Professional Documents
Culture Documents
(Ningbo) Final Draft - Rejoinder - 11062024
(Ningbo) Final Draft - Rejoinder - 11062024
(Ningbo) Final Draft - Rejoinder - 11062024
15 JUNE 2024
FILED THROUGH:
RPV Legal
INDEX
S. No. Particulars Page No.
1. Rejoinder to Statement of Claim
2. Annexure C-1:
3. Annexure C-2:
Through,
RPV Legal
Counsel for the Respondent
D-19, Second Floor, Geetanjali Enclave
New Delhi – 110017
Date: 15 June 2024 Phone: +91 11 41834272
Place: New Delhi E: info@rpvlegal.com
BEFORE THE HON’BLE TRIBUNAL COMPRISING OF:
HON’BLE MR. JUSTICE S. MURALIDHAR (RETD.)
(SOLE ARBITRATOR)
I. INTRODUCTION
I.2. All capitalized terms and abbreviations used herein shall have the same
meaning given to them in the Contract executed between the Parties and
the pleadings of the Parties, unless otherwise stated or the context
requires otherwise.
I.3. The Claimant denies all the allegations, statements and contentions set
out by the Respondent in the SoD in totality. Nothing contained therein
shall be deemed to have been admitted by the Claimant merely for want
of specific denial and nothing may be construed as being admitted on
the ground of non-traverse. Further, anything stated in the SoD which is
in variance with the pleadings filed by the Claimant, is specifically
denied.
Andy wrote:
“… Vikas, please let me know what can you deliver in June and July.
Also please give me CFR price, no fob. …”
Yash wrote:
“… Our price for CFR is $ 1470 PMT and rest terms and conditions
remain the same.
… In June and July 2021 we will deliver the 1500 MT material either
in 3 or 5 parts as per the availability of the containers. …”
A copy of the email trail titled “Quote for Ferro Silico Manganese”
exchanged between the Parties is annexed herewith and marked as
Annexure C-____.
II.3. It is also relevant to highlight that upon further inquiry and clarification
sought by the Claimant regarding the need for prompt delivery, the
Respondent reassured and represented itself to be a regular trader of
FESIMN and boasted about previous dealings with other international
clients. The Respondent further represented to the Claimant that it
exports FESIMN on a weekly basis and had more than sufficient stock
of the required FESIMN available with it for a prompt delivery. It
categorically stipulated that the agreed quantity of FESIMN shall be
ready by 15.06.2021, and that the estimated transit time for delivery of
the same would be a month after the SOB Date. A copy of the relevant
screenshots of the WhatsApp communications exchanged between the
Parties are annexed herewith and marked as Annexure C- (Colly.)
[14.07.2021, 22.07.2021, 09.08.2021]
II.4. Thus, it was only on account of the numerous representations and
assurances made by the Respondent regarding the ready availability of
the required stock, and the timely delivery thereof, that the Parties
integrated the terms of the present Contract for the sale and purchase of
1000 MT of FESIMN at USD 1,470/- PMT to be delivered in June and
July 2021. It was based on this understanding, that the terms of the
Contract were signed, including the SOB Date which was to fall strictly
within 20.06.2021 to 19.07.2021.
II.5. At the outset, it is pertinent to highlight and emphasize on the object and
purpose of the Contract dated 14.05.2021 (‘Contract’). As per the terms
of the Contract, the Respondent (seller) was obligated to supply a total
quantity of 1000 MT of Ferro Silico Manganese (‘FESIMN’) having the
specifications provided under Clause 1. Further, as per Clause 5 of the
Contract, the said quantity of FESIMN was to be shipped on board by
the Respondent within 20.06.2021 to 19.07.2021 (‘SOB Date’).
II.6. The Contract also laid down provisions for ‘Guarantee on Quality’
(Clause 14), ‘Penalty of Quality’ (Clause 15), ‘Late Delivery and
Penalty’ (Clause 18), etc., which categorically highlight that adherence
to the quality specifications and the SOB Date as stipulated under the
Contract formed the basis and essence of the Contract. In view thereof,
it is clear that prompt and timely delivery of FESIMN, having the
contractually provided specifications, was the sine qua non of the
Contract.
II.7. It is significant to note that the Respondent committed a flagrant and
material breach of the terms that formed the essence of the Contract.
Specifically, despite repeated requests and objections raised by the
Claimant, the Respondent never supplied FESIMN conforming to the
contractual specifications and failed to ship on board any FESIMN at all
within the SOB timeline stipulated under Clause 5 of the Contract. The
same is evident from the following table:
II.8. As discussed above, the terms of the Contract required the Respondent
to ship on board the entire quantity of FESIMN i.e., 1000 MT, within
20.06.2021 to 19.07.2021. However, despite receiving the Advance
Payment of USD 588,000/- from the Claimant on 18.05.2021, i.e., 40%
of the total Contract Value, the Respondent has only supplied 187 MT of
FESIMN (18.7% of the entire quantity) till date. Moreover, the FESIMN
supplied by the Respondent did not even conform with the specifications
provided under the Contract.
II.9. Notably, the Respondent has not provided any explanation in its SoD for
its failure to supply FESIMN having the contractually provided
specification. Therefore, the Respondent’s breach to supply FESIMN of
the specifications provided under Clause 1 of the Contract stands
established.
II.11. As discussed above, the terms of the Contract required the Respondent
to supply 1000 MT of specified quality of FESIMN to the Claimant,
which was to be shipped on board within 20.06.2021 to 19.07.2021, for
a total contract value of USD 1,470,000/-. Thus, making it clear that the
Respondent was obligated to ship on board the entire quantity of
FESIMN i.e., 1000 MT, by 19.07.2021. On this premise, the Contract
required the Claimant to make an Advance Payment of USD 588,000/-,
i.e., 40% of the total Contract Value (Clause 9), which was duly
remitted by the Claimant on 18.05.2021, i.e., within 4 days of the date of
the Contract.
II.13. Notwithstanding the above, even if the arbitrary and hypothetical rates
proposed by the Respondent for the supply of FESIMN, which were
never approved by the Claimant, are taken into account, the total value
of the FESIMN supplied till date amounts to USD 337,340/-. The same
is evident from the table given below:
II.20. The Respondent, throughout the SoD, has contended that the terms of
the Contract, specifically pertaining to the delivery schedule (Clause 5),
quality specifications and price of FESIMN (Clause 1), as were initially
agreed, stood novated on account of the mutual agreement between the
Parties. It is the Respondent’s contention that since the Claimant had
agreed and assented to the revised terms of the Contract, it has thereby
waived its right(s) to raise any claim in relation to delivery time and
composition of the FESIMN delivered.
II.22. In this background, the Claimant submits that insofar the alleged
revision of the Delivery Schedule/SOB Date is concerned, the
Claimant’s acceptance was obtained by way of fraudulent
misrepresentations and false promises made by the Respondent
regarding the ready availability of FESIMN and timely delivery thereof.
Throughout the duration of the Contract, the Respondent took advantage
of the Claimant’s need for prompt and immediate delivery and resorted
to dilatory tactics and fraudulent approach to keep the transaction open.
Notably, upon Respondent’s repeated failure, the Claimant, on several
occasions, also gave opportunities to the Respondent to immediately
intimate it if the delivery within the indicated time was not possible, and
accordingly proceed with the refund of the Advance Payment. This was
to allow the Claimant to arrange alternate suppliers to meet the delivery
deadline set by its downstream buyer. However, the Respondent adopted
a lackadaisical approach and repeatedly made false assurances regarding
the timely delivery of goods. Despite the accommodation and flexibility
provided by the Claimant, the Respondent continued to take advantage
of the situation for it personal economic gains and kept deferring the
delivery schedule on one pretext or the other, with no sign of delivery.
II.23. In view thereof, the Respondent’s contention that the SOB Date was
novated by mutual agreement by the Parties is utterly misplaced. The
Claimant’s reluctance and disinterest to continue with the Contract, in
view of the frequent deferments made by the Respondent in the delivery
schedule, is further evident from various email communications dated
07.10.2021, 13.10.2021 & 18.10.2021, whereby the Claimant gave final
warnings and last opportunities to the Respondent to ship on board the
required goods by 07.11.2021. The Claimant also categorically informed
the Respondent that in case of its failure to adhere to the final deadline,
the Claimant would request a refund of the deposit made by it and assign
the Contract to another supplier. [Annexure C- , Annexure C- , &
Annexure C- ]
II.26. Regardless, soon after, the Respondent started giving excuses regarding
the difficulties around initiating refunds. On 19.11.2021, Amit stated,
"As informed earlier, this will be done by next week." Then, on
01.12.2021, Amit provided a circular for Third Country Trade or
Merchant Trade, suggesting thorough legal review and the long
procedure surrounding the refund process. These issues were being
continuously highlighted by the Respondent, despite it representing
initially that it was a regular international trader. In fact, even until a
year later, on 23.11.2022, Amit mentioned, "But due to RBI guidelines,
it has been stuck at the bank's side and not from our side." A copy of the
relevant WhatsApp communications and e-mails wherein the
Respondent raised concerns regarding initiating refund are annexed
herewith and marked as Annexure C-___.
II.27. In view thereof, the Claimant was left with no option but to either accept
delivery as per the Respondent’s timelines or to wait indefinitely for the
refund. Therefore, the alleged novation in the Delivery Schedule/SOB
Date was not upon mutual agreement but out of economic duress. Below
is a list of dates wherein the Respondent made false representations and
assurances regarding prompt delivery of FESIMN and reimbursement of
the balance Advance Payment but reneged on the said promises:
“…
First of all, I would appreciate it if you could answer the phone and
have a conversation as we used to. Rejecting calls and blocking
messages on WhatsApp is not the solution to your problems.
Amit, over the last six months, there have always been constant
changes and difficulties from your company, which have not been
explained in time and create uncertainty at our end.
… It seems like you have had issues with everyone involved in your
operations.
At this stage, my advice is to be realistic and honest. If you don't
have the material, refund us our balance, and we will finish this
here.
….
To summarise, please share it with us if you have a CONFIRMED
delivery plan from INDIA for the remaining 6 FCLs.
If not, do not worry about finding solutions at this stage; place our
reimbursement, and we will conclude our contracts without
escalating the issue to arbitration.
…”
II.28. In view of the foregoing, it is evident that the Claimant categorically and
repeatedly requested the Respondent to reimburse/refund the balance
advance amount paid to it by the Claimant, in case delivery was not
possible within the proposed deadlines. However, the Respondent
continued to give false assurances to the Claimant regarding its ability to
make timely delivery. The said conduct of the Respondent rendered the
Claimant helpless, leaving it with no option but to accede to the
timelines proposed by the Respondent.
II.30. It is the Respondent’s case that the Claimant accepted the FESIMN
supplied by the Respondent even though all inspection reports were sent
to the Claimant prior to the delivery of the goods. However, as has
already been discussed, the Certificate of Quality/Analysis were to be
provided to the Claimant not prior to the ‘delivery of the goods’ rather
prior to the same being ‘shipped on board’. This was essential to afford
an opportunity to the Claimant to inspect the material(s) for any quality
deviation before the goods were dispatched. As already elaborated in
para 2.18 of this Rejoinder, the Respondent miserably failed to furnish
the Shipment Documents before the SOB Date, thus, depriving the
Claimant of the opportunity to raise concerns regarding any deviations
in specifications prior to the goods being shipped on board. Although
the Certificate of Quality/Analysis for the 2 nd Consignment was issued
on 10.09.2021, i.e., prior to its SOB Date, it highlighted several
discrepancies in the FESIMN, which were duly communicated to the
Respondent.
II.31. It may be relevant to mention that time and again, the Claimant raised
issues and objections with respect to deviations in specifications of the
FESIMN supplied by the Respondent, however, it completely
discredited and disregarded the deviations highlighted by the Claimant.
Instead, the Respondent imposed the FESIMN of varying specifications
upon the Claimant by stating that the same were of a superior quality
than the one stipulated under the Contract. The same is evident from
numerous correspondences exchanged between Parties, some of which
are reproduced below:
“…
1. FOR 54 MT FE SI MN , WE HAVE ALREADY INFORMED
YOU NOT TO RETEST AND WASTE TIME AND MONEY ,
INSTEAD ASK THE CUSTOMER TO USE THE GOODS .
…”
“…
ALL specifications must meet criteria as per our contract
agreement (chemical composition, size and packing)
…
Every other single supplier has delivered their material within time
and the required tolerances, under the same circumstances and
market conditions.
We are not authorised to accept any other delivery out of
specification.
…”
II.32. In view thereof, it is incorrect for the Respondent to assert that the
quality specifications as specified in Clause 1 of the Contract were
mutually revised by the Parties. Instead, it was the Respondent who, as
early as 19.05.2021, i.e., 5 days after entering the Contract, proposed to
supply a substituted/different quality of FESIMN, contrary to the terms
of the Contract. The said proposal was categorically and explicitly
declined by the Claimant on 20.05.2021, in light of its commitments to
its downstream buyers and requested the Respondent to strictly adhere
to the terms of the Contract. Therefore, it becomes manifestly clear that
from the very nascent stage of the Contract, the Respondent lacked both
the ability and the intent to perform the present Contract, but it
continued to misrepresent and give false assurance to the Claimant.
II.34. The Respondent has further contended in the SoD that the price of
FESIMN, as was contractually agreed between the Parties, stood
novated broadly on the following counts: a) the Claimant’s approval of
the Respondent’s request to pay an additional fee of USD 100/- PMT,
over and above the contractually agreed price, i.e., USD 1,470/- PMT on
account of enhanced composition of FESIMN; b) the Claimant’s
acceptance of 2nd and 3rd Consignments of FESIMN at escalated prices.
II.35. At the outset, it is highlighted that the alleged additional fee of USD
100/- PMT for the 2nd Consignment was not accepted by the Claimant on
account of the enhanced composition of FESIMN, but on Respondent’s
false representation to promptly delivery the same. It already stands
established that the Claimant did not only raise concerns regarding the
FESIMN being out of contractual specification but categorically denied
the requirement of the alleged better product than the one agreed in the
Contract. Reference in this regard is made to Paras 2.30 to 2.33 of this
Rejoinder.
II.36. In this regard, it must be highlighted that the additional support of USD
100 PMT was sought by the Respondent on the false pretext that 81 MT
cargo would be shipped within 30 days, i.e., by 17.10.2021. It was only
on this pretext, that the Claimant reluctantly agreed to provide an
additional support of USD 100 PMT, over and above the contractual
price. Pertinently, the said approval was conditional upon prompt
delivery of goods by the Respondent, which is clear from the contents of
the email dated 17.09.2021. (Reference is drawn from Annexure D-9
of the SoD)
II.40. The said conduct of the Respondent is clearly infested with malafide as
it deliberately withheld the documents from the Claimant, depriving the
latter of the opportunity to raise any objection with respect to price or
composition of the goods supplied, prior to the same being dispatched.
In view thereof, it is wholly erroneous and out of place for the
Respondent to state that the said price was mutually agreed between the
Parties. Needless to mention that the said consignment of 56 MT of
FESIMN was only shipped on board on 05.05.2022, i.e., after an
extraordinary and unexplained delay of around 10 months from the
expiry of the SOB Date. Additionally, the Respondent has failed to
place on record any document to substantiate that the Parties mutually
agreed to the price escalation with respect to the said consignment.
Thus, the Respondent’s averment regarding the alleged novation in the
contractually agreed price for the 3 rd Consignment of FESIMN also falls
short of truth, is completely erroneous and devoid of merit.
II.41. In conclusion, it is submitted that the terms of the Contract were never
mutually or even willingly revised/novated by the Parties, rather the
whole transaction is perpetrated by Respondent’s fraudulent
misrepresentations from the very inception. A bare perusal of the
correspondences exchanged between the Parties, makes it abundantly
clear that the Claimant’s acquiescence to the repeated deferments in the
delivery schedule, were solely premised on the misrepresentations, false
promises and excused made by the Respondent to make refunds,
deliveries, etc., even though it neither had the intention nor the ability to
honor the terms of the Contract.
II.43. The Respondent has falsely alleged that the Claimant delayed in
accepting the delivery of goods from the Port of Destination, which
resulted in the Respondent being blacklisted by the shipping/logistics
agency, i.e., Maersk. It is thus the Respondent case that the
extraordinary delay caused by the Claimant led to outstanding
demurrage and detention charges, which were allegedly borne by the
Respondent. However, these allegations are not only a misrepresentation
of facts and devoid of merit but also made in bad faith.
II.44. At the outset, it is pertinent to highlight that the delivery of goods at the
Port of Destination was the sole responsibility of the independent
Consignee, Orinoco Flow Comercializadora C. A.
(‘Orinoco/Consignee’), who was an integral part of this commercial
transaction. As an independent third-party agency, Orinoco was solely
responsible for receiving the goods and autonomously organizing their
collection in Venezuela, i.e., the Port of Destination.
II.45. Notably, the issues faced by the Respondent concerning the unloading of
cargo at the Port of Destination were not due to the Consignee’s alleged
outstanding charges at the Venezuela Port, but were due to issues
between the Respondent, its freight forwarder Reload Logistics, and
Maersk. The Respondent, via an email dated 02.03.2022, highlighted
these issues to the Claimant. The relevant excerpt of the said email is as
follows:
“NOW FOR THE BALANCE OF THE GOODS WE ARE FACING
THE FOLLOWING ISSUE:
1. FORWARDER ISSUE WITH MAERSK STILL NOT
RESOLVED AND OUR BANK HAS MADE SOME
RESTRICTIONS FOR OVERSEAS PAYMENTS LEADING TO
DOUBLE ISSUES.
2. OUR OWN ISSUE WITH MAERSK REGARDING 5 CNTRS
HIGH CARBON FERRO MANGANESE (STILL UNDER
PROCESS)”
A bare perusal of the aforesaid email makes it clear that the Respondent
was in discussion with Maersk regarding issues for the balance goods
which had nothing to do either with the Claimant or the Consignee. The
email also highlighted that the Respondent’s bank had some issues
regarding overseas payments, which further complicated the situation. A
copy of the email dated 02.03.2022 is attached herewith and marked as
Annexure C-___.
II.46. The frivolity of the Respondent’s argument is further evident from the
fact that the issues regarding the unloading of material at the Port of
Destination due to the Consignee’s overdue charges were raised by the
Respondent in early March 2022, when no consignment under the
present Contract was pending at the Port of Destination. The timeline of
events shows that the 1st Consignment had already arrived on
31.10.2021, the delivery of which was taken by the Consignee on
14.12.2021. While the 2nd Consignment only arrived at the Port of
Destination on 25.04.2022. Thus, the alleged unloading issues faced by
the Respondent could not have arisen in respect of the Consignments
made under the present Contract.
II.47. Despite the aforesaid discrepancy, the Claimant promptly offered an
alternative consignee, i.e., Prosuministros, C.A., to alleviate any
inconvenience on the same day, i.e., 14.03.2022. Despite the Claimant’s
prompt action and arrangement, the Respondent still failed to proceed
with the shipment of the remaining FESIMN. This clearly indicates that
the delays were not due to external factors but rather internal issues
within the Respondent’s organization and management. A copy of the
email trail titled “Delivery For Balance Cargo” is attached herewith and
marked as Annexure C-___.
“Andres Rodriguez: Vikas, last question, the goods you are going
to supply are from india or Durban?
Vikas Rawat: India...”
III.9. Further, it is specifically denied that the Shipment Documents for the 1 st
Consignment were provided to the Claimant on 28.07.2021 thereby
entitling the Respondent to the remaining 60% payment. Notably, the
Certificate of Quality/Analysis for the said consignment was only shared
with the Claimant on 28.10.2021, i.e., after a delay of 48 days, from the
shipping on board of the said consignment . Pertinently, as discussed
above, the Respondent was under the obligation to share the Certificate
of Quality/Analysis with the Claimant prior to dispatching of goods
from the Port of Shipment to allow the Claimant to verify the same,
before the same are shipped on board. However, the Respondent
negligently shipped the goods without Claimant’s consent regarding the
quality deviations. In this regard, the contents of Preliminary
Submission (D) of this Rejoinder are reiterated and not repeated for the
sake of brevity.
b. Re: Revision in the name of the Notify Party 2 from Clover
International C.A. to Global Partner Co. Ltd.
III.10. The contents of paragraphs 15 – 24, save and except for what is a matter
of record, are denied for being incorrect and wholly misconceived. It is
specifically denied that the Consignee, i.e., Orinoco, was Claimant’s
agent. Instead, the Consignee was an independent third-party agency,
who was solely responsible for receiving the goods and autonomously
organizing their collection in Venezuela, i.e., the Port of Destination.
III.11. The Respondent has further contended that since the request for change
in the name of Notify Party 2 from Clover International C.A. to Global
Partner Co. Ltd., was intimated by the Claimant after 40 days of
receiving the Shipment Documents, the same is indicative of the fact
that time was never the fundamental essence. The aforesaid contention
of the Respondent is denied in entirety for being wholly misconceived
and devoid of merit. It is submitted that the aforesaid revision in the
name of the Notify Party 2 was wholly immaterial and had no bearing
whatsoever on the Respondent’s performance of its obligations under
the Contract. The said contention is nothing but an afterthought and a
desperate attempt by the Respondent to mislead this Tribunal by pinning
its own failure to make timely delivery, on the Claimant.
III.14. The Respondent has further relied upon the Claimant’s email dated
17.09.2021 to contend that since the Claimant had confirmed/accepted
receipt of the Bill of Lading shared by the Respondent and sought for
the scanned copy of original Shipment Documents, the Respondent
became entitled to the remaining 60% payment in terms of Clause 9 of
the Contract. The said contention is not only baseless and devoid of
merit but is wholly extraneous to the terms of the Contract, hence
denied. Notably, it was the receipt of the scanned Shipment Documents
by the Claimant, that could have triggered the payment obligation under
Clause 9 and not the request for the same. It is highlighted that in the
email dated 17.09.2021, the Claimant categorically listed the Shipment
Documents that were to be supplied by the Respondent to initiate
balance payment. The said email clearly shows the Claimant’s bonafide
and intention to make the payment. However, the Respondent miserably
failed to provide all the Shipment Documents to the Claimant in
accordance with the terms of the Contract. Pertinently, the Respondent
has failed to highlight the date when the same were provided by it to the
Claimant. Thus, it is wholly out of place for the Respondent to contend
that it became entitled to the remaining 60% payment in respect of the
1st Consignment on 17.09.2021, when as per its own contention the
scanned copy of the Shipment Documents was yet to be supplied to the
Claimant. Reliance in this regard is made to the contents of Preliminary
Submission (C) of this Rejoinder, which are reiterated but not repeated
for the sake of brevity.
III.18. It is specifically denied that since the country of origin was revised from
India to Zambia, upon the Respondent’s repeated requests, the SOB
Date as stipulated in the Contract also stood altered. The aforesaid
contention of the Respondent is not only bereft of logic but is totally
uncorroborated and false. It is highlighted that the Respondent on
16.06.2021 had requested the Claimant to accept deliveries from Durban
instead of India on the pretext of expedited delivery at cheaper rates.
The Respondent promised that the delivery will be made within 2
months, i.e., by 16.08.2021. However, the Respondent miserably failed
to honor the said deferred timeline proposed by it. It was only in
pursuance of the said false assurance made by the Respondent that the
Claimant accommodated Respondent’s request to change the country of
origin. Thus, the Respondent cannot diametrically change its stance to
state that the SOB Date stood revised on account of the alleged revision
in the country of origin. Reference in this regard is made to paragraph
3.8 of this Rejoinder which are not being repeated to avoid prolixity.
III.20. In light of the above, it is vehemently denied that the overall value of the
Contract was mutually increased from USD 1,470,000/- to USD
1,570,000/-, without any dispute. Thus, the Respondent’s reliance on the
email dated 17.09.2021 to contend that the additional support of USD
100/- PMT was agreed to by the Claimant on account of improved
quality of FESIMN is wholly untrue and devoid of merit. Notably, the
alleged revision was approved by the Claimant, albeit with reluctance,
only on account of the false assurance made by the Respondent that the
remaining cargo (i.e., 864 MT FESIMN) would be shipped within 30
days, i.e., by 17.10.2021. However, it is a matter of record that the
Respondent miserably failed to meet the aforesaid deadline, as the 2 nd
Consignment of 77 MT (as against the 81 MT promised) was only
shipped on board on 01.02.2022. It already stands established that the
Claimant did not only raise concerns regarding the FESIMN being out
of contractual specification but categorically denied the requirement of
the alleged better product than the one agreed in the Contract.
III.21. The Respondent has further placed reliance on emails dated 14.11.2021
and 15.11.2021, exchanged between the Parties to contend that since,
the Parties were going ahead with the performance of the Contract even
in November 2021, i.e., 5 months from the initially agreed SOB Date,
thus, the Claimant’s claim towards the purported delay is untenable. The
aforesaid contention is wholly misconceived, concocted and therefore
denied in entirety. It is once again reiterated that the Respondent has
cherrypicked and selectively relied upon the correspondences exchanged
between the Parties with malafide intent of misleading this Tribunal.
Reference in this regard is made to the contents of Preliminary
Submissions (D (i)), which are reiterated but no repeated to avoid
prolixity.
III.22. It is further the case of the Respondent that the terms of the Contract in
respect of the specification of FESIMN stood revised/novated in view of
the Claimant’s acceptance of FESIMN of varying specifications
supplied by the Respondent, even though all inspection reports were sent
to the Claimant prior to the delivery of the goods. To support the
aforesaid contention, the Respondent has relied upon Claimant’s email
dated 17.09.2021. In this regard, it is reiterated that Certificate of
Quality/Analysis were to be provided to the Claimant prior to the goods
being ‘shipped on board’ to enable it to inspect the material(s) for any
quality deviation before the goods were dispatched to minimize costs.
The same was also highlighted by the Claimant in its email dated
17.09.2021, which has been relied upon by the Respondent. However, as
has been established paragraph 2.18 of this Rejoinder that the
Respondent miserably failed to fulfill the aforesaid obligation.
Reference in this regard is made to the contents of Preliminary
Submissions (D (ii)), which are reiterated but not for the sake of brevity.
III.24. The contents of paragraphs 39 – 40, are denied for being false,
misleading and bereft of merit. From a perusal of the emails exchanged
amongst the Claimant, Defendant and Bureau Veritas (‘BV’), it can be
clearly seen that it was not due to BV’s delay and/or default in
responding or providing an inspection report on time, but due to
Respondent’s own failure to provide BV with the requested sample of
FESIMN that lead to the delay. From a perusal of the email trail
attached by the Respondent in support of this argument [Annexure D-12
(Colly)], it can be clearly seen that the Respondent not only failed to
provide the sample FESIMN to BV for testing but also failed to give
clear instructions to BV to conduct the testing while it kept changing the
quantity of FESIMN to be inspected. Particularly, the Respondent’s
fraudulent conduct is further evident from the fact that it represented to
the Claimant that 162 MT and 300MT of FESIMN and 350 MT of
HCFEMN was ready and available for delivery. However, on
25.10.2021, the Respondent requested BV to only inspect 56 MT of
FESIMN, which was then increased to 70 MT on 26.10.2021, and 108
MT on 27.10.2021. Notably, only 77 MT of FESIMN was supplied by
the Respondent in the 2nd Consignment.
III.25. In regards to the alleged increase in the price for 338 MT and 450 MT of
FESIMN, it is submitted that it was due to Respondent’s own delay in
delivering the 1000MT of FESIMN, that the circumstances changed, if
any, and the same cannot and should not be attributed to the Claimant. It
may also be pointed out that it was never the Claimant’s duty to follow
up and get involved in the Respondent’s responsibilities. Finally, BV’s
failure to respond to the Respondent, if at all, could have been due to the
Respondent’s own previous conduct on other cargoes. At this point, it
had become extremely clear that the Respondent had no control over the
material they offered. The Respondent planned to wait for market
conditions to correct to deliver and maintain more profits.
Unfortunately, the market continued to rise, and they delayed
everything, waiting for the market to play in their favor. They tried to
pass the increased material price to the Claimant, without taking
responsibility for the Contract, which was for a fixed price and a
determined period. Without any signed addendum, the Respondent set
false dispatch plans, wasting Claimant’s time and money and
compromising Claimant’s reputation. In view of the aforesaid, the
contents of the Preliminary Submission (A), Preliminary Submission
(B), and Preliminary Submission (D) of this Rejoinder are reiterated and
not repeated for brevity.
III.26. The contents of paragraphs 41 – 42, are denied for being false,
misconstrued and based on conjectures. The Claimant denies being in
possession of any information regarding the Respondent paying an
advance amount to its suppliers, and the same then allegedly being stuck
with them. It is submitted that the Claimant duly transferred the
Advance Payment to the Respondent, whereafter, the supply of FESIMN
was the sole responsibility of the Respondent. It is undisputed that the
Respondent agreed to refund the balance Advance Payment, however,
the said refund has never been received by the Claimant. The
Respondent’s argument regarding termination has already been reverted
to and merits no further response. In this regard, the contents of the
Preliminary Submission (A), Preliminary Submission (B), and
Preliminary Submission (C) of this Rejoinder are reiterated and not
repeated for brevity.
III.31. It is further submitted that the delay in refund was caused due to
Respondent’s failure to comply with the RBI Regulations. The same is
evident from Annexure D-39, at Page 43 of the Counter claim. The said
document is a letter dated 30.04.2024, sent by Bank of Baroda to the
Respondent, highlighting its outstanding outward remittances. The letter
clearly stipulated that “…We request you to scan your portfolio and
submit the Bill of Entry number, date & port code to the respective AD
branch with additional clarifications / information, if any, to knock off
the respective outward remittances.” This clearly evinces that the
Respondent failed to comply with the RBI Regulations to ensure smooth
outward remittance. Needless to mention, the Respondent portrayed
itself to be an international trader but lacked the basic knowledge
regarding the compliances surrounding inward and outward international
remittances. This further substantiates that the Respondent
misrepresented its position from the very inception of the Contract for
its economic gains and took advantage of Claimant’s situation.
III.32. That the contents of paragraphs 50-52 are denied for being false,
misleading and misconstrued. The Claimant has already explained in the
SoC and then reiterated in this Rejoinder, that it was paramount for the
specifications of FESIMN to comply with the contractual specifications
in view of its commitments made to its downstream buyer. With respect
to the email highlighted by the Respondent in this context, it is
submitted that the entire transaction was so delayed that the Claimant
was left with no option but to accept whatever little quantities were
being supplied by the Respondent to minimize losses. In fact, the email
itself captures this wherein the Respondent wrote, “However, at this
stage, we have no option but to accept the materal”. Needless to
mention that every time there was a quality shift, the Claimant had to
renegotiate terms with its downstream buyer(s). This is evident from the
fact that when the Respondent imposed the FESIMN on the Claimant,
the Claimant clearly told the Respondent that since the FESIMN did not
comply with the contractual specifications, the delivery of the same shall
be accepted only after a quality analysis and confirmation by the
Consignee at the Port of Destination. [Annexure C-]
III.33. That the contents of paragraph 53 are denied for being misleading,
incorrect and misconceived. The Claimant has already discussed the
same in length, and no further response is merited. In this regard, the
contents of this Rejoinder and the SoC are reiterated and not repeated
for brevity.
III.34. The contents of paragraphs 54 – 55, are denied for being misleading and
incorrect, except for what is a matter of fact. The Claimant submits that
the Respondent is interpreting communications to suit its narrative and
to mislead this Tribunal. That on 20.01.2022, the Claimant did not
request for a new delivery but followed up on a long pending delivery
which the Respondent had assured months ago to have been ready and
available for immediate delivery. In this regard, the contents of
Preliminary Submission (A) and Preliminary Submission (D) of this
Rejoinder are reiterated and not repeated for brevity.
III.35. The contents of paragraph 56 are denied for being incorrect and
misleading, except for what is a matter of record. The Claimant submits
that it is undisputed that the Contract was subsisting even until March
2022, however, the same was a result of the Respondent’s consistent
misrepresentations and false assurances to the Claimant to complete the
delivery of 1000MT of FESIMN. In this regard, the contents of
Preliminary Submission (A) and Preliminary Submission (D) of this
Rejoinder are reiterated and not repeated for brevity.
III.36. That the contents of paragraphs 57 – 58, are denied for being false,
frivolous and bereft of substance. In this regard, the contents of
Preliminary Submission (C) and Preliminary Submission (D) of this
Rejoinder are reiterated and not repeated for the sake of brevity.
III.37. The contents of paragraphs 59 – 63, are denied for being incorrect and
misleading, except for what is a matter of record. In this regard, the
contents of Preliminary Submission (A), Preliminary Submission (B)
and Preliminary Submission (D) of this Rejoinder are reiterated and not
repeated for brevity.
Response: Failure on part of Claimant to take timely delivery of
Consignments: Demurrage & Detention Charges and Loss of
Business by the Defendant
III.39. The contents of paragraphs 68 – 71, are denied for being false,
misconceived and devoid of merit. Particularly, with regards to the
Respondent’s contention that the Consignee was blocked at destination
due to outstanding dues, it is submitted that due to a large shipment of
the Consignee arriving in March 2022, there was waiting for picking up
the containers at the Port of Destination. Due to this situation, which too
was a result of the Respondent’s failure to make timely delivery within
the assured time, Maersk decided not to ship new cargoes under the
Consignee’s name until the previous cargoes were cleared. Although
this matter was beyond Claimant’s scope of responsibility, but to resolve
the difficulty promptly and to complete the established Contracts, on
14.03.2022, the Claimant proceeded, under instructions from the
Consignee, to immediately indicate a new consignee named
Prosuministros, C.A., who was also a part of the same Consignee group.
It may be noted, that originally, as per the terms of the Contract the
goods were schedule to arrive at the Port of Destination much prior to
when this issue arose. However, despite the same, the Claimant, in bona
fide, assisted the Respondent in every way possible. In this regard, the
contents of Preliminary Submission (E) are reiterated and not repeated
for brevity.
III.40. The contents of paragraphs 72 – 76, are denied for being false,
misleading and without merit, except for what is matter of record. As
already discussed above, the detention and demurrage charges, if any,
were paid by the Consignee and not by the Respondent. It is further
disputed that an amount of USD 20,000/- was paid by the Defendant to
satisfy the mounting demurrage and detention charges. Notably, the
Respondent has simply made a bald assertion without placing on record
any document to substantiate the aforesaid averment. Finally, it is
vehemently denied that due to the alleged faults of the Consignee, the
entire supply line was disrupted because of which the final consignment
had to be sent from India instead of Zambia. Rather, it was due the
longstanding issues that the Respondent and its bank had with Maersk
alongwith Respondent’s poor planning and management, that it begged
the Claimant to allow it to import the remaining shipment from India
instead of Zambia to close the issue. In the interest of the business
relationship and being left with no option, the Claimant once again
acceded to the aforesaid. In this regard, reference is drawn to the email
dated 09.03.2022, the relevant excerpts of the same are reproduced
below:
“Dear Andy,
As we informed you, remittance from Yash is on hold due to
some technical issues. You can talk to the bank manager also
regarding the same.
We tried to make the remittance from ARV engineering to
Zambia but there is a rule over here that in Third country trade
with the company from which the remittance is being done the
payment should be received by that company only and here it was
received by us.
We can give the contact details of the bankers of ARV engineering
also for verification.
Now the only option is to make it from India.
Because sorting out from the bank will take another 2 weeks or
so.
Our issue with Maersk now is solved , however that of the
forwarder is still there , however we have made the payment to the
agent under different remittance code from the bank.
The aforesaid email makes it abundantly clear that issues were always
from the Respondent’s end because of which the Port of Origin was
repeatedly changed by the Respondent. In this regard, the contents of the
SoC and specifically Preliminary Submission (E) of this Rejoinder are
reiterated and not repeated for brevity.
III.41. The contents of paragraphs 77 – 82, are denied for being misleading,
misconstrued and false. It is specifically denied that the Claimant ever
gave its consent to USD 2,350/- PMT for the third consignment of 56
MT of FESIMN. Further, as already discussed, the extra cost and/or
penalty which Maersk mentioned to charge to the Origin Party was on
account of a confusion which was subsequently clarified upon further
negotiations. Notably, the charges were finally paid by the Consignee
and not the Respondent. The same is evident from the contents of
Respondent’s own email dated 08.03.2023 at Annexure D-34, at Page
196-197 of the SoD, addressed to Maersk on 08.03.2023, which reads as
follows:
“Dear Team
Till last week you have e-mailed us that the delivery has not been
taken and charges have piled up to USD 85,000.
Now as per your email, nothing of that sort exists
So the case is closed now ?
Kindly confirm.
Amit”
The above email clearly shows that the said delivery issues were
resolved without Respondent’s assistance and the alleged charges were
also duly taken care of without the Respondent having to pay for the
same. Pertinently, the Respondent has very conveniently highlighted
only one of the many e-mails that were exchanged between itself and
Maersk in an attempt to mislead this Tribunal.
Following the same pattern, the Respondent has again reproduced and
highlighted only a portion of the email dated 02.08.2022 sent by the
Claimant instead of placing the complete picture before this Tribunal.
The contents of email dated 02.08.2022 reads as under:
“Hi Amit,
Yes, the consignee has a large backload of cargo, and they are
clearing all their goods at their capacity.
The shipping line is aware of their case, and they are working closely
together to overcome the difficulty in place.
Amit, I don't know what problems you are having with your
forwarders.
First of all, as mentioned on many occasions, your responsibility is
only at the origin (loading port) as per our contract.
Any duties arising at destination are not in your contract and are
only the consignee's responsibility, NOT YOURS.
The consignee is in fact the only one paying for any fees related to
the collection of the cargo, NOT YOU.
None of our freight forwarders has had the issue you are mentioning.
Subrata Mondal can confirm this. She handled more than 30
containers with the same consignee details.
Once again, I do not know how you operate and why you are the
only one (out of many suppliers with the same circumstances)
facing all the issues you have mentioned.
To sum up, the consignee is in the process of collecting the goods.
It is out of our scope and yours any logistic at the destination.
Kind regards.”
The aforesaid email clearly shows Respondent’s mala fide and that it is
the Respondent, who is approaching the present arbitration with unclean
hands. Finally, in this regard, the contents of the SoC, Preliminary
Submissions (A) and Preliminary Submissions (E) of this Rejoinder are
reiterated and not repeated for the sake of brevity.
III.42. The contents of paragraphs 83 – 85, are denied for being false,
misleading and completely devoid of merit. In this regard, the contents
of this Rejoinder and the SoC are reiterated and not repeated for the sake
of brevity.
Re: Prayer
III.44. That the contents of paragraphs under the ‘Para-wise reply’ from I-XL
are completely and absolutely denied for being false, frivolous,
incomplete, misleading and baseless. That the Claimant stands by the
contents of the SoC and this Rejoinder, and the same are not repeated
herein for the sake of brevity and proximity.
III.45. Hence, in light of the facts and circumstances of this case and
submissions made in the SoC and hereinabove, the Claimant prays that
this Hon’ble Tribunal may be pleased to grant the prayers as sought by
the Claimant in the captioned SoC.
Through,
RPV Legal
Counsel for the Respondent
D-19, Second Floor, Geetanjali Enclave
New Delhi – 110017
Date: 15 June 2024 Phone: +91 11 41834272
Place: New Delhi E: info@rpvlegal.com