be final.]

As per rule 21 of PPR-14:

21. Blacklisting.–(1) A procuring agency may, for a specified period, debar a bidder
or Contractor from participating in any public procurement process of the procuring
agency, if the bidder or Contractor has:
(a) acted in a manner detrimental to the public interest or good practices;
(b) consistently failed to perform his obligation under the Contract;
(c) not performed the Contract up to the mark; or
(d) indulged in any corrupt practice.
(2) If a procuring agency debars a bidder or Contractor under sub-rule (1), the
procuring agency:
(a) shall forward the decision to the Authority for publication on the
website of the Authority; and
(b) may request the Authority to debar the bidder or Contractor for
procurement of all procuring agencies.
(3) The Managing Director may debar a bidder or Contractor of any procuring
agency from participating in any public procurement process of all or some of the
procuring agencies for such period as the Managing Director may determine.
(4) Any person aggrieved by a declaration made under rule 20 or a decision
under sub-rule (1) of this rule may, within thirty days from the date of the publication
of the information on the website of the Authority, file a representation before the

Page 61 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Managing Director and the Managing Director may pass such order on the
representation as he may deem fit.
(5) Any person or procuring agency aggrieved by an order under sub-rule (3) or
(4) may, within thirty days of the order, file a representation before the Chairperson
and the Chairperson may pass such order on the representation as he may deem
appropriate.
(6) The mechanism or process for barring a bidder or Contractor from
participating in procurement process of a procuring agency, procuring agencies and a
representation under this rule is specified in the Schedule appended to these rules.
As per Schedule appended with PPR-14:
SCHEDULE
see sub-rule (6) of rule 21
BLACKLISTING MECHANISM OR PROCESS
1. The procuring agency may, on information received from any resource, issue
show cause notice to a bidder or Contractor.
2. The show cause notice shall contain:
(a) precise allegation, against the bidder or Contractor;
(b) the maximum period for which the procuring agency proposes to debar
the bidder or Contractor from participating in any public procurement of
the procuring agency; and
(c) the statement, if needed, about the intention of the procuring agency to
make a request to the Authority for debarring the bidder or Contractor
from participating in public procurements of all the procuring agencies.
3. The procuring agency shall give minimum of seven days to the bidder or
Contractor for submission of written reply of the show cause notice.
4. In case, the bidder or Contractor fails to submit written reply within the
requisite time, the procuring agency may issue notice for personal hearing to
the bidder or Contractor/ authorize representative of the bidder or Contractor
and the procuring agency shall decide the matter on the basis of available record
and personal hearing, if availed.
In case the bidder or Contractor submits written reply of the show cause notice, the
procuring agency may decide to file the matter or direct issuance of a notice to
the bidder or Contractor for personal hearing.
6. The procuring agency shall give minimum of seven days to the bidder or
Contractor for appearance before the specified officer of the procuring agency
for personal hearing.

Page 62 of 125
Appendices Lump-Sum

7. The procuring agency shall decide the matter on the basis of the available record
and personal hearing of the bidder or Contractor, if availed.
8. The procuring agency shall decide the matter within fifteen days from the
date of personal hearing unless the personal hearing is adjourned to a next
date and in such an eventuality, the period of personal hearing shall be reckoned
from the last date of personal hearing.
9. The procuring agency shall communicate to the bidder or Contractor the order
of debarring the bidder or Contractor from participating in any public
procurement with a statement that the bidder or Contractor may, within thirty
days, prefer a representation against the order before the Managing Director of
the Authority.
10. The procuring agency shall, as soon as possible, communicate the order of
blacklisting to the Authority with the request to upload the information on its
website.
11. If the procuring agency wants the Authority to debar the bidder or Contractor
from participating in any public procurement of all procuring agencies, the
procuring agency shall specify reasons for such dispensation.
12. The Authority shall immediately publish the information and decision of
blacklisting on its website.
13. In case of request of a procuring agency under para 11 or representation of any
aggrieved person under rule 21, the Managing Director shall issue a notice for
personal hearing to the parties and call for record of proceedings of blacklisting.
The parties may file written statements and documents in support of their
contentions.
14. In case of representation of any aggrieved person or procuring agency under
rule 21, the Chairperson shall issue a notice for personal hearing to the parties
and may call for the record of the proceedings. The parties may file written
statements and documents in support of their contentions.
15. In every order of blacklisting under rule 21, the procuring agency shall record
reasons of blacklisting and also reasons for short, long or medium period of
blacklisting.
16. The Authority shall upload all the decisions under rule 21, available with it, on
its website. But the name of a bidder or Contractor shall immediately be
removed from the list of blacklisted persons on expiry of period of blacklisting
or order of the competent authority to that effect, whichever is earlier.
17. An effort shall be made for electronic communication of all the notices and
other documents pursuant to this mechanism or process.

Page 63 of 125
REQUEST FOR PROPOSAL FOR CONSULTANCY SERVICES

Section 7. Terms of References

Page 64 of 125
TERMS OF REFERENCE (TORs)
FOR RESIDENT CONSTRUCTION SUPERVISION CONSULTANT
1. INTRODUCTION
1.1. This Section outlines requirements about construction supervision services to be provided by the Consultant.
1.2. The Consultant is required to provide full time Post-Contract Resident Supervision, Quantity Surveying and
Project Management Consultancy Services in accordance with Consultancy Services Agreement (CSA), and
all relevant notices or circulars or directions issued (or will be issued) by the Infrastructure Development
Authority of the Punjab (IDAP), Government of the Punjab.
1.3. The Consultant shall review and assist the IDAP with the coordination and the construction of the Project from
a qualitative perspective, safety and logistical issues. All communication, coordination and management of
issues related to quality, time and cost shall be the responsibility of the Consultant. The Consultant will, as
part of their professional diligence, be expected to identify and report on such items if their observations,
indicate that important issues affecting the success of the Project may have been overlooked. Final Authority
over time and money will however be of the IDAP. The Consultant's staff for the Post Contract and Supervision
Services will supervise the works, make recommendations to the IDAP on contractual issues as and when
requested, and perform quality control reviews as well as advise and assist on cost related issues. Any input,
assistance, collaboration or coordination that may be required to or provided by other consultant(s), shall not
absolve the Consultant from his obligations.

2. DESCRIPTION AND SCOPE OF SERVICES


2.1. General
2.1.1 The Consultant shall, if appointed by IDAP, undertake the duties assigned to ‘the Engineer’ and/or ‘the
Engineer’s Representative’ in the Conditions of Contracts between IDAP and the Contractor(s) for the Project.
The term “Contractor(s)” include but is not limited to any General Contractor(s), Specialist Contractor(s), Lab
Equipment Contractor(s), Furniture Supplier(s) and any other contractors or consultants engaged by IDAP on
any component for completion of the Project. These duties, responsibilities and obligations shall include the
duties and functions assigned to either ‘the Engineer’ and/or ‘the Engineer’s Representative’ (as the case may
be), under the Construction Contracts except for the duties excluded as per the Conditions of the contracts
signed between IDAP and the Contractors (referred herein as the “Construction Contracts”). The Consultant
shall obtain “specific approval” of the Employer before taking any action with regards to the following:
a) Consenting to the sub-letting of any part of the Works under “Subcontracting”
b) Certifying additional cost determined under “Not Foreseeable Physical Obstructions or Conditions”.
c) Any action relating to “Performance Security” and “Insurances”.
d) Any action relating to “Suspension”
e) Any action relating to “Extension of Time for Completion”
f) Any action relating to “Liquidated Damages for Delay” or Payment of Bonus for Early Completion of Works
g) Issuance of “Taking Over Certificate”
h) Issuing or Instructing a Variation, except:

IDAP | TORs for Construction Supervision Page 1 of 19

Page 65 of 125
a. In an emergency situation, as stated here below1, and
b. If sum of all such variations during the Contract Period would increase the Contract Price by
less than the ceiling amount stated in the Appendix-A to Bid.
i) Fixing rates or prices for Variations
j) Extra Payment as a result of the Contractor’s Claims under any of the conditions of Construction Contract
or otherwise in connection with the Construction Contract
k) Release of Retention Money to the Contractors
l) Issuance of “Final Payment Certificate(s)”
m) Issuance of “Defects Liability Certificate(s)”
n) To use “Termination Clause” of the Conditions of Contract.
o) Any other limitation(s) indicated in Construction Contract(s) or requirements specified by the Employer at
any time during the CSA.

2.1.2 The Consultant shall have no authority to relieve the Contractor(s) of any of the obligations under the
Construction Contract(s).
2.1.3 Advise IDAP and the Contractors on all matters regarding the requirements and interpretation of the
Construction Contract documents.
2.1.4 Provide the services of staff in accordance with the CSA.
2.1.5 Provide complete site supervision services involving, but not limited to, full inspection of materials on site and
at materials batching/manufacturing/supply plants, equipment, goods, machinery, and all other manufactured
goods, monitoring the schedule, arranging trade tests and samples for testing, evaluating and interrogating
all necessary testing, and verify accurate calibration of equipment and staff. Conduct full inspection, check
and verify requirements of the contractors temporary and permanent works-in-progress, including review and
approval of shop drawings, and all works items and components finished both on site and off site –
prefabrication yards etc. - to confirm and audit works construction quality to specification, drawings and
Contractual requirements. Inspection of the Works, amongst other inspection requirements, shall cover all the
stages of construction and in particular pre and post stages for all embedded and covered works, excavations,
foundations, reinforcement quality and placement, piling, MEP, finishing, architectural, structural, HVAC, Fire
Fighting, IT, Biomedical, Supply & Installation of Fixed & Loose Furniture etc. Responding to the contractors’
clarification requests (Requests for Information-RFIs) in liaison with the designer, as required.
2.1.6 The Consultant may propose any alterations to the design necessitated by the site conditions throughout the
Contract Duration. Such alterations shall be submitted to the designer (IDAP) for review and approval.
2.1.7 The Consultant shall comply with the provisions of the Specifications regulations, terms and conditions,
standard procedures and requirements stipulated within the documents of CSA and the Conditions of
Construction Contracts.
2.1.8 The Consultant shall exercise all reasonable skill, duty of care and due diligence in the performance of the
Services and shall carry out his duties and obligations as set out in the Agreement.

2.2. Resident Supervision

1
If in the opinion of the Engineer an emergency occurs affecting the safety of life or of the Works or of adjoining property, the
Engineer may, without relieving the Contractor of any of his duties and responsibilities under the Construction Contract, instruct
the Contractor to execute all such work or to do all such things as may, in the opinion of the Engineer, be necessary to abate or
reduce the risk.

IDAP | TORs for Construction Supervision Page 2 of 19

Page 66 of 125
2.2.1 The Site Supervision Services to be carried out by the Consultant shall involve, but not limited to, the following
for the duration of the Construction Contracts. The Consultant shall provide the necessary supervisory staff
to be employed during the period of implementation in executive and supervisory capacities in respect of the
construction contracts.

2.2.2 The Consultant shall be appointed to act as “the Engineer" and/or the “Engineer’s Representative” for the
implementation of the Project. The individual who will be nominated by the Consultant to act as “the Engineer”
/ the “Engineer’s Representative” will be subject to approval by IDAP and IDAP may require the Consultant to
replace the individual if he fails to perform to the satisfaction of IDAP. The Consultant shall be fully and
independently responsible for all actions of the appointed individuals.

2.2.3 It will be the responsibility of the Consultant to supervise all operations on behalf of IDAP and to ensure that
the work of the Contractors is carried out in a proper workmanlike manner, with best quality, in an expeditious
manner and in accordance with the contract documents. During the course of providing Services, the
Consultant shall be obligated to abide by and adhere to any standard operating procedures as may be
specified by IDAP. The Consultant shall be responsible for:

a. Issuing Notice to Proceed to the Contractor as per the general conditions of contract in coordination
with the IDAP.
b. Supervising the Setting-out of the buildings within the site as per the Master Plan.
c. Review, scrutinize and approve all Shop drawings submitted by the Contractors.
d. Review, approval and monitoring of Contractors' construction method statements, risk assessments,
shop drawings, project execution plan, project quality assurance & quality control plan, inspection
and test plans and the like.
e. Review, approval and monitoring of the Contractors’ site management plans and diversions and their
maintenance.
f. Inspection of all temporary and permanent works, materials, manufactured goods, Plant & Equipment
arranging sampling and testing as appropriate, Factory Acceptance Testing (FAT), Site Acceptance
Testing (SAT), rejection sub-standard/non- conforming works and materials, enforcing construction
to highest qualitative specification, ensuring appropriate Consultant supervision resources present
on site for duration of the Construction Contracts.
g. Review and processing/approval of Contractors’ materials submittals in accordance with the
Specifications and the procedure specified by IDAP.
h. Review and approval of Contractors proposed sub-contractors and make recommendations to IDAP.
i. Attending and reviewing FAT of the Equipment including preparation of FAT Plan, physically
attending pre-shipment inspection at Original Equipment Manufacturer (OEM) factory, vet the
manufacturing against approved design, drawings, specifications and boundary conditions, certify
the executed tests, identify punch lists & oversee its completion and issuance of the FAT Reports in
the template approved by IDAP.
j. Evaluating and monitoring added value requirements and in particular undertake value engineering
evaluations of Contractors’ proposals (if any).
k. Reviewing, analyzing, approving and monitoring the Contractors’ Work programmes, their updates
and revisions, procedures for cost control, change control, risk management, document management
and reporting, advising on logic, misnomers, rescheduling requirements all in accordance with
industry best practices.

IDAP | TORs for Construction Supervision Page 3 of 19

Page 67 of 125
l. Keeping complete records of Project documents which include but are not limited to: records of work
executed (daily and contemporaneously), Test Results, Drawings, Material Inspection Reports and
other similar documents. Such records shall be kept in both hard copy and electronic format and
must be furnished to IDAP, as needed.
m. Advising IDAP in the event of persistent failure by a contractor to comply with the Construction
Contract Documents and in the event of unsatisfactory rate of progress and poor quality of the Works
n. Reviewing and recommending alteration proposals for proposed changes and preparing Site
Instructions as directed by the Engineer and/or IDAP, as the case may be.
o. Reviewing and assessing Contractors’ submittals regarding correction of non-conforming works.
p. Evaluation and recommendation of the cost of Contractors’ design/alteration proposals and
Variations.
q. Reviewing the Contractors’ Project Specific Plans in accordance with their contractual requirements
r. Review, evaluation, approval, implementation and regular monitoring of the Contractors’ site Health,
Safety & Environment (HSE) and Quality Assurance / Quality Control procedures & processes and
advise for improving standards, as directed by IDAP. This also includes reviewing and ensuring
compilation of the HSE file and Quality Assurance Records.
s. Preparing and delivering presentations and reports to IDAP and higher authorities.
t. Coordination with other authorities, outside agencies and departments within or outside IDAP, as
directed/required by IDAP.
u. Periodic checking of the principal survey points and line and level of works to ensure work is carried
out as per the Contract Documents.
v. Evaluation, verification, scrutiny, certification and approval of monthly interim payment requests by
the Contractors. The Consultant will ensure and certify the running /interim Certificates for
progressive payments based on BOQ rates and final payment to the Contractor that the Works
executed by the Contractor has been completed in all respects. The Consultant shall ensure
certifying the monthly statements and final statements within the times specified in the respective
Construction Contracts and forward the same to IDAP for arranging payment.
w. Preparation of, and review/evaluation/recommendation of, Variation Orders including determination
of Unit Rate(s) and justification for the variation Items.
x. Review, evaluation and recommendation of Contractors’ claims.
y. Advising IDAP on the contractual matters, as and when requested.
z. Advising IDAP, at appropriate time, whenever any contractual action or obligation is due or about to
become due on part of the IDAP
aa. Reviewing Contractors’ Guarantees, Securities and Insurances and keeping a track of expiries
thereof.
bb. Participation, as necessary, at dispute resolution / arbitration proceedings.
cc. Adhering and ensuring compliance with standard policies, guidelines, manuals (such as QA/QC
manual etc.), procedures and forms prepared by IDAP for Project Management purposes. Upon
commencement of services, the Consultant may request IDAP for a copy of such documents.
dd. Arranging for the commissioning of permanent Works including electrical and mechanical
installations and arrange and supervise all required commissioning/acceptance tests including Tests
on Completion, by all concerned parties.

IDAP | TORs for Construction Supervision Page 4 of 19

Page 68 of 125
ee. Evaluation at Practical/Substantial Completion and issuance of Taking Over Certificate(s),
Maintenance Certificate(s), Defects Liability Certificate(s) and Performance Certificate(s), as
applicable, after approval of IDAP.
ff. Preparing lists of defective and incomplete works (snag lists) and arranging for maintenance work
during the maintenance or defects liability or defects notification periods and arrange final
inspections.
gg. Producing, agreeing and managing procedures for handover to operation and maintenance in
accordance with applicable contracts
hh. Certification of Final account including analysis and recommendation on all claims.
ii. Reviewing and revising Contractors’ As-built Drawings and Records reflecting in detail as-built
conditions and preparing all Documents to allow the Government to operate and maintain the works.
Delivering the aforesaid documents to IDAP after scrutiny and within the time to be indicated by IDAP
Project Team.
jj. All the above responsibilities shall cover the entire Project Duration starting from the Commencement
Date till the issuance of last Taking Over Certificate.
IDAP reserves the right to assign any of the duties of the Consultant, as indicated herein, to any other individual or firm
as deemed appropriate. Such decision shall be taken by IDAP at its sole discretion.
2.3. Project Controls
2.3.1 The Consultant shall be responsible for controlling the time and cost of the Project. The Consultant shall
closely monitor the Progress of Works, cashflow requirements, etc. in accordance with the requirements of
the Construction Contracts. The Consultant shall obtain and maintain all necessary software/ computer
programs, licenses and documents associated with complying to such requirements.
2.3.2 IDAP is using Primavera Systems’ enterprise-level scheduling tool, Primavera P6. The Consultant shall use
Primavera P6 for all planning and scheduling needs and advise the Contractors to use the same application.
2.3.3 Within 07 days of receipt of the Contractors’ updated work programs (every month), the Consultant shall
review and analyze the same and forward it to IDAP. The Consultant shall also provide its
comments/recommendations to IDAP for recovering any delays or lags in the planned progress of the Project.
After consultation with IDAP, the Consultant shall follow up with the Contractors for compliance with such
recovery schedules.
2.3.4 The Consultant shall be responsible for review, evaluation, scrutiny and analysis of the Contractors’ Extension
of Time Claims (using Primavera P6) and submit their detailed recommendations with delay analysis to IDAP,
duly supported by cogent justifications.
2.3.5 The Consultant shall review the Project Execution Plan (PEP), to be prepared by the General Contractor, for
the Project detailed methodologies and project control systems.

2.4. Quality Control & Assurance


2.4.1 The Consultant shall, as a minimum, provide the following services as part of the quality control and
assurance:
a) Supervising testing activities in the Contractors’ laboratory to assure that tests are properly carried
out.
b) Collate test results and issue a copy thereof to IDAP.
c) Monitoring and witnessing of the Contractors sampling and testing to ensure compliance with testing
procedures and reporting any non-compliances (NCRs).

IDAP | TORs for Construction Supervision Page 5 of 19

Page 69 of 125
d) Recommending Corrective Actions for the NCRs and ensuring that all NCRs are closed as per the
recommended corrective actions in a timely manner.
e) Periodic checking of calibration & certification, as applicable, of all laboratory equipment.
f) Reviewing of materials testing results to ensure compliance with Specifications. Recommendations
to the Engineer and IDAP regarding how corrective action is implemented in the case of unacceptable
results, and how borderline materials are dealt with.
g) Sample taking jointly with Contractors’ staff for required independent testing.
h) Reviewing of all independent laboratory test results submitted by the Contractors as part of the
material approval process.
i) Witnessing of all tests required as part of the commissioning of the works.
j) Ensuring the compliance by the Consultant’s own staff and by the Contractors of the Health, Safety
& Environment (HSE) Specification requirements as per the Contract Documents and applicable
laws.

2.4.2 The Consultant shall be fully responsible to ensure that the Works are executed by the Contractor(s) strictly
in accordance with the contract documents.

2.5. Post-Award Costing & Quantity Surveying


2.5.1 For the provision of these services the Consultant shall employ the industry’s best Quantity Surveying
practices in compliance with the requirements of IDAP:
2.5.2 The Scope of Services is as outlined herein and in particular, the Consultant shall note that it is responsible
for the activities listed below. This list is non-exhaustive and may be amplified or added to, at the discretion
of the IDAP, as necessary:
a) The Consultant is to note that adherence to the approved budget is of paramount importance and regular
cost planning exercises shall be required throughout the post contract phase to ensure that the awarded
contract sum is not exceeded.
b) The Consultant is to forewarn IDAP immediately he considers that the budget is being exceeded and is
to offer suggestions and recommendation to rectify the situation.
c) Evaluation of works and recommendation for payments. This includes, without limitation, verification,
scrutiny, certification and approval of monthly interim payment requests by the Contractors. The
Consultant will ensure and certify the running/interim certificates for progressive payments based on
contractual rates thereby confirming that the Works executed by the Contractor have been completed in
all respects. The Consultant shall ensure certifying the monthly statements and final statements within
the times specified in the respective Construction Contracts and forward the same to IDAP for arranging
payment.
d) The Consultant shall prepare Final Accounts incorporating all Variation Orders, Site Instructions and re-
measured items which shall be completed within 30 calendar days of the completion certificates for
Works being issued by the Engineer after approval of IDAP. The format of the Final Accounts shall be to
the approval of IDAP.
e) Monthly check on works completed.
f) Preparation of Monthly schedules of works completed to form the basis of agreement for interim
payments.
g) Evaluation and preparation of contract variation orders including “in-principle” determination of the
Variation and the “valuation” of the Variation.
h) Maintain records of materials delivered to site and collate delivery invoices.
i) Maintain daily records of Plant, Equipment, Machinery and manpower of the Contractors.

IDAP | TORs for Construction Supervision Page 6 of 19

Page 70 of 125
j) Attending and making measurements and computation of quantities of the completed works as per
requirements of the Construction Contracts and those of IDAP’s, computing quantities and costs of the
balance works or any work which is about to be covered and maintain permanent records of all such
measurements as basis for progressive payments to the Contractors and keep the measurement
documents and records in safe custody.
k) Providing Cost to Complete as and when requested. This shall include, without limitation, cost forecast,
price adjustment projections, potential variations & claims, balance works etc.
l) Reviewing and verifying Cashflow projections prepared by the Contractor(s).
m) Preparing revision(s) in PC-I, as may be required by IDAP.

2.6. Project Management Services ("PMS")


2.6.1 The Consultant shall be fully and ultimately responsible to manage the Project as per the best industry
practices.
2.6.2 The Project may be executed in various work packages which may be awarded to different contractors. These
interfaces, if not well managed, may negatively impact the cost and schedule of the Project. Hence, the
Consultant shall be responsible for the interface management and the integration of work packages.
2.6.3 The obligations in this context shall include, but will not be limited to, the following:

a) Managing coordination of all elements of the Project i.e., coordinating tasks, resources, stakeholders,
and any other project elements
b) Identifying and managing interface risks between the stakeholders
c) Anticipating interface issues or scenarios that can or will impede progress, and have advance
measures in place to avoid situations that could negatively impact IDAP’s projected completion goals
and budget
d) Convening regular meetings between stakeholders to identify and manage new interfaces and
issuing collaborative interface reports to capture particular interface workings or outcomes and
mutual distribution of work requirements as per respective contracts
e) Identifying and assessing mutual dependencies and sequencing the Works in a manner to avoid any
delays, rework, extra work or any oversight
f) Managing coordination and sequencing among Civil, MEP, Biomedical Equipment Works and
Furniture Installation & Supply, as the case may be.

2.6.4 The Consultant shall be responsible to prepare, update (monthly) and revise a Master Baseline Schedule
using Primavera P6. The Master Baseline Schedule would be an Integrated Project Schedule (IPS), in which
all tasks, activities, resources, stakeholders, work packages, disciplines, phases, processes, etc. must be
taken into account. The IPS should be prepared within the first month after commencement and it should be
revised, as and when needed, particularly whenever a new stakeholder joins the Project. The IPS should be
so designed that it provides complete information regarding the below:
a) Independent Progress Status of various work packages
b) Mutual dependencies of various stakeholders
c) Status of key milestones
d) Overall progress status of the Project
e) Project Completion Date and budget
f) Earned Value Measurement Parameters (Schedule Performance Index-SPI, Cost
Performance Index-CPI, Schedule Variance-SV, Cost Variance-CV etc.)

IDAP | TORs for Construction Supervision Page 7 of 19

Page 71 of 125
2.6.5 IDAP’s Project Management team, at its discretion, may identify further requirements to the Consultant for
preparation, revision and updating of the IPS.

2.7. Inspection of Drawings and Documents


The Consultants are required to employ computerized methods in carrying out the work all surveys, drawings or
documents produced by the Consultant shall be recorded in digital form; the Consultant shall provide IDAP with copies
of these records in a format approved by IDAP. Drawings shall be in a format suitable for input to the latest version of
AutoCAD and agreed in advance with IDAP.

2.8. Ownership
All data, drawings and documents prepared under this project shall, after being approved by the IDAP, become the
property of IDAP. Such data, drawings and documents shall not be subsequently altered without the prior permission
of IDAP.

2.9. As-Built Drawings and Records


The Consultant's responsibilities with regards to reviewing and approving of As-built drawings and records are as
follows:
2.9.1 The Consultant shall review, revise and approve the Contractors’ drawings reflecting in detail the As-built
conditions of the project. All final approved As-built documentation shall be stamped and signed "Approved
As-Built Records" by the Consultants accordingly.
2.9.2 On conclusion of reviewing, revising and on final approval by the Consultant of the Contractors’ As-built
drawings and documentation, the Consultant shall put together a complete 'As-built Documentation Package'
for the project and deliver it to IDAP.
2.9.3 The 'As-built Documentation Package', shall be reviewed by the Consultant and include the following
documents, without limitation. The Consultant shall obtain these documents from the Contractors’ in required
number of copies:
a) Five prints of every drawing issued by the Consultants, Contractors, Specialist Sub- Contractors and
Suppliers, marked up to show the whole of the Works as built.
b) The copies of all manufacturers’ manuals issued in connection with the Works.
c) Two copies of every report, piling record, test result, site instruction, or correspondence issued or
received in connection with the Site Monitoring of the Works.
d) All Utility Services approvals from all relevant agencies, if applicable.
e) As-built surveys.
f) Complete Room Data Sheets and Inventory of fixtures, fittings, furniture, equipment, tools, spares,
plants, ancillaries etc. supplied, installed, erected and commissioned at the Project
g) Soft (MS Word, Excel, Power point, PDF and CAD) files for the above documents, as applicable
2.9.4 All of the above shall be replicated in digital form in the appropriate electronic format/software, etc. and be
submitted to IDAP.
2.9.5 The Consultant shall maintain an independent record of all data pertaining to the As-built records and shall
ensure that the Contractors maintain their data and information up to date. The Consultant shall ensure that
access to the Contractors’ files is available to IDAP at any time.
2.9.6 The staff deployed by the Consultant based either on the site or supported by main or sub offices, shall be
fully conversant with the preparation of digital designs and As-built records of the type specified in the contract
for the works.

IDAP | TORs for Construction Supervision Page 8 of 19

Page 72 of 125
2.9.7 The Consultants site staff shall be responsible for checking all data gathered by the Contractors in the
development of the data base for the preparation of the As-built drawings, and for conducting checks of actual
works for the determination of the accuracy of the data collected and approve and stamp the drawings
prepared by the Contractors.
2.9.8 As built drawings shall be prepared in the latest version of AutoCAD and shall be in a suitable format for use
of IDAP
2.9.9 The Consultant shall ensure that as-built drawings and records are produced as the work progresses and that
a final and completed set of as built drawings are provided within time to be specified by IDAP.
2.9.10 On completion of his Services, the Consultant shall deliver to IDAP in digital form on CD the complete file
system for the project, fully indexed and cross referenced, together with original drawings provided for the
purpose of execution.

3. REVIEW PERIOD
The Consultant is expected to provide reviews, feedbacks and approvals to the Contractors (and IDAP) in a timely
manner to allow the execution of the Works in an expeditious manner and without delay. Unless otherwise specified in
the Construction Contracts or specifically required by IDAP on case-to-case basis, the Consultant shall not consume
more than fourteen (14) calendar days, in total, to review any of the documents/submittals/claims etc. that will be
submitted to the Consultant. IDAP may reduce this period to from fourteen (14) days to seven (07) days, at its sole
discretion, depending upon requirements of the Project.

4. SITE SUPERVISION STAFF RESOURCES


4.1. General
4.1.1 The Consultant shall be responsible for the provision of suitably qualified staff to carry out the services to the
standard required by IDAP. The site staff positions that will be required during the delivery of the services are
indicated at the end of these TORs/CSA. The Consultant’s resourcing will be subject to the approval of IDAP.
4.1.2 Proposed team definition of the Consultant’s Resident Supervision Staff at the end of these TORs indicates
minimum2 requirements as determined by IDAP.If the Consultant considers that it is necessary to engage
any other staff in his team for satisfactory performance of its obligations, the Consultant must include the
costs thereof in the fee offer. No extra payment will be made, and no additional position will be allowed
other than those agreed in the CSA.
4.1.3 All the Key Personnel shall be interviewed by IDAP and the Consultant must obtain IDAP’s approval prior to
mobilizing any of them at Site.
4.1.4 If the Consultant comprises a Joint Venture (JV), the Key Personnel shall be deputed from the JV Lead
Member’s organization.
4.1.5 IDAP shall accept no responsibility for the procurement of visas (for any foreign personnel), accommodation
or transport for any member of the Consultant's staff employed on the Project.
4.1.6 The Consultant shall ensure that all Key Personnel hold a valid Pakistan Engineering Council (PEC) License
at all times.

2
The word ‘minimum’ shall not restrict IDAP’s discretion stipulated at Article 4.2.5 of these Terms of Reference.

IDAP | TORs for Construction Supervision Page 9 of 19

Page 73 of 125
4.1.7 IDAP shall have the full authority to disqualify any staff (whether Key Personnel or Non-Key Personnel) on
the technical grounds or if one is not performing his duties to the satisfaction of IDAP.
4.1.8 If the Project is not completed within the original “Time for Completion” due to the delays on the Project, the
remuneration for the extended period will be paid based on the original billing rates stipulated in CSA. The
original billing rates shall be deemed to be fixed for the original as well as the extended period, unless stated
otherwise in the conditions of the CSA. However, the team definition may be re-adjusted by IDAP as per
budget requirements.

4.2. Working Hours for Staff engaged Full Time


4.2.1 All staff who is engaged full time shall be based on Site.
4.2.2 The minimum working hours for Consultant's site staff shall be eight (8) hours per day, six (6) days per week,
excluding break time and as work may dictate usually from Monday to Saturday inclusive. The days of
absence, other than the gazetted holidays and weekly one day of rest, shall not be payable.
4.2.3 The Consultant's shall take into account the 'Time for Completion' and the nature of the construction Works
and that it may be necessary for the Contractors to work outside normal hours or in more than one shift and/or
on weekends, as may be required at Site. The Consultant shall therefore adjust its staff rotation in attendance
accordingly or as may be directed by the IDAP, to ensure uninterrupted supervision of work activities. IDAP
shall be kept informed of any such changes in working hours. No additional payments shall be made for such
occurrences and costs thereof shall be deemed to be covered in the Consultant's rates. The remuneration
must include any costs related to Consultant's office support as well.
4.2.4 The said staff is expressly prohibited to carry out any work, tasks or provide service for the Consultants other
than that work, tasks or services directly related to the project or as directed by IDAP.
4.2.5 IDAP may, at its sole discretion, increase/decrease or reduce, the level and/or duration of supervision, by
increasing or decreasing the Consultant’s staff using the monthly rates quoted in the fee offer.
4.3. Site Staff Engaged on Intermittent Input Basis
4.3.1 These provisions shall apply on the Staff required on intermittent input basis, if separately indicated in the
ensuing parts of these Terms of Reference.
4.3.2 The mobilization and amount of actual attendance required is the responsibility of the Consultant and the
intermittent input stipulated in CSA shall be deemed to be sufficient to carry out the functions and duties
necessary for completion of the Project as per these TORs. If in the opinion of the Consultant, more than the
specified period is required to carry out the services and complete the Project, the Consultant must allow for
such additional costs as necessary in his CSA Price.
4.3.3 The actual attendance of such staff shall be as and when the staff attends the Site during Time for Completion
for the purpose of carrying out the services as per terms of the CSA and TORs. The Consultant must provide
a schedule showing proposed utilization of intermittent staff input for concurrence of IDAP.
4.4. Staff Mobilization and/or Unauthorized Absence from the Site
4.4.1 The Consultant shall mobilize its staff within fourteen (14) calendar days of the Notice to Commence Services
to be issued by IDAP. Depending on Site requirements, IDAP may also require the Consultant to progressively
mobilize its staff as per the work requirements.
4.4.2 In case of failure to mobilize the required staff fourteen (14) calendar days from the instruction of IDAP, the
Consultant may be subjected to a deduction of the amount of the rate fixed for such member(s) of staff, for
the entire duration of the delay.
4.4.3 If the Consultant fails to mobilize its staff within further fourteen (14) days, IDAP may appoint suitably qualified
individual at its discretion and may back-charge the actual expenses to the Consultant.

IDAP | TORs for Construction Supervision Page 10 of 19

Page 74 of 125
4.4.4 In case of resignation/departure of any of the Consultant’s staff, the Consultant shall be obligated to provide
a suitable replacement. For smooth transition, project knowledge sharing and continuity of services, the
Consultant shall ensure that there should be an overlap of at least fourteen (14) days between the predecessor
and his successor.
4.5. Attendance Requirements

4.5.1 The Consultant shall maintain daily attendance record for the staff deployed on site and shall provide the
records to IDAP on monthly basis. The attendance record shall be retained by the Consultant and made
available for audit as and when required. Invoice for monthly payments, time spent in offices or sites must be
supported by a ‘Monthly Timesheet’ transcribed from the ‘Daily Attendance Record’ maintained in the site
offices.

4.5.2 Full deduction shall be made for unauthorized absence of staff. For deduction purposes, the daily rate shall
be calculated by dividing the Monthly Rate by no. of days in the corresponding month.

4.5.3 For periods of vacation, the Consultant shall provide a x advance about staff vacations of anticipated long
periods of absence. Replacements shall only be placed after their approval by IDAP. The alternative staff shall
be required to overlap with the relevant permanent staff for at least seven (7) days.

4.5.4 The Consultant shall ensure that during vacations or long periods of absence of the designated and approved
staff; suitable alternative staffing arrangements are made in agreement with IDAP. The replacement staff shall
have prior knowledge of the project and have similar qualifications and experience to ensure continuity of
service.

4.5.5 The Consultant’s staff, where necessary, shall be required to attend all site and other project meetings
throughout the currency of the CSA, including the Period of Maintenance.

4.5.6 In case if the Consultant fails to perform the Services to the satisfaction of IDAP, an appropriate deduction
may be applied by IDAP and recovery thereof shall be made from any monies due to the Consultant. Such
action shall be without prejudice to any other recourse(s) that IDAP may adopt under the CSA.

IDAP | TORs for Construction Supervision Page 11 of 19

Page 75 of 125
5. OTHER CONSIDERATIONS
5.1. The Consultant office shall provide necessary Head/Sub office support to the Engineer, referred in the
fulfilment of their obligations during the Time for Completion and during the maintenance/Defects
Liability/Notification period of the Contracts being supervised. Unless stated otherwise in the conditions of
CSA, the costs of any assistance, input and/or travelling of the Consultant’s head office staff shall be deemed
to be covered in the price of CSA.

5.2. For the duration of the CSA, IDAP may, at its sole discretion, assign up to two (2) engineers to the Site to
work alongside the Consultant's Site staff. The dates, duration and agenda of such secondment shall be
agreed in advance with the Consultant. The seconded staff shall be at IDAP’s payroll however the Consultant
shall be responsible for adjusting these engineers in its office alongside its project team.

5.3. The Consultants will assist IDAP in settlement of Audit Paras and Objections raised (if any) and prepare
replies related to the Project and provide all the relevant documents/papers/letters etc. to support the replies
and shall intimate the IDAP accordingly. The Consultant shall be responsible to provide support, cooperation,
input, documentation and replies during audit(s) conducted by IDAP’s internal or external auditors.

5.4. The Consultant shall coordinate with the end user of the Project to meet any specific requirements of the
Project, as may be required by IDAP.

5.5. All documents, reports, designs, research work and all deliverables prepared by the Consultant shall become
and remain the property of the IDAP. Any future use of these documents and software by the Consultant shall
not be done without permission of IDAP.

5.6. The Consultant is advised to take account of and include the costs relating to running expenses of the Site
Office for the entire period specified in the CSA.

5.7. IDAP may require the Consultant to abide by and adhere to any standard operating procedures as may be
specified by IDAP. This may also include the requirement of using a specified electronic system for performing
any of the Services.

5.8. The Consultant shall, with every invoice, provide an undertaking on IDAP’s specified format affirming that the
remunerations for the Consultant’s entire staff at the Project Site, have been cleared till previous invoice
(against which IDAP has released payment) in accordance with their respective employment contracts. The
Consultant undertakes that the IDAP will be at liberty to take any contractual/legal action against the
Consultant in case the above statement/undertaking is found to be untrue which may be deemed as an action
detrimental to the public interest or good practices. No invoice shall be processed for payment until it is
accompanied with the required undertaking on the specified format.

6. REPORTING REQUIREMENTS
The Consultant will keep IDAP continually informed on the progress of the works and all budgetary & financial matters
pertaining to the project, by submitting the following reports without limitation:

IDAP | TORs for Construction Supervision Page 12 of 19

Page 76 of 125
6.1. Weekly progress reports including: information on measurements of works executed, equipment and material
supplied to site, used and/or stored - quality tests on earthworks, concrete works, steel works, sewage and
water supply, construction materials and equipment – Safety Measures - labor force - variation orders if any
– payments made to the Contractor - acceptance tests of structures problems encountered and
recommendation made by the Consultant - photographs recording (electronic/digital) the progress of work
and other information as required by IDAP.

6.2. Monthly progress reports, indicating the progress made since the submission of the previous report and
commenting on the progress to date in relation to the program and whether completion of the works is likely
to be advanced or delayed. The Consultant shall obtain IDAP’s approval on the template of Monthly Progress
Report.

6.3. All presentation materials using Microsoft Power Point when asked to. He is expected to give several
presentations relating to the works to IDAP officials, Government officials, and other officials. He is also
expected to assist in presentations to be given by IDAP.

6.4. Project Completion Report upon completion of works and/or Consultants' assignment.

6.5. The Consultant is required to submit all project reports, drawings and documents in the format listed below
and recorded on computer media using software and formats standardized and approved by the IDAP. Costs
associated with all items to be provided shall be deemed to be covered in the overall price submitted by the
Consultant.

6.6. In case if the Consultant fails to adequately meet reporting requirements and/or he fails to perform up-to the
satisfaction of IDAP and/or if the Project is adversely affected due to the Consultant’s inadequate project
management, an appropriate deduction may be applied by IDAP and recovery thereof may be made from any
outstanding monies of the Consultant. Such action shall be without prejudice to any other recourse(s) that
IDAP may adopt under the CSA.

Table 1: Reporting Requirements

Sr. # Description No. of sets Frequency Size & Color Scale


1. Monthly Progress Report including
As per IDAP
Master Baseline Schedule (Integrated 05 Monthly -
Requirement
Project Schedule-IPS)
2. Daily/Weekly Progress Report As per IDAP
02 Daily/Weekly -
Requirement
3. Quality Assurance and Quality Control
Documents and test reports along-with As per IDAP
02 Monthly -
updated registers duly signed by the Requirement
respective contractor and the Consultant
4. As Built Drawings and Records (to be
obtained from the Contractor and As per IDAP As per IDAP As per IDAP
05
approved by the Consultant after/upon Requirement Requirement Requirement
Taking Over of the Works)
5. Other Project Completion Documents, to As per IDAP As per IDAP As per IDAP As per IDAP
be obtained from the Contractor and Requirement Requirement Requirement Requirement

IDAP | TORs for Construction Supervision Page 13 of 19

Page 77 of 125
Sr. # Description No. of sets Frequency Size & Color Scale
approved by the Consultant, as stated in
the Construction Contracts
6. Progress Presentations As per IDAP As per IDAP As per IDAP
-
Requirement Requirement Requirement
7. Cost to Complete Report As per IDAP Quarterly or As per As per IDAP
-
Requirement IDAP Requirement Requirement
8. Project Completion Report in a format
agreed with IDAP. This will summarize
all relevant aspects of the Project
As per IDAP
implementation. A suitable selection of 05 At Completion -
Requirement
photographic records shall be
reproduced and included in the Final
Report.

7. DEFECTS LIABILITY PERIOD


7.1. Defect Liability Period shall begin upon latest Taking Over among the Construction Contract(s) and will
continue for the stipulated number of days as per the corresponding Construction Contract.
7.2. Perform periodic maintenance inspection visits during the Defects Liability Period visits, as and when required,
will be conducted by the different disciplines engineers to ensure the proper working of system.
7.3. To assess defects and/or construction damage(s) and warranty status on systems. Prepare and submit visit
reports with progress on attendance of Punch List.
7.4. Check and recommend the final payment certificate(s) at the end of Defects Liability Period for the IDAP's
approval and comments.
7.5. Preparing a Final Report in a format agreed upon with the IDAP. This will summarize all the relevant aspects
of the Project implementation, and specific recommendations on routine maintenance, highlighting locations
requiring special care and attention. A suitable selection from the project photographic records shall be
reproduced and included in the Final Report.
7.6. Staff to be deployed during Defects Liability Period shall be in accordance with the table annexed at the end
of these TORs and the staff input will be intermittently spread over the Defects Liability Period.

8. PAYMENTS TERMS:
A payment of 10% shall be retained from each Invoice of the Consultant which shall be released as per following
Schedule:

Table 2: Payment Terms & Retention

No. Deliverables Payment %

1 Submission of Project Taking Over Documents and IDAP 04%


acceptance thereto

2 As-built Documents & Records and IDAP acceptance thereto 04%

3 Project Completion Report and IDAP acceptance thereto 02%

IDAP | TORs for Construction Supervision Page 14 of 19

Page 78 of 125
9. CONSULTANT’S LIABILITY:
Notwithstanding anything contained herein or stated elsewhere in the CSA, the Consultant shall remain completely
responsible for all of his obligations stated in the CSA & these TORs and any failure or breach by the Consultant shall
entitle IDAP to recover the financial losses from any outstanding monies of the Consultant or through encashment of
Performance Guarantee (if furnished under the CSA) or through combination of possible remedies.

10. PROFESSIONAL LIABILITY


Professional liability, as stands in the prevalent conduct and practice of Consulting Engineers prescribed by the PEC
and provisions mentioned in prevalent Procurement Rules issued by the relevant Procurement Regulatory Authority,
shall be as follows:
i. The Consultant selected and awarded the contract shall be liable for consequence of errors or
omissions on the part of the Consultant.
ii. The Consultant shall also be liable for the consequences of its actions and/or all kinds of technical and
contractual advice which it may give to IDAP under the CSA.
iii. The extent of liability of the Consultant shall be as per the upper/maximum limit mentioned in the
prevalent Procurement Rules issued by the relevant Procurement Regulatory Authority.
iv. The Consultant shall be held liable for all losses or damages suffered by the procuring agency on
account of any misconduct by the consultant in performing the consulting services.

IDAP | TORs for Construction Supervision Page 15 of 19

Page 79 of 125
STAFF TO BE ENGAGED FULL TIME
(EXCLUDING DEFECTS LIABILITY PERIOD)
Table 3: Staff to be Engaged Full Time (Excluding DLP)

SR. NO. OF
DESCRIPTION EDUCATION & EXPERIENCE REQUIREMENTS
NO. PROFESSIONAL

Key Personnel:
B.Sc. Civil Engineering with minimum 15 years of
relevant experience OR Masters in relevant field (Civil
Engineering/Project Management etc.) with minimum 13
1 Resident Engineer 01 years of relevant experience. The individual should be
well conversant with FIDIC and Pakistan Engineering
Council (PEC) forms of Contracts. The individual must be
registered as “Professional Engineer” with the PEC.
B.Sc. Civil Engineering with minimum 8 years of relevant
experience OR Masters in relevant field (Civil
Assistant Resident Engineer Engineering/Project Management etc.) with minimum 6
2 01 years of relevant experience. The individual must be a
(Civil)
Registered Engineer with the PEC.
ARE Civil should have expertise in primavera and
capability to prepare Presentations & Progress Reports
B.Sc. Elec/Mech. Engineering with minimum 8 years of
Assistant Resident Engineer relevant experience (PEC Registered) OR M.S in
3 01 Elec/Mech. Engineering/Project Management with
(MEP)
minimum 6 years of relevant experience. The individual
must be a Registered Engineer with the PEC.

B.Sc. Civil Engineering/Geological Engineering with


minimum 8 years of relevant experience. The individual
4 QA/QC & Material Engineer 01
must be registered with the Pakistan Engineering
Council.

B.Sc. Engineering with minimum 8 years of relevant


experience on large scale building projects OR M.S in
Planning & Project Controls Engineering/Project Management with minimum 6 years
5 01 of relevant experience (Strong familiarity with project
Specialist
management software such as Primavera P6 is must).
The individual must be registered with the Pakistan
Engineering Council.
Non-Key Personnel:

B.Sc Civil Engineering with preferably 03 years of


6 Junior Engineer - Civil 01
experience

IDAP | TORs for Construction Supervision Page 16 of 19

Page 80 of 125
SR. NO. OF
DESCRIPTION EDUCATION & EXPERIENCE REQUIREMENTS
NO. PROFESSIONAL

B.Sc Electrical Engineering with preferably 03 years of


7 Junior Engineer - Electrical 01
experience

DAE Civil with minimum 10 years of relevant


8 Field/Site Inspectors (Civil) 04 experience, OR B.Sc. Engineering (Civil) with minimum
06 years of relevant experience.

DAE Elec/Mech. with minimum 10 years of relevant


9 Field/Site Inspectors (MEP) 01 experience, OR B.Sc. Engineering (Elec/Mech.) with
minimum 06 years of relevant experience.

10 Quantity Surveyors 02 DAE Civil with minimum 10 years of relevant experience

11 Surveyor 01 DAE Civil with minimum 10 years of relevant experience

12 HSE Officer 01 Graduate with NEBOSH/OSHA certification and


minimum 03 years’ of relevant experience

13 Document Controller 01 Graduation with relevant experience of three (03) years.


Proficient user of MS office / other equivalent software.

STAFF TO BE ENGAGED ON INTERMITTENT INPUT BASIS


(EXCLUDING DEFECTS LIABILITY PERIOD)
Table 4: Staff to be Engaged on Intermittent Input Basis (Excluding DLP)

SR. NO. OF No. of


DESCRIPTION PROFESSION Input EDUCATION & EXPERIENCE REQUIREMENTS
NO.
ALS Months

Key Personnel:

B.Sc. Computer Science/IT with minimum 10 years of


1 IT/Networking Specialist 01 06 relevant experience or Masters in relevant discipline with
minimum 08 years of relevant experience.

Bachelor's in Architecture or Architectural Engineering


with minimum 10 years relevant experience or Masters in
relevant discipline with minimum 08 years relevant
2 Architect 01 04
experience. The individual must be registered with the
Pakistan Council for Architects & Town Planners
(PCATP).

IDAP | TORs for Construction Supervision Page 17 of 19

Page 81 of 125
NO. OF No. of
SR.
DESCRIPTION PROFESSION Input EDUCATION & EXPERIENCE REQUIREMENTS
NO.
ALS Months

B.Sc. Biomedical/Electrical Engineering with a minimum


of 10 years total experience or Masters in relevant
3 Biomedical Specialist 01 06 discipline with a minimum of 08 years total experience.
Total experience shall include a minimum of 06 years of
relevant experience.

Notes:
(i) The Consultant shall provide a deployment schedule for intermittent staff as per Site requirements for concurrence of IDAP.
(ii) Unless otherwise approved by the IDAP’s Project Director, the Intermittent Staff shall be required to be present at Site during the
duration of their work at the Project. The attendance of such staff shall be verified by the Resident Engineer and countersigned by IDAP’s
Site Staff.

Important Notes:

 The Consultant is advised to take account of and include the costs relating to running expenses of the Site
Office for the entire period specified in the CSA. For this purpose, the Consultant, in his offer, should specify
a monthly fixed cost to be reimbursed by IDAP on monthly basis. Separate costs should be indicated for
Construction Supervision and Defects Liability Phase.

 The Contractors will be obligated to provide and maintain a furnished office with standard facilities at Site for
the Consultant’s Resident Supervision Staff. However, the Consultant shall be responsible to arrange
computers, laptops etc. for its staff. The Consultant shall be responsible to engage administration staff and
office boy(s) for providing general office support services to its staff. An excerpt from the Contractor’s Bidding
Documents is appended with these TOR’s showing Facilities to be provided by the Contractor.

 The Consultant’s Price should include the costs related to the travelling needs of its staff. The Consultant shall
provide the following vehicles at Site as a minimum. IDAP may, at any time, require the Consultant to provide
the evidence of the availability of such vehicles at Site. IDAP may, at its discretion, apply reasonable
deductions if the Consultant fails to provide the below-mentioned vehicles at Site:

Table 5: Vehicles for use of Consultant's Site Staff

Vehicle
S/N Cost should cover Quantity/No.
Specifications

1 Providing, Operating, Insuring and Maintaining


specified vehicle (including Fuel, Oil, Lubricants, Drivers
02 1000cc Car
etc.) for exclusive use of Consultant’s Site Staff and its
travelling for any activity related to the Project.

IDAP | TORs for Construction Supervision Page 18 of 19

Page 82 of 125
MINIMUM STAFF TO BE ENGAGED ON INTERMITTENT INPUT BASIS
DURING DEFECTS LIABILITY PERIOD
Table 6:Minimum Staff to be Engaged on Intermittent Input Basis during DLP

Tentative Tentative
SR. NO. OF Monthly Input Total No.
DESCRIPTION (man-months) of Man- EDUCATION & EXPERIENCE
NO. PROFESSIONALS
Months

1 Resident Engineer 01 0.33 04 As provided for staff to be engaged full time

Assistant Resident Engineer As provided for staff to be engaged on


2 01 0.33 04
(MEP) intermittent input basis

As provided for staff to be engaged full time


3 Field/Site Inspector 01 0.33 04

As provided for staff to be engaged full time


4 Quantity Surveyor 01 0.33 04

*Illustration: Tentative input taken as 0.33 Man-month per calendar month x 12 = 04 Man-Months for entire 01-year DLP.

IDAP | TORs for Construction Supervision Page 19 of 19

Page 83 of 125
ANNEX-A
EMPLOYER: PROJECT:
TENDER DOCUMENT FOR
Infrastructure Development Authority of the ESTABLISHMENT OF NAWAZ SHARIF
Punjab (IDAP) Government of Punjab CONTRACTOR INSTITUTE OF CARDIOLOGY, SARGODHA

19.9 Handing Over/Removal after Completion

accommodation, site office, other installations and buildings constructed and all facilities provided by the
Contractor under this Clause, and the Site cleared and reinstated to the satisfaction of the Engineer.

19.10 Measurement and Payment


Except as provided in SP-19.8 no separate payment will be made for the work included under the Clause SP-
19; the cost thereof is deemed to be included in the rates and prices of other items entered in the Bill of
Quantities.

SP-20 PROVISION OF FACILITIES FOR THE ENGINEER STAFF/EMPLOYER


20.1
(a) Site offices:

The Contractor shall at his own cost and expense, provide and maintain, temporary site office (porta cabin) at
the Site having 04 no. 40 ft containers/porta cabins/equal area temporary building having 5 workstations in each
porta cabin (design/size etc will be subject to approval of the Engineer) for the resident supervision staff. The
site office shall be well furnished and well-equipped including heating cooling arrangement and allied facilities
including generator of appropriate capacity as backup power arrangement at the Site.

The facilities shall be serviced with water supply (portable, hot & cold), sewerage facilities/toilet (with essential
toiletries), janitorial services etc separately for Male and Female Staff.

The Contractor shall maintain the office and bear all charges in respect of providing and maintaining, among
others, utilities such as electricity (including fuel for electric generator required to handle full load of the Site
office). Provision of above mentioned facilities shall be subject to approval of the Engineer.

(b) Furniture:

The Contractor shall provide and maintain furniture including but not limited to sufficient number of workstations,
office chairs, visiting chairs & tables etc. and all other allied furniture items for at least 20 persons required for
office use, as directed/approved by the Engineer.

(c) Transport:

NOT USED

(d) Office Equipment & Stationery:

Site Office shall be fully equipped with office equipment { Internet, printers (1xA3 Colour Copier & Printer +
2xA4 Printers), stationary etc} necessary to perform the work.

All of the above facilities mentioned under sub-clause 20.1 shall be provided within 30 days from the
Commencement Date and maintained for complete project duration from Commencement Date till completion
of the project and may change as per instructions of the Engineer.

Page 98 of 113

Page 84 of 125
EMPLOYER: PROJECT:
TENDER DOCUMENT FOR
Infrastructure Development Authority of the ESTABLISHMENT OF NAWAZ SHARIF
Punjab (IDAP) Government of Punjab CONTRACTOR INSTITUTE OF CARDIOLOGY, SARGODHA

20.2
(a) Site offices:

The Contractor shall at his own cost and expense, provide and maintain, temporary site office (porta cabin)
comprising of 02 no. 40ft porta cabin offices/containers/temporary building of similar area each having at least
4 work stations (design/size etc will be subject to approval of the Engineer/Employer). Offices shall be fully
equipped with office equipment necessary to perform the work. The site office shall be well furnished and well
equipped including heating cooling arrangement and allied facilities including generator of appropriate capacity
as backup power arrangement at the Site.

The facilities shall be serviced with water supply (portable, hot & cold), sewerage facilities/toilet (with essential
toiletries), janitorial services etc separately for Male and Female Staff.

The Contractor shall maintain the office and bear all charges in respect of providing and maintaining, among
others, utilities such as electricity (including fuel for electric generator required to handle full load of the Site
office). Provision of above mentioned facilities shall be subject to approval of the Engineer/Employer.

(b) Furniture:

The Contractor shall provide and maintain furniture including sufficient number of workstations office chairs,
visiting chairs & tables etc and all other allied furniture items for at least 4 persons required for office use, or as
directed by the Engineer/Employer, including but not limited to:

i. A separate 20 ft container for kitchen along with all the kitchen supplies (Including fridge and
microwave oven)
ii. 6 no. tables
iii. 6 no. chairs
iv. 12 no. visitor chairs
v. Conference table with 16 no. chairs at least
(c) Transport:

NOT USED

(d) Office Equipment & Stationery:

Site Office shall be fully equipped with office equipment (Internet, printers, stationary etc) necessary to perform
the work, including but not limited to:

i. 3 no. Zong/PTCl or equivalent internet devices paid for the complete project duration.
ii. 1 no. A3 size Black & white laser 3 in 1 printer/copier/scanner
iii. Sufficient stationary including papers for printing.
iv. 01 no. A4 colour printer & 01 no. A3 colour printer
v. A conference room with HD Audio Video Conferencing Arrangement.
vi. Personal Protective Equipment (PPEs)
Page 99 of 113

Page 85 of 125
EMPLOYER: PROJECT:
TENDER DOCUMENT FOR
Infrastructure Development Authority of the ESTABLISHMENT OF NAWAZ SHARIF
Punjab (IDAP) Government of Punjab CONTRACTOR INSTITUTE OF CARDIOLOGY, SARGODHA

(e) Staff for Office Site:

The General Contractor shall hire, at his own cost and expense, office boys for site office.

(f) Security:

The General Contractor shall also be responsible for the complete security of the site offices and their contents
at all times. Necessary insurances shall be maintained.

(g) Site Visit Arrangements

The General Contractor shall be responsible for arranging the site visits of Government Officials in all respects
i.e., Debriefing arrangements, HSE arrangements, Seating arrangements, and Refreshments (if required).

All of the above facilities mentioned under sub-clause 20.2 shall be provided within 30 days from the
Commencement Date and maintained {maintenance not required for transport provide under sub-clause 20.2
(c)} for complete project duration from Commencement Date till completion of the project and may change as
per instructions of the Engineer.

20.3 Ownership of Site facilities


The facilities mentioned under sub-clause 20.1 and 20.2 except 20.2(c)(if used) shall become the property of
the Contractor upon completion of the Works.

20.4 Measurement and Payment


No separate payment will be made for the work specified in Clause SP-20; the cost thereof is deemed to be
included in the rates and prices of other items entered in the Bill of Quantities.

In case of failure of the Contractor to provide any of facilities stipulated under SP-20, the same will be arranged

10% shall be payable by the Contractor and shall be recovered from the Contractor through Interim Payment

be conclusive and binding.

SP-21 PROGRESS PHOTOGRAPHS


The Contractor shall furnish to the Engineer every month, for the site of each building twelve colour photographs
on CD and 4 colour prints of each photograph taken with a digital camera to clearly show the progress of
construction. Each photograph shall be submitted in four prints of size 20 cm x 25 cm. Each print shall be marked
on the back side with the caption of the activity, date and serial number. There shall be no writing, lettering or
marking on the face of the photograph. Progress photographs shall be submitted from the month, following the
month in which Notice to Commence is issued and continued till completion of the Works.

No separate payment will be made for the work specified herein and the cost thereof shall be deemed to be
included in the other items of the Bill of Quantities.

Page 100 of 113

Page 86 of 125
Appendices Lump-Sum

Section 8: Standard Forms of Contract

Page 87 of 125
CONTRACT FOR PROCUREMENT OF ENGINEERING
CONSULTANCY SERVICES

BY & BETWEEN

INFRASTRUCTURE DEVELOPMENT
AUTHORITY OF THE PUNJAB

AND

________________________________________
____________________

FOR

RESIDENT CONSTRUCTION SUPERVISION FOR


CONSTRUCTION OF NAWAZ SHARIF INSTITUTE OF
CARDIOLOGY, SARGODHA

Contract No:

Page 88 of 125
TABLE OF CONTENTS

I. FORM OF CONTRACT
II. GENERAL CONDITIONS OF CONTRACT
1. GENERAL PROVISIONS
1.1 Definitions
1.2 Law Governing the Contract
1.3 Language
1.4 Notices
1.5 Location
1.6 Authorized Representatives
1.7 Taxes and Duties
1.8 Leader of Joint Venture
2. COMMENCEMENT, COMPLETION,
MODIFICATION, AND TERMINATION OF
CONTRACT
2.1 Effectiveness of Contract
2.2 Termination of Contract for Failure to Become Effective
2.3 Commencement of Services
2.4 Expiration of Contract
2.5 Modification
2.6 Extension of Time for Completion
2.7 Force Majeure
2.7.1 Definition
2.7.2 No Breach of Contract
2.7.3 Extension of Time
2.7.4 Payments
2.8 Suspension of Payments by the Client
2.9 Termination
2.9.1 By the Client
2.9.2 By the Consultants
2.9.3 Cessation of Services
2.9.4 Payment upon Termination
2.9.5 Disputes about Events of Termination
3. OBLIGATIONS OF THE CONSULTANTS
3.1 General
3.2 Consultants Not to Benefit from Commissions, Discounts, etc.
3.3 Confidentiality
3.4 Liability of the Consultants
3.5 Other Insurances to be Taken out by the Consultants
3.6 Consultants' Actions Requiring Client's Prior Approval
3.7 Reporting Obligations
3.8 Documents Prepared by the Consultants to be the Property of the Client
3.9 Equipment and Materials Furnished by the Client
3.10 Accounting, Inspection and Auditing

Page 89 of 125
4. CONSULTANTS' PERSONNEL AND SUB-CONSULTANTS
4.2 Description of Personnel
4.3 Approval of Personnel
5. OBLIGATIONS OF THE CLIENT
5.1 Assistance, Coordination and Approvals
5.1.1 Assistance
5.1.2 Co-ordination
5.1.3 Approvals
5.2 Access to Land
5.3 Change in the Applicable Law
5.4 Services and Facilities
5.5 Payments
6. PAYMENTS TO THE CONSULTANTS

6.1 Lump Sum Remuneration


6.2 Contract Price
6.3 Terms and Conditions of Payment
6.4 Period of Payment
6.5 Delayed Payments
6.6 Additional Services
6.7 Consultants' Entitlement to Suspend Services

7. SETTLEMENT OF DISPUTES

7.1 Amicable Settlement


7.2 Dispute Settlement

8. INTEGRITY PACT

III. SPECIAL CONDITIONS OF CONTRACT

IV. APPENDICES

Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F
Appendix G
Appendix H

Page 90 of 125
I. FORM OF CONTRACT

This CONTRACT (hereinafter called the "Contract") is made on the _____ day of month of
_________ of 2021, between, on the one hand

Infrastructure Development Authority of the Punjab (IDAP) having its head office at
50-B-3 Gulberg – III Lahore, Pakistan (hereinafter called the "Client" which expression
shall include the successors, legal representatives and permitted assigns) and, on the other
hand,

M/s ___________________________________ having its office at


____________________________________________________________
(hereinafter called the "Consultants" which expression shall include the successors, legal
representatives and permitted assigns).

WHEREAS,

(a) the Client has requested the Consultants to provide consultancy services as defined in this
Contract (hereinafter called the "Services"); and

(b) the Consultants, having represented to the Client that they have the required professional
skills and personnel, and technical resources, have agreed to provide the Services on the
terms and conditions set forth in this Contract;

NOW THEREFORE, the Parties hereby agree as follows:

1. The following documents attached hereto shall be deemed to form an integral part of
this Contract:

(a) the General Conditions of Contract;


(b) the Special Conditions of Contract;
(c) the following Appendices:
Appendix A: Description of the Services
Appendix B: Reporting Requirements
Appendix C: Key Personnel and Subconsultants
Appendix D: Breakdown of Contract Price in Foreign Currency (NOT USED)
Appendix E: Breakdown of Contract Price in Local Currency
Appendix F: Services & Facilities to be Provided by the Client
Appendix G: Integrity Pact
Appendix H: Form of Guarantees
2. The mutual rights and obligations of the Client and the Consultants shall be as set forth in
the Contract, in particular:

(a) the Consultants shall carry out the Services in accordance with the provisions of the
Contract; and

(b) the Client shall make p a y m e n t s t o the Consultants in accordance with the provisions

Page 91 of 125
of the Contract.

IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed in their
respective names in two identical counterparts, each of which shall be deemed as the original, as
of the day, month and year first above written.

For and on behalf of

INFRASTRUCTURE DEVELOPMENT AUTHORITY OF THE PUNJAB

Witness
Signature ___________________ Signature _________________
Name ______________________ Name ____________________
Title _______________________ Title _____________________
CNIC ______________________ (Seal)

For and on behalf of

THE CONSULTANTS

Witness
Signature ___________________ Signature _________________
Name ______________________ Name ____________________
Title _______________________ Title _____________________
CNIC ______________________ (Seal)

Page 92 of 125
II. GENERAL CONDITIONS OF CONTRACT

1. GENERAL PROVISIONS

1.1 Definitions

Unless the context otherwise requires, the following terms whenever used in this
Contract have the following meanings:

(a) "Applicable Law" means the laws and any other instruments having the force of
law in the Islamic Republic of Pakistan, as those may be issued and in force from
time to time;

(b) "Contract" means the Contract signed by the Parties, to which these General
Conditions of Contract (GC) are attached, together with all the documents listed
in Clause 1 of such signed Contract;

(c) "Contract Price" means the price to be paid for the performance of the Services,
in accordance with Clause 6;

(d) "Effective Date" means the date on which this Contract comes into force and
effect pursuant to Sub-Clause 2.1;

(e) "GC" means these General Conditions of Contract;

(f) "Government" means the Government of the Islamic Republic of Pakistan;

(g) "Foreign Currency" means currency other than the currency of Islamic Republic
of Pakistan;

(h) "Local Currency" means the currency of the Islamic Republic of Pakistan;

(i) "Member" in case the Consultants consist of a joint venture of more than one
entity, means any of the entities, and "Members" means all of these entities;

(j) "Party" means the Client or the Consultants, as the case may be, and "Parties"
means both of them;

(k) "Personnel" means persons hired by the Consultants or by any Sub-consultant as


employees and assigned to the performance of the Services or any part thereof;
(l) "SC" means the Special Conditions of Contract by which the GC are amended or
supplemented;

(m) "Services" means the work to be performed by the Consultants pursuant to this
Contract, as described in Appendix A;

Page 93 of 125
(n) "Sub-consultant" means any entity to which the Consultants subcontract any part
of the Services in accordance with the provisions of Sub-Clause 3.6;

(o) "Third Party" means any person or entity other than the Client, the Consultants
or a Sub-consultant; and

(p) "Project" means the work specified in SC for which engineering consultancy
services are desired.

1.2 Law Governing the Contract

This Contract, its meaning and interpretation, and the relation between the Parties shall
be governed by the Applicable Law.

1.3 Language

This Contract has been executed in the English language which shall be the binding and
controlling language for all matters relating to the meaning or interpretation of this
Contract. All the reports and communications shall be in the English language.

1.4 Notices

Any notice, request, or consent made pursuant to this Contract shall be in writing and
shall be deemed to have been made when delivered in person to an Authorized
Representative of the Party to whom the communication is addressed, or when sent by
registered mail, telex, or facsimile to such Party at the address of the Authorized
Representative specified under Sub-Clause SC 1.6. A Party may change its address for
notice hereunder by giving the other Party notice of such change.

1.5 Location

The Services shall be performed at such locations as are specified in Appendix A and,
where the location of a particular task is not so specified, at such locations as mutually
agreed by the Parties.

1.6 Authorized Representatives

Any action required or permitted to be taken, and any document required or permitted to
be executed, under this Contract by the Client or the Consultants shall be taken or
executed by the Authorized Representatives specified in the SC.

1.7 Taxes and Duties

Unless specified in the SC, the Consultants, Sub-consultants, and their Personnel shall
pay such taxes, duties, fees, and other impositions as may be levied under the Applicable
Law, the amount of which is deemed to have been included in the Contract Price.

Page 94 of 125
1.8 Leader of Joint Venture

In case the Consultants consist of a joint venture of more than one entity, the Consultants
shall be jointly and severally bound to the Client for fulfillment of the terms of the
Contract and designate the Member named in SC, to act as leader of the Joint Venture,
for the purpose of receiving instructions from the Client.

2. COMMENCEMENT, COMPLETION, MODIFICATION, AND TERMINATION


OF CONTRACT

2.1 Effectiveness of Contract

This Contract shall come into force and effect on the date (the "Effective Date") of the
Client's notice to the Consultants instructing the Consultants to begin carrying out the
Services. This notice shall confirm that the effectiveness conditions, if any, listed in the
SC have been met.

2.2 Termination of Contract for Failure to Become Effective


If this Contract has not become effective within such time period after the date of the
Contract signed by the Parties as shall be specified in the SC, either Party may, by not
less than twenty eight (28) days written notice to the other Party, declare this Contract to
be null and void, and in the event of such a declaration by either Party, neither Party
shall have any claim against the other Party except for the work (if any) already done or
costs already incurred by a Party at the request of the other Party.

2.3 Commencement of Services


The Consultants shall begin carrying out the Services at the end of such time period after
the Effective Date as shall be specified in the SC.

2.4 Expiration of Contract

Unless terminated earlier pursuant to Sub-Clause 2.9, this Contract shall expire when,
pursuant to the provisions hereof, the Services have been completed and the payments
of remunerations including the direct costs if any, have been made. The Services shall
be completed within a period as is specified in the SC, or such extended time as may be
allowed under Sub-Clause 2.6.

The term "Completion of Services" is as specified in the SC.

2.5 Modification

Modification of the terms and conditions of this Contract, including any modification of
the scope of the Services or of the Contract Price, may only be made in writing, which
shall be mutually agreed and signed by both the Parties.

Page 95 of 125
2.6 Extension of Time for Completion

If the scope or duration of the Services is increased:

(a) the Consultants shall inform the Client of the circumstances and probable effects;
(b) the increase shall be regarded as Additional Services; and
(c) the Client shall extend the time for Completion of the Services accordingly.

2.7 Force Majeure

2.7.1 Definition

(a) For the purposes of this Contract, "Force Majeure" means an event which is
beyond the reasonable control of a Party and which makes a Party's performance
of its obligations under the Contract impossible or so impractical as to be
considered impossible under the circumstances, and includes, but is not limited
to, war, riots, civil disorder, earthquake, fire, explosion, storm, flood or other
adverse weather conditions, strikes, lockouts or other industrial actions (except
where such strikes, lockouts or other industrial actions are within the power of
the Party invoking Force Majeure to prevent), confiscation or any other action by
government agencies.

(b) Force Majeure shall not include (i) any event which is caused by the negligence
or intentional action of a Party or such Party's Sub-consultants or agents or
employees, nor (ii) any event which a diligent Party could reasonably have been
expected to both
(A) take into account at the time of the conclusion of this Contract and
(B) avoid or overcome in the carrying out of its obligations hereunder.

(c) Force Majeure shall not include insufficiency of funds or failure to make any
payment required hereunder.

2.7.2 No Breach of Contract

The failure of a Party to fulfill any of its obligations under the Contract shall not be
considered to be a breach of, or default under this Contract insofar as such inability arises
from an event of Force Majeure, provided that the Party affected by such an event; (a)
has taken all reasonable precautions, due care and reasonable alternative measures in
order to carry out the terms and conditions of this Contract; and (b) has informed the
other Party in writing not later than fifteen (15) days following the occurrence of such
an event.

2.7.3 Extension of Time

Any period within which a Party shall, pursuant to this Contract, complete any action or
task, shall be extended for a period equal to the time during which such Party was unable
to perform such action as a result of Force Majeure.

2.7.4 Payments

Page 96 of 125
During the period of their inability to perform the Services as a result of an event of
Force Majeure, the Consultants shall be entitled to continue to be paid under the terms
of this Contract, as well as to be reimbursed for additional costs reasonably and
necessarily incurred by them during such period for the purpose of the Services and in
reactivating the Services after the end of such period.

2.8 Suspension of Payments by the Client

The Client may, by written notice of suspension to the Consultants, suspend all payments
to the Consultants hereunder if the Consultants fail to perform any of their obligations
under this Contract, including the carrying out of the Services, provided that such notice
of suspension (i) shall specify the nature of the failure, and (ii) shall request the
Consultants to remedy such failure within a period not exceeding thirty (30) days after
receipt by the Consultants of such notice of suspension.

2.9 Termination

2.9.1 By the Client

The Client may terminate this Contract, by not less than thirty (30) days written notice
of termination to the Consultants, to be given after the occurrence of any of the events
specified in paragraphs (a) through (e) of this Sub-Clause 2.9.1 and sixty (60) days in
the case of the event referred to in paragraph (f):

(a) if the Consultants do not remedy a failure in the performance of their obligations
under the Contract, within thirty (30) days after being notified or within any
further period as the Client may have subsequently approved in writing;

(b) if the Consultants become (or, if the Consultants consist of more than one entity,
if any of their Members becomes) insolvent or bankrupt or enter into any
agreements with their creditors for relief of debt or take advantage of any law for
the benefit of debtors or go into liquidation or receivership whether compulsory
or voluntary;

(c) if the Consultants fail to comply with any final decision reached as a result of
arbitration proceedings pursuant to Clause-7 hereof;

(d) if the Consultants submit to the Client a statement which has a material effect on
the rights, obligations or interests of the Client and which the Consultants know
to be false;

(e) if, as the result of Force Majeure, the Consultants are unable to perform a material
portion of the Services for a period of not less than sixty (60) days;

(f) if the Client, in its sole discretion, decides to terminate this Contract.

2.9.2 By the Consultants

Page 97 of 125
The Consultants may terminate this Contract, by not less than thirty (30) days written
notice to the Client, such notice to be given after the occurrence of any of the events
specified in paragraphs (a) through
(d) of this Sub-Clause 2.9.2:

(a) if the Client fails to pay any monies due to the Consultants pursuant to this
Contract and not subject to dispute pursuant to Clause-7 within forty-five (45)
days after receiving written notice from the Consultants that such payment is
overdue;

(b) if the Client is in material breach of its obligations pursuant to this Contract and
has not remedied the same within forty-five (45) days (or such longer period
as the Consultants may have subsequently approved in writing) following the
receipt by the Client of the Consultants' notice specifying such breach;

(c) if, as a result of Force Majeure, the Consultants are unable to perform a material
portion of the Services for a period of not less than sixty (60) days;

(d) if the Client fails to comply with any final decision reached as a result of
arbitration proceedings pursuant to Clause-7 hereof.

2.9.3 Cessation of Services

Upon receipt of notice of termination under Sub-Clause 2.9.1, or giving of notice of


termination under Sub-Clause 2.9.2, the Consultants shall take all necessary steps to
bring the Services to a close in a prompt and orderly manner and shall make every
reasonable effort to keep expenditures for this purpose to a minimum. With respect to
documents prepared by the Consultants, and equipment and materials furnished by the
Client, the Consultants shall proceed as provided, respectively, by Sub-Clauses 3.8 or
3.9.

2.9.4 Payment upon Termination

Upon termination of this Contract pursuant to Sub-Clauses 2.9.1 or 2.9.2, the Client shall
make the following payments to the Consultants:

(a) remuneration and reimbursable direct costs expenditure pursuant to Clause 6 for
Services satisfactorily performed prior to the effective date of termination.
Effective date of termination for purposes of this Sub-Clause means the date
when the prescribed notice period would expire;

(b) except in the case of termination pursuant to paragraphs (a) through (d) of Sub-
Clause 2.9.1, reimbursement of any reasonable cost incidental to the prompt and
orderly termination of the Contract, including the cost of the return travel of the
Personnel, according to Consultants Traveling Allowance Rules.

Page 98 of 125
2.9.5 Disputes about Events of Termination

If either Party disputes whether an event specified in paragraphs (a) through (e) of Sub-
Clause 2.9.1 or in paragraphs (a) through (d) of Sub- Clause 2.9.2 hereof has occurred,
such Party may, within forty-five (45) days after receipt of notice of termination from
the other Party, refer the matter to arbitration pursuant to Clause 7 hereof, and this
Contract shall not be terminated on account of such event except in accordance with the
terms of any resulting arbitral award.

3. OBLIGATIONS OF THE CONSULTANTS

3.1 General
The Consultants shall perform the Services and carry out their obligations with all due
diligence, efficiency, and economy, in accordance with generally accepted professional
techniques and practices, and shall observe sound management practices, and employ
appropriate advanced technology and safe methods. The Consultants shall always act, in
respect of any matter relating to this Contract or to the Services, as faithful advisers to
the Client, and shall at all times support and safeguard the Client's legitimate interests in
any dealings with Sub-consultants or third parties.

3.2 Consultants Not to Benefit from Commissions, Discounts, etc.


The remuneration of the Consultants pursuant to Clause 6 shall constitute the
Consultants' sole remuneration in connection with this Contract or the Services, and the
Consultants shall not accept for their own benefit any trade commission, discount, or
similar payment in connection with activities pursuant to this Contract or to the Services
or in the discharge of their obligations under the Contract, and the Consultants shall use
their best efforts to ensure that the Personnel, any Sub consultants, and agents of either
of them similarly shall not receive any such additional remuneration.

3.3 Confidentiality
The Consultants, their Sub-consultants, and the Personnel of either of them shall not,
either during the term or after the expiration of this Contract, disclose any proprietary or
confidential information relating to the Project, the Services, this Contract, or the
Client's business or operations without the prior written consent of the Client.

3.4 Liability of the Consultants

The Consultants are liable for the consequence of errors and omissions on their part or
on the part of their employees in so far as the design of the Project is concerned to the
extent and with the limitations as mentioned herein below.

If the Client suffers any losses or damages as a result of proven faults, errors or omissions
in the design of a project, the Consultants shall make good such losses or damages,
subject to the conditions that the maximum liability as aforesaid shall not exceed twice
the total remuneration of the Consultants for design phase in accordance with the terms
of the Contract.

Page 99 of 125
The liability of the Consultants expires after one (1) year from the stipulated date of
completion of construction or after three (3) years from the date of final completion of
the design whichever is earlier.

The Consultants may, to protect themselves, insure themselves against their liabilities
but this is not obligatory. The extent of the insurance shall be up to the limit specified in
second para above. The Consultants shall procure the necessary cover before
commencing the Services and the cost of procuring such cover shall be borne by the
Consultants up to a limit of one percent of the total remuneration of the Consultants for
the design phase for every year of keeping such cover effective.

The Consultants shall, at the request of the Client, indemnify the Client against any or
all risks arising out of the furnishing of professional services by the Consultants to the
Client, not covered by the provisions contained in the first para above and exceeding the
limits set forth in second para above provided the actual cost of procuring such indemnity
as well as costs exceeding the limits set forth in fourth para above shall be borne by the
Client.

3.5 Other Insurances to be Taken out by the Consultants

The Consultants (a) shall take out and maintain, and shall cause any Sub-consultants to
take out and maintain, at their (or the Sub-consultants', as the case may be) own cost but
on terms and conditions approved by the Client, insurance against the risks, and for the
coverage, as are specified in the SC; and (b) at the Client's request, shall provide evidence
to the Client showing that such insurance has been taken out and maintained and that the
current premiums have been paid.

3.6 Consultants' Actions Requiring Client's Prior Approval

The Consultants shall obtain the Client's prior approval in writing before taking any of
the following actions:

(a) appointing such Personnel as are listed in Appendix-C merely by title but not by
name;
(b) entering into a subcontract for the performance of any part of the Services, it
being understood (i) that the selection of Sub-consultants and the terms and
conditions of the subcontract shall have been approved in writing by the Client
prior to the execution of the subcontract, and (ii) that the Consultants shall remain
fully liable for the performance of the Services by the Sub-consultants and its
Personnel pursuant to this Contract;
(c) any other action that may be specified in the SC.

3.7 Reporting Obligations

The Consultants shall submit to the Client the reports and documents specified in

Page 100 of 125


Appendix-B in the form, in the numbers, and within the periods set forth in the said
Appendix.

3.8 Documents Prepared by the Consultants to be the Property of the Client

All plans, drawings, specifications, reports, and other documents and software prepared
by the Consultants in accordance with Sub-Clause 3.7 shall become and remain the
property of the Client, and the Consultants shall, not later than upon termination or
expiration of this Contract, deliver (if not already delivered) all such documents and
software to the Client, together with a detailed inventory thereof. The Consultants may
retain a copy of such documents and software.

Restriction(s) about the future use of these documents, is specified in the SC.

3.9 Equipment and Materials Furnished by the Client

Equipment and materials made available to the Consultants by the Client, or purchased
by the Consultants with funds provided by the Client, shall be the property of the Client
and shall be marked accordingly. Upon termination or expiration of this Contract, the
Consultants shall make available to the Client an inventory of such equipment and
materials and shall dispose of such equipment and materials in accordance with the
Client's instructions or afford salvage value of the same. While in possession of such
equipment and materials, the Consultants, unless otherwise instructed by the Client in
writing, shall insure them at the expense of the Client in an amount equal to their full
replacement value.

3.10 Accounting, Inspection and Auditing

The Consultants (i) shall keep accurate and systematic accounts and records in respect
of the Services hereunder, in accordance with internationally accepted accounting
principles and in such form and detail as will clearly identify all relevant time charges,
and cost, and the basis thereof, and (ii) shall permit the Client or its designated
representatives periodically, and up to one year from the expiration or termination of this
Contract, to inspect the same and make copies thereof as well as to have them audited
by auditors appointed by the Client.

4. CONSULTANTS' PERSONNEL AND SUB-CONSULTANTS

4.1 Description of Personnel

The titles, agreed job descriptions, minimum qualifications, and estimated periods of
engagement in the carrying out of the Services of the Consultants' Key Personnel are
described in Appendix C. The Key Personnel and Sub-consultants listed by title and/or
by name, as the case may be, in Appendix C are deemed to be approved by the Client.

4.2 Removal and/or Replacement of Personnel

Page 101 of 125


(a) Except as the Client may otherwise agree, no changes shall be made in the Key
Personnel. If, for any reason beyond the reasonable control of the Consultants, it
becomes necessary to replace any of the Key Personnel, the Consultants shall
provide as a replacement a person of equivalent or better qualifications.
(b) If the Client; (i) finds that any of the Personnel has committed serious misconduct
or has been charged with having committed a criminal action; or (ii) has
reasonable cause to be dissatisfied with the performance of any of the Personnel,
then the Consultants shall, at the Client's written request specifying the grounds
therefor, provide as a replacement a person with qualifications and experience
acceptable to the Client.
(c) Except as the Client may otherwise agree, (i) the Consultants shall bear all
additional travel and other costs arising out of or incidental to any removal and/or
replacement, and (ii) the remuneration to be paid for any of the Personnel
provided as a replacement shall not exceed the remuneration which would have
been payable to the Personnel replaced.

5. OBLIGATIONS OF THE CLIENT

5.1 Assistance, Coordination and Approvals

5.1.1 Assistance

The Client shall use its best efforts to ensure that the Client shall:

(a) provide at no cost to the Consultants, Sub-consultants and Personnel such


documents prepared by the Client or other consulting engineers appointed by the
Client as shall be necessary to enable the Consultants, Sub-consultants or
Personnel to perform the Services. The documents and the time within which
such documents shall be made available, are as specified in the SC;

(b) assist to obtain the existing data relevant to the carrying out of the Services, with
various Government and other organizations. Such items shall be returned by the
Consultants upon completion of the Services under this Contact;

(c) issue to officials, agents and representatives of the concerned organizations, all
such instructions as may be necessary or appropriate for prompt and effective
implementation of the Services;

(d) assist to obtain permits which may be required for right-of-way, entry upon the lands
and properties for the purposes of this Contract.

(e) provide to the Consultants, Sub-consultants, and Personnel any such other assistance and
exemptions as may be specified in the SC;

5.1.2 Co-ordination

The Client shall:

Page 102 of 125


(a) coordinate and get or expedite any necessary approval and clearances relating to
the work from any Government or Semi- Government Agency, Department or
Authority, and other concerned organization named in the SC.

(b) coordinate with any other consultants employed by him.

5.1.3 Approvals

The Client shall accord approval of the documents within such time as specified in the
SC, whenever these are applied for by the Consultants.

5.2 Access to Land

The Client warrants that the Consultants shall have, free of charge, unimpeded access to
all land of which access is required for the performance of the Services.

5.3 Change in the Applicable Law

If, after the date of this Contract, there is any change in the Applicable Law which
increases or decreases the cost of the Services rendered by the Consultants, then the
remunerations and direct costs otherwise payable to the Consultants under this Contract
shall be increased or decreased accordingly, and corresponding adjustment shall be made
to the amounts referred to in Sub-Clause 6.2 (a) or (b), as the case may be.

5.4 Services and Facilities

The Client shall make available to the Consultants, Sub-consultants and the Personnel,
for the purpose of the Services and free of any charge, the services, facilities and property
described in Appendix F at the times and in the manner specified in said Appendix F,
provided that if such services, facilities and property shall not be made available to the
Consultants as and when so specified, the Parties shall agree on; (i) any time extension
that it may be appropriate to grant to the Consultants for the performance of the Services;
(ii) the manner in which the Consultants shall procure any such services, facilities and
property from other sources; and (iii) the additional payments, if any, to be 17 made to
the Consultants as a result thereof pursuant to Clause 6 hereinafter.

5.5 Payments

In consideration of the Services performed by the Consultants under this Contract, the
Client shall make to the Consultants such payments and in such manner as is provided
by Clause 6 of this Contract.
6. PAYMENTS TO THE CONSULTANTS

6.1 Lump Sum Remuneration

The Consultants' total remuneration shall not exceed the Contract Price and shall be a
fixed lump sum including all staff costs, incurred by the Consultants in carrying out the

Page 103 of 125


Services described in Appendix A. Other reimbursable direct costs expenditure, if any,
are specified in the SC. Except as provided in Sub-Clause 5.3, the Contract Price may
only be increased above the amounts stated in Sub-Clause 6.2 if the Parties have agreed
to additional payments in accordance with Sub-Clauses 2.5, 2.6, 5.4 or 6.6.

6.2 Contract Price

(a) Foreign currency payment shall be made in the currency or currencies specified
as foreign currency or currencies in the SC, and local currency payment shall be
made in Pakistani Rupees.
(b) The SC shall specify the breakup of remuneration to be paid, respectively, in
foreign and in local currencies.

6.3 Terms and Conditions of Payment

Payment will be made to the account of the Consultants and according to the payment
schedule stated in the SC. Payments shall be made after the conditions listed in the SC
for such payments have been met, and the Consultants have submitted an invoice to the
Client specifying the amount due.

6.4 Period of Payment

(a) Advance payment to the Consultants shall be affected within the period specified
in the SC, after signing of the Contract Agreement between the Parties.
(b) Any other amount due to the Consultants shall be paid by the Client to the
Consultants within twenty-eight (28) days in case of local currency and fifty-six
(56) days in case of foreign currency after the Consultants' invoice has been
delivered to the Client.

6.5 Delayed Payments

If the Client has delayed payments beyond the period stated in paragraph (b) of Sub-
Clause 6.4, financing charges shall be paid to the Consultants for each day of delay at
the rate specified in the SC.

6.6 Additional Services

Additional Services means:

(a) Services as approved by the Client outside the Scope of Services described in
Appendix A;

(b) Services to be performed during the period extended pursuant to Sub-Clause 2.6,
beyond the original schedule time for completion of the Services; and

(c) any re-doing of any part of the Services as a result of Client's instructions. If, in
the opinion of the Client, it is necessary to perform Additional Services during
the currency of the Contract for the purpose of the Project, such Additional

Page 104 of 125


Services shall be performed with the prior concurrence of both the Parties. The
Consultants shall inform the Client of the additional time (if any), and the
additional remuneration and reimbursable direct costs expenditure for such
Additional Services. If there is no disagreement by the Client within two weeks
of this intimation, such additional time, remuneration and reimbursable direct
costs expenditure shall be deemed to become part of the Contract. Such
remuneration and reimbursable direct costs expenditure shall be determined on
the basis of rates provided in Appendices D and E, in case the Additional Services
are performed during the scheduled period of the Services, otherwise
remuneration for Additional Services shall be determined on the basis of
Consultants' billing rates prevailing at the time of performing the Additional
Services.

6.7 Consultants' Entitlement to Suspend Services

If the Client fails to make the payment of any of the Consultants' invoice (excluding the
advance payment), within twenty-eight (28) days after the expiry of the time stated in
paragraph (b) of Sub-Clause 6.4, within which payment is to be made, the Consultants
may after giving not less than fourteen (14) days' prior notice to the Client, suspend the
Services or reduce the rate of carrying out the Services, unless and until the Consultants
have received the payment.

This action will not prejudice the Consultants entitlement to financing charges under
Sub-Clause 6.5.

7. SETTLEMENT OF DISPUTES

7.1 Amicable Settlement

The Parties shall use their best efforts to settle amicably all disputes arising out of or in
connection with this Contract or its interpretation.

7.2 Dispute Settlement

Any dispute between the Parties as to matters arising pursuant to this Contract which
cannot be settled amicably within thirty (30) days after receipt by one Party of the other
Party's request for such amicable settlement may be submitted by either Party for
settlement in accordance with the provisions of the Arbitration Act, 1940 (Act No. X of
1940) and Rules made thereunder and any statutory modifications thereto.

Services under the Contract shall, if reasonably possible, continue during the arbitration
proceedings and no payment due to or by the Client shall be withheld on account of such
proceedings.

8. INTEGRITY PACT

8.1 If the Consultants or any of his Sub-consultants, agents or servants is found to have
violated or involved in violation of the Integrity Pact signed by the Consultants as
Appendix-G to this Form of Contract, then the Client shall be entitled to:

Page 105 of 125


(a) recover from the Consultants an amount equivalent to ten times the sum of any
commission, gratification, bribe, finder’s fee or kickback given by the
Consultants or any of his Sub-consultant, agents or servants;

(b) terminate the Contract; and

(c) recover from the Consultants any loss or damage to the Client as a result of such
termination or of any other corrupt business practices of the Consultants or any
of his Sub-consultant, agents or servants.

On termination of the Contract under Sub-Para (b) of this Sub-Clause, the Consultants shall
proceed in accordance with Sub-Clause 2.9.3. Payment upon such termination shall be made
under Sub-Claus 2.9.4
(a) after having deducted the amounts due to the Client under Sub- Para (a) and (c) of this
Sub-Clause.

Page 106 of 125


III. SPECIAL CONDITIONS OF CONTRACT

1.1 Definitions

Following definition (ca) is added.


(ca) “Defects Liability Period” means a period of Three Hundred Sixty-Five (365) days
starting from the date of taking over/completion of the Project/parts of project as
mentioned in the taking over/completion certificate or in the event of more than one
taking over/completion certificate from the respective dates, issued to the contractor.
During this period the Consultants shall be responsible to test and inspect in detail, the
works done by the contractor and get any defects and / or omissions rectified through the
contractor.

(p) "Project “means “RESIDENT CONSTRUCTION SUPERVISION FOR


CONSTRUCTION NAWAZ SHARIF INSTITUTE OF CARIOLOGY,
SARGODHA”

1.6 Authorized Representatives

The Authorized Representatives are the following:

For the Client: _________________


_________________
50-B-3, Gulberg-III, Lahore
Telephone : +92 42 99332631- 42
Email :

For the Consultant: __________________


__________________
__________________

1.8 Leader of Joint Venture


The leader of joint venture is _____________________

2.1 Effectiveness of Contract

The date on which this Contract shall come into effect is the date when the Contract is
signed by both the Parties.

2.2 Termination of Contract for Failure to Become Effective

This sub-clause is deleted in its entirety.

Page 107 of 125


2.3 Commencement of Services

The Services shall commence on the date mentioned in the letter of


commencement issued by the Client.

Confirmation of key experts’ availability to start the Services shall be submitted


by Consultants to the Client in writing as a written statement signed by each key
expert.
Client reserves the right to interview & approve or otherwise reject key personnel
for the project provided by the Consultant.

2.4 Expiration of Contract

The period of completion of Services shall be Four Hundred and Fifty Six
(456) days for construction supervision phase plus Three-Hundred Sixty-Five
(365) days for Defect Liability Period from the date of commencement of the
Services or such other period as the Parties may agree in writing.

Completion of Services" means all Services to be performed and deliverables,


documents, drawings, etc. to be submitted to the Client as mentioned in
Appendices A and B have been completed and delivered to the satisfaction of the
Client.

2.6 Extension of Time for Completion

The text of this sub-Clause is deleted and replaced with the following text

1. If the scope of the Services is required to be increased:


a) the Consultants shall inform the Client of the circumstances and
probable effects of such increase in the Services;
b) the Client and the Consultants may increase the scope of Services
for which remuneration and reimbursable direct costs expenditure shall
be determined on the basis of rates provided in Appendix E; and
c) the Client may extend the time for completion of Additional
Services, if necessary, as it may deem appropriate. The increase
in scope of Services shall be regarded as Additional Services.

2. If the duration for Completion of the Services is required to be


increased:

a) the Consultants shall request the Client for such increase and shall
provide sufficient cause for it along with probable effects of such
increase;
b) the Client may accord such extension if deemed

Page 108 of 125


appropriate.

2.7.3 Extension of Time

The text of this sub-Clause is deleted and replaced with the following text

If as a result of Force Majeure a party is rendered unable to perform its duties under this
Contract, the Parties shall mutually determine period of extension of time for completion
of such duties.

3.4 Liability of the Consultants

The text of this sub-Clause is deleted and replaced with the following text
“The Consultants are liable for the consequence of errors and omissions on their part or
on the part of their employees to the extent and with the limitations as mentioned herein
below.

If the Client suffers any losses or damages as a result of proven faults, errors or omissions
by the Consultants, the Consultants shall make good such losses or damages, subject to
the conditions that the maximum liability as aforesaid shall not exceed twice the total
remuneration of the Consultants in accordance with the terms of the Contract.

The liability of the Consultants expires after one (1) year from the stipulated date of
completion of construction.

The Consultants may, to protect themselves, insure themselves against their liabilities
but this is not obligatory. The extent of the insurance shall be up to the limit specified in
second para above. The Consultants shall procure the necessary cover before
commencing the Services and the cost of procuring such cover shall be borne by the
Consultants up to a limit of one percent of the total remuneration of the Consultants for
every year of keeping such cover effective.

The Consultants shall, at the request of the Client, indemnify the Client against any or
all risks arising out of the furnishing of professional services by the Consultants to the
Client, not covered by the provisions contained in the first para above and exceeding the
limits set forth in second para above provided the actual cost of procuring such indemnity
as well as costs exceeding the limits set forth in fourth para above shall be borne by the
Client.”

3.6 Consultants' Actions Requiring Client's Prior Approval

The Consultants shall seek prior approval from the Client, before any action they propose
to take under the following:

i) Consenting to the sub-letting of any part of the Works under “Subcontracting”

Page 109 of 125


ii) Certifying additional cost determined under “Not Foreseeable Physical
Obstructions or Conditions”.
iii) Any action relating to “Performance Security” and “Insurances”.
iv) Any action relating to “Suspension”
v) Any action relating to “Extension of Time for Completion”
vi) Any action relating to “Liquidated Damages for Delay” or Payment of Bonus for
Early Completion of Works
vii) Issuance of “Taking Over Certificate”
viii) Issuing or Instructing a Variation, except:
- In an emergency situation, as stated here below[1], and
- If sum of all such variations during the Contract Period would increase the
Contract Price by less than the ceiling amount stated in the Appendix-A to
Bid.
ix) Fixing rates or prices for Variations
x) Extra Payment as a result of the Contractor’s Claims under any of the conditions
of Construction Contract or otherwise in connection with the Construction
Contract
xi) Release of Retention Money to the Contractors
xii) Issuance of “Final Payment Certificate(s)”
xiii) Issuance of “Defects Liability Certificate(s)”
xiv) To use “Termination Clause” of the Conditions of Contract.
xv) Any other limitation(s) indicated in Construction Contract(s) or requirement
specified by the Client at any time during the currency of Contract.

3.8 Documents Prepared by the Consultants to be the Property of the Client

The Consultants shall not use these documents for purposes unrelated to this Contract
without the prior written approval of the Client.

4.1 Description of Personnel

Following text is added at the end of this Clause

“In case the Consultant fails to provide the Key Personnel in accordance with the
Sub-Clause 4.1 [Description of Personnel] and provision of staff requirement as
mentioned in Annexure A [Scope of Services] the Consultant shall be liable as
under:

An amount equivalent to fifty percent (50%) of the corresponding monthly


remuneration of the personnel shall be deducted from any Payment due to the

1
If in the opinion of the Engineer an emergency occurs affecting the safety of life or of the Works or of adjoining property, the
Engineer may, without relieving the Contractor of any of his duties and responsibilities under the Construction Contract, instruct
the Contractor to execute all such work or to do all such things as may, in the opinion of the Engineer, be necessary to abate or
reduce the risk.

Page 110 of 125


Consultant by the Client. For a period less than one month this amount shall be
calculated on an hourly basis for actual time spent by the Personnel (one hour
being equivalent to 1/170th of a month).

Such deduction shall continue for the period till the provision of the personnel by
the Consultant or any other person having equivalent or better qualification duly
accepted by the Client.

In the event the Consultant does not provide the personnel or any other person
having equivalent or better qualification as accepted by the Client; then the Client
may arrange for the personnel at the risk and cost of the Consultant.

These deductions shall be made without prejudice to any other liability of the
Consultant contained in this Contract. “

4.2 Removal and / or Replacement of Personnel

In Sub-Clause (a) the word “provide” shall be replaced with “propose”.

At the end of Sub-Clause (a), the following text shall be added:

“the Client shall accord its approval, or otherwise rejection, within fourteen (14) days of
receipt of the request for replacement from the Consultants”.

5.1.1 Assistance

(a) The Client shall make available to the Consultants within twenty one
(21) days from the Commencement Date, all existing documents, data,
information, studies and reports related to the project available with the Client.

The Client shall also assist the Consultants in obtaining necessary permits
wherever required.
5.1.2 Coordination

The Client shall assist the Consultant in obtaining any data, approval / clearance relating
to the services as required from the concerned departments and other agencies;

5.1.3 Approvals

The Client shall accord approval of or otherwise comment on the documents


immediately but not later than fourteen (14) days from the date of their submission by
the Consultants.

5.3 Change in the Applicable Law

The text of this sub-Clause is deleted and replaced with the following text

If, after the date of this Contract, there is any change in the law related to Sales Tax only,

Page 111 of 125


which increases or decreases the cost of the Services rendered by the Consultants, then
the remunerations and direct costs otherwise payable to the Consultants under this
Contract shall be increased or decreased accordingly, and corresponding adjustment
shall be made to the amounts referred to in Sub-Clause 6.2 (a) or (b), as the case may be.

6.2 Contract Price

Total Contract Price in Pak Rupees is __________

6.3 Terms and Conditions of Payment


Remunerations for the personnel shall be determined on the basis of time actually spent
by such personnel in the performance of the Services from the date of commencement of
services.

The staff month rates for Consultants’ staff set forth in Appendix E, hereof shall be used
for monthly billing purposes on terms stated as under.

1. Resident Construction Supervision Phase

a. The remuneration for construction supervision shall be paid on monthly basis


against the personnel actually present at site for that specific period in
accordance with the billing rates provided in Appendix-E.

b. Remuneration for periods of less than one month shall be calculated on an


hourly basis for actual time spent in the Consultants' home office and directly
attributable to the Services (one hour being equivalent to 1/170th of a month)
and on a calendar-day basis for time spent away from home office.

c. Payment for Direct Cost Expenses (construction supervision phase) as stated


in Appendix E shall be claimed on monthly basis over total resident
construction supervision services period.

2. Defect Liability Phase

Payment for defect liability period (salary cost + direct cost) as stated in Appendix-E
shall be claimed on quarterly basis over total defect liability period

As soon as practicable and preferably within thirty (30) days after the end of each calendar
month during the period of the Services, the Consultants shall submit their bill in duplicate
to the Client. Supporting documents shall be submitted for reimbursable direct costs
expenditure, if any.

All payments in respect of Services shall be made through bank draft/crossed cheque
‘Payees A/C Only’ or through direct transfer in favour of the Consultants.

Page 112 of 125


Ten percent (10%) shall be retained from each invoice of the Consultant which shall be
released as per following schedule
1. Submission of Project Taking Over Documents and IDAP acceptance thereto:
04%
2. As built Documents & Records and IDAP acceptance thereto: 04%
3. Project Completion Report and IDAP acceptance thereto: 02%

6.4 Period of Payment

1. The Consultants may request for an advance payment of an amount upto ten per
cent (10%) of the Contract Price. The time period to request for advance payment
shall be twenty eight (28) days after signing of the Contract. However, advance
payment shall only be released after submission of bank guarantee, securing the
full amount of advance payment. This bank guarantee shall be issued by a
scheduled bank of Pakistan or by an international bank counter- guaranteed by a
scheduled bank of Pakistan, against the requested advance payment in the format
provided at Appendix H.

The advance payment will be set off by the Client in the following manner:
Twenty percent (20%) of advance payment shall be deducted by Client from first
five payments to the Consultants against Consultants’ Invoice within seven (07)
days of full adjustment of the advance payment, the Client shall release the
advance payment guarantee.

6.5 Delayed Payments

This Clause is deleted in its entirety

6.6 Additional Services

Sub-Clause (c) is deleted and replaced with following text


If, in the opinion of the Client, it is necessary to perform additional services during the
currency of the Contract for the purpose of the Project / redoing of work upon
written/verbal instructions of the Client, such Additional Services shall be performed
with the prior concurrence of both the Parties unless such redoing is attributable as a
fault of the Consultants. The Consultants will submit an estimate of the additional time
(if any) and the additional remuneration for such additional services which shall be
approved by the Client in writing before commencement of the additional services. Such
remuneration and reimbursable direct costs expenditure shall be determined on the basis
of rates provided in Appendix E

7.2 Dispute Settlement


Following text is added in the end:
Venue of arbitration shall be Lahore.
Number of arbitrators shall be three (3) including umpire. Each party shall appoint their
arbitrator and the arbitrators shall appoint the umpire.

Page 113 of 125


Page 114 of 125
IV APPENDICES

Page 115 of 125


Appendix A

Description of the Services (Terms of Reference)

Page 116 of 125


Appendix B

Reporting Requirements

Page 117 of 125


Appendix C
Key Personnel and Sub consultants

Page 118 of 125


Key Personnel

Page 119 of 125


Appendix D

Breakdown of Contract Price in Foreign Currency

NOT USED

Page 120 of 125


Appendix E

Breakdown of Contract Price in Local Currency

Page 121 of 125


Appendix F

Services and Facilities to be Provided by the Client

Services and Facilities to be provided by the Client are mentions in TORs.

Page 122 of 125


Appendix G
(INTEGRITY PACT)

DECLARATION OF FEES, COMMISSION AND BROKERAGE ETC. PAYABLE BY THE SUPPLIERS


OF GOODS, SERVICES & WORKS

Contract No. Dated


Contract Value:
Contract Title
M/s ________ hereby declares that it has not obtained or induced the procurement of any contract, right,
interest, privilege or other obligation or benefit from Government of the Punjab (GoPb) or any administrative
subdivision or agency thereof or any other entity owned or controlled by GoPb through any corrupt business
practice.

Without limiting the generality of the foregoing, M/s _______ represents and warrants that it has fully declared
the brokerage, commission, fees etc. paid or payable to anyone and not given or agreed to give and shall
not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural
or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter,
shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder’s fee or kickback, whether
described as consultation fee or otherwise, with the object of obtaining or inducing the procurement of a
contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoPb, except that
which has been expressly declared pursuant hereto.

M/s _________ certifies that it has made and will make full disclosure of all agreements and arrangements
with all persons in respect of or related to the transaction with GoPb and has not taken any action or will not
take any action to circumvent the above declaration, representation or warranty.

M/s _______ accepts full responsibility and strict liability for making any false declaration, not making full
disclosure, misrepresenting facts or taking any action likely to defeat the purpose of this declaration,
representation and warranty. It agrees that any contract, right, interest, privilege or other obligation or benefit
obtained or procured as aforesaid shall, without prejudice to any other rights and remedies available to GoPb
under any law, contract or other instrument, be voidable at the option of GoPb.

Notwithstanding any rights and remedies exercised by GoPb in this regard, M/s _____ agrees to indemnify
GoPb for any loss or damage incurred by it on account of its corrupt business practices and further pay
compensation to GoPb in an amount equivalent to ten time the sum of any commission, gratification, bribe,
finder’s fee or kickback given by M/s ______ as aforesaid for the purpose of obtaining or inducing the
procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from
GoPb.

Infrastructure Development ________________________


Authority the Punjab: ________________________

Signature: Signature:
[Seal] [Seal]

Page 123 of 125


Appendix H
FORM OF GUARANTEES

Form of Advance Payment Guarantee

Guarantee No. ___________________ Date: __________________________

WHEREAS (hereinafter called the 'Client') has entered into a Contract for (Particulars of
Contract) with (hereinafter called the "Consultants').

AND WHEREAS, the Client has agreed to advance to the Consultants, at the Consultants'
request, an amount of Rupees (Rs
) which amount shall be advanced to the Consultants as per provisions of the
Contract.

AND WHEREAS, the Client has asked the Consultants to furnish Guarantee to secure the
mobilization advance for the performance of his obligations under the said Contract.

AND WHEREAS,
(Scheduled Bank in Pakistan acceptable to the Client)
(hereinafter called the “Guarantor”) at the request of the Consultants and in consideration of
the Client agreeing to make the above advance to the Consultants, has agreed to furnish the said
Guarantee.

NOW, THEREFORE, the Guarantor hereby guarantees that the Consultants shall use the
advance for the purpose of above mentioned Contract and if he fails and commits default in
fulfilment of any of his obligations for which the advance payment is made, the Guarantor shall
be liable to the Client for payment not exceeding the aforementioned amount.

Notice in writing of any default, of which the Client shall be the sole and final judge, on the
part of the Consultants, shall be given by the Client to the Guarantor, and on such first written
demand, payment shall be made by the Guarantor of all sums then due under this Guarantee
without any reference to the Consultants and without any objection.

This Guarantee shall remain in force until the advance is fully adjusted against payments from
the Interim Payment Certificates of the Consultants or until whichever is earlier.
(Date)

The Guarantor's liability under this Guarantee shall not in any case exceed the sum of Rupees
(Rs
).

This Guarantee shall remain valid up to the aforesaid date and shall be null and void after the
aforesaid date or earlier if the advance made to the Consultants is fully adjusted against
payments from Interim Payment Certificates of the Consultants provided that the Guarantor
agrees that the aforesaid period of validity shall be deemed to be extended if on the above

Page 124 of 125


mentioned date the advance payment is not fully adjusted.
_______________
Guarantor (Bank)
Witness:
1. _______________________ Signature _______________

_______________________ Name __________________


Corporate Secretary (Seal)
Title ___________________

2. _______________________

_______________________ _______________________
Name, Title & Address Corporate Guarantor (Seal)

Page 125 of 125

You might also like